Tender Document for Bibiyana-3 400MW Combined Cycle Power
Transcription
Tender Document for Bibiyana-3 400MW Combined Cycle Power
BANGLADESH POWER DEVELOPMENT BOARD TENDER DOCUMENT FOR Design-Build, Supply, Erection, Installation, Testing & Commissioning of Skid Mounted Gas Regulating & Metering Station for Supplying Natural Gas to Bibiyana III 400 MW Combined Cycle Power Plant at Nabiganj Upazila, Habiganj District on Turnkey Basis. (Open Tendering Method) International Tender No.1022-BPDB(Sectt.)/Dev.-187/2007 Gas RMS Bib-III Date: 07/04/2016 1 BANGLADESH POWER DEVELOPMENT BOARD INVITATION FOR INTERNATIONAL TENDERS 1. Ministry / Division 2. Procuring Entity Name 3. Invitation for 4. Procurement Method 5. Source of Fund 6. Invitation for Tenders Ref. & Date 7. Date of start of selling of Tender document 8. Tender Name 9. Time for Completion of Commissioning from the effective date of contract 10. Eligibility of Tenderers 11. Price of Tender Document 12. Amount of Tender Security 13. Validity of Tender and Tender Security 14. Name and address of the Office for selling the tender document 15. Name and address of the Office for receiving and opening of tender 16. Last Date and Time for selling the Tender document 17. Last Date and Time for submission of Tenders 18. Date and Time for Gas RMS Bib-III Ministry of Power, Energy & Mineral Resources / Power Division. Bangladesh Power Development Board (BPDB). Design-Build, Supply, Erection, Installation, Testing & Commissioning of Skid Mounted Gas Regulating & Metering Station for Supplying Natural Gas to Bibiyana-III 400 MW Combined Cycle Power Plant at Nabiganj Upazila, Habiganj District on Turnkey Basis. Open Tendering method. Tenders shall be submitted in single envelope. “Development Fund” Memo no. 1022 -BPDB (Sectt)/Dev-187/2007 date: /04/2016 10.04.2016 Design-Build, Supply, Erection, Installation, Testing & Commissioning of Skid Mounted Gas Regulating & Metering Station for Supplying Natural Gas to Bibiyana-III 400 MW Combined Cycle Power Plant at Nabiganj Upazila, Habiganj District on Turnkey Basis. 300 days. As mentioned in Tender Document. Tk. 10,000.00 (Tk. Ten thousand) only payable in the form of Pay order / Demand draft in favour of the Director, Purchase, BPDB, Dhaka for each set of tender document. US$ 100,000 (US$ One hundred thousand) or BDT 8,000,000 (BDT Eight million) in the form of an irrevocable and unconditional bank guarantee (on non-judicial stamp) issued by any scheduled Bank of Bangladesh or by a Foreign Bank duly endorsed by a scheduled Bank in Bangladesh payable in favour of the Secretary, BPDB. 180 (One hundred eighty) days and 208 (Two hundred and eight) days respectively from the date of opening of tender. Director of Purchase, Bangladesh Power Development Board, WAPDA Building (9th floor), Motijheel C/A, Dhaka-1000. Secretary Bangladesh Power Development Board WAPDA Building (1st floor), Motijheel Commercial area, Dhaka-1000. Date: 24/05/2016 Time: 17.00 hours (BST) Date: 25/05/2016 Time: 11.00 hours (BST) The tenders shall be opened at 11:30 hours (BST), Date: 25/05/2016. 2 opening of Tenders 19. Place & date of PreTender Meeting 20. Special Instructions Tenderers and thier authorized representative are allowed to attend. If saught by tenderer, will be informed later. Tender Documents will http://www.bpdb.gov.bd be posted in the BPDB website : The Procuring Entity reserves the right to accept any or reject any/ all Tenders prior to acceptance without assigning any reason whatsoever. 22. Name of official Inviting the Tender 23. Designation and address inviting the Tender Tenders submitted by Fax, Telex, Swift, Cable, E-mail & by post/courier shall not be accepted. Md. Zahurul Haque Secretary Bangladeshh Power Development Board WAPDA Building (1st floor) Motijheel Commercial area, Dhaka-1000. Tel: 9554209, 9567350 Fax: 880-2-9564765 Signed/07.04.2016 (Md. Zahurul Haque) Secretary Bangladesh Power Development Board WAPDA Building (1st Floor) Motijheel C/Area, Dhaka-1000, Bangladesh Fax : 880-2-9564765 Memo no. 1022 -BPDB (Sectt)/Dev-187/2007 date: 070 /04/2016 Copy for information to: 1. Secretary, Power Division, Ministry of Power, Energy and Mineral Resources, Dhaka. 2. DG, IMED, Planning commission, CPTU, Dhaka. He is requested to take necessary action for posting the said notice in the CPTU website. 3. Member, P&D/Generation/ Finance, BPDB, Dhaka. 4. Chief Engineer, Generation/ P&D/PSC, BPDB, Dhaka. 5. Project Director Bibiyana-III 400MW Combined Cycle Power Plant Project, BPDB. 6. Controller (Finance & Accounts), BPDB, Dhaka. 7. C.S.O to Chairman, BPDB, Dhaka. 8. Director, Design & Inspection-1 / Finance/ Contract & C.A, BPDB, Dhaka. 9. Director, Purchase, BPDB, Dhaka. Tender document will be available on 10/04/2016 for selling. 10. Director, Public Relation, BPDB Dhaka. He is requested to take necessary steps to publish the tender notice in national daily newspapers. 11. Senior System Analyst, BPDB Dhaka. He is requested to post the said notice in BPDB website. 12. Office copy. Signed/07.04.2016 (Pranab Kumar Ghosh) Assistant Secretary (Dev) BPDB, Dhaka. Gas RMS Bib-III 3 REJECTION CLAUSES (Te nde r shall be rejected if the Tenderer does not comply with but not limite d to the following crite ria) 1. Tenderer shall have to comply with Eligibility criteria (ITT 5), Experience criteria (ITT 14) and Eligibility criteria for Materials, Equipment and Associated Services (ITT6.1); 2. Tenderer must submit certificate(s) from the End-User in support of his experience [TDS(ITT14.1b)]; 3. If the Tenderer is a Joint Venture, Consortium or Associations (JVCA), JVCA agreement or Letter of Intent along with the proposed agreement duly signed by all partners of the intended JVCA and authenticated by a Notary Public must be submitted (ITT 18.1); 4. For JVCA, lead partner and its other partners must meet minimum qualification criteria (ITT 18.2); 5. A Tenderer shall submit only one (1) Tender, either individually or as a JVCA (ITT 20) 6. Tender Submission Letter (Form PW 3-1) shall be properly filled up by the Tenderer (ITT 25.1, 51.2) otherwise tender will be rejected ; 7. Bill of Quantities using the form(s) furnished in Section 6: Bill of Quantities shall be properly filled up by the Tenderer (ITT 25.2, 51.2). Tenderers are not allowed to change/ modify the format of Bill of Quantities; 8. If the Tenderer is not manufacture, Manufacturer’s Authorisation & Warranty/Guarantee Letter for the items mentioned in TDS must be submitted to demonstrate that it has been duly authorized by the manufacturer or producer of the Goods to supply the Goods to Bangladesh [TDS(ITT24.1(I)-3]; 9. Tenderer must submit Guarantee/warranty certificate of the offered equipment/system including turnkey work and its satisfactory performance during warranty period [24 (Twenty Four) months from the date of issuing Provisional Acceptance Certificate] [TDS(ITT24.1(l)-5]; 10. Tenderer must comply Completion period [TDS(ITT26.2) and TDS (ITT 49.1)]; 11. Tenderer shall have to submit Audited financial reports and other documents in favour of financial criteria [TDS(ITT24.1(I)-13]; 12. Tenderer shall have to submit Certificate from the manufacturer confirming that his offered items are new, unused, in good condition. [TDS(ITT24.1(l)-6]; 13. Tenderer shall have to submit English version Original printed catalogue, drawings of offered equipments/ spares/items [TDS(ITT24.1(l)-8]; 14. Tenderer shall have to submit Detail specification, name of Manufacturer and the country of origin of the offered equipments/ spares/items [Specifications Submission and Compliance Sheet (Form PW3-13)] [TDS(ITT24.1(l)-9]; 15. Tender shall remain valid for the period specified in the TDS after the date of Tender submission deadline (ITT 33); 16. Tender must be accompanied by a valid Tender Security (ITT 35, 36, 51.2); 17. Tender must be accompanied by Letter of Authorization to sign the Tender on behalf of the Tenderer (ITT 24.1f, 51.2); 18. Tender must comply the scope of supply and scope of work as stated under Section 6,7,8 and 9 without any material deviation or reservation (ITT 52.2); 19. Tenderer shall have to comply with the payment terms [PCC (GCC 66.1)]; Gas RMS Bib-III 4 20. Tenderer shall have to submit sealed & signed tender document [TDS(ITT24.1(I)-1]; 21. Tenderer shall have to submit Certificate confirming compliance to the terms and conditions of the Tender Document. [TDS(ITT24.1(I)-11]; 22. If Tenderer has any reservations, he has to mention it in deviation list (PW3-12). [TDS(ITT24.1(I)-12]; 23. Tenders shall have to be submitted in a single sealed envelope in accordance with the requirements of the Tender document including addenda (if any).The original and three (03) copies of the complete proposal shall be submitted within the date and time as mentioned in the tender notice. [TDS(ITT41.1)]; Gas RMS Bib-III 5 Table of Contents Section 1. Instructions to Tenderers ................................................................... A. General..................................................................................................................... 1. Scope of Tender..................................................................................................... 2. Interpretation........................................................................................................... 3. Source of Funds........................................................................................................ 4. Corrupt, Fraudulent, Collusive or Coercive Practices............................................ 5. Eligible Tenderers ..................................................................................................... 6. Eligible Materials, Equipment and Associated Services....................................... 7. Site Visit...................................................................................................................... B. Tender Document .................................................................................................. 8. Tender Document: General .................................................................................... 9. Clarification of Tender Document.......................................................................... 10. Pre-Tender Meeting................................................................................................ 11. Addendum to Tender Document ............................................................................ C. Qualification Criteria ..................................................................................................... 12. General Criteria........................................................................................................ 13. Litigation History ...................................................................................................... 14. Experience Criteria .................................................................................................. 15. Financial Criteria ...................................................................................................... 16. Personnel Capacity.................................................................................................. 17. Equipment Capacity................................................................................................. 18. Joint Venture, Consortium or Association (JVCA)................................................ 19. Subcontractor(s)..................................................................................................... D. Tender Preparation ................................................................................................ 20. Only one Tender ...................................................................................................... 21. Cost of Tendering .................................................................................................... 22. Issuance and Sale of Tender Document ............................................................ 23. Language of Tender ................................................................................................ 24. Contents of Tender.................................................................................................. 25. Tender Submission Letter and Bill of Quantities................................................... 26. Alternatives............................................................................................................... 27. Tender Prices, Discounts and Price Adjustment................................................... 28. Tender Currency ...................................................................................................... 29. Documents Establishing Eligibility of the Tenderer............................................... 30. Documents Establishing the Eligibility and Conformity of Materials, Equipment and Services........................................................................................ 31. Documents Establishing Technical Proposal........................................................ 32. Documents Establishing the Tenderer’s Qualification......................................... 33. Validity Period of Tender........................................................................................ 34. Extension of Tender Validity and Tender Security .......................................... 35. Tender Security....................................................................................................... 36. Form of Tender Security.......................................................................................... 37. Authenticity of Tender Security.............................................................................. 38. Return of Tender Security...................................................................................... 39. Forfeiture of Tender Security ................................................................................. 40. Format and Signing of Tender............................................................................... E. Tender Submission ............................................................................................... 41. Sealing, Marking and Submission of Tender .................................................... 42. Deadline for Submission of Tender....................................................................... 43. Late Tender............................................................................................................. 44. Notice for Modification, Substitution or Withdrawal of Tender............................ Gas RMS Bib-III 6 45. Tender Modification................................................................................................. 46. Tender Substitution.................................................................................................. 47. Tender Withdrawa ............................... .............................. ............................... .. F. Tender Opening and Evaluation ......................................................................... 48. Tender Opening ....................................................................................................... 49. Evaluation of Tenders.............................................................................................. 50. Evaluation Process.................................................................................................. 51. Preliminary Examination ........................................................................................ 52. Technical Responsiveness and Technical Evaluation ........................................ 53. Clarification on Tender ............................................................................................ 54. Restrictions on Disclosure of Information............................................................. 55. Correction of Arithmetical Errors ........................................................................... 56. Financial Evaluation................................................................................................. 57. Price Comparison .................................................................................................... 58. Negotiations ............................................................................................................. 59. Post-qualification...................................................................................................... 60. Procuring Entity’s Right to Accept any or to Reject Any or All Tenders............. 61. Informing Reasons for Rejection........................................................................... G. Contract Award ...................................................................................................... 62. Award Criteria........................................................................................................... 63. Notification of Award................................................................................................ 64. Performance Security ............................................................................................. 65. Form and Time Limit for Furnishing of Performance Security .......................... 66. Validity of Performance Security ........................................................................... 67. Authenticity of Performance Security .................................................................... 68. Adjudicator............................................................................................................... 69. Contract Signing ................................................................................................... 70. Publication of Notification of Award of Contract................................................... 71. Debriefing of Tenderers.......................................................................................... 72. Right to Complain ................................................................................................... Section 2. B. C. D. E. F. G. Section 3. A. Tender Data Sheet ............................................................................... Tender Document .................................................................................................. Qualification Criteria ............................................................................................. Tender Preparation ................................................................................................ Tender Submission ............................................................................................... Tender Opening and Evaluation ......................................................................... Contract Award ...................................................................................................... General Conditions of Contract ......................................................... General..................................................................................................................... 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Gas RMS Bib-III Definitions .......................................................................................................................... Inte rpretation ..................................................................................................................... Communications and Notices.............................................................................................. Governing Law .................................................................................................................. Governing Language....................................................................................................... Documents Forming the Contract and Priority of Documents.................................. Scope of Works................................................................................................................. Assignment........................................................................................................................ Eligibility ............................................................................................................................. Gratuities / Agency fees................................................................................................. Confidential Details .......................................................................................................... JVCA ................................................................................................................................... Possession of the Site ..................................................................................................... Access to the Site ............................................................................................................. Procuring Entity ’s Responsibilitie s ............................................................................... Approval of the Contractor’s Temporary Works.......................................................... 7 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 30. 31. 32. 33. 34. 35. 36. 37. 38. 39. B. Time Control ........................................................................................................... 40. 41. 42. 43. 44. 45. 46. 47. 48. 49. 50. C. Execution of Works .......................................................................................................... Examination of Works before covering up ................................................................... Identify ing Defects............................................................................................................ Testing................................................................................................................................ Rejection of Works ........................................................................................................... Remedial Work .................................................................................................................. Correction of Defects ....................................................................................................... Uncorrected Defects......................................................................................................... Cost Control............................................................................................................ 59. 60. 61. 62. 63. 64. 65. 66. 67. 68. 69. 70. 71. 72. 73. 74. 75. 76. 77. 78. 79. Gas RMS Bib-III Commencement of Works .................................................................................................... Completion of Works........................................................................................................ Programme of Works ....................................................................................................... Pro Rata Progress............................................................................................................. Early Warning .................................................................................................................... Extension of Intended Completion Date ....................................................................... Delays Caused by Authorities ........................................................................................ Acceleration....................................................................................................................... Delays Ordered by the Project Manager ....................................................................... Suspension of Work ......................................................................................................... Consequences of Suspension........................................................................................ Quality Control ....................................................................................................... 51. 52. 53. 54. 55. 56. 57. 58. D. Contractor’s Responsibilitie s ......................................................................................... Taxes and Duties............................................................................................................... Contractor’s Personnel.................................................................................................... Subcontracting.................................................................................................................. Nominated Subcontractor ............................................................................................... Other Contractors ............................................................................................................. Project Manager’s Decisions .......................................................................................... Delegation .......................................................................................................................... Instructions,....................................................................................................................... Queries about the Contract conditions......................................................................... Safety, Security and Protection of the Environment................................................... Working Hours................................................................................................................... Welfare of Labourers........................................................................................................ Child Labour ...................................................................................................................... Discoveries ........................................................................................................................ Procuring Entity ’s and Contractor’s Risks................................................................... Procuring Entity ’s Risks.................................................................................................. Contractor’s Risks............................................................................................................ Copy right............................................................................................................................ Limitation of Liability........................................................................................................ Insurance............................................................................................................................ Management and Progress Mee tings ............................................................................ Corrupt, Fraudulent, Collusive or Coercive Practices................................................ Contract Price.................................................................................................................... Bill of Quantities................................................................................................................ Changes in the Quantities and Unit Rate or Price ....................................................... Variations ........................................................................................................................... Costing of Variations or Extra Orde rs ........................................................................... Cash Flow Forecasts........................................................................................................ Payment Certificates ........................................................................................................ Payments to the Contractor ............................................................................................ Delayed Payment .............................................................................................................. Payments to Nominated Subcontractor(s) ................................................................... Compensation Events ...................................................................................................... Adjustments for Changes in Legislation....................................................................... Price Adjustment............................................................................................................... Retention Money ............................................................................................................... Liquidated Damages......................................................................................................... Bonus.................................................................................................................................. Advance Payment............................................................................................................. Performance Security....................................................................................................... Provisional Sums.............................................................................................................. Dayworks............................................................................................................................ Cost of Repairs to Loss or Damages............................................................................. 8 80. 81. 82. 83. 84. 85. 86. 87. 88. 89. 90. 91. 92. 93. 94. Completion......................................................................................................................... Taking Over........................................................................................................................ Amendment to Contract................................................................................................... Final Account..................................................................................................................... As-built Drawings and Manuals...................................................................................... Force Majeure .................................................................................................................... Notice of Force Majeure ................................................................................................... Consequences of Force Majeure.................................................................................... Release from Performance.............................................................................................. Termination........................................................................................................................ Payment upon Termination............................................................................................. Property .............................................................................................................................. Frustration.......................................................................................................................... Contractor’s Claims.......................................................................................................... Settlement of Disputes..................................................................................................... Section 4. Particular Conditions of Contract...................................................... Section 5. Tender and Contract Forms ............................................................... Tender Submission Letter (Form PW3-1)................................................................................ Tenderer Information (Form PW3-2)........................................................................................ JVCA Partne r Information (Form PW3-3)................................................................................ Subcontractor Information (Form PW3-4) .............................................................................. Personnel Information (Form PW3-5)...................................................................................... Manufacture r’s Authorisation & Warranty/Guarantee Lette r [Form PW3-5(a)]................. Bank Guarantee for Tender Security (Form PW3-6).............................................................. Notification of Award (Form PW3-7)........................................................................................ Contract Agreement (Form PW3-8).......................................................................................... Bank Guarantee for Performance Security (Form PW3-9)................................................... Bank Guarantee for Advance Payment (Form PW3-10)........................................................ Bank Guarantee for Retention Money Security (Form PW3-11) ......................................... Deviation List (Form PW3-12) ................................................................................................... Specifications Submission and Compliance Sheet (Form PW3-3).................................... Section 6. Bill of Quantities & Schedule of Requirement ................................. Section 7. Technical Specifications........................................................................ Section 8. General Specifications/ Particular Specifications .......................... Section 9. Drawings .................................................................................................. Gas RMS Bib-III 9 Section 1. Instructions to Tenderers A. 1. Scope of Tender 2. Interpretation 3. Source of Funds Gas RMS Bib-III General 1.1 The Procuring Entity, as indicated in the Tender Data Sheet (TDS) issues this Tender Document for the procurement of Works and associated Services incidental thereto as specified in the TDS and as detailed in Section 6: Bill of Quantities . The name of the Tender and the number and identification of its constituent lot(s) are stated in the TDS. 1.2 The successful Tenderer shall be required to execute the works and physical services as specified in the General Conditions of Contract 2.1 Throughout this Tender Document: (a) the term “in writing” means communication written by hand or machine duly signed and includes properly authenticated messages by facsimile or electronic mail; (b) if the context so requires, singular means plural and vice versa; (c) “day” means calendar days unless otherwise specified as working days; (d) “Person” means and includes an individual, body of individuals, sole proprietorship, partnership, company, association or cooperative society that wishes to participate in Procurement proceedings; (e) “Tenderer” means a Person who submits a Tender; (f) “Tender Document” means the Document provided by a Procuring Entity to a Tenderer as a basis for preparation of the Tender; and (g) “Tender” depending on the context, means a Tender submitted by a Tenderer for execution of Works and Physical Services to a Procuring Entity in response to an Invitation for Tender. 3.1 The Procuring Entity has been allocated public funds as indicated in the TDS and intends to apply a portion of the funds to eligible payments under the Contract for which this Tender Document is issued. 3.2 For the purpose of this provision, “public funds” means any monetary resources appropriated to Procuring Entities under Government budget, or loan, grants and credits placed at the disposal of Procuring Entities through the Government by the development partners or foreign states or organisations. 3.3 Payments by the development partner, if so indicated in the TDS, will be made only at the request of the Government and upon approval by the development partner or foreign state or Organisation in accordance with the applicable Loan / Credit / Grant Agreement, and will be subject in all respects to the terms and conditions of that Agreement. 10 4. Corrupt, Fraudulent, Collusive or Coercive Practices 4.1 The Government requires that Procuring Entities, as well as Tenderers and Contractors shall observe the highest standard of ethics during implementation of procurement proceedings and the execution of Contracts under public funds. 4.2 For the purposes of ITT Sub Clause 4.3, the terms set forth belo w as follows: (a) “corrupt practice” means offering, giving or promising to give, receiving, or soliciting either directly or indirectly, to any officer or employee of a Procuring Entity or other public or private authority or individual, a gratuity in any form; employment or any other thing or service of value as an inducement with respect to an act or decision or method followed by a Procuring Entity in connection with a Procurement proceeding or Contract execution; (b) “fraudulent practice” means the misrepresentation or omission of facts in order to influence a decision to be taken in a Procurement proceeding or Contract execution; (c) “collusive practice” means a scheme or arrangement between two (2) or more Persons, with or without the knowledge of the Procuring Entity, that is designed to arbitrarily reduce the number of Tenders submitted or fix Tender prices at artificial, non-competitive levels, thereby denying a Procuring Entity the benefits of competitive price arising from genuine and open competition; or “coercive practice” means harming or threatening to harm, directly or indirectly, Persons or their property to influence a decision to be taken in the Procurement proceeding or the execution of a Contract, and this will include creating obstructions in the normal submission process used for Tenders. “obstructive practice” means deliberately destroying, falsifying, altering or concealing of evidence material to the investigation or making false statements to investigators in order to materially impede an investigation into allegations of a corrupt, fraudulent, coercive or collusive practice; and/or threatening, harassing or intimidating any party to prevent it from disclosing its knowledge of matters relevant to the investigation or from pursuing the investigation. (d) (e) 4.3 Gas RMS Bib-III Should any corrupt, fraudulent, collusive, coercive or obstructive practice of any kind come to the knowledge of the Procuring Entity, it will, in the first place, allow the Tenderer to provide an explanation and shall, take actions only when a satisfactory explanation is not received. Such exclusion and the reasons thereof, shall be recorded in the record of the procurement proceedings and promptly communicated to the Tenderer concerned. Any communications between the Tenderer and the Procuring Entity related to matters of alleged corrupt, fraudulent, collusive, coercive, or obstructive practices shall be in writing. 11 4.4 5. Eligible Tenderers Gas RMS Bib-III If corrupt, fraudulent, collusive, coercive or obstructive practices of any kind is determined by the Procuring Entity against any Tenderer or Contractor in competing for, or in executing, a contract under public fund, the Procuring Entity shall : (a) exclude the concerned Tenderer from further participation in the concerned procurement proceedings; (b) reject any recommendation for award that had been proposed for that concerned Tenderer; and (c) declare, at its discretion, the concerned Tenderer to be ineligible to participate in further Procurement proceedings, either indefinitely or for a specific period of time. 4.5 The Tenderer shall be aware of the provisions on corruption, fraudulence, collusion, coercion and obstruction as stated in GCC Clause 39 and 89.1(b)(vii). 5.1 This Invitation for Tenders is open to all potential Tenderers from all countries, except for any specified in the TDS. 5.2 A Tenderer may be a physical or juridical individual or body of individuals, or company, association or any combination of them in the form of a Joint Venture, Consortium or Association (JVCA) invited to take part in public procurement or seeking to be so invited or submitting a Tender in response to an Invitation for Tenders. 5.3 A Government-owned enterprise in Bangladesh may also participate in the Tender if it is legally and financially autonomous, it operates under commercial law, and it is not a dependent agency of the Procuring Entity. 5.4 The Tenderer shall have the legal capacity to enter into the Contract. 5.5 Tenderers should not be associated, or have been associated in the past, directly or indirectly, with a consultant or any of its affiliates which have been engaged by the Procuring Entity to provide consulting services for the preparation of the design, specifications, and other documents to be used for the procurement of the works to be performed under this Invitation for Tenders. 5.6 The Tenderer in its own name or its other names or also in the case of its Persons in different names, shall not be under a declaration of ineligibility for corrupt, fraudulent, collusive, coercive, or obstructive practices as stated under ITT Sub Clause 4.4. 5.7 The Tenderer with a poor performance, consistent history of litigation or arbitration awards against it shall not be eligible to Tender. 5.8 The Tenderer shall not be insolvent, be in receivership, be bankrupt, be in the process of bankruptcy, be not temporarily barred from undertaking business and it shall not be the subject of 12 legal proceedings for any of the foregoing. 5.9 The Tenderer shall have fulfilled its obligations to pay taxes and social security contributions under the provisions of laws and regulations of the country of its origin. 5.10 Tenderers shall provide such evidence of their continued eligibility satisfactory to the Procuring Entity, as the Procuring Entity will reasonably request. 5.11 These requirements for eligibility will extend, as applicable, to each JVCA partner and Subcontractor proposed by the Tenderer. 6.1 6. Eligible Materials, Equipment and Associated Services All materials, equipment and associated services to be supplied under the Contract are from eligible sources, unless their origin is from a country specified in the TDS. 6.2 For the purposes of this Clause, “origin” means the place where the Materials and Equipments are mined, grown, cultivated, produced or manufactured or processed, or through manufacturing, processing, or assembly, another commercially recognized new product results that differs substantially in its basic characteristics from its components or the place from which the associated services are supplied. 6.3 The origin of materials and equipment and associated services is distinct from the nationality of the Tenderer. 7.1 The Tenderer is advised to visit and examine the Site of Works and its surroundings and obtain for itself on its own responsibility all information that may be necessary for preparing the Tender and entering into a contract for construction of the Works. 7.2 The Tenderer and any of its personnel or agents will be granted permission by the Procuring Entity to enter into its premises and lands for the purpose of such visit, but only upon the express condition that the Tenderer, its personnel, and agents will release and indemnify the Procuring Entity and its personnel and agents from and against all liability in respect thereof, and will be responsible for death or personal injury, loss of or damage to property, and any other loss, damage, costs, and expenses incurred as a result of the inspection. 7.3 The Tenderer should ensure that the Procuring Entity is informed of the visit in adequate time to allow it to make appropriate arrangements. 7.4 The costs of visiting the Site shall be at the Tenderer’s own expense. 7. Site Visit B. 8. Tender Document: General Gas RMS Bib-III 8.1 Tender Document The Sections comprising the Tender Document are listed below, and should be read in conjunction with any Addendum issued under ITT Clause 11. • Section 1 Instructions to Tenderers (ITT) 13 • • • • • • • • 9. Clarification of Tender Document 10. Pre-Tender Meeting Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Section 8 Section 9 Tender Data Sheet (TDS) General Conditions of Contract (GCC) Particular Conditions of Contract (PCC) Tender and Contract Forms Bill of Quantities (BOQ) General Specifications Particular Specifications Drawings 8.2 The Procuring Entity is not responsible for the completeness of the Tender Document and their addenda, if these were not purchased directly from the Procuring Entity, or through its agent as stated in the TDS. 8.3 The Tenderer is expected to examine all instructions, forms, terms, and specifications in the Tender Document as well as in addendum to Tender, if any. 9.1 A prospective Tenderer requiring any clarification of the Tender Document shall contact the Procuring Entity in writing at the Procuring Entity’s address and within time as indicated in the TDS. 9.2 A Procuring Entity is not obliged to answer any clarification request received after that date as stated under ITT Sub Clause 9.1. 9.3 The Procuring Entity shall respond in writing within five (5) working days of receipt of any such request for clarification received under ITT Sub Clause 9.1. 9.4 The Procuring Entity shall forward copies of its response to all those who have purchased the Tender Document, including a description of the enquiry but without identifying its source. 9.5 Should the Procuring Entity deem it necessary to revise the Tender Document as a result of a clarification, it will do so following the procedure under ITT Clause 11 and ITT Sub Clause 42.2. 10.1 To clarify issues and to answer questions on any matter arising in the Tender Document, the Procuring Entity may, if stated in the TDS, hold a pre-Tender Meeting at the place, date and time as specified in the TDS. All potential Tenderers are encouraged and invited to attend the meeting, if it is held. 10.2 The Tenderer is requested to submit any questions in writing so as to reach the Procuring Entity no later than one day prior to the date of the meeting. 10.3 Minutes of the pre-Tender meeting, including the text of the questions raised and the responses given, together with any responses prepared after the meeting, will be transmitted within five (5) working days after holding the meeting to all those who purchased the Tender document and to even those who did not attend the meeting. Any revision to the Tender document listed in ITT Sub-Clause 8.1 that may become necessary as a result of the pre-Tender meeting will be made by the Procuring Entity exclusively Gas RMS Bib-III 14 through the issue of an Addendum pursuant to ITT Sub Clause 11 and not through the minutes of the Pre-Tender meeting. 10.4 Non-attendance at the Pre-Tender meeting will not be a cause for disqualification of a Tenderer. 11. Addendum to Tender Document 11.1 At any time prior to the deadline for submission of Tenders, the Procuring Entity, on its own initiative or in response to an inquiry in writing from a Tenderer, having purchased the Tender Document, or as a result of a Pre-Tender meeting may revise the Tender Document by issuing an Addendum. 11.2 The Addendum issued under ITT Sub Clause 11.1 shall become an integral part of the Tender Document and shall have a date and an issue number and must be circulated by fax, mail or e-mail, to Tenderers who have purchased the Tender Documents, within three (3) working days of issuance of such Addendum, to enable Tenderers to take appropriate action. 11.3 The Tenderers will acknowledge receipt of an Addendum within three (3) working days. 11.4 Procuring Entities shall also ensure posting of the relevant addenda with the reference number and date on their websites including notice boards, where the Procuring Entities had originally posted the IFTs. 11.5 To give a prospective Tenderer reasonable time in which to take an addendum into account in preparing its Tender, the Procuring Entity may, at its discretion, extend the deadline for the submission of Tenders, pursuant to ITT Sub Clause 42.2. 11.6 If an addendum is issued when time remaining is less than one-third of the time allowed for the preparation of Tenders, a Procuring Entity at its discretion shall extend the deadline by an appropriate number of days for the submission of Tenders, depending upon the nature of the Procurement requirement and the addendum. In any case, the minimum time for such extension shall not be less than three (3) working days. C. Qualification Criteria 12. General Criteria Gas RMS Bib-III 12.1 The Tenderer shall possess the necessary professional and technical qualifications and competence, financial resources, equipment and other physical facilities, managerial capability, specific experience, reputation, and the personnel, to perform the contract. 12.2 To qualify for multiple number of contracts/lots in a package made up of this and other individual contracts/lots for which tenders are invited in the Invitation for Tenders, the Tenderer shall demonstrate having resources and experience sufficient to meet the aggregate of the qualifying criteria for the individual contracts. 15 13. Litigation History 13.1 Litigation history shall comply with the requirement as specified in ITT 15.1(c). 14. Experience Criteria 14.1 The Tenderer shall have the following minimum level of construction experience to qualify for the performance of the Works under the Contract: (a) (b) 15. Financial Criteria 16. Personnel Capacity a minimum number of years of general experience in the construction of works as Prime Contractor or Subcontractor or Management Contractor as specified in the TDS; and Specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of a nature, complexity and methods/construction technology similar to the proposed Works in at least a number of contract(s) and of a minimum value over the period, as specified in the TDS. 15.1 The Tenderer shall have the following minimum level of financial capacity to qualify for the performance of the Works under the Contract. 16.1 (a) the average annual construction turnover as specified in the TDS during the period specified in the TDS; (b) availability of minimum liquid assets or working capital or credit facilities, as specified in the TDS; and (c) satisfactory resolution of all claims, arbitrations or other litigation cases and shall not have serious negative impact on the financial capacity of the Tenderer. The Tenderer shall have the following minimum level of personnel capacity to qualify for the performance of the Works under the Contract: (a) a Construction Project Manager, Engineers, and other key staff with qualifications and experience as specified in the TDS; 17. Equipment Capacity 17.1 The Tenderer shall own suitable equipment and other physical facilities or have proven access through contractual arrangement to hire or lease such equipment or facilities for the desired period, where necessary or have assured access through lease, hire, or other such method, of the essential equipment, in full working order, as specified in the TDS. 18. Joint Venture, Consortium or Association (JVCA) 18.1 The Tenderer may participate in the procurement proceedings forming a Joint Venture, Consortium or Associations (JVCA) by an agreement,executed case by case on a non judicial stamp of value as stated in TDS or alternately with the intent to enter into such an agreement supported by a Letter of Intent along with the proposed agreement duly signed by all partners of the intended JVCA and authenticated by a Notary Public . 18.2 The figures for each of the partners of a JVCA shall be added Gas RMS Bib-III 16 together to determine the Tenderer’s compliance with the minimum qualifying criteria; however, for a JVCA to qualify, lead partner and its other partners must meet the criteria stated in TDS Failure t comply with these requirements will result in rejection of the JVCA Tender. Subcontractors’ experience and resources will not be taken into account in determining the Tenderer’s compliance with the qualifying criteria. 19. Subcontractor(s) 18.3 Each partner of the JVCA shall be jointly and severally liable for the execution of the Contract, all liabilities and ethical and legal obligations in accordance with the Contract terms. 18.4 The JVCA shall nominate a Representative (partner-in-charge) who shall have the authority to conduct all business for and on behalf of any and all the partners of the JVCA during the tendering process and, in the event the JVCA is awarded the Contract, during contract execution including the receipt of payments for and on behalf of the JVCA. 18.5 Each partner of the JVCA shall complete the JVCA Partner Information (Form PW3-3) for submission with the Tender. 19.1 A Tenderer may intend to subcontract an activity or part of the Works, in which case such elements and the proposed Subcontractor shall be clearly identified. 19.2 The Procuring Entity may require Tenderers to provide more information about their subcontracting arrangements. If any Subcontractor is found ineligible or unsuitable to carry out the subcontracted tasks, the Procuring Entity may request the Tenderer to propose an acceptable substitute. 19.3 The Procuring Entity may also select nominated Subcontractor(s) to execute certain specific components of the Works and if so, those will be specified in the TDS. 19.4 The successful Tenderer shall under no circumstances assign the Works or any part of it to a Subcontractor. 19.5 Each Subcontractor shall complete the Subcontractor Information (Form PW3-4 ) for submission with the Tender. D. Tender Preparation 20. Only one Tender 20.1 A Tenderer shall submit only one (1) Tender for each lot, either individually or as a JVCA. The Tenderer who submits or participates in more than one (1) Tender in one (1) lot will cause all the Tenders of that particular Tenderer to be rejected. 21. Cost of Tendering 21.1 The Tenderer shall bear all costs associated with the preparation and submission of its Tender, and the Procuring Entity shall not be responsible or liable for those costs, regardless of the conduct or outcome of the Tendering process. 22. Issuance and Sale of 22.1 Tender Document A Procuring Entity shall make Tender Documents available immediately to the potential Tenderers, requesting and willing to purchase at the corresponding price if the advertisement has been published in the newspaper. 22.2 There shall not be any pre-conditions whatsoever, for sale of Tender Gas RMS Bib-III 17 Documents and the sale of such Document shall be permitted up to the day prior to the day of deadline for the submission of Tender. 23. Language of Tender 24. Contents of Tender 23.1 The Tender shall be written in the English language. Correspondences and documents relating to the Tender may be written in English or Bangla. Supporting documents and printed literature furnished by the Tenderer that are part of the Tender may be in another language, provided they are accompanied by an accurate translation of the relevant passages in the English or Bangla language, in which case, for purposes of interpretation of the Tender, such translation shall govern. 23.2 The Tenderer shall bear all costs of translation to the governing language and all risks of the accuracy of such translation. 24.1 The Tender prepared by the Tenderer will comprise the following: (a) the Tender Submission Letter in accordance with ITT Clause 25 (Form PW3-1); 24.2 (b) Tenderer Information in accordance with ITT Clauses 5,29 and 32 (Form PW3-2); (c) the priced Bill of Quantities for each lot in accordance with ITT Clauses 25,27 and 28; (d) Tender Security as stated under ITT Clauses 35, 36 and 37. (e) alternatives, if permissible, as stated under ITT Clause 26; (f) written confirmation authorizing the signatory of the Tender to commit the Tenderer, as stated under ITT Sub Clause 40.3; (g) Valid Trade license ; (h) documentary evidence of Tax Identification Number (TIN) and Value Added Tax (VAT) as a proof of taxation obligations as stated under ITT Sub Clause 5.9; (i) documentary evidence as stated under ITT Clause 29 establishing the Tenderer’s qualifications to perform the Contract if its tender is accepted; (j) Technical Proposal describing work plan & method, personnel, equipment and schedules as stated under ITT Clause 31; (k) documentary evidence as stated under ITT Clause 32 establishing the minimum qualifications of the Tenderer required to be met for due performance of the Works and physical services under the Contract; and (l) any other document as specified in the TDS. In addition to the requirements stated under ITT Sub Clause 24.1, Tenders submitted by a JVCA or proposing a Subcontractor shall include: (a) a Joint Venture Agreement entered into by all partners, executed on a non-judicial stamp of value or equivalent as stated under ITT Sub Clause 18.1; or (b) Gas RMS Bib-III a Letter of Intent alo ng with the proposed agreement duly signed by all partners of the intended JVCA with the 18 declaration that it will execute the Joint Venture agreement in the event the Tenderer is successful; 25. Tender Submission Letter and Bill of Quantities 26. Alternatives 27. Tender Prices, Discounts and Price Adjustment the JVCA Partner Information (Form PW3-3 ); (d) the Subcontractor Information (Form PW3-4). 25.1 The Tenderer shall submit the Tender Submission Letter (Form PW3-1), which shall be completed without any alterations to its format, filling in all blank spaces with the information requested, failing which the Tender may be rejected as being incomplete. 25.2 The Tenderer shall submit the priced Bill of Quantities using the form(s) furnished in Section 6: Bill of Quantities. 25.3 If in preparing its Tender, the Tenderer has made errors in the unit rate or price or the total price, and wishes to correct such errors prior to submission of its Tender, it may do so, but shall ensure that each correction is initialled by the authorised person of the Tenderer. 26.1 Unless otherwise stated in the TDS, alternatives shall not be considered. 26.2 When alternative times for completion are explicitly invited, a statement to that effect will be included in the TDS, as will the method of evaluating different times for completion. 26.3 Except as provided under ITT Sub Clause 26.4, Tenderers wishing to offer technical alternatives to the requirements of the Tender Documents must first price the Procuring Entity’s design as described in the Tender Documents and shall further provide all information necessary for a complete evaluation of the alternative by the Procuring Entity, including drawings, designs, design calculations, technical specifications, breakdown of prices, and proposed construction methodology and other relevant details. 26.4 When specified in ITT clause 26.1, Tenderers are permitted to submit alternative technical solutions for specified parts of the Works, and such parts will be identified in the TDS. 26.5 Only the technical alternatives, if any, of the lowest evaluated Tenderer conforming to the basic technical requirements will be considered by the Procuring Entity. 27.1 The prices and discounts quoted by the Tenderer in the Tender Submission Letter (Form PW3-1 ) and in the Bill of Quantities (BOQ) shall conform to the requirements specified below. 27.2 27.3 27.4 Gas RMS Bib-III (c) The Tenderer shall fill in unit rates or prices for all items of the Works both in figures and in words as described in the BOQ. The items quantified in the BOQ for which no unit rates or prices have been quoted by the Tenderer will not be paid for, by the Procuring Entity when executed and shall be deemed covered by the amounts of other rates or prices in the BOQ and, it shall not be a reason to change the Tender price. The Procuring Entity may, if necessary, require the Tenderer to submit the detail breakdown of the unit rates or prices quoted by the Tenderer for the facilitation of the Tender proceedings. 19 27.5 The price to be quoted in the Tender Submission Letter, as stated under ITT Sub Clause 25.1, shall be the total price of the Tender, excluding any discounts offered. 27.6 The Tenderer shall quote any unconditional discounts and the methodology for application of discount in the Tender Submission Letter as stated under ITT Sub Clause 25.1. 27.7 Tenderers wishing to offer any price reduction for the award of more than one lot shall specify in their Tender the price reductions applicable to each lot, or alternatively, to any combination of lo ts within the package. Price reductions or discounts will be submitted as stated under ITT Sub Clause 27.1, provided the Tenders for all lots are submitted and opened together. 27.8 All applicable taxes, custom duties, VAT and other levies payable by the Contractor under the Contract, or for any other causes, as of the date twenty-eight (28) days prior to the deadline for submission of Tenders, shall be included in the unit rates and prices and the total Tender price submitted by the Tenderer. 27.9 Unless otherwise provided in the TDS and the Contract, the price of a Contract shall be fixed in which case the unit rates or prices may not be modified in response to changes in economic or commercial conditions. 27.10 If so indicated under ITT Sub Clause 27.9, Tenders are being invited with a provision for price adjustments. The unit rates or prices quoted by the Tenderer are subject to adjustment during the performance of the Contract in accordance with the provisions of GCC Clause 71 and, in such case the Procuring Entity shall provide the indexes and weightings or coefficients in Appendix to the Tender for the price adjustment formulae specified in the PCC. 27.11 The Procuring Entity may require the Tenderer to justify its proposed indexes, if any of those as stated under ITT Sub Clause 27.10, are instructed to be quoted by the Tenderer in Appendix to the Tender. 28. Tender Currency Gas RMS Bib-III 28.1 The Tenderer shall quote all prices in the Tender Submission Letter and in the Bill of Quantities in Bangladesh Taka currency unless otherwise specified in the TDS. 20 29. Documents Establishing Eligibility of the Tenderer 29.1 A Tenderer, if applying as a sole Tenderer, shall submit documentary evidence to establish its eligibility as stated under ITT Clause 5 and, in particular, it shall: (a) complete the eligibility declarations in the Tender Submission Letter (Form PW3-1); (b) complete the Tenderer Information (Form PW3-2 ); (c) provide completed Subcontractor Information (Form PW3-4), if it intends to engage any Subcontractor(s). 29.2 A Tenderer, if applying as a partner of an existing or intended JVCA shall submit documentary evidence to establish its eligibility as stated under ITT Clause 5 and, in particular, in addition to as specified in ITT Sub Clause 29.1, it shall: (a) (b) provide for each JVCA partner, completed JVCA Partner Information (Form PW3-3); provide the JVCA agreement or Letter of Intent along with the proposed agreement of the intended JVCA as stated in ITT Sub Clause 18.1. 30. Documents 30.1 Establishing the Eligibility and Conformity of Materials, Equipment and Services 30.2 The Tenderer shall submit documentary evidence to establish the origin of all Materials, Equipment and services to be supplied under the Contract as stated under ITT Clause 6. 31. Documents Establishing Technical Proposal The Tenderer shall furnish a Technical Proposal including a statement of work methods, equipment, personnel, schedule and any other information as stipulated in TDS, in sufficient detail to demonstrate the adequacy of the Tenderer’s proposal to meet the work requirements and the completion time. Gas RMS Bib-III 31.1 To establish the conformity of the Materials, Equipment and services to be supplied under the Contract, the Tenderer shall furnish, as part of its Tender, the documentary evidence (which may be in the form of literature, specifications and brochures, drawings or data) that these conform to the technical specifications and standards specified in Section 7, General Specifications and Section 8, Particular Specifications. 21 32. Documents Establishing the Tenderer’s Qualification 32.1 Tenderers shall complete and submit the Tenderer Information (Form PW3-2) and shall include documentary evidence, as applicable to satisfy the following: (a) general experience of construction works as stated under ITT Sub Clause 14.1(a) ; (b) specific experience in construction works of similar nature and size as stated under ITT Sub Clauses 14.1(b) (c) average annual construction turnover for a period as stated under ITT Sub Clause 15.1(a); (d) adequacy of working capital for this Contract i.e. access to line(s) of credit and availability of other financialresourcesas stated under ITT Sub Clause 15.1(b); (e) technical and administrative personnel along with their qualification and experience proposed for the Contract as stated under ITT Clause 16; (f) major items of construction equipment proposed to carry out the Contract as stated under ITT Clause 17; (g) authority to seek references from the Tenderer’s bankers or any other sources. (h) information regarding any litigation, current or during the last five years, in which the Tenderer is involved, the parties concerned, and disputed amount; (i) reports on the financial standing of the Tenderer, such as profit and loss statements and auditor’s reports for the past five years. 32.2 An Procuring Entity shall disqualify a Tenderer who submits a document containing false information for purposes of qualification or mislead or makes false representations in proof of qualification requirements. An Procuring Entity may declare such a Tenderer ineligible, either indefinitely or for a stated period of time, from participation in future procurement proceedings 32.3 An Procuring Entity may disqualify a Tenderer if it finds at any time that the information submitted concerning the qualifications of the Tenderer was materially inaccurate or materially incomplete. Also, an Procuring Entity may disqualify a Tenderer who has record of poor performance such as abandoning the works, not properly completing the contract, inordinate delays, litigation history or financial failures. 33. Validity Period of Tender 33.1 Tenders shall remain valid for the period specified in the TDS after the date of Tender submission deadline prescribed by the Procuring Entity.. A Tender valid for a period shorter than that specified will be rejected by the Procuring Entity as non- responsive. 34. Extension of Tender Validity and Tender Security 34.1 In exceptional circumstances, prior to the expiration of the Tender validity period, the Procuring Entity may solicit the Tenderers’ consent to an extension of the period of validity of their Tenders. 34.2 The request and the responses shall be made in writing. Validity of the tender security provided under ITT Clause 35 shall also be Gas RMS Bib-III 22 suitably extended for twenty eight (28) days beyond the new date for the expiry of the Tender Validity. If a Tenderer does not respond or refuses the request it shall not forfeit its tender securit , but its tender shall no longer be considered in the evaluation proceedings. A Tenderer agreeing to the request will not be required or permitted to modify its tender. 35. Tender Security 35.1 The Tenderer shall furnish as part of its Tender, in favour of the Procuring Entity or as otherwise directed on account of the Tenderer, a Tender Security in original form and in the amount, as specified in the TDS. 35.2 If the Tender is a Joint Venture, the Tenderer shall furnish as part of its Tender, in favour of the Procuring Entity or as otherwise directed on account of the title of the existing or intended JVCA or any of the partners of that JVCA or in the names of all future partners as named in the Letter of Intent of the JVCA, a Tender Security in original form and in the amount as stated under ITT Sub Clause 35.1. 36. Form of Tender Security 36.1 The Tender Security shall: (a) at the Tenderer’s option, be either; i. in the form of a bank draft or pay order, or ii. in the form of an irrevocable bank guarantee issued by a scheduled Bank of Bangladesh, in the format (Form PW3-6) furnished in Section 5: Tender and Contract Forms; (b) be payable promptly upon written demand by the Procuring Entity in the case of the conditions listed in ITT Sub Clause 39.1 being invoked; and (c) remain valid for at least twenty eight (28) days beyond the expiry date of the Tender Validity in order to make a claim in due course against a Tenderer in the circumstances as stated under ITT Sub Clause 39.1. 37. Authenticity of Tender Security 37.1 The authenticity of the Tender Security submitted by a Tenderer may be examined and verified by the Procuring Entity at its discretion in writing from the Bank issuing the security. 37.2 If a Tender Security is found to be not authentic, the Procuring Entity may proceed to take measures against that Tenderer as stated under ITT Sub Clause 4.4. 37.3 A Tender not accompanied by a valid Tender Security will be rejected by the Procuring Entity. 38.1 No Tender Securities shall be returned by the Tender Opening Committee (TOC) during and after the opening of the Tenders. 38.2 No Tender Security shall be returned to the Tenderers before contract signing, except to those who are found unsuccessful. 38.3 Unsuccessful Tenderer’s tender security will be discharged or returned as soon as possible but within 28 days of the end of the tender validity period specified in ITT Sub-Clauses 33.1. 38. Return of Tender Security Gas RMS Bib-III 23 39. Forfeiture of Tender Security 40. Format and Signing of Tender 38.4 The tender security of the Successful Tenderer will be discharged upon the Tenderer’s furnishing of the performance security pursuant to ITT Clause 33 and signing the Agreement. 39.1 The Tender Security may be forfeited, if a Tenderer: (a) withdraws its Tender after opening of Tenders but within the validity of the Tender as stated under ITT Clause 33 and 34; or (b) refuses to accept a Notification of Award as stated under ITT Sub Clause 63.1; or (c) fails to furnish Performance Security as stated under ITT Sub Clause 64.1 and 64.2; or (d) refuses to sign the Contract as stated under ITT Sub Clause 69.2 ; or (e) does not accept the correction of the Tender price following the correction of the arithmetic errors as stated under ITT Clause 55. 40.1 The Tenderer shall prepare one (1) original of the documents comprising the Tender as described in ITT Clause 24 and clearly mark it “ORIGINAL.” In addition, the Tenderer shall prepare the number of copies of the Tender, as specified in the TDS and clearly mark each of them “COPY.” In the event of any discrepancy between the original and the copies, the ORIGINAL shall prevail. 40.2 Alternatives, if permitted in accordance with ITT Clause 26, shall be clearly marked “Alternative”. 40.3 The original and each copy of the Tender shall be typed or written in indelible ink and shall be signed by the Person duly authorized to sign on behalf of the Tenderer. This authorization shall be attached to the Tender Submission Letter (Form PW3-1). The name and position held by each Person(s) signing the authorization must be typed or printed below the signature. All pages of the original and of each copy of the Tender, except for un-amended printed literature, shall be numbered sequentially and signed or initialled by the person signing the Tender. 40.4 Any interlineations, erasures, or overwriting will be valid only if they are signed or initialled by the Person(s) signing the Tender. E. 41. Sealing, Marking and Submission of Tender Tender Submission 41.1 The Tenderer shall enclose the original in one (1) envelo pe and all the copies of the Tender, including the alternatives, if permitted under ITT Clause 26, in another envelope, duly marking the envelopes as “ORIGINAL” “ALTERNATIVE” (if permitted) and “COPY.” These sealed envelopes will then be enclosed and sealed in one (1) single outer envelope. 41.2 The inner and outer envelopes shall: (a) Gas RMS Bib-III be addressed to the Procuring Entity at the address as stated under ITT Sub Clause 42.1; 24 (b) bear the name of the Tender and the Tender Number as stated under ITT Sub Clause 1.1; (c) bear the name and address of the Tenderer; (d) bear a statement “DO NOT OPEN BEFORE ----------------------” the time and date for Tender opening as stated under ITT Sub Clause 48.1; (e) bear any additional identification marks as specified in the TDS. 41.3 The Tenderer is sole ly and entirely responsible for pre-disclosure of Tender information if the envelope(s) are not properly sealed and marked. 41.4 Tenders shall be delivered by hand or by mail, including courier services at the address(s) as stated under ITT Sub Clause 42.1. 41.5 The Procuring Entity will, on request, provide the Tenderer with acknowledgement of receipt showing the date and time when it’s Tender was received. 42. Deadline for Submission of Tender 42.1 Tenders shall be delivered to the Procuring Entity at the address specified in the TDS and no later than the date and time specified in the TDS. 42.2 The Procuring Entity may, at its discretion, extend the deadline for submission of Tender as stated under ITT Sub Clause 42.1, in which case all rights and obligations of the Procuring Entity and Tenderers previously subject to the deadline will thereafter be subject to the new deadline as extended. 42.3 In general, the submission of Tenders will not be allowed in more than one place. If, in exceptional cases, for procurement using government’s own fund, submission of Tenders is allowed in more than one location/place, name of such primary and secondary location/place(s) shall be as specified in the TDS. 43. Late Tender 43.1 Any Tender received by the Procuring Entity after the deadline for submission of Tenders as stated under ITT Sub Clause 42.1 shall be declared LATE, rejected, and returned unopened to the Tenderer. 44. Notice for 44.1 A Tenderer may modify, substitute or withdraw its Tender after it has Modification, been submitted by sending a written notice duly signed by the Substitution or authorized signatory and properly sealed, and shall include a copy of Withdrawal of Tender the authorization ; provided that such written notice including the affidavit is received by the Procuring Entity prior to the deadline for submission of Tenders as stated under ITT Clause 42. 45. Tender Modification 45.1 The Tenderer shall not be allowed to retrieve its original Tender, but shall be allowed to submit corresponding modification to its original Tender marked as “MODIFICATION”. 46. Tender Substitution 46.1 The Tenderer shall not be allowed to retrieve its original Tender, but shall be allowed to submit another Tender marked as “SUBSTITUTION”. Gas RMS Bib-III 25 47. Tender Withdrawal F. 48. Tender Opening 47.1 The Tenderer shall be allowed to withdraw its Tender by a Letter of Withdrawal marked as “WITHDRAWAL”. Tender Opening and Evaluation 48.1 Tenders shall be opened in one location, immediately, but no later than one hour, after the deadline for submission of Tenders at the place as specified in the TDS. In case of submission of tender for procurement using Government’s own fund, tenders shall be opened at the primary place of submission within three hours of the deadline for submission of tenders. 48.2 Persons not associated with the Tender may not be allowed to attend the public opening of Tenders. 48.3 The Tenderers’ representatives shall be duly authorised by the Tenderer. Tenderers or their authorised representatives will be allowed to attend and witness the opening of Tenders, and will sign a register evidencing their attendance. 48.4 The authenticity of withdrawal or substitution of, or modifications to original Tender, if any made by a Tenderer in specified manner, shall be examined and verified by the Tender Opening Committee (TOC) based on documents submitted as stated under ITT Sub Clause 44.1. 48.5 Ensuring that only the correct (M), (S), (A), (O) envelo pes are opened, details of each Tender will be dealt with as follows: (a) the Chairperson of the Tender Opening Committee will read aloud each Tender and record in the Tender Opening Sheet (TOS) : (i) (ii) (iii) (iv) (v) (vi) (vii) the name and address of the Tenderer; state if it is a withdrawn, modified, substituted or original Tender; the Tender price; any discounts; any alternatives; the presence or absence of any requisite Tender Security; and such other details as the Procuring Entity, at its discretion, may consider appropriate (b) only discounts and alternatives read alo ud at the Tender opening will be considered in evaluation. (c) all pages of the original version of the Tender, except for unamended printed literature, will be initialled by members of the Tender Opening Committee. 48.6 Upon completion of Tender opening, all members of the Tender Opening Committee and the Tenderers or Tenderer’s duly authorised representatives attending the Tender opening shall sign Gas RMS Bib-III 26 by name, address, designation, the Tender Opening Sheet, copies of which shall be issued to the Head of the Procuring Entity or an officer authorised by him or her and also to the members of the Tend Opening Committee and any authorised Consultants and, to the Tenderers immediately. 48.7 The omission of a Tenderer’s signature on the record shall not invalidate the contents and effect of the record under ITT Sub Clause 48.6. 48.8 No Tender will be rejected at the Tender opening stage except the LATE Tenders as stated in the ITT Clause 43. 49. Evaluation of Tenders 49.1 Tenders shall be examined and evaluated only on the basis of the criteria specified in the Tender Document. 49.2 The Procuring Entity’s Tender Evaluation Committee (TEC) shall examine, evaluate and compare Tenders that are substantially responsive to the requirements of Tender Documents in order to identify the successful Tenderer. 50.1 The TEC will consider a Tender responsive that conforms in all respects to the requirements of the Tender Document without material deviation, reservation, or omission. The evaluation process should begin immediately after tender opening, following four broad steps: 50. Evaluation Process 51. Preliminary Examination (a) Preliminary examination (b) Technical examination and responsiveness (c) Financial evaluation and price comparison (d) Post-qualification of the Tender. 51.1 The Procuring Entity shall examine the tenders to confirm that all documentation requested in ITT Clause 24 has been provided, to determine the completeness of each document submitted. 51.2 The Procuring Entity shall confirm that the following documents and information have been provided in the tender. If any of these documents or information is missing, the offer shall be rejected. (a) Tender Submission Letter; (b) Priced Bill of Quantities; (c) Written confirmation of authorization to commit the Tenderer; and (d) Tender Security. 52. Technical 52.1 The Procuring Entity’s determination of a tender’s responsiveness is Responsiveness and to be based on the contents of the tender itself without recourse to Technical Evaluation extrinsic evidence. 52.2 Gas RMS Bib-III A substantially responsive tender is one that conforms in all respects to the requirements of the Tender Document without material deviation, reservation, or omission. A material deviation, reservation, or omission is one that: 27 (a) (b) (c) affects in any substantial way the scope, quality, or performance of the Works specified in the Contract; or limits in any substantial way, or is inconsistent with the Tender Documents, the Procuring Entity’s rights or the Tenderer’s obligations under the Contract; or if rectified would unfairly affect the competitive position of other Tenderers presenting substantially responsive tenders. 52.3 If a tender is not substantially responsive to the Tender Document, it shall be rejected by the Procuring Entity and shall not subsequently be made responsive by the Tenderer by correction of the material deviation, reservation, or omission. 52.4 There shall be no requirement as to the minimum number of responsive tenders. 52.5 There shall be no automatic exclusion of tenders which are above or belo w the official estimate. 52.6 The Procuring Entity shall now examine the tender to confirm that all terms and conditions specified in the GCC and the PCC have been accepted by the Tenderer without any material deviation or reservation. 52.7 The Procuring Entity shall evaluate the technical aspects of the tender submitted in accordance with ITT Clauses 30,31 and 32, to confirm that all requirements specified in Section 7: General Specifications and Section 8: Particular Specifications of the Tender Document have been met without any material deviation or reservation. 52.8 If, after the examination of the terms and conditions and the technical aspects of the tender, the Procuring Entity determines that the tender is not substantially responsive in accordance with ITT Sub-Clauses 52.6 and 52.7 , it shall reject the tender. 52.9 Provided that a tender is substantially responsive, the Procuring Entity may request that the Tenderer submit the necessary information or documentation, within a reasonable period of time, to rectify nonmaterial nonconformities or omissions in the tender related to documentation requirements. Such omission shall not be related to any aspect of the rates of the tender reflected in the Priced Bill of Quantities. Failure of the Tenderer to comply with the request may result in the rejection of its tender. 52.10 The TEC may regard a Tender as responsive even if it contains; 53. Clarification on Gas RMS Bib-III 53.1 (a) minor or insignificant deviations which do not meaningfully alter or depart from the technical specifications, characteristics and commercial terms and, conditions or other mandatory requirements set out in the Tender Document; or (b) errors or oversights, that if corrected, would not alter the key aspects of the Tender. The TEC may ask Tenderers for clarification of their Tenders, 28 Tender 54. Restrictions on Disclosure of Information 55. Correction of Arithmetical Errors including breakdowns of unit rates or prices, in order to facilitate the examination and evaluation of Tenders. The request for clarification by the TEC and the response from the T nderer s be in writing, and Tender clarifications which may lead to a change in the substance of the Tender or in any of the key elements of the Tender pursuant to ITT Sub Clause 52.2, will neither be sought nor be permitted. 53.2 Changes in the Tender price shall also not be sought or permitted, except to confirm the correction of arithmetical errors discovered by the TEC in the evaluation of the Tenders, as stated under ITT Sub Clause 55.1. 54.1 After the opening of tenders, information relating to the examination, clarification, and evaluation of tenders and recommendations for award shall not be disclosed to tenderers or other persons not officially concerned with the evaluation process until the award of the contract is announced. 54.2 Any effort by a Tenderer to influence a Procuring Entity in its decision concerning the evaluation of Tenders, Contract awards may result in the rejection of its Tender as well as further action in accordance with Section 64 (5) of the Public Procurement Act, 2006. 55.1 Provided that the Tender is substantially responsive, the TEC shall correct arithmetical errors on the following basis: 55.2 56. Financial Evaluation (a) if there is a discrepancy between the unit price and the line item total price that is obtained by multiplying the unit price and quantity, the unit price will prevail and the line item total price shall be corrected, unless in the opinion of the TEC there is an obvious misplacement of the decimal point in the unit price, in which case the total price as quoted will govern and the unit price will be corrected; and (b) if there is an error in a total corresponding to the addition or subtraction of subtotals, the subtotals shall prevail and the total shall be corrected; and (c) if there is a discrepancy between words and figures, the unit price in words will prevail, unless the amount expressed in words is related to an arithmetic error, in which case the amount in figures shall prevail subject to (a) and (b) above. If the Tenderer determined to be the lowest evaluated tenderer does not accept the correction of errors, its tender shall be disqualified and its tender security may be forfeited. 56.1 The TEC will evaluate each Tender that has been determined, up to this stage of the evaluation, to be substantially responsive to the requirements set out in the Tender Document. 56.2 To evaluate a Tender, the TEC will consider the following: (a) Gas RMS Bib-III the Tender price, excluding Provisional Sums and the provision, if any, for contingencies in the priced Bill of Quantities, but including Daywork items, where priced 29 competitively; (b) adjustments for correction of arithmetical errors pursuant to ITT Sub Clause 55.1; (c) adjustments in order to take into consideration the unconditional discounts or methodology for application of the discount offered pursuant to ITT Sub Clause 27.7; (d) adjustments for any other acceptable variations or deviations pursuant to ITT Sub Clause 52.10. 56.3 Variations, deviations, alternatives and other factors which are in excess of the requirements of the Tender Document or otherwise result in unsolicited benefits for the Procuring Entity will not be taken into account in Tender evaluation. 56.4 The estimated effect of any price adjustment provisions under GCC Clause 71, applied over the period of execution of the Contract, will not be taken into account in Tender evaluation. 56.5 If so indicated in the ITT Sub Clause 1.1 the Procuring Entity may award one or multiple lo ts to one Tenderer following the methodology specified in ITT Sub Clause 56.6. 56.6 To determine the lowest-evaluated lot or combination of lo ts, the TEC will take into account: (a) the experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual lot; (b) the lowest-evaluated Tender for each lot calculated in accordance with all the requirements of Evaluation Criteria; (c) the price reduction on account of discount per lot or combination of lots and the methodology for application of the discount as offered by the Tenderer in its Tender; and (d) the Contract-award sequence that provides the optimum economic combination on the basis of least overall cost of the total Contract package taking into account any limitations due to constraints in Works or execution capacity determined in accordance with the postqualification criteria stated under ITT Clause 59. 56.7 If the tender, which results in the lowest Evaluation Tender Price, is Substantially below the updated official estimate or seriously unbalanced as a result of front lo ading in the opinion of the Procuring Entity, the Procuring Entity may require the Tenderer to produce details price analyses for any or all items of the Bill of Quantities, to demonstrate the internal consistency of those prices with the construction methods and schedule proposed. After evaluation of the price analyses, taking into consideration the schedule of estimated Contract payments, the Procuring Entity may require that the amount of the performance security set forth in ITT Clause 64 be increased at the expenses of the Tenderer to a level sufficient to protect the Procuring Entity against financial loss in the event of default of the successful Tenderer under the Contract. Gas RMS Bib-III 30 57. Price Comparison 57.1 The TEC will compare all substantially responsive Tenders to determine the lo west-evaluated Tender, in accordance with ITT Clause 56. 57.2 In the extremely unlikely event that there is a tie for the lowest evaluated price, the Tenderer with the superior past performance with the Procuring Entity shall be selected, whereby factors such as delivery period, quality of Works delivered, complaints history and performance indicators could be taken into consideration. 57.3 In the event that there is a tie for the lowest price and none of the Tenderers has the record of past performance with the Procuring Entity as stated under ITT Sub Clause 57.2, then the Tenderer shall be selected, subject to firm confirmation through the Postqualification process, after consideration as to whether the Tenderer has demonstrated in its Tender superior past performance with the other Procuring Entities or a more efficient work programme and work methodolo gy. 57.4 The successful Tenderer as stated under ITT Sub Clauses 57.1, 57.2 and 57.3 shall not be selected through lottery under any circumstances. 58. Negotiations 59. Post-qualification 58.1 No negotiations shall be held during the Tender evaluation or award with the lowest or any other Tenderer. 58.2 The Procuring Entity through the TEC may, however, negotiate with the lowest evaluated Tenderer with the objective to reduce the Contract price by reducing the scope of works or a reallocation of risks and responsibilities, only when it is found that the lowest evaluated Tender is significantly higher than the official estimate; the reasons for such higher price being duly analyzed. 58.3 If the Procuring Entity decides to negotiate for reducing the scope of the requirements under ITT Sub Clause 58.2, it will be required to guarantee that the lowest Tenderer remains the lowest Tenderer even after the scope of work has been revised and shall further be ensured that the objective of the Procurement will not be seriously affected through this reduction. 58.4 In the event that the Procuring Entity decides because of a high Tender price to reduce the scope of the requirements to meet the available budget, the Tenderer is not obliged to accept the award and shall not be penalised in any way for rejecting the proposed award. 59.1 The Procuring Entity shall determine to its satisfaction whether the Tenderer that is selected as having submitted the lo west evaluated and substantially responsive tender is qualified to perform the Contract satisfactorily. 59.2 The determination shall be based upon an examination of the documentary evidence of the Tenderer’s qualifications submitted by the Tenderer, pursuant to ITT Clause 32, clarifications in accordance with ITT Clause 53 and the qualification criteria indicated in ITT Clauses 12 to 17. Factors not included therein shall not be used in the evaluation of the Tenderer’s qualification. Gas RMS Bib-III 31 59.3 An affirmative determination shall be a prerequisite for award of the Contract to the Tenderer. A negative determination shall result in rejection of the tenderer’s tender, in which event the Procuring Entity shall proceed to the next lo west evaluated tender to make a similar determination of that Tenderer’s capabilities to perform satisfactorily 59.4 The TEC may verify information contained in the Tender by visiting the premises of the Tenderer as a part of the post qualification process, if practical and appropriate. 60. Procuring Entity’s Right to Accept any or to Reject Any or All Tenders 60.1 61. Informing Reasons for Rejection 61.1 Notice of the rejection will be given promptly within seven (7) days of decision taken by the Procuring Entity to all Tenderers and, the Procuring Entity will, upon receipt of a written request, communicate to any Tenderer the reason(s) for its rejection but is not required to justify those reason(s). The Procuring Entity reserves the right to accept any tender, to annul the tender proceedings, or to reject any or all tenders at any time prior to contract award, without thereby incurring any liability to Tenderers, or any obligations to inform the Tenderers of the grounds for the Procuring Entity’s action. G. 62. Award Criteria Contract Award 62.1 The Procuring Entity shall award the Contract to the Tenderer whose offer is responsive to all the requirements of the Tender Document and that has been determined to be the lowest evaluated Tender, provided further that the Tenderer is determined to be Post-qualified in accordance with ITT Clouse 59. 62.2 A Tenderer will not be required, as a condition for award, to undertake responsibilities not stipulated in the Tender documents, to change its price, or otherwise to modify its Tender. 63. Notification of Award 63.1 Prior to the expiry of the Tender Validity period and within seven (7) working days of receipt of the approval of the award by the Approving Authority, the Procuring Entity shall issue the Notification of Award (NOA) to the successful Tenderer. 63.2 The Notification of Award, attaching the contract as per the sample (Form PW3-7) to be signed, shall state : (a) (b) (c) (d) (e) 63.3 Gas RMS Bib-III the acceptance of the Tender by the Procuring Entity; the price at which the contract is awarded; the amount of the Performance Security and its format; the date and time within which the Performance Security shall be submitted; and the date and time within which the Contract shall be signed. Until a formal contract is signed, the Notification of Award will constitute a Contract, which shall become binding upon the furnishing of a Performance Security and the signing of the 32 Contract by both parties. 64. Performance Security 64.1 The Performance Security shall be provided by the successful Tenderer in the amount as specified in the TDS and denominated in the currencies in which the Contract Price is payable. 64.2 The Procuring Entity may increase the amount of the Performance Security above the amounts as stated under ITT Sub Clause 64.1 but not exceeding twenty five (25) percent of the Contract price, if it is found that the Tender is Substantially below the updated official estimated or unbalanced as a result of front loading as stated under ITT Sub Clause 56.7. 64.3 The proceeds of the Performance Security shall be payable to the Procuring Entity unconditionally upon first written demand as compensation for any loss resulting from the Contractor’s failure to complete its obligations under the Contract. 65. Form and Time Limit 65.1 The Performance Security, as stated under ITT Clause 64, may for Furnishing of be in the form of a Bank Draft, Pay Order or an irrevocable Bank Performance Guarantee in the format (Form PW3-9), issued by any scheduled Security Bank of Bangladesh acceptable to the Procuring Entity. 65.2 Within fourteen (14) days from the date of acceptance of the Notification of Award (NOA) but not later than the date specified therein, the successful Tenderer shall furnish the Performance Security for the due performance of the Contract in the amount as stated under ITT Sub Clauses 64.1 or 64.2. 66. Validity of Performance Security 66.1 The Performance Security shall be required to be valid until a date twenty eight (28) days beyond the Intended Completion Date as specified in Tender Document. 67. Authenticity of Performance Security 67.1 The Procuring Entity may verify the authenticity of the Performance Security submitted by the successful Tenderer by sending a written request to the branch of the bank issuing the Pay Order, Bank Draft or irrevocable Bank Guarantee in specified format. 68. Adjudicator 68.1 The Procuring Entity proposes the person named in the TDS to be appointed as Adjudicator under the Contract, at an hourly fee and for those reimbursable expenses specified in the TDS. 69. Contract Signing 69.1 At the same time as the Procuring Entity issues the Notification of Award (NOA), the Procuring Entity will send the draft Contract Agreement and all documents forming the Contract to the successful Tenderer. 69.2 Within twenty-one (21) days of receipt of the Agreement, but not later than twenty–eight (28) days of issuance of the NOA, the successful Tenderer shall sign, date, and return it to the Procuring Entity. 69.3 Failure of the successful Tenderer to submit the Performance Security, pursuant to ITT Sub-Clause 64.1, or sign the Contract, pursuant to ITT Sub-Clause 69.2, shall constitute sufficient grounds for the annulment of the award and forfeiture of the Gas RMS Bib-III 33 Tender Security. In that event the Procuring Entity may award the Contract to the next lowest evaluated Tenderer, whose offer is substantially responsive and is determined by the Procuring Entity to be qualified to perform the Contract satisfactorily. 70. Publication of 70.1 Notification of Awards for Contracts of Taka ten (10) million and Notification of Award above shall be notified by the Procuring Entity to the Central of Contract Procurement Technical Unit within seven (7) days of issuance of the NOA for publication in their website, and that notice shall be kept posted for not less than a month. 70.2 Notification of Award for Contracts below Taka ten (10) million, shall be published by the Procuring Entity on its Notice Board and where applicable on the website of the Procuring Entity and that notice shall be kept posted for not less than a month. 71. Debriefing of Tenderers 71.1 Debriefing of Tenderers by Procuring Entity shall outline the relative status and weakness only of his or her Tender requesting to be informed of the grounds for not accepting the Tender submitted by him or her, without disclosing information about any other Tenderer. 71.2 In the case of debriefing, confidentiality of the evaluation process shall be maintained. 72. Right to Complain Gas RMS Bib-III 72.1 Any Tenderer has the right to complain in accordance with Section 29 of the Public Procurement Act 2006 and Part 12 of Chapter Three of the Public Procurement Rules, 2008. 34 Section 2. ITT Clause ITT 1.1 Tender Data Sheet Amendments of, and Supplements to, Clauses in the Instructions to Tenderers A. General The Employer is: Bangladesh Power Development Board. Representative : Secretary Bangladesh Power Development Board WAPDA Building (1st floor) Motijheel Commercial area, Dhaka-1000. Tel: 9554209, 9567350 Fax: 880-2-9564765 Consignee: Project Director, Bibiyana- III 400 MW CCPP Construction Project, BPDB, Bangladesh. The Name of the Tender is: ITT 3.1 ITT 3.3 ITT 5.1 ITT 6.1 ITT 7.1 ITT 8.2 Design-Build, Supply, Erection, Installation, Testing & Commissioning of Skid Mounted Gas Regulating & Metering Station for Supplying Natural Gas to Bibiyana -III 400 MW Combined Cycle Power Plant at Nabiganj Upazila, Habiganj District on Turnkey Basis. The source of public funds is Energy Development & Maintenance Fund of BPDB (Cash Foreign Exchange Allocation). The name of the Development Partner is – None Tenderers from the following countries are not eligible: Israel Materials, Equipments and associated services from the following countries are not eligible: Israel Each Tenderer before submitting his Tender will carefully examine the tender requirements and will visit the site at their own cost to determine the existing conditions, facilities and limitations. Any neglect to delay or failure on the part of the tenderer to obtain reliable information upon the foregoing or any matter effecting the work and completion period shall not relieve the successful tenderer of his responsibilities, risks or liabilities until final acceptance of the work in case of award of the contract. B. Tender Document The following are authorised agents of the Procuring Entity for the purpose of issuing the Tender Document: Director, Directorate of Purchase Bangladesh Power Development Board WAPDA Bhaban (9th Floor) Motijheel C/A, Dhaka -1000, Bangladesh Telephone: 9550532; Fax: 8802-7126151 Gas RMS Bib -III 35 ITT 9.1 ITT 10.1 For clarification of Tender Document purposes only, the Procuring Entity’s address is: Secretary Bangladesh Power Development Board WAPDA Building (1st floor) Motijheel Commercial area, Dhaka-1000. Tel: 9554209, 9567350 Fax: 880-2-9564765 Clarification should be submitted before two-third of time allowed for preparation and submission of Tender elapses as mentioned in Tender Invitation Notice. A Pre- Tender meeting shall not be held or The Pre- Tender meeting shall be held at (if sought by the ProspectiveTenderer) : Time & Date: To be informed later. ITT 14.1(a) ITT 14.1(b) C. Qualification Criteria The minimum number of years of general experience of the Tenderer shall be Ten (10) years. Qualification requirement of Tenderer: (a)The Tenderer shall have minimum ten (10) years of overall experience in Design, Supply, Installation/ Fabrication/ Construction, Testing and Commissioning of Skid Mounted Gas Regulating and Metering station on Turnkey basis; and (b)The Tenderer shall have proven experience in Detail Engineering, Design, Installation/ Fabrication / Construction, Testing and Commissioning of at least 02 (two) such CMS/RMS of minimum capacity of 50(fifty) MMCFD on Turnkey basis during last ten (10) years ; out of which at least 1 (one) CMS/RMS shall be in other than the home country of the Tenderer. (c) Bidders may form joint venture/ consortium/ Association (JCVA) to enhance their qualification. At least one of the members of the JVCA shall have qualification mentioned above in (a) and (b) Other members shall have Construction/ Fabrication work experience of minimum 40 MMCFD Gas CMS/RMS within last 7 years. Any member of qualified JVCA or any authorized local agent can purchase the bid document. Properly notarized version of all pertinent documents regarding change of name of any bidder or bidder inherited qualification from an acquired organization shall be submitted with the technical offer. Tenderers shall submit the documentary evidences i.e. copies of certificates obtained from the clients/end users evidencing satisfactory completion (along with satisfactory performance for at least 01 year) of such CMS/RMS on turnkey basis in favour of its specific experience. The certificates shall contain name of the major equipments/plants installed in the station, station capacity (MMSCFD), pressure designations, and year of completion, name and address (with Telephone, FAX & E-mail) of the clients.The certificate shall be in the official pad of the employers containing its full address. ITT 15.1(a) The required average annual construction turnover shall be greater than Equivalent USD 5.0 million over the last five (5) years; years counting backward from the date of publication of IFT in the newspaper. Gas RMS Bib -III 36 ITT 15.1(b) The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Equivalent USD 1.0 million. ITT 16.1(a) A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience: Qualified Engineer having at least 05 years experience of similar work. ITT 17.1 The Tenderer shall own or have proven access to hire or lease of the major construction equipments, in full working order as follows : As required to perform the work. ITT 18.1 The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk 300 (Three Hundred). ITT 18.2 The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows : TDS Clauses References Requirements by summation ITT-14.1(a) ITT-14.1(b) Summation not applicable 100% ITT-15.1(a) Requirements for Leading Partner Requirements for other Partner(s) As stated in TDS As stated in TDS As stated in TDS As stated in TDS 100% 40% 25% ITT-15.1(b) 100% 40% 25% ITT-16.1(a) 100% Not applicable Not applicable ITT-17.1 100% Not applicable Not applicable ITT 19.3 The Nominated Subcontractor(s) named [None] shall execute the following specific components of the proposed Works: None D. Tender Preparation The Tenderer shall submit with its Tender the following additional documents: ITT 24.1 The Tenderer must demonstrate that it has adequate expertise and resources to carry (l) out the scope of supply and work (as stated in the scope of work in Section 7). 1) Sealed & signed Tender document. 2) The Tenderer shall mention maximum days required for the completion of supply of spares/ equipment/ materials (at site) reckoning from the date of L/C opening and maximum days required for the completion of actual Turnkey work, including the schedule of work in bar chart form as well as in critical path method in the tender. 3) If Tenderer does not manufacture or produce the Goods it offers to supply shall submit the Manufacturer’s Authorization & Warranty/Guarantee Letter [Form PW3-5(a)] furnished in Section 5: Tender and Contract Forms, to demonstrate that it has been duly authorized by the manufacturer or producer of the Goods to supply the Goods to Bangladesh. Authorization & Warranty/Guarantee Letter from Dealer /Trading house will not be accepted if not supported by Manufacturer’s Authorization Letter. Authorization Gas RMS Bib -III 37 Letter from Manufacturer’s Sales office located in other country (not in the country of origin) may be allowed if supported by Manufacturer’s letter in this regard. Photocopy, Scanning Paper, E-mail copy, Faxed copy will not be allowed. Manufacturer’s Authorization & Warranty/Guarantee Letter is required for the items mentioned Section 6, Table 2 (RMS Equipment); Equipment/ Items shall have to be supplied from manufacturer/vendor as listed in Table 8 (G. Vendor List) of Setion 6: Schedule of Requirements. 4) Supply records of offered items/spares for last 5 years from manufacturer. 5) Warranty Certificate for a period of 24 (Twenty four) months from the date of Provisional Acceptance Certificate for the Turnkey work. 6) Tenderers shall have to submit Certificate from the manufacturer confirming that his offered items are new, unused, and in good condition. 7) Tenderer shall visit and examine the site and submit a site visit report along with confirmation that they have adequate information of the site and any work including supply of all necessary equipment, materials and consumables (in addition to those as specified in the scope of work) require to complete Turnkey work in all respect. 8) English version Original printed catalogue, drawings of offered equipment/ spares/items. 9) Detail specification, name of Manufacturer and the country of origin of the offered equipment/ spares/items. [Specifications Submission and Compliance Sheet (Form PW3-13)] 10) Tenderer shall have to submit Certificate confirming compliance to the terms and conditions of the Tender Document. 11) If Tenderer has any reservations, he has to mention it in deviation list (PW3-12). 12) End user certificates as mentioned in TDS [ITT14.1b]. 13) Audited financial reports and other documents in favour of financial criteria. 14) Supplier/vendor/manufacturer must have valid relevant ISO and API certificate. Supplier/vendor/ manufacturer must submit different Test certificate, Quality certificate, Technical operation & maintenance manual, Demo copy etc. of all materials & equipments. Gas RMS Bib -III 38 ITT 26.1 Alternatives will not be permitted. ITT 26.2 There shall not be alternative times for completion of the Works. ITT 26.4 Alternative technical solutions for any parts of works will not be permitted. ITT 27.9 The prices quoted by the Tenderer shall be fixed for the duration of the Contract. ITT 28.1 The currency of the Tender shall be: US Dollar/ Freely convertible international currency and Bangladesh Taka. Tenderers shall quote a Firm Turnkey Contract Price for the work as described in Section 6,7,8 & 9 of this Tender document. If the Tenderer deemed necessary any additional equipment/ materials / works out of the list of tender schedule for completion of the said Turnkey work, contractor shall have to do the additional works without any additional cost. The costs of these additional works are deemed to be included within the quoted price. During the course of work, the Contractor require to be carried out, that additional Contractor including supply of necessary complete the said additional work within payment shall be allowed in this respect. finds any additional supply/works work shall also be done by the spares/materials/ consumables to the Contract price. No additional ITT 31.1 The required Technical Documents shall include the following additional information: a) Detailed specification of all equipments, spares, materials & consumables to be supplied under this tender. b) Common approach or methodology for carrying out the work including detailed relevant information and work program. c) Complete CV with detail experience of the key personnel, who will perform the work. d) List of special tools, equipment and instruments which they intend to bring to Bangladesh on re-exportable basis for completion of the work. e) Each Tenderer before submitting his Tender, will carefully examine the tender requirements and will visit the site at their own cost to determine the existing conditions, facilities and limitations any neglect to delay or failure on the part of the Tenderer to obtain reliable information upon the foregoing or any matter effecting the work and completion period shall not relieve the successful Tenderer of his responsibilities, risks or liabilities until final acceptance of the work in case of award of the contract. f. List of special equipment and tools, which will be handed over to BPDB after completion of work (If any). ITT 33.1 The Tender Validity period shall be 180 (one hundred eighty) days. ITT 35.1 The amount of the Tender Security shall be USD 100,000.00 (US Dollar One Hundred Thousand only) or BDT 8,000,000.00 (Bangladesh Taka Eight million only) in the form of an irrevocable and unconditional Bank Guarantee(on non-judicial stamp) issued by a scheduled bank of Bangladesh or by a foreign bank duly confirmed by a scheduled bank in Bangladesh (“confirmed” means Bank Guarantee shall be payable/ encashable from the confirming bank in Bangladesh) in favour of Director, Directorate of Purchase, Bangladesh Power Development Board. Dhaka Gas RMS Bib -III 39 ITT 40.1 In addition to the original of the Tender, 03 (Three) copies shall be submitted. E. Tender Submission Tenders shall have to be submitted in a single sealed envelope in accordance with the ITT 41.1 requirements of the Tender document including addenda (if any). The original and three (03) copies of the complete proposal shall be submitted within the date and time as mentioned in the tender notice. ITT 41.2 The inner and outer envelopes shall bear the following additional identification marks: 1. Tender Enquiry No. & Date (e) 2. Brief Description of work 3. Name & Address of the Employer 4. Name & Address of the Tenderer. ITT 42.1 For Tender submission purposes only, the Procuring Entity’s address is: Attention: Secretary Address: Secretary Bangladesh Power Development Board WAPDA Building (1st floor) Motijheel Commercial area, Dhaka-1000. The deadline for the submission of Tenders is: As specified in the Tender Notice ITT 42.3 For Tender submission purposes only, the Procuring Entity’s address is: Address (PRIMARY PLACE ): Secretary Bangladesh Power Development Board WAPDA Building (1st floor) Motijheel Commercial area, Dhaka-1000. Address (SECONDARY PLACES): Submission of Tenders will not be allowed in more than one place. F. Tender Opening and Evaluation ITT 48.1 The Tender opening shall take place at (always the PRIMARY PLACE): Address: Secretary Bangladesh Power Development Board WAPDA Building (1st floor) Motijheel Commercial area, Dhaka-1000. Time & Date: As specified in the Tender Notice ITT 49.1 & Evaluation of the Tenders shall be carried out based on the following: 56.1 1.0 Exchange Rate For evaluation and comparison purpose, TEC shall convert all Tender prices expressed in the amounts in various currencies into an amount in Bangladeshi Taka currency, using the selling exchange rates established by the Bangladesh Bank, on the date of Tender opening . 2.0 Method of Tender Evaluation The Technical conformance shall be evaluated considering all the aspects (in Gas RMS Bib -III 40 connection with specified work) offered by each Tenderer as well as the data and information submitted and on proper judgment of the capability of individual Tenderer. The technical qualifications and overall capabilities of the Tenderers for carrying out the work as specified as well as the specifications of the equipment/system/ materials offered and fulfillment of the key dates shall be the essence for selection of technically responsive Tenderers. The evaluation will take into account the initial costs of the Tenders, which shall be determined by bringing the scope of work of all the Tenders to a common basis for complete fulfillment of the work. BPDB reserves the right to judge the reasonableness of the cost components quoted by the Tenderers. For the purpose of evaluation all costs shall be based on current prices as of the date of the tender closing. The Tender of which total evaluated cost is the lowest shall be adjudged the lowest Tender. The Tender quoting Completion time (including supply of materials and turnkey work) more than 300 days (From the date of opening of L/C to the date of completion of ICO) shall be rejected. G. Contract Award ITT 64.1 The amount of Performance Security shall be ten (10) percent of the Contract Price. The Performance Security shall be in the form of an irrevocable and unconditional Bank Guarantee issued by a scheduled bank of Bangladesh or by a foreign bank duly endorsed/authenticated by a scheduled bank of Bangladesh. ITT 68.1 The Adjudicator proposed by the Procuring Entity is [Will be selected as and when necessary. Adjudicator Appointing Authority: President of the Institution of Engineers, Bangladesh.]. The hourly fee shall be Tk [Will be informed later] and the reimbursable expenses shall be limited to [ will be informed later]. Gas RMS Bib -III 41 Section 3. General Conditions of Contract A. 1. Definitions Gas RMS Bib -III 1.1 General In the Conditions of Contract, which include Particular Conditions and these General Conditions, the following words and expressions shall have the meaning hereby assigned to them. Boldface type is used to identify the defined terms: (a) Act means The Public Procurement Act, 2006 (Act 24 of 2006). (b) Adjudicator is the expert appointed jointly by the Procuring Entity and the Contractor to resolve disputes in the first instance, as provided for in GCC Sub Clause 94.2. (c) Bill of Quantities (BOQ) means the priced and completed Bill of Quantities forming part of the Contract defined in GCC Clause 60. (d) Compensation Events are those defined in GCC Clause 69. (e) Competent Authority means the authority that gives decision on specific issues as per delegation of administrative and/or financial powers. (f) Completion Certificate means the Certificate issued by the Project Manager as evidence that the Contractor has executed the Works and Physical services in all respects as per design, drawing, specifications and Conditions of Contract. (g) Completion Date is the actual date of completion of the Works and Physical services certified by the Project Manager, in accordance with GCC Clause 80. (h) Contract Agreement means the Agreement entered into between the Procuring Entity and the Contractor, together with the Contract Documents referred to therein, including all attachments, appendices, and all documents incorporated by reference therein to execute, complete, and maintain the Works. (i) Contract Documents means the documents listed in GCC Clause 6, including any amendments thereto. (j) Contractor means the Person under contract with the Procuring Entity for the execution of Works under the Rules and the Act as stated in the PCC. (k) Contract Price means the price payable to the Contractor as specified in the Contract Agreement, 42 subject to such additions and adjustments thereto or deductions therefrom, for the execution, completion and maintenance of the Works in accordance with the provisions of the Contract. Gas RMS Bib -III (l) Contractor’s Tender is the completed Tender Document including the priced Bill of Quantities and the Schedules submitted by the Contractor to the Procuring Entity. (m) Cost means all expenditures reasonably incurred or to be incurred by the Contractor, whether on or off the Site, including overhead ,profit, taxes, duties, fees, and such other similar levies (n) Day means calendar day unless otherwise specified as working days. (o) Dayworks means work carried out following the instructions of the Procuring Entity or the authorised Project Manager and is paid for on the basis of time spent by the Contractor’s workers and equipment at the rates specified in the Schedules, in addition to payments for associated Materials and Plant. (p) Defect is any part of the Works not completed in accordance with the Contract. (q) Defects Correction Certificate is the certificate issued by the Project Manager upon correction of defects by the Contractor. (r) Drawings include calculations and other information provided in Section 9 or as approved by the Project Manager for the execution and completion of the Contract. (s) Goods mean the Contractor’s Equipment, Materials, Plant and Temporary Works, or any of them as appropriate. (t) Equipment is the Contractor’s apparatus, machinery, vehicles and other things required for the execution and completion of the Works and remedying any defects excluding Temporary Works and the Procuring Entity’s Equipment (if any ), Plant, Materials and any other things to form or forming part of the Permanent Works. (u) Force Majeure means an event or situation beyond the control of the Contractor that is not foreseeable, is unavoidable, and its origins not due to negligence or lack of care on the part of the Contractor; such events may include, but not be limited to, acts of the Government in its sovereign capacity, wars or revolutions, fires, floods, epidemics, quarantine restrictions, and freight embargoes or more as included 43 in GCC Clause 85.; me Gas RMS Bib -III neral Conditions of Cont (w) Government means the Government of the People’s Republic of Bangladesh. (x) “Head of the Procuring Entity” means the Secretary of a Ministry or a Division, the Head of a Government Department or Directorate; or the Chief Executive, by whatever designation called, of a local Government agency, an autonomous or semi-autonomous body or a corporation, or a corporate body established under the Companies Act; (y) Intended Completion Date is the date calculated from the Commencement Date as specified in the PCC, on which it is intended that the Contractor shall complete the Works and Physical services as specified in the Contract and may be revised only by the Project Manager by issuing an extension of time or an acceleration order. (z) Materials means things of all kinds other than Plant intended to form or forming part of the Permanent Works, including the supply-only materials, if any, to be supplied by the Contractor under the Contract. (aa) Month means calendar month. (bb) Original Contract Price is the Contract Price stated in the Procuring Entity’s Notification of Award (Form PW37) and further clearly determined in the PCC. (cc) Permanent works means the permanent works to be executed by the Contractor under the Contract. (dd) PCC means the Particular Conditions of Contract. (ee) Plant means the apparatus, machinery and other equipment intended to form or forming part of the Permanent Works, including vehicles purchased for the Procuring Entity and relating to the construction of the Works and Physical services. (ff) Procuring Entity means a Procuring Entity having administrative and financial powers to undertake procurement of Works and Physical services using public funds and is as named in the PCC who employs the Contractor to carry out the Works. (gg) Project Manager is the person named in the PCC or any other competent person appointed by the Procuring Entity and notified to the Contractor who is responsible for supervising the execution and completion of the Works and Physical services and administering the 44 Contract. (hh) Provisional Sums means amounts of money specified by the Procuring Entity in the Bill of Quantities which shall be used, at its discretion, for payments to Nominated Subcontractor(s) and for meeting other essential expenditures under the Contract pursuant to GCC Sub Clause 77. (ii) Retention Money means the accumulated retention moneys which the Procuring Entity retains under GCC Clause 72. (jj) Schedules means the document(s) entitled schedules, completed by the Contractor and submitted with the Tender Submission Letter, as included in the Contract. Such document may include the data, lists and schedules of rates and/or prices. (kk) Site means the places where the Permanent Works are to be executed including storage and working areas and to which Plant and Materials are to be delivered, and any other places as may be specified in the PCC as forming part of the Site. (ll) Site Investigation Reports are those that were included in the Tender Document and are factual and interpretative reports about the surface and subsurface conditions at the Site. (mm) Specification means the Specification of the Works included in the Contract and any modifications or additions to the specifications made or approved by the Project Manager in accordance with the Contract. Gas RMS Bib -III (nn) Start Date is the date defined in the PCC and it is the last date when the Contractor shall commence execution of the Works under the Contract. (oo) Subcontractor means a person or corporate body, who has a contract with the Contractor to carry out a part of the work in the Contract, which includes work on the Site. (pp) Temporary Works means all temporary works of every kind other than Contractor’s Equipment required on the Site for the execution and completion of the Permanent Works and remedying of any defects. (qq) Variation means any change to the Works directly procured from the original Contractor to cover increases or decreases in quantities, including the introduction of new work items that are either due to change of plans, design or alignment to suit actual field conditions, within the general scope and physical boundaries of the 45 contract. 2. Interpretatio n (rr) Works means all works associated with the construction, reconstruction, site preparation, demolition, repair, maintenance or renovation of railways, roads, highways, or a building, an infrastructure or structure or an installation or any construction work relating to excavation, installation of equipment and materials, decoration, as well as physical services ancillary to works as detailed in the PCC, if the value of those services does not exceed that of the Works themselves. (ss) Writing means communication written by hand or machine duly signed and includes properly authenticated messages by facsimile or electronic mail. 2.1 In interpreting the GCC, singular also means plural, male also means female or neuter, and the other way around. Headings in the GCC shall not be deemed part thereof or be taken into consideration in the interpretation or construance of the Contract. Words have their normal meaning under the language of the Contract unless specifically defined. 2.2 Entire Agreement The Contract constitutes the entire agreement between the Procuring Entity and the Contractor and supersedes all communications, negotiations and agreements (whether written or verbal) of parties with respect thereto made prior to the date of Contract Agreement; except those stated under GCC Sub Clause 6.1(j). 2.3 2.4 Non waiver (a) Subject to GCC Sub Clause 2.3(b), no relaxation, forbearance, delay, or indulgence by either party in enforcing any of the terms and conditions of the Contract or the granting of time by either party to the other shall prejudice, affect, or restrict the rights of that party under the Contract, neither shall any waiver by either party of any breach of Contract operate as waiver of any subsequent or continuing breach of Contract. (b) Any waiver of a party’s rights, powers, or remedies under the Contract must be in writing, dated, and signed by an authorized representative of the party granting such waiver, and must specify the right and the extent to which it is being waived. Severability If any provision or condition of the Contract is prohibited or Gas RMS Bib -III 46 rendered invalid or unenforceable, such prohibition, invalidity or unenforceability shall not affect the validity or enforceability of any other provisions and conditions of the Contract. 2.5 Sectional completion If sectional completion is specified in the PCC, references in the GCC to the Works, the Completion Date, and the Intended Completion Date apply to any section of the Works (other than references to the Completion Date and Intended Completion Date for the whole of the Works). 3. Communicati ons and Notices 3.1 Communications between Parties such as notice, request or consent required or permitted to be given or made by one party to the other pursuant to the Contract shall be in writing to the addresses specified in the PCC. 3.2 A notice shall be effective when delivered or on the notice’s effective date, whichever is later. 3.3 A Party may change its address for notice hereunder by giving the other Party notice of such change to the address. 4. Governing Law 4.1 The Contract shall be governed by and interpreted in accordance with the laws of the People’s Republic of Bangladesh. 5. Governing Language 5.1 The Contract shall be written in English. All correspondences and documents relating to the Contract may be written in English or Bangla. Supporting documents and printed literature that are part of the Contract may be in another language, provided they are accompanied by an accurate translation of the relevant passages in English, in which case, for purposes of interpretation of the Contract, such translation shall govern. 5.2 The Contractor shall bear all costs of translation to the governing language and all risks of the accuracy of such translation. 6. Documents Forming the Contract and Priority of Documents Gas RMS Bib -III 6.1 The following documents forming the Contract shall be interpreted in the following order of priority: (a) the signed Contract Agreement (Form PW3-8); (b) the Notification of Award (PW3-7); (c) the completed Tender and the appendix to the Tender; (d) the Particular Conditions of Contract; (e) the General Conditions of Contract; (f) the Technical Specifications; (g) the General Specifications; 47 7. Scope of Works (h) the Drawings; ( th (j) any other document listed in the PCC forming part of the Contract. riced Bill of Quantitie and the Schedu a 7.1 The Works to be executed, completed and maintained shall be as specified in the Bill of Quantities, the General and Particular Specifications and Drawings. 7.2 Unless otherwise stipulated in the Contract, the Works shall include all such items not specifically mentioned in the Contract but that can be reasonably inferred from the Contract as being required for completion of the Works as if such items were expressly mentioned in the Contract. 8. Assignment 8.1 Neither the Contractor nor the Procuring Entity shall assign, in whole or in part, its obligations under the Contract 9. Eligibility 9.1 The Contractor and its Subcontractor(s) shall have the nationality of a country other than that specified in the PCC. 9.2 All materials, equipment, plant, and supplies used by the Contractor in both permanent and temporary works and services supplied under the Contract shall have their origin in the countries except any specified in the PCC. 10. Gratuities / Agency fees 10.1 No fees, gratuities, rebates, gifts, commissions or other payments, other than those shown in the tender or in the Contract, have been given or received in connection with the procurement process or in the Contract execution. 11. Confidential Details 11.1 The Contractor’s and the Procuring Entity’s personnel shall disclose all such confidential and other information as may be reasonably required in order to verify the Contractor’s compliance with the Contract and allow its proper implementation. 11.2 Each of them shall treat the details of the Contract as private and confidential, except to the extent necessary to carry out their respective obligations under the Contract or to comply with applicable Laws. Each of them shall not publish or disclose any particulars of the Works prepared by the other Party without the previous agreement of the other Party. However, the Contractor shall be permitted to disclose any publicly available information, or information otherwise required to establish his qualifications to compete for other projects. 12. JVCA 12.1 If the Contractor is a JVCA , (a) Gas RMS Bib -III each partner of the JVCA shall be jointly and severally liable for all liabilities and ethical or legal obligations to 48 (b) 13. Possession of the Site 14. Access to the Site the Procuring Entity for the fulfilment of the promises of the Contract; the JVCA partners shall nominate a representative who shall have the authority to conduct all business including the receipt of payments for and on behalf of all partners of the JVCA; (c) the JVCA shall notify the Procuring Entity of its composition and legal status which shall not be altered without the prior approval of the Procuring Entity. (d) (d) alteration of partners shall only be allowed if any of the partners is found to be incompetent or has any serious difficulties which may impact the overall implementation of the works. 13.1 The Procuring Entity shall give possession of the Site or part(s) of the Site, to the Contractor on the date(s) stated in the PCC. If possession of a part of the Site is not given by the date stated in the PCC, the Procuring Entity will be deemed to have delayed the start of the relevant activities, and this will be a Compensation Event as stated under GCC Sub Clause 69.1(a). 14.1 The Contractor shall allow the Project Manager and any person authorised by the Project Manager access to the Site and to any place where work in connection with the Contract is being carried out or is intended to be carried out. 15.1 The Procuring Entity shall pay the Contractor, in consideration 15. Procuring of the satisfactory progress of execution and completion of the Entity’s Works and Physical services, and the remedying of defects Responsibili therein, the Contract price or such other sum as may become ties payable under the provisions of the Contract at the times and in the manner prescribed by the Contract Agreement. 15.2 The Procuring Entity shall make its best effort to guide and assist the Contractor in obtaining, if required, any permit, licence, and approvals from local public authorities for the purpose of execution of the Works and Physical services under the Contract. 16. Approval of the Contractor’s Temporary Works Gas RMS Bib -III 16.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary Works to the Project Manager, who is to approve them, if they comply with the Specifications and Drawings. 16.2 The Contractor shall be responsible for design of Temporary Works. 49 16.3 The Project Manager’s approval shall not alter the Contractor’s responsibility for design of the Temporary Works. 16.4 The Contractor shall obtain approval of third parties to the design of the Temporary Works, where required. 17. Contractor’s Responsibili ties 17.1 The Contractor shall execute and complete the Works and remedy any defects therein in conformity in all respects with the provisions of the Contract Agreement. 18. Taxes and Duties 18.1 The Contractor shall be entirely responsible for all taxes, duties, fees, and other such levies imposed inside and outside Bangladesh. 19. Contractor’s Personnel 19.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel, as referred to in the PCC, to carry out the functions stated in the Schedule or other personnel approved by the Project Manager. 19.2 The Project Manager will approve any proposed replacement of key personnel only if their relevant qualifications and abilities are equal to or higher than those of the personnel named in the Schedule. 19.3 If the Project Manager asks the Contractor to remove a particular person who is a member of the Contractor’s staff or work force from the Site, he or she shall state the reasons, and the Contractor shall ensure that the person leaves the Site within three (3) days and has no further connection with the work in the Contract. 20.1 Subcontracting the whole of the Works by the Contractor shall not be permissible. The Contractor shall be responsible for the acts or defaults of any Subcontractor, his or her agents or employees, as if they were the acts or defaults of the Contractor. 20.2 The prior consent, in writing, of the Project Manager shall however be obtained for other proposed Subcontractor(s). Subcontractors shall comply with the provisions of GCC Clause 39. 20. Subcontracti ng 20.3 21. Nominated Subcontract or Gas RMS Bib -III 21.1 Nominated Subcontractor named in the Contract shall be entitled to execute the specific components of the Works stated in the PCC. 21.2 The Contractor shall not be under obligations to employ a Nominated Subcontractor against whom the Contractor raises reasonable objection by notice to the Project manager as soon as practicable, with supporting particulars while there are reasons to believe that the Subcontractor does not have sufficient competence, resources or financial strength, or does not accept to indemnify the Contractor against and from any 50 negligence or Subcontractor. misuse of Goods by the nominated 21.3 Subcontracting shall in no event relieve the Contractor from any of its obligations, duties, responsibilities, or liability under the Contract and all Subcontractors shall comply with the provisions of GCC Clause 39. 22. Other Contractors 22.1 The Contractor shall cooperate and share the Site with other Contractors, public authorities, utilities, the Project Manager and the Procuring Entity between the dates given in the Schedule of other Contractors. The Contractor shall also provide facilities and services for them as described in the Schedule. The Procuring Entity may modify the Schedule of other Contractors, and shall notify the Contractor of any such modification. 23. Project Manager’s Decisions 23.1 Except where otherwise specifically stated in the PCC, the Project Manager will decide Contractual matters between the Procuring Entity and the Contractor in its role as representative of the Procuring Entity. 24. Delegation 24.1 The Project Manager may delegate any of his duties and responsibilities to his representative except to the Adjudicator, after notifying the Contractor, and may cancel any delegation, without retroactivity, after notifying the Contractor. 24.2 Any communications to the Contractor in accordance with such delegation shall have the same effect as if it was given by the Project Manager. 25. Instructions, 25.1 The Contractor shall carry out all instructions of the Project Manager that comply with the applicable law. 26. Queries about the Contract conditions 26.1 The Project Manager, on behalf of the Procuring Entity, will clarify queries on the Conditions of Contract. 27. Safety, Security and Protection of the Environment 27.1 The Contractor shall throughout the execution and completion of the Works and the remedying of any defects therein: (a) take all reasonable steps to safeguard the health and safety of all workers working on the Site and other persons entitled to be on it, and to keep the Site in an orderly state; (b) provide and maintain at the Contractor’s own cost all lights, guards, fencing, warning signs and watching for the protection of the Works or for the safety on-site; Gas RMS Bib -III 51 and (c) take all reasonable steps to protect the environment on and off the Site and to avoid damage or nuisance to persons or to property of the public or others resulting from pollution, noise or other causes arising as a consequence of the Contractors methods of operation. 28. Working Hours 28.1 The Contractor shall not perform any work on the Site on the weekly holidays, or during the night or outside the normal working hours, or on any religious or public holiday, without the prior written approval of the Project Manager. 29. Welfare of Labourers 29.1 The Contractor shall comply with all the relevant labour Laws applicable to the Contractor’s personnel relating to their employment, health, safety, welfare, immigration and shall allow them all their legal rights. 29.2 The Contractor, in particular, shall provide proper accommodation to his or her labourers and arrange proper water supply, conservancy and sanitation arrangements at the site for all necessary hygienic requirements and for the prevention of epidemics in accordance with relevant regulations, rules and orders of the government. 29.3 The Contractor, further in particular, shall pay reasonable wages to his or her labourers, and pay them in time. In the event of delay in payment the Procuring Entity may effect payments to the labourers and recover the cost from the Contractor. 30. Child Labour 30.1 The Contractor shall not employ any child to perform any work that is economically exploitative, or is likely to be hazardous to, or to interfere with, the child’s education, or to be harmful to the child’s health or physical, mental, spiritual, moral, or social develo pment in compliance with the applicable labor laws and other relevant treaties ratified by the government. 31. Discoveries 31.1 Anything of historical or other interest or of significant value unexpectedly discovered on the Site shall be the property of the Procuring Entity. The Contractor shall notify the Project Manager of such discoveries and carry out the Project Manager’s instructions for dealing with them. 32. Procuring Entity’s and Contractor’s Risks 32.1 The Procuring Entity carries the risks that the Contract states are Procuring Entity’s risks and the Contractor carries the risks that the Contract states are Contractor’s risks. 33. Procuring 33.1 From the Start Date until the Defects Correction Certificate Gas RMS Bib -III 52 Entity’s Risks has been issued, the following are Procuring Entity’s risks: (a) (b) 33.2 the risk of personal injury, death, or loss of or damage to property (excluding the Works, Plant, Materials, and Equipment), which are due to i. use or occupation of the Site by the Works or for the purpose of the Works, which is the unavoidable result of the Works or ii. negligence, breach of statutory duty, or interference with any legal right by the Procuring Entity or by any person employed by or Contracted to him except the Contractor. the risk of damage to the Works, Plant, Materials, and Equipment to the extent that it is due to a fault of the Procuring Entity or in the Procuring Entity’s design, or due to war or radioactive contamination directly affecting the country where the Works are to be executed. From the Completion Date until the Defects Correction Certificate has been issued, the risk of loss of or damage to the Works, Plant, and Materials is Procuring Entity’s risk, except loss or damage due to: (a) a Defect which existed on the Completion Date; (b) an event occurring before the Completion Date, which was not itself Procuring Entity’s risk; or the activities of the Contractor on the Site after the Completion Date. (c) 34. Contractor’s Risks 34.1 From the Start Date until the Defects Correction Certificate has been issued the risks of personal injury, death, and loss of or damage to property including without limitation, the Works, Plant, Materials, and Equipment, which are not Procuring Entity’s risks are Contractor’s risks. 35. Copyright 35.1 The copyright in all drawings, documents, and other materials containing data and information furnished to the Procuring Entity by the Contractor herein shall remain vested in the Contractor, or, if they are furnished to the Procuring Entity directly or through the Contractor by any third party, including Suppliers of materials, the copyright in such materials shall remain vested in such third party. 35.2 The Contractor shall not, except for the purposes of performing the obligations under the Contract, without the written permission of the Procuring Entity disclose or make use of any specification, plan, design and drawing, pattern, sample or information furnished by or on behalf of the Gas RMS Bib -III 53 Procuring Entity. 36. Limitation of Liability 37. Insurance 36.1 37.1 Except in cases of criminal negligence or wilful misconduct: (a) the Contractor shall not be liable to the Procuring Entity, whether in Contract, tort, or otherwise, for any indirect or consequential loss or damage, loss of use, loss of production, or loss of profits or interest costs, provided that this exclusion shall not apply to any obligation of the Contractor to pay liquidated damages to the Procuring Entity; and (b) the aggregate liability of the Contractor to the Procuring Entity, whether under the Contract, in tort or otherwise, shall not exceed the total Contract Price, provided that this limitation shall not apply to the cost of repairing or replacing defective Works, or to any obligation of the Contractor to indemnify the Procuring Entity with respect to patent infringement. The Contractor shall provide, in the joint names of the Procuring Entity and the Contractor, insurance cover from the Start Date to the end of the Defects Liability Period, in the amounts and deductibles specified in the PCC for the following events which are due to the Contractor’s risks: (a) loss of or damage to the Works, Plant, and Materials; (b) (c) loss of or damage to Equipment; loss of or damage to property (except the Works, Plant, Materials, and Equipment) in connection with the Contract; and personal injury or death. (d) 37.2 The Contractor shall deliver policies and certificates of insurance to the Project Manager, for the Project Manager’s approval, before the Start Date. All such insurances shall provide for compensation to be payable in the types and proportions of currencies required to rectify the loss or damage incurred. 37.3 If the Contractor does not provide any of the policies and certificates required, the Procuring Entity may effect the insurance which the Contractor should have provided and recover the premiums the Procuring Entity has paid from payments otherwise due to the Contractor or, if no payment is due, the payment of the premiums shall be a debt due. 37.4 Alterations to the terms of insurance shall not be made without the approval of the Project Manager. 37.5 Both parties shall comply with conditions of the insurance policies. Gas RMS Bib -III 54 38. Management and Progress Meetings 39. Corrupt, Fraudulent, Collusive or Coercive Practices Gas RMS Bib -III 38.1 Either the Project Manager or the Contractor may require the other to attend a management and progress meeting. The business of such meeting shall be to review the progress and plans for remaining work and to deal with matters raised in accordance with the early warning procedure. 38.2 The Project Manager shall record the business of the meetings and provide copies of the record to those attending the meeting and to the Procuring Entity. The responsibility of the parties for actions to be taken shall be decided by the Project Manager either at the management and progress meeting or after the meeting, and stated in writing to all concerned. 39.1 The Government requires that Procuring Entity, as well as the Contractor shall observe the highest standard of ethics during the implementation of procurement proceedings and the execution of the Contract under public fund. 39.2 For the purposes of GCC Sub Clause 39.4, the terms set forth below as follo ws: (a) “corrupt practice” means offering, giving or promising to give, receiving, or soliciting either directly or indirectly, to any officer or employee of a Procuring Entity or other public or private authority or individual, a gratuity in any form; employment or any other thing or service of value as an inducement with respect to an act or decision or method followed by a Procuring Entity in connection with a Procurement proceeding or Contract execution; (b) “fraudulent practice” means the misrepresentation or omission of facts in order to influence a decision to be taken in a Procurement proceeding or Contract execution; 55 Gas RMS Bib -III (c) “collusive practice” means a scheme or arrangement between two (2) or more Persons, with or without the knowledge of the Procuring Entity, that is designed to arbitrarily reduce the number of Tenders submitted or fix Tender prices at artificial, non-competitive levels, thereby denying a Procuring Entity the benefits of competitive price arising from genuine and open competition; or (d) “coercive practice” means harming or threatening to harm, directly or indirectly, Persons or their property to influence a decision to be taken in the Procurement proceeding or the execution of the Contract, and this will include creating obstructions in the normal submission process used for Tenders. (e) “obstructive practice” means deliberately destroying, falsifying, altering or concealing of evidence material to the investigation or making false statements to investigators in order to materially impede an investigation into allegations of a corrupt, fraudulent, coercive or collusive practice; and/or threatening, harassing or intimidating any party to prevent it from disclosing its knowledge of matters relevant to the investigation or from pursuing the investigation. 39.3 Should any corrupt, fraudulent, collusive, coercive or obstructive practice of any kind come to the knowledge of the Procuring Entity, it will, in the first place, allow the Contractor to provide an explanation and shall, take actions only when a satisfactory explanation is not received. Such exclusion and the reasons thereof, shall be recorded in the record of the procurement proceedings and promptly communicated to the Contractor. Any communications between the Contractor and the Procuring Entity related to matters of alleged corrupt, fraudulent, collusive, coercive or obstructive practices shall be in writing. 39.4 If corrupt, fraudulent, collusive, coercive or obstructive practices of any kind determined by the Procuring Entity against the Contractor alleged to have carried out such practices, the Procuring Entity will : (a) exclude the Contractor from further participation in the particular Procurement proceeding; or (b) declare, at its discretion, the Contractor to be ineligible to participate in further Procurement proceedings, either indefinitely or for a specific period of time. 56 39.5 39.6 The Contractor shall be aware of the provisions on corruption, fraudulence, collusion and coercion in Section 64 of the Public Procurement Act, 2006 and Rule 127 of the Public Procurement Rules, 2008. The Contractor shall permit the Procuring Entity and/or the Development Partner to inspect the Contractor’s accounts and records and other documents relating to the submission of tender and contract performance, and to have them audited by auditors appointed by the Procuring Entity and/or the Development Partner, if so required. B. Time Control 40. Commenceme 40.1 Except otherwise specified in the PCC , the Commencement Date shall be the date at which the following precedent nt of Works conditions have all been fulfilled and the Project Manager’s instruction recording the agreement of both Parties on such fulfilment and instructing to commence the Works is received by the Contractor: (a) (b) (c) signing of the Contract Agreement by both parties upon approval of the by relevant authorities; possession of the Site given to the Contractor as required for the commencement of the Works; and receipt by the Contractor of the Advance Payment under GCC Clause 75 provided that the corresponding Bank Guarantee has been delivered by the Contractor, if any. 40.2 The Contractor shall commence the execution of the Works as soon as is reasonably practicable by the Start Date as specified in the GCC Sub Clause 1.1(nn) after the Commencement Date, and shall then proceed with the Works with due expedition and without delay. 41. Completion of Works 41.1 The Contractor shall carry out the Works in accordance with the Programme of Works submitted by the Contractor and as updated with the approval of the Project Manager as stated under GCC Clause 42 to complete them in all respects by the Intended Completion Date. 42. Programme of Works 42.1 Within the time stated in the PCC, the Contractor shall submit to the Project Manager for approval a Programme of Works showing the general methods, arrangements, order, and timing for all the activities in the Works. The programme may be in the form of an Implementation Schedule prepared in any software or other form acceptable to the Project Manager. 42.2 The Contractor shall submit to the Project Manager for approval of an updated Programme at intervals no longer Gas RMS Bib -III 57 than the period stated in the PCC. An update of the Programme shall be a Programme showing the actual progress achieved on each activity and the effect of the progress achieved on the timing of the remaining work, including any changes to the sequence of the activities. 42.3 If the Contractor does not submit an updated Programme of Works at the intervals as stated under GCC Sub Clause 42.2 , the Project Manager may withhold an amount as stated in the PCC from the next payment certificate and continue to withhold this amount until the next due payment after the date on which the overdue Programme of Works has been submitted. 42.4 The Project Manager’s approval of the Programme of Works shall not alter the Contractor’s obligations. The Contractor may revise the Programme and submit it to the Project Manager again at any time for approval. A revised Programme shall show the effect of Variations and Compensation Events. 43. Pro Rata Progress 43.1 The Contractor shall maintain Pro Rata progress of the Works. Progress to be achieved shall be pursuant to GCC Clause 42 and shall be determined in terms of the value of the works done. 44. Early Warning 44.1 If at any time during performance of the Contract, the Contractor or its Subcontractors should encounter events, circumstances, conditions that may adversely affect the quality of the work, increase the original Contract Price or delay the execution of the Works, the Contractor shall promptly notify the Project Manager in writing of the delay, its likely duration, and its cause. As soon as practicable after receipt of the Contractor’s notice, the Project Manager shall evaluate the situation, and the Contractor shall cooperate with the Project Manager in making and considering proposals for how the effect of such an event or circumstance can be avoided or reduced. 44.2 The Project Manager may require the Contractor to provide an estimate of the expected effect of the future event or circumstance on the original Contract price and Completion Date. The Contractor shall provide the estimate and the Project Manager shall further proceed as soon as reasonably possible. 45. Extension of Intended Completion Date Gas RMS Bib -III 45.1 The Contractor shall be entitled to an extension of the Intended Completion Date, if and to the extent that completion of the Works or any part thereof is or will be delayed by Compensation Events or a Variation or Extra Work Order. 58 45.2 The Project Manager shall decide whether and by how much to extend the Intended Completion Date within twentyone (21) days of the Contractor asking the Project Manager for a decision upon the effect of a Compensation Event or Variation and submitting full supporting information. If the Contractor has failed to give early warning of a delay or has failed to cooperate in dealing with a delay, the delay by this failure shall not be considered in assessing the extension of Intended Completion Date. 45.3 Except in case of Force Majeure, as provided under GCC Clause 85, a delay by the Contractor in the performance of its Completion obligations shall render the Contractor liable to the imposition of Liquidated Damages pursuant to GCC Clause 73, unless an extension of Intended Completion Date is agreed upon, pursuant to GCC Clause 45. 46. Delays Caused by Authorities 46.1 If the following conditions apply, namely: (a) the Contractor has diligently followed the procedures laid down by the relevant legally constituted public authorities, (b) these public authorities delay or disrupt the Contractor’s work, and (c) the delay or disruption was unforeseeable; then this delay or disruption will be considered as a cause of delay under GCC Sub Clause 45.1. 46.2 The Project Manager shall notify the Contractor accordingly keeping the Procuring Entity posted. 47. Acceleration 47.1 When the Procuring Entity wants the Contractor to finish the Works before the Intended Completion Date, the Project Manager will obtain priced proposals for achieving the necessary acceleration from the Contractor. If the Procuring Entity accepts these proposals, the Intended Completion Date will be advanced accordingly and confirmed by both the Procuring Entity and the Contractor. 47.2 If the Procuring Entity accepts the Contractor’s priced proposals for acceleration, they will be incorporated in the Contract Price and treated as a Variation under GCC Clause 62. 48. Delays Ordered by the Project Manager 48.1 The Project Manager may instruct the Contractor to delay the start or progress of any activity within the Works. 49. Suspension of Work 49.1 The Project Manager may at any time instruct the Contractor to suspend progress of part or all of the Works. During such suspension, the Contractor shall protect, store and secure Gas RMS Bib -III 59 such part or the Works against any deterioration, loss or damage. 50. Consequenc es of Suspension 50.1 If the Contractor suffers delay and/or incurs Cost from complying with the Project Manager’s instructions under GCC Clause 49 and/or from resuming the work, the Contractor shall give notice to the Project Manager and shall be entitled subject to GCC Clause 93 to: (a) an extension of time for any such delay, if Completion is or will be delayed and (b) payment of any such cost, which shall be included in the Contract Price. 50.2 After receiving this notice, the Project Manager shall proceed to agree or determine these matters. 50.3 The Contractor shall not be entitled to any extension of time for, or to any payment of the cost incurred in, making good the consequences of the Contractor’s faulty design, workmanship or materials, or of the Contractor’s failure to protect, store or secure in accordance with GCC Clause 49. C. Quality Control 51. Execution of Works 51.1 The Contractor shall construct, install and carry out the Works and Physical services in accordance with the Specifications and Drawings as scheduled in GCC Clause 6. 52. Examination of Works before covering up 52.1 All works under the Contract shall at all times be open to examination, inspection, measurements, testing and supervision of the Project Manager, and the Contractor shall ensure presence of its representatives at such actions provided proper advance notice is given by the Project Manager. 52.2 No part of the Works shall be covered up or put out of sight without the approval of the Project Manager. The Contractor shall give notice in writing to the Project Manager whenever any such part of the Works is ready for examination and the Project Manager shall attend to such examination without unreasonable delay. 53. Identifying Defects Gas RMS Bib -III 53.1 The Project Manager shall check the works executed by the Contractor and notify the Contractor of any Defects found. Such checking shall not relieve the Contractor from his or her obligations. The Project Manager may also instruct the Contractor to search for a Defect and to uncover and test any work that the Project Manager considers may have a Defect. 60 54. Testing 54.1 If the Project Manager instructs the Contractor to carry out a test not specified in the Specification to check whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test and any samples. If there is no Defect, the test shall be a Compensation Event. 55. Rejection of Works 55.1 56. Remedial Work 56.1 Notwithstanding any test or certification, the Project Manager may instruct the Contractor to: (a) remove from the Site and replace any Plant or Materials which is not in accordance with the Contract, (b) remove and re-execute any other work which is not in accordance with the Contract, and If, as a result of an examination, inspection, measurement or testing, of Works it is found to be defective or otherwise not in accordance with the Contract, the Project Manager may reject the Works by giving notice to the Contractor, with reasons. The Contractor shall then promptly make good the defect and ensure that the rejected Works subsequently complies with the Contract. (c) execute any work which is urgently required for the safety of the Works, whether because of an accident, unforeseeable event or otherwise. 56.2 The Contractor shall comply with the instruction issued under GCC Sub Clause 56.1 within a reasonable time, which shall be specified in the instruction, or immediately if urgency is specified under GCC Sub Clause 56.1I. 56.3 If the Contractor fails to comply with the instruction issued under GCC Sub Clause 56.2, the Procuring Entity shall be entitled to employ and pay other persons to carry out the work. Except to the extent that the Contractor would have been entitled to payment for the work, the Contractor shall be liable to pay all such costs arising from this failure. 57. Correction of Defects 57.1 The Project Manager shall give notice to the Contractor, with a copy to the Procuring Entity and others concerned, of any Defects before the end of the Defects Liability Period, which begins at Completion Date, and is defined in the PCC. The Defects Liability Period shall be extended for as long as Defects remain to be corrected. 57.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Project Manager’s notice. 58. Uncorrected Gas RMS Bib -III 58.1 If the Contractor has not corrected a Defect within the time specified in the Project Manager’s notice, the Project 61 Defects Manager shall assess the cost of having the Defect corrected by it, and the Contractor shall remain liable to pay the expenditures incurred on account of correction of such Defect. D. Cost Control 59. Contract Price 59.1 The Contract Price shall be as specified in the Contract Agreement subject to any additions and adjustments thereto, or deductions therefrom, as may be made pursuant to Contract 60. Bill of Quantities 60.1 The Bill of Quantities shall contain priced items for the construction, installation, testing, and commissioning work to be done by the Contractor. 60.2 The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for the quantity of the work done at the rate in the Bill of Quantities for each item. 61.1 If the final quantity of the work done for any particular item increases from the quantity in the Bill of Quantities by more than twenty-five percent (25%), provided the change in case exceeds one percent (1%) of the original Contract Price, the Project Manager shall adjust the rate to allow for the change. 61.2 If requested by the Project Manager, the Contractor shall provide the Project Manager with a detailed cost breakdown of any rate in the Bill of Quantities. 62. Variations 62.1 All Variations and Extra Work Orders under the Contract shall be included in the updated Programme of Works produced by the Contractor. 63. Costing of Variations or Extra Orders 63.1 The Contractor shall provide the Project Manager with a quotation for carrying out the Variation when requested to do so by the Project Manager. The Project Manager shall assess the quotation, which shall be given within seven (7) days of the request or within any longer period stated by the Project Manager and before the Variation is ordered. 63.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Project Manager, the quantity of work not above the limit stated in GCC Sub-Clause 61.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the Bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of 61. Changes in the Quantities and Unit Rate or Price Gas RMS Bib -III 62 Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work. 63.3 If the Contractor’s quotation is found to be unreasonable, the Project Manager may order the Variation and make a change to the Contract price, which shall be based on the Project Manager’s own forecast of the effects of the Variation on the Contractor’s costs. 63.4 If the Project Manager decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event under GCC Sub Clause 69. 63.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning under GCC Sub Clause 44.1. 64. Cash Flow Forecasts 64.1 When the Programme of Works is updated under GCC Sub Clause 42.2, the Contractor shall provide the Project Manager with an updated cash flow forecast. 65. Payment Certificates 65.1 The basis for payment certificates shall be Bill of Quantities used to determine the Contract price. 65.2 The Contractor shall submit to the Project Manager monthly statements of the estimated value of the works executed less the cumulative amount certified previously. 65.3 The Project Manager shall check the Contractor’s monthly statement and certify the amount to be paid to the Contractor. 65.4 The value of work executed shall be determined by the Project Manager. 65.5 The value of work executed shall include the valuation of Variations or Extra Work Orders, Certified Dayworks and Compensation Events. 65.6 The Project Manager may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information. 66.1 Payments shall be adjusted for deductions for advance payments and retention. The Procuring Entity shall pay the Contractor the amounts certified by the Project Manager within twenty eight (28) days of the date of each certificate after due adjustments for deductions for advance payments, retention and any other additions or deductions which may have become due under the Contract or 66. Payments to the Contractor Gas RMS Bib -III 63 otherwise, including those under GCC Clause 93. 66.2 Items of works quantified in the Bill of Quantities for which no rates or prices have been quoted shall be deemed covered by the amounts at rates and prices of other items in the Contract. 66.3 Payments due to the Contractor in each certificate shall be made into the Bank Account in any scheduled Bank of Bangladesh of the title of the Contract specified in the PCC, nominated by the Contractor in the currency specified in the Contract. 67.1 If the Procuring Entity makes a late payment, the Contractor shall be paid interest on the late payment in the next payment. Interest shall be calculated from the date by which the payment should have been made up to the date when the late payment is made at the prevailing rate of interest for commercial borrowing for each of the currencies in which payments are made. 67.2 If an amount certified is increased in a subsequent certificate as a result of an award by the Adjudicator or an Arbitrator, the Contractor shall be paid interest upon the delayed payment as set out in this clause. Interest shall be calculated from the date upon which the increased amount would have been certified in the absence of dispute. 68. Payments to Nominated Subcontract or(s) 68.1 The Contractor shall pay to the Nominated Subcontractor(s) the amounts shown on the Nominated Subcontractor’s invoices approved by the Contractor which the Project Manager certifies to be due in accordance with the subcontract included under the Contract. 69. Compensati on Events 69.1 The following shall be Compensation Events: (a) The Procuring Entity does not give access to or possession of the Site or part of the Site by the Site Possession Date stated in the GCC Sub Clause 13.1; (b) The Procuring Entity modifies the Schedule of other Contractors in a way that affects the works of the Contractor under the Contract; (c) The Project Manager orders a delay or does not issue Drawings, Specifications, or instructions required for execution of the Works on time; (d) The Project Manager instructs the Contractor to uncover or to carry out additional tests upon work, which is then found to have no Defects; (e) The Project Manager unreasonably does not approve a subcontract to be let, if applicable; 67. Delayed Payment Gas RMS Bib -III 64 (f) (g) (h) (i) (j) The effects on the Contractor of any of the Procuring Entity’s Risks; (k) The Project Manager unreasonably delays issuing a Completion Certificate; A situation of Force Majeure has occurred, as defined in GCC Clause 85; and (l) (m) Gas RMS Bib -III Ground conditions are substantially more adverse than could reasonably have been assumed before issuance of the Notification of Award from the information issued to Tenderers (including the Site Investigation Reports), from information available publicly and from a visual inspection of the Site; The Project Manager gives an instruction for dealing with an unforeseen condition, caused by the Procuring Entity, or additional work required for safety or other reasons; Other Contractors, public authorities, utilities, or the Procuring Entity do not work within the dates and other constraints stated in the Contract, and they cause delay or extra cost to the Contractor; The advance payment is delayed; Other Compensation Events described in the Contract or determined by the Project Manager in the PCC shall apply. 69.2 If a Compensation Event would cause additional cost or would prevent the work being completed before the Intended Completion Date, the Contract price shall be increased and/or the Intended Completion Date shall be extended. The Project Manager shall decide whether and by how much the Contract price shall be increased and whether and by how much the Intended Completion Date shall be extended, only on justifiably acceptable grounds duly recorded. 69.3 As soon as the Contractor has provided information demonstrating the effect of each Compensation Event upon the Contractor’s forecast cost, the Project Manager shall assess it, and the Contract price shall be adjusted accordingly. If the Contractor’s forecast is deemed unreasonable, the Project Manager shall adjust the Contract price based on the Project Manager’s own forecast. The Project Manager will assume that the Contractor will react competently and promptly to the event. 69.4 The Contractor shall not be entitled to compensation to the extent that the Procuring Entity’s interests are adversely affected by the Contractor not having given early warning 65 or not having cooperated with the Project Manager. 70. Adjustments for Changes in Legislation 71. Price Adjustment 70.1 Unless otherwise specified in the Contract, if between the date twenty-eight (28) days before the submission of Tenders for the Contract and the date of the last Completion Certificate, any law, regulation, ordinance, order or bylaw having the force of law is enacted, promulgated, abrogated, or changed in Bangladesh (which shall be deemed to include any change in interpretation or application by the competent authorities) that subsequently affects the Completion Date and/or the Contract price, then such Completion Date and/or Contract price shall be correspondingly increased or decreased, to the extent that the Contractor has thereby been affected in the performance of any of its obligations under the Contract. 70.2 The Project Manager shall adjust the Contract Price on the basis of the change in the amount of taxes, duties, and other levies payable by the Contractor, provided such changes have not already been accounted for in the price adjustment as defined in GCC Clause 69 and/or reflected in the Contract price. 71.1 Prices shall be adjusted for fluctuations in the cost of inputs only if provided for in the PCC. If so provided, the amounts as certified in each payment certificate, before deducting for Advance Payment, shall be adjusted by applying the respective price adjustment factor to the payment amount. The formula indicated below applies: P= A + B (Im/Io) where: P is the adjustment factor A and B are Coefficients specified in the PCC, representing the nonadjustable and adjustable portions, respectively, of the Contract; and Im is the Index during the month the work has been executed and Io is the Index prevailing twenty eight (28) days prior to the deadline for submission of Tender. The Indexes to be used is as published by the Bangladesh Bureau of Statistics (BBS) on a monthly basis. In case not available, then other countries or authorities of the sources mentioned in Appendix to the Tender may be used. 72. Retention Money Gas RMS Bib -III 72.1 The Procuring Entity may retain from each progressive payment due to the Contractor at the percentage specified in the PCC until completion of the whole of the Works under the Contract. 66 72.2 On completion of the whole of the Works, the first half the total amount retained under GCC Sub Clause 72.1 shall be repaid to the Contractor and the remaining second half after the Defects Liability Period has passed and the Project Manager has certified in the form of Defects Corrections Certificate.. 72.3 On completion of the whole of the Works, the Contractor may substitute an unconditional Bank Guarantee in the format as specified (Form PW3-11 ) acceptable to the Procuring Entity for the second half of the retention money as stated under GCC Sub Clause 72.2. 73.1 The Contractor shall pay liquidated damages 1 6 to the Procuring Entity at the rate per day stated in the PCC for each day that the Completion Date is later than the Intended Completion Date. The total amount of liquidated damages shall not exceed the amount defined in the PCC. The Procuring Entity may deduct liquidated damages from payments due to the Contractor. Payment of liquidated damages shall not affect the Contractor’s liabilities. 73.2 If the Intended Completion Date is extended after liquidated damages have been paid, the Project Manager shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment certificate. 74. Bonus 74.1 The Contractor shall be paid a Bonus calculated at the rate per calendar day if stated in the PCC for each day (less any days for which the Contractor is paid for acceleration) that the Completion of the whole of the Works is earlier than the Intended Completion Date. The Project Manager shall require certifying that the Works are complete, although they may not have fallen due to being complete as per approved updated Programme of Works. 75. Advance Payment 75.1 If so specified in the PCC, the Procuring Entity shall make advance payment to the Contractor of the amounts and by the dates stated in the PCC against provision by the Contractor of an Unconditional Bank Guarantee in a form and by a bank acceptable to the Procuring Entity in an amount equal to the advance payment. The Guarantee shall remain effective until the advance payment has been repaid, but the amount of the Guarantee shall be progressively reduced by the amounts repaid by the Contractor. Interest will not be charged on the advance payment. 75.2 The Contractor shall use the advance payment only to pay 73. Liquidated Damages Gas RMS Bib -III 67 for Equipment, Plant, Materials, and mobilization expenses required specifically for execution of the Contract. The Contractor shall demonstrate that advance payment has been used for such specific purposes by supplying copies of invoices or other documents to the Project Manager. 76. Performance Security 75.3 The advance payment shall be repaid by deducting at proportionate rate from payments otherwise due to the Contractor, following the schedule of completed percentages of the Works on a payment basis. No account shall be taken of the advance payment or its repayment in assessing valuations of work done, Variations, price adjustments, Compensation Events, Bonuses, or Liquidated Damages. 76.1 The Procuring Entity shall notify the Contractor of any claim made against the Bank issuing the Performance Security. 76.2 The Procuring Entity may claim against the security if any of the following events occurs for fourteen (14) days or more. (a) (b) 77. Provisional Sums Gas RMS Bib -III The Contractor is in breach of the Contract and the Procuring Entity has duly notified him or her ; and The Contractor has not paid an amount due to the Procuring Entity and the Procuring Entity has duly notified him or her. 76.3 In the event the Contractor is liable to pay compensation under the Contract amounting to the full value of the Performance Security or more, the Procuring Entity may call the full amount of the Performance Security. 76.4 The Performance Security furnished at the time of signing of the Contract Agreement shall be substituted, after the issuance of certificate of Completion of works by the Project Manager, by a new Security covering fifty (50) percent amount of the Performance Security to cover the Defects Liability Period. 76.5 If there is no reason to call the Performance Security, the Performance Security shall be discharged by the Procuring Entity and returned to the Contractor after the Defects Liability period has passed and the Project Manager has certified in the form of Defects Corrections Certificates. . 77.1 Provisional Sums shall only be used, in whole or in part, in accordance with the Project Manager’s instructions and the Contract price shall be adjusted accordingly. The total sum paid to the Contractor shall include only such amounts, for the work, supplies or services to which the Provisional Sum relates, as the Project Manager shall have instructed. 68 78. Dayworks 79. Cost of Repairs to Loss or Damages E. 77.2 Plants, Materials or Services to be purchased by the Contractor under the provisions of GCC Sub Clause 77.1 from Nominated Subcontractor(s) or for meeting the other expenditures under the Contract, and for which there shall be included in the Contract price, the actual amounts paid or due to be paid by the Contractor, and a sum for VAT, profit and overhead charges, as applicable, calculated as a percentage of these actual amounts by applying the relevant percentage rate stated in the PCC. 77.3 The Contractor shall, when required by the Project Manager, produce quotations, invoices, vouchers and accounts or receipts in substantiation of purchases under GCC Sub Clause 77.2. 78.1 If applicable, the Dayworks rates in the Contractor’s Tender shall be used for small additional amounts of work only when the Project Manager has given written instructions in advance for additional work to be paid for in that way. 78.2 All works to be paid for as Dayworks shall be recorded by the Contractor on forms approved by the Project Manager. Each completed form shall be certified and signed by the Project Manager within seven (7) days of the works being done. 78.3 The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks forms. 79.1 Loss or damage to the Works or Materials to be incorporated in the Works between the Start Date and the end of the Defects Liability Period shall be remedied by the Contractor at the Contractor’s own cost, if the loss or damage arises from the Contractor’s acts or omissions. Completion of the Contract 80. Completion 80.1 The Contractor shall apply by notice to the Project Manager for issuing a Completion Certificate of the Works, and the Project Manager shall do so upon deciding that the work is completed. 81. Taking Over 81.1 The Procuring Entity shall take over the Site and the Works within seven (7) days of the Project Manager’s issuing a certificate of Completion. 82. Amendment to Contract 82.1 The amendment to Contract shall generally include extension of time to the Intended Completion Date, increase or decrease in original Contract price and any other changes acceptable under the conditions of the Gas RMS Bib -III 69 Contract. 83. Final Account 84. As-built Drawings and Manuals 85. Force Majeure 82.2 The Procuring Entity, in accordance with the Delegation of Financial Power or sub-delegation thereof, shall amend the Contract incorporating the changes introduced to the original terms and conditions of the Contract in line with the Rules. 83.1 The Contractor shall submit with a detailed account of the total amount that the Contractor considers payable under the Contract to the Project Manager before the end of the Defects Liability Period. 83.2 The Project Manager shall certify the Final Payment within fifty six (56) days of receiving the Contractor’s account if the payable amount claimed by the Contractor is correct and the corresponding works are completed. 83.3 If it is not, the Project Manager shall issue within fifty six (56) days a Defects Liability Schedule that states the scope of the corrections or additions that are necessary. 83.4 If the Final Account of Works submitted under GCC Sub Clause 83.1 is unsatisfactory even after it has been resubmitted, the Project Manager shall decide on the amount payable to the Contractor and issue a payment certificate. 84.1 If “As Built” Drawings and/or operating and maintenance manuals are required, the Contractor shall supply them by the dates stated in the PCC. 84.2 If the Contractor does not supply the Drawings and/or Manuals by the dates specified in GCC Sub Clause 84.1, or they do not receive the Project Manager’s approval, the Project Manager shall withhold a nominal amount specified in the PCC from payments due to the Contractor. 85.1 Force Majeure may include, but is not limited to, exceptional events or circumstances of the kind stated below; (a) (b) (c) (d) Gas RMS Bib -III war, hostilities (whether war be declared or not), invasion, act of foreign enemies ; rebellion, terrorism, sabotage by persons other than the Contractor’s personnel, revolution, insurrection, military or usurped power, or civil war ; riot, commotion, disorder, strike or lockout by persons other than the Contractor’s personnel ; munitions of war, explosive materials, ionising radiation or contamination by radio-activity, except as may be attributable to the Contractor’s use of 70 (e) 86. Notice of Force Majeure 87. Consequenc es of Force Majeure 86.1 If a party is or will be prevented from performing its substantial obligations under the Contract by Force Majeure, then it shall give notice, within fourteen (14) days after the party became aware, to the other party of the event or circumstances constituting the Force Majeure and shall specify the obligations, the performance of which is or will be prevented. 86.2 Notwithstanding any other provision of this Clause, Force Majeure shall not apply to obligations of either party to make payments to the other party under the Contract. 87.1 If the Contractor is prevented from performing its substantial obligations under the Contract by Force Majeure of which notice has been given under GCC Sub Clause 86, and suffers delay and/or incurs cost by reason of such Force Majeure, the Contractor shall be entitled subject to GCC Sub Clause 93 to: (a) an extension of time for any such delay, if completion is or will be delayed, under GCC Clause 45, and (b) 87.2 88. Release from Performance Gas RMS Bib -III such munitions, explosives, radiation or radioactivity ; and natural catastrophes such as fires, floods, epidemics, quarantine restrictions, freight embargoes, cyclone, hurricane, typhoon, tsunami, storm surge, earthquake, hill slides, landslides, and volcanic activities. if the event or circumstance is of the kind described sub-paragraphs (a) to (e) of GCC Sub Clause 85.1 occurs in the Country, payment of any such cost, including the costs of rectifying or replacing the Works and Physical services damaged or destructed by Force Majeure, to the extent they are not indemnified through the insurance policy referred to in GCC Clause 37. After receiving notice under GCC Sub Clause 86.1, the Project Manager shall proceed to determine these matters under the provisions of the Contract. 88.1 Notwithstanding any other provision of this Clause, if any event or circumstance outside the control of the parties (including, but not limited to, Force Majeure) arises which makes it impossible or unlawful for either or both parties to fulfil its or their contractual obligations or which, under the law governing the Contract, entitles the parties to be released from further performance of the Contract, then upon notice by either party to the other party of such event 71 or circumstance: F. (a) the parties shall be discharged from further performance, without prejudice to the rights of either party in respect of any previous breach of the Contract, and (b) the sum payable by the Procuring Entity to the Contractor shall be the same as would have been payable under GCC Sub Clause 90.3 if the Contract had been terminated under GCC Sub Clause 89.3. Termination and Settlement of Disputes 89. Termination 89.1 Termination for Default (a) The Procuring Entity or the Contractor, without prejudice to any other remedy for breach of Contract, by giving twenty eight (28) days written notice of default to the other party, may terminate the Contract in whole or in part if the other party causes a fundamental breach of Contract. (b) Fundamental breaches of the Contract shall include, but shall not be limited to, the following: (i) (ii) (iii) (iv) (v) (vi) Gas RMS Bib -III the Contractor stops work for twenty-eight (28) days when no stoppage of work is shown on the current Programme and the stoppage has not been authorized by the Project Manager; the Project Manager instructs the Contractor to delay the progress of the Works, and the instruction is not withdrawn within eighty four ( 84) days; the Project Manager gives Notice that failure to correct a particular Defect is a fundamental breach of Contract and the Contractor fails to correct it within a reasonable period of time determined by the Project Manager; the Contractor does not maintain a Security, which is required; the Contractor has delayed the completion of the Works by the number of days for which the maximum amount of Liquidated Damages can be paid, as specified in GCC Sub Clause 73; the Contractor has subcontracted the whole of the Works or has assigned the Contract without the required agreement and without the approval of the Project Manager; 72 (vii) (viii) 89.2 the Contractor, in the judgment of the Procuring Entity has engaged in corrupt or fraudulent practices, as defined in GCC Sub Clause 39, in competing for or in executing the Contract. A payment certified by the Project Manager is not paid by the Procuring Entity to the Contractor within eighty-four (84) days of the date of the Project Manager’s certificate. Termination for Insolvency The Procuring Entity and the Contractor may at any time terminate the Contract by giving twenty eight (28) days written notice to the other party if either of the party becomes bankrupt or otherwise insolvent. In such event, termination will be without compensation to any party, provided that such termination will not prejudice or affect any right of action or remedy that has accrued or will accrue thereafter to the other party. 89.3 Termination for Convenience (a) (b) 89.4 Gas RMS Bib -III The Procuring Entity, by giving twenty eight (28) days written notice sent to the Contractor, may terminate the Contract, in whole or in part, at any time for its convenience. The notice of termination shall specify that termination is for the Procuring Entity’s convenience, the extent to which performance of the Contractor under the Contract is terminated, and the date upon which such termination becomes effective. The Procuring Entity shall not terminate the contract under GCC Sub Clause 89.3 (a) in order to execute the Works itself or to arrange for the Works to be executed by another contractor or to avoid a termination of the Contract by the Contractor as stated under GCC Sub Clause 89.1(a). In the event the Procuring Entity terminates the Contract in whole or in part, the Procuring Entity shall accept the portion of the Works that are complete and ready for handing over after the Contractor’s receipt of notice of termination of the Contract. For the remaining portion of the Works, the Procuring Entity may elect: (a) to have any portion completed by the Contractor at the Contract terms and prices; and /or (b) to cancel the remainder and pay to the Contractor an agreed amount for partially completed Works and for materials and parts previously procured by 73 the Contractor, or (c) 90. Payment upon Termination 89.5 If the Contract is terminated, the Contractor shall stop work immediately, make the Site safe and secure, and leave the Site as soon as is reasonably possible 90.1 If the Contract is terminated because of a fundamental breach of Contract under GCC Sub Clause 89.1 by the Contractor, the Project Manager shall issue a certificate for the value of the Works done and Plant and Materials ordered less advance payments received up to the date of the issue of the certificate and less the amount from percentage to apply to the contract value of the works not completed, as indicated in the PCC. If the total amount due to the Procuring Entity exceeds any payment due to the Contractor, the difference shall be a debt payable to the Procuring Entity. 90.2 If the Contract is terminated for the Procuring Entity’s convenience or because of a fundamental breach of Contract by the Procuring Entity, the Project Manager shall issue a payment certificate for the value of the work done, Materials ordered, the reasonable cost of removal of Equipment, repatriation of the Contractor’s foreign personnel employed solely on the Works and recruited specifically for the Works, and the Contractor’s costs of protecting and securing the Works, and less advance payments received up to the date of the certificate. 90.3 If the Contract is terminated for reasons of Force Majeure, the Project Manager shall determine the value of the work done and issue a Payment Certificate which shall include: (a) (b) Gas RMS Bib -III except in the case of termination for convenience as stated under GCC Sub Clause 89.3., engage another Contractor to complete the Works, and in that case the Contractor shall be liable to the Procuring Entity for any cost that may be incurred in excess of the sum that would have been paid to the Contractor, if the work would have been executed and completed by him or her. the amounts payable for any work carried out for which unit rates or prices are stated in the Contract; the cost of Plant and Materials ordered for the Works which have been delivered to the Contractor, or of which the Contractor is liable to accept delivery: this Plant and Materials shall become the property of (and be at the risk of) the 74 (c) (d) (e) Procuring Entity when paid for by the Procuring Entity, and the Contractor shall place the same at the Procuring Entity’s disposal; other costs or liabilities which in the circumstances were reasonably and necessarily incurred by the Contractor in the expectation of completing the Works; the cost of removal of Temporary Works and Contractor’s Equipment from the Site; and the cost of repatriation of the Contractor’s staff and labour employed wholly in connection with the Works at the date of termination. 91. Property 91.1 All Materials on the Site, Plant, Equipment, Temporary Works, and Works shall be deemed to be the property of the Procuring Entity if the Contract is terminated because of the Contractor’s default stated under GCC Sub Clause 89.1. 92. Frustration 92.1 If the Contract is frustrated by the occurrence of a situation of Force Majeure as defined in GCC Sub Clause 85, the Project Manager shall certify that the Contract has been frustrated. The Contractor shall make the Site safe and stop work as quickly as possible after receiving this certificate and shall be paid for all works carried out before receiving it and for any work carried out afterwards to which a commitment was made. G. Claims, Disputes and Arbitration 93. Contractor’s Claims Gas RMS Bib -III 93.1 If the Contractor considers himself to be entitled to any extension of the Completion Time and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Procuring Entity, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than twenty eight (28) days after the Contractor became aware, or should have become aware, of the event or circumstance. 93.2 If the Contractor fails to give notice of a claim within such period of twenty eight (28) days, the Intended Completion Date shall not be extended, the Contractor shall not be entitled to additional payment, and the Procuring Entity shall be discharged from all liability in connection with the claim. 75 94. Settlement of Disputes 93.3 Within forty two (42) days after the Contractor became aware or should have become aware of the event or circumstance giving rise to the claim, or within such other period as may be proposed by the Contractor and approved by the Project Manager, the Contractor shall send to the Project Manager a fully detailed claim which includes full supporting particulars of the basis of the claim and of the extension of time and/or additional payment claimed, for settlement. 94.1 Amicable settlement The procuring Entity and the Contractor shall use their best efforts to settle amicably all possible disputes arising out of or in connection with this Contract or its interpretation. 94.2 Gas RMS Bib -III Adjudication (a) If the Contractor believes that a decision taken by the Project Manager was either outside the authority given to the Project Manager by the Contract or that the decision was wrongly taken, the decision shall be referred to the Adjudicator within fourteen (14) days of notification of the Project Manager’s decision in writing. (b) The Adjudicator named in the PCC is jointly appointed by the parties. In case of disagreement between the parties, the Appointing Authority designated in the PCC shall appoint the Adjudicator within fourteen (14) days of receipt of a request from either party. (c) The Adjudicator shall give its decision in writing to both parties within twenty-eight (28) days of a dispute being referred to it. (d) The Contractor shall make all payments (fees and reimbursable expenses) to the Adjudicator, and the Procuring Entity shall reimburse half of these fees through the regular progress payments. (e) Should the Adjudicator resign or die, or should the Procuring Entity and the Contractor agree that the Adjudicator is not functioning in accordance with the provisions of the Contract; a new Adjudicator will be jointly appointed by the Procuring Entity and the Contractor. In case of disagreement between the Procuring Entity and the Contractor the Adjudicator shall be designated by the Appointing Authority within fourteen (14) days of receipt of a request from either party as stated under GCC Sub Clause 94.2 (b) 76 94.3 Gas RMS Bib -III Arbitration (a) If the parties are unable to reach a settlement as per GCC Clauses 94.1 and 94.2 within twenty-eight (28) days of the first written correspondence on the matter of disagreement, then either party may give notice to the other party of its intention to commence arbitration in accordance with GCC Sub Clause 94.3(b). (b) The arbitration shall be conducted in accordance with the Arbitration Act (Act No 1 of 2001) of Bangladesh as at present in force and in the place shown in the PCC. 77 Section 4. Particular Conditions of Contract In the case of any discrepancy between the Sections 3 and 4, the Section 4 shall prevail. GCC Clause Amendments of, and Supplements to, Clauses in the General Conditions of Contract GCC 1.1(j) The Contractor is [Name, address, and name of authorized representative] GCC 1.1(ff) The Procuring Entity is Bangladesh Power Development Board (BPDB) “BOARD” means Bangladesh Power Development Board (BPDB) “Engineer” means Jalalabad Gas Transmission and Distribution System Ltd. Name & Address of authorized representative: Secretary Bangladesh Power Development Board WAPDA Building (1st floor) Motijheel Commercial area, Dhaka-1000. The Consignee: Project Director, Bibiyana III 400 MW CCPP Construction Project, BPDB, Dhaka, Bangladesh. Whatsoever mentioned in section 6 and section 7 of this Tender Document, Purchaser/ Employer means Bangladesh Power Development Board (BPDB). All communication (by the Contractor) with the “Engineer” must be done through “Consignee”. GCC 1.1(gg) The Project Manager is Project Director Bibiyana -III 400 MW CCPP Construction Project, BPDB, Dhaka, Bangladesh. GCC 1.1 (bb) The original Contract price is [insert the amount in the NOA] GCC 1.1(y) The Intended Completion Date for the whole of the Works shall be: GCC 1.1(kk) The Site is located at Bibiyana III 400 MW CCPP Project, Nabiganj Upazila, Habiganj District, Bangladesh and is defined in drawings No.: .................... GCC 1.1(nn) The Start Date shall be: Immediately after opening of L/C The Completion time (including supply of materials and turnkey work) will be 300 days (From the date of opening of L/C to the date of completion of ICO). Gas RMS Bib -III 78 GCC 1.1(rr) The Works consist of GCC 2.5 The Sectional Completion Dates are: As mentioned in the offer GCC 3.1 The Procuring Entity’s address for the purpose of communications under this contract is : As mentioned in Section 6, 7, 8 and 9. Project Director, Bibiyana III 400 MW CCPP Construction Project, BPDB, Dhaka, Bangladesh. The Contractor’s address for the purpose of communications under this contract is : Contact person: Address: Tel: Fax: e-mail address: GCC 6.1 (j) Other documents forming part of the Contract are: GCC 9.1 A Contractor or a Subcontractor that is a national of, or registered in, the following countries are not eligible: All correspondences between Procuring Entity and Contractor prior to signing of the Contract agreement. Israel GCC 9.2 Materials, Equipments Plants and supplies shall not have their origin in the following countries: Israel GCC 13.1 Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s): As per site work schedule. Taxes and Duties a) Bangladesh Income tax and VAT for Income Earned in Bangladesh The Contractor shall be entirely liable to pay Income Tax at the prevailing rule of the Government of Bangladesh for payments of Foreign currency (i.e. CIF price and service cost in Foreign currency) & Local currency portion under the Contract. Income Tax shall be deducted at source during payment of bills/invoice for onward deposition of the same into Government Treasury. GCC 18 The contractor shall not be responsible for payment of applicable Value Added Tax (VAT) on the imported permanent materials and equipments of the contract price. BPDB will pay the same VAT during clearing stage at the port. But, the applicable VAT on the service portion of the contract price shall be paid by the contractor which will be deducted at source from the contractor’s invoice/bill during payment. b) For Contractor’s equipment, materials imported on re-exportable basis The Contractor shall be entirely responsible for all Bangladesh Custom and Import duties, VAT, taxes and all other levies imposed under applicable law of Gas RMS Bib -III 79 Bangladesh for Importation of Contractor’s Construction equipment, tools and materials required for implementation of the contract in Bangladesh which shall be imported on the condition to be exported after completion of the work, if the same are not exempted from such taxes, VAT & levies. The Board shall assist to the contractor to obtain exemption from NBR [National Board of Revenue] for import of the contractor’s equipment and materials on the basis of re-export. c) Foreign country Taxes and Permits The Contractor shall pay all sales, income and other taxes and duties, tariffs and imports that can be lawfully assessed against the contractor by the Government or any lawful authority of any country other than the people’s Republic of Bangladesh which has jurisdiction over the contractor in connection with this contract and shall pay for all licenses permits and inspection required for the work including the cost or securing all export licenses and permits for materials, equipment, supplies and personnel exported from that country to Bangladesh. d) IMPORT DUTY, VAT, TAXES, LEVIES AND OTHER TAXES FOR PERMANENT MATERIALS OF THE WORK The Contractor shall obtain all import permits or licenses required for any part of the work within the terms stated in the program or if not so stated, in reasonable time having regard to the time for delivery of the work and the time for completion. The Board shall pay all Bangladesh customs and import duties, VAT, taxes and all other levies arising from the importation of all permanent materials and equipments (on CIF Value). The Board shall provide its extreme effort to pay such taxes in a timely manner to avoid any extra cost thereon. The contractor shall submit to the owner 5 (five) copies of nonnegotiable shipping document ahead of shipment for arranging payment of such taxes and clearing the materials in time. The Board shall not bear any expenditure on account of import of cement, if any, by the Contractor. Normally, equipment and materials that will be incorporated in the permanent works shall be transported by vessel. If the Contractor decides to air freight any items, the excess freight beyond freight of vessel or excess inland transportation or any other additional cost on account of air freight shall be borne by the Contractor. e) CONTRACTOR’S RESPONSIBILITY TO GET ACQUAINTED WITH BANGLADESH LAWS, IMPORT POLICY, ETC. The Contractor shall get himself acquainted with the relevant Bangladesh Laws as well as the Import Policy of the Government of People’s Republic of Bangladesh remaining in force regarding import of banned items, if any, during the execution of the Contract. In case of import of any banned items and/or contraband item, the consequential effect shall rest with the Contractor. Similarly the Contractor shall be responsible for any non-conformance of Bangladesh Laws either by his own employees or any of the employees of his Subcontractors during execution of the Contract. GCC 19.1 Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor: As mentioned in the offer or Personnel having experience in similar work Gas RMS Bib -III 80 GCC 21.1 Nominated Subcontractor(s) named below: As mentioned in the Offer or other Subcontractor(s) with the consent of Project Director (Consignee) GCC 23.1 The Contractual matters between the Procuring Entity and the Contractor shall be decided by Project Manager 1.INSURANCE The Contractor shall arrange the following insurance except “Workmen’s compensation Insurance for the Contractor’s expatriate personnel” from M/S Bangladesh Sadharan Bima Corporation in the joint name of the BOARD and Contractor and Policies to be taken in foreign currency and local currency wherever necessary and the payment of premium shall be made by the Contractor. GCC 37.1 2.MARINE INSURANCE Insurance of equipment/Spare parts/materials/ Vehicles and other goods covering all risks including war, strike, riots, civil commotion from the port of shipment to the port of discharge transit after discharge to the Site, and warehouses to warehouse anywhere in Bangladesh. The Contractor shall promptly furnish one set of shipping documents, a copy of Bill of lading, invoice, packing list etc, of each consignment direct to the Deputy Director, Insurance. Finance Directorate, BPDB, Dhaka well in time of the shipment of goods indicating the contract number and name of the insurer. If they fail to comply with this instruction they will be held responsible to compensate the losses if any arising out of the non –compliance of this conditions. 3. ERECTION INSURANCE “Builder’s risk Insurance” and “Erection Insurance’ and or “Structural Insurance” including third party liabilities wherever considered necessary by the Contractor and approved by the Board. 4.TRANSPORT LIABILITY INSURANCE Comprehensive water crafts if necessary automobile insurance on motor vehicles to be used by the Contractor during the working period in Bangladesh. 5.WORKMEN’S COMPENSATION INSURANCE The Contractor shall procure and maintain Workman’s Compensation Insurance for all expatriate personnel employed by the Contractor for services in Bangladesh and shall provide for such employees other insurance benefits such as it customarily provides for overseas assignments Of its other employees. 6. REPLACEMENT AND REPAIR UNDER INSURANCE The Contractor shall follow customary insurance claim procedures in seeking to effect recovery under the applicable insurance coverage, of the costs of repair or replacement of any materials lost or damaged in shipment or handling, replacement shipments for materials being replaced or materials that has been returned to the country of origin for repair shall be shipped at no charge to the Board. However, any costs for custom duties, taxes, import licenses under an insurances claim will be borne by the Contractor. The contractor shall in no way withheld the project works/ supplies / services for finalization of the insurance claimed, if any. Gas RMS Bib -III 81 GCC 40.1 Commencement Date of Works shall be as follows: Date of Opening of L/C. GCC 42.1 The Contractor shall submit a Programme for the Works within fifteen (15) days of signing the Contract. GCC 42.2 The period between Programme updates is monthly GCC 42.3 The amount to be withheld for late submission of an updated Programme is : As decided by Project Director (Consignee) GCC 52 Post landing inspection Post Landing Inspection shall be done after arrival of the materials/ equipment at Bibiyana -III 400 MW CCPP Project site, Nabiganj Upazila, Habiganj District, Bangladesh. The Post landing Inspection of the materials/ equipment shall be conducted by BPDB’s Inspectors or its authorized representative and Engineer in the presence of the representative of the Contractor. The program of such Inspection shall be intimated to the representative of the Contractor by BPDB upon arrival of the materials/ equipment at above site. “Receiving cum Inspection Report” will be prepared after Post Landing Inspection. GCC 54 Witnessing of manufacturing process, tests of the equipment/ materials/ spares and foreign training at manufacturer(s)/ Supplier(s)/ T enderer Country(s). It is agreed by the Contractor that BPDB shall send its authorized representatives to carry out witnessing of manufacturing process, tests of the equipment/ materials/ spares and foreign training at manufacturer(s)/ Supplier(s)/ Tenderer Country(s) works and engage a few personnel to inspect the work to be performed at Site under this Contract for compliance with the Contract requirements. The Contractor shall furnish all reasonable aid and assistance required by BPDB or inspectors, for the proper inspection and examination of the work and all parts thereof. The Contractor shall also bear the cost of round air tickets, food, hotel accommodations, internal transportations, taxes, medical insurance and out of pocket expenses @ US $ 120.00 per person per day for 10 days (excluding travel time) for the witnessing of manufacturing process, tests of the equipment/ materials/ spares and foreign training at manufacturer(s)/ Supplier(s)/ Tenderer Country(s) works. The number of such personnel will be Four (04) Nos [02 from BPDB, 02 from Jalalabad Gas]. The Contractor shall obey the directions of BPDB or it's designated persons when they are consistent with the obligations of this Contract, should the Contractor object to any order given by any BPDB's designated person, the Contractor may make written appeal to BPDB for its decision. The representatives of BPDB shall be free at all times to perform their duties and any intimidation or attempted intimidation of any one of them by the Contractor or by any of his employees shall be sufficient reasons if BPDB so decides, to terminate the Contract. Gas RMS Bib -III 82 Such witnessing/inspection shall not relieve the Contractor from any obligation to perform the work in accordance with the Contract Documents. Work not so constructed shall be removed and made good by the Contractor at his own expenses. The programme of witnessing of manufacturing process, factory test and technical know-how transfer shall cover the following: i) Introduction to the Equipment and Materials. ii) Familiarization with Production Line/Cycle and equipment used in such Cycle. iii) Standard of Production. iv) Production Procedure of the equipment. v) Quality Control System of produced equipment and goods. vi) Familiarization Standard of Testing Equipment. vii) Testing Procedure of the equipment manufactured. viii) Witnessing of Test as per standard and requirements of Contract Document. ix) Trainees will have to ensure and certify that the test results observed qualify the standard specified in the contract. x) Operation & Maintenance of the equipment after using it in the system of BPDB. xi) Any other related matters with Test of Equipment. GCC 57.1 The Defects liability / warranty shall cover the following : The Contractor warrants that each item of materials and work furnished under this Contract will be as specified and will be free from defects in design to the extent the Contractor is responsible for design, workmanship and material. The warranties contained in this Contract document are in lieu of any other warranties and are the only warranties made by Contractor with respect to the materials, equipment and work. If within the warranty period set forth below any part of the material or work fails to meet the warranty BPDB will notify the Contractor and the Contractor shall promptly correct any defect including nonconformance with specifications by adjustment, repair or replacement of any and all defective parts or materials. Unless otherwise specified the warranty period hereunder shall begin from the date of issuance of Provisional Acceptance Certificate (PAC) by BPDB and shall end after 24 (twenty four) months until final acceptance. The Contractor shall pay all costs for correction of defects including shop and field labour and supervision, transportation, parts, supplies, all tackles and special tools. The Contractor will be given an opportunity to check the existence of the defect and he shall promptly do the correction within reasonable time. This section states the limit of the Contractor’s liability for defects for which he is responsible. Gas RMS Bib -III 83 When it is necessary to dismantle piping, ducts, machinery, equipment or other work furnished or performed by the Contractor in order to obtain access to the work, the cost of all such dismantling and re-assembling will be paid by the Contractor. The Contractor shall extend the provisions of this warranty to cover all turnkey works furnished under the warranty provisions for a period of 24 (twenty four) months of operation from the date of repair, replacement, commissioning thereof. If within twenty (20) days after BPDB gives the Contractor notice of a defect, the Contractor neglects to make or undertake with due diligence to make the necessary corrections, BPDB is hereby authorized to make the corrections himself or order the work to be done by a third party and cost of the corrections shall be paid by the Contractor. BPDB will be permitted to make repairs or replacements on equipment without affecting the warranty or without prior notice to the Contractor so long as the repairs or replacements involve the correct installation of spares. BPDB shall also be permitted to adjust or test equipment as outlined in instruction manuals provided by the manufacturer. In the case of an emergency where in the judgment of BPDB the delay resulting from giving formal notice would cause serious loss or damage which could be prevented by immediate action, defects may be corrected by BPDB or a third party chosen by BPDB without giving prior notice to the Contractor and cost of corrections shall be paid by the Contractor. In the event, such action is taken by BPDB, the Contractor will be notified promptly and the Contractor shall assist wherever possible in making the necessary corrections. The Contractor shall extend the provisions of the Defects Liability Period to cover all repaired and replacement parts furnished under the Defects Liability Period. GCC 66.1 Payments Payments under this Contract shall be effected in the currency of the Tender for Foreign Currency and in Taka for local currency. Foreign currency payments shall be made through Letter of credit (L/C) and local currency through transfer of fund to Contractor’s account or through cheque. Local currency shall be made through accounts office of the Procurement Entity or through CP & AA cell of BPDB. The charges within Bangladesh for establishment of the L/C shall be borne by BPDB but the L/C charges outside Bangladesh shall be borne by the Contractor. The Contractor shall have to bear all such charges both inside and outside Bangladesh in case of extension of L/C if done at the request of the contractor. An irrevocable L/C shall be opened by BPDB within 30 days upon signing of the Contract. BPDB shall pay to the Contractor in the following manner: a) Payments against CIF value of the material, spares and consumables (Foreign currency part of Schedule 1.1) 1) 70% (Seventy percent) payment within 30 days upon Contractor’s presentation of shipping documents to the negotiating bank and issuance of payment advice by the concerned office of the BOARD upon receipt of negotiable shipping documents for each consignment. Gas RMS Bib -III 84 2) 20% (Twenty percent) upon presentation of “Receiving cum Inspection Report” for each consignment delivered at site and a claim bill duly verified by Project office certified by the Engineer and approved by Project Director. 3) 5% (Five percent) upon issuance of Provisional Acceptance Certificate and a claim bill duly verified by Project office, certified by the Engineer and approved by Project Director. 4) 5% (Five percent) upon issuance of Final Acceptance Certificate and a claim bill duly certified by the Engineer and approved by Project Director/ Head of Power Plant. b) Payment for Local currency part of Schedule 1.1 100% upon submission of Receive cum Inspection report and a claim bill duly verified by Project office, certified by the Engineer and approved by Project Director. Note: The Port handling charges and Inland Transportation shall be paid at actual but not exceeding the quoted amount. c) Payment for Serv ice (Foreign currency part and local currency part; Schedule 1.2, Schedule 1.3 & Schedule 1.4) 1) 90% (Ninety percent) payment upon monthly progress according to the progress of the work at site and provided that the work is performed satisfactorily and in accordance with the stipulations of the Contract documents against submission of invoices/claim bill duly verified by Project office, certified by the Engineer and approved by Project Director. . 2) 5% (Five percent) upon issuance of the Provisional Acceptance Certificate after successful completion of commissioning and handing over against submission of invoices/claim bill duly verified by verified by Project office, certified by the Engineer and approved by Project Director. . 3) 5% (Five percent) upon issuance of Final Acceptance Certificate and a claim bill duly certified by the Engineer and approved by Project Director/ Head of Power Plant. Procedure for Progress payment against Service On or about the first day of each month the Contractor will prepare a bill in prescribed form of the value (As per Breakdown estimate) of the service done up-to such date. The estimated cost of service which, do not conform to the specifications will be deducted from the billed amount. Payment will be made to the Contractor as stipulated above. Such intermediate payment shall be regarded as payment by way of advance against the final payment for work actually done and shall not preclude the requiring of bad, unsound and imperfect work to be removed and reconstructed. Such payments shall not be considered as admission that the Contract performance has been completed nor shall it indicate the accruing or any claim, or shall it Gas RMS Bib -III 85 conclude, determine or affect in any way the powers of BPDB under this Contract to final settlement and adjustment of the account or in any other way vary or affect the Contract. Contractor’s Breakdown Estimate The Contractor shall prepare and submit to the Consignee for approval a breakdown estimate for and covering each lump-sum price stated in the Contract. The breakdown estimate, showing the value of each kind of service shall be certified by Consignee and approved by the Engineer before any partial payment estimate is prepared. Such items as bond premium, temporary facilities and plant may be listed separately in the breakdown estimate, provided that their cost can be substantiated. The sum of the items listed in any breakdown estimate shall equal the Contract lump-sum price or prices, overhead and profit shall not be listed as separate items. GCC 66.3 The particulars of the Bank Account nominated are as follows : Title of the Account : [insert title to whom the Contract awarded] Name of the Bank [insert name with code, if any] : Name of the Branch : [insert branch name with code ,if any] Account Number : [insert number] Address : [insert location with district] Tel Fax : : e-mail address : [information furnished by the Contractor shall be substantiated by the concerned Bank and authenticated by the Procuring Entity] GCC 67 Contractor shall not be paid interest on the late/ delayed payment GCC 69.1(m) The following additional events shall also be the Compensation Events: None GCC 71.1 The Contract is not subject to price adjustment. GCC 72 The proportion of payments to be retained is : As mentioned in PCC (GCC 66.1) GCC 73.1 Delay in target milestone 0.1 % (Zero point one percent) of the final Contract price per day of delay of work completion. GCC 73.1 Limit for maximum amount of liquidated damages: 10% of contract price for delay in target milestone. GCC 74.1 The Bonus for the whole of the Works is None The maximum amount of Bonus for the whole of the Works is None Gas RMS Bib -III 86 GCC 75.1 The Advance Payment shall be: Not Applicable GCC 77.2 The percentage for adjustment of Provisional Sums is None GCC 80.1 After completion of the work, Provisional Acceptance Certificate (Completion Certificate) shall be issued as stated below: Provisional Acceptance Certificate (PAC) The work shall not be considered as complete provisionally until a PAC has been issued for the work, signed and dated by the Consignee and the Engineer and delivered to the Contractor. The PAC will be issued only after the final inspection and performance test has been carried out by a team of representatives of the Contractor and witness and accepted by the PAC committee of BPDB formed by the competent authority the members of the Acceptance Committee of BPDB and the work has been judged complete and in compliance with the Contract Documents. The test shall be performed as specified in the applicable Technical Requirements. Necessary testing equipment will be supplied by the Contractor. The final inspection and the performance test of equipments and the subsequent issuance of the PAC shall not be construed as a release to the Contractor from any Contractual liability or responsibility, such release being subject only to the provisions of the Release of Liability clause PCC [New clause GCC 98]. BPDB may take over completed portions of the work, prior to completion of the Contract, by written notice to the Contractor. The Provisional Acceptance Certificate shall not be unreasonably withheld nor shall BPDB delay the issuing of the PAC on account of minor omissions or defects, which do not affect the commercial operation without any serious risk to the plant, provided always that the Contractor undertakes to make good such omission and defects within a reasonable time. From the date of final inspection and test of completed works, at least three (3) weeks time should be taken for observation to the outcome of the work, after which Provisional Acceptance Certificate should be issued for the work, signed and dated by the Consignee and the Engineer and delivered to the Contractor, provided that no omissions or defects are found which may affect the commercial operation of the plant. The final inspection and test will commence upon a written notice from the Contractor stating that the RMS has successfully completed continuous initial commercial operation (ICO) at full capacity for at least 168 hours without any trouble after turnkey work. After completion of the Defects Liability Period /Warranty period, Final Acceptance Certificate shall be issued as mentioned below: Final Acceptance Certificate (FAC) The work shall not be considered as completed until a Final Acceptance Certificate (FAC) is signed and issued by the consignee and the Engineer on the basis of the successful report of FAC committee formed by the competent authority stating that all work has been finally completed to their satisfaction. The Gas RMS Bib -III 87 Final Acceptance Certificate (FAC) will be given by the consignee latest twenty eight (28) days after the expiration of the Defects liability period or if different guarantee periods shall become applicable to different parts of the work, after the expiration of the latest of such periods and as soon as any and all work to be made good is completed to the satisfaction of the Consignee/ Project Manager and the competent Authority. GCC 84.1 The date by which “as-built ” drawings are required is: Within one month from the date of PAC. The date by which operating and maintenance manuals are required is: Within one month from the date of PAC. All documents including Drawing/ Testing Report/ Operational/ Maintenance Manual must be submitted in English language. GCC 84.2 The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is : No money will be withheld but Final Acceptance Certificate shall not be issued until the submission of “as-built” drawings and/or operating and maintenance manuals GCC 90.1 The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is twenty (20) percent. GCC (b) The Adjudicator jointly appointed by the parties is: Will be appointed as and when necessary. 94.2 Name: Address: Tel No: Fax No: e-mail address: GCC 94.2(b) In case of disagreement between the parties, the Appointing Authority for the Adjudicator is the President of the Institution of Engineers, Bangladesh. GCC (b) The arbitration shall be conducted in the place mentioned below; 94.3 New Clause GCC 95 Dhaka, Bangladesh Approval of Engineering Data Five (5) copies of each drawings and necessary data shall first be submitted to Engineer. Two copies of drawings and data shall be returned to the Contractor marked “APPROVED” “APPROVED AS NOTED”, “RETURNED FOR CORRECTION” within 21 days after receipt from the Contractor. If drawings submitted for approval are not returned within 21 days after receipt by the Engineer, the Contractor shall notify Engineer of such fact, and if the drawings still have not been returned within 15 days after such notice the Contractor may Gas RMS Bib -III 88 proceed as if drawings have been returned approved. When the drawings and data are returned marked “APPROVED AS NOTED” or “RETURNED FOR CORRECTION” the corrections or changes shall be made and five (5) revised copies shall be submitted to Engineer. Two copies of the revised drawings and data will be returned to the Contractor by (15) days from the receipt of the same with due approval, if not anything otherwise specified. The approval by the Engineer of drawing and data submitted by the Contractor will cover only general conformity to the plans and specifications and the external connections and dimensions which affect the plant arrangement. This approval of drawings returned marked “APPROVED” or “APPROVED AS NOTED” will not constitute a blanket approval of all dimensions, quantities and details of the materials, equipment, device or item shown and does not relieve the Contractor from any responsibility for errors or deviations from the Contract requirements. All drawings and data after final procession by BPDB shall become a part of the Contract document and the work shown or described thereby shall be performed in conformity therewith unless otherwise required by BPDB. When the work is completed, two copies of all final approved drawings on AO Size Paper and 1 (One) soft copy shall be sent by the Contractor to the Consignee/ Project Manager. New Clause GCC 96 Shipping Documents No goods will be shipped without prior instruction from the Procurement Entity. Each set of shipping documents will comprise the following: 1. Bill of Lading 1 copy 2. Invoice 1 copy 3. Shipping Specification 1 copy 4. Freight paid memo 1 copy 5. Insurance premium paid memo 1 copy 6. Packing list 1 copy 7. Manufacturer’s test certificate 1 copy The invoices and shipping specifications shall bear the Insurance cover note number. The shipping documents described above shall be received by BPDB at the latest one week before arrival of cargoes at the port of destination. Set of shipping documents shall be submitted to as follows: 1. -----2. Consignee/ Project Manager. 3. Director, Clearance & Movement, BPDB, Chittagong. 4. Director, Finance, BPDB, Dhaka. 5. Deputy Director, Clearance & Movement, BPDB, Chittagong/ Dhaka/ Khulna. 6. Deputy Director, Insurance, BPDB, Dhaka. New Clause GCC 97 Packing All equipment and materials shall be suitably coated, wrapped or duly covered in Gas RMS Bib -III 89 boxes for export shipment and to prevent damage during handling and storage at the site. Card-board containers shall be enclosed in a solid wooden container. Equipment and process materials shall be packed and semi-knocked down to the extent possible to facilitate handling and storage and to protect bearings and other machine surfaces from oxidation. Each container or bundle shall be reinforced with steel strapping in such a manner that breaking of one strap will not cause complete failure of the packaging. The packing shall be of best standards to withstand rough handling and to provide suitable protection from tropical weather while in transit and while awaiting erection at the site. Equipment and materials in wooden cases or crates shall be properly cushioned to withstand the abuse of handling, transportation and storage. Packing shall include preservatives suitable to tropical conditions. All machine surfaces and bearing shall be coated with oxidation preventive compound. All parts subject to damage when in contact with water shall be coated with suitable grease and wrapped in heavy asphalt or tar impregnated paper. Crates and packing materials used for shipping will become the property of BPDB but the Contractor will be allowed to use the same for the work as needed but the remaining material shall be turned over to BPDB upon completion of the project. Packing or shipping units shall be designed within the limitations of the unloading facilities of the receiving ports and the ship which will be used. Ships with special heavy capacity unloading rigging may be required for large units of equipment. It shall be the Contractor’s responsibility to investigate these limitations and to provide suitable packing and shipping to permit unloading at Chittagong / Dhaka. Each package or shipping unit shall be clearly marked or stenciled on at least two sides as follows : BANGLADESH POWER DEVELOPMENT BOARD Bibiyana -III 400 MW CCPP Construction Project, Habiganj. New Clause GCC 98 Release of Liability The acceptance by the Contractor of the last payment shall operate as, and shall be, a release to the BOARD and every officer, agent and employee thereof, from all claims and liability hereunder for anything done or furnished for or relating to the work, or for any act or neglect of the BOARD or of any person relating to or the affecting the work. The last payment by the BOARD to the Contractor shall constitute final acceptance of all work performed under this Contract and shall release the Contractor and his surety, from all Contractual liabilities and responsibilities to the BOARD except these liabilities assumed under the Warranty clause PCC [GCC 57.1] of these Special Conditions or arising out of hidden defects. In the event a suit were to be instituted in Bangladesh against the BOARD and the Contractor as defendants neither shall be released from his respective liabilities under this Contract. Gas RMS Bib -III 90 Appendix to the Tender – Not Applicable [In Tables below, the Procuring Entity shall indicate the source and base values with dates of Indexes, unless otherwise instructed to be quoted by the Tenderer, for the different Cost Components and mention its Weightings or Coefficients] Table 1.1: Price Adjustment Data – Not Applicable [ ITT Sub Clause 27.10: To be provided by the Procuring Entity] Index Descriptions Base Value Sources of Index Note: 1. The sources of Indexes and its values with dates shall be Bangladesh Bureau of Statistics (BBS) unless otherwise mentioned by the Procuring Entity or instructed to be quoted by the Tenderer. 2. The Procuring Entity may require the Tenderer to justify its proposed Indexes, if quoted by the Tenderer. 3. The Base Value of the Indexes shall be those prevailing twenty eight (28) days prior to the deadline for submission of the Tenders. Gas RMS Bib -III 91 Table 1.2: Price Adjustment Data – Not Applicable [ GCC Sub Clause 71.1: To be provided by the Procuring Entity] Item Group Bill No. if applicable Index Descriptions Coe fficients or Weightings for non-adjustable Cost Component Coefficients or We ightings for adjustable Cost Components Total a b c d e f g h i j 1 1 1 1 1 1 Note: The Weightings or Coefficients of the Cost Components shall be mentioned by the Procuring Entity based on the proportion of components involved in the work items caused to be impacted by rise and fall in its prices. Gas RMS Bib -III 92 Section 5. Form Tender and Contract Forms Title Tender Forms PW3 – 1 Tender Submission Letter PW3 – 2 Tenderer Information PW3 – 3 JV Partner Information (if applicable ) PW3 – 4 Subcontractor Information (if applicable ) PW3 – 5 Personnel Information PW3 – 5(a) Manufacturer’s Authorisation & Warranty/Guarantee Letter PW3 – 6 Bank Guarantee for Tender Security (when this option is chosen ) PW3-12 Deviation list PW3-13 Specifications Submission and Compliance Sheet Contract Forms PW3 – 7 Notification of Award PW3 – 8 Contract Agreement PW3 – 9 Bank Guarantee for Performance Security (when this option is chosen ) PW3 –10 Bank Guarantee for Advance Payment (if applicable ) PW3 –11 Bank Guarantee for Retention Money Security (when this option is chosen ) Forms PW3 -1 to PW3 -6, PW-12 and PW3-13 comprises part of the Tender Format and should be completed as stated in ITT Clauses 24. Forms PW3 -7 to PW3 -11 comprises part of the Contract as stated in GCC Clause 6. Gas RMS Bib -III 93 Tender Submission Letter (Form PW3-1) [This letter should be completed and signed by the Authorised Signatory preferably on the Letter-Head Pad of the Tenderer] To: Date: [Contact Person] [Name of Procuring Entity] [Address of Procuring Entity] Invitation for Tender No: [indicate IFT No] Tender Package No: [indicate Package No] This Package is divided into the following Number of Lots [indicate number of Lot(s )] We, the undersigned, offer to execute in conformity with the Conditions of Contract and associated Contract documents, the following Works and Physical services, viz: In accordance with ITT Clauses 27 and 28, the following prices and discounts apply to our Tender: The Tender Price is: (ITT Sub Clause 27.1) [in figures] [in words] The unconditional discount for being Tk [in figures] awarded more than one lot in this Taka [in words] package is: (ITT Sub Clause 27.6) The methodology for application of [state the methodology]. the discount is: The advance payment is: (GCC Sub Clause 75.1) [state the amount based percentage of the Tender Price] on and we shall accordingly submit an Advance Payment Guarantee in the format shown in Form PW3–10. In signing this letter, and in submitting our Tender, we also confirm that: (a) Gas RMS Bib -III our Tender shall be valid for the period stated in the Tender Data Sheet (ITT Sub Clause 33.1) and it shall remain binding upon us and may be accepted at any time before the expiration of that period; 94 (b) a Tender Security is attached in the form of a [state pay order, bank draft, bank guarantee] in the amount stated in the Tender Data Sheet (ITT Sub Clause 35.1) and valid for a period of twenty eight (28) days beyond the Tender validity date; (c) if our Tender is accepted, we commit to furnishing a Performance Security within the time stated under ITT Sub Clause 65.2 in the amount stated in the Tender Data Sheet (ITT Sub Clauses 64.1 and 64.1) and in the form specified in the Tender Data Sheet (ITT Sub Clause 65.1) valid for a period of twenty eight (28) days beyond the date of issue of the Completion Certificate of the Works; (d) we have examined and have no reservations to the Tender Document, issued by you on [insert date]; including Addendum to Tender Document No(s) [state numbers ] , issued in accordance with the Instructions to Tenderers (ITT Clause 11). [insert the number and issuing date of each addendum; or delete this sentence if no Addendum has been issued]; (e) we, including as applicable, any JVCA partner or Subcontractor for any part of the contract resulting from this Tender process, have nationalities from eligible countries, in accordance with ITT Sub Clause 5.1; (f) we are submitting this Tender as a sole Tenderer in accordance with ITT Sub Clause 40.3 or we are submitting this Tender as the partners of a JVCA, comprising the following other partners in accordance with ITT Sub Clause 40.3 ; Name of Partner Location & District of Partner 1 2 3 4 (g) we are not a Government owned entity as defined in ITT Sub Clause 5.3 or we are a Government owned entity, and we meet the requirements of ITT Sub Clause 5.3; (h) we, including as applicable any JVCA partner, declare that we are not associated, nor have been associated in the past, directly or indirectly, with a consultant or any other entity that has prepared the design, specifications and other documents in accordance with ITT Sub Clause 5.5; (i) we, including as applicable any JVCA partner or Subcontractor for any part of the contract resulting from this Tender process, have not been declared ineligible by the Government of Bangladesh on charges of engaging in corrupt, fraudulent, collusive or coercive practices in accordance with ITT Sub Clause 5.6; Gas RMS Bib -III 95 (j) furthermore, we are aware of ITT Clause 4 concerning such practices and pledge not to indulge in such practices in competing for or in executing the Contract; (k) we intend to subcontract an activity or part of the Works, in accordance with ITT Sub Clause 19.1, to the following Subcontractor(s); Activity or part of the Works Name of Subcontractor with Location and District (l) we, including as applicable any JVCA partner, confirm that we do not have a record of poor performance, such as abandoning the works, not properly completing contracts, inordinate delays, or financial failure as stated in ITT Clause 5.7, and that we do not have, or have had, any litigation against us, other than that stated in the Tenderer Information (Form PW3-2 ); (m) we are not participating as Tenderers in more than one Tender in this Tendering process. We understand that your written Notification of Award shall constitute the acceptance of our Tender and shall become a binding Contract between us, until a formal Contract is prepared and executed; (n) we, including as applicable any JVCA partner, confirm that we do not have a record of insolvency, receivership, bankrupt or being wound up, our business activities were not been suspended, and it was not been the subject of legal proceedings in accordance with ITT Sub Clause 5.8; we, including as applicable any JVCA partner, confirm that we have fulfilled our obligations to pay taxes and social security contributions applicable under the relevant national laws and regulations of Bangladesh in accordance with ITT Sub Clause 5.9; we understand that you reserve the right to reject all the Tenders or annul the Tender proceedings, without incurring any liability to Tenderers, in accordance with ITT Clause 60. Signature: [insert signature of authorised representative of the Tenderer] (o) (p) Name: [insert full name of signatory with National ID Number] In the capacity of: [insert capacity of signatory] Duly authorised to sign the Tender for and on behalf of the Tenderer [If there is more than one (1) signatory, or in the case of a JVCA, add other boxes and sign accordingly].Attachment 1 : [ITT Sub Clause 40.3] Written confirmation authorising the above signatory(ies) to commit the Tenderer [and, if applicable] Attachment 2 : [ITT Sub Clause 29.2(b)] Copy of the JVCA Agreement / Letter of Intent to form JVCA with draft proposed Agreement Gas RMS Bib -III 96 Tenderer Information (Form PW3-2) [This Form should be completed only by the Tenderer, preferably on its Letter-Head Pad] Invitation for Tender No: [indicate IFT No] Tender Package No: [indicate Package No] This Package is divided into the following Number of Lots: [indicate number of Lot(s)] 1. Eligibility Information of the Tenderer [ITT –Clauses 5 & 29] 1.1 Nationality of individual or country of registration 1.2 Tenderer’s legal title 1.3 Tenderer’s registered address 1.4 Tenderer’s legal status [complete the relevant box] Proprietorship Partnership Limited Liability Concern Government-owned Enterprise Others [please describe, if applicable] 1.5 Tenderer’s year of registration 1.6 Tenderer’s authorised representative details Name National ID number Address Telephone / Fax numbers e-mail address 1.7 Litigation [ITT Cause 13] If there is no history of litigation or no pending litigation then state opposite “None”. If there is a history of litigation, or a number of awards, against the Tenderer provide details below A. Arbitration Awards made against Gas RMS Bib -III 97 Year Matter in dispute Value of Award Value of Claim B. Arbitration Awards pending Year 1.8 Matter in dispute Value of Claim Tenderer to attach photocopies of the original documents mentioned aside [All documents required under ITT Clauses 5 and 29] The following two information are applicable for National Tenderers 1.9 Tenderer’s Value Added Tax Registration (VAT) Number 1.10 Tenderer’s Tax Identification Number(TIN) [The foreign Tenderers, in accordance with ITT Sub Clause 5.1, shall provide evidence by a written declaration to that effect to demonstrate that it meets the criterion] 2. 2.1 Qualification Information of the Tenderer [ITT Clause 32] General Experience in Construction Works of Tenderer Start Month Year 2.2 End Month Year Years Contract No and Name of Contract Name and Address of Procuring Entity Brief description of Works Role of Tenderer [Prime/Sub /Managem ent] Specific Experience in Construction Works of Tenderer Completed Contracts of similar nature, complexity and methods/construction technology Contract No [ insert reference no] of [ insert year] Name of Contract [insert name] Role in Contract [tick relevant box]. Prime Contractor Award date Completion date [insert date] [insert date] Gas RMS Bib -III Subcontractor Management Contractor 98 Total Contract Value [insert amount] Procuring Entity’s Name Address Tel / Fax e-mail Brief description with justifications of the [state justification in support of its similarity compared to the similarity compared to the proposed works] Procuring Entity’s requirements 2.3 Average annual construction turnover [ITT Sub Clause15.1(a)] [amount invoiced to Procuring Entity(s) for each year of works in progress or completed, using rate of exchange at the end of the period reported] Year 2.4 Amount & Currency Taka or Equivalent Taka Financial Resources available to meet the construction cash flow [ITT Sub Clause 15.1(b)] No Source of Financing Amount Available In order to confirm the above statements the Tenderer shall submit , as applicable, the documents mentioned in ITT Sub Clause 32.1(a), (b), (c) & (d) 2.5 Contact Details [ITT Sub Clause 32.1 (g) & (i) Name, address, and other contact details of Tenderer Bankers and other Procuring Entity(s) that may provide references, if contacted by this Procuring Entity 2.6 Qualifications and experience of key technical and administrative personnel proposed for Contract administration and management [ITT Sub Clause 32.1(e)] Gas RMS Bib -III 99 Position Years of Specific Experience Years of General Experience [Tenderer to complete details of as many personnel as are applicable. Each personnel listed above should complete the Personnel Information (Form PW3-5)] 2.7 Major Construction Equipments proposed to carry out the Contract [ITT Sub Clause 32.1(f)] Item of Equipment Condition (new, good, average, poor) Owned, leased or to be purchased (state owner, lessor or seller) [Tenderer to list details of each item of major construction equipment, as applicable] Gas RMS Bib -III 100 JVCA Partner Information (Form PW3-3) [This Form should be completed by each JVCA partner]. Invitation for Tender No: [indicate IFT No] Tender Package No [indicate Package No] This Package is divided into the following Number of Lots [indicate number of Lot(s)] 1. Eligibility Information of the JVCA Partner [ITT –Clauses 5 & 29] 1.1 Nationality of Individual or country of Registration 1.2 JVCA Partner’s legal title 1.3 JVCA Partner’s registered address 1.4 JVCA Partner’s legal status [complete the relevant box] Proprietorship Partnership Limited Liability Concern Government-owned Enterprise Other (please describe, if applicable) 1.5 JVCA Partner’s year of registration 1.6 JVCA Partner’s authorised representative details Name National ID number Address Telephone / Fax numbers e-mail address 1.7 Litigation [ITT Sub Cause 13] If there is no history of litigation or no pending litigation then state “None”. If there is a history of litigation, or a number of awards, against the JVCA Partner provide details below: A. Arbitration Awards made against Year Gas RMS Bib -III Matter in dispute Value of Value of 101 Award Claim B. Arbitration Awards pending Year 1.8 Matter in dispute Value of Claim JVCA Partner to attach copies of the original documents mentioned aside [All documents required under ITT Clauses 5 and 29] The following two information are applicable for national JVCA Partners only 1.9 JVCA Partner’s Value Added Tax Registration (VAT) Number 1.10 JVCA Partner’s Tax Identification Number (TIN) [The foreign JVCA Partners, in accordance with ITT Sub Clause 5.1, shall provide evidence by a written declaration to that effect to demonstrate that it meets the criterion] 2. Key Activity(ies) for which it is intended to be joint ventured [ITT Sub Clause 18.2 & 18.3] Elements of Activity Brief description of Activity 3. Qualification Information of the JVCA Partner [ITT Clause 32] 3.1 General Experience in Construction Works of JVCA Partner Start Month Year 3.2 End Month Year Years Contract No and & Name of Contract Name and Address of Procuring Entity Brief description of Works Role of JVCA Partner [Prime/Sub /Managem ent] Specific Experience in Construction Works of JVCA Partner Completed Contracts of similar nature, complexity and methods/construction technology Contract No [ insert reference no] of [ insert year] Name of Contract [insert name] Gas RMS Bib -III 102 Role in Contract [tick relevant box] Prime Contractor Award date Completion date Total Contract Amount [insert date] [insert date] [insert amount] Subcontractor Management Contractor Procuring Entity’s Name Address Tel / Fax e-mail Brief description with justifications of the similarity compared to [state justification in support of its similarity compared to the the Procuring Entity’s proposed works] requirements 3.3 Average annual construction turnover [ITT Sub Clause 15.1 (a)] [amount invoiced to Procuring Entity(s) for each year of work in progress or completed, using rate of exchange at the end of the period reported] Year 3.4 Amount & Currency Taka or Equivalent Taka Financial Resources available to meet the construction cash flow [ITT Sub-Clause 15.1(b)] No Source of financing Amount available In order to confirm the above statements the JVCA Partner shall submit , as applicable, the documents mentioned in ITT Sub Clause 32.1 (a), (b), (c) & (d) 3.5 Contact Details [ITT Sub Clause 32.1 (g) & (i) Name, address, and contact details of Tenderer’s Bankers and other Procuring Entity(s) that may provide references if contacted by this Procuring Entity Gas RMS Bib -III 103 3.6 Qualifications and experience of key technical and administrative personnel proposed for Contract administration and management [ITT Sub Clause 32.1(e)] Position Name Years of General Experience Years of Specific Experience [Tenderer to complete details of as many personnel as are applicable. Each personnel listed above should complete the Personnel Information (Form PW3-5)] 3.7 Major items of Construction Equipment proposed for carrying out the works [ITT SubClause 32.1(f)] Item of Equipment Condition (new, good, average, poor) Owned, leased or to be purchased (state owner, leaser or seller) [Tenderer to list details of each item of Major equipment, as applicable] Gas RMS Bib -III 104 Subcontractor Information (Form PW3-4) [This Form should be completed by each Subcontractor, preferably on its Letter-Head Pad] Invitation for Tender No: [indicate IFT No] Tender Package No [indicate Package No] This Package is divided into the following Number of Lots [indicate number of Lot(s)] 1. Eligibility Information of the Subcontractor [ITT –Clauses 5 & 29] 1.1 Nationality of Individual or country of Registration 1.2 Subcontractor’s legal title 1.3 Subcontractor’s registered address 1.4 Subcontractor’s legal status [complete the relevant box] Proprietorship Partnership Limited Liability Concern Government-owned Enterprise Other (please describe) 1.5 Subcontractor’s year of registration 1.6 Subcontractor’s authorised representative details Name Address Telephone / Fax numbers e-mail address 1.7 Subcontractor to attach copies of the following original documents All documents to the extent relevant to ITT Clause 5 and 29 in support of its qualifications The following two information are applicable for national Subcontractors 1.8 Subcontractor’s Value Added Tax Registration (VAT) Number 1.9 Subcontractor’s Tax Identification Number(TIN) Gas RMS Bib -III 105 [The foreign Subcontractors , in accordance with ITT sub Clause 5.1, shall provide evidence by a written declaration to that effect to demonstrate that it meets the criterion] 2. Key Activity(ies) for which it is intended to be Subcontracted [ITT Sub Clause 19.1] 2.1 Elements of Activity Brief description of Activity 2.2 List of Similar Contracts in which the proposed Subcontractor had been engaged Name of Contract and Year of Execution Value of Contract Name of Procuring Entity Contact Person and contact details Type of Work performed Gas RMS Bib -III 106 Personnel Information (Form PW3-5) [This Form should be completed for each person proposed by the Tenderer on Form PW3-2 & PW3-3, where applicable] Invitation for Tender No: [indicate IFT No] Tender Package No [indicate Package No] This Package is divided into the following Number of Lots [indicate number of Lot(s )] A. Proposed Position (tick the relevant box) 0 Construction Project Manager 0 Prime Candidate 0 Alternative Candidate 0 Key Personnel 0 Prime Candidate 0 Alternative Candidate B. Personal Data Name Date of Birth Years overall experience National ID Number Years of employment with the Tenderer Professional Qualifications: 1. 2. 3. 4. C. Present Employment [to be completed only if not employed by the Tenderer] Name of Procuring Entity: Address of Procuring Entity: Present Job Title: Years with present Procuring Entity: Tel No: Gas RMS Bib -III Fax No: e-mail address: 107 Contact [manager/personnel officer]: D. Professional Experience Summarise professional experience over the last twenty years, in reverse chronological order. Indicate particular technical and managerial experience relevant to the project. From To Company / Project / Position / Relevant technical and management experience. 1 2 3 4 5 Gas RMS Bib -III 108 Manufacturer’s Authorisation & W arranty/Guarantee Letter [Form PW3-5(a)] [The Tenderer shall require the Manufacturer to fill in this Form in accordance with the instructions indicated. This letter of authorization should be on the letterhead of the Manufacturer and should be signed by a person with the proper authority to sign documents that are binding on the Manufacturer. The Tenderer shall include it in its tender, if so indicated in the TDS as stated under ITT (TDS) SubClause24.1(I)-3] Invitation for Tender No: Date: Tender Package No: Tender Lot No: To: Name and address of Purchaser] WHEREAS We [insert complete name of Manufacturer], who are official manufacturers of [insert type of goods manufactured], having factories at [insert full address of Manufacturer’s factories] , do hereby authorize [insert complete name of Tenderer] to supply the following Goods, manufactured by us [insert name and or brief description of the Goods] . We hereby extend our full guarantee and warranty as stated under GCC (PCC) Clause 57.1 of the General Conditions of Contract, with respect to the Goods manufactured by us. Signed: [insert signature(s) of authorized representative(s) of the Manufacturer] Name: [insert complete name(s) of authorized representative(s) of the Manufacturer] Address: [insert full address including Fax and e-mail] Title: [insert title] Date: [insert date of signing] Gas RMS Bib -III 109 Bank Guarantee for Tender Security (Form PW3-6) [This is the format for the Tender Security to be issued by a scheduled bank of Bangladesh or by a foreign bank duly endorsed/authenticated by a scheduled bank of Bangladesh in accordance with ITT Clause 35 & 36] Invitation for Tender No: Date: Tender Package No: To: [Name and address of the Procuring Entity ] TENDER GUARANTEE No: We have been informed that [name of Tenderer] (hereinafter called “the Tenderer”) intends to submit to you its Tender dated [date of Tender] (hereinafter called “the Tender”) for the execution of the Works of [description of works] under the above Invitation for Tenders (hereinafter called “the IFT”). Furthermore, we understand that, according to your conditions, the Tender must be supported by a Bank Guarantee for Tender Security. At the request of the Tenderer, we [name of bank] hereby irrevocably undertake to pay you, without cavil or argument, any sum or sums not exceeding in total an amount of Tk [insert amount in figures and words] upon receipt by us of your first written demand accompanied by a written statement that the Tenderer is in breach of its obligation(s) under the Tender conditions, because the Tenderer: a. has withdrawn its Tender after opening of Tenders but within the validity of the Tender Security; or b. refused to accept the Notification of Award (NOA) within the period as stated under ITT; or c. failed to furnish Performance Security within the period stipulated in the NOA; or d. refused to sign the Contract Agreement by the time specified in the NOA; or e. did not accept the correction of the Tender price following the correction of the arithmetic errors as stated under ITT. This guarantee will expire (a) (b) if the Tenderer is the successful Tenderer, upon our receipt of a copy of the Contract Agreement signed by the Tenderer or a copy of the Performance Security issued to you in accordance with the ITT; or if the Tenderer is not the successful Tenderer, twenty eight (28) days after the expiration of the Tenderer’s Tender validity period, being [date of expiration of the Tender validity plus twenty eight (28) days ]. Consequently, we must receive at the above-mentioned office any demand for payment under this guarantee on or before that date. Signature Gas RMS Bib -III Signature 110 Notification of Award (Form PW3-7) Contract No: To: Date: [Name of Contractor] This is to notify you that your Tender dated [insert date] for the execution of the Works for [name of projec t/Contract] for the Contract Price of Tk [state amount in figures and in words], as corrected and modified in accordance with the Instructions to Tenderers, has been approved by [name of Procuring Entity]. You are thus requested to take following actions: i. accept in writing the Notification of Award within seven (7) working days of its issuance pursuant to ITT Sub Clause 63.1 ii. furnish a Performance Security in the form as specified and in the amount of Tk [state amount in figures and words] ,within fourteen (14) days of acceptance of this Notification of Award but not later than (specify date), in accordance with ITT Clause 65. iii. sign the Contract within twenty eight (28) days of issuance of this Notification of Award but not later than (specify date), in accordance with ITT Sub Clause 69.2. You may proceed with the execution of the Works only upon completion of the above tasks. You may also please note that this Notification of Award shall constitute the formation of this Contract which shall become binding upon you. We attach the draft Contract and all other documents for your perusal and signature. Signed Duly authorised to sign for and on behalf of [name of Procuring Entity] Date: Gas RMS Bib -III 111 Contract Agreement (Form PW3-8) THIS AGREEMENT made the [day] day of [month] [year] between [name and address of Procuring Entity] (hereinafter called “the Procuring Entity”) of the one part and [name and address of Contractor] (hereinafter called “the Contractor”) of the other part: WHEREAS the Procuring Entity invited Tenders for certain works, viz, [brief description of works] and has accepted a Tender by the Contractor for the execution of those works in the sum of Taka [Contract price in figures and in words] (hereinafter called “the Contract Price”). NOW THIS AGREEMENT WITNESSETH AS FOLLOWS: 1. In this Agreement words and expressions shall have the same meanings as are respectively assigned to them in the General Conditions of Contract hereafter referred to. 2. 3. The documents forming the Contract shall be interpreted in the following order of priority: (a) the signed Contract Agreement (b) the Notification of Award (c) the completed Tender and the appendices to the Tender (d) the Particular Conditions of Contract (e) the General Conditions of Contract (f) the Technical Specifications (g) the General Specifications (h) the Drawings (i) the priced Bill of Quantities and the Schedules (j) any other document listed in the PCC forming part of the Contract. In consideration of the payments to be made by the Procuring Entity to the Contractor as hereinafter mentioned, the Contractor hereby covenants with the Procuring Entity to execute and complete the works and to remedy any defects therein in conformity in all respects with the provisions of the Contract. 4. The Procuring Entity hereby covenants to pay the Contractor in consideration of the execution and completion of the works and the remedying of defects therein, the Contract Price or such other sum as may become payable under the provisions of the Contract at the times and in the manner prescribed by the Contract. IN WITNESS whereof the parties hereto have caused this Agreement to be executed in accordance with the laws of Bangladesh on the day, month and year first written above. For the Procuring Entity For the Contractor Signature Name National ID No. Title In the presence of Name Address Gas RMS Bib -III 112 Bank Guarantee for Performance Security (Form PW3-9) [This is the format for the Performance Security to be issued by a scheduled bank of Bangladesh or by a foreign bank duly endorsed/authenticated by a scheduled bank of Bangladesh in accordance with ITT Clause 64, 65, 66 & 67] Contract No: [insert reference number] Date: [insert date] To: [ insert Name and address of Procuring Entity] PERFORMANCE GUARANTEE No: We have been informed that [name of Contractor] (hereinafter called “the Contractor”) has undertaken, pursuant to Contract No [insert reference number of Contract] dated [insert date of Contract] (hereinafter called “the Contract”), the execution of works [desc ription of works] under the Contract. Furthermore, we understand that, according to your conditions, the Contract must be supported by a Bank Guarantee for Performance Security. At the request of the Contractor, we [name of bank] hereby irrevocably undertake to pay you, without cavil or argument, any sum or sums not exceeding in total an amount of Tk [insert amount in figures and in words] upon receipt by us of your first written demand accompanied by a written statement that the Contractor is in breach of its obligation(s) under the Contract conditions, without you needing to prove or show grounds or reasons for your demand of the sum specified therein. This guarantee is valid until [date of validity of guarantee], consequently, we must receive at the abovementioned office any demand for payment under this guarantee on or before that date. Signature Gas RMS Bib -III Signature 113 Bank Guarantee for Advance Payment (Form PW3-10) - Not Applicable [This is the format for the Advance Payment Guarantee to be issued by a scheduled bank of Bangladesh or by a foreign bank duly endorsed/authenticated by a scheduled bank of Bangladesh in accordance with GCC Clause 75] Contract No: [insert reference number] Date: [insert date] To: [insert Name and address of the Procuring Entity] ADVANCE PAYMENT GUARANTEE No: We have been informed that [name of Contractor] (hereinafter called “the Contractor”) has undertaken, pursuant to Contract No [insert reference number of Contract] dated [insert date of Contract] (hereinafter called “the Contract”), the execution of works [desc ription of works] under the Contract. Furthermore, we understand that, according to your Conditions of Contract under GCC Clause 75, the Advance Payment on Contract must be supported by a Bank Guarantee. At the request of the Contractor, we [insert name of bank ] hereby irrevocably undertake to pay you, without cavil or argument, any sum or sums not exceeding in total an amount of Tk [insert amount in figures and in words] upon receipt by us of your first written demand accompanied by a written statement that the Contractor is in breach of its obligation(s) under the Contract conditions, without you needing to prove or show grounds or reasons for your demand of the sum specified therein. We further agree that no change, addition or other modification of the terms of the Contract to be performed, or of any of the Contract documents which may be made between the Procuring Entity and the Contractor, shall in any way release us from any liability under this guarantee, and we hereby waive notice of any such change, addition or modification. This guarantee is valid until [insert date of validity of guarantee], consequently, we must receive at the above-mentioned office any demand for payment under this guarantee on or before that date. Signature Gas RMS Bib -III Signature 114 Bank Guarantee for Retention Money Security (Form PW3-11) – N/A [This is the format for the Retention Money Guarantee to be issued by a scheduled bank of Bangladesh or by a foreign bank duly endorsed/authenticated by a scheduled bank of Bangladesh in accordance with GCC Sub Clause 72.3] Demand Guarantee [Bank’s Name, and Address of Issuing Branch or Office] Beneficiary: [insert Name and Address of the Procuring Entity] Date: [insert date] RETENTION MONEY GUARANTEE No.: [insert number] We have been informed that [insert name of Contractor] (hereinafter called “the Contractor”) has entered into Contract Number [insert reference number of the Contract] dated [insert date] with you, for the execution of [insert name of Contract and brief description of Works] (hereinafter called “the Contract”). Furthermore, we understand that, according to the conditions of the Contract, when the Taking-Over Certificate has been issued for the Works and the first half of the Retention Money has been certified for payment, payment of Tk. [insert the amount of the second half of the Retention Money] which becomes due after the Defects Liability Period has passed and certified in the form of Defects Correction Certificate, is to be made against a Retention Money Guarantee. At the request of the Contractor, we [insert name of Bank] hereby irrevocably undertake to pay you any sum or sums not exceeding in total an amount of Tk. [insert amount in figures] (Taka [insert amount in words]) upon receipt by us of your first demand in writing accompanied by a written statement stating that the Contractor is in breach of its obligation under the Contract because the Contractor failed to properly correct the defects duly notified in respect of the Works. It is a condition for any claim and payment under this guarantee to be made that the payment of the second half of the Retention Money referred to above must have been received by the Contractor on its account number[insert A/C no] at [name and address of Bank]. This guarantee is valid until [insert the date of validity of Guarantee that being twenty eight (28) days beyond the Defects Liability Period]. Consequently, we must receive at the above-mentioned office any demand for payment under this guarantee on or before that date. Signature Gas RMS Bib -III Signature 115 Deviation List (Form PW3-12) [If Tenderer has any reservations on terms and conditions, Tenderer has to mention his reservations in Deviation list] Sl. No. Reference No./ Clause No. Proposed Deviation Remarks [ Add rows if necessary] Signature: [insert signature of authorised representative of the Tenderer] Name: [insert full name of signatory] In the capacity of: [insert designation of signatory] Duly authorised to sign the Tender for and on behalf of the Tenderer Gas RMS Bib -III 116 Specifications Submission and Compliance Sheet (Form PW3-13) Invitation for Tender No: Date: Tender Package No: Package Description: Tender Lot No: Lot Description: [enter description as specified in Section 6] [enter description as specified in Section 6] List of main Equipments/ materials/ items of proposed Bibiyana III 400 MW CCPP RMS SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) A. Station Inlet Unit 1 Insulating joint, W/N 2 3 4 5 6 7 8 9 Station Inlet Ball Valve Pressure Gauge (01500)psig Purging Va lve Temperature Transmitter(Digital) Pressure Transmitter(Digital) Emergency Shutdown valve (ESD) By -Pass Ball Valve Other required line pipe, elbow, flanges /blind flanges, gasket, screwed Valve, Needle valve for pressure gauge, Thermo well, fittings, stud-bolts, cables and accessories as per design, drawing (P&ID, inlet part) and schedule of requirement. 8”x600 Class 8”x600RF ½” screwed ½” screwed 3/4” Ø / 1”Ø screwed 3/4” Ø / 1”Ø screwed 8”x600 Class F ull Technical Specificatio ns (To be filled by the Tenderer) As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). 2”x600RF B. Knock Out Drum (KOD) Unit 1 85 MMSCFD KOD (at minimum 600 psig and maximum 1100 psig operating pressure) and other fittings, screwed needle valve for pressure gauge, drain valves, gasket, gauges and Gas RMS Bib -III 8"Ø x8"Ø x 600 Class As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). 117 SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) 2 3 4 5 6 accessories as per design, drawing (P&ID, KOD part) and specification. Inlet & Outlet Ball Valve By-Pass Ball Valve F ull Technical Specificatio ns (To be filled by the Tenderer) 8”x600RF 8”x600RF Pressure Gauge (01500)psig ½” screwed Purging Valve ½” screwed Other required line pipe, relief valve, elbow, tee, flanges, screwed Needle valves for pressure gauge, stud-bolts, gasket, fittings and accessories as per design, drawing (P&ID, beyond KOD) and schedule of requirement. C. Filter Separator (FS) Unit 1 2 3 4 5 6 7 85 MMSCFD Filter Separator (Horizontal and Twin lock quick opening type) at minimum 600 psig and maximum 1100 psig operating pressure and other fittings, Purging/Drain valves, gasket, gauges and accessories as per Design, drawing (P&ID, FS part) and specification. Inlet Ball Valve Outlet Ball Valve By -Pass Ball Valve Pressure Gauge(0 1500)psig Purging Valve Other required line pipe, relief valve ,elbow, tee, reducer, flanges, screwed Gas RMS Bib -III 8"Ø x8"Ø 600RF As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). 8”x600RF 8”x600RF 8”x600RF ½” screwed ½” screwed 118 SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) F ull Technical Specificatio ns (To be filled by the Tenderer) needle valve for pressure gauge, stud-bolts, gasket, fittings and accessories as per design, drawing (P&ID, beyond FS) and schedule of requirement. D. Water bath Heater (WBH) Unit 1 2 3 4 5 6 7 8 9 10 85 MMSCFD Water Bath Heater (at minimu m 600 psig and maximum 1100 psig operating pressure) and other fittings, gasket, screwed valves and accessories as per design, drawing (WBH) and specification to maintain delivery temperature between 15 to 22 °C at 150 psig pressure. Inlet & Outlet Ball Valve By -Pass Ball Valve Three way Control Valve with all other controlling unit Control Panel (PLC Control) Pressure Gauge(0 1500)psig Purging Valve Temperature Transmitter(Digital) Temperature Indicator Other required line pipe, elbow, tee, flanges, screwed needle valve for pressure gauge, gasket, Stud -bolts, Thermo well, fittings, cables and accessories as per design, drawing (P&ID, beyond WBH), specification, and schedule of requirement. 8"Ø x8"Ø 600RF As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). 8”x600RF 8”x600RF 8”x600RF ½” screwed ½” screwed 3/4” Ø / 1”Ø screwed 3/4” screwed E . 1 s t stage Regulating Unit Gas RMS Bib -III 119 SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Slam shut off Valve Monitor Regulator Active Regulator Header Relief Runs Relief Inlet Ball Valve Outlet Ball Valve Control (Glob) Valve Valve for Header Relieves Check Valve Noise Silencer Noise Silencer Pressure Gauge(01500)psig Purging Valve Drain Valve/Valve in screwed relief Temperature Indicator Blind Flange for off take Other required line pipe, elbow, tee, reducer, saddle, flanges/blind flanges, screwed Needle valves for pressure gauge and sensing line, studbolts, Thermo well, gasket, fittings, tubescoupling and accessories as per design, drawing (P&ID, Regulating unit), specification, and schedule of requirement. 8”x600RF 6”x600RF 6”x600RF 2”x600RF 1”x600 Screwed 8”x600RF 10”x600RF 6”x600RF 2”x600RF 10”x600RF 10”x600 10”x600 ½” screwed Gas RMS Bib -III (To be filled by the Tenderer) As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). ½” screwed 1” screwed 3/4” screwed 10”x600RF F. 1 st Liquid Separator Unit 85 MMSCFD Liquid 10”x10”x 300RF 1 Separator (Vertical type ) at 500 psig operating pressure and other fittings, gasket, screwed needle valve, purging/drain valves and accessories as per design, drawing (P&ID, VME part) and F ull Technical Specificatio ns As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). 120 SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) 2 3 4 5 6 specification and schedule of requirement. Inlet & Outlet Ball Valve Bypass Ball Valve Pressure Gauge(0 -500)psig Purgin g Valve Other required line pipe, relief valve, elbow, tee, flanges, gasket, stud-bolts, fittings and accessories as per design, drawing (P&ID, beyond VME), specification, and schedule of requirement. G.2nd stage Regulating Unit Slum shut off Valve 1 Monitor Regulator 2 Active Regulator 3 Header Relief 4 Runs Relief 5 Inlet Ball Valve 6 Outlet Ball Valve 7 Control (Globe) Valve 8 Valve for Header Relief 9 10 Check Valve 11 Noise Silencer 12 Noise Silencer 13 Pressure Gauge(0 -600)psig 14 Purging Valve 15 16 17 F ull Technical Specificatio ns (To be filled by the Tenderer) 10”x300RF 10”x300RF ½” screwed ½” screwed 08”x300RF 6”x300RF 6”x300RF 2”x300RF 1”x300 Screwed 10”x300RF 14”x300RF 6”x300RF 2”x300RF 14”x300RF 14”x300 14”x300 ½” screwed ½” screwed 1” screwed As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). Drain Valve/Valve in screwed relief Temperature 3/4” screwed Transmitter(Digital) Other required line pipe, elbow, tee, reducer, saddle, flanges/blind flanges, screwed needle valves for pressure gauge and sensing line, studbolts, fittings, Thermo well gasket, tubesGas RMS Bib -III 121 SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) F ull Technical Specificatio ns (To be filled by the Tenderer) couplings and accessories as per design, drawing (P&ID, regulating unit), specification, and schedule of requirement. H. 2nd Liquid Separator Unit 1 2 3 4 5 6 7 8 85 MMSCFD Liquid Separator (at 150 psig to 320 psig operating pressure) and other fittings, gasket, gauges, screwed needle valve for pressure gauge, Purging/drain valves and accessories as per design, drawing (P&ID, VME part) and specification and schedule of requirement. Inlet Ball Valve Outlet Ball Valve Pressure Gauge(0 -500)psig Purging Valve Bypass Ball Valve Ball Valve for off Take Other required line pipe, relief valve, elbow, tee, flanges, screwed needle valve for pressure gauge, stud-bolts, fittings, gasket, and accessories as per design, drawing (P&ID, beyond VME), specification, and schedule of requirement. 14”x14”x 300RF As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). 14”x300RF 14”x300RF ½” screwed ½” screwed 14”x300RF 4”x300RF I. Oriface Metering Unit 1 85 MMSCFD Senior Type 16”x300RF (Dual Chamber) Orifice Meter at 150 psig to 320 psig operating pressure and other Flanges, fittings, gasket, tubes, straightening vane, screwed needle valve, Gas RMS Bib -III As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). 122 SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) stud-bolts and accessories as per design, drawing (P&ID, Orifice Meter part), specification and schedule of requirement. 2 Inlet & Outlet Ball Valve Pressure Ga uge(0-500)psig 3 Purging Valve 4 Purging Valve 5 Temperature 6 Transmitter(Digital) Pressure 7 Transmitter(Digital) Diff.Pressure 8 Transmitter(Digital) Regulator (Fisher-627) 9 Chart Recorder With three pens for Static pressure (0-500psig), differential pressure (0 10 100”WC) and temperature (0-150°F) record with thermo well and all accessories. Plani meter with Turn 11 table (Chart Drive) to read Chart Paper Other required line pipe ,stud-bolts, screwed needle valve for pressure gauge, gasket, Thermo fittings, cables and 12 well, accessories as per design, drawing (P&ID, Orifice meter part), specification, and schedule of requirement. J. Flow Computer Unit Flow Computer 1 (Microprocessor Based) Control Panel 2 Laptop Computer 3 Supervisory Computer 4 Gas RMS Bib -III F ull Technical Specificatio ns (To be filled by the Tenderer) 16”x300RF ½” screwed ½” screwed 1” screwed 3/4” Ø / 1”Ø screwed 3/4” screwed 3/4” Ø / 1”Ø screwed 1” NPT As mentioned in Setion 6: Schedule of Requiremen 123 SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) 5 6 7 8 9 4 As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). Mounted Carrier Gas Calibration Gas Other required fittings, cables, software, Manual and accessories as per design, specification and schedule of requirement. L. Station Outlet Insulating Joint, W/N 1 2 Station outlet Check Valve Station Outlet Ball Valve 3 Pressure Gauge(0 -500)psig 4 Purging Valve 5 Temperature Indicator 6 16”x 300 Class 16”x 300 RF 16”x 300 RF ½” screwed ½” screwed 3/4” screwed Other required line pipe, Tee, flanges/blind Flanges, screwed needle valve, gasket, thermo well, 7 fittings and accessories as per design, drawing (P&ID, Station outlet Part), and schedule of requirement. M. Condensate Storage Tank Skid. Condensate Storage Tank 10,000 Liters 1 (Under grounded): With Safety Relief, Gas RMS Bib -III (To be filled by the Tenderer) ts (G. Vendor List). Online UPS Voltage Stabilizer Backup Battery Printer Other required fittings, cables, software, Manual, continuous printing sheet (50 pkts) and accessories as per design, specification and schedule of requirement. K. Gas Chromatograph Gas Chromatograph 1 (On Line, C 6+) Panel 2 3 F ull Technical Specificatio ns As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). As mentioned in Setion 6: 124 SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) 2 4 1”Ø API 5L X52, Seamless Pipe (Drain line) Other required line pipe, Tee, Elbow ,flanges/blind Flanges, screwed needle valve, gasket, thermo well, fittings, Wrapping Tape , Primer and accessories as per design, drawing (P&ID, Station outlet Part), and schedule of requirement. (To be filled by the Tenderer) Schedule of Requiremen ts (G. Vendor List). Counter Meter, Fire Safety Valve, Flame arrestor, gauge, Level Gauge, gasket, Insulating flange/kit Cathotic Protection, fittings and accessories as per design, drawing (P&ID of Condensate Tank), and schedule of requirement. Other required drain pipe, valves, flange, gasket, and accessories as per design, drawing (P&ID) and schedule of requirement. N. Interconnecting Line pipe/ Materials. 16”Ø API 5L X52, ERW Sch /80 1 8”Ø API 5L X52, ERW Sch /80 2 3 F ull Technical Specificatio ns Sch /80 As mentioned in Setion 6: Schedule of Requiremen ts (G. Vendor List). O. UPS & VS etc. 1 UPS & VS for FC, GC, WBH, T ransmitter etc. R. Lighting 1 2 Area lighting (Explosion proof) Lighting for WBH (Explosion proof) S.Protection 1 Cathodic Protection 2 Earthing system for RMS 3 Lightning arrester for Gas RMS Bib -III 125 SL Name & Description Technical Specifications (As per BPDB’s Requirements) Required Country of origin Country of Origin (To be filled by the Tenderer) Proposed Manufactur er’s Name and Model/Part no. (To be filled by the Tenderer) 4 5 6 F ull Technical Specificatio ns (To be filled by the Tenderer) control building Fire Extinguishers for RMS Fire hydrant Methane detector [The Tenderer should complete all the columns] Signature: [insert signature of authorised representative of the Tenderer] Name: [insert full name of signatory] [insert designation of signatory] In the capacity of: Duly authorised to sign the Tender for and on behalf of the Tenderer Gas RMS Bib -III 126 Section 6. Bill of Quantities & Schedule of Requiement Gas RMS Bib -III 127 The Tenderer shall fill-up the following table of prices and shall submit it with the Technical proposal Schedule-1.1 Supply of Equipmet, Spares & Tools for construction of Bibiyana III 400 MW CCPP RMS Sl. No Item Name Foreign Currency (FC) CIF Price Total 2 3 1 1 2 3 4 Bangladesh Taka (LC) Insurance for Inland Transportation up to Transportation , Port Site handling Charges and others 4 5 Total amount FC LC 6=3 7=4+5 Supply of Main Equipments/ materials/ items of Bibiyana III 400 MW CCPP RMS (Schedule 1.1.1) Supply of Mandatory Spare parts (to be used after warranty Period) for Bibiyana III 400 MW CC Power Plant RMS (Schedule 1.1.2) Supply of Required Tools for operation & maintenance of Bibiyana III 400 MW CC Power Plant RMS (Schedule 1.1.3) Supply of Recommended Spare and Tools (including calibration equipments) for dtart up and commissioning of the RMS. (Schedule 1.1.4) Total (in Figures and in Words): Gas RMS Bib -III 128 Schedule-1.1.1 Supply of Main Equipment/ materials/ items of Bibiyana III 400 MW CCPP RMS Item Name Sl. No 1 2 A. Station Inlet Unit 1 Insulating joint, W/N 2 3 4 5 Station Inlet Ball Valve Pressure Gauge (0-1500)psig Purging Valve Temperature Transmitter(Digital) 6 Pressure Transmitter(Digital) 7 8 9 Emergency Shutdown valve (ESD) By -Pass Ball Valve Other required line pipe, elbow, flanges /blind flanges, gasket, screwed Valve, Needle valve for pressure gauge, Thermo well, fittings, stud-bolts, cables and accessories as per design, drawing (P&ID, inlet part) and schedule of requirement. Gas RMS Bib -III Size & Class 3 8”x600 Class 8”x600RF ½” screwed ½” screwed 3/4” Ø / 1”Ø screwed 3/4” Ø / 1”Ø screwed 8”x600 Class 2”x600RF Unit Qty 4 5 No. No. No. No. No. 01 01 03 06 01 No. 01 No. No. Lot 01 01 01 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 129 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 85 MMSCFD KOD (at minimum 600 psig and maximum 1100 psig operating pressure) and other fittings, screwed needle valve for pressure gauge, drain valves, gasket, gauges and accessories as per design, drawing (P&ID, KOD part) and specification. Inlet & Outlet Ball Valve By-Pass Ball Valve 8"Ø x8"Ø x 600 Class No. 01 8”x600RF 8”x600RF Nos. No. 02 01 Pressure Gauge (0-1500)psig ½” screwed No. 03 Purging Valve ½” screwed No. 02 Lot 01 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 B. Knock Out Drum (KOD) Unit 1 2 3 4 5 6 Other required line pipe, relief valve, elbow, tee, flanges, screwed Needle valves for pressure gauge, stud-bolts, gasket, fittings and accessories as per design, drawing (P&ID, beyond KOD) and schedule of requirement. Gas RMS Bib -III 130 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 C. Filter Separator (FS) Unit 1 2 3 4 5 6 7 85 MMSCFD Filter Separator (Horizontal and Twin lock quick opening type) at minimum 600 psig and maximum 1100 psig operating pressure and other fittings, Purging/Drain valves, gasket, gauges and accessories as per Design, drawing (P&ID, FS part) and specification. 8"Ø x8"Ø 600RF Nos. 02 Inlet Ball Valve Outlet Ball Valve By -Pass Ball Valve Pressure Gauge(0-1500)psig Purging Valve Other required line pipe, relief valve ,elbow, tee, reducer, flanges, screwed needle valve for pressure gauge, stud-bolts, gasket, fittings and accessories as per design, drawing (P&ID, beyond FS) and schedule of requirement. 8”x600RF 8”x600RF 8”x600RF ½” screwed ½” screwed Nos. Nos. No. No. No. Lot 02 02 01 06 06 Gas RMS Bib -III 131 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 D. Water bath Heater (WBH) Unit 85 MMSCFD Water Bath Heater (at minimum 600 psig and maximum 1100 psig operating pressure) and other fittings, gasket, screwed valves and accessories as per design, drawing (WBH) and specification to maintain delivery temperature between 15 to 22 °C at 150 psig pressure. 8"Ø x8"Ø 600RF Nos. 02 2 3 4 Inlet & Outlet Ball Valve By -Pass Ball Valve Three way Control Valve with all other controlling unit 8”x600RF 8”x600RF 8”x600RF Nos. No. Nos. 04 01 02 5 6 7 8 Control Panel (PLC Control) Pressure Gauge(0-1500)psig Purging Valve Temperature Transmitter(Digital) Nos. Nos. Nos. Nos. 02 06 06 02 1 Gas RMS Bib -III ½” screwed ½” screwed 3/4” Ø / 1”Ø screwed 132 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 3/4” screwed Nos. Lot 03 01 8”x600RF 6”x600RF 6”x600RF 2”x600RF 1”x600 Screwed 8”x600RF 10”x600RF 6”x600RF 2”x600RF 10”x600RF 10”x600 10”x600 ½” screwed Nos. Nos. Nos. Nos. Nos. Nos. Nos. No. Nos. Nos. Nos. Nos. Nos. 02 02 02 01 02 04 03 01 01 02 02 02 10 Temperature Indicator Other required line pipe, elbow, tee, flanges, screwed needle valve for pressure gauge, gasket, Stud -bolts, T hermo well, fittings, cables and accessories as per design, drawing (P&ID, beyond WBH), specification, and schedule of requirement. E . 1 s t stage Regulating Unit Slam shut off Valve 1 2 Monitor Regulator 3 Active Regulator 4 Header Relief 5 Runs Relief 6 Inlet Ball Valve Outlet Ball Valve 7 Control (Glob) Valve 8 Valve for Header Relieves 9 10 Check Valve 11 Noise Silencer 12 Noise Silencer 13 Pressure Gauge(0-1500)psig 9 10 Gas RMS Bib -III Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 133 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 14 Purging Valve Drain Valve/Valve in screwed relief Temperature Indicator Blind Flange for off take Other required line pipe, elbow, tee, reducer, saddle, flanges/blind flanges, screwed Needle valves for pressure gauge and sensing line, stud-bolts, Thermo well, gasket, fittings, tubes -coupling and accessories as per design, drawing (P&ID, Regulating unit), specification, and schedule of requirement. ½” screwed 1” screwed 3/4” screwed 10”x600RF Nos. Nos. No. No Lot 14 06 01 02 01 85 MMSCFD Liquid Separator (Vertical type ) at 500 psig operating pressure and other fittings, gasket, screwed needle valve, purging/drain valves and accessories as per design, drawing (P&ID, VME part) and specification and schedule of requirement. Inlet & Outlet Ball Valve Bypass Ball Valve Pressure Gauge(0-500)psig 10”x10”x 300RF Nos. 01 10”x300RF 10”x300RF ½” screwed Nos. No. Nos. 02 01 02 15 16 17 18 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 F. 1st Liquid Separator Unit 1 2 3 4 Gas RMS Bib -III 134 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 5 6 Purging Valve Other required line pipe, relief valve, elbow, tee, flanges, gasket, stud-bolts, fittings and accessories as per design, drawing (P&ID, beyond VME), specification, and schedule of requirement. Nos. Lot 02 G.2nd stage Regulating Unit Slum shut off Valve 1 Monitor Regulator 2 Active Regulator 3 Header Relief 4 Runs Relief 5 Inlet Ball Valve 6 Outlet Ball Valve 7 Control (Globe) Valve 8 Valve for Header Relief 9 10 Check Valve 11 Noise Silencer 12 Noise Silencer 13 Pressure Gauge(0-600)psig 14 Purging Valve Gas RMS Bib -III ½” screwed 08”x300RF 6”x300RF 6”x300RF 2”x300RF 1”x300 Screwed 10”x300RF 14”x300RF 6”x300RF 2”x300RF 14”x300RF 14”x300 14”x300 ½” screwed ½” screwed Nos. Nos. Nos. No. Nos. Nos. Nos. No. No. Nos. Nos. Nos. Nos. Nos. Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 01 02 02 02 01 02 03 03 01 01 02 02 02 10 14 135 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 Nos. No. Lot 08 01 01 14”x14”x 300RF No. 01 14”x300RF 14”x300RF ½” screwed ½” screwed Nos. Nos. Nos. Nos. 01 01 02 02 15 16 17 Drain Valve/Valve in screwed relief 1” screwed Temperature Transmitter(Digital) 3/4” screwed Other required line pipe, elbow, tee, reducer, saddle, flanges/blind flanges, screwed needle valves for pressure gauge and sensing line, stud -bolts, fittings, Thermo well gasket, tubes -couplings and accessories as per design, drawing (P&ID, regulating unit), specification, and schedule of requirement. Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 H. 2nd Liquid Separator Unit 1 2 3 4 5 85 MMSCFD Liquid Separator (at 150 psig to 320 psig operating pressure) and other fittings, gasket, gauges, screwed needle valve for pressure gauge, Purging/drain valves and accessories as per design, drawing (P&ID, VME part) and specification and schedule of requirement. Inlet Ball Valve Outlet Ball Valve Pressure Gauge(0-500)psig Purging Valve Gas RMS Bib -III 136 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 No. No. Lot 01 01 01 16”x300RF No. 01 1 6”x300RF ½” screwed ½” screwed 1” screwed Nos. Nos. Nos. No. Nos. 02 03 02 01 01 6 7 8 Bypass Ball Valve 14”x300RF Ball Valve for off Take 4”x300RF Other required line pipe, relief valve, elbow, tee, flanges, screwed needle valve for pressure gauge, stud-bolts, fittings, gasket, and accessories as per design, drawing (P&ID, beyond VME), specification, and schedule of requirement. Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 I. Oriface Metering Unit 1 2 3 4 5 6 85 MMSCFD Senior Type (Dual Chamber) Orifice Meter at 150 psig to 320 psig operating pressure and other Flanges, fittings, gasket, tubes, straightening vane, screwed needle valve, stud-bolts and accessories as per design, drawing (P&ID, Orifice Meter part), specification and schedule of requirement. Inlet & Outlet Ball Valve Pressure Gauge(0-500)psig Purging Valve Purging Valve Temperature Transmitter(Digital) Gas RMS Bib -III 3/4” Ø / 1”Ø screwed 137 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 Nos. Nos. 02 03 No. Set 01 01 Set 01 Lot 01 No. 01 No. No. 01 01 7 8 Pressure Transmitter(Digital) Diff.Pressure Transmitter(Digital) Regulator (Fisher-627) Chart Recorder With three pens for Static pressure (0500psig), differential pressure (010 100”WC) and temperature (0-150°F) record with thermo well and all accessories. Plani meter with Turn table (Chart 11 Drive) to read Chart Paper Other required line pipe ,stud-bolts, screwed needle valve for pressure gauge, gasket, Thermo well, fittings, cables and 12 accessories as per design, drawing (P&ID, Orifice meter part), specification, and schedule of requirement. J. Flow Computer Unit Flow Computer 1 (Microprocessor Based) 2 Control Panel Laptop Computer 3 9 Gas RMS Bib -III 3/4” screwed 3/4” Ø / 1”Ø screwed 1” NPT Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 138 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 4 5 6 7 8 Supervisory Computer Online UPS Voltage Stabilizer Backup Battery Printer Other required fittings, cables, software, Manual, continuous printing sheet (50 pkts) and accessories as per design, specification and schedule of requirement. No. No. No. No. No. Lot 01 01 01 01 01 01 No. 01 Cylind er Cylind er Lot 02 No. No. No. 01 01 01 9 K. Gas Chromatograph Gas Chromatograph 1 (On Line, C 6+) Panel Mounted 2 3 4 Carrier Gas Calibration Gas Other required fittings, cables, software, Manual and accessories as per design, specification and schedule of requirement. L. Station Outlet Insulating Joint, W/N 1 Station outlet Check Valve 2 Station Outlet Ball Valve 3 Gas RMS Bib -III 16”x 300 Class 16”x 300 RF 16”x 300 RF Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 02 01 139 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 Nos. Nos. No. Lot 02 02 01 01 No. 01 Lot 01 Pressure Gauge(0-500)psig ½” screwed Purging Valve ½” screwed Temperature Indicator 3/4” screwed Other required line pipe, Tee, flanges/blind Flanges, screwed needle valve, gasket, thermo well, fittings and 7 accessories as per design, drawing (P&ID, Station outlet Part), and schedule of requirement. M. Condensate Storage Tank Skid. Condensate Storage Tank (Under 10,000 Liters grounded): With Safety Relief, Counter Meter, Fire Safety Valve, Flame arrestor, gauge, 1 Level Gauge, gasket, Insulating flange/kit Cathotic Protection, fittings and accessories as per design, drawing (P&ID of Condensate Tank), and schedule of requirement. Other required drain pipe, valves, flange, gasket, and accessories as per design, 2 drawing (P&ID) and schedule of requirement. 4 5 6 Gas RMS Bib -III Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 140 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 Meter Meter Meter 350 200 250 N. Interconnecting Line pipe/ Materials. 16”Ø API L X52, ERW 1 8”Ø API L X52, ERW 2 3 4 1”Ø API L X52, Seamless Pipe (Drain line) Other required line pipe, Tee, Elbow ,flanges/blind Flanges, screwed needle valve, gasket, thermo well, fittings, Wrapping Tape , Primer and accessories as per design, drawing (P&ID, Station outlet Part), and schedule of requirement. Sch /80 Sch /80 Sch /80 Lot 01 Lot 01 Lot Lot 01 01 Lot Lot Lot 01 01 01 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 O. UPS & VS etc. 1 UPS & VS for FC, GC, WBH, Transmitter etc. R. Lighting Area lighting (Explosion proof) 1 Lighting for WBH (Explosion proof) 2 S.Protection Cathodic Protection 1 Earthing system for RMS 2 Lightning arrester for control building 3 Gas RMS Bib -III 141 Sl. No Item Name Size & Class Unit Qty 1 2 3 4 5 4 5 6 Fire Extinguishers for RMS Fire hydrant Methane detector Lot Lot Lot Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuran Inland ce for Transportati Transp on , Port ortation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 01 01 01 Total * Tenderer has to mention clearly the name of foreign currency. ** Point of Delivery: Bibiyana III 400 MW CCPP Project site, Nabiganj Upazila, Habiganj District. *** Scope of supply of equipment/ items/ materials are not limited by the items mentioned above. If any other additional materials/ equipment are required for completion of Turnkey work, contractor shall have to supply the additional equipment/ items/ materials without any additional cost. The cost of these additional spares/materials/ equipment are deemed to be included within the quoted price. Gas RMS Bib -III 142 Schedule-1.1.2 Supply of Mandatory Spare parts (to be used after warranty Period) for Bibiyana III 400 MW CC Power Plant RMS. SL No Equipment Name Description of Spare parts (to be supplied by the Contractor) Country Unit of origin (To be filled by the Tendere r) Qty Foreign Currency (FC) CIF Price Rate 1 2 Inlet Unit 1. ESD 2. PT (Pressure Transmitter) 3. Resistance temperature detector (RTD) 4. Temperature Gauge (0150º F) 5. Pressure Gauge(0-1500 psig) 6. Pressure Gauge (0- 500 psig) Filter Separator Unit 7. Filter Element for Filter Separator 8. O-ring for Filter separator Pressure 9. Differential T ransmitter 10. Auto discharge drain valve 11. Safety valve Gas RMS Bib -III 3 4 5 6 Spare kits of ESD Set Set No No No 05 02 04 Set No 06 Set No 12 Set No 12 Filter cartridge No 80 Set No No 24 02 Set No 08 Body Repair kits for Safety valve. No 04 7 Total 8=6x7 Bangladesh Taka (LC) Insuranc e for Transpor tation up to Site Total 9 Total amount Inland Transport ation , Port handling Charges and others Total FC LC 10 11=8 12=9+10 143 SL No Equipment Name 1 2 Heater unit 12. Slam Shut for Heater RMS 13. Regulator for Heater RMS 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. Main Burner for WBH Pilot Burner for WBH Main Burner nozzles Pilot Burner nozzles High Pressure switch Low Pressure switch Temperature switch Temperature controller Level switch Power supply unit PLC Resistance temperature detector 26. 27. Ignition Transformer Ignition Electrode Gas RMS Bib -III Description of Spare parts (to be supplied by the Contractor) 3 Country Unit of origin (To be filled by the Tendere r) 4 Qty Foreign Currency (FC) CIF Price 5 6 Body Repair kits. No 15 Body & Pilot Repair kits for Regulator No 20 complete set complete set complete set complete set Set Set Set Set Set Set Set Set No No No No No No No No No No Set No 02 02 08 12 04 04 04 04 02 08 02 04 Set Set No No Rate 7 Total 8=6x7 Bangladesh Taka (LC) Insuranc e for Transpor tation up to Site Total 9 Inland Transport ation , Port handling Charges and others Total 10 Total amount FC LC 11=8 12=9+10 04 04 144 SL No 1 28. 29. Equipment Name 2 Solenoid valve complete set for main Burner & Pilot Burne r Damper motor Description of Spare parts (to be supplied by the Contractor) 3 Set Country Unit of origin (To be filled by the Tendere r) 4 Qty CIF Price 5 No 6 16 Set No 01 30. Blower motor Set No 01 31. Flame amplifier set No 04 32. Flame detector Set No 04 33. Ionization Rod Set No 06 34. Relays set Set No 40 set No 04 Set No 04 Set No 30 No 30 Pressure Gauge(0-100) bars Gauge(0-2.5) 36. Pressure bars Fuses (Glass & cartridge 37. type) Regulation Unit 35. 38. Slam Shut 8”x600RF Gas RMS Bib -III Valve Slam Shut Valve Repair kits. Foreign Currency (FC) Rate 7 Total 8=6x7 Bangladesh Taka (LC) Insuranc e for Transpor tation up to Site Total 9 Inland Transport ation , Port handling Charges and others Total 10 Total amount FC LC 11=8 12=9+10 145 SL No 1 39. 40. 41. 42. 43. 44. 45. 46. 47. 48. 49. Equipment Name Description of Spare parts (to be supplied by the Contractor) 2 Monitor Regulator 6”x600RF Active Regulator 6”x600RF Pilot for Monitor Regulator 6”x600RF Pilot for Active Regulator 6”x600RF Slam Shut Valve 8”x300RF Monitor Regulator 6”x300RF Active Regulator 6”x300RF Pilot for Monitor Regulator 6”x300RF Pilot for Active Regulator 6”x300RF Run Relief Safety valve 3 Body Repair kits for Regulator. Body Repair kits for Regulator. Pilot Repair kits for Regulator. Pilot Repair kits for Regulator. Slam Shut Valve Repair kits. Body Repair kits for Regulator. Body Repair kits for Regulator. Pilot Repair kits for Regulator. Pilot Repair kits for Regulator. Body Repair kits for Safety valve. Common Header Safety valve Body & Pilot Repair kits for Safety valve. Gas RMS Bib -III Country Unit of origin (To be filled by the Tendere r) 4 Qty Foreign Currency (FC) CIF Price 5 No 6 40 No 40 No 50 No 50 No 30 No 40 No 40 No 50 No 50 No 25 No 20 Rate 7 Total 8=6x7 Bangladesh Taka (LC) Insuranc e for Transpor tation up to Site Total 9 Inland Transport ation , Port handling Charges and others Total 10 Total amount FC LC 11=8 12=9+10 146 SL No Equipment Name 1 2 Metering unit 50. Plani meter with Turn table 51. Chart papers 52. Mechanical chart drive 53. Spare Chart Pen ( Three Different Color) 54. Spare Chart Pen Arm ( Three Different Color) 55. Orifice Plate & oring of different size to meet demand (25%, 50%, 75% capacity). 56. PT (Pressure Transmitter) (Differential 57. DPT Pressure Transmitter ) 58. Temperature Transmitter 59. T hermometer ºC 60. T hermometer ºF Regulator (1” NPT, 61. Fisher-627) 62. Body & Pilot Spare kits Regulator (1” NPT, Fisher-627) Gas RMS Bib -III Description of Spare parts (to be supplied by the Contractor) 3 Country Unit of origin (To be filled by the Tendere r) 4 Qty Foreign Currency (FC) CIF Price 5 6 Set No 02 Box (100pcs) Set Set Box No Set 50 02 50 Set No 25 Set No 06 Set Set No No 02 03 Set Set Set Set No No No No 02 12 12 01 Set No 10 Rate 7 Total 8=6x7 Bangladesh Taka (LC) Insuranc e for Transpor tation up to Site Total 9 Inland Transport ation , Port handling Charges and others Total 10 Total amount FC LC 11=8 12=9+10 147 SL No Equipment Name 1 2 Gas chromatograph 63. Power supply unit 64. I/O cards 65. Mother board 66. Software for GC 67. Calibration Gas 68. Carrier Gas 69. Sample gas regulator Flow Computer 70. Power supply unit 71. I/O cards 72. Mother board 73. Software for FC 74. Laptop (Software & data upload & down load) 75. Printer with scanner 76. Desktop computer with UPS & printer removal 77. Condensate pump motor, 1HP 78. 1”Ø Hose Pipe Gas RMS Bib -III Description of Spare parts (to be supplied by the Contractor) 3 Country Unit of origin (To be filled by the Tendere r) 4 Qty Foreign Currency (FC) CIF Price 5 6 Set Set Set Set Cylinder Cylinder Set No No No Set No No No 04 02 01 01 08 08 02 Set Set Set Set Set No No No Set No 04 02 01 01 01 Set Set No No 01 01 Set No 01 Mete r 50 Rate 7 Total 8=6x7 Bangladesh Taka (LC) Insuranc e for Transpor tation up to Site Total 9 Inland Transport ation , Port handling Charges and others Total 10 Total amount FC LC 11=8 12=9+10 148 SL No Equipment Name 1 2 Description of Spare parts (to be supplied by the Contractor) 3 Country Unit of origin (To be filled by the Tendere r) 4 Qty Foreign Currency (FC) CIF Price 5 6 Set Set Set No No No 12 12 12 Set Set Set No No No 06 06 25 Set Set Set No No No 25 Set Set No No 04 04 Rate 7 Total 8=6x7 Bangladesh Taka (LC) Insuranc e for Transpor tation up to Site Total 9 Inland Transport ation , Port handling Charges and others Total 10 Total amount FC LC 11=8 12=9+10 Spare Pressure Gauge 79. (0-1500) Psig range 80. (0-1000) Psig range 81. (0-500) Psig range FC/Heater PANEL 82. Safety barriers 83. Lightning barriers for Panel 84. Set of indication lamps 85. 86. 87. 88. 89. (LED) & holder Set of Switches Relay Circuit breaker (different size & amp) Panel Display Magnetic contractor with thermal relay KOD, Filter separator & Liquid Separator: Set 90. Spare parts -kit for the auto 91. discharge system (level control valve) Spare parts -kit for the Vessel Safety Relief Valve Set No 25 No 25 25 25 * Tenderer has to mention clearly the name of foreign currency. ** Point of Delivery: Bibiyana III 400 MW CCPP Project site, Nabiganj Upazila, Habiganj District. Gas RMS Bib -III 149 Schedule-1.1.3 Supply of Required Tools for operation & maintenance of Bibiyana III 400 MW CC Power Plant RMS. Sl. No Item Name 1 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 2 Special tools for opening Filter separator Special tools for maintenance regulator Lever and chain for maintenance regulator Ratchet set box with tools Adjustable Slide Wrench 12Pcs different size (06” – 48”) Pipe wrench 05 Pcs different size (12” – 48”) Ring Wrench 18Pcs different size (6 – 62 mm) Dally Wrench 18Pcs different size (6 – 62 mm) Allen Key set ( 13 pcs of different size in Inch) Allen Key set ( 13 pcs of different size in mm) Wooden Hammer 1lb Wooden Hammer 2lb Gas RMS Bib -III Name of manufacturer, Country of Origin. Model/Type no. of offered equipment (To be filled by the Tenderer) 3 Unit Qty 4 5 Set 02 Set 02 Set 02 Set Set 02 02 Set 02 Set 02 Set 02 Set 02 Set 02 no no 02 02 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuranc Inland e for Transportatio Transpo n , Port rtation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 150 Sl. No Item Name 1 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 2 Monkey Ring Wrench ( 3 pcs of different size in mm) Nose Pliers ( 6 pcs of different size ) Pliers ( 6 pcs of different size ) Screw driver(Flat) 6 pcs of different size Screw driver(Star) 6 pcs of different size Screw ( Combination) Driver set ( 10 pcs of different size ) Ratchet wrench flange separator (06 pcs for different size) Tool Box ( For Carrying varies types of tools) Flat file 4 pcs of different size (06” – 12”) Round file 4 pcs of different size (06” – 12”) Tapper file 4 pcs of different size (06” – 12”) Half round file different size (06” – 12”) Grease Gun (High & low pressure) latest model Gas RMS Bib -III Name of manufacturer, Country of Origin. Model/Type no. of offered equipment (To be filled by the Tenderer) 3 Unit Qty 4 5 Set 02 Set Set Set 02 02 02 Set 02 Set 02 set 02 Set 02 Set 02 Set 02 Set 02 Set 02 Set 02 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuranc Inland e for Transportatio Transpo n , Port rtation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 151 Sl. No Item Name 1 2 26. 27. 28. 29. 30. 31. 32. 33. Steel tape (100 feet) Hacksaw frame with blade Tube cutter Tube bender Digital Multi Meter Remote methane leak detection Hax key set (1.5mm -12mm) Portable BTU gas analyzer Digital Sound Level Measurement Equipment (Unit db) Hydraulic Dead weight tester (For Static pressure) Hand pump Pneumatic Dead weight tester (For DP) Clamp Meter Multi plug (cable length-50 meter) Soldering iron with voltage regulator Hart communicator Fire extinguisher safety Shoes Ear protector Helmet safety Glass Hand Gloves 34. 35. 36. 37. 38. 39. 40. 41. 42. 43. 44. 45. 46. Gas RMS Bib -III Name of manufacturer, Country of Origin. Model/Type no. of offered equipment (To be filled by the Tenderer) 3 Unit Qty 4 5 Set Set Set Set Set Set Set Set Set 02 02 02 02 02 02 02 01 02 Set 01 Set 01 Set Set Set Set No Pair Set No No No 02 02 02 01 12 12 12 12 12 12 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuranc Inland e for Transportatio Transpo n , Port rtation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 152 Sl. No Item Name 1 47. 48. 2 First Aid Box Ladder (steel structure) Name of manufacturer, Country of Origin. Model/Type no. of offered equipment (To be filled by the Tenderer) 3 Unit Qty 4 5 No No 02 02 Foreign Currency (FC) CIF Price Rate 6 Total 7=5x6 Bangladesh Taka (LC) Insuranc Inland e for Transportatio Transpo n , Port rtation handling up to Charges and Site others Total Total 8 9 Total amount FC LC 10=7 11=8+ 9 Total * Tenderer has to mention clearly the name of foreign currency. ** Point of Delivery: Bibiyana III 400 MW CCPP Project site, Nabiganj Upazila, Habiganj District. Gas RMS Bib -III 153 Schedule-1.1.4 Supply of Recommended Spare and Tools (including calibration equipments) for dtart up and commissioning of the RMS. Sl. No Item Name Unit Qty 1 2 3 4 01 INLET FILTER SEPARATOR 02 HEATERS 03 PRESSURE REGULATORS 04 PRESSURE RELIEF VALVES 05 SLAM SHUT OFF VALVE 06 ORIFICE METER 07 ONLINE GAS CHROMAT OGRAPH Gas RMS Bib -III Foreign Currency (FC) CIF Price Rate 5 Total 6=4x5 Bangladesh Taka (LC) Insuranc Inland e for Transportatio Transpo n , Port rtation handling up to Charges and Site others Total Total 7 8 Total amount FC LC 9=6 11=7+ 8 154 Sl. No Item Name Unit Qty 1 2 3 4 08 FIELD INSTRUMENT 09 CONTROL PANEL 10 FLOW COMPUTER 11 CONDENSATE TANK 12 ORIFICE METER CHART RECORDER 13 STATION MAINTENANCE TOOLS 14 UPS/DC PANEL 15 CALIBRATION EQUIPMENTS Gas RMS Bib -III Foreign Currency (FC) CIF Price Rate 5 Total 6=4x5 Bangladesh Taka (LC) Insuranc Inland e for Transportatio Transpo n , Port rtation handling up to Charges and Site others Total Total 7 8 Total amount FC LC 9=6 11=7+ 8 155 Sl. No Item Name Unit Qty 1 2 3 4 16 Foreign Currency (FC) CIF Price Rate 5 Total 6=4x5 Bangladesh Taka (LC) Insuranc Inland e for Transportatio Transpo n , Port rtation handling up to Charges and Site others Total Total 7 8 Total amount FC LC 9=6 11=7+ 8 OTHERS Total * Tenderer has to mention clearly the name of foreign currency. ** Point of Delivery: Bibiyana III 400 MW CCPP Project site, Nabiganj Upazila, Habiganj District. ***Tenderer may add additional rows as required. Gas RMS Bib -III 156 Schedule- 1.2 Services for TurnkeyWork [ Erection, Installation, Testing, commissioning etc. as specified in Section 6,7 ,8 and 9] SL Description No. a. b. c. d. e. f. g. h. i. j. Total Schedule-1.2: Qty Cost in foreign currency Unit cost Total cost Cost in Bangladeshi Taka Unit cost Total cost Note: 1) Tenderer has to mention clearly the name of foreign currency. 2) Tenderers are requested to split the whole work in individual items as per work approach and to fill the schedule accordingly. Tenderer may add additional rows as required. 3) During work if any other additional works are required for completion of Turnkey work, contractor shall have to do the additional works without any additional cost. The costs of these additional works are deemed to be included within the quoted price. Gas RMS Bib -III 157 Schedule- 1.3 Civil Works [as specified in Section 6,7,8 and 9] SL No. 1. 2. 3. Description Qty Construction of Control Building : Design & construct a two stored control building cum office of 2500 sqft (each floor 1250 sqft) to accommodate control panel equipments and office personnel for operation as per foundation drawing. Full civil construction with 3 -phase electrical wiring, Furniture (cabinet, almirah, table, front chair, back chair, cot, bed, AC, ceiling fan, light, TV, kitchen accessories, etc) Earthing system for, Lightning arrester, Deep tube well with water pump motor 1 HP, Smoke detector. Earth Filling and Compaction Works: Filling and developing of the land to formation level (same level of Bibiyana III power plant site). Earth shall be compacted in six inch layer with water sprinkling. CC Walkway, Stone Pitching, Boundary Wall and Surface Drain: Supplier shall construct 1.5 meter wide walk ways across the RMS, around the Skid foundation and complete stone pitching in surface area and drain as per foundation drawing and instructed by EIC and according to schedule of requirement and technical specification Boundary Wall: Over 10 inch thick, 20 inch width cc foundation and at least 3 feet below ground level over a compacted WBM, boundary wall shall be at least 5 feet height 2500sq ft Gas RMS Bib -III Cost in foreign currency Unit cost Total cost Cost in Bangladeshi Taka Unit cost Total cost Lot Lot 158 SL No. Description Qty Cost in foreign currency Unit cost Total cost Cost in Bangladeshi Taka Unit cost Total cost and 5 inch from the finished ground level all around the RMS premises. On the top of brick wall there shall be 2 feet height fencing all around the boundary wall. Actual design shall be approved by EIC. Gates to be placed in the position shown in the drawing and to be approved by the EIC. 4. Base foundation, RCC Pipe Supports Lot Design and Construction of RCC foundation and pipe supports for installation of KOD, Filter Separators, Water Bath Heaters, Regulating skids, Liquid Separators (VMEs), Orifice Metering Skid, Condensate Tank and for other piping equipments (if required). The Supplier shall supply all the required materials for construction Works. 5. Steel Structure Skids, Steel Structure Foot Lot over bridges, Shade on Heaters & Metering Unit, Painting, area lighting, Lightening Arrestor, Fencing, Guard Room and other as per Foundation drawing, schedule of requirement and Technical Specification. Total Schedule -1.3: Note: 1) Tenderer has to mention clearly the name of foreign currency. 2) Scope of works is not limited by the above mentioned items. If any other additional works are required for completion of Turnkey work, contractor shall have to do the additional works without any additional cost. The costs of these additional works are deemed to be included within the quoted price. 3) Tenderers are requested to split the whole work in individual items as per work approach and to fill the schedule accordingly. Tenderer may add additional rows as required Gas RMS Bib -III 159 Schedule- 1.4 Services for Other Related Items [as specified in Section 6,7,8 and 9] SL Description Unit Qty Cost in foreign No. currency Unit cost Total cost Cost in Bangladeshi Taka Unit cost Total cost A. Technology Transfer/Know -how from Manufacturer’s/Supplier’s Country 1 Witnessing of manufacturing process, tests of the Lot 01 equipment/ materials/ spares and foreign training at manufacturer(s)/ Supplier(s)/ Tenderer Country(s) [As per PCC(GCC 54), details are given Section 6: Schedule of requirement (C. Schedule for Technology T ransfer/Know-how from Manufacturer/Supplier Country for 4 (four) personnel [02 from BPDB, 02 from Jala labad Gas]. B. Other Facilities 1. Vehicle: To provide 01(one) Vehicle (Latest No. 01 Model) including full time driver and fuel & Oil for movement of Purchaser/Employer’s site personnel. Vehicle should be minimum 07(seven) seater and high roof with AC. Vehicle shall be provided within one week from the date of LC opening and shall continue till issuance of PAC. 2. Office F urniture, Computer and others : Supply Lot 01 of 02 (two) executive table, 02 (two) executive chair, 05 (five) front chair, 02 (two) file cabinet, 01 (one) File rack, 01 (one) Drinking Water Filter, 02(Two) Office Almeria, 02 (Two) AC, 2(two) Semi double cots with bed and one Tea set. Office furniture should be of high quality standard preferably local Otobi brand. One latest model computer, one computer table, one Scanner and a laser printer for Office used to be supplied. Furniture and computer shall be Gas RMS Bib -III 160 Description SL No. Unit Qty Lot 01 Lot 01 Lot 01 Cost in foreign currency Unit cost Total cost Cost in Bangladeshi Taka Unit cost Total cost provided /supplied within 300 days from the date of LC opening. Supply of 03 (three) post-paid/ Prepaid mobile phone (Latest model) & 03 (three) Laptop computer (Latest model), 03 sets of safety equipment, 03 carrying bag for site execution personnel (supervision committee) of the Purchaser/Employer. Handsets should be of high quality. Mobile Phone shall be provided within two weeks from the date of LC opening and the Supplier/Contractor shall continue to pay the bill till issuance of PAC. C. Local site Training and Supervision. 1 2 Local site training at RMS site for 15 officials & 07 days (with refreshments , transportation, carrying bag, pen drive, manual & other training material) during station commissioning. During site supervision/construction entertainment should be provided. D. Warranty 1 Two year warranty period with maintenance Total Schedule-1.4: Note: 1) Tenderer has to mention clearly the name of foreign currency. 2) Scope of works is not limited by the above mentioned items. If any other additional works are required for completion of Turnkey work, contractor shall have to do the additional works without any additional cost. The costs of these additional works are deemed to be included within the quoted price. 3) Tenderers are requested to split the whole work in individual items as per work approach and to fill the schedule accordingly. Tenderer may add additional rows as required Gas RMS Bib -III 161 Schedule- 2 Summary of prices for Design- Build, Supply, Erection, Installation, Testing & Commissioning of Skid Mounted Gas Regulating & Metering Station for Supplying Natural Gas to Bibiyana III 400 MW Combined Cycle Power Plant at Nabiganj Upazila, Habiganj District on Turnkey Basis. Sch No. Description Sch No. 1.1 Supply of Equipment, Spares & Tools. Sch No. 1.2 Services for Turnkey Work Sch No. 1.3 Civil Works Sch No. 1.4 Services for Other Related Items Total Foreign Currency(FC) Total Bangladesh Taka Total (in Figures and in Words): Gas RMS Bib -III 162 Section 6. Schedule of Requirements Invitation for Tender No: Tender Package No: Date Brief Description of Goods & Related Services: The work under this IFIT shall be contacted on turnkey basis for detailed engineering, designdrawing, supply of gas Regulating & Metering Station with Knock Out Drum ,Filter Separators, Water Bath Heaters, Liquid Separators (VME), Orifice Meter, Flow Computer, Gas Chromatograph, Mechanical Chart Recorder, Condensate Storage Tank, Pressure Regulators, Check Valves, Ball Valves, Hand Control Valves, Insulating Joint, Fittings, Tools, Instruments, Spares parts, Fabrication, Assembling, Construction, Installation, Erection, Testing, Commissioning and Test Run Operation of Skid Mounted RMS of 85 MMSCFD capacity and interconnecting with existing pipeline for Bibiyana-III, 400MW Combined Cycle Power Plant at Nabigang Upzalia, Habiganj, Sylhet. Delivery and Completion Time: The proposed job as detailed in this section and Technical Specifications will have to be completed in all respects and shall have to hand over to the Purchaser after successful installation, testing, commissioning and test run operation of the RMS within 300 (Three hundred ) days from the date of opening of letter of credit (LC). Scope Of Work: Station Capacity: 85 MMSCFD Inlet Source Pressure : 980 to 1000 PSIG Inlet Temperature 10 to 15 C Design Pressure- Maxm 1440 PSIG Design Temperature -5 to 60 C Operating Pressure : 600 to 1100 PSIG Outlet Flow 85 MMSCFD Outlet Pressure 150PSIG Outlet Operating Temperature 10 to 15 C A. List of Goods Required for Completion/Construction of Skid Mounted RMS and interconnecting pipeline: Following are the minimum requirements of Goods (Equipments, Materials, Fittings, Instruments, Auxiliaries, and Accessories etc.) to be included for Supplying a Skid Mounted Regulating & Metering Station (RMS) at Bibiyana-III, 400MW Combined Cycle Power Plant at Nabigang Upzalia, Habiganj . The supplier/ Tenderer shall have to incorporate item(s) or increase quantity (ies) of the Goods/Materials if required as per detail engineering design & drawings done by the Tenderer and for conforming/Complying all the requirements stated in this tender, Section 7: Technical Specifications and Section 9: Drawings. Size/dimension of any item cannot be reduced/decreased by tenderer though that are seem to be over designed, then Tenderer will be disqualified. If Tenderer, as per detail engineering design, thinks that the size/dimension of any item given bellow may need to change (increase only), Tenderer can increase the size/dimension of that item and shall quote in that way. Gas RMS Bib-III 163 RMS Design & Drawing: Table-1 Item Description No 1. Remarks Detailed Engineering, design, drawing & documentation. ( As per Front end Engineering Design and Detail design) RMS Equipments: Table-2 Skid/ Section Description of equipment/ materials & Size & Class thereof Fitting and accessories A. Station Inlet Unit 1. Insulating joint, W/N 2. Station Inlet Ball Valve 3. Pressure Gauge (0-1500)psig 4. Purging Valve 5. Temperature Transmitter(Digital) 6. Pressure Transmitter(Digital) B. Knock Out Drum (KOD) Unit Gas RMS Bib-III 7. Emergency Shutdown valve (ESD) 8. By-Pass Ball Valve 9. Other required line pipe, elbow, flanges /blind flanges, gasket, screwed Valve, Needle valve for pressure gauge, Thermo well, fittings, stud-bolts, cables and accessories as per design, drawing (P&ID, inlet part) and schedule of requirement. 1. 85 MMSCFD KOD (at minimum 600 psig and maximum 1100 psig operating pressure) and other fittings, screwed needle valve for pressure gauge, drain valves, gasket, gauges and accessories as per design, drawing (P&ID, KOD part) and specification. 2. Inlet & Outlet Ball Valve 3. By-Pass Ball Valve 4. Pressure Gauge (0-1500)psig 5. Purging Valve 6. Other required line pipe, relief valve, elbow, tee, flanges, screwed Needle valves for pressure gauge, stud-bolts, gasket, fittings and accessories as per design, drawing (P&ID, beyond KOD) and schedule of requirement. Quantity Unit 01 01 03 06 01 No. No. No. No. No. 01 No. 01 01 Lot No. No. 8"Ø x8"Ø x 600 Class 01 No. 8”x600RF 8”x600RF ½” screwed ½” screwed 02 01 03 02 Lot Nos. No. No. No. 8”x600 Class 8”x600RF ½” screwed ½” screwed 3/4” Ø / 1”Ø screwed 3/4” Ø / 1”Ø screwed 8”x600 Class 2”x600RF 164 C. Filter Separator (FS)Unit 1. 85 MMSCFD Filter Separator( Horizontal and Twin lock quick opening type) at minimum 600 psig and maximum 1100 psig operating pressure and other fittings, Purging/Drain valves, gasket, gauges and accessories as per Design, drawing (P&ID, FS part) and specification. 2. Inlet Ball Valve 3. Outlet Ball Valve 4. By-Pass Ball Valve 5. Pressure Gauge(0-1500)psig 6. Purging Valve 7. Other required line pipe, relief valve ,elbow, tee, reducer, flanges, screwed needle valve for pressure gauge, stud-bolts, gasket, fittings and accessories as per design, drawing (P&ID, beyond FS) and schedule of requirement. D. Water 1. 85 MMSCFD Water Bath Heater (at Bath Heater minimum 600 psig and maximum 1100 (WBH) Unit psig operating pressure) and other fittings, gasket, screwed valves and accessories as per design, drawing (WBH) and specification to maintain delivery temperature between 15 to 22 °C at 150 psig pressure. 2. Inlet & Outlet Ball Valve 3. By-Pass Ball Valve 4. Three way Control Valve with all other controlling unit 5. Control Panel (PLC Control) 6. Pressure Gauge(0-1500)psig 7. Purging Valve 8. Temperature Transmitter(Digital) 9. Temperature Indicator 10. Other required line pipe, elbow, tee, flanges, screwed needle valve for pressure gauge, gasket, Stud-bolts, Thermo well, fittings, cables and accessories as per design, drawing (P&ID, beyond WBH), specification, and schedule of requirement. E. 1 st Regulating Unit 1. Slam shut off Valve 2. Monitor Regulator 3. Active Regulator 4. Header Relief 5. Runs Relief 6. Inlet Ball Valve 7. Outlet Ball Valve 8. Control (Glob) Valve 9. Valve for Header Relieves 10. Check Valve Gas RMS Bib-III 8"Ø x8"Ø 600RF 02 Nos. 8”x600RF 8”x600RF 8”x600RF ½” screwed ½” screwed 02 02 01 06 06 Lot Nos. Nos. No. No. No. 8"Ø x8"Ø 600RF 02 Nos. 8”x600RF 8”x600RF 8”x600RF 04 01 02 Nos. No. Nos. 02 06 06 02 Nos. No. No. No. 03 Lot No. 02 02 02 01 02 Nos. Nos. Nos. Nos. Nos. 04 03 01 01 02 Nos. Nos. No. Nos. Nos. ½” screwed ½” screwed 3/4” Ø / 1”Ø screwed 3/4” screwed 8”x600RF 6”x600RF 6”x600RF 2”x600RF 1”x600 Screwed 8”x600RF 10”x600RF 6”x600RF 2”x600RF 10”x600RF 165 11. Noise Silencer 12. Noise Silencer 13. Pressure Gauge(0-1500)psig 14. Purging Valve 15. Drain Valve/Valve in screwed relief 16. Temperature Indicator 17. Blind Flange for off take 18. Other required line pipe, elbow, tee, reducer, saddle, flanges/blind flanges, screwed Needle valves for pressure gauge and sensing line, stud-bolts, Thermo well, gasket, fittings, tubes-coupling and accessories as per design, drawing (P&ID, Regulating unit), specification, and schedule of requirement. st F. 1 Liquid 1. 85 MMSCFD Liquid Separator (Vertical Separator type ) at 500 psig operating pressure and (VME) other fittings, gasket, screwed needle valve, purging/drain valves and accessories as per design, drawing (P&ID, VME part) and specification and schedule of requirement. 2. Inlet & Outlet Ball Valve 3. Bypass Ball Valve 4. Pressure Gauge(0-500)psig 5. Purging Valve 6. Other required line pipe, relief valve, elbow, tee, flanges, gasket, stud-bolts, fittings and accessories as per design, drawing (P&ID, beyond VME), specification, and schedule of requirement. G. 2nd 1. Slam shut off Valve Regulating 2. Monitor Regulator Unit 3. Active Regulator 4. Header Relief 5. Runs Relief Gas RMS Bib-III 10”x600 10”x600 ½” screwed ½” screwed 1” screwed 3/4” screwed 10”x600RF 02 02 10 14 06 01 02 Lot Nos. Nos. Nos. Nos. Nos. No. No 10”x10”x 300RF 01 Nos. 10”x300RF 10”x300RF ½” screwed ½” screwed 02 01 02 02 Lot Nos. No. Nos. Nos. 02 02 02 01 02 Nos. Nos. Nos. No. Nos. 6. Inlet Ball Valve 7. Outlet Ball Valve 08”x300RF 6”x300RF 6”x300RF 2”x300RF 1”x300 Screwed 10”x300RF 14”x300RF 03 03 Nos. Nos. 8. Control (Globe) Valve 09. Valve for Header Relief 10. Check Valve 11. Noise Silencer 12. Noise Silencer 13. Pressure Gauge(0-600)psig 14. Purging Valve 15. Drain Valve/Valve in screwed relief 16. Temperature Transmitter(Digital) 6”x300RF 2”x300RF 14”x300RF 14”x300 14”x300 ½” screwed ½” screwed 1” screwed 3/4” screwed 01 01 02 02 02 10 14 08 01 No. No. Nos. Nos. Nos. Nos. Nos. Nos. No. 166 H. 2 nd Liquid Separator Unit I. Orifice Metering Unit 17. Other required line pipe, elbow, tee, reducer, saddle, flanges/blind flanges, screwed needle valves for pressure gauge and sensing line, stud-bolts, fittings, Thermo well gasket, tubes-couplings and accessories as per design, drawing (P&ID, regulating unit), specification, and schedule of requirement. 1. 85 MMSCFD Liquid Separator (at 150 psig to 320 psig operating pressure) and other fittings, gasket, gauges, screwed needle valve for pressure gauge, Purging/drain valves and accessories as per design, drawing (P&ID, VME part) and specification and schedule of requirement. 2. Inlet Ball Valve 3. Outlet Ball Valve 4. Pressure Gauge(0-500)psig 5. Purging Valve 6. Bypass Ball Valve 7. Ball Valve for off Take 8. Other required line pipe, relief valve, elbow, tee, flanges, screwed needle valve for pressure gauge, stud-bolts, fittings, gasket, and accessories as per design, drawing (P&ID, beyond VME), specification, and schedule of requirement. 1. 85 MMSCFD Senior Type (Dual Chamber) Orifice Meter at 150 psig to 320 psig operating pressure and other Flanges, fittings, gasket, tubes, straightening vane, screwed needle valve, stud-bolts and accessories as per design, drawing (P&ID, Orifice Meter part), specification and schedule of requirement. 2. Inlet & Outlet Ball Valve 3. Pressure Gauge(0-500)psig 4. Purging Valve 5. Purging Valve 6. Temperature Transmitter(Digital) 7. Pressure Transmitter(Digital) 8. Diff.Pressure Transmitter(Digital) 9. Regulator (Fisher-627) 10. Chart Recorder With three pens for Static pressure (0500psig), differential pressure (0-100”WC) and temperature (0-150 °F) record with thermo well and all accessories. 11. Plani meter with Turn table (Chart Drive) to read Chart Paper Gas RMS Bib-III Lot 14”x14”x 300RF 01 No. 14”x300RF 14”x300RF ½” screwed ½” screwed 14”x300RF 4”x300RF 01 01 02 02 01 01 Lot Nos. Nos. Nos. Nos. No. No. 16”x300RF 01 No. 16”x300RF ½” screwed ½” screwed 1” screwed 3/4” Ø / 1”Ø screwed 3/4” screwed 3/4” Ø / 1”Ø screwed 1” NPT 02 03 02 01 01 Nos. No. No. No. No. 02 03 No. No. 01 01 Nos. Set 01 Set 167 12. Other required line pipe ,stud-bolts, screwed needle valve for pressure gauge, gasket, Thermo well, fittings, cables and accessories as per design, drawing (P&ID, Orifice meter part), specification, and schedule of requirement. J. Flow 1.Flow Computer Computer (Microprocessor Based) Unit 2. Control Panel 3. Laptop Computer 4. Supervisory Computer 5. Online UPS 6. Voltage Stabilizer 7. Backup Battery 8. Printer 9. Other required fittings, cables, software, Manual, continuous printing sheet (50 pkts) and accessories as per design, specification and schedule of requirement. K. Gas 1. Gas Chromatograph Chromatogr (On Line, C 6+) Panel Mounted aph 2. Carrier Gas Lot 3. Calibration Gas 4. Other required fittings, cables, software, Manual and accessories as per design, specification and schedule of requirement. L. Station 1. Insulating Joint, W/N outlet 2. Station outlet Check Valve 3. Station Outlet Ball Valve 4. Pressure Gauge(0-500)psig 5. Purging Valve 6. Temperature Indicator 7. Other required line pipe, Tee, flanges/blind Flanges, screwed needle valve, gasket, thermo well, fittings and accessories as per design, drawing (P&ID, Station outlet Part), and schedule of requirement. M. 1. Condensate Storage Tank (Under Condensate grounded): Storage With Safety Relief, Counter Meter, Fire Tank Skid. Safety Valve, Flame arrestor, gauge, Level Gauge, gasket, Insulating flange/kit Cathotic Protection, fittings and accessories as per design, drawing (P&ID of Condensate Tank), and schedule of requirement. Gas RMS Bib-III 01 No. 01 01 01 01 01 01 01 Lot No. No. No. No. No. No. No. 01 No. 02 Cylin der Cylin der 02 Lot 16”x 300 Class 16”x 300 RF 16”x 300 RF ½” screwed ½” screwed 3/4” screwed 02 01 02 02 02 01 Lot No. No. No. No. No. No. 10,000 Liters 01 No. 168 Lot 3.Other required drain pipe, valves, flange, gasket, and accessories as per design, drawing (P&ID) and schedule of requirement. N. Interconnec ting Line pipe/ Materials. 1.16”Ø API L X52, ERW Sch /80 350 Meter 2. 8”Ø API L X52, ERW Sch /80 3. 1”Ø API L X52, Seamless Pipe (Drain Sch /80 line) 4. Other required line pipe, Tee, Elbow ,flanges/blind Flanges, screwed needle valve, gasket, thermo well, fittings, Wrapping Tape , Primer and accessories as per design, drawing (P&ID, Station outlet Part), and schedule of requirement. 200 250 Meter Meter Lot B. Schedule of Supplying & Construction of Control building and other civil, electrical, Mechanical works: Table-3 Item No 01 02 Description Quantity Unit Remarks Construction of Control Building: Design & construct a two stored control building cum office of 2500 sqft (each floor 1250 sqft) to 2500sq ft accommodate control panel equipments and office (1250sqft personnel for operation as per foundation drawing. x 2) Full civil construction with 3-phase electrical wiring, Furniture (cabinet, almirah, table, front chair, back chair, cot, bed, AC, ceiling fan, light, TV, kitchen accessories, etc), PABX system,Earthing system, Lightning arrester, Deep tube well with water pump motor 1 HP, Smoke detector. Earth Filling and Compaction Works: L.S Filling and developing of the land to formation level (same level of Bibiyana III power plant site). Earth shall be compacted in six inch layer with water sprinkling Gas RMS Bib-III 169 03 04 05 CC Walkway, Stone Pitching, Boundary Wall and Surface Drain: Supplier shall construct 1.5 meter wide walk ways across the RMS, around the Skid foundation and complete stone pitching in surface area and drain as per foundation drawing and instructed by EIC and according to schedule of requirement and technical specification Boundary Wall: Over 10 inch thick, 20 inch width cc foundation and at least 3 feet below ground level over a compacted WBM, boundary wall shall be at least 5 feet height and 5 inch from the finished ground level all around the RMS premises. On the top of brick wall there shall be 2 feet height fencing all around the boundary wall. Actual design shall be approved by EIC. Gates to be placed in the position shown in the drawing and to be approved by the EIC. Base foundation, RCC Pipe Supports Design and Construction of RCC foundation and pipe supports for installation of KOD, Filter Separators, Water Bath Heaters, Regulating skids, Liquid Separators (VMEs), Orifice Metering Skid, Condensate Tank and for other piping equipments (if required). The Supplier shall supply all the required materials for construction Works. L.S L.S Steel Structure Skids, Steel Structure Foot over bridges, Shade on Heaters & Metering Unit, L.S Painting, area lighting, Lightening Arrestor, Fencing, Guard Room and other as per Foundation drawing, schedule of requirement and Technical Specification. C. Schedule for Technology Transfer/Know-how from Manufacturer/Supplier Country for 4 (four) personnel [02 from BPDB, 02 from Jalalabad Gas]. Table-4 Item No Remarks Description Unit Quantity 01. Round Trip Air Tickets to Manufacture’s / Supplier’s/ Tenderer’s Country (ies). Person 04 02 Training Fees for Trainees. Person 04 03 Pocket Allowances for Trainees (for ten days). (Pocket allowance shall be reasonable and conforms to international standard) Person Day 04X10=40 Gas RMS Bib-III 170 04. Taxes, Medical, Insurance, Food & Accommodations and Transportation etc. 04 Person D. Schedule for Supplying of Auxiliary Facilities for Jalalabad Gas Personnel & Site office: Table-5 Item No Description Quantity 01. Vehicle: To provide 01(one) Vehicle (Latest Model) including full time driver and fuel & Oil for movement of Purchaser/Employer’s site personnel. Vehicle should be minimum 07(seven) 01(one) seater and high roof with AC. Vehicle shall be provided within one week from the date of LC opening and shall continue till issuance of PAC. 02 Office Furniture, Computer and others: Supply of 02 (two) executive table, 02 (two) executive chair, 06 (six) front chair, 02 (two) file cabinet, 01 (one) File rack, 01 (one) Drinking Water Filter, 02(Two) Office Almeria, 02 (Two) AC, Laptop, 2(two) Semi double cots with bed with well decorated room furniture, one Tea set and kitchen accessories etc. Office furniture should be of high quality standard preferably local Otobi brand. One latest model desktop computer, one computer table, one Scanner and a laser printer, UPS for Office used to be supplied. Furniture and computer shall be provided /supplied within 300 days from the date of LC opening. Remarks Lot Supply of 03 (three) post-paid/ Prepaid mobile phone (Latest model) & 03 (three) Laptop computers (Latest model), 03 sets of safety equipment, 03 carrying bag for site execution personnel (supervision committee) of the Purchaser/Employer. Handsets should be of high quality. Mobile Phone shall be provided within two weeks from the date of LC opening and the Supplier/Contractor shall continue to pay the bill till issuance of PAC. Gas RMS Bib-III 171 E. Qualification requirement of Tenderer/ Equipment Supplier /Vendor/ Sub Contractor: 1. Qualification of Supplier/Vendor/Manuf acturer 1 2.Qualification requirement of Tenderer. 1 Table-6 Supplier should have valid relevant ISO and API certificate. Supplier must supply different Test certificate, Quality certificate, Technical operation & maintenance manual, Demo copy etc. of all materials & equipments. (a)The Tenderer shall have minimum ten (10) years of overall experience in Design, Supply, Installation/ Fabrication/ Construction, Testing and Commissioning of Skid Mounted Gas Regulating and Metering station on Turnkey basis; and (b)The Tenderer shall have proven experience in Detail Engineering, Design, Installation/ Fabrication/ Fabrication/ Construction, Testing and Commissioning of at least 02 (two) such CMS/RMS of minimum capacity of 50(fifty) MMCFD on Turnkey basis during last ten (10) years ; out of which at least 1 (one) CMS/RMS shall be in other than the home country of the Tenderer. (c) Bidders may form joint venture/ consortium/ Association (JCVA) to enhance their qualification. At least one of the members of the JVCA shall have qualification mentioned above in (a) and (b) Other members shall have Construction/ Fabrication work experience of minimum 40 MMCFD Gas CMS/RMS within last 7 years. Any member of qualified JVCA or any authorized local agent can purchase the bid document. Properly notarized version of all pertinent documents regarding change of name of any bidder or bidder inherited qualification from an acquired organization shall be submitted with the technical offer. Tenderers shall submit the documentary evidences i.e. copies of certificates obtained from the clients/end users evidencing satisfactory completion of such CMS/RMS on turnkey basis in favour of its specific experience. The certificates shall contain name of the major equipments/plants installed in the station, station capacity (MMSCFD), pressure designations, and year of completion, name and address (with Telephone, FAX & E-mail) of the clients. ] The certificate shall be in the official pad of the employers containing its full address. Gas RMS Bib-III 172 F. Others Requirements: Table-7 Item. sl . 1. UPS & VS 1 2. Lighting 1 2 1 2 3. Protection 3 4 5 6 4. Local site Training and Supervision. 1 2 Description Country of Origin UPS & VS for FC, GC, WBH, Transmitter etc. Area lighting (Explosion proof) Lighting for WBH (Explosion proof) Cathodic Protection Earthing system for RMS Lightning arrester for control building Fire Extinguishers for RMS Fire hydrant Methane detector Local site training at RMS site for 15 officials & 07 days (with entertainments, carrying bag, pen drive, training material) during station commissioning. During site supervision/construction entertainment should be provided. Remarks. Bangladesh/ China Good Quality Good Quality Good Quality Good Quality Good Quality Good Quality Good Quality Good Quality --- ---- 5. Work completion time 1 300 days --- 6.Warranty 1 Two year warranty period with maintenance (By Tenderer). ---- N.B. After completion of the whole work, remaining materials, if any, shall be handed over to Jalalabad Gas T & D System Ltd. G. Vendor List: Table-8 Tenderer shall follow the Vendor list as mentioned bellow: [Note: The equipments offered must fulfil the requirements and specifications of the Tender Documents and mere compliance with the list shall not be treated as the basis for technical responsiveness. Moreover, vendor list of some equipments are short listed for most users friendly to the Purchaser’s/Employer’s personnel] a. Filter Separator / Liquid Separator (VME ) / Knock Out Drum(KOD) : Forain Spa , Italy PECO . USA Premabergo ltd . UK/Italy /USA Smith Industries Inc , USA/Italy Otto Klein , Germany Kings Tool , USA RMG Gmbh , Germany Siteco , Italy Tormene Spa Italy Gas RMS Bib-III 173 Pietro Fiorentini Spa, Italy Instromet International, Belgium. GTS Thielmann Energietechnik Gmbh , Germany Nuovo pignone SpA , Italy . Valvatalia S.P.A –System Division WAGA Warme Gastechnik, GmbH RMG, GmbH b. Water Bath Gas Heater : Forain SpA. Italy Premabergo ltd . uk/Italy/USA Smith Indus tries Inc . USA GTS Thelemann Engergietechnik Gmbh , Germany Tormene spa . Italy Pietro Fiorentini SpA , Italy King Tools ,USA Otto Klein , Germany . GTS,USA Valvatalia S.P.A –System Division WAGA Warme Gastechnik , GmbH RMG, GmbH c. Orifice Meter : Instromet, USA/BELGIUM Actaris Metering Systems,Germany/Singapore. Daniel Flow Indusries/Products,Inc., USA/ Emerson Process Management PECO, USA. Canalta, Antec Singapore/Canada RMG MeBtechnik GmbH, Germany Equimeter Inc.,USA TMCo Inc. USA TMCO, Canada Schlumberger, Germany/France Valvatalia S.P.A –System Division WAGA Warme Gastechnik , GmbH RMG, GmbH d. Flow Computer : Omni Inc , USA Daniel Industries Inc , USA /Emerson Process Management Spetro -Teck , UK Solartron, UK Instromet, Belgium / Netherlands / UK Pietro Fiorentini SpA , Italy Schlumberger srl, France . OMT Tartarini SpA , Italy RMG Gmbh , Germany Yokogawa Engineering Asia Pte. Ltd, Japan ABB USA/UK/Italy/Germany Valvatalia S.P.A –System Division e. Transmitters : Gas RMS Bib-III 174 Fisher Rosemount USA/Singapore/ Emerson Process Management ABB Kent UK/Italy/Germany Honeywell UK/USA/Singapore ITT Barton Inc , USA Bestobel , Germany Robert Shaw, USA OMT Tartarini SpA Italy Yokogawa, Japan /USA CVS Controls, Canada Valvatalia S.P.A –System Division WAGA Warme Gastechnik, GmbH RMG, GmbH f. Recorders Foxboro, USA. Barton, USA/Canada OGME, USA g. Ball Valves/ Check (Non Return) Valve Perar SpA, Italy Audco Valves , Germany /UK Grove Italia, Italy Cameron, USA/UK Argus Gmbh, Germany Tormene SpA, Italy Pietro Fiorentini SpA , Italy Flow control Technologies , France Raimondi SpA, Italy Kitamura Valves, Japan OMB Spa Italy Zug Gazomet SP Z.O.O, Germany Nuovo Pignone SpA , Italy Borsig, Italy Crane, UK Hinddle-Cockburn,UK SMC, France WKM, Japan Valvatalia S.P.A –System Division WAGA Warme Gastechnik, GmbH RMG, GmbH h. Plug Valves : Nordstorm Valves, USA BRDR Christensen Haner, Denmark Audco Valves, UK/Germany WAGA Warme Gastechnik, GmbH RMG, GmbH i. Pressure Regulators & Relief Valves : Axial Flow Valve, AMCO, USA. Emerson Process Mangement, USA Pietro Fiorentini, Italy WAGA Warme Gastechnik (RMG), GmbH Gas RMS Bib-III 175 RMG, Germany. Gorter Controls, Germany Tormene Spa Italy j. SLAM SHUT-OFF VALVES Francel, Emerson Process Management, France/USA. Tormene SjpA, Italy Schlumberger srl, France RMG GmbH, Germany Tartarini SpA Italy Instromet , Belgium / Netherlands Pietro Fiorentini SpA , Italy CVS Controls, Canada Nuvo Pignone SpA , Italy Gorter Control. Schoonsoven, The Netherlands /Germany Valvatalia S.P.A –System Division WAGA Warme Gastechnik, GmbH RMG, GmbH k. Pressure gauge Wika, Germany Swage Lok, USA Nuova Fima, Italy Ettore Cella, Itally Scrast, Germany Burdenbery, UK Stewart-Bnchna, UK l. Temperature gauge/ Thermometer Wika, Germany Swage Lok, USA Nuova Fima, Italy Ettore Cella, Itally Scrast, Germany Burdenbery, UK Stewart-Bnchna, UK m. Screwed Ball/ Needle Valve/Fitting Hy-Lok, Korea Kerotest, USA SMC, USA/France Sapj, France n. Insulating Joint Nuovagiungs, Italy Zunt Italyana, Italy o. Gas Chromatograph Omni Inc. USA Daniel Industries Inc. USA/ Emerson Process Management Spetro –Tech, UK Gas RMS Bib-III 176 Solarton, UK Instromet, Belgium/ Netherlands/ UK Pietro Forentini SpA, Italy Schlumberger srl, France OMT Tartarini SpA, Italy RMG GmbH, Germany Yokogawa Engineering Asia Pte. Ltd, Japan ABB USA/UK/Italy/Germany Valvatalia S.P.A –System Division H. Mandatory Spare Parts , Tools and other required Material for two years operational Purpose of the RMS (After warranty period) Following are the minimum requirements of Spare parts and materials to be supplied for operation and maintenance of Equipments, Instruments, Auxiliaries, and Accessories etc. supplied against RMS at Bibiyana-III, 400MW Combined Cycle Power Plant ,Habiganj. The supplier/ Tenderer shall have to incorporate item(s) or increase quantity (ies) of Spare parts if required as per requirements for the equipment stated in this tender, Section 7: Technical Specifications and Section 9: Drawings. Table-9 SL No Equipment Name Description of Spare parts Unit Quantity of Spare kits of ESD No 05 Remarks Spare Parts INLET UNIT 1. ESD 2. PT (Pressure Transmitter) Set No 02 Resistance detector (RTD) Set No 04 3. temperature 4. Temperature Gauge (0-150º F) Set No 06 5. Pressure Gauge(0-1500 psig) Set No 12 6. Pressure Gauge (0- 500 psig) Set No 12 Filter cartridge No 80 No 24 Filter Separator Unit 7. Filter Element Separator for Filter 8. O-ring for Filter separator 9. Differential Pressure Transmitter Set No 02 10. Auto discharge drain valve Set No 08 11. Safety valve Body Repair kits for Safety valve. No 04 Heater unit Gas RMS Bib-III 177 12. Slam Shut for Heater RMS Body Repair kits. No 15 13. Regulator for Heater RMS Body & Pilo t Repair kits for Regulator No 20 14. Main Burner for WBH complete set No 02 15. Pilot Burner for WBH complete set No 02 16. Main Burner nozzles complete set No 08 17. Pilot Burner nozzles complete set No 12 18. High Pressure switch Set No 04 19. Low Pressure switch Set No 04 20. Temperature switch Set No 04 21. Temperature controller Set No 04 22. Level switch Set No 02 23. Power supply unit Set No 08 24. PLC Set Set 02 Set No 04 25. Resistance detector temperature 26. Ignition Transformer Set No 04 27. Ignition Electrode Set No 04 Solenoid valve complete set for main Burner & Pilot Burner Set No 16 29. Damper motor Set No 01 30. Blower motor Set No 01 31. Flame amplifier set No 04 32. Flame detector Set No 04 33. Ionization Rod Set No 06 34. Relays set Set No 40 35. Pressure Gauge(0-100) bars set No 04 36. Pressure Gauge(0-2.5) bars Set No 04 37. Fuses (Glass & cartridge type) Set No 30 28. Regulation Unit Gas RMS Bib-III 178 38. Slam Shut Valve 8”x600RF 39. 40. 41. 42. Slam Shut Valve Repair kits. No 30 Monitor Regulator 6”x600RF Body Repair kits for Regulator. No 40 Active Regulator 6”x600RF Body Repair kits for Regulator. No 40 Pilot for Monitor 6”x600RF Regulator Pilot Repair kits for Regulator. No 50 Pilot for 6”x600RF Regulator Pilot Repair kits for Regulator. No 50 Slam Shut Valve Repair kits. No 30 Active 43. Slam Shut Valve 8”x300RF 44. Monitor Regulator 6”x300RF Body Repair kits for Regulator. No 40 45. Active Regulator 6”x300RF Body Repair kits for Regulator. No 40 46. 47. Pilot for Monitor 6”x300RF Regulator Pilot Repair kits for Regulator. No 50 Pilot for 6”x300RF Regulator Pilot Repair kits for Regulator. No 50 Body Repair kits for Safety valve. No 25 Body & Pilot Repair kits for Safety valve. No 20 Set No 02 Box (100pcs) Box 50 Set No 02 Set Set 50 Arm Set No 25 Orifice Plate & oring of different size to meet demand (25%, 50%, 75% capacity). Set No 06 PT (Pressure Transmitter) Set No 02 DPT (Differential Transmitter ) Set No 03 Active 48. Run Relief Safety valve 49. Common Header Safety valve Metering unit 50. Plani meter with Turn table 51. Chart papers 52. Mechanical chart drive 53. 54. 55. 56. 57. Spare Chart Pen Different Color) ( Three Spare Chart Pen ( Three Different Color) Pressure 58. Temperature Transmitter Set No 02 59. Thermometer ºC Set No 12 Gas RMS Bib-III 179 60. Thermometer ºF 61. Regulator (1” NPT, Fisher-627) 62. Body & Pilot Spare kits Regulator (1” NPT, Fisher-627) Set No 12 Set No 01 Set No 10 Gas chromatograph 63. Power supply unit Set No 04 64. I/O cards Set No 02 65. Mother board Set No 01 66. Software for GC Set Set 01 67. Calibration Gas Cylinder No 08 68. Carrier Gas Cylinder No 08 69. Sample gas regulator Set No 02 Flow Computer 70. Power supply unit Set No 04 71. I/O cards Set No 02 72. Mother board Set No 01 73. Software for FC Set Set 01 Laptop (Software & data upload & down load) Set No 01 Printer with scanner Set No 01 Desktop computer with UPS & printer Set No 01 Condensate motor, 1HP Set No 01 Met er 50 74. 75. 76. 77. 78. removal pump 1”Ø Hose Pipe SPARE PRESSURE GAUGE 79. (0-1500) Psig range Set No 12 80. (0-1000) Psig range Set No 12 81. (0-500) Psig range Set No 12 FC/Heater PANEL Gas RMS Bib-III 180 82. Safety barriers Set No 06 83. Lightning barriers for Panel Set No 06 Set of indication lamps (LED) & holder Set No 25 85. Set of Switches Set No 25 86. Relay Set No 25 Circuit breaker (different size & amp) Set No 25 Panel Display Set No 04 Magnetic contractor with thermal relay Set No 04 Spare parts-kit for the auto discharge system (level control valve) Set No 25 Spare parts-kit for the Vessel Safety Relief Valve Set No 25 84. 87. 88. 89. KOD, Filter separator & Separator: 90. 91. Gas RMS Bib-III Liquid 181 Table -10 Maintenance Tools Unit Quantity Special tools for opening Filter separator Set 02 Special tools for maintenance regulator Set 02 Lever and chain for maintenance regulator Set 02 Ratchet set box with tools Set 02 Adjustable Slide Wrench 12Pcs different size (06”– 48”) Set 02 Pipe wrench 05 Pcs different size (12” – 48”) Set 02 7. Ring Wrench 18Pcs different size (6 – 62 mm) Set 02 8. Dally Wrench 18Pcs different size (6 – 62 mm) Set 02 Allen Key set ( 13 pcs of different size in Inch) Allen Key set ( 13 pcs of different size in mm) Wooden Hammer 1lb Wooden Hammer 2lb Monkey Ring Wrench ( 3 pcs of different size in mm) Nose Pliers ( 6 pcs of different size ) Pliers ( 6 pcs of different size ) Screw driver(Flat) 6 pcs of different size Screw driver(Star) 6 pcs of different size Screw ( Combination) Driver set ( 10 pcs of different size ) Ratchet wrench flange separator (06 pcs for different size) Tool Box ( For Carrying varies types of tools) Flat file 4 pcs of different size (06” – 12”) Round file 4 pcs of different size (06” – 12”) Tapper file 4 pcs of different size (06” – 12”) Half round file different size (06” – 12”) Grease Gun (High & low pressure) latest model Steel tape (100 feet) Hacksaw frame with blade Tube cutter Tube bender Digital Multi Meter Remote methane leak detection Hax key set (1.5mm-12mm) Portable BTU gas analyzer Digital Sound Level Measurement Equipment (Unit db) Hydraulic Dead weight tester (For Static pressure) Hand pump Pneumatic Dead weight tester (For DP) Clamp Meter Multi plug (cable length-50 meter) Soldering iron with voltage regulator Hart communicator Fire extinguisher safety Shoes Ear protector Helmet safety Glass Hand Gloves First Aid Box Ladder (steel structure) Set Set no no Set Set Set Set Set Set set Set Set Set Set Set Set Set Set Set Set Set Set Set Set Set Set Set Set Set Set Set No Pair Set No No No No No 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 02 01 02 01 01 02 02 02 01 12 12 12 12 12 12 02 02 SL No 1. 2. 3. 4. 5. 6. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 30. 31. 32. 33. 34. 35. 36. 37. 38. 39. 40. 41. 42. 43. 44. 45. 46. 47. 48. Gas RMS Bib-III 182 J. Recommended Spare and Tools (Including Calibration Equipments) for start up & commissioning of the RMS Items and tools required for start up and commissioning of RMS will be mention here and shall be supplied during testing & commissioning of the RMS. Left-over materials should be returned to JG store. Table-11 Item Description Quantity Remarks No A INLET FILTER SEPARATOR B HEATERS C PRESSURE REGULATORS D PRESSURE RELIEF VALVES E SLAM SHUT OFF VALVE F ORIFICE METER G ONLINE GAS CHROMATOGRAPH H FIELD INSTRUMENT I CONTROL PANEL J FLOW COMPUTER K CONDENSATE TANK L ORIFICE METER CHART RECORDER M STATION MAINTENANCE TOOLS N UPS/DC PANEL Gas RMS Bib-III 183 O CALIBRATION EQUIPMENTS P OTHERS K. List of Related Works and Services to be provided. Works and services which are required to fulfilment under this tender are listed bellow as per Item No 01. Description of Works Detailed Engineering, Design, Drawing & Documentation considering and confirming all requirements stated in this tender, Section 6,7,8 and 9.. 02. Technology Transfer/Know-how for 4 personnel (2 from BPDB 2 from Jalalabad Gas) for Manpower Development (Foreign Training) at Contractor’s/ Manufacturer’s (Home Office) plant. 03. Clearing & Forwarding, Port authority, Handling, Local Transportation, Loading and unloading charges. 04 Fabrication, assembly, installation, erection for Bibiyana-III, 400MW Combined Cycle Power Plant RMS ,Habiganj, and interconnecting pipeline considering and confirming all requirements stated in this Section, Section 6,7,8 and 9 at site. 05 Testing, Commissioning and Test run operation of the Equipments supplied by the Tenderer /Supplier considering and confirming all requirements stated in this Section. Section 6,7,8 and 9 and site/local training. 06 Design, Supply & construction of Control building, Boundary Wall and other civil, electrical, Mechanical works considering and confirming all requirements stated in this Section, Section 6,7,8 and 9. 07 Supplying of Auxiliaries & Facilities (including entertainment) for Purchaser’s/ Employer’s Personnel /Site office. 08 Fulfilment of Specification Submission Sheet and Price schedule for Recommended spare part and tools to be valid up to end of two years contract period effective from the expire date of warranty period Gas RMS Bib-III 184 L. Description of Related works and Services to be performed/provided 1.0 A brief description of Related Works and Services to be provided by the Supplier are described here as follows: a. In general , works under this IFIT are to Supply a skid mounted Gas Regulating and Metering Station (RMS) on turn-key basis Comprising of b. c. d. e. f. g. h. One Knock-out drum unit, Two Filter separator units, Two Water Bath Heater units, 1st stage regulating units, 02 (two) regulating runs & 01 (one) bypass run 2nd stage regulating unit, 2 (two) regulating runs & 01 (one) bypass run Two Liquid Separators (VME) units (One after 1 st stage regulation and another one after 2nd stage regulation), Orifice Meter unit with Flow Computer, Gas Chromatograph & Three Pen Chart Recorder and Inter connecting Pipeline. b. The Supplier/ Tenderer shall provide all materials, labour, equipment, tools, services and goods required to carry out the works including civil foundation, RCC pipe supports, steel structure skids, stairs, fence, shed for metering and heater unit, area lighting, Lightening Arrestor, water pipe line for proposed heaters from Bibiyana-III, 400MW Combined Cycle Power Plant RMS ,Habiganj etc as described herein. c. Installation, Fabrication, Testing , Commissioning & Test run Operation works shall be carried out at site under direct supervision of Purchaser’s/Employer’s Engineers. 1.1 Steel Structure Skids: Steel structure skids shall be constructed for KOD, Filter Separator Units, Heating Units, 1st stage- regulating unit, 2n d stage regulating unit, metering unit, Liquid Separators , and for other equipments (if required). The Supplier/Contractor shall supply all the required materials for the skids. Gas RMS Bib-III 185 1.2 Civil Construction: (a) Control/Office Building The Supplier/ Tenderer shall design, draw & construct a two storied control building cum office of 2500sq ft (each floor 1250 Sqft) to accommodate control panel equipments and office personnel for operation. The building shall have plinth area as shown in the typical drawing no: JG/ Bibiyana-3, 400MW Combined Cycle Power Plant RMS ,Habiganj (foundation and others). All the windows shall have glazed aluminium frame, sliding tinted glass, mosquito net and Venetian blind curtains and MS grilling for protection. All the stairs and corridor shall be Stainless steel supported railing. Floor shall be covered with homogenous (450 × 450 mm) type finished tiles. Toilets shall have tiles in the walls with garzan wooden frame and solid wood (Gamari) shutter in all the doors. Every room shall have ceiling fan with 56” blade with modern lighting arrangement and eight securities light outside the building. Control room & office room will also have a 2- ton AC (two) with antibugler caging. Ground floor shall be RCC. The building will be framed structure type and each footing will be on at least four numbers of 20’ long pre-cast piles if soil test does not require more. If soil test suggests deep foundation then cast-in-situ pile should be provided according to the soil test report recommendation. Internal walls shall be plastic painted and external wall surface shall have weather protection coating supplied from Berger/Equivalent. Roof shall have at least 4” thick lime terracing coverage with two coat roofing compound supplied from Berger/Equivalent. Other details shall be maintained according to PWD standard. The control building will be facilitated with GI waterline providing installation of submergible pump at proper level. The supplier shall provide one food grade water tank with capacity not less than one thousand litre. The supplier/contractor will construct at least 15 ft wide RCC road connecting gate to the control building and RMS. The road will be constructed over two feet deep WBM compacted with water sprinkling and rolled by sheep foot roller machine with high tonnage. (b) Earth Filling and Compaction Works Filling and developing of the land to formation level (same level of Bibiyana -III power plant site).To provide carted earth to develop the appx. 4000sq feet (285’ x 145’) land for max. 1 meter height on which RMS will be erected. Earth shall be compacted in six inch layer with water sprinkling by roller machine with high tonnage to prevent settling. (c) Base foundation Construction of Civil foundation is required for installations of Knock-Out-Drum (KOD), Filter Separator Skids, regulating skids, Single stage Liquid Separators (VMEs), Condensate Tank, Metering Skid, Water Bath Heater skids and for other equipments (if required) as described in Section.7: Technical Specifications. and drawing noJG/ Bibiyana-3, 400MW Combined Cycle Power Plant RMS ,Habiganj (foundation and others). The Supplier/Contractor shall supply all the required materials for the Civil Foundations. (d) Pipe Supports with RCC Base Sufficient number of pipe supports with RCC Base shall be constructed for supporting pipe works as described in Section 7: Technical Specifications and as per drawing no.-JG/ Bibiyana-3, 400MW Combined Cycle Power Plant RMS ,Habiganj .The Supplier/Contractor shall supply all the required materials for the construction of RCC pipe supports. Gas RMS Bib-III 186 1.3 (e) Guard Room The Supplier/ Tenderer shall construct one guard room of 6 ftx6 ft (36sq ft, approx.) for guard personnel of the RMS. The Supplier/Contractor shall supply all the required materials (light, fan, auxiliary support) for the construction of Guard Room. Fittings and other specifications shall be according to control building. (f) Boundary Wall: Boundary wall shall be constructed with RCC frames including foundation, column, Grade beam and top beam/copping. Foundation should be placed at least four feet below EGL, over 24 inch thick WBM 3 inch brick soling and CC work each. Boundary wall shall be at least five feet high and five inch from FGL all around the RMS premises. On the top of brick wall there shall be two feet high grill fencing all around the brick wall. Gates are to be placed in the position approved by EIC. Grill, fencing and gates are to be painted with two coats of enamel paint over a coat of red-oxide. Boundary wall should be coloured with two coats of weather coat on both sides. Painting: All the equipments, Valves, Heaters, VME, Filter Separators, Orifice Meter, Regulators, Pipe Spool, interconnecting pipe, Fittings etc of Bibiyana 3, 400 MW CCPP RMS shall be painted with standard applicable paint by the Supplier/Contractor. The painting works cover all the materials from the station Inlet to Outlet of the RMS. The colours of top coats for painting in accordance with the specification shall be as follows :01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 Inlet valves of all units Bypass valves Sensing/impulse valves Drain valves Vent valves Outlet valves of all units Regulators/meters Skid Gas Pipe Lines Instrument air pipe Lines Vessels (KOD/FS/ VME) Vessels (Scrubber/heater) Condensate drain line Relief Valve/ESD Valve Orifice Meter Pig launcer/receiver : Postal Red : Postal Red : Postal Red : Navy Blue : Postal Red : Navy Blue : Grey : Black : Aluminum : Cobalt Blue : Aluminum : Aluminum : Dark Grey : Post Office Red : Grey : Aluminum The painting of completely factory-assembled units of any equipment shall be completed prior to shipment. 1.4 Steel Structure Foot over bridges: Standard Steel Structure Foot over bridges should be constructed as not less shown given in drawing over pipe and installations as required for free movement of personnel for the purpose of operation and Maintenance. The Supplier/Contractor shall supply all the required materials for the construction of Foot over bridges. 1.5 Fencing: Wire mesh net fence required to be constructed as per drawing by the Supplier/Contractor around the RMS as per requirement and instruction given by the Purchaser’s/Employer’s engineer supplying 12 BWG wire fence, M.S. angle, F.I. bar etc,. Gas RMS Bib-III 187 1.6 Shed For Metering Unit: A ndard shed shall be constructed for orifice meter in order to protect it fr weather. The Supplier/Contractor shall supply all the required materials for the construction of shed and shall take prior approval before erection. 1.7 Area Lighting Arrangement: The Supplier/Contractor should provide proper area lighting arrangement for the RMS. Lighting system should be explosion-prove and suitable for hazardous areas. Lighting fixtures should be mounted on a pole above the ground at suitable height for proper illuminations. Quantity defined by the Purchaser/Employer will be the final requirement. 1.8 Lightning Arrestor and Equipment Grounding The Supplier/Contractor should provide a proper thunder protection Lightning Arrestor for the RMS. Lightning arrestor should be mounted on a pole above the ground at suitable height for proper thunder elimination. All the equipments shall need to be properly grounded as per standard. Lightning arrestor and others shall be supplied by Tenderer 1.9 Water Pipeline for Heaters: The Supplier/Contractor shall supply all the required materials and construct water pipeline from Bibiyana-III, 400MW Combined Cycle Power Plant RMS ,Habiganj water treatment plant to the RMS for supplying water to the proposed Water Bath Heater. The length of the water pipeline may be approximately 150 meter. It is to be noted that if water supply is not available from the water treatment plant of Bibiyana-III, 400MW Combined Cycle Power Plant RMS ,Habiganj before commissioning of the Water Bath Heater, the Supplier shall arrange demy water for commissioning of heater at his own cost in addition to laying required water pipe line for regular use. 1.10 Shade for Heater: A standard shed needs to be constructed at the front-end of proposed Water Bath Heater for convenient operation and maintenance purpose during rough weather. All the materials shall be supplied by the Supplier/Contractor and shall take prior approval before erection. The shade will be constructed over steel frame angle/pipe post with corrugated iron sheet (thickness not less than 0.42 mm) coloured/non-coloured as per approval of EIC. 1.11 CC Walkway, Stone Pitching and Surface Drain: Supplier shall construct at least one meter wide Walk ways across the RMS as per drawing, instructed by EIC and shall have at least 12” depth sand filling, 12” depth compacted soil, 8” WBM and on top of it shall be covered with ceramic bricks/pavers. Walk-ways shall be at least 8” high from surrounding ground level and maintains 1:1 slope at the edges. Moreover, Supplier shall construct at least one (01) meter wide CC walkway to facilitate the movement of Employer’s Personnel to each units/skids of the RMS (KOD, Filter Separator, Water Bath Heater, Pressure Regulating units, Liquid Separator units, Orifice Meter, etc). The Supplier/Contractor shall construct at least 1 (one) meter walkway around all skids/units beyond the original RCC structures/foundations to facilitate the maintenance works. The Supplier shall also do stone pitching all over the ground inside the RMS area as per standard and good civil engineering practice. The supplier shall construct surface drain around the RMS of width 10”, height 12” with RCC floor to facilitate drainage of rain water and liquid wastage. The Supplier/Contractor shall supply all the required materials for the above construction works. Gas RMS Bib-III 188 1.12 Installation of Condensate Tank: Tank shall be installed with cathodic Protection System bellow base level of RMS and one layer RCC Slab shall be constructed above tank. All accessories and interconnecting condensate line shall be connected with tank with insulating kit and RF ball Valve. 1.12 Construction of interconnecting pipeline and Tie-in /Hook up works: a) 8”x1000 Pipeline interconnection between existing 8”x1000 psig pipeline and RMS inlet shall need be constructed with proper pipe support and tie-in work arranging all safety precaution and others. b) Pipeline interconnection between 16”x150 psig pipeline and RMS outlet shall need be constructed with proper pipe support and tie-in work arranging all safety precaution and others. 2.0 Front end Engineering Design and Detail Design: 2.1 General: Front end engineering and detail design of the RMS shall be in accordance with the Tender Documents and shall include but not limited to: • Reviewing and verifying preliminary engineering; • Perform additional engineering required to complete the design; • Prepare construction drawings; • Prepare bill of material; • Prepare specifications, material, equipment construction etc. and other technical documents; • Complete “as built” drawing. Within 6 (six) weeks after award of Contract, the Supplier/ Tenderer shall forward for the RMS detailed scope of work for the Purchaser/Employer including: Detail design drawing of Office/Control Building, Steel structure skids drawing ; Civil foundation detail drawing, RCC pipe support drawing Skid /Package dimensions; Skid /Package weights; Estimated manpower and qualification; Time schedule for fabrication, construction, erection, Installation, Precommissioning, Commissioning, Test run operation and Training. Gas RMS Bib-III 189 2.2 Feed: For the front-end engineering design the following issues, drawings, specifications etc. shall be prepared as a minimum requirement. Supplier/Contractor shall obtain approval from Purchaser/ Employer for items to be executed during front end engineering design phase: Design basis; Control and operating philosophy; Piping & instrumentation diagrams (P& ID s); Line list, process conditions; 2.3 Detail Design: For the detail design the following issues, drawings and specifications shall be prepared as a minimum requirement. a. General: Electrical goods list; Control valve data sheets; Instruments list; Material safety data sheets; Instrument data sheets; Operation and maintenance manuals. Final documents shall be assembled in book form and shall be issued containing the following: Document schedule; Drawings material take-off; Calculations; Specifications. Operation and maintenance manuals. b Civil /Structural Engineering: The following drawings, specifications etc. shall be prepared as a minimum: Design & Drawing of a two storied control Building. Equipment plot plans; Pipe support details; Gas RMS Bib-III 190 RCC foundations details; Standard details; Steel Structure; Skid drawings Site security drawings (fencing etc.) c Mechanical / Piping Engineering: The following drawings, specifications etc. shall be prepared as a minimum: Piping and instrumentation diagrams (final); Line lists; Data sheets; Material take-off Specifications, drawings and design calculations of vessels; Plans, sections and details; Isometric drawings (where needed); Stress analysis calculations. Acoustic calculations Standard details d Electrical and Instrumentation Engineering: The following drawings, specifications etc. shall be prepared as a minimum: Gas RMS Bib-III • Data sheets and specifications (final); • Loop diagrams; • Standards, installation and hook-up drawings; • Instrument index; • Electrical single line drawings; • Electrical plot plan and lighting plan drawings; • Panel design and layout of control room; • Switch gear / distribution panel drawings; • Cable and conduit schedules; 191 3.0 • Grounding and lighting protection system; • Electrical equipment specifications; • • Pre-commissioning checks of all instruments and electrical equipment; Wiring diagrams; • Safety and function evaluation charts for API RP14C. Procurement. The Supplier/Contractor shall be responsible for procurement of all materials, equipment, start-up and commissioning tools & spares, mandatory tools, calibration equipment and spare parts and subcontract services for packing, shipping and transportation of the same to the job site. Copies of all purchase Orders issued by the Supplier/Contractor to its Vendor(s)/ Manufacturer(s) must be forwarded to the Purchaser for its intimation. These responsibilities of the Supplier/Contractor shall include, but not be limited to the following procurement activities: 4.0 a. Prepare a Procurement Plan and issue to Purchaser/Employer for approval; b. Prepare the “master list” of imported materials and equipment and issue to government authority on behalf of Employer/ Purchaser; c Expedite delivery of materials and equipment and control delivery schedules; d Establish and maintain quality control, inspection procedures and schedules and ensure conformance of all purchased items to the established specifications including quality inspection and test witnessing; e Obtain all required documentation, drawings, manuals etc. Manufacturer(s)/Vendor(s) as required for job books and quality control; f Tools and spares for start-up and commissioning of the RMS; g Obtain mandatory tools, calibration equipment and spare parts for the RMS as required in the Tender Documents for supply to the Employer/Purchaser under the contract; h Obtain quotes for vendor representative to direct, assist and certify proper onsite equipment installation; i Prepare and issue status report to Employer/Purchaser on monthly basis from Fabrication and installation 4.1 The Supplier/Contractor /Tenderer shall be responsible for complete fabrication, installation, testing, commissioning and Test Run Operation of the facilities. The work shall be performed in accordance with the contract documents, including the approved construction drawings and specifications. 4.2 The Supplier/ Contractor/Tenderer shall complete the work in accordance with the construction schedule submitted in the proposal and approved by the Purchaser/ Employer. 4.3 A written status report prepared by the Contractor/Supplier detailing the work completed and the portion of the work forecasted to be completed shall be presented to the Purchaser/ Employer at regularly scheduled progress meetings. Gas RMS Bib-III 192 4.4 The Supplier/Contractor/Tenderer shall obtain and provide suitable transportation, living accommodation and catering for its (Supplier/Contractor) personnel. The Supplier/Contractor shall provide field offices, which include sufficient rooms. Facilities shall be furnished, adequately lighted. Furnishings, utilities and janitorial services shall be provided for the duration of the contract period. 4.5 The Supplier/Contractor/Tenderer shall obtain and provide insurance policy against it’s equipments/tools and manpower at his own responsibilities, security arrangements for the protection of its personnel and property during the contract period, all medical and sanitary facilities required for the health and the Supplier/Contractor shall provide welfare of the Supplier’s/Contractor’s personnel. In addition, the Supplier/ Contractor shall be responsible for the proper disposal of all liquid and solid wastages generated as a result of the construction operation. 4.6 During construction at site proper safety measures & precautions shall be taken by the Supplier/Contractor as per standard practice and safety rules. 4.7 The Supplier/Contractor will provide any additional sites required for Supplier/Contractor’s temporary field activities. 4.8 The Supplier/Contractor’s work shall include, but not be limited to the following construction and operations: Gas RMS Bib-III (a) Construct and maintain temporary access roads, if required, to facilitate passage of construction equipment and material transport; (b) Transport and store materials and equipment; (c) Construction and foundations of all civil works; (d) Prepare welding procedures and qualifications; (e) Prepare welding and piping book including isometric drawings; (f) Apply corrosion coating to welded joints; (g) Install liquid catchers, metering systems and associated piping, including supports and foundations and site fencing; (h) Install electrical cabling & all electrical fittings, gas piping; (i) Make tie-ins; (j) Paint above ground piping, equipment and facilities; (k) (l) Lifting the gas stations equipment on foundation, alignment and bolt down; Grouting of skids or supports with non shrinking grout; (m) Assembly of all interconnection piping; (n) Prepare station site; (o) Install instruments and prefabricated instrument piping; (p) Tightness test of the RMS; 193 (q) Acceptance test will be witnessed by Purchaser/Employer; (r) Final calibration and functional testing of instrumentation will be witnessed by Purchaser/Employer; (s) Water filling of heater (with demy water); (t) Preparation of purging with gas; (u) Provide all necessary equipment e.g. ear muffler, gas detectors, fire prevention and safety equipment cross over / cat walk ladders etc. tools and consumables in separate sets for the RMS as applicable for the maintenance and operation of the stations; (v) To carry out Test Run Operation. (w) Commissioning of the RMS; (x) Laying and termination of field cables; (y) Cabling between cabinets; (a’) Arrange supply of electric power from control room Premises including cabling and supply and installation of necessary equipment; (b’) Cabling between communication (telemetry and instrumentation panels); (c’) Install Earthing and grounding systems. (d’) Provide standard rubber/ insulation materials/sheets to avoid metal-tometal contact between pipe and skids / pipe and pipe supports. (e’) 5.0 To make Tie-in of the station outlet with internal pipeline of Bibiyana-III, 400MW Combined Cycle Power Plant RMS ,Habiganj Miscellaneous: The Supplier/Contractor shall be responsible for the following: 5.1 Supply of mandatory spare parts of relevant manufacturers for the equipment included in the RMS and other materials as per (Table-9). 5.2 Supply of auxiliaries & facilities (including entertainment) for Purchaser’s/ Employer’s site office and personnel as per (Table-5). 5.3 Provide site training for at least 15 (fifteen) personnel of Purchaser/Employer for minimum 7 (seven) days during testing and commissioning of the RMS/ equipments on the operation and maintenance of all sections/equipments of the RMS. The site training shall facilitate theoretical and field training. Training includes manuals/materials. 5.4 Arrange and carry out a training program (Table- 4) for 4 (four) personnel of Purchaser/Employer for ten days (10 days) at supplier’s / manufacturer’s plant. Supplier/Contractor shall provide details of training courses available for maintenance personnel. The courses shall be based around the full servicing and programming of the flow computer, meter, regulator, heater, liquid separator, equipment and instrumentations etc. Training courses shall be available preferably prior to Factory acceptance Tests of Water Bath Heater. Gas RMS Bib-III 194 5.5 5.6 5.7 Provide all necessary tools, spare parts and consumables for start-up, commissioning and Test run operation of the RMS/ all equipments supplied by the Supplier/contractor (Table-9, Table-10, Table-11). Provide 6 (six) copies of the materials and parts list along with catalogues and other publications containing description, materials specifications and drawings, part reference number and other identification adequate for reordering purposes, pertaining to spare parts manufactured or distributed by the Supplier/Contractor or its Suppliers at least 30 (thirty) days before initial commissioning of the RMS. Transportation facilities (24 hours) with entertainments for supervision committee (From work starting to station handover). Mobile, Laptop, safety equipment, carrying bag for supervision committee – 06 (six) sets. Local site training at RMS site for 15 officials & 07 days (with entertainments, carrying bag, pen drive, training material) during station commissioning. Foreign training in Manufacturer(s)/Supplier(s)/Tenderer Country(s) for 4 concerned officials & 10 days with round trip, food and accommodation, pocket allowance, taxes, medical insurance, transportation etc. for entire during of the training. 5.8 Gas RMS Bib-III Provide 6 (six) bound copies of complete Engineering Dossier of all supplied equipment for the RMS to be received by the Purchaser/Employer at least 30 (thirty) days before initial commissioning of the RMS comprising but not limited to the following: (a) Descriptive literature; (b) Complete data sheets; (c) Performance curves; (d) Instructions; (e) Maintenance and trouble shooting instructions; (f) Mill test certificates; (g) Manufacturers data sheets; (h) Fabrication data sheets; (i) Vendors drawings catalogues; (j) Radiography records; (k) Inspection reports and certifications; (l) Stress relief charts; (m) Hydrostatic test records; (n) Name plate rubbing; (o) Lubrication schedule (if applicable); (p) Line lists. 195 Section 7. General Specifications/Technical Specifications The Goods/ Equipments and Related Services shall comply with the Technical Specifications, Design Criteria and Construction specifications laid down in the following Sub-Sections. The Goods/ Equipments shall equipped with all necessary/ associated auxiliaries, accessories, fittings required for proper functioning and the Tenderer shall provide spare parts as stated in the following sub-section, clauses : A. Design Basis - General 1. The RMS shall be designed and constructed to ensure quantity, pressure and quality specifications of gas to be supplied by Jalalabad Gas T & D System. Ltd. (JGTDSL) as Gas Seller to Bibiyana-III, 400MW Combined Cycle Power Plant at Nabiganj Upzila , Habiganj. 2. (a) The RMS shall incorporate volumetric measurement as per AGA Report No.3 and 8. Orifice Metering with microprocessor based Flow Computer providing gas flow volume and also with Chart Recorder as well. (b) The Gas Metering System shall operate at an accuracy measurement within the limited range of plus or minus point five percent (0.5%). 3. The quality and performance by the Supplier/Contractor shall meet proven international standards and practices of American Petroleum Institute (API) or the accepted usage under the standards and practices of the Oil and Gas Industry of the United States of America (USA) and any reference to internationally accepted standards and practices shall mean those generally used by the Oil and Gas Industries of North America and Europe. Some of the major codes and standards which shall apply for this IFIB are as follows: (a) Bangladesh Natural Gas Safety Rules 1991 and its subsequent amendment. American Petroleum Institute (API) Specifications: (b) Gas RMS Bib -III Spec. 5L -Specifications for Line Pipes. Spec 6D -Specifications for Pipeline Valves. Spec. 1104 -Specifications for Welding Pipelines and related facilities. RP520 Part-I -Recommended practice for design and installation of Pressure Relieving System. RP520 Part-II -Recommended practice for sizing selection and installation of Pressure Relieving Devices. RP521 -Guide for Pressure Relieving and De-Pressurizing system. RP500C -Recommended practice for classification of locations for electrical installation at pipeline transport facilities. RP550 -Recommended practice for Fire Safe Testing. 196 (c) American National Standards Institute (ANSI) Specifications: (d) (e) A58 - B 2.1 B 16.1 B 16.5 B 16.9 B 16.11 - Minimum design loads in building and other structures (for wind loading) Pipe threads (except dry seal). Cast iron pipe flanges and flanged fittings. Steel pipe flanges and flanged fittings Factory made wrought steel butt-welding fittings. Forged steel fittings, socket welded and threaded. B 16.21 B 31.3 B 31.8 - Non-metallic gaskets for pipe flanges. Chemical plant and petroleum refinery piping. Gas Transmission and Distribution Piping System. American Society for Testing and Materials (ASTM) Specifications: A 36 A 106 A 105 A 325 - A 501 A 435 - Structural Steel. Seamless Carbon Steel Pipes for high temperature services. Forged Carbon steel for piping components. High strength bolts for structural steel joints, including suitable nuts and plain harder washers. Hot formed welded and seamless carbon steel structural tubing. Straight beam ultrasonic examination of steel plates for pressure. Mechanical testing of steel products. A 370 American Society of Mechanical Engineers (ASME) Specifications: Sec-VIII - Boiler and Pressure Vessels Code. (f) AISC - Specification for the design, fabrication and erection of structural steel for building. (g) AWSD1.1 - Structural Welding code. (h) AGA No. 3 (i) NFPA - National Fire Protection Association, USA. (j) NEMA - National Electrical Manufacturers Association, USA. (k) NACE - National Association for Corrosion Engineers, USA. (l) ASCII - American Standards Code for Information Interchange. (m) GPA - Gas Processors Association. (n) ISP - Instrument Society of America. (o) IP - Institute of Petroleum. (p) ISO - International Organization for Standardizations. (q) IOML - International Organization of Legal Metrology. (r) ISO 6976 (s) MSS - Specification for calculation of calorific value, density and Relative density of natural gas. - Manufacturer’s Standardization Society. (t) MSS SP-44 - Steel Pipeline flanges. (u) MSS SP-72 - Ball valves with Flanged or Butt-Welding ends. (v) MSS SP-75 - Specification for high test wrought welding fittings. (w) MSS SP-84 - Valves, socket welding and threaded ends. Gas RMS Bib-III Report - Orifice Metering. 197 (x) 4. UPC - Uniformed plumbing code, International Association of Plumbing and Mechanical officials. RMS shall be Supplied/Constructed to fulfil all fundamental requirements of flow control and measurement as well as operational safety requirements listed below but not limited to the following: (a) No pulsation of flow; Noise level shall not exceed the standard acceptable maximum sound limit ( 85db) (b) Filtration and liquid separations shall be stated in specified Equipment; (c) No reverse flow; (d) No liquid droplets in the measurement stream; (e) Regulatory, hazards zone, safety requirements; (f) Access requirements for maintenance and operational requirement; (g) Metering accuracy requirements; (h) Pressure and quality requirements; (i) Secondary instrument and interference requirements; and (j) Sources of interface, special requirement. B. 5. Design Data / Criteria Operating Conditions: (a) Station design : Capacity of KOD, Filter Separator, VME and Heating unit capacity will be 85 MMSCFD individually. 1 st regulating unit shall be design to reduce pressure from 1000 psig to 500 psig and 2nd regulating unit shall be design to reduce pressure from 500 psig to 150 psig and temperature 10°C - 15°C for supply of 85 MMSCFD gas to Bibiyana-3, 400MW Combined Cycle Power Plant and Orifice meter will be 85 MMSCFD at a pressure of 150 psig respectively. (b) Station pressure (c) Station outlet/ : 150 psig (150±5) Psig delivery pressure Set Pressure : 500 Psig for 1st stage regulating unit and 150 psig for 2nd stage regulating unit. (d) (e) inlet : 600 - 1100 Psig Average Pressure - 1000 Psig. Velocity limits : 60 ft/sec before filtration and 60 ft/sec to 120 ft / sec after filtration Gas : Specification Gas source is Bibiyana Gas field, Nabiganj, Habiganj of Bangladesh. Gas properties delivered to the Bibiyana-III, 400 MW CCPP RMS inlet will be generally as follows: (f) - gross heating value : 950--1070 BTU/SCF : 0.12 g/m³(n), sometimes Compressor lob oil may come with gas. Gas Composition (mol%) - water vapour contents Gas RMS Bib-III 198 - nitrogen carbon dioxide methane ethane propane Iso-butane N-butane Iso-pentane N-pentane N-Hexane N-Heptane N-Octane H2 S Specific gravity of gas Inlet temperature to pipeline : : : : : : : : : : : : : : : 0.3200 0.1100 96.0346 2.583 0.4001 0.2992 0.0743 0.0678 0.0200 0.0250 0.0550 0.0110 0.00 0.57 – 0.60 24°C (max) / 10°C (min) Scm/M³(n) means normal cubic meter at 101.560 kPa and 273.15°k, dry. 6. Environmental Data: 6.1 Climate: Tropical consisting of three major seasons as follows: 6.2 (a) Winter (November to February) which is cool and almost rainless. (b) Pre-monsoon (March to May) which is hot and has periodic thunder showers. (c) Monsoon or rainy season (June to October) which is warm and humid and during which more than 80% of the annual rainfall occurs. Temperature: (a) Maximum ambient temperature : 60°C (b) Max, black bulb temperature (unshaved) Min, ambient temperature in winter : 70°C (c) (d) 6.3 6.4 : 6°C Average soil temperature 1m below : 15°C surface Wind: (a) The prevailing wind direction is north west (b) Maximum wind velocity shall be 193 km / hr (c) Sandstorms are rare, some, dust may be encountered during summer (d) Cyclonic storms often occur in the rainy season, velocity may be 245 km/ hr. Rainfall: (a) Average annual : 2900 mm rainfall Maximum rainfall : 4320 mm [[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[[= (b) (c ) Gas RMS Bib-III Maximum rate of : 12 mm / hr. rainfall 199 6.5 Snowfall : None 6.6 Earthquake loading: As per Bangladesh National Building Design Code. 7.0 Data for Equipments Design 7.1 Knock Out Drum (KOD) (Ref. Drawing no. no.-JG/ Bibiyana-3, 400MW Combined Cycle Power Plant. RMS, P&ID) One Knock Out Drum (KOD) of 85 MMSCFD capacities at a range of operating pressure of 1100 psig to 600 psig shall be installed immediately after inlet valve with necessary full capacity bypass to knockout any incoming liquid surges/ condensate mist and large solid particles. (a) Mist removal : The effluent/delivered gas shall not contain entrained mist efficiency over 2.0 US Gallons/MMSCF and shall completely (99%) remove liquid particles of 5 microns or smaller and 100% removes Liquid particles of 8 microns and larger and solid particles. Turndown ratio will be 1:5. (b) Design Pressure (c) Allowable Pressure drop Design/ Construction Std. : Not exceeding 5 Psig across clean filter/vane under worst flow conditions. : ASME Pressure Vessels Code, Sec-VIII. (e) Discharge : (f) Noise Level : Auto discharge by gas pressure with the help of Level Controller and Drain Valve. By pass valve of auto discharge system should be installed. Noise level shall not exceed the standard acceptable maximum sound limit (85db) beyond 5ft of equipments. (d) 7.2 : 1440 psig Filter Separator (Ref. Drawing no. no.-JG/ Bibiyana-3, 400MW Combined Cycle Power Plant. RMS, P&ID) The section will comprise of 2 (two) numbers Two-stage type (Twin Lock quick opening) Filter separators to provide separation of liquid and solid entrainment from gas to be installed at the station inlet for 85 MMSCFD capacities at a range of operating pressure of 1100 psig to 600 psig (each). Filter Separators shall be installed and will be outdoor, unprotected, unattended type. Salient functional features are as follows: (a) First stage : Filter cartridge made of fibber glass. (b) Second stage : Vane mist extractor. (c) Installation : Skid mounted horizontal type. (d) No. of units : 2 (two) units of 100% capacity each. (e) Capacity :Each unit of 100% station capacity with 100% common by-pass provision having valves. (f) Solid / removal efficiency liquid : 99.9% of solid and liquid entrails above 5 microns at a turndown ratio of 1:5. Gas RMS Bib-III 200 7.3 (g) Allowable pressure drop : Not exceeding 5 Psig across clean filter under worst flow conditions. (h) Discharge : Auto discharge by gas pressure with the help of Level Controllers & Drain Valves and also having provision of manual discharge with by pass valves. (i) End closure : Quick Closing Door type. (j) Design Std. (k) Noise Level (l) Design Pressure /Const. : ASME Pressure Vessels Code Section-VIII. Noise level shall not exceed the standard acceptable maximum sound limit (85db) beyond 5ft of equipments. : 1440 psig Condensate Collector/ Storage Tank (Ref. Drawing no. no.-JG/ Bibiyana-3, 400MW Combined Cycle Power Plant. RMS, P&ID). The purpose of this section is to store condensate/liquids collected from KOD, Filter Separators and VMEs. All the discharge lines shall be connected with the storage tank. Features of the storage tank shall be as follow: (a) (b) (c) (d) Storage Capacity Design Pressure Installation Design / Const. Std. Discharge Meter (e) (f) : : : : 10000 Ltrs 285 Psig Under ground ASME Pressure Vessels Code, Section-VIII. : : By gas pressure Non-resettable digital display type index, to be intrinsically safe. (g) Accessories : Safety Relief, Fire Safety Valve, Flame arrestor, Level Gauge, Cathotic Protection and other fittings as per design, drawing (P&ID of Condensate Tank), and schedule of requirement. 7.4 Heating Unit (Ref. Drawing no. no.-JG/ Bibiyana-3, 400MW Combined Cycle Power Plant. RMS, P&ID): Water Bath Heaters with inbuilt RMS will be installed to heat the gas to an extent, which compensates for the subsequent temperature drop through the pressure regulator valves caused by the Joule-Thompson Effect. The heater shall be field installed, outdoor, unprotected type and shall be suitable for unattended operation. The Tenderer will submit with the Tender a brief description of the operating principle of the Heaters and the Heating Section along with and Heat Data calculations. Salient functional features are as follows: (a) Operation : Self contained with gas. (b) No. of heater : 2 (two) no of heater, for flowing 85 MMSCFD capacity gas each at a operating pressure of (max.)1100psig to (min.) 600psig. (c) Design temp : 100°C Gas RMS Bib-III 201 (d) Operation (gas) temp : temperature of gas before heating is Min 10°C at RMS inlet and After heating and at downstream of 2nd stage pressure regulation unit is to maintain between 10°C to 15 °C at 150 psig pressure. (e) Operation (water) temp : Max 80°C (water bath) (f) Thermal efficiency : 85% under full load (g) Burners : The heater will have 2 (two) main and burners. (h) Heater Instrumentation and Control : (i) 2 (two) pilot Heater should be PLC controlled (on, off & re-set) by its control panel. (ii) Displaying information of Inlet and outlet temperature of gas, temperature of water bath & temperature of RMS outlet gas after 2n d stage regulating unit. (iii) Display of every pre-alarm on the heater. (Pre-alarm is an alarm, which requires an operator’s action but does not shut the unit). (iv) Noise level shall not exceed the standard acceptable maximum sound limit ( 85db) beyond 5ft of equipments. 7.5 1st stage regulation unit (Ref. Drawing no. no.-JG/ Bibiyana-3, 400MW Combined Cycle Power Plant. RMS, P&ID): In the 1 st stage regulating unit pressure will be cut down into 500 psig from a source pressure between 1100 and 600psig. There will be two regulating runs and one bypass connector in this unit. All the equipments shall be 600 Class. 1 st stage regulating unit will consist of 2(two) regulating runs. Two runs for 85 MMSCFD and each of 100% capacity and each regulating run will consist of the following: (a) Regulator (2 nos), Regulator shall be configured as Active and Monitor system. (b) Slam Shut-Off Valve (1 no) (c) Noise Silencer (2 nos), (d) Ball valve (2 nos) (e) Check Valve (1 no.) (f) Pop-up Relief (1 no.) One 2”x600 RF Pilot operated Outlet Header Relief h) One 100 % Capacity by-pass line with 2(two) Ball Valves and 1(one) Hand Control Valve. Gas RMS Bib-III 202 Noise level shall not exceed the standard acceptable maximum sound limit (85db) beyond 5ft of equipments. 7.6 2nd stage regulating Unit (Ref. Drawing no. S no.-JG/ Bibiyana-3, 400MW Combined Cycle Power Plant. RMS, P&ID): In the 2nd stage regulating unit pressure will be cut down into 150 psig from 1st unit pressure of 500 psig. There will be two regulating runs, each of 100% capacity and one bypass run in this unit. All the equipments shall be 300 Class. Each regulating run of 2nd stage regulating unit will consist of the following: (a) Regulator (2 nos), Regulator shall be configured as Active and Monitor system. (b) Slam Shut-Off Valve (1 no) (c) Noise Silencer (2 nos.) (d) Ball valve (2 nos.) (e) Check Valve (1 no) (f) Pop-up Relief (1 no) (g) One 2”x300 RF Pilot operated Outlet Header Relief Valve. (h) One 100 % Capacity by-pass line with 2(two) Ball Valves and 1(one) Hand Control Valve. Noise level shall not exceed the standard acceptable maximum sound limit (85db) beyond 5ft of equipments. 7.7 Flow Measurement (Orifice Meter)(Ref. Drawing no. no.-JG/ Bibiyana-3, 400MW Combined Cycle Power Plant. RMS, P&ID): Flow measurement shall be done by means of Orifice Meter (senior type) to be installed after 2nd stage liquid separation and immediately before the delivery point of 400 MW RMS. Flow computer based on live data will perform metering calculation. Orifice meter is for measuring the gas flow range from 2 MMSCFD to 85 MMSCFD at 150 psig. This operating pressure may vary from 150 psig to 320 psig. The metering run shall also include mechanical 3-pen Chart Recorder for manual flow calculation. 7.7. 1 Major technical features for metering unit of Bibiyana-3, 400MW Combined Cycle Power Plant RMS are as follows: (a) Base Temp & Pressure : 60°F and 14.73 Psia respectively (b) Unit of vol. measurement : SCM/SCF (c) Standard : AGA Report No.3 (latest edition) and AGA Report No 8 (d) Static Press. : Range (e) Set Pressure : 150 Psig (f) Maximum allowable Diff. Press. : 90% of 100” WC (g) Meter type : 16” X 300 RF Dual chamber Orifice Meter. Metering run will consist of two ball valves. Gas RMS Bib-III 0-500 psig 203 (h) By-pass (i) Flow Computer Common bypass will be used as a Orifice bypass. : Micro Processor based Electronic Flow Computer to be mounted on a desk type control panel to be installed inside control building. (i) Flow computer should be control panel mounted. (ii) Displaying information of all running units (e.g. Static, differential pressure & flowing temperature) of meter run. (iii) Displaying corrected and uncorrected instantaneous and totalized flow hourly, daily and monthly. (iv) Readout of all variables, which are required to be manipulated to control the flow rate. (v) Control all set points and associated readouts, which are required to obtain above function. (j) 7.8 (vi) Flow computer should be interface with a Desk-top computer to be installed in control room in addition to default display unit (LCD) on the control panel. Digital smart transmitters. : (k) Data transmitter Input Data : Static Pressure, Differential pressure and flowing temperature through smart transmitters. (l) Output : Instantaneous volume flow rate, hourly volume flow rate, daily volume flow rate and cumulative / totalized monthly volume flow rate, pressure (static & differential) & temperature data, minimum 90 days stored data etc. (m) Chart Recorder : Mechanical 3-pen Chart recorder shall be provided to record Static Pressure, Differential pressure and flowing temperature for manual gas flow rate calculation. (n) Gas Chromatogra ph : For measuring heating value compressively of gas and others. of gas, sp. gravity, Liquid Separators (VMEs) (Ref. Drawing no. no.-JG/ Bibiyana-3, 400MW Combined Cycle Power Plant RMS, P&ID): The purpose of Liquid Separator units is to separate liquid condensate mist from gas downstream of pressure reduction. In this IFID, it will be required to install 02 (two) liquid separators. 1st VME One is 10"X10"X300 RF inlet & outlet connection and 85 MMSCFD capacity at 500 psig pressure which will be installed at the outlet of 1st stage regulating unit for Bibiyana-3, 400MW Combined Cycle Power Plant. Design Pressure : 720 psig 2nd VME Another one is 14"X14"X300 RF inlet & outlet connection and 85 MMSCFD capacity at 150 to 350 psig operating pressure, which will be installed at the outlet of 2nd stage regulating unit for Bibiyana-3, 400MW Combined Cycle Power Plant. Design Pressure : 720 psig All liquid Separators shall be placed outdoor and be unprotected and unattended Gas RMS Bib-III 204 type. Salient functional features shall be as follows: (a) Mist removal efficiency : The effluent/delivered gas shall not contain entrained mist over 2.0 US Gallons/MMSCF and shall completely (100%) remove liquid particles of 8 microns or smaller and 98% above 8 microns. Turndown ratio will be 1:5. (b) Allowable Pressure drop Design/ Construction Std. : Not exceeding 5 Psig across clean filter under worst flow conditions. : ASME Pressure Vessels Code, Sec-VIII. (d) Discharge : (e) Noise Level : Auto discharge by gas pressure with the help of Level Controllers and Drain Valves. By pass valve of auto discharge system should be installed. Noise level shall not exceed the standard acceptable maximum sound limit (85db) beyond 5ft of equipments. (c) 8. Piping, Valves and Fittings 8.1 Piping components, system and design shall meet the requirements of ASME B31.8. Equipment location, piping layout and valve and instrument positioning shall be suitable to facilitate operation, inspection and maintenance activities. All piping system shall be provided with means of draining low points and venting high points. Instrument gas takeoffs from header shall be from the tops, with a block valve located at the header. 8.2 Ball valves shall be used for all section isolation and relevant bypass line valves. C. 09. Design Basis: General Pipe, Valves and Fittings Introduction: This specification covers design considerations, arrangement requirements, and material requirements for piping systems for Bibiyana-III, 400MW Combined Cycle Power Plant, Habiganj. Any requirements not covered in this specification shall be specially addressed by the Supplier/Contractor utilizing the principles contained in this specification. The requirements in this specification shall govern in the event of a conflict between this specification, applicable codes and standards. xi. Codes, Standards and Specifications : Piping system shall conform to this specification and the requirements of the applicable provisions of the latest edition of the following codes, standards and specifications: ANSI B16.1 ANSI B16.5 ANSI B16.9 ANSI B16.11 ANSI B16.21 ANSI B16.34 API 5L Gas RMS Bib-III Cast Iron pipe flanges and flanged fittings. Steel pipe flanges and flanged fittings Factory-made Wrought Steel Butt welding Fittings Forged steel fittings, socket-welding, and threaded Non-metallic gaskets for pipe flanges Valves-flanged and butt-welding ends Specification for Line Pipe 205 API 6D Specification for Pipelines Valves. API 600 Steel Gate Valves, Flange and Butt-welding ends. API 602 Compact Gate Valves ASME B 31.3 Chemical plant and petroleum refinery piping ASME B31.8 Gas Transmission and Distribution piping systems ASTM (various) American Society for Testing Materials MSS SP – 44 Steel Pipe Line Flanges MSS SP – 72 Ball valves with flanged or butt welding ends. MSS SP – 75 Specification for High Test Wrought welding fittings MSS SP – 84 Valves – Socket welding and threaded ends. UPC Uniform plumbing code, international association of plumbing and mechanical officials 10 General: Piping components, systems and design shall meet the requirements of ASME B 31.8 except as specifically provided otherwise. Piping specifications are included in the Appendices and shall be used to select pipe, valves and fittings in accordance with designated service and ANSI pressure class. Because of the remote location of facilities, items should be standardized where possible to minimize the types and sizes utilized in the field. Cast iron or malleable iron shall not be used in hydrocarbon service. Pipe, valves and fittings shall be purchased and received with mill test reports and marking per applicable standards. Equipment location, piping layout, and valve and instrument positioning shall be suitable to facilitate operation, inspection and maintenance activities. Piping shall be adequately supported. Supports shall be designed for wind loads and loads from piping full of water attached to unsupported equipment. Pipe support design shall insure the ease of dismantling piping components for maintenance. Maximum unsupported span for straight piping runs shall be in accordance with the following table. NOMINAL PIPE SIZE (INCHES) Up to 1½" 2–3 4 6–8 10 12 – 14 16 – 18 20 and above WALL THICKNESS Schedule 80 Std. – Sch. 80 Std. and above Std. and above Std. and above Std. and above Std. and above Std. and above LENGTH OF SPAN (METER) 3.5 4.5 6.5 7.5 9.0 10.0 11.0 12.0 Notes : Spans shown are continuous pipe runs of steel pipe; Every seventh pipe support span shall be shortened by at least 20% to provide imbalance in the natural resonant frequency. Unsupported lengths at elbows shall not exceed two thirds of the tabled spans. Minimum pipe size in the rack shall be 2 inch. All piping systems shall be provided with means of draining low points and venting high points. Such vents and drains shall meet the requirements for the systems to which they connect. Gas RMS Bib-III 206 Instrument air, utility air and gas takeoffs from a header shall be from the top, with a block valve located at the header. For tanks and vessels subject to hydrostatic testing, the permanent piping shall not be connected to tank or vessel nozzles until after the tanks vessels have been filled with water for testing and the initial settlement has taken place. Nominal pipe sizes 1/8 inch, 3/8 inch, 1 1 /2 inch, 21 /2 inch, 3 1 /2 inch 5 inch, 14 inch, 18 inch, 22 inch and 26 inch shall be avoided. Above ground piping shall be installed on fabricated pipe supports, racks or sleepers with adequate flexibility, guides and anchors to accommodate thermal expansion for a temperature range of 14 0 C to 65 0C, unless fluid temperature exceeds this range. In that case, the design temperature shall be governed by the maximum temperature of the fluid. All tie-in welds shall be made only during periods when the pipe metal temperature is between 21 0 C and 45 0 C, unless more stringently controlled tie-temperatures are required by detailed design. The thermal displacement stress shall be based on the differential between maximum pipe stress design temperature (65 0 C or greater) and minimum pipe stress design temperature (14 0 C) as per ASME B 31.8. However, nozzle force/moment and maximum one-way displacements shall be based on the differential between: the maximum design temperature and minimum installation temperature (21 o ) or the minimum design temperature (14o C) and maximum installation temperature (45o C) whichever is most significant in the area under consideration. For insulated piping, If the maximum or minimum design temperatures are moderated due to the insulation, the moderated temperatures may be used. During the initial layout, a piping study should be made to identity lines where piping flexibility could be a significant consideration. Pipe stress analysis shall be performed on hydrocarbon piping 12 inch NPS and larger, and on other piping as warranted. Generous lateral legs shall be provided to ensure adequate flexibility for thermal growth and differential settlement, especially on leads to equipment. Minimum pipe size in the rack shall be 2 inch, except: air, gas, fuel and water supply lines from a header to a user may be 1 inch or larger up to the point of connection; instrument tubing and piping may be 10 mm or larger; water lines for plumbing within buildings may be 3 /4 inch; drain headers under gravity flow shall be 2 inch or larger; sanitary sewers under gravity flow shall be 4 inch or larger. Minimum pipe pup length shall be the greater of 150 mm or one pipe diameter. Gas or liquid pockets are to be avoided if possible. High point vents and low point drains shall be provided with valves near takeoffs. Means shall be provided to collect condensate. Spools and field welds shall be provided to permit flexibility in field make-up. Fitting to fitting design shall be avoided. Space requirements for equipment removal shall be considered for ring type joint applications. Unions in screwed piping shall not be installed in straight runs, but in offsets to facilitate installation. Plugs in screwed piping shall be provided as hex-head, solid bar stock. Connections made on fittings shall be avoided except where such taps are required in the design, such as a sweep-o-let for thermo well insertion etc. Gas RMS Bib-III 207 Reduction in line size shall not be permitted upstream of a branch connection. Instrument process connections piping shall m. 3 4 inch NPT, wherever possible Design: General: Line sizing shall be in accordance with the criteria in the Design Basis criteria. Material and wall thickness shall be calculated per ASME B31.8, and correspond with appropriate tables for respective service and pressure designation. Fittings, flanges and other materials shall conform to the requirements stated in the codes and standards and to the following requirements. • The carbon content based on the product analysis shall not exceed 0.23 percent. • Charpy V-notch tests per ASTM A370 shall be performed on representative fittings or flanges used in ANSI Class 600 and higher gas service. Three full size specimens are required for each test for each lot. Unless higher values are specified in ASTM material specifications, the minimum average impact energy of the three specimens shall be 40 ft.lbs. and no specimen shall be less than 30 ft.-lbs. for full size specimens. The average shear area exhibited by the three test specimens shall be 80%. No specimen shall exhibit a shear area less that 60%. Test temperature shall be 0 o C. Vender shall provide certificates of compliance in accordance with ASME, API 5L and other codes, standards and specification referenced herein, including chemical analysis, physical test results and heat treatment applied. 11. Above Ground Piping: Piping guides, clamps, stops and expansion loops shall be included to control the growth and movement of the pipe in the racks due to changing process and temperature conditions. Pipe shoes and wear pads shall be included to prevent overstressing the pipe at the point of contact with the support. Piping operating at temperatures above 72 o C shall be insulated for personnel protection. Minimum centerline spacing between un-insulated adjacent lines in a pipe rack shall be based on ½ the outside diameter (OD) of the smaller pipe plus ½ the OD of the flange of the larger pipe plus 80 mm. Line spacing shall be adjusted to include the insulation thickness for the smaller pipe. Pipe rack elevations are established on the basis that the primary rack has an allowance of 1(one) meter clearance (minimum) between bottom of pipe and top of grade. The clearance is to allow bottom pipe connections. Rack elevations and route shall provide appropriate access to valves and equipment. A secondary, or crossing, pipe rack shall be at a different elevation to allow pipes to cross without additional offsets. Pipe racks shall initially include at least 20 percent additional width for expansion purposes. Pipe racks crossing over facility roads shall maintain a minimum clearance of 4.8 meters between the bottom of pipe or structure and surface of road. Gas RMS Bib-III 208 12. Blow down Vent Piping: Blow down vent piping shall be designed without pockets and shall be properly sloped and trapped to control condensable accumulation. Vents and piping shall be adequately braced for the thrust forces and vibrations generated during blow down 13. Valves – General: The hardness of the body base materials and main parts of the valves shall not exceed 22 HRC in accordance with ASTM E18 or not exceed 248 HV10 in accordance with ASTM E92. Ball valves shall be used for all Section isolation and relevant bypass line valves. Manual operators, or the centre line of the hand wheel, shall be between 1.0 m and 1.4 m above finished grade. Bleed, lube, drain and sealant injection lines shall be brought above grade. 14. Control Valves: Bypass valves for control valves shall be globe type valves with Cg similar to control valve Cg. 15. Blow down and Equalization Valves: Blow down valves shall be lubricated Plug Type Valves/ Gate valves suitable for throttling service and shall include secondary sealant injection capabilities. Actuated blow down valves shall have fire-safe trim and shall be configured for fail closed, remote and local operation without mechanical latches or manual resets. Equalization valves shall be lubricated Plug type/ Globe type valves/Ball valves, suitable for throttling service. Equalization valves and piping shall be installed around all sectional valves and at other locations as required to introduce high-pressure gas into a low-pressure section prior to opening a major valve. Vent and drain valves smaller than 2 inch shall be Gate Valves. 16. Relief and Check Valves: 16.1 Relief Valves: Each relief valve shall have a vent bypass to facilitate relief valve maintenance and testing without plant shutdown. Liquid thermal relief valves shall be installed with locked-open inlet and outlet block valves to permit replacement without plant shutdown. Relief headers shall be sloped toward disposal to avoid accumulation of liquid against the relief valve. A low point knockout or drip leg shall be included in gas relief headers to control condensates. Relief discharge lines, other than thermal relief of non-flashing liquids, shall tie in to either the pit or the vent stack. Relief valve discharge lines shall not tie into drain systems. Gas RMS Bib-III 209 16.2 Check Valves: Check valves or lines leading from equipment and connected to headers shall be installed with a downstream block valve to permit check valve servicing without header shutdown. Swing check valves shall be sized for minimum velocity at design flow rate to ensure full disc lift. 17. 17.1 Piping Line Identification: Each line in the mechanical flow sheets and piping drawings shall be marked to denote nominal line size, service, line numbering, piping service class and piping pressure class. ........................................................................................................................... 17.2 Gas RMS Bib-III Abbreviations: ATM - Atmospheric BBE - Bevel Both Ends BE - Bevel ended BW - Butt Welded CS - Carbon Steel CWP - Cold Working Pressure DSAW - Double Submerged Arc Welded Electric ERW or type E- Electric Resistance Welded F/F - Face to Face FFFE - Flat Face Flanged End FO - Fully Open Gr - Grade GO - Gear Operated HW - Hand Wheel LCS - Low Carbon Steel LO - Lever Operated MSS - Manufacturers Standardization Society NACE - National Association of Corrosion Engineers NI - Nickel PSI - Pounds Per Square Inch PSIG - Pounds per Square Inch Gauge RF - Raised Face 210 D. 18. RFFE - Raised Face Flanged End RTFE - Reinforced Teflon Sch. - Schedule SMLS orType S - Seamless: SS - Stainless Steel SW - Socket Welded T&C - Threaded and Coupled TBE - Threaded Both End TC - Through Conduit WN - Welding Neck WT - Wall Thickness Design Basis and Construction Specifications – Civil 18.1 The RCC Structure/Concrete foundations have to be constructed over the consolidated ground bed. The Supplier is required to be assured by investigation of the soil of proposed station area.. All kinds of RCC or Concrete structures have to be designed / constructed according to the soil investigation report. 18.2 The skids / equipments/vessels like Heater, Liquid Separators, Regulating units, Metering unit, Condensate storage tank etc of the station should be set on RCC (1:1.5:3) structure. The RCC structures/Foundations have to be constructed as per site and soil (filling earth) condition by the Supplier/Contractor dully designed by the competent authority /designer considering the weight and size of the skids/Equipments. 18.3 All the specifications in constructing two storied control office building shall follow PWD standard. If soil report does not require more, all footing shall be on at least on 20’ height pre-cast piling. 19 19.1 The Supplier/Contractor shall construct sufficient nos of RCC pipe supports for supporting the pipe, pipe spool and pipe works as per requirement and instruction of the Purchaser’s/Employer’s Engineer. 19.2 The detail design and drawing of the aforesaid RCC structures/foundations and RCC pipe supports will have to be prepared by the Supplier/Contractor and has to take approval from JGTDSL authority. The Supplier/Contractor shall construct at least 1 (one) meter walkway around all skids/units beyond the original RCC structures/foundations to facilitate the maintenance works. E. 20. Design Basis – Instrumentation Codes, Standards and Specifications: This Design Basis was prepared based on the US codes and standards. Unless otherwise noted, reference made herein to codes, standards and specifications are to the latest edition of such code. Gas RMS Bib-III 211 Codes, standards and specifications are listed in the parts of the Design Basis to which they apply. API ASME 21 American Petroleum Institute RP – 520 Recommended practice for Sizing, Selection and Installation of Pressure Relieving Systems in Refineries. RP - 550 Recommended Practice Manual on Installation of Refinery Instruments and Control systems STD 527 Commercial Seat Tightness of Safety Relief Valves with Metal / to / Metal Seats, second edition. STD 2000 Venting Atmospheric and (Low Pressure Storage Tanks) Non / refrigerated and refrigerated), third edition American Society of Mechanical Engineers Section VIII Boiler and Pressure Vessel/Codes, Section VIII, Rules for Construction of Pressure Vessels, Division 2, Alternative Rules. ISA Instrument Society of America S5.1 Instrumentation Symbols and Identification. S5.2 Binary Logic Diagrams for Process Operations. S5.3 Graphic Symbols for Distributed Control / Shared Display Instrumentation, Logic and Computer Systems. S20 Specification Forms for Process Measurement and Control Instruments, Primary Elements and Control Valves. Site and Service Conditions: Instrumentation materials and /or equipment shall perform their specified functions under the site conditions (i.e. elevation, design temperatures, wind velocities) for each station. 22 Units of Measurements: All scales, charts and documents covered by this specification shall be prepared using standard metric units of measurement, with the exception of pipe diameter and valve size. Pipe diameter and valve sizes shall be expressed in Inches using nominal pipe size. The following units of measurement shall be used in process measurement and controls: 23. Flow (Gas) SCMH/SCFH Flow (liquid) Cubic meters/min @ flowing temperature Level (Storage tanks) Meters, millimeters Level (Vessels) Percent of range Pressure (Gauge) bar/psig Pressure (Absolute) bar(a)/PSIA Pressure (Vacuum) mm H2 O/inches of H2 O column Temperature º C/º F Instrumentation Symbols and Nomenclature: Instrument symbols and nomenclature on Process Flow Diagram (PFD) and Piping and Instrumentation Diagrams (P & ID ‘S) shall be derived from ISA Standards. This symbols shall be documented, in condensed form, on the P & ID legend and symbols instrumentation sheet. Gas RMS Bib-III 212 Instrument identification and tagging shall be provided on all diagrams, Instrument loops, Individual instruments, Instrument specification sheets, correspondence and documentation. Each instrument loop of individual instrument shall have a unique alphanumeric designation (tag number). If an instrument is common to two loops, it shall be numbered the same as the primary loop .An assigned tag number cancelled because of instrument revisions shall not be reused. 24. Instrument Identification and Tagging: Each instrument shall be identified by the manufacturer with a stamped or engraved stainless steel tag bearing the complete tag number permanently wired to the instrument. Characters shall be at least 19 mm high. All instrumentation and associated equipment including junction boxes, terminals, cables, and covers shall be clearly identified by a permanent marker / label bearing the appropriate Identification /tag number. Instrument identification tags shall have white letters of black background. Instruments, except for flow element and temperature sensor assemblies, shall have the following identifying information of a nameplate. This plate shall be installed on the instrument at the factory. ° manufacturer’s name, model and serial number; ° pressure rating of pressure holding parts; ° operating range; ° materials of parts exposed to process fluid; ° as applicable, information on voltage, frequency and test authority approval; ° accuracy, and ° factory test certificate. 25. Instrument Data Sheets: Data sheets shall be prepared for each instrument component identifying it by tag number, type and model number and shall indicate all operating data such as range, capacity action and set point. Data sheets forms shall meet ISA S20 format. 26. Instrument Location and Accessibility: Local instruments shall be accessible from grade, a permanent floor, platform or ladder. Line mounted instruments such as close coupled pressure gauges, temperature gauges, and temperature elements shall be located as follows: ? not more 1.5 meters above platform or more than 457 mm out side the platform handrail, and ? not more than 160 mm from centerline of permanent ladders. ? Level instruments (i.e. level gauge glasses, level switches, and displacer type level transmitters) including their isolation valves shall be accessible from platforms. In particular, the case of level switches and displacer type transmitters shall be a maximum of 1.5 meters above the platform. ? In-line instruments such as Control Valves and flow elements shall be accessible from grade or a platform. ? When vibration of a line or equipment is possible the instruments shall be remotely mounted with the instruments centreline 1.5 meters above ground or the platform. Gas RMS Bib-III 213 ? All other instruments (i.e. Pressure Transmitters, Temperature Switches and Flow Transmitters) shall be remotely mounted on a 2-inch pipe stand with the instrument’s centreline 1.5 meters above ground or the platform. 27. Instrumentation: General Instrumentation shall be installed to provide the data and functionality. Additional instrumentation not expressly called for but Supplier/Contractor shall provide necessary for the proper and safe operation of the metering system. Supplier/Contractor shall provide completed instrument data sheets, per ISA S20 for all instruments. The primary measuring device shall be an orifice plate, with differential pressure created being measured by differential pressure transmitter. Ancillary measurements of static pressure, differential pressure and temperature shall be included for correction of “Line” flow conditions to “Standard Volume” by means of microprocessor - based flow computer using calculations in accordance with AGA Report no.3. “Standard Volume” conditions shall be taken as 1013.25 mbar absolute and 0° C. Each instrument will be subjected to a 5-point calibration, both up and down scale. 28. It shall be demonstrated that the overall accuracy is maintained under conditions of static pressure shift covering the range from atmospheric to design ,for the full range of ambient condition changes. this shall include surface temperature rises due to tropical sunlight. Each transmitter shall be complete with integral vent connections and a 316 SS, 3- Valve manifold to permit isolation and zero balancing. Supplier/Contractor shall provide 02(two) portable calibrator for use with the static pressure, differential pressure & temperature transmitters. Pressure Instrumentation: 28.1 Pressure Gauges: Pressure gauges shall be weatherproof and protected with phenol resin cases unless otherwise specified. The minimum requirement shall consist of 316 stainless steel bourdon tubes welded to forged alloy steel sockets with wrench flats. Movements and micrometer pointer shall be stainless steel with silicone – treated wear surfaces. The gauges shall be provided with safety armoured glass blow out disks located on the back and white faced laminated dials with black markings. Gauges shall be 150 mm diameter for all applications except those used on instrument air service, whose diameter may be 60 mm. All 150 mm gauges shall be equipped with threaded connections having a nominal pipe size (NPS) of 0.5 inch. The range of all pressure gauges shall be selected to ensure that the normal operating range is within the middle third of the scale. The pressure range shall be at least 125 percent of the pressure relief set pressure on the system The minimum accuracy of the gauge shall be ± 1.0 percent of the full scale. A valves block and bleed manifold that can also be used for calibration with NPS 0.5 inch threaded connections shall be provided upstream of each pressure gauge. In pulsating or vibrating service pressure gauges shall be filled with liquid and pressure dampeners shall be installed. Dampeners shall be adjustable while the instruments are in service. Diaphragm seals shall be used for all waxy or corrosive fluids. As a minimum requirements, pressure gauges shall be installed as follows: ° on the discharge of each pump compressor and blower; Gas RMS Bib-III 214 ° on the discharge of each stage of a multistage compressor; • on each pressure vessel ; • on all utility headers ; • After each pressure regulator and ahead of each back pressure regulator, and • In/outlet streams of stations. 28.2 Static Pressure Transmitters and Auxiliary Pressure Instruments: Pressure transmitters may be of the “smart” type that microprocessor based electronics as well as digital interfaces. incorporates Electronic transmitters shall be the capacitance type. All pressure transmitters shall have 2(two) valve manifolds as required. All bodies and wetted parts shall be 316 series stainless steel. The pressure range shall be approximately 200 percent of operating pressure for liquids and 150 percent for gases and shall be at least 125 percent of the relief valve setting on the system. All pressure instruments shall be provided with a valves block and bleed manifold, diaphragm seals, and dampeners as specified in section-6 of Tender document. Pressure instruments on gas and vapor service shall be mounted above the pressure tapping wherever possible the tapping shall be located on the top or side of the equipment. For pressure switches the repeatability shall be 1 percent of set point, and the set point shall be internally adjustable. Accuracy should be as a minimum ± 0.5 % of the range. Switches shall be in accordance with applicable standard. 28.3 Differential Pressure Transmitters and Auxiliary Pressure Instruments: Differential Pressure Transmitter shall be “Smart “ type two wire ,4-20 mA output differential pressure transmitter, capacitive or piezo-resistive type with integral pressure and temperature compensation in accordance with specification. The quantity and range of the transmitter for meter run shall be adequate to provide the desired rangeability of 10:1 meter run with out exceeding the maximum uncertainties of the system. The overall accuracy of the Differential Pressure Transmitter shall be equal or better than ±0.1% of the span to suit turndown requirements. It shall demonstrate that the overall accuracy is maintained under condition of static pressure shift covering the range from atmospheric to design for the range of ambient condition changes. This shall be including surface temperature rises due to tropical sunlight. Each transmitter shall be complete with integral vent conditions and a 316 SS, 3-valve manifold to permit isolation and zero balancing. Supplier/Contractor shall provide portable calibrations equipments for use with the static and differential pressure transmitters. 28.4 Calibration Checks: Transmitter, receiver and signal conditioner calibration checks shall be performed by using calibration equipment to simulate 0 %( percent), 25 %( percent), 50 %( percent), 75%(percent) and 100 %(percent) of the instrument input signal range, adjusting at each setting where necessary. At completion of calibration check a calibration check/testing shall be completed. Gas RMS Bib-III 215 If calibration check indicates that the instrument cannot meet the manufacturer's specification the unit shall be replaced with good one /unit. 29. Temperature Instruments: 29.1 Thermo wells: Thermo wells shall be provided for all insertion – type temperature instruments and indicators. Sufficient test thermo wells, equipped with plug and chain shall be provided so that temperature surveys can be made throughout the facilities. As a guideline thermo wells shall be provided on all lines to and from all heaters, inlet / outlet pipelines. Thermo wells shall be 316 series annealed stainless steel constructed from onepiece bar stock machined to a smooth tapered profile to avoid sharp corners. Thermo well connections to the external side shall be NPT ½ inch threaded and on the instrument side NPT 3/8 inch threaded . Sufficient lag extensions shall be used according to insulation thickness Thermo well immersion depth in piping shall not less than one third and not more than two thirds of the distance to the centerline of the pipe. Thermowells shall be installed on the centerline of piping. 29.2 Temperature Gauges: Locally mounted thermometers shall be bimetallic type with a 125 mm diameter, adjustable angle, while faced / black marking dials, built – in zero adjustment, and weatherprove case: ? scale division shall be less than 1/40 of span; ? accuracy shall be ± 1% full scale; ? zero point shall be adjustable; ? fully ambient temperature compensated. If necessary for operating visibility (i.e. when the temperature measurement point is more than 3 meter above ground) of gauges in vibrating service, a remote bulb shall be used with the indicator mounted off the line at a convenient location. As a minimum, temperature gauges shall be installed as follows: • On the inlet and outlet of heaters; • Adjacent to the measurement point of the temperature transmitters or local temperature controllers. • Inlet / outlet of pressure regulators or • In/out gas pipelines of stations. 29.3 Temperature Detectors: Resistance Temperature detectors (RTDS) are the preferred means of temperature measurement for centralized control and for multipoint. Three–wire platinum resistance RTDS shall be used for temperatures up to 649 ºC. RTDs shall conform to international standards RTDs shall be grade II, 100 ohms at 0 ºC, a = 0.00385 ohms/ohms/ºC (international) To measure the same temperature for two different purposes, a dual –element RTD shall be used Gas RMS Bib-III 216 29.4 Temperature Transmitters and Switches: Temperature transmitters shall be of the “smart” type that incorpor microprocessor based electronics as well as digital interfaces. The transmitters shall be two–wired devices, loop powered at 24 volts direct current (VDC). Output shall be 4-20 milli amperes direct current (mA DC) for a 0 percent to a 100 percent process variable change unless otherwise specified on the instrument data sheets. The primary elements for temperature transmitters shall be or RTDs. Temperature switches shall be vacuum filled. Set point adjustments shall be internal. Switches shall be in accordance with applicable standard. Switches shall have ambient temperature stability of ± 0.56-ºC maximum set point shifts per 67 ºC ambient change and a repeatability of 1 percent of range. Switch dead band shall be less than ± 5% of span. All capillary tubing shall be armoured stainless steel. Maximum length is 3 meters. Capillary tubing shall be supported throughout its length. The range of all temperature instruments shall be selected to ensure that the normal temperature will be in the middle third of the scale. 29.5 Calibration Checks Thermocouple (TC) and resistance thermal detector transmitters shall be calibrated as follows: * At a minimum of five points (0 %(percent), 25 %(percent), 50 %(percent), 75%(percent) and 100 %(percent) ) calibration as per manufacturer's specification. * Upper and lower operating limits shall be verified and adjusted; * Activation of thermocouple burnout feature shall be checked; * Thermocouple Instrument shall be calibrated applying increasing and decreasing millivolts signals from a potentiometer; * RTD instruments shall be calibrated using either a precision decade resistance box or a portable decade bridge. 30. Calibration: Pressure Transmitter & Instruments shall be calibrated at three points representing minimum scale, maximum scale and normal operating pressure. Pressure and differential transmitters shall be bench calibrated by providing an input matched against a calibrated standard and monitoring the output with precision meter. Pressure Indicator, recorder and controllers shall be bench calibrated against a precision meter. Draft gauges shall be calibrated using a water using a water column or inclined tube manometer Receiver type pressure gauge shall be calibrated with either a manometer or a precision pressure gauge. Pressure gauge located on or near reciprocating equipment where vibration hinders gage reading shall be installed with pulsation dampeners. F. 31. Design Basis: Metering and Regulating System . Codes, Standards and Specifications: The metering/regulator system shall be designed and fabricated in accordance with this specification and the applicable provision of the latest edition of the below listed codes, standards and specifications. Gas RMS Bib-III 217 In case of conflict between this specification and its associated specifications and the below codes and standards, Supplier/Contractor shall bring the matter to the Purchaser’s/Employer's attention for resolution and approval in writing. In all cases the most stringent requirements shall apply. Compliance by the Supplier/Contractor with the provisions of this specification does not relieve him or his responsibility to furnish equipment and accessories of a proper mechanical design suited to meet the specified service conditions for fabrication and health and safety. AGA Reports no. 5 Fuel Gas Energy Metering. AGA Reports no. 3 Fuel Gas Metering by orifice meter. AGA Reports no. 7 Gas Metering by turbine Meter. AGA Report no. 8 Compressibility Factors of Natural Gas and Other Related Hydrocarbon Fluids. AGA GMM Part. 9 Gas Measurement Manual, Part 9, Design of Metering and Regulating Stations. AISC MO11 Manual of Steel Construction Allowable Stress Design. API RP 550 Recommended Practice for Classification of Locations for Electrical Installation in Petroleum Refineries. API RP 550 Recommended Practice for Manual on Installation of Refinery Instruments and Control Systems. ASME Boiler and Pressure Vessel Code, Section VIII, Unfired pressure Vessels, Division 1. ASME B16.5 Pipe Flanges and Flanged Fittings. ASME B31.8 Gas Transmission and Distribution Piping Systems. ASTM A36 Standard Specification for Structural Steel. AWS D1.1 Structural Welding Code. BS 1904 Industrial Platinum Resistance Thermometer Elements. ISA S20 Specification forms for Process Measurement and Control Systems, Primary Elements and Control Valves. NFPA 70 National Electric Code (NEC) Relevant clause of Equipment/material Specification. Tender document 32. Site and Service Condition: RMS Site is described in relevant clause of Tender document. Service conditions are Listed in Process Flow Diagrams (PFD'S) and preliminary design done by the Purchaser/Employer (Attached P&ID). Supplier/Contractor shall provide the materials and/or equipment, which are capable of performing their function under the conditions listed. 33. System Design Configuration and Components: 33.1 Gas RMS Bib-III General Detail design configuration of the metering and regulating systems shall be in accordance with the Process Flow Diagrams (PFD´S) and preliminary design done by the Purchaser/Employer (Attached P&ID). The system components shall be capable of performing the requirements under the conditions detailed in this specification and associated material specifications. 218 The Supplier/Contractor shall establish a Manufacturing Procedure (MP) and Quality Control Specification for manufacture and inspection of the systems describing all proposed operations in their correct sequence with their parameters of execution. The Metering/ Regulating unit shall be equipped with all the instrumentation and equipment detailed in the specification and required by the referenced design codes and standards. 33.2 Structural It is preferred that all equipment except for the control panel and related equipment supplied by the Supplier/Contractor shall be mounted firmly on a heavy duty field skid. The skid shall be built for specification packaged Assembly, relevant clause of Tender document 33.3 Scrubbers/ Liquid Separators, Liquid Catchers and Liquid Storage Liquid Separators shall be provided to Separate liquids, which are carried through the pipeline during normal operations and in some cases after pressure reduction. Liquid collected in the separators shall be discharged to storage tank. The separators shall be supplied in accordance with the specification given in relevant Section 7of Tender document. 33.4 Gas Heating System Gas shall be heated in the cases if the gas temperature drop, caused by pressure reduction (Joule Thomson effect) exceeds the allowable lower limit at the outlet of the stations. A gas heating system shall be provided and the thermal capacity shall be based on the maximum temperature drop and 100% gas flow through put. In other words the heating system shall be capable of maintaining the gas temperature of at least 18ºC down stream of the 1st stage Pressure Regulators under all given conditions except as otherwise required or stated. 33.5 Pressure Regulator and Pressure Safety Device The regulators shall be fail to open and shall be designed to produce maximum noise level of 80 dBA at 1-meter distance. The Slam Shut Valve shall prevent over-pressure in the downstream pipeline systems by interrupting the flow in the pressure regulator run in case of a faulty regulator and shall be installed upstream of the regulators. Pressure Relief Valves shall be provided if over-pressure in pipeline systems or vessels either through leaking valves or due to thermal expansion that could occur. Gas Pressure Regulators and safety devices shall be supplied in accordance with the specifications given in relevant Section 7 of Tender document. 33.6 Metering System The Orifice Metering system shall be designed to measure gas of the given composition over the range of volumes, pressure, temperatures provided on specifications. The meter tubes shall be designed in accordance with the minimum requirements of AGA Report no. 3 for Orifice Meter. Super-compressibility factor shall be calculated in accordance with AGA Report no.8. Gas RMS Bib-III 219 The meter tubes shall also meet requirements of ASME B31.8. Meter Tub The length of the upstream tube shall be at least the minimum length required by AGA Report no.3. The downstream tube shall be at least the minimum length required by AGA Report no.3 for Orifice Meter. The orifice meter run shall include a removable spool to enable inspection of meter tube. The spool shall be as short as possible while still remaining within the tolerance given in AGA Report no.3. Chart Recorder: Three-pen mechanical chart recorder will be associated with orifice meter. Bypass Run: Bypass line shall be provided in accordance with P&ID’s . 34 Flow Computer Panel: 34.1 General The Flow computer control panel shall be installed in an-air conditioned control room and in accordance with relevant clause of meter panels of material/ equipment specification. 34.2 Flow computer Flow computer shall be a microprocessor-based unit. Flow computers shall perform all required compensation using AGA Retort no.3 in metric/ imperial customary units Calculations shall be compensated for static pressure, Differential pressure, temperature and supper compressibility factor. 35. Safety: It is the intention of the Purchaser/Employer that operational hazards be reduced to a minimum. Supplier/Contractor shall use sound engineering judgment in the design, fabrication, installation, testing and commissioning of the equipment and ensure that it will perform the required process function without compromising this aim. Piping, valves, electrical conduit, cable and instrument tubing shall be arranged in such a manner as to avoid tripping and overhead hazards. Piping, tubing and conduit shall be of sufficient mechanical strength for standing and shall be protected from personnel traffic. 36. Surface Preparation and Coating: Surface preparation and coating shall be in accordance with applicable standard. The referenced specification applies only to structural steel and piping. Equipment shall be as per manufacturer's standard painting procedure. 37. Inspection: The responsibility for inspection and compliance with this specification rests with the Supplier/Contractor. Purchaser/Employer reserves the right to inspect materials, manufacturing and fabrication and to witness tests at any time. Supplier/Contractor shall provide the required access for such inspections and test witnessing or his representative inspects it. 38. Testing: 38.1 Gas RMS Bib-III General In addition to the inspection and testing specified in the accompanying requisition documents, Supplier/Contractor shall also comply with the minimum requirements specified herein. 220 Supplier/Contractor shall provide to Purchaser/Employer not less than six weeks prior to the date of ommencement of the gas fiscal metering system test, a detailed schedule of the tests and sample test record forms for approval. The tests shall not be undertaken until the test schedule and Purchaser/Employer approves test forms. An operating and maintenance manual and final certified copy of as built drawings shall be provided for the Purchaser’s/Employer’s exclusive use during final works testing and inspection. 38.2 Mechanical Testing Testing shall be witnessed by Purchaser/Employer. Pressure piping testing shall be in accordance with the applicable sections of ASME B31.8, Design Factor 0.6, Unless otherwise specified. Structural welding test shall be in accordance with the applicable sections of AWS D1.1. Rust-Inhibited water or other approved non-corrosive liquid shall be used for hydrostatic testing and performance testing. Process instrumentation, which could be damaged by the elevated hydrostatic test pressure, shall be removed prior to hydrostatic testing and reinstalled prior to system performance testing. Filtered, dehydrated, compressed air or nitrogen shall be used for pneumatic tests. All instrument gas tubing connectors shall be tested for leaks. Hydrostatic test pressure shall be per ASME B31.8 and shall be held for a minimum of 2 hours. 38.3 Pre-Factory Acceptance Tests Piping and other components shall be dewatered and dried after hydrostatic testing to achieve a -40ºc dew point. Calibration of all instrument Items shall be witnessed to ensure the required accuracy is achieved. Calibration and test certificates of all Supplier/Contractor-supplied equipment shall be included in the final test report for Purchaser’s/ Employer's approval and acceptance prior to shipment. Orifice meters and transmitters shall be calibrated and tested by an independent body. The test procedure shall satisfy the requirements of this specification as a minimum and shall include but not be limited to: • All wiring shall be tested for insulation and the test voltage shall be compatible with the wiring being tested (equipment likely to be damaged shall be disconnected for these tests). • All wiring shall be tested for continuity against Purchaser/Employer approved wiring diagrams. • A 48 hour soak test at an elevated temperature of 50º C shall be carried out on all solid-state devices under full load conditions. If satisfactory certification of such tests by the component manufacturer is not made available to Purchaser/Employer, Supplier/Contractor shall carry out and certify such tests either on individual components or on the complete system, as agreed with Purchaser/Employer. Representative internal Gas RMS Bib-III temperatures and ambient conditions 221 shall be continuously recorded. These tests shall be carried out prior to the simulated function tests. • If a component failure occurs, all tests shall be repeated so that all components have undergone the minimum testing specified. 38.4 Factory Acceptance Tests Full-simulated function tests of the complete system shall be performed with all equipment in position and connected to suitable temporary supplies. Supplier/Contractor shall provide the test simulator consisting of dummy loads with indication of the status of every output. The test simulator shall only be connected to the field connection terminals and input/ output interface shall be individually labeled to facilitate testing. Supplier/Contractor shall obtain approval of supply unit characteristics and simulated input/ output interface. All equipment failure modes e.g. fail safe, self-diagnostic; power supply dip etc. shall be checked. All equipment shall be tested for radio frequency immunity. All tests and corrective work shall be recorded, subject to Purchaser/Employer approval. Supplier/Contractor shall ensure that all inspections and tests are completed and satisfactory. Purchaser/Employer reserves the right to back-charge any additional inspection work if Supplier/Contractor preparations are found to be unsatisfactory by Purchaser/Employer. Full functional tests shall be performed on the flow and totalizing computers using simulated inputs and outputs. The whole system (equipment, computers etc.) shall be interconnected and powered for this test. This includes the testing of all data transfer via the RS232 ports. 38.5 Site Acceptance Test Supplier/Contractor shall certify the installation of the metering system at the construction site. Supplier/Contractor must validate the metering system after commissioning. This shall include a per-start-up, on-site calibration so as to obtain a “First Calibration Certificate”. Purchaser/Employer shall witness the validation. The validation procedure must be submitted to Purchaser/Employer for approval four weeks prior to commencement. 39. Documentation: 39.1 Design Documentation Design Documentation shall be supplied in accordance documentation. This shall include, as a minimum, the following: • complete data sheet; • sizing calculation; • uncertainty calculations; • user’s reference list; with project • mean time between failure figures for electrical/electronic equipment; • general agreement and cross sectional drawings, complete with parts list, • materials of construction and description; • prices list of recommended commissioning spares; • prices list of recommended spare parts for two years operation; • prices list of special tools; Gas RMS Bib-III 222 • itemized list of Supplier/Contractor’s deviations from specification; • weights, and • delivery. 39.2 40 Final Documentation 39.2.1 A manufacturing Record Book shall be complied concurrently with fabrication such that a full record of the fabrication, materials, inspection and testing is available. 39.2.2 All items in the Manufacturing Record Book shall be numbered. Contents shall include, but not to be limited of the following : • front cover sheet detailing; project title, equipment title, and equipment item no.; • index; • purchase release note; • purchase order or extract thereof; • a list of all applicable codes, standards and specifications; • all drawings and data sheets, “as built”; • CD containing the configuration and programming software for flow computer; GC, WBH. • approved weld procedures, weld procedure qualifications and NDT procedures; • summary of approved welders’ and NDT technicians’ qualifications; • all NDT/PWHT/hydrostatic test reports; • MTR’s and ETR’s; • certificates giving accuracy’s for all equipment supplied with these systems and assuring the quality of the software to be employed; • photocopy of nameplate(s) and • final signed Quality Plan. 39.2.3 Operating manuals shall be assembled into an A4 size post binder and shall contain: • operating and maintenance procedures; • commissioning instructions; • all “ as built” drawings and data sheet referred to in section above; • schedules of commissioning and operating spare parts for two years service, and • programming data and software for the flow computers. 39.2.4 The following should be conspicuously marked on all documents; • Jalalabad Gas, Sylhet, Bangladesh; • Bibiyana-III, 400MW Combined Cycle Power Plant, Habiganj. • Contract/Work Order number, and • Item number. Warranty: Warranty provisions are specified in the standard Terms and Conditions attached to the Tender Request and apply to the Supplier/Contractor and to sub-contractor/Contractors and/or suppliers. If modified warranty terms are agreed to between Purchaser/Employer and contractor, these modified provisions will be incorporated in the work order/contract 41. Marking and Tagging: The metering system shall have a tag number as indicated on the data sheets. Nameplates shall be die-stamped stainless steel plates permanently attached at an easily accessible port on the skid equipment or instrument. Each major piece of equipment shall have a tag name describing its function and technical data. Gas RMS Bib-III 223 The metering system (skid) nameplate shall include the following additional information: • tag number ; • Supplier/Contractor or Vendor equipment serial number; • maximum flow rate; • maximum design pressure and temperature, and •hydrostatic test pressure. Nameplates and tags are required for each vessel, instrument skid, relief valve, control valve and other component identified by a tag number on the approved piping and instrument diagrams. Supplier/Contractor shall mark tag numbers on the Supplier/Contractor’s approval drawings. 42. Preparation for Shipment: Unless otherwise noted, preparation for shipment shall be in accordance with Supplier/Contractor’s standards for export shipping, augmented where necessary to include the general requirements stated herein. All items shall be properly packed and protected from damage during shipment. Each crate, bag or package shall be clearly identified with the contents and identification symbol. Exposed machined surfaces shall be coated with easily removable rust preventive. Supplier/Contractor shall pay particular attention to preserving the integrity of the internal surface condition of the meter tubes. All flanged openings shall be protected with steel plate covers attached by proper bolting and sealed with a neoprene gasket. Screwed connections shall be protected with threaded forged steel plugs. Supplier/Contractor shall be solely responsible for the adequacy of the preparation for shipment provisions employed in respect to materials and applications to insure that materials arrive at their destination in ex-works condition when handled by a commercial carrier system. Supplier/Contractor shall include his standard procedures for preparation for shipment in his tender for review by Purchaser/Employer. Supplier/Contractor shall also state in his Tender his recommendations for long term storage (up to 12 months) for both indoors and open air storage. The following data should be conspicuously marked on all crates, boxes, and shipping containers: • Bibiyana-III, 400MW Combined Cycle Power Plant, Habiganj. • Contract/Work Order number, and • Item number. G. 43. Construction Specifications: Mechanical/Piping Scope: This specification covers the minimum requirements for workmanship and materials used in the installation of piping and mechanical facilities associated with the construction of Bibiyana-III, 400MW Combined Cycle Power Plant RMS at Nabiganj Upazila , Habiganj. . Gas RMS Bib-III 224 44. Codes Standards and Specifications: Piping and mechanical installations shall be in accordance with this specification and the applicable provisions of the latest editions of the following codes, standards and specifications. API Std. 1104 Welding of Pipelines and Related Facilities ASME B31.8 Gas Transmission and Distribution Piping Systems. ASME Sec. IXQualification Standard for Welding and Brazing Procedures, Welders, Brazers, and Welding and Brazing Operators. 45. Piping: 45.1 General: Piping systems shall be fabricated, inspected, tested, installed as described in the project drawings, and in strict accordance with ASME B31.8, and the General Pipe, Valves and Fittings Specification as applicable. The Supplier/Contractor shall maintain adequate material control and checks to ensure that only the correct materials are used on each piping system. Only proper tools and equipment, operated by qualified personnel, shall be used during the lifting and setting of piping materials. The Supplier/Contractor shall comply with the handling requirements and provisions of the manufacturer’s. Booms, hooks, supports, skids, tie-downs, and similar devices used in lifting of pipe shall be padded to prevent damage to the pipe, end bevels and coating where applicable. 45.2 Cleaning: Piping shall be kept clean and free of all dirt and oily matters. Prior to welding or spool fabrication, the Supplier/Contractor shall brush each pipe joint using a full diameter wire brush attached to a cleaning rod or cable to remove loose mill scale and other debris. After brushing, the remaining foreign material shall be blown out using 7 (seven) bar compressed air and “air lance”. After welding or fabrication, piping shall be blown out using 7 (seven) bar compressed air and “air lance to remove any loose material and weld splatter. Piping to be installed upstream of flow meters, control valves, or other equipment; lube oil piping and instrument gas piping shall be wire brushed and swabbed with a full diameter fabric swab. The brushing and swabbing shall be repeated until no visible loose mill scale, weld splatter, dirt or rust is evident on the fabric swab. 45.3 Preparation of Pipe and Fittings for Welding: All pipe ends and faces which are to form part of the welded joint shall be cleaned to sound metal immediately prior to welding to ensure complete removal of all paint, grease, dust and any other deleterious matter. Cleaning shall extend for at least 25 millimeters from the pipe edges on both internal and external surfaces. Prior to thermal cutting, pipe shall be heated to a temperature of between 30º C in the vicinity of the cut. Field bevels shall be cut by machine tool or by automatic or semiautomatic oxy–acetylene means only. Manual cuts using oxy-acetylene torches shall not be permitted. Burns, small score marks, indentations or other small defects within the joint preparation area shall at the discretion of the welding inspector, be blended out by grinding, otherwise, the joint shall be re-prepared. No repairs of bevels by welding shall be permitted. Gas RMS Bib-III 225 All cutting swarf or shavings from beveling or cutting pipe shall be collected and removed from the construction site. Bevel cut ends shall have dimensions and geometry as per the applicable codes and standards. Pipe and heat jumpers shall be transferred to both ends of lengths of pipe cut from any joints of pipe. Should any lamination or split end be discovered at the pipe end, either before or during welding, the joints shall be cut back a minimum of 300 millimeters and rebeveled to the satisfaction of Purchaser/Employer. If the cut back also revels such a defect, the rest of that full joint shall be removed and clearly marked as defective. Such joints of pipe shall be stockpiled and records kept of all data and identification marks on each joint. 45.4 Line-up: The ends of pipe-to-pipe or fitting-to-pipe shall be aligned as accurately as practicable. Methods of alignment shall comply with ASME B31.8 as they may apply. Line-up clamps shall be used on pipe with a nominal pipe size (NPS) of 2 inches and larger. Internal line-up clamps shall be used on pipes larger than 16 inch, except for tie-ins and other prohibitive joints. Spacing tools shall be used with lineup clamps to assure proper joint spacing and to permit full-weld penetration. Line-up clamps shall be left in place until a minimum of 50 percent of the root pass, half of which shall be diametrically opposite to the other half, has been completed. Pipe shall be lined-up to minimum the offset between surfaces. For pipe of the same nominal wall thickness, the offset due to misalignment shall not exceed 2 millimeters. Any greater offset, provided it is caused by dimensional variations within prescribed tolerances, shall be equally distributed around to circumference of the joint, but shall not exceed 3 millimeters unless a transition bevel is used. Longitudinal seams of adjacent pipe joints shall be offset a minimum of 100 millimeters and placed alternately in the two upper quadrants. Wherever possible, these conditions shall apply to seam welds in fittings. Branches, fittings and attachments shall be located such that the toes of welds are at least 50 millimeters from circumferential or longitudinal welds. Temporary pipe support used during line-up and welding shall be such as to minimize stress and sag in the joints being welded. Temporary support shall not be welded to the pipe. When tack welds are used for alignment purposes, only a sufficient number shall be made to ensure that alignments is maintained. Tack welds shall be completely remelted during welding and incorporated into the final weld. Tack welding shall be performed by qualified welders. Excessive hammering to align pipe is prohibited. Only hard rubber or other type of hammers that prevent notching of the pipe wall shall be used. No hammering shall be permitted once welding has commenced. 45.5 Welding: 45.5.1 General: Welding may be performed by manual gas tungsten arc and shielded metal arc or other approved welding process. Gas RMS Bib-III 226 45.5.2 Qualification: The qualification of ding procedures, welders and welding operators shal be in accordance with the latest edition of API STD 1104 of ASME Boiler Pressure Vessel Code, Section. IX. Prior to procedure qualifications, the Supplier/Contractor shall submit written welding procedure specifications, including repairs, to Purchaser/Employer for review and approval. The Supplier/Contractor shall only use welders and welding operators qualified for the specific approved welding procedure. 45.5.3 Procedure: Prior to welding, the surface shall be thoroughly cleaned and dried and shall be free of paint, oil, rust, scale and any other material detrimental to weld quality. Each weld bead shall be cleaned by power grinding or brushing prior to deposition of successive bead. The hot pass shall be applied immediately after the stringer bead is completed. If the hot pass is not applied immediately after the stringer bead is completed, the stringer bead shall be inspected and repaired, and the joint shall be preheated prior to applying the hot pass. Stringer bead repair and joint preheat shall be in accordance with the approved welding procedures. Protective pads shall be used when welding pipe with shop applied coating to prevent coating damage from weld spatter. 45.5.4 Welds Ends on Valves: Before welding to weld ends on valves, the Supplier/Contractor shall take appropriate measures to prevent splatter of other foreign matter from entering the valve. Prior to welding, internal passage leading to the valve seats shall be cleaned by blowing with compressed air or by washing with solvent or detergent. All welding shall be performed with due care taken to prevent damage to the valve seat assembly and sealing surfaces by the action of overheating. The Supplier/Contractor shall perform the welding with the valve in the fully open position. 45.5.5 Welds Defects: Weld defects may be repaired following procedures described in ASME B31.8 and the approved welding procedure for repairs as required. Each weld shall be identified as specified in ASME B31.8. Welding not clearly identified may be rejected by Purchaser/Employer. The Supplier/Contractor shall prepare and submit to Purchaser/Employer a daily report which shall include, as a minimum, the welder’s symbol, total number of weld defects on one job and weld defects in the last 50 welds for each welder. Purchaser/Employer shall review the daily weld defect report and instruct the Supplier/Contractor of remedial action based on the approved procedure. 45.6 Fabrication: The Supplier/Contractor may elect to prefabricate piping on site for installation later, or to install the piping by working in a continuous and sequential manner. If the Supplier/Contractor elects to prefabricate the piping, he shall be responsible for the preparation of spool pieces, including adequate cutting lengths to perform Gas RMS Bib-III 227 the work. The spool pieces shall be prepared in such a way as to minimize the number of field welds required to install the piping in place. The Supplier/Contractor may also elect to prefabricate the main piping at a location remote from the construction site. If so, the work shall be done in a prefabrication shop that is inspected and approved by Purchaser/Employer. When two different grades of material are covered by different welding procedures, the weld shall be made with the procedure for the highest grade material. The minimum pup joint length shall be 1.0 times the pipe diameter or 150 millimeters, whichever is greater, unless otherwise approved by Purchaser/Employer or required for proper fit-up. The cutting of 90 degree welding elbows to make 45 degree or non--standard angle elbows is permitted; provide the cut end is re-beveled as specified, subject to approval by Purchaser/Employer. The minimum distance between pipe girth welds and supports shall be as follows: * * * * pipe smaller than 4 inches from 4 inches to 10 inches from 12 inches to 16 inches 20 inches and larger 300 millimeters 450 millimeters 600 millimeters 750 millimeters All openings for vents, drains, instruments, controls and other similar connections made after the piping system is fabricated shall be drilled. No torch cutting shall be permitted for these openings. 45.7 Installation: 45,7.1 General The Supplier/Contractor shall prevent contamination to piping during construction by installing watertight plugs on the end of pipe at the close of each day’s work. Unless otherwise indicated on the drawings, piping field welds and connections shall be performed when the pipe metal temperature is at least 20 oC, but less than 45o C. Pipe metal temperature shall be measured at each end and at the center of each piping run at the time of tie-in. Piping connections between equipment and headers shall be started at the equipment flanges, and then continued toward the pipe rack system or manifold. Gravity drain lines shall be sloped as shown on the construction drawings. Cold springing of misaligned pipe shall not be permitted. 45.7.2 Flanged Connections: Bolting shall be in accordance with ASME B31.8 as applicable. Flanges shall be installed such that bolt holes straddle the vertical centerline, except where equipment flanges are oriented otherwise. Stud bolt threads shall be lubricated with graphite thread lubricant before installation of nuts. Gasket and flanges faces shall be thoroughly cleaned of all foreign matter before installation. A minimum of 2 (two) threads at each nut shall be exposed after properly tensioning bolts. 45.7.3 Threaded Connections: Threaded pipe shall be installed as shown on piping plans, sections and isometrics. Gas RMS Bib-III 228 Ends of pipe shall be cut square and reamed. Threads shall be cut using thread cutting lubricant and shall be straight and to proper length. Threads shall be wire-brushed to remove burrs. All damaged or substandard threads shall be rethreaded. All threaded connections shall be made up tight using Tetra Floro Ethylene (TFE) tape or approved equal on male threads only. Threaded unions shall not be installed in straight runs but in offsets to facilitate installation and removal. 45.8 45.7.4 Supports: The Supplier/Contractor shall adjust all pipe supporting elements as may be required during erection and before initial operation. Pipe supports shall also be adjusted during commissioning and initial operation. After all piping systems have attained normal operating conditions; each pipe-supporting element shall be checked in the hot position and readjustments made. Final setting shall be inspected, recorded and certified to meet the requirements of the applicable codes and this specification. Inspection: 48.8.1 General: The Supplier/Contractor shall be responsible for the inspection and documentation of its work. Purchaser/Employer shall have the right to inspect materials and procedures at any time during the construction process. The Supplier/Contractor shall provide the required access for such inspections. 45.8.2 Radiography: Radiography procedures shall be performed as per ASME B31.8 and specifications QC Discipline Requirements, as applicable. When radiography equipment is being used on the site, the Supplier/Contractor shall ensure that the area surrounding the equipment is clean and that all personnel are at a safe distance from the radiation source. The Supplier/Contractor shall confer with the radiography technician to establish the safety perimeter. Full circumferential radiography shall be performed on a minimum of 100 percent of the welded joints as follows: - lines with ANSI 150 and higher ratings; - piping for process gas service, and -field tie-in welds and field welds of mating shop-fabricated piping spools. Purchaser/Employer reserves the right to have any or all welds nondestructively tested. Lines containing air and drains to atmosphere shall not be radiographed. Procedures for radiography girth welds shall be such that conclusive images of the entire welds are available. Welds of a size or type preventing conclusive radiographic images, such as branch connection welds, shall undergo magnetic particle, dye penetrate, or ultrasonic examination as approved by Purchaser/Employer. Where examination of any type shows a weld fails to meet code requirements, examination shall be made of two more welds made by the Gas RMS Bib-III 229 same welder. If either of the additional welds fails to satisfy the code, Purchaser/Employer may reject all work by the welder. Repairs to defective or rejected work shall be at the Supplier/Contractor’s expense. The Supplier/Contractor shall maintain a daily log of all inspected welds and the disposition of welds. Records shall be traceable to a specific weld, welder identification, and location. The radiographic record system shall be submitted to Purchaser/Employer for approval. 45.9 Hydrostatic Testing: 45.9.1 General: All piping components shall be checked for correct pressure ratings before hydrostatic testing. The Supplier/Contractor shall hydrostatically test all process piping in accordance with applicable ASME B31.8 requirements and specification QC Discipline Requirement. Pumps, gauges and non-in-line instruments shall be tested as part of piping system unless otherwise directed by Purchaser/Employer. Control valves and in-line instruments shall be tested as part of the piping system unless otherwise directed by Purchaser/Employer. Low-pressure portions of control valves and instruments shall be protected from overpressure during test. Rotating spool pieces or removing valves shall be subject to approval of the Purchaser/Employer. Instrument gas lines, as well as vents and open drains shall not be hydro tested. The Supplier/Contractor shall provide the necessary tools and apparatus to generate a permanent record of pressures and temperatures applied during the test period. Temperature recording instruments shall accurately measure water temperature along the total length of the test segment. The Supplier/Contractor shall submit all test plans, hydro test testing forms, procedures and details to Purchaser/Employer for approval. High point vents and low point drains shall be installed subject to approval of Purchaser/Employer. The Supplier/Contractor shall furnish a strainer with a 100-mesh filter to prevent pumping mud and other foreign materials into the pipe during the fill operations. Girth weld and other fabrication welds shall not be painted or coated prior to hydrostatic testing. Pipe mill produced seam welds may be painted prior to hydrostatic testing. 45.9.2 Test Medium: The test medium shall be water for all piping. Water used for hydro testing shall be fully deoxygenated to 20 ppb maximum dissolved oxygen and treated with bactericide to kill sulphate-reducing bacteria before use. Water quality and chemical addition programs shall be specified by the Supplier/Contractor and approved by Purchaser/Employer. The Supplier/Contractor shall be responsible for filling, removal and disposition of all test waters. Temporary drain points may be installed where approved by Purchaser/Employer. Any drain points shall be plugged and seal-welded as directed by Purchaser/Employer. Air from the test segment shall be completely removed before pressurization. The test shall start after the water temperature has stabilized. The test shall Gas RMS Bib-III 230 be postponed if weather conditions do not permit stabilized test temperatures. 45.9.3 Duration: The test pressure holding time shall be minimum 2 hours. Additional time may be necessary to conduct an examination for leakage. 45.9.4 Valves: When a piping system of one rating connects to a piping system of a different rating at a valve flange, the valve shall be included in the test of the system with the greater rating. When a piping system terminates at a screwed valve, this valve shall be included in the test with the other end plugged. All plug type valves shall be greased prior to hydrostatic testing. Testing shall be performed with valves open. On completion of hydrostatic testing, the Supplier/Contractor shall ensure that the body cavities of all valves are free of water. This shall be done by injecting sealant into the valve, using methanol to absorb the water, followed by an application of glycol. 45.9.5 Leak Detection and Repair: The Supplier/Contractor shall be responsible for reading, recording and analyzing pressure and temperature data to determine whether leaks are present in the piping. This activity shall be witnessed by Purchaser/Employer. All leaks shall be located and repaired by the Supplier/Contractor. Above ground piping shall be visually inspected during hydrostatic test for evidence of leaks. After any leaks or failures disclosed by the pressure tests have been repaired, the test shall be repeated until the pressure can be satisfactorily maintained and is accepted by Purchaser/Employer. 45.9.6 Certified Records: A certified record of test pressures, temperatures, time, pressuretemperature variation calculations and test notes shall be furnished to Purchaser/Employer as part of the as built records. 45.9.6 Cleaning and Drying: After removal of all test water the piping shall be cleaned and dried by blowing dry compressed air through the line, until no free water is evidenced at any low point drain and a dew point of at least – 40 o C is achieved. The test section shall then be closed in and allowed to stand for 24 hours, after which the low point drains shall be rechecked for free water and the dew point rechecked. 45.10 Pneumatic Test: 45.10.1 General: Pneumatic (instruments gas) supply and signal piping not subject to mainline pressures shall be tested pneumatically, and connections shall be checked for leaks by soap bubble tests or other methods approved by Purchaser/Employer. Gas RMS Bib-III 231 45.10.2 Air Blowing: The Supplier/Contractor shall air blow all instrument gas lines with compressed air dried to a dew point of –23 o C, supplied at 150 psig in such quantities as to dislodge and eject from the piping all debris and/or residue left in the lines. All instrument gas lines shall be blown in such a manner as to prevent contamination of previously accepted lines. All lines shall be blown until there is not evidence of dust or debris escaping from the lines during blow down and until the exhaust air has a dew point of –7 o C or below. The Supplier/Contractor shall submit a blow down diagram to Purchaser/Employer that designates which lines will be blown down and the sequencing to ensure that all interconnecting lines are cleaned. Nitrogen may be used in lieu of air for blowing the instrument gas lines. 45.10.3 Pneumatic Leak Test: The Supplier/Contractor shall test all instrument gas lines for leaks after air blowing and before commissioning. Oil-free air or nitrogen shall be used to pressurize air pipe to the specified operating pressure. Tests shall be in accordance with ASME B31.8. After pressurization of lines, the Supplier/Contractor shall bubble-test every connection with a soap solution. To facilitate the bubble test, the gap between facing flanges shall be sealed with tape around the circumference of the flange, and a pinhole shall be punched into the tape. The pinhole shall then be bubble-tested for leaks. 45.11 Adjustment and Tightness Guarantee: The Supplier/Contractor shall remedy all leaks in the piping system and system appurtenances that may develop during hydrostatic and pneumatic testing and precommissioning. All pipe shall be guaranteed by the Supplier/Contractor to be leaktight at the design temperature and pressure. 45.12 Painting: External metallic surfaces shall be cleaned, primed and painted in accordance with applicable painting standards. Surfaces that will be insulated shall be primed by not top-coated. Fabricated piping, excluding areas with 75 millimeters of a fabrication weld, may be painted prior to hydrostatic testing. Fabrication welds shall be hydrostatically tested prior to painting. 46. Mechanical: 46.1 Installation: After the piping has been installed, the equipment flanges shall be checked with a feeler gauge for proper face alignment. When the flange stud bolts are tightened, no equipment misalignment shall be permitted. Flanges shall be aligned so that when the stud bolts are loosened, the studs may be removed freely. The Supplier/Contractor shall thoroughly clean and check equipment foundations for level, dimensions and anchor bolt locations before installation of equipment. Skids and base plates shall be inspected and cleaned of all scale, rust, grease, oil, or other matter that could prevent adequate bonding of grouting before placement in the foundation. Gas RMS Bib-III 232 Grouting of equipment shall be in accordance with the project documents and shall be poured only after equipment alignment has been set at the elevations specified on the drawings. The Supplier/Contractor shall follow manufacturer’s specific requirements for the installation and alignment of equipment. Equipment alignment shall be rechecked after equipment is secured to the foundation, and again after ancillary equipment and piping are installed. After grout has cured, disassembled equipment components shall be installed and equipment secured in place as per the manufacturer’s directions. Electrical components and instrumentation shall be installed in accordance with the project documents. 46.2 Checklist: After installation and before testing, the Supplier/Contractor shall inspect and pretest the equipment and prepare a checklist to ensure compliance on a point-bypoint basis with the manufacturer’s installation and testing procedures. The list shall include a summary of all adjustments and corrective actions performed. Purchaser/Employer will sign off each such completed action. The Supplier/Contractor shall provide a written log of all tests performed, including time of test and results. As build Documentation: 47. The Supplier/Contractor shall provide “as built” information consisting of revision to each piping drawing and isometric, complete with field notes and reports to accurately document the installation of the equipment and piping system. Supporting field notes and reports shall include: • • • • • • Notes identifying all field changes required to correct errors found in existing drawings. A record of the location and dimension of all underground piping, fittings, valves, concrete supports, cable banks and foundations. Field welds logbooks and radiographic logbooks. Flanged joints bolting reports showing bolts furnished, torque applied, gaskets furnished and leaks found. The location of changes in pipe grade, wall thickness, size, welding procedure and test pressure. The location of all valves, instrument fittings and instrument connections. H. 48. Construction Specification: Electrical Scope: This specification covers the general requirements for the equipment materials and design of electrical installation for operating the Flow Computer of Bibiyana-III, 400MW Combined Cycle Power Plant , Habiganj. 49. Codes Standards and Specifications: The electrical installations shall conform where applicable to the latest edition of the following codes standards and specifications. API RP 500 Recommended practice for classification of locations for Electrical Installations at petroleum Facilities. IEEE Gas RMS Bib-III Institute of Electrical and Electronic Engineers 233 IEC 79-10 Electrical apparatus for explosive gas atmospheres, Part 10: Classification of hazardous areas IEC 364-5- Electrical installations of buildings Part 5: Selection and erection of 54 electrical equipment Chapter 54: Ear thing arrangements and protective conductors. 50. NEMA National Electrical Manufacturers Association NFPA 70 National Electrical Code (NEC) UL Underwriter’s Laboratories Area Classification: The pipeline facilities shall be classified in accordance with the application sections and latest editions of API RP 500 and IEC 79-10. All equipment and materials shall be listed and labeled by Underwriter’s Laboratories (UL) or IEC equivalent for usage in designated area classifications. 51. General: These specifications are intended to supplement the construction drawings and to serve, as an installation guide for activities not detailed on drawings .In the event of conflict between these specifications and the drawings the information shown on the drawings shall govern. In the absence of any specification covering an installation activity the construction manager shall be consulted. 52. Power Supply and Electrical System Design: General electrical system shall utilize the voltages and frequencies indicated inTable-1 Supplier/Contractor is to determine if sufficient and reliable electrical power is available at the site. Also the Supplier/Contractor should be aware of wide voltage variation of the nearby power source. As such Voltage stabilizer equipment shall be installed. Maximum variation allowed at secondary may be 230/440 ±10% (static), 230/400 ± 15% (dynamic). Voltage drop on motor starting shall be limited to 10 percent. Voltage drop on feeders shall be limited to 3 percent and a maximum overall voltage drop of 5 percent from service equipment (i.e. motor control center) to final utilization equipment. The main power supply shall be obtained by the Supplier/Contractor from the 400MW Combined Cycle Power Plant source. A temporary connection from nearby PDB source may be taken if required by the Contractor/Supplier. A UPS system shall be installed to provide 8 hours back up power supply for the critical equipment like instrumentation, Flow computer and its control panel, printer and safety systems for the RMS. The out put voltage shall be 24V DC. The power feeder shall run from the 400MW Combined Cycle Power Plant source to a Power Distribution Board (PDB) located in the control building. The power distribution board (PDB) shall distribute power to plant / building lighting, station process and control equipment and UPS charger. 53. Electrical System Requirements: The electrical system shall utilize the voltages and frequencies specified in the design basis The voltage spread at the motor terminal of three phase motors shall be no more than + / -5 percent, The voltage spread at lighting fixtures shall not exceed +/-5 percent of the rated lamp or ballast voltage. Gas RMS Bib-III 234 The voltage drop in cables shall not exceed the following in percentage of system nominal to neutral voltage: • All motor feeders: 3 percent at full load current and 10 percent at full voltage locked rotor current. • All other feeders: 3%(percent) at full load; • Lighting feeders: 1%(percent), and • Any branch circuit (including lighting): 2 percent The total voltage drop in any complete circuit shall not exceed 5%(percent) from the point of service to the utilization equipment. The voltage drop shall be calculated based on the minimum short circuit level of the supply. 54. Distribution Equipment: 54.1 Motor Control Centres Motor control centers shall be required to provide power and control to motor loads. Equipment and circuits operating on a system voltage indicated in table 1 shall be controlled and protected by starters and other devices grouped in factory built motor control centers located in the control buildings. Starters and other devices shall be arranged in individual compartments, fed by bus bars. Motor starters shall be combination type with motor circuit protector (MCP) adjustable trip breaker and be furnished complete with an integral control power transformer and three overload elements. Contactors shall be magnetic, combination, circuit breaker type, and thermal magnetic circuit breaker, complete with integral control power transformer. 54.2 Feeder circuit breakers shall be molded case thermal magnetic. Power Distribution Board (PDB) In general, Power Distribution Board for power and lighting are three phases four wires rated for the voltage levels 230/400 VAC, 50 Hz - 3 phase, 4 – wire with main circuit breaker and 20 ampere minimum branch circuit breakers. Power Distribution Board shall be located in the control buildings. Power Distribution Board shall be installed at a height not exceeding 1.8 meters from the floor or walkway to the centerline of the topmost breaker. Branch circuit breakers shall be sized to permit circuit loading to a maximum of 80 percent of rating. Equipment Receptacles Outlet receptacles shall be rated for the voltage levels indicated in Table 1 and installed in all control building. Receptacles are not required to be located in general yard and process areas. Power transformers shall be built in accordance with IEC publication 76. Lighting and distribution transformers shall be three-phase delta primary, Wye secondary or single-phase indoor open ventilated dry type, 1500 C rise with two 2.5% full capacity taps above and four 2.5% full capacity taps below nominal voltage. Gas RMS Bib-III 235 54.3 Uninterruptible Power Systems: Backup power for Flow computer, Transmitters, programmable logic controlle (PLC) and printer shall be provided from a dedicated UPS. No general purpose lighting fixtures, convenience outlets or other type of utility outlets shall be connected to these UPS circuits. UPS power outlet receptacles shall be colorcoded orange. The UPS system components shall be self-contained with the appropriate sized batteries, battery chargers and manual bypass switch. 54.4 55. The UPS battery system shall consist of sealed lead calcium or nickel cadmium maintenance free batteries that are suitable for installation in control room environments and do not require special ventilation. Battery system capacity shall be sized for minimum 8 hours of backup power The UPS system shall be sized according to load requirements. Input power to the UPS shall be fed from the motor control center or PDB. The UPS and battery systems shall be located in the control buildings. The total load shall not exceed 80 percent of the UPS full load rating. DC power required for instrumentation and /or other electrical loads shall be provided by the package vendor. Motors (For Heater): Power to motors shall be supplied by a motor control center or by individual wall mounted combination starters located in the Heating Skid. All motors shall be rated for continuous duty with a minimum 1.15 service factor and shall meet the requirements of IEC Standards for use in the applicable classified areas Motor winding insulation shall be type required by IEC or NEMA. Motor windings and construction shall be rated for tropical environment. Oil lubricated bearings shall be equipped with a device for visible indication of oil level. Grounding: All metallic structures vessels, conduit duct banks, manholes, cable tray, fencing and electrical equipment shall be permanently and effectively grounded to provide safety and protection for personnel and equipment. All grounding installations are to comply with IEC publication 364-5-54. Maximum resistance to ground shall not exceed 5 ohms. The grounding systems shall consist of grounding electrodes, ground loops, ground grids, deep wells and connections to all equipment requiring grounding. Main grounding cables shall be installed stranded annealed copper cable not smaller than no 4/0 American Wire Gauge (AWG). Taps shall consist of insulated or bare copper cable not smaller than of 2 AWG. Motor and equipment rated above 600 volts shall have a minimum of 2 (two) ground connections from the terminal enclosure to the ground grid. All motor control centers, switch gear and large equipment shall have a minimum of 2 (two) ground connections one at each end of equipment. All above ground grounding connections shall be bolted to equipment or structures by means compression connectors. This includes such equipment and structures as meters, skidded equipments junction boxes control stations, building columns, pipe racks and structural steel. Gas RMS Bib-III 236 Where soil resistively measurements show that individual grounding electrodes will not achieve maximum 5 ohms resistance to ground a ground grid shall be installed consisting of a main cable loop connecting distributed grounding electrodes and branch cables connecting individual facilities and a deep well anode bed. Exposed ground cables shall be protected with short lengths of Schedule 40 or Schedule 80 PVC conduit where there is substantial risk of mechanical damage when installed so as to minimize mechanical injury. Station grounding shall be isolated from pipeline grounding by insulated flanged or unions at connection points to the main line. A separate equipment-grounding conductor shall be furnished in all power cables and conduit runs. Grounding conductors shall be bare stranded copper or with green insulation. All buried connections to ground electrodes and cable shall be by means of exothermic welding or compression connectors. All shielded instrument cables shall have the shield drain wire connected to ground at the main control panel terminals. Should wires and shields shall be isolated from ground at the transmitter or sensing end. At all junction boxes, the shields shall be connected as if they were a continuous conductor. Equipment capable of accumulating a static charge (i.e. storage tanks, heat exchangers, process vessels) shall be grounded to a connection to the ground network or by bonding to a grounded metal structure. Ground rods shall be copper clad steel, minimum 3 meters long ¾ inch diameter. Ground rods are to be located a minimum of 4.5 meters from all piping. Grounding bushings with insulated throats will be used on all conduit ends. Connections between ground rods and ground grid shall be accessible for inspection and testing through the use of ground wells. 56. Cable Tray: Cable tray systems shall be installed using the tray sizes designated of the construction drawings. Cable trays shall have strong rigid supports such that they • Will have no deflection exceeding 6.35 mm with maximum cable loading • Can resist vibration, and • Can support full load of cables plus an additional 113 kg at mid-point of supports (on 4.6 meters centers) No cable tray shall be installed which has been crushed, deformed or damaged in any way. No cable tray shall be installed within 6 inches of the insulation on hot process or steam lines. The end of each field cut section of cable tray shall be reamed and filed to remove burrs before assembly. Site fabrication and cutting of sections shall be kept to a minimum. For sections that are fabricated or cut of site all sharp edges shall be filled smooth to eliminate projections that may damage cable. Installation and routing of the cable tray shall be in accordance with the construction drawings. The installation shall be neat, level and plumb both horizontally and vertically. Multiple trays shall be run parallel, evenly space and in a straight line unless noted otherwise on the drawings. Gas RMS Bib-III 237 Cable trays shall be bolted or clamped to supports. For long span installations where there is only one support per cable tray straight section the splices shall be located at points on quarter of the distance between supports where the load stresses on the side rails will be at a minimum. Only the material listed on the drawings shall be used. Substitution of inferior quality material is not acceptable. Cables shall be secured to trays at 1-meter intervals on vertical trays and 3-meter interval on horizontal trays with cable ties. Cable trays shall be supported when routed vertically at a minimum of every 610 mm. Cable tray covers shall be installed on all exterior cable trays and where cables in interior tray are exposed to physical damage. 57. Rigid Galvanized Steel Conduit (If Required): Rigid galvanized steel conduit shall be used in all locations specified on the construction drawings. Underground conduit shall be rigid galvanized steel with PVC coating or Schedule 40 or Schedule 80 PVC with a minimum 51 mm concrete cover. Minimum size of conduit shall be ¾ inch except that on pipe racks the minimum size shall be 2 inches to span 4.9 meters with supports. Conduit connections to junction boxes shall be made using insulated watertight threaded hubs or factory threaded hubs. All rigid galvanized steel conduits shall have metric standard threads, or ANSI standard threads tapered 0.75 inch per foot and shall be factory cut or field cut with dies designed specifically for the type of conduit being threaded. Aluminum threading dies shall not be used on steel conduit. Continuous running threads are not acceptable. To minimize sparing if fault current flows through the conduit system the conduit joints shall be made up wrench tight. Crouse – Hinds type ST-L thread compound or equal thinned with lightweight motor oil (SAE 30) to the ratio of-2-to 1 (oil –to-compound) shall be applied to conduit threads before make up. After make up the exposed field cut threads shall be cleaned of thread compound.. Bends in 1 inch and smaller hot-dip, galvanized conduit shall be made with manufacturerapproved bending tools. Bends in 1 ¼ inch and larger hot dip galvanized rigid conduit shall be made with hydraulic or mechanical benders designed specifically for the type of conduit being bent. The effective internal diameter of the conduit shall not be reduced in the bend. The centerline radius of a field bend shall not be less than 7.5 times the nominal conduit diameter Conduits shall be installed in a workmanlike manner, level and plumb both horizontally and vertically neat and uniform bends and offsets, with repaired wrench marks and with multiple conduit runs parallel to one another and in a straight line. Conduits shall be supported at such intervals as required to prevent objectionable sag. Support for rigid galvanized steel conduit shall be as per IEC recommendations. Conduit support materials shall be compatible with the type of conduit used in the specified atmospheric conditions. The following are acceptable support methods for hot dip galvanized rigid steel conduit installation in the order of preference. Gas RMS Bib-III 238 • Hot –dip galvanized Uninstructed or equal channel with hot dip galvanized hardware. • Hot-dip galvanized or stainless steel/ u-bolts/ and nuts and • Galvanized, one hole, malleable iron conduit straps with countersunk stainless steel or hot dip galvanized bolts and nuts (not to be used for supporting horizontal runs on the underneath side or outside of structural members). 58. Flexible Metallic Conduit (If required): Flexible metallic conduit with a PVC jacket shall be used in Zone-2 (class-1, Division-2) area, and non-hazardous areas at locations where flexibility is required. Terminations of flexible metallic conduit shall be made using connectors that are matched to the flexible conduit so as to provide ground continuity. Outdoor terminations shall be waterprove. The minimum length for flexible conduit shall be 457 mm for straight runs and 310 mm for angled runs. Connections to junction boxes or terminal boxes shall be rigid. Flexible connections to arc marking devices in a Zone-2 (Division-2) area, having integral terminal chambers shall be fitted with a conduit seal and union adjacent to the device. Flexible connections to are marking devices in a Zone-1 (Division-2) area, without integral terminal chambers, shall have a condulet/close-nipple to the device to make wiring connections and conduit seal located adjacent to the don culet. Flexible connections to devices in Zone-1 or 2 (Division-1) areas shall be explosion – prove. 59. Electrical Metallic Tubing: Electrical metallic tubing (EMT) may be used only in concealed, dry areas where not subject to mechanical damage. Minimum size shall be ¾ inch for home runs. EMT fittings shall be steel compression-type fittings. Die cast fittings are not acceptable. EMT, which is 1 inch and smaller may be bent using a manual bender. EMC 1 ¼ inch and larger shall be bent using a hydraulic bender manufactured specifically for bending EMT. Where EMT must be field cut, the end of each EMT shall be reamed and filed to remove burrs before assembly. 60. Wire and Cable: 60.1 Wire and Cable Electrical circuits shall be installed in accordance with the construction drawings using one of the following methods. • Single conductor or multi conductor insulated and jacketed wires or cables drew in conduit minimum no 12 AWG and no 14 AWG for instrument and control. • Multi conductor insulated tray rated cables installed in cable trays or direct buried. Metal clad cable shall be used where cable is direct buried or subject to mechanical damage. • Type SIS, 90ºC rated 600 volts, tinned copper and sized for the applications shall be used for internal wiring in equipment. All wire and cable shall be continuous without splices from origin to termination as far as practicable where splices are equaled they shall be made in approved junction boxes. No splices or repaired wires or cables will be permitted within conduits or cable trays between approved junction boxes or between pull points. No wire or cable with damaged i8nsulation or jacket shall be installed. Gas RMS Bib-III 239 All multi conductor armored cables shall remain sealed until immediately before termination. Maximum cable bending rail shall not be less than indicated in the following table expressed in terms of multiples of cable diameters. Cable Minimum Radius 1 inch OD or less 10/64 inch insulation or less 11/64--20/64 inch insulation 3 4 times OD times OD 5 7 8 times OD times OD times OD 8 times OD 1 –2 inch OD 10/64 inch insulation or less 11/64 20/64 inch insulation 21/64 inch insulation or more Control cables 19 conductor and larger Flat type and wire armored cables, 12 single conductor or multi conductor times OD Tape shielded cable 12 times OD 10 12 15 times OD times OD times OD Shielded cable Not more than ¾ inch OD Not more than 1 ½ inch OD More than 1 ½ inch OD Conductors in vertical cable trays shall be supported by strapping the conductors directly to the cable tray rungs with insulated tie wraps or by clamping in isolated blocks fastened to the trays. 60.2 Cable installation in T ray: Cables shall be laid in place or pulled with a basket type (Kellems or equal) pulling grip, Care shall be exercised when pulling the cable to avoid damaging the tray and cable. Cable shall be laid in single layers and parallel in the tray with no twists or corroders. Cables shall be spaced from each other by a distance of not less than one fourth of the cable diameter. In general all cables shall be run in continuous lengths from the point of origin to their destination. Where splices or taps are necessary they shall be made in as approved junction or splice box. 61. Splices, Taps and Terminations: All splices, taps and terminations of 600 Volts or less insulated conductors shall be made using crimp-type compression sleeves, insulated ring-type lungs. The compression fittings used shall be compatible metallurgical with the conductor material and shall be compatible with the wire, crimpling tool and terminal strips. Silver-plated copper body fittings shall be used on copper conductors only. No aluminum shall be allowed. Six hundred volt cable connections requiring field installed insulation shall be wrapped uniformly with rubber tape to a minimum thickness of twice the cable insulation thickness and then covered by two layers minimum of neoprene tape, Scotch no 88 or equal, applied snugly but not stretched. Gas RMS Bib-III 240 Connections to the 5 kilovolt and 15 kilovolt-shielded cables shall be made with stress cones. The 5 kilovolt and 15 kilovolt connectors shall be made in accordance with the cable and stress cones manufactures recommendations. Thermocouple wires shall not be spliced. Duplex thermocouple wires shall be continuous from the thermocouple heads to the receiving instruments. Thermocouple terminal blocks shall be compatible with the alloys of the thermocouple extension wires and the multi conductor thermocouple cables attached thereto. Thermocouple extension wires will be terminated bare (no lungs). Every wire and terminal point shall be clearly marked colour coded and / or numbered to correspond with drawings. No more than two conductors may be terminated under one screw. Wiring harnesses to terminal strips shall be so formed that rerouting is possible. Spare conductors shall be taped and bundled together with sufficient pull out for the most distant terminal in the panel. Slip on plastic markers shall be used (Raychem or Brady sleeve typewriter/printable type). Information on wire markers shall be typed. Hand written labels are not acceptable. All lighting panel circuits shall be permanently labeled on panel door. 62. Conduit Fittings (If required): 62.1 Conduit fittings, junction boxes, unions, seals and device enclosures shall be installed as shown on the drawings. All fittings installed shall be new, unused and in good condition. Substitution of material shown on the drawings will be permitted only if the replacement material is of the same type and size as the original material specified. Vapor – tight and explosion-prove materials shall not be interchangeable. Ground joint and threaded covers of explosion prove fittings and device enclosures shall be coated with. Crouse Hinds “ ST-L “ or equal, thread lubricant to prevent corrosion of the ground joint surfaces and to prevent galling of the threads. No threaded fitting with a cracked hub shall be left in the final installation. All covers shall be secured in place and all unused threaded openings shall be plugged. During construction, open conduits and fittings that are outdoors shall be plugged or covered to prevent the entrance of rain water when there is a possibility that electrical current carrying devices might be subjected to exposure to water. Threaded conduit connections to conduit fittings, function boxes, union’s seals and device enclosures shall be made up wrench-tight. Hand tight assembly is not acceptable. 62.2 Junction Boxes No. holes shall be drilled through the body of an explosion prove /Intrinsic safe or vapor-tight junction box for mounting the box or mounting internal devices in the box. Internal devices may be mounted by means drilled and tapped holes (drilled only partly through), epoxy cement or contact cement. No top entry of conduit into junction boxes shall be permitted. Gas RMS Bib-III 241 Junction boxes shall be installed in locations such that the covers and internal wiring are easily accessible. Care shall be exercised in the placement of spliced wires in junction boxes so that the wire or joint insulation will not be injured when the cover is fast ended to the box. Internal wiring in large enclosure shall be done in a neat orderly manner particularly if relays and terminal blocks comprise part of the internal equipment. All wirings shall be square with the sides of the enclosure and shall be neatly tied in bundles or placed in prefabricated wiring troughs. All wires shall be tagged as shown on the drawings with wire markers. 62.3 Conduit and cable seals Seals/cable glands shall be installed to prevent passage of hazardous gases in the conduit or cable systems from an unclassified to a classified location and to prevent entry of water into a enclosure. Pouring of seals shall be delayed until all circuits passing through the seals have been verified as being correct. At that time, the wires passing through the seals shall be packed with fibers of suxseal to prevent sealing compound from draining into the conduit systems or enclosures. It is very important that seals above enclosures containing control devices be properly packed (dammed) before pouring the sealing compound in order to prevent the compound from draining into the devices. 62.4 Unions Both halves of unions installed in conduit systems should be accurately aligned before attempting to tighten the union nuts so as to preserve the explosion prove rating of the unions in hazardous areas. Conduit unions are not designed to be waterprove hence care should be observed in their installation. Unions installed outdoors above seals, fittings or enclosures shall be installed so that the union nut is non the top of the union. After the union nuts is tightened, the clearance between the top half of the union and the conduit shall be packed with a sealing compound to prevent moisture from entering the union. Union may be used to facilitate installations at locations not shown on the drawings. 62.5 63. Breathers and Drain. Conduit systems and device enclosures shall be equipped with drain fittings at low points. If the enclosure is not equipped with a moisture drain at least one of the entry conduits shall be fitted with a continuous moisture drain, Moisture drains shall be screen-covered to prevent entrance points for vermin. Horizontal conduit connectors shall be arranged to drain away from the enclosure. Motor Control Centres Installation: The motor will be used for the operation of the gas heater, burner & other equipments (if required) of the skid for which the floor or foundation supporting the motor control centre shall be level and smooth. Anchor bolts and hold down clips will be required only if the motor control centre is to be installed outdoors or subjects to high winds or severe vibration. All plug in modules and blank panels of the motor control centre shall be removed and a complete inspection shall be made of the structure after setting in place. All buses, bus supports and structure bolts shall be tested for tightness and a visual inspection shall be made for damaged bus supports, buses and for debris in the area of the buses. Gas RMS Bib-III 242 64. All plugs in units shall be inspected for tightness of factory cable connections before reinstallation in the motor control centre. All wiring shall be checked for loose connections and tagging in accordance with the manufactures final approved as built drawings All external feeder cables shall be checked for proper phasing continuity and insulation resistance phase to phase and phase to ground before connection to end devices using a direct current mugger. Motors shall be checked before connection to feeders for resistance to ground. Motor phase rotation shall be checked at this time using a phase rotation meter. If a phase rotation meter is not available, phase rotation shall be checked by emerging after feeders have been connected. Assure that all motor driven pumps are uncoupled before testing with this method. Circuit Breakers and Starters: 64.1 Circuit Breakers, fused and Disconnects and Fuses: All plug in units containing circuit breakers fused disconnect switches or fuse blocks for control circuits shall be checked as follows to assure that they conform to construction drawings and manufacturers approved fabrication drawings. Switches or fuse blocks for control circuits shall be checked as follows to assure that they conform to construction drawings and manufacturers approval fabrication drawings. • Circuit breakers shall have the number of poles voltage and ampere trip rating as specified. Circuit breakers with adjustable instantaneous magnetic trips shall be set as indicated on the drawings. Trip settings shall be adjusted upward one step at a time should the circuit breaker trip under operating conditions until the circuit breaker holds on inrush. • Fused disconnect switches are fuse blocks for control circuitry shall be of the number of poles voltage rating and ampere rating as indicated on the drawings. 64.2 Combination Starter Circuit Breaker: All plug in units containing combination magnetic starter and magnetic only circuit breakers shall be checked to assure that they conform to construction drawings and manufacturers approved fabrication drawings. Magnetic starters shall be of the correct number of poles, voltage rating and ICE (or NEMA) sizes as indicated on the drawings, with the starter foil voltage corresponding to the secondary voltage of the control transformer . Assure that the control transformer is of the proper voltage rating and is sized to accommodate any additional burdens such as motor space heaters. The correct number of auxiliary contacts both in service and spare shall be provided according to the drawings. Overload relay heater sizes shall be set at 85% unless otherwise specified on the drawings. This setting may be adjusted upward step by step to a maximum setting of 115 % should the relay trip under motor full load conditions. Assure that the minimum setting is provided at which the motor will operate continuously without tripping the overload relay. In no case should the setting be increased beyond 115% or the heater size be increased beyond the manufacturer’s recommended rating for the motor. Circuit breakers shall be checked as specified above. Gas RMS Bib-III 243 65. Power Distribution Boards Installation: 65.1 Foundations for switchgear shall be constructed in accordance with the manufacture’s recommendations and the construction drawings for the project. Floor and channels shall be flush and level to within 6 mm over any 1-m² area under and in front of the switchgear in order to maintain alignment of draw-out circuit breakers and fitting of the doors. Doors shall be checked for easy closing without binding and the securing screws shall be adjusted for easy tightening by hand. Draw out circuit breakers shall be removed from their cells and inspected for loose and broken parts and for corrosion. Buses and wiring shall be cheeked for loops and broken connections and for corrosion. Meters shall be inspected to assure proper range freedom of movement and absence of damage. Broken glass shall be replaced before field-testing. 65.2 Protective relays Shipping packing shall be removed from the protective relays and the rotating disks shall be checked for freedom of movement and for any damage on corrosion Broken glass shall be replaced before field-testing. 65.3 Circuit Breakers All interlock circuits shall check for functional conformity with the requirements of the project switchgear specifications. 66. Heating Ventilation and Air Conditioning: All electrical air conditioning / heating units and electric exhaust fans, feeders, branch circuit panels and grounding connections shall be installed in accordance with the construction drawings. Where any details of installation are not shown on construction drawings, all installation procedures, materials and devices shall be in accordance with the manufacturer’s recommendations and as directed by Purchaser/Employer. 67. Fire Protection: All ultraviolet /infrared sensors and combustible gas monitors and associated wiring and alarms shall be installed in accordance with the construction drawings. Where any details of installations are not shown on engineering construction drawings, all materials, devices and installation are not shown on engineering construction drawings all materials devices and installation procedures shall be in accordance with manufacture’s recommendations. 68. Anti-Lighting/Thundering Protection: The use of air terminal for lightning protection for buildings and other permanent structures (Heater) is recommended where a high risk of strikes are anticipated. Surge diverter/ lighting arresters shall be considered for system protection. 69. Lighting: Lighting fixtures shall be approved and suitable for installation in the classification in which they are installed. Fixtures shall not be mounted above equipments with exposed moving parts emits appreciable heats or fumes. Gas RMS Bib-III 244 Fixtures shall be mounted in such a manner that they are not obstructed by piping or cables trays. Fixtures shall be located facilitate re-lamping. Fixtures shall be mounted on standard pole above the ground at a suitable height. Lighting shall be controlled by switches from panel mounted on walls of the control building. Fixtures shall be mounted anti-vibration mounts, such as a flexible conduit , in building subject to vibration. 70. Future Provisions: 70.1 Equipment shall be designed with consideration for future expansion capabilities. Distribution and lighting panel boards shall be installed having a minimum of 10% spare circuit breakers and 20% space only. Motor control centers shall be installed having approximately 10% spare motor controllers and 20% space only. Each underground raceway run shall contain 10% spare conduits. Each multiconductor cable run shall contain 10% spare conductors. 70,2 Spare Parts: Spare parts for high-pressure sodium explosion prove lights, motor control centers and distribution boards shall be provided for one-year operation and / or 10% of all installed equipment. 71. Workmanship: Properly qualified tradesman shall execute all electrical work in a neat workmanlike manner. Any changes from drawings or specifications shall be recorded on a daily basis. Any deviations from the drawings or specifications shall be approved in writing, Any modifications on the drawings arising from field changes shall be marked on one set of drawings kept for such purposes and submitted for as built drawings. Careful attention shall be paid to the mechanical execution of the work in connection with any electrical installation. Any installation that has been poorly arranged or executed will not be accepted. 72. Testing: Testing and inspection shall be made to ensure proper operation of the equipment and systems before plant startup. The Supplier/Contractor shall supply all labour and equipment necessary for the support of testing and calibration activities. All errors or deficiencies found during the testing that are a result of construction activities shall be corrected. Each control loop shall be tested to assure that the entire loop operates as it was designed. Purchaser/Employer shall witness testing. 73. Equipments Marking and T agging: Nameplates, indicating equipment number and name shall be installed at switch gear, motor starters, circuit breakers, push buttons, lighting panels and miscellaneous electrical control devices, junction and pull boxes shall be marked with nameplates indicating box number as shown on the construction drawings. Gas RMS Bib-III 245 Nameplates shall be die stamped stainless steel and permanently attached to the respective component. Each nameplate shall be 425 mm high with 13 mm lettering. Conduit tags are to be provided for all spare conduits stubbed up through the floor for future identification Spare conduits are to be tagged at both ends. Other electrical equipment shall be tagged as specified on the construction drawings. TABLE-1 Electrical System Requirements Service Nominal Voltage System Control Building. 50 Hz - 230/400 VAC, 3 phase, 4 – wire Low Voltage Motor control centers, Power Distribution 50 Hz - 230/400 VAC, 3 phase, 4 – Panel Boards wire Motors 0.37 kw (1/2 hp/ 2 kw (2.5 hp) 50 Hz –400 VAC, 3 phase High Intensity Discharge Lighting (High Pressure 50 Hz –400 VAC, phase to phase ,2Sodium or Metal Halide)-Outdoor Area Floodlighting. wire. Motors below 0.37 kw (1/2 hp) 50 Hz – 230 VAC, 1 phase UPS DC, Emergency lighting, instrumentation, Telecom etc. I. 74. 50 Hz – 230 VAC, 1 phase 24 VDC 2- wire General Requirements for Pressure Vessels Scope: This specification covers minimum requirements regarding design, manufacturing, inspection and testing for carbon steel pressure vessels for design pressures>20<80 barg and temperatures between 5 o C and + 100 o C. This specification is a general guide establishing the minimum requirements for pressure vessels. Specific design data such as actual design pressure/ temperature and volume, dimensions, locations, installation, type of connection and equipment and the function etc. of the pressure vessels, will be given in separate specifications or in the tender documents. 75. References: 75.1 The pressure vessels shall be designed, manufactured and tested in accordance with the following documents to the extent stated in this specification: 75.2 Codes and Standards In this specification reference is made to the following Codes and Standards: ASME Boiler and Pressure Vessel Code, Section VIII. ASTM A435 API 5L. ASME B16.5. ASME A 388 ASME A 370 75.3 Specification Steel structures Specification will be as per applicable standard. Gas RMS Bib-III 246 76. Design and Manufacturing Requirements: 76.1 Design In addition to the codes and standards referred above, the pressure vessels shall comply with the following: high and low point – depending on the final installation shall be equipped with 1” flanged vent and drain connections. The drain opening shall be at least 500 mm above foundation level. each compartment of each pressure vessel shall have an inspection opening as required by ASME BPV-VII-1; gaskets and sealing material shall be resistant to natural gas, gas condensates, oil, glycol and methanol; the weld joint factor E of all welds in each pressure vessel shall be at least 0.85; each pressure vessel shall be equipped with lifting lugs. 76.2 Manufacture Only fully killed steel in accordance with the applicable material standard shall be used for the manufacture of pressure vessels. The specific minimum yield strength of the steel used for pressure vessels shall not be higher than 415 N/M². Steel castings shall not be used for pressure vessel components. 76.3 Welding Welding shall be carried out in accordance with section IX of the ASME PVB Code. All welding work shall be performed in accordance with suitable welding procedure specifications. All welding procedure specifications shall be submitted to the Purchaser/Employer for approval in a written form in accordance with the form recommended in section IX of the ASME Boiler and Pressure Vessel Code. Welding procedure qualification and welder’s performance tests shall be carried out and recorded in accordance with section IX of the ASME BPV Code. All joints shall be welded both from the inside and from the outside, where space allows> Plate offset and any welded joint shall not exceed 10% of the smallest plate /wall thickness of the joint or 1.5mm, whichever is less. Minor surface imperfection in the parent material may be removed by grinding , provided that the minimum wall thickness is not reduced to less than the calculated wall thickness. Grinding may take place over a length not exceeding 1.0 X D (where D is the diameter of the component in question) or 300mm, whichever is less, and shall leave a smooth contour. Repair welding of the parent material is not permitted. Welds shall only be repaired under the following conditions : -repair welding shall be performed only accordingly to approved procedures and by qualified welder; - only manual arc –welding with suitable electrodes shall be used for repair welds; - the defect shall be removed in such a way that the repair weld can be carried out with at least two passes; - items with repaired weld seam shall be completely stress-relieved after the completion of the repair work.; - Gas RMS Bib-III non-destructive tests according to the clause 16.4.3.1 of this specification shall be performed on all repair welds. 247 77. Inspection and Tests: 77.1 General Inspection and test certificates shall be submitted as specified on data sheets or, otherwise for pressure retaining parts, as recommended in the ASME BPV Code. 77.2 77.3 Inspection of Semi-Finished Products 77.2.1 Plate Material: Each plate to be used for the manufacture of pressure vessels shall be inspected for laminations by ultrasonic methods in accordance with ASTM A435. Acceptance or rejection of such plates shall be governed by the acceptability standards stated in ASTM A435. The Constructor/Manufacturer shall propose a method for such ultrasonic inspection, which shall be subject to approval by the Purchaser/Employer. 77.2.2 Tubular Material: All tubular material to be used for the manufacture of pressure vessels shall be of the seamless or longitudinal double submerged are-welded type. All such material shall be non-destructively tested in accordance with the requirements of API 5L, including supplementary requirements SR4, before use. 77.2.3 Forging and Bars: Forging and bars used for the manufacture of pressure vessels shall be subjected to ultrasonic inspection before machining, in accordance with ASTM A388. The Purchaser/Employer shall approve the standard of acceptability. The Purchaser/Employer may also use other ultrasonic inspection methods/procedures and acceptance standards subject to the approval. 77.2.4 Mechanical properties (destructive testing): After the last post-weld heat treatment, a control of the mechanical properties shall be carried out. The test shall be performed in accordance with the latest edition of ASTM A370. Inspection of Complete Pressure Vessels: 77.3.1 Non-Destructive Tests: All pressure retaining stressed and repair welds of each pressure vessel shall be non-destructively tested in accordance with the requirements of the ASTM Boiler and Pressure Vessel Code. All radiographs shall be evaluated by the manufacturer’s quality assurance inspection and shall, upon request of the Purchaser/Employer, be submitted for evaluation by a recognized independent inspection authority appointed by the Purchaser/Employer. Weld’s, which do not permit interpretable radiographs, shall be inspected by ultrasonic methods in accordance with the requirements of the ASTM Builder and Pressure Vessel Code. 77.4 Hydrostatic Test and Inspection for Conformity: Each completed pressure vessel shall be inspected for conformity with the requirements of this specification and the order, including marking/stamping of the materials, marking of welds, heat treatment performed, dimensions and tolerances and compliance with the drawings. Each pressure vessel shall be hydra/hydrostatically/tested. The test pressure shall be 1.5 times design pressure and shall be maintained for at least 15 minutes. Gas RMS Bib-III 248 78. Quality Assurance: Under all circumstances, the Manufacturer shall be responsible for ensuring that the pressure vessels ordered and manufactured in compliance with this specification and shall provide prove thereof upon request by the Purchaser/Employer. During work on the pressure vessels, for the Purchaser/Employer and his representative shall have free access to those parts of the Manufacturer’s premises where the pressure vessels ordered are manufactured and tested. 79. Certification: In respect of the inspection for conformity and hydrostatic tests in accordance with clause 86.3 above, the Supplier shall submit inspection certificates in accordance with the ASME Boiler and Pressure Vessel Code. Such inspection certificates shall be submitted to the Purchaser/Employer together with NDT records and test reports. 80. Documentation: All documentation shall be presented in the English language and SI units shall be used. Operation and maintenance instructions and/or manuals shall be in the English language. The documentation listed below shall be submitted at the times indicated below: With the tender: • drawing showing main dimensions, indication general arrangements, location of equipment and size and types of outlets; • list of materials with standards and grades; • estimated weight. Before the start or production: • detailed documentation-drawings with all details (dimensions, welding, testing), calculations, welding documentations, inspection & test documentation, welding documents concerning materials used with chemical analyses and mechanical characteristics, auxiliary equipment; • foundation drawing indication dimensions and loads; • calculations necessary of design evaluation; • list of materials and certification levels; • welding procedure specification; • heat treatment procedure; • NDT procedure; • hydrostatic test procedure; • manufacturing schedule. This documentation shall be submitted in eight copies, one of which will be returned after approval by the Purchaser/Employer. • During production: • progress reports; • inspection plan; • list of spare parts recommended (for two years operation). • By the latest of delivery: Gas RMS Bib-III 249 • comprehensive installation, operating, maintenance and repair manuals; • reproducible “as built” drawings (transparent). 81. Identification: Before the hydrostatic test laid down in clause 86.3 of this specification, each Pressure Vessel shall be fitted with a stainless steel identification plate. 82. External Surface Treatment: Unless otherwise specified in the specification, each pressure vessel shall be delivered externally sandblasted and primed in accordance with the Purchaser’s/Employer’s instruction. J. 83. Specification: Knock Out Drum (KOD) SCOPE: This specification covers minimum requirements regarding design, manufacturing, and inspection and testing for Knock Out Drum (KOD) for use in a natural gas piping system. 84. References: Liquid separators shall comply with the requirements of the following documents: • ASME B 31.8 Guide for Gas Transmission and Distribution piping; • “Environmental data”. • “Design criteria gas analysis”. • “Pressure Vessels, general requirements”; • “Construction specification- instrumentation”; • “Painting” as applicable; • SIS 185111 “European corrosion scale for anti-corrosive paint; 85. Functional Requirements: Knock Out Drum shall be suitable for unattended operation and separate condensate mist from natural gas. Liquid particles of 8 microns and larger shall be removed 100% and 98% up to 8 microns and solid particles. Turndown ratio will be 1:5.The pressure drop across the separator shall not exceed 0.4 bars under worse flow condition. Minimum condensate retention shall be less than 0.6 m3 Condensate shall be drained off by installing gas operated level controllers and drain valves into the condensate storage tank. A pressure balance line shall be connected to the low pressure (pressure less than 5 bar) pipeline if available. 86. Design Requirements: Knock Out Drum shall be designed, fabricated, inspected, tested and stamped in accordance with the relevant clause of section 7 “Pressure vessel, general requirements”. Vessel not covered by the general specification shall be designed, manufactured, tested and stamped in accordance with ASME Boiler and Pressure Vessel Code, Section VIII and these specifications. 86.1 Technical Data: Connection Size & Class Type Max. Operating pressure Gas RMS Bib-III : 08” x 600 RF (Inlet and Outlet) : Vertical type : 1100 psig 250 Min. Operating pressure Capacity operating pressure. Operating Temperature Range Specific Gravity of Gas Body Element Design/Const. Std. Discharge Noise Level 86.2 : 5 o C to+ 100 o C : 0.6 : Carbon steel : Stainless Steel : ASME Pressure Vessels Code, Sec-VIII : Auto discharge by the gas pressure with the help of level controller and drain valve. By pass valve of auto discharge system should be installed. : Noise level shall not exceed the standard acceptable maximum sound limit (85db) beyond 5ft of equipments. Each KOD must be equipped with the following accessories, nozzles and other necessary fittings as per design requirements: • • • • • • • • • • • • • • 86.3 : 600psig : 3.125 MMSCFH (85 MMSCFD) at 600 psig Gas inlet with RF flange Gas outlet with RF flange, 180º angle with inlet flange Pressure vent on the top of the vessel with 1” valve and blind flange. 1” Safety/thermal Relief with valve on the top of the vessel set to 110% of maximum operating pressure. ½”pressure gauge with ½” needle valve; dial 160 mm with accuracy ±1%. Two studs with Level indicator complete with valves. Level switch high mounted on to level indicator. Stud with Differential Pressure gauge complete with manifold 3 ways. Pressure drop instrument complete with manifold 5 ways. Stud with gas operated Liquid level controller complete with valves. 1” drain with socket weld /flanged plug valve 02 (two) nos with metallic sealing. Auto discharge system (level control valve) for drain with inlet and outlet valves and also auto discharge system bypass valve. Arrangement should be made to connect drain line from auto discharge system to liquid storage tank Inspection opening will be provided and shall be opened with blind flange. Suitable equipment shall be provided to lift and to swing the closure open. All nozzles shall be located such that the connecting valves, instruments etc. are accessible from one side of the separator. The auxiliary equipment specified shall be fitted to the separator in the Supplier/Contractor/ Manufacturer’s plant, including all tubing and fittings, necessary for hook up. Instrument piping shall be in accordance for proper functioning. All threads shall be female and be in accordance with ANSI B1.1. The complete KOD unit including auxiliary equipment shall be tightness tested to 1.1 x Design Pressure with air or inert gas at the Supplier/ Contractor/ Manufacturer’s plant test report should be submitted. After the tightness test, a functional test of Separator shall be carried out in accordance with written test procedures to be approved by the Purchaser /Employer. Gas RMS Bib-III 251 Manufacturer name & country of origin must be mention for Liquid Separator (VME) and its all accessories. 87. 88. Coating: All exposed, exterior surface including structural members shall be coated in accordance with the standard specification for “Painting” as applicable. Vessel and nozzles are to be internally shot blasted for removing debris and scale. Documentation: All documentation shall be in SI units and shall be in English. The Supplier/Contractor/Manufacturer shall submit the following documentation at the times indicated below. With the tender: • general key lay out drawings of the separators; • assembly drawings showing internal design; • list of materials (with name of manufacturers/ Company both VME and accessories); • overall weight; • procurement and manufacturing schedule; • list of references; • list of special tools. No later then three weeks after contract award: • detailed construction drawings indicating all dimensions, locations of accessories, nozzles etc. ; • design calculations; • list of materials and certifying authorities; • welding procedure specification; • welding procedure qualification records; • welding performance approval records; • heat treatment specification; • non-destructive testing specification; • pressure test specification; • functional test specification; • identification plate text. • Foundation drawings indicating dimensions and loads; These documents shall be forwarded in eight copies, one of which will be returned following approval by the Purchaser/Employer. At delivery: • Technical information; • as built drawing; • tightness test report should be submitted. • list of recommendation spare parts for 2 years of operating; • list of all spare parts; • drawings showing spare part numbering; • commissioning manual; • operation manual; • servicing manual. 89. 90. Identification: Separators shall be fitted with durable identification plates in accordance with the code or standard to which they are constructed. The text of such plates shall be in English and shall include the Purchaser’s/Employer’s Identification Number. Delivery: The Manufacturer shall not be deemed to have delivered the Separators until the Gas RMS Bib-III 252 Purchaser/Employer has received the Separators and the associated documentation and certificates. After testing, each separator shall be prepared for export shipment. All nozzles shall blank off and all flange faces shall be protected against corrosion and damages. Such protection shall be adequate for long term storage (up to six months under site conditions). K. 91 Equipment Specification: Filter Separators SCOPE: This specification covers minimum requirements regarding design, manufacturing, inspection and testing for Two Stage Separators (Filter Separator) for use in the Bibiyana-III, 400MW Combined Cycle Power Plant ,Habiganj RMS. 92 REFERENCES: The Separators shall comply with the requirements of the following documents : • • • • • 93 “Environmental data”. “Design criteria gas analysis”. “Pressure Vessels, general requirements”. “Construction instrumentation” SIS 185111 “European Separators scale for anti-corrosive paint; GENERAL: 93.1 Purpose The purpose of the Gas Separators is to provide separation of liquid and solid entertainment from sweet natural gas in the operation of natural gas transmission system. 93.2 Site Conditions The Gas Separator will be field installed at outdoors, unprotected in Bangladesh. Refer to specification of Environmental Data. 94 FUNCTIONAL REQUIREMENTS: The Separators shall be suitable for unattended operation. The Gas Scrubber shall separate liquid entrainments like natural gas condensate, water and methanol, as well as solid particles like rust, sand scale etc. The Separators shall be able to remove 99.9% of liquid entrainment >5 Micron and 99.9% of solid parties > 5 Micron at a turn down ratio of 1:5. Minimum condensate storage shall be 0.6 m3 . . The pressure drop across the clean separator shall not exceed 0.35 bars under worse flow condition. 95 DESIGN REQUIREMENTS AND DATA : 95.1 Gas RMS Bib-III Each vessel shall be designed, fabricated, tested and stamped in accordance with the relevant clause of section 7 “Pressure Vessel, General requirements”. Vessel not covered by the general specification for pressure vessel shall be designed, manufactured, tested and stamped in accordance with ASME Boiler and Pressure Vessel Code, Section VIII and this specification. All separators shall have two separation stages. Separators for a design flow of 85 MMSCFD or more the first stage shall comprise fitter cartridges made of fiber glass. The second stage shall be equipped with a vane-mist extractor made of 253 stainless steel ASTM A316 or similar. For smaller separators the first and second stage may comprise cartridges. Identical cartridges shall be used in all separators sizes designed and contracted with this project. The plate separating the two stages shall be designed to withstand at least the bursting pressure of the cartridges. Separators up to 3000 mm max. height may be of the vertical or horizontal design. Separators executing the above limit shall be of the horizontal design. 95.2 Technical Data: Connection Size & Class Connection Size & Class : 8” x 600 RF (Inlet) : 8” x 600 RF (Outlet) Type : Skid mounted Horizontal type Max. Operating pressure : 1100 psig Min. Operating pressure : 600 psig Capacity design : 3.125 MMSCFH (85 MMSCFD) at 600 psig operating pressure. Operating Temperature Range : 5 o C to 60 o C Specific Gravity of Gas : 0.6 Body : Carbon steel Element : Stainless Steel Design/Const. Std. : ASME Pressure Vessels Code, Sec-VIII Discharge : Auto discharge by gas pressure with the help of level controller and drain valve. By pass valve of auto discharge system should be installed 96 97 END CLOSURE: 96.1 For replacing the cartridges the vessel shall be equipped with a full size Quick Opening Hinged Closure. Suitable equipment shall be provided to lift or to swing the closure open. Safety protection against opening under pressure shall be provided. 96.2 The quick closing Door shall be designed manufactured and tested in accordance with API spec. 6D, Section 8. In addition to the requirement in Section 8.7, the design of the closure shall be such that during opening the cover forces mechanically away from the sealing surface before the holding members release the cover. NOZZLE SECHEDULE AND EQUIPMENT: 97.1 Gas RMS Bib-III Each separator shall be equipped with the following nozzles and auxiliary equipment: • gas inlet with flange RF; • gas outlet with flange RF; • pressure vent on top of vessel with 1” socket weld plug valve with metallic sealing including blind flange; • ½" thermal relief valve on top of vessel set to 110% design pressure; • direct mounted pressure gauge; Diameter 160 mm; accuracy + 1%. • two studs with female threads at the Separators inlet and outlet equipped with • ½" ball valves, directly screwed into the studs; • Differential pressure gauge with maximum pointer and switch in accordance with relevant clause of bid document for “Pressure Gauges”. 254 The differential pressure gauge shall be capable of withstanding the maximum pressure differential on either side of the gauge without damage. Each separation stage shall be equipped with the following: • Drain 1” socket weld plug valve, metallic sealed with blind flange. • Stud with gas operated level controller in accordance with relevant clause of bid document, including automatic operated drain valve flanged between metallic sealed plug valves to the drain outlet. The drain valve shall have satellite hardened trim. Actuator shall be fail safe (spring to close). • Manual bypass with 1” flanged plug valve metallic sealed. Two studs with level indicator including level switch high in accordance with relevant clause of bid document All nozzles shall be located such that the connecting valves, instruments etc. are accessible from one side of the scrubber. The auxiliary equipment specified shall be fitted to the scrubber in the Contractor/Manufacturer’s plant, including all tubing and fittings, necessary for hook up. Instrument piping shall be in accordance with relevant clause of bid document All threads shall be female and be in accordance with ANSI B1.1. 98 The complete separator unit including auxiliary equipment shall be tightness tested to 1.1 x design pressure with air or inert gas at the Contractor/Manufacturer’s plant. After the tightness test, a functional test of each scrubber shall be carried out in accordance with written test procedures to be approved by the Employer. INSPECTION AND CERTIFICATION: At all times during which work on the order is being carried out, the Employer or his representative shall have free access to those parts of the Contractor/Manufacturer’s premises where the separators are being manufactured and tested. 99 100 COATING: 99.1 All exposed, exterior surface including structural members shall be coated in accordance with the applicable standard specification of Painting. 99.2 Vessel and nozzles are to be internally shot blasted, as a minimum to Sa 2 ½ (SIS 185111). Additional chemical cleaning or baking shall be done in accordance with the requirements of the coating manufacturer 130 to 175 mm of a phonetic epoxy coating are to be applied internally to the vessel and nozzles until all coated surfaces are holiday free. The pore frequency shall be controlled by means of a low voltage pore locator, e.g. POROTEST using a sensor of conductive rubber as well as a low voltage moist sponge pore locator. At least 5% of the coated surface shall be tested. DOCUMENTATION: 100.1 Gas RMS Bib-III All documentation shall be in SI units and shall be in English. The Contractor/Manufacturer shall submit the following documentation at the times indicated below. With the tender: • general key lay out drawings of the separators; • assembly drawings showing internal design; • list of materials; • overall weight (with and without water); • procurement and manufacturing schedule; • list of consumable spare parts with prices for 2 (two) years of operation; 255 • • • list of references; list of recommended spare parts for 2 (two) years of operating; list of special tools. No later then three weeks after contract award: • detailed construction drawings indicating all dimensions, locations of nozzles etc.; • design calculations; • list of materials and certifying authorities; • welding procedure specification; • welding procedure qualification records; • welding performance approval records; • heat treatment specification; • non-destructive testing specification; • pressure test specification; • functional test specification; • identification plate text. 101 These documents shall be forwarded in eight copies, one of which will be returned following approval by the Employer. At delivery: • technical information; • as built drawing; • all necessary test and approval certificates; • list of consumable spare parts; • list of all spare parts; • drawings showing spare part numbering; • commissioning manual; • operation manual; • servicing manual. IDENDIFICATION: Separators shall be fitted with durable identification plates in accordance with the code or standard to which they are constructed. The text of such plates shall be in English and shall include the Employer’s Identification Number. 102 DELIVERY: The Manufacturer shall not be deemed to have delivered the separators until the Employer has received the separators and the associated documentation and certificates. After testing, each separator shall be prepared for export shipment. All nozzles shall be blanked off and all flange faces shall be protected against corrosion and damages. Such protection shall be adequate for long-term storage (up to six months under site conditions). L. 103. Specification: Single Stage Liquid Separator (VME) SCOPE: This specification covers minimum requirements regarding design, manufacturing, and inspection and testing for Single Stage Liquid Separators (VME) for use in a natural gas piping system. 104. References: Liquid separators shall comply with the requirements of the following documents: Gas RMS Bib-III 256 • ASME B 31.8 Guide for Gas Transmission and Distribution piping; • “Environmental data”. • “Design criteria gas analysis”. • “Pressure Vessels, general requirements”; • “Construction specification- instrumentation”; • “Painting” as applicable; • SIS 185111 “European corrosion scale for anti-corrosive paint; 105. Functional Requirements: Separators shall be suitable for unattended operation and separate condensate mist from natural gas. Liquid particles of 8 microns and larger shall be removed 100% and 98% up to 8 microns. Turndown ratio will be 1:5.The pressure drop across the separator shall not exceed 0.4 bars under worse flow condition. Minimum condensate retention shall be less than 0.6 m3 Condensate shall be drained off by installing gas operated level controllers and drain valves into the condensate storage tank. A pressure balance line shall be connected to the low pressure (pressure less than 5 bar) pipeline if available. 106. Design Requirements: Each Liquid Separator (VME) shall be designed, fabricated, inspected, tested and stamped in accordance with the relevant clause of section 7 “Pressure vessel, general requirements”. Vessel not covered by the general specification shall be designed, manufactured, tested and stamped in accordance with ASME Boiler and Pressure Vessel Code, Section VIII and these specifications. 106.1 1st Stage liquid Separator (VME) for Bibiyana-3, 400MW Combined Cycle Power Plant ,Habiganj: Connection Size & Class : 10” x 300 RF (Inlet and Outlet) Type : Vertical type Design pressure : 720 psig Max. Operating pressure : 600 psig Min. Operating pressure : 300 psig Capacity : 3.125 MMSCFH (85 MMSCFD) at 500 psig operating pressure. Operating Temperature Range : 0 o C to 60 o C Specific Gravity of Gas : 0.6 Body : Carbon steel Element : Stainless Steel Design/Const. Std. : ASME Pressure Vessels Code, Sec-VIII Discharge : Auto discharge by the gas pressure with the help of level controller and drain valve. By pass valve of auto discharge system should be installed Noise Level : Noise level shall not exceed the standard acceptable maximum sound limit (85db) beyond the 5ft of equipment. 106.2 2nd Stage liquid Separator (VME): Connection Size & Class Gas RMS Bib-III : 14” x14” x 300 RF (Inlet and Outlet) 257 Type Design pressure Max. Operating pressure Min. Operating pressure Capacity : Vertical type : 720 psig : 500 psig : 100 psig : 3.125 MMSCFH (85 MMSCFD) at 150 psig operating pressure Operating Temperature Range : 0 o C to + 60 o C Specific Gravity of Gas : 0.6 Body : Carbon steel Element : Stainless Steel Design/Const. Std : ASME Pressure Vessels Code, Sec-VIII Discharge : Auto discharge by the gas pressure with the help of level controller and drain valve. By pass valve of auto discharge system should be installed Noise Level : Noise level shall not exceed the standard acceptable maximum sound limit (85db) beyond the 5ft of equipment 106.3 Each separators must be equipped with the following accessories, nozzles and other necessary fittings as per design requirements: • • • • • • • • • • • • • • 106.5 Gas inlet with RF flange Gas outlet with RF flange, 180º angle with inlet flange Pressure vent on the top of the vessel with 1” valve and blind flange. 1” Safety/thermal Relief with valve on the top of the vessel set to 110% of maximum operating pressure. ½”pressure gauge with ½” needle valve; dial 160 mm with accuracy ±1%. Two studs with Level indicator complete with valves. Level switch high mounted on to level indicator. Stud with Differential Pressure gauge complete with manifold 3 ways. Pressure drop instrument complete with manifold 5 ways. Stud with gas operated Liquid level controller complete with valves. 1” drain with socket weld /flanged plug valve 02 (two) nos with metallic sealing. Auto discharge system (level control valve) for drain with inlet and outlet valves and also auto discharge system bypass valve as well as manual discharge with valve. Arrangement should be made to connect drain line from auto discharge system to liquid storage tank Inspection opening will be provided and shall be opened with blind flange. Suitable equipment shall be provided to lift and to swing the closure open. All nozzles shall be located such that the connecting valves, instruments etc. are accessible from one side of the separator. The auxiliary equipment specified shall be fitted to the separator in the Supplier/Contractor/ Manufacturer’s plant, including all tubing and fittings, necessary for hook up. Instrument piping shall be in accordance for proper functioning. All threads shall be female and be in accordance with ANSI B1.1. The complete separator unit including auxiliary equipment shall be tightness tested to 1.1 x Design Pressure with air or inert gas at the Supplier/ Contractor/ Manufacturer’s plant test report should be submitted. Gas RMS Bib-III 258 After the tightness test, a functional test of Separator shall be carried out in accordance with written test procedures to be approved by the Purchaser /Employer. Manufacturer name & country of origin must be mention for Liquid Separator (VME) and its all accessories. 107. 108. Coating: All exposed, exterior surface including structural members shall be coated in accordance with the standard specification for “Painting” as applicable. Vessel and nozzles are to be internally shot blasted for removing debris and scale. Documentation: All documentation shall be in SI units and shall be in English. The Supplier/Contractor/Manufacturer shall submit the following documentation at the times indicated below. With the tender: • general key lay out drawings of the separators; • assembly drawings showing internal design; • list of materials (with name of manufacturers/ Company both VME and accessories); • overall weight; • procurement and manufacturing schedule; • list of references; • list of special tools. No later than three weeks after contract is awarded: • detailed construction drawings indicating all dimensions, locations of accessories, nozzles etc. ; • design calculations; • list of materials and certifying authorities; • welding procedure specification; • welding procedure qualification records; • welding performance approval records; • heat treatment specification; • non-destructive testing specification; • pressure test specification; • functional test specification; • identification plate text. • Foundation drawings indicating dimensions and loads; These documents shall be forwarded in eight copies, one of which will be returned following approval by the Purchaser/Employer. At delivery: • Technical information; • as built drawing; • tightness test report should be submitted. • list of recommendation spare parts for 2 years of operating; • list of all spare parts; • drawings showing spare part numbering; • commissioning manual; • operation manual; • servicing manual. 109. Identification: Separators shall be fitted with durable identification plates in accordance with the code or standard to which they are constructed. The text of such plates shall be in English and shall include the Purchaser’s/Employer’s Identification Number. Gas RMS Bib-III 259 110. Delivery: The Manufacturer shall not be deemed to have delivered the Separators until the Purchaser/Employer has received the Separators and the associated documentation and certificates. After testing, each separator shall be prepared for export shipment. All nozzles shall blank off and all flange faces shall be protected against corrosion and damages. Such protection shall be adequate for long term storage (up to six months under site conditions). M. Equipm ent/Material Specification: W ater Bath Heater Scope: 111. 112. This specification provides minimum requirements of water bath heater for preheating sweet natural gas for Bibiyana-III, 400MW Combined Cycle Power Plant RMS ,Habiganj References The heater shall comply with the requirements of the following documents: • • • • • 113. “Environmental data”. “Gas analysis”. Applicable painting specification pressure vessels, general requirements”, “Insulation”, “Pressure gauge, temperature gauge, level indicator, instrument piping, temperature controller”, • “Equipment noise limits”, • “General requirement for pressure vessels”. General: 113.1 Purpose: The function of the heater is to heat natural gas to an extent, which compensates for the subsequent temperature drop through the pressure regulator valves, caused by the Joule-Thomson effect. 113.2 Site Conditions: The heater will be field installed, outdoors, and unprotected type, Refer to specification of environmental data relevant clause of Tender document. 114. Functional Requirements: The heater will be PLC (Programmable Logic Controller) controlled .So it shall be suitable for unattended operation. The heater shall be capable of maintaining gas temperature at 15 o C downstream of 2 nd stage pressure regulation (i.e. 1100 psig to 150 psig) at 150 psig pressure and shall not be above 20o C.under all given flow conditions (or otherwise stated). The water bath temperature shall be maximum 80 o C. The heater shall operate self-contained with gas without any auxiliary energy. The heater will be Control/Operate by the heater control panel. Electric or electronic instrumentation shall be used for monitoring/control purposes only. 115. Design Data: The following design data are general for all sizes of heaters foreseen, specific design data will be given on separate data sheet and provided by Supplier/Contractor: Heater Inlet Gas Pressure (Maximum) Heater Inlet Gas Pressure (Minimum) Inlet connection Size & Class Gas RMS Bib-III : 1100 psig : 600 psig : 8”ø, ANSI Class 600 RF 260 Outlet connection Size & Class Maximum Capacity Design temperature : 8”ø, ANSI Class 600 RF : 85 MMSCFD (3.125 MMSCFH) : 100 o C Max. Pressure loss through tube bundle (worse conditions) : 0.5 barg Max. Gas velocity in tube bundle : To be set by the manufacturer as per standard design Codes and engineering practice. : Inlet gas temperature at 1100 psig is 10-15 oC. Delivery gas temperature shall need to be maintained within 15o C to 20o C at 150 psig downstream of 2nd stage pressure regulation . Operation temperature (water bath) : Max. 80 o C Min. corrosion allowance on all carbon : 3 mm. steel parts in water bath except tubes Thermal efficiency under full load : 85% condition Burners : The heater will have 2 (two) main and 2 (two) pilot burners Design Requirements: 116.1 The open water bath heater consists of a cylindrical vessel with removable flame tube and gas tube bundle. The entire heater shall be skid mounted and be ready for operation. As heat transfer medium water shall be used. The heater shall have its own fuel gas system. Operation temperature (gas) 116. Minimum requirements are shown in the attached P&I diagram. On top of the cylindrical vessel an expansion tank shall be installed. All valves and instruments shall be accessible from one side of the heater. 116.2 Tube Bundle: The tube bundle shall be designed, constructed, tested and stamped in accordance with relevant clause of Tender document. Gas inlet and out shall have ANSI 600 class RF flanges in accordance with ANSI B16.5. The entire tube bundle shall be removable from the shell for inspection. Therefore and to allow for thermal expansion the bundle shall be supported on wheels. The wheels shall run on guiding rails. Precaution shall be taken against buoyancy of the tube bundle. The tube handle shall be made of heavy walled pipe with at least 2" NPS: hairpin tubes shall not be used. The tube handle shall be equipped with the following instrumentation as shown in the attached P&I diagram: Temperature gauge installed in welded thermo well at gas inlet and outlet; Pressure gauge with ball valve; ½" thermal relief valve. Relief valves shall be in accordance with BVP code, Section VIII. The complete tube bundle shall be tightness tested at 1.1 times the design pressure. 116.3 Gas RMS Bib-III Flame Tube: The flame tube shall consist of combustion chamber and flue gas return. It shall be possible to clean the flue gas tube through a hinged door. The flame tube shall be fully welded. Complete penetration shall be achieved on all welded joints. All weld seams shall radio graphically tested. The quality of the 261 weld seam shall correspond to the area “green to blue” in IWW’s welding atlas. The completed flame tube shall be tightness tested with compressed air at a pressure of 0.5 bars. The entire flue gas bundle shall be removable from the shell for inspection. Therefore and to allow for thermal expansion the flue gas bundle shall be supported on wheels. The wheels shall run on guiding rails. Precaution shall be taken against buoyancy of the flue gas bundle. The air intake shall be equipped with a flame arrestor, made of stainless steel. The flame arrestor housing shall have a sight glass with cover for observing the burner flame under operation, and an opening with cover for igniting the pilot burners with the manual ignition device. 116.4 Burner Arrangement: The Heater shall have two main and two pilot burners arranged such that each pilot burner does ignite each of the main burners as well as the second pilot burner. Each pilot burner shall heat a bi-metal thermo element producing thermo current for opening the solenoid, operated shutoff valves. The complete burner assembly shall be withdrawable on rails for easy repair and maintenance. The cable length of the thermocouple shall allow for withdraw without disconnecting. On flame failure the solenoid valve shall close within twenty seconds. 116.5 116.6 Gas RMS Bib-III Directly in front of each pilot burner a filter shall be installed in the fuel gas line. The filter cartridge shall be an exchangeable sintered element removing contamination of 5 mm and larger. It shall be possible to exchange the cartridge without taking the filter body out of the line. Main burner shall be self-aspirating and shall have a turndown ratio of 2:1. It shall be possible to adjust the gas to air ratio to control CO. The CO. content in the flue gas shall not exceed 0.3% determined with “Dragger measuring tube”. Co 2 content shall not be less than 8.5% determined with “Brigon” measuring device. Exhaust Stack: The exhaust gas stack shall be flanged to the outlet of the flue gas tube. Min. height of the stack outlet shall be at least 6 m above ground. Stack shall be designed for maximum wind load refer to the Environmental Data stated in clause 6. , Section 7. Technical Specifications. Use of rigging is not allowed. The flue stack shall be double walled with at least 20 mm thermal insulation between the inner and outer tube. Inner tube shall be made of stainless steel at least 0.75 mm thick. Outer tube shall be made of ordinary C-steel. The stack shall be equipped with lifting lugs for mounting. Maximum surface temperature shall not exceed 60 o C The stack shall be equipped with the following devices: Temperature indicator; Stud with ½" opening with plug; Rain hood. Rain hood shall be hinged to the stack. The rain hood shall be made of stainless steel. Fuel Gas System: The fuel gas system shall be installed at the heater. The entire fuel gas and burner control system downstream of the separator shall be made of stainless steel refer to Section 7. All vent lines shall be piped to safe area. The fuel gas system shall have a weather-protecting roof made of hot dipped galvanized steel sheet including rainwater chute and pipe. 262 Shell: The shell shall be designed to withstand the hydrostatic pressure of the water bath and the supporting requirements of the connected members. It shall be made of ordinary structural carbon steel with an internal corrosion allowance of 3 mm. Care shall be taken that no air pockets are existent at the extreme outer ends of the shell due to bending of the shell by the water load. The shell shall be equipped with the required studs for installation of the instrumentation. The shell shall have a thermal insulation. Refer to Section relevant clause of Tender document Care shall be taken that the water bath is not overheated during no gas flow conditions by the thermal heat of the pilot burners. The shell shall have lifting lugs suitable for lifting the entire heater. 116.8 Heater Control Panel: The PLC controlled heater will be controlled and operated from the heater control panel. The heater control panel should be installed at control room in accordance with relevant clause of material/equipments specification. The heater control panel feed power from Power distribution board located at control room. The heater control panel will provide minimum necessary information like alarm, inlet & out let temperature of both gas and water. To operate /control the heater from the heater control panel, which is installed at control room, necessary cables, instrument, materials and other accessories should be supplied by the Supplier/Contractor. 116.9 Expansion Tank: The expansion tank shall be flanged to the top of the shell. The tank shall be entirely hot dipped galvanized. The cover shall be hinged up to the tank. The expansion tank shall be dimensioned; to take the entire water expansion from heating the water bath from 20 o C to 100 o C and to store water for at least 1month operation. The design shall be such that the water bath has minimum contact to the air and that vaporization losses are minimized. An overflow pipe shall run down close to soil level. 116.10 Ladder: 116.7 A ladder inc luding platform and handrail shall allow for easy access to the expansion tank. The ladder shall be hot dipped galvanized. For general requirements refer to specification of steel structures. 116.11 Skid: The complete heater shall be mounted on a skid. Refer to specification of steel works/skid assemblies. 116.12 External Surface Treatment: All exposed, exterior surface including structural members shall be coated in accordance with applicable standard specification of Painting. 117. Functional Test: The complete heater shall be functionally tested at the Manufacturer’s Plant, operating at natural gas. At the same time the proper function of all instruments, the fuel gas system and of the burners shall be shown. The test shall be carried out in accordance with written test procedures to be approved by the Purchaser/Employer. The results of the test shall be stated in an inspection certificate issued by an independent Purchaser/Employer/third party inspector. To install, test, commission and for proper function the heater’s necessary equipments and materials should be supplied/ ensured by the Supplier. 118. Inspection and Certification: At all times during which work on the order is being carried out, the Purchaser/Employer or his representative shall have free access to those parts of the Supplier/ manufacturer’s Gas RMS Bib-III 263 premises where the heater is being Manufactured and tested. The manufacturer shall without charge, provide the Purchaser/Employer or his representative with all reasonable facilities which they may require to satisfy themselves that the heater is being produced in compliance with this specification. Documentation: 119. All documentation shall be in SI units and shall be in English. The Supplier/Contractor/Manufacturer shall submit the following documentation at the times indicated below. With the tender: • General key lay out drawings of the Heater; • Assembly drawings showing internal design; • List of materials; • Overall weight (with and without water); • Procurement and manufacturing schedule; • List of references; • List of special tools. Not later than three weeks after award of contract, before start of production: • Detailed drawings indicating all details (dimensions and locations of equipment and connections).; • Pressure vessel documentation; • Foundation drawings indicating dimensions and loads; • Test specification; • Identification plate text; • Manufacturing schedule; These documents shall be forwarded in eight copies, one of which will be returned following approval by the Purchaser/Employer. At delivery: • Comprehensive commissioning, operation and maintenance manual; • Reproducible “as built” drawings (one transparent); • list of all spare parts; • Drawings showing spare part numbering; • All necessary test and approval certificates. Delivery: The Manufacturer shall not be deemed to have delivered the gas heater until the Purchaser/Employer has received the Heater and the associated documentation and certificates. After testing the gas heater shall be prepared for export shipment. All nozzles shall blank off and all flange faces shall be protected against corrosion and damages. Such protection shall be adequate for long-term storage (up to six months under site conditions). 120. N. 121 Equipment / Material Specification: Orifice Meter (Dual Chamber) & Mechanical Chart Recorder. References: The following standards and publications form integral part of this specification: # # # # # Gas RMS Bib-III ASME guide for gas Transmission and Distribution piping system; AGA report no. 03; API Chapter 14.3 Latest Edition; API 6D; ANSI B 16.5; 264 # MSS SP-53; # MSS SP-54; # MSS SP-55; # MSS SP-93; # ASNT-SNT-TC-IA; # ANSI B 31.3; 122. Purpose: The orifice meter (Dual Chamber) run will be used for the custody transfer metering for Bibiyana-III, 400MW Combined Cycle Power Plant ,Habiganj. The complete Orifice meter run consists of the meter tube, flow straightener, orifice fitting, orifices section isolation valves (full bore ball valves) and necessary instrument & piping. 123. Site Condition: The orifice meter run will be field installed outdoors, unprotected in Bangladesh environmental condition. 124. Scope: It is classified as differential pressure meter. It consists of primary and secondary element. It shall be applicable to handle high volume of Sweet Natural Gas having Molecular weight-17.3. Specific Gravity 0.55-0.60 (At air 1.0) & water content not more than 7 Lb/MMSCF, condensate not more than 2 (two) US gallon per MMSCF at high pressure in steady state flow for a particular plate installed in moderate temperature mode. The Dual chamber Orifice Meter and Meter Tube should be 16" & ANSI 300 Class. The Orifice Meter will be operated at 150 psig. Maximum gas flow rate at 150 psig will be 85 MMCFD and minimum 2 mmcfd should be measure through this Orifice Meter. So Orifice plates’ bore shall be sized considering the present flow condition and one set orifice plate (different sizes) should be supplied by the Supplier/Contractor as per manufacturer design to measure the maximum & minimum gas flow accurately. The Orifice should be equipped with electronic Flow computer and 3-pen mechanical Chart recorder. 125. Primary Element: Orifice Plate: Material : ANSI 316 (SS). Thickness Upstream edge : To be measured as per Pressure rating (Class 300) to avoid buckling of the Plate (To be designed as per ASME standard). : Sharp, Square edge (As per AGA Report # 3 latest version). Downstream edge : To be beveled to an angle as per AGA Report # 3. Surface parameters : Flatness, smoothness, sharpness, cleanliness, etc. (to be maintained as per AGA Report # 3 latest versions). Flow direction : Unidirectional. Plate Bore associated Parameters : 1) Beta ratio: 0.2<ß<0.75 2) Reynolds No. 1260×ß²×D <Re<108 (to be decided by the Tenderer as per AGA Report-3 depending upon the load pattern) : It shall not exceed 250 mbar (100" of water column) at maximum flow rate across the plate. Differential pressure Orifice Plate Sealing Unit Marking of the Plate : Orifice Plate Sealing Unit shall provided for rubber-to-metal sealing surfaces 360° around the plate. The units positively seal against both outer faces of the plate and against both seats of the orifice fitting to prevent leakage. : Bore dia, Orifice constant, serial no. etc 126. Secondary Elements: Gas RMS Bib-III 265 126.1 Up & Down Stream Meter T ube: Material : It shall be 16”Ø seamless carbon steel pipe of ANSI 300 class pressure rating. Length : As per AGA Report-3 Latest Version. Diameter : Diameter of the line pipe is 16 “ANSI 300 class with which meter tube shall be fitted. End Connection : RF Flanged type of ANSI Class 300, ANSI B16.5. : Internal roughness of inside walls shall be as smooth as possible and must within the tolerances specified in AGA Report # 3 Latest Versions to achieve maximum smoothness of 250micro inch. The inside pipe walls to be bored honed. Tolerances of Dimensional Parameters (Roundness, Roughness, Denting, Internal Surface, Configuration etc.) 126.2 Flow Straightening Vanes Meter tube shall be provided with Straightening Vanes and shall be designed as per AGA Report-3 Latest Version to condition the flow pattern as to obtain the optimum accuracy in measurement of Flow of Natural Gas through Orifice meter in question. It shall be used in the upstream meter tube. It should be welded to the carrier plate with RF Flange facing at its both ends. To keep the flow straightener in order the carrier plate shall be clamped between the Flanges. All parts relating to the straightener shall be welded joint type. The mode of design shall be of such that it can be drawn out of the Meter Tube as and when necessary and free of flow induced vibration. Material used for the Straightening Vanes must conform to withstand specified design pressure recommended for meter tubes. 126.3 Orifice Fittings Dual Chamber Orifice Fitting Connecting ends Main parts of the fittings. Seat Gap Meter Taps Flange Tap : It refers to dual chamber orifice fitting wherein the chambers are separated by a hardened stainless steel slide valve. It shall be of RF Flanged Facing Type. It shall be applicable where flow varies. In this case plates of different bores to be designed as per clause no. 113. Orifice fittings small feature quick-replacement of plate and inspection facility without flow interruptions. : RF flanged end of ANSI 300 : Body : Cast Carbon Steel Equalizer Valve Complete: : 18-8 Stainless steel Operating Wrench : Ductile iron or equivalent. Slide Valve Indicator : Cast iron. : Not more than 0.25" : Two sets of Flange Taps should be provided in accordance with AGA Report # 3 Latest Version. : 1. Flange tap meter connection are ½" NPT 2. Operating Shaft Slide Valve Gas RMS Bib-III Internal tap hole sizes to be as per AGA Report # 3 latest Version. 3. Internal edges of tap holes are free from burr & square edged. : Single end operating shafts are standard on left side of fitting when looking downstream. : Slide valve cannot be closed unless orifice is concentric to bore of fitting or in upper chamber during plate removal. 266 Indicator Plate Opening Wrench Plate carrier Plate Alignment Lubricant Lubricating Gun 126.4 Quality assurance Instrumentation The Orifice metering tube shall be equipped with the electronic Transmitters (e.g.: Static pr., Differential pr., Temperature) for Flow computer. Additional Static & Differential Pressure tapping and Thermo-well for measuring the Parameters such as Static & Differential pressure & Temperature in 3-pen mechanical Chart Recorder. Differential Pressure Transmitter Static Pressure & Temperature Transmitter Flow Computer &Chart Recorder 127 : Orifice meter should be provided with indicator plate to see clearly the direction of open and close position of the slide valve. : A speed wrench should be provided with each fitting to operate shaft, pinions, equalizer, valve, grease gun, bleed valve and clamping bar screws. : Orifice meter to be provided with plate carrier to protect orifice plate at all times while inserting or removing it from the fittings. The plate carriers in all senior fittings shall be centered using either a fixed three point positioning system or any other convenient system which assures concentricity within the fitting in accordance with the latest AGA Report # 3 Version. : Type : Stick of chemical compound with no filler or inert materials Operating Temp. : -48ºF to +500ºF Size : 3/8"Ø to 1½"Ø Box Size : 24 Nos. or more per box : The gun shall be designed to lubricate the different points of the fittings during the operation. : As per ISO-9001 : It shall be associated with LDPT & HDPT or LDPT-HDPT Electronic transmitter in meting run for Flow computer and an additional Differential Pressure tapping for Chart Recorder : It shall be associated with Static pressure & Temperature Transmitters at down stream of Orifice metering run for Flow Computer and additional Static Pressure tapping and Thermo-well (for Temperature Sensing) required for Chart Recorder. : It shall be associated with flow computer and chart recorder to Calculate flow along with other parameters Chart Recorder Specifications: The orifice meter should be equipped with 3-pen mechanical chart recorder. The Chart Recorder will record Static pressure, Differential pressure and Temperature from the orifice meter in a paper Chart for 24 hours. The chart paper will be change every day (after 24hours). 127.1 Rectangular Case: Casing : Die cast Aluminum, Black Vinyl Finish. Display : Circular Chart recording (24 –hours per Chart) Gas RMS Bib-III Function Mounting : Record only. : Yoke Chart Drive or Scale : Mechanical Chart drive. Pens or Pointers : Three Pen Type or Scale : Box type Pen 267 127.2 Type Recorder & Indicator shall Include Following : - 100 Humitex Charts per Instruments - 1 Fluid ounce (US) Plastic dispenser of ink per Pen - Element: Pressure Measurement, ANSI Type - 316 Stainless Steel Helical. - Element: Temperature Measurement, Class 1A - Thermal System, Liquid Expansion, Fully Compensated Tubing, - Flexible Stainless over Stainless Capillary, - Length 15 feet (4.5 meter) Sensor adjustable Union with bendable extension ANSI Type - 316 Stainless Steel , 3/8” Dia. extension Length J=18 inches (450mm) - Element: Type 37 Diaphragm, Cadmium-Plated, Carbon Steel, - 0-100" Water Differential (25KPa, 250 mbar) - Type W-PTS Plain Thermometer Well. - ID 0.378 inches (9.8mm); ½"NPT External Threaded, AISI Type S04. - Stainless Steel U=4" - Shatter Prove Glass for Metal Case - Mechanical Single Speed Chart Drive, 24 Hours Rotation Up to 7 Days Wind. - Customer Tag: - Chart No. 898419 - Chart Range: 0-10SQ; 0-100 Uniform, - Calibrated Range : Static Pressure : 0-500 Psig : Differential Pressure : 0-100" W.C : Temperature : 0-150ºF - Three Box type Pen of Color Red for Differential Pressure, Green for Static Pressure & Violet for Temperature Measurement. - Three Pen Arm. - Product Specification Sheet: PSS Parts. - MINK 1800 VIT OZ, 1800 RED OZ and 1800 GRN OZ - Mechanical Chart Drive Lubricants 128. Documents: Tenderers shall have to submit the following documents at the time of submission of Tender – # The relevant valid ISO certificate in fovour of the manufactured meters. # Meter must be manufactured & undergone various test as per AGA Report-3 & such performance certificate issued from the relevant Authority as applicable for the meters in question. # Relevant technical catalogues (general, Maintenance & Parts Lists) / brochures of the offered model O. 129. Equipments Specification: Flow Computer Scope: Flow Computer should be installed with Orifice Meter through Smart type Different Transmitters (e.g. Differential pressure, Static Pressure & Temperature). The flow Gas RMS Bib-III 268 computer shall calculate gas volume by using AGA Report no-3 and AGA Report no.8. This flow computer should be panel mounted placed in control-room. 130. Technical Specifications: Flow computer shall be a microprocessor-based unit. Flow computers shall perform all required compensation using AGA Retort no.3 (Latest Version) in Imperial units for run. Calculations shall be compensated for Static Pressure, Differential pressure, and temperature and compressibility factor. The flow computer shall provide for the following analog inputs from Orifice meter tube: · Signal from the temperature transmitter (TT). · Signal from the pressure transmitter (PT) · Signal from the Differential pressure transmitters (DPT) The Flow Computer shall have minimum following communications interfaces (Ports): · One serial port shall be connected to printer interface · One port shall be for future provision of the Gas chromatograph Controller interface. · One LAN port for Ethernet (using FTS and TCP/IP Protocols). · One Serial port for modbus SCADA data network. . One Serial port for DCS Supervisory system. · One dedicated configuration port for Soft-ware/data down/upload The computer shall have the capability to automatically print hourly, daily and monthly reports in a format and time period as defined by Purchaser/Employer. The printer shall be supplied by Supplier/Contractor and shall be compatible with the meter panel. The computer shall have an Internal precision reference voltage to allow auto calibration of the computer prior to each calculation cycle. An internal battery shall be used to maintain programmed and calculation memory for a minimum of 5 years. Supplier/Contractor shall provide system software to enable off-line programming and configuring using an IMB compatible lap top computer. The flow computer for Orifice Metering shall calculate the gas Supper compressibility factor by using the AGA Report no.8 (Latest version). The flow computer shall have a selectable high and low flow limit, with adjustable discrepancy for calculated values of density. Low or high range differential pressure transmitter switching shall be automatic with an adjustable switching point and adjustable dead bend to eliminate “hunting”. Upon reaching the upper level of the respective High Range Transmitter, out of accuracy alarms and pre-alarms will indicate the meter run has under ranged. Analog output signals (4 to 20 mA DC) shall be fully isolated and be provided for standard volume flow rates and temperature. Supplier/Contractor shall specify in his quotation the percent that the flow computers will contribute to the overall uncertainty, e.g. accuracy of analog input circuitry, accuracy of A/D conversion etc. 130.1 Flow data: The Flow Computer shall generate and stores data for meter run the following. • Previous day data (a minimum of 90 days of data shall be stored): - Start and finish time -Number of events -Total measured volume -Average temperature -Average static pressure -Average flow rate -Average differential pressure -Average supper compressibility factor (FPV) -Average Extension factor Gas RMS Bib-III 269 • Previous hour (the last 168 hours shall be memorized): -Start and finish time -Number of events - Minutes consider -Total measured volume -Average temperature -Average static pressure -Average flow rate -Average differential pressure -Average supper compressibility factor (FPV) -Average Extension factor 130.2 • Current hour data: - Minutes considered -Number of events -Total measured volume -Current gas temperature -Current static pressure -Current compensated flow rate -Hourly peak volume rate and time Operational Facilities: The Flow Computer front panel shall consist of keypad and minimum four lines digital display. This shall be suitable for both local mounting. The flow computer shall have high and low limits for Specific Gravity, should these limits be exceeded a ´´out of range `` alarm will be activated and the flow calculation will use the manual internal preset values. The keypad shall be used to access data for display and to change factors, coefficients etc., including ranges for input signals and output signals, range switching point and dead band, alarm limits, manually entered values etc. A security system shall be used to permit and control data entry and adjustment of alarms. Manually entered values shall include base Specific Gravity and compressibility. The display shall present an operator interface to view the data accessed by the keypad in addition to the following: 130.3 Gas RMS Bib-III • Non-resetable totalized volume of meter run. • Instantaneous flow rate of meter run in SCF. Additional panel mounted, dedicated tantalizers shall be used for continuous indication of totalized volumetric flow of meter run. These counters shall be nonresetable type and of a type which will prevent loss of data on failure of electrical power, supply. Flow and Totalizing Computers-Physical Requirements: The Flow Computer and auxiliary equipment shall be self contained in one modularized unit suitable for front panel mounting and shall be complete with any necessary support shelves. FC shall be mounted in a control panel to be installed in an unclassified control room. Power supply to the control panel shall normally be 220 V AC single 50 Hz supplied from an uninterruptible power supply external to the control panel, unless otherwise specified vendor to state power consumption, power supply tolerance and earthing requirements. The power supply to the computers shall nominally 24V DC from individual single pole circuit breakers within the control panel. Supplier/Contractor shall supply the 24-VDC-power supply. The flow computer shall supply the power for the field located transmitters connected to it. 270 The flow computer shall supply the following isolated and powered analog signals (4-20 mA DC, 2 wire) from its gas meter run, to drive output load up to 600 ohms to be connected to the pipeline SCADA system. • Standard volumetric gas flow rate: • Gas stream temperature and pressure. The flow computer shall also provide the following volt free pulse contact output (suitable for switching 24 VDC): • Totalized standard volumetric flow, for the meter run for connection to the dedicated totalize and odorant injection purpose and • Common fault alarm for connection to the SCADA system. All inputs and outputs shall be available on a kilopon or equal terminal strip with clamp type terminals suitable for 2.5 mm² stranded copper conductors. 131. 130.4 Flow computers –Software, Laptop and Printer Requirements: The resolution of analog to digital conversion shall be better than ± 0.02% of full scale. The flow computer shall be equipped with internal control functions such as a`` watchdog timer ´´ to monitor and insure that the program loops are executed with the correct intervals. The part of the memory that contains data which is permanent or seldom changed shall have a periodically controlled `` Check-sum ´´. The algorithms and fixed parameters important for accurate computation of fiscal quantities shall be stored in a protected memory. Relevant Software (windows based version 5 or greater) is to be supplied for data retrieval and configuration as well as the data management for further evaluation of the data. Compatible one very-latest model Laptop computer for data retrieval and configuration should be supplied. A printer should be associated with Flow Computer for printing gas consumption report hourly, daily and monthly flow data automatically. Gas consumption report shall contain Static pressure and gas flowing Temperature. 130.5 Control Logic: The Supplier/Contractor shall develop control logic. The logic shall provide for required compensation using AGA Report no.03 and AGA Report no.8. Supplier/Contractor is not released from responsibility for designing a fully functional metering control unit by meeting the requirements of this specification. A security switch shall be fitted for protection against illegal data entry. Availability of Equipment: As a minimum, Supplier/Contractor shall take into account the following requirements: • Availability shall be optimized. In case of an electrical, power failure or failure of the telecommunication system, the metering skid shall remain in operation and the flow computer shall continue operating, memorizing all flow data. • Data retrieving shall be possible locally at any time when normal operation has resumed. 131.1 Power Distribution Board: Power Distribution Board Shall be Supplied by the Supplier/Contractor. Power Distribution Board will feed power to Control panel, control equipments, UPS charger and voltage stabilizer. The main power feeder shall run from Bibiyana-III, 400MW Combined Cycle Power Plant power source to power distribution board located in the control building. Gas RMS Bib-III 271 131.2 Control Panel: A control panel shall be installed for Flow Computer in control om accordance with relevant clause of meter panel of material/equipments specification. To operate /control/proper functioning of the flow computer mounted in control panel, which is installed in control room, necessary cables, instrument, materials, fittings, software and other accessories should be supplied by the Supplier/Contractor. 131.3 UPS: An uninterrupted power supply unit should be supplied for flow computer and its control panel for minimum 08 hours backup power supply in accordance with relevant clause of UPS of material/equipments specification. 134.4 Voltage Stabilizer: An ISO certified voltage Stabilizer is required to stable output voltage level 220230 AC volts and 50 Hz. The power feed to the voltage stabilizer from the power distribution board. 131.5. Connection /Electrical Circuit Diagram: 131.6 The Supplier/Contractor should supply detail electrical connection and circuit diagram of Flow computer, Different Transmitters, UPS and Voltage stabilizer. RF Immunity: The metering system shall be designed so that, under normal operating conditions, it shall be unaffected by radio transmissions. P. 132. Equipments Specification: Pressure Regulating Valves SCOPE: This specification provides a description Pressure Regulating Valves for installation in Metering and Regulating stations for the Bibiyana-3, 400MW Combined Cycle Power Plant , RMS. 133 134.0 REFERENCES: 133.1 The following Standards and Specifications form an integral part of this Specification: • “Environmental data”. • “Design criteria”. • ASME B31.8 Guide for Gas Transmission and Distribution Piping Systems; • API 6D; • ANSI B16.5; • ANSI B16.04. The Employer may use equivalent codes and standards subject to approval. GENERAL: The Regulating valves will be installed outdoor unprotected in Bangladesh. Reference is made to relevant clause of bid document of “Environmental data”. A complete Regulating valve consists of a controller, an actuator, a control valve and all other items necessary to provide a safe and proper function of the regulator. It is not limited to the below mentioned items. The Regulator shall conform to the requirements laid down in DIN 3380 unless otherwise specified in this specification. Gas RMS Bib-III 272 135 ITEM/FUNCTIONAL REQUIREMENTS: 135.1 The purpose of the regulator is to maintain the outlet pressure within the specified pressure range under normal operating inlet pressures and temperatures. The regulator shall function properly in the valve arrangements as shown in the relevant Drawing / PFD’s. These regulators shall be functioning in M/R systems as a “Active Monitor” installation. The regulator valve shall be selfcontained gas operated. The regulator shall utilize the differential pressure across the valve. During normal operation, no gas shall be vented to the atmosphere. The regulator shall be of the pilot operated type. In a monitor installation, shall each of the valves be able to control on full differential pressure if one of the control valves in the same run fails. Gas used in normal operation shall be returned to the piping downstream of the regulator. In case of a breakdown of a diaphragm etc. gas may be vented to the atmosphere. The regulator shall be equipped with a valve trim travel indicator. The regulator valve shall have exchangeable internal valve assemblies to ease an up rating or down rating of the flow range. The valve shall be provided with soft seals. Internal inspection and exchange of internals sleeve shall be possible without taking the valve body out of the line. A sudden change of the downstream pressure shall cause immediate correction of the main valve position. The pilot shall respond simultaneously and control final positioning of main valve. The regulator valve shall be designed to minimize the sound pressure level created in the valve. Reference is made to relevant clause of bid document of “Equipment noise limits”. 135.2 DESIGN and DATA: The pressure rating shall be upstream ANSI rating as shown in the relevant Drawing / PFD’s. The Controller, external connection, if any, actuator, central volume and all other items shall be designed to at least the same pressure ratio. 135.3 Materials for pressure-containing components shall be made of either forged or cast-steel. The steel used shall conform to the standards stated in API 6D, or other material standards equivalent to these. The hydrostatic test pressure of the regulator valve body shall be 1.5 times design pressure for cast bodies and 1.3 times design pressure for forged bodies. The dimension and type of gas inlet and gas outlet flanges shall be in accordance with ANSI B16.5 RF. DATA (i) 6”Ø x ANSI 600 Regulator and pilot. Inlet Gas Pressure : 1100 to 600 psig Regulator Body : Carbon Steel (Nickel Plated/ Zinc plated) Pilot Spring Pr. Range : 250-650 Psig Delivery gas Pressure : 500 psig Gas RMS Bib-III 273 Stud Bolts & Nuts : ANSI 600 (ii) 6”Ø x ANSI 300 Regulator and pilot. Regulator Body Inlet Gas Pressure Pilot Spring Pr. Range Delivery set Pressure Stud Bolts & Nuts 136.0 137.0 : Carbon Steel (Nickel Plated/ Zinc plated) : 550 to 400 psig : 100-400 Psig : 150 psig : ANSI 300 QUALITY CONTROL: Hydrostatic test shall be made with the test pressures given in API 6D. These pressures shall be maintained for at least 10 minutes. Test pressure and hold time shall be recorded and be entered in the test certificate. DOCUMENTATION: Documentation shall fulfil the requirements of project instruction relevant clause of bid document “Vendor data requirements” at the times indicated. To be completed by Contractor for every Regulator valve: COMPONENT: PRESSURE CONTROL VALVE: Station No Name Drawing no: PROCESS DATA: Process fluid Inlet pressure range Normal inlet tem. range Upset inlet temp. range Outlet pressure range Normal outlet temp. range Upset outlet temp. range Max. controlled flow Min. controlled flow Silencer type PERFORMANCE DATA: Max. flow at max. pressure Min. flow at max. pressure Max. flow at min. pressure Min. flow at min. pressure Regulating accuracy Closing pressure group Max. SPL at max. flow & pres. drop Valve flow characteristic Flow coefficient Valve plug & seat type Min. diff. pressure required Inst. area: Comp. ID: Contractor ID: Refer to Relevant P&I diagram Integral +/- 1% of set pressure + 10% max. 0.4 bar 85 dB(A) in 1 m distance Equal percentage DESIGN AND CONSTRUCTION DATA: Pressure rating Design code Hydrostatic test pressure Gas RMS Bib-III 274 Leak test pressure Valve body, material Valve plug, material Valve seat, material Seat material Diaphragm material Process connections, type Inlet dimension Outlet dimension Auxiliary connections, type Control line, dimension Downstream return line, dimension Vent line, dimension Integrated silencer Weight Length Flange, ANSI Class RF CERTIFICATES: Type test authority/no. Material certificate Factory test certificate SUPPLY: Manufacturer Auxiliary regulator type/no. Pilot regulator type/no. Actuator type/no. Control valve type/no. Supplier Q. 138 Equipments Specification: Slam Shut Valves SCOPE: This specification provides description for safety shutoff devices Slam Shut Valves with operating pressure above 15 bars for installation in metering and Regulating Stations at Bibiyana-III, 400MW Combined Cycle Power Plant ,Habiganj 139 REFERENCES: 149.1 The following standards and publications form an integral part of this specification: • “Environmental Data” • “Design criteria” • “switches” The Employer may use equivalent codes and standards subject to approval. Codes and Standards: • • • • Gas RMS Bib-III ASME B 31.8 Guide for Gas Transmission and Distribution Piping System DIN 3381 DIN 17245 AD-Merkblatt W5 275 • • 140 API Spec. 6D ANSI B16.5 GENERAL: The Slam Shut Valves will be installed outdoor unprotected in Bangladesh. Reference is made to relevant clause of bid document of “Environmental Data” A Slam Shut Valve consists of a controller, an actuator a control valve body and all other items necessary to provide a safe and proper function of the slam shut valve. It is not limited to the mentioned items. The Slam Shut Valve shall conform to the requirements laid down in DIN 3381 unless otherwise specified in this specification 141 FUNCTIONAL REQUIREMENTS: The purpose of the slam shut valve is to prevent over pressure of downstream pipe systems by interrupting the flow in a regulator run in case of a faulty regulator and monitor. The sensing element (controller) of the slam shut valve shall have provision against unauthorized changes of set point. The slam shut valve shall be gas operated, but may not consume gas in normal operation. Vent openings shall be protected against ingress of rain and shall have bug screens. The slam shut valve may not have greater response time than 0.5 second. Response accuracy shall be better than 2.5% Internal inspection and exchange of internals shall be possible without taking the valve body out of the line. The slam shut valve shall be provided with a local manually operated triggering device. The slam shut valve shall be provided with local position indication (open closed). The slam shut valve shall be provided with an electric position switch for remote indication (closed). The electric switch shall be in accordance with applicable specification. The slam shut valve shall be provided with a built in pressure equalizing line. The design of the slam shut valves shall minimize the sound pressure level created by the valve. Max. gas flow velocity shall be limited to 50 m/sec. 141.1 DESIGN and DATA: The pressure rating shall be in accordance with PFD’s and design criteria. The Controller, external connections, if any, actuator, valve and all other items shall be designed to at least the same pressure rating. Materials for pressure – containing components shall be made of either forged or cast steel. The steel used shall conform to the standards stated in API 6D, AD-Merkblatt W5 or other material standards equivalent to these. The hydrostatic test pressure of the slam shut valve body shall be 1.5 times design pressure for cast bodies and 1.3 times for forged bodies. The dimension and type of gas inlet and gas outlet flanges shall be in accordance with ANSI B 16.5 Class 300 and 600 RF. The dimension of gas inlet and outlet may be the same if the valve otherwise is provided with indication of flow direction. The slam shut valve shall be provided with a nameplate in accordance with applicable standard. 141.2 DATA 8”Ø X ANSI 600 RF Slam Shut Valve: Body Material : Carbon Steel Built-in Pilot spring Range : 420 to 700 psig. Set pressure : 560 psig or any pressure within pilot spring Range. 8”Ø ANSI 300 RF Slam Shut Valve: Gas RMS Bib-III 276 Body Material Built-in Pilot spring Range Set pressure 142 : Carbon Steel : 300 to 500 psig. : 210 psig or any pressure within pilot spring Range. QUALITY CONTROL: 142.1 Type test: The complete slam shut valve shall be subject to a type test and be provided by a recognized institution to obtain a DIN DVGW number Factory Test: Each slam shut valve shall pass a factory test. The outline of the factory test shall be as stated in DIN 3381. At all times during which work on the order is being carried out, the Employer or his representative shall have free access to those parts of the Contractor/Manufacturers premises which concern the manufacture and testing of the items ordered. The Contractor/Manufacturer shall, without charges provide the Employer or his representative with all reasonable facilities necessary to satisfy him that the product is being produced in compliance with this specification. For materials for pressure-containing components, control certificates shall be issued from the third party inspector. The outline of the test shall be as stated in AD Merkblatt W5 and shall at least include a chemical analysis; a tensile test, impact resistance tests and internal crack detection tests. To satisfy this specification, the methods used and values obtained in the tests shall be in accordance with the material standard chosen and shall at least correspond to the standard stated in DIN 17345 Class 3. The outcome has to be state in a factory test certificate, which shall include the necessary material certificate. 143 DOCUMENTATION: 143.1 The documentation shall fulfill the requirements of Section documents” “Vendor DELIVERY: The delivery is not considered fulfilled until all the items and the associated documentation and certificates are received. S. 144 Equipments Specification: Pressure Safety Valves SCOPE: This specification covers Safety Relief Valves with operating pressure below 50 bars for installation in metering and Regulating Stations at Bibiyana-III, 400MW Combined Cycle Power Plant ,Habiganj 145 REFERENCES: 145.1 The following standards and publications form an integral part of this specification: • • • • Gas RMS Bib-III “Environmental Data” “Design criteria” ASME B 31.8 Guide for Gas Transmission and Distribution piping system ANSI B16.5; 277 146.0 • API RP 520; • API RP 521; The Employer may use equivalent codes and standards subject to approval. GENERAL: The safety relief valves will be installed outdoor unprotected in Bangladesh. Reference is made to relevant clause of bid document of “Environmental Data”. Safety relief valves shall conform to the requirements laid down in ASME Boiler and Pressure Vessel Code, section VIII, Division 1 unless otherwise specified in this specification. Reference should also be made to API RP 520 AND RP 521. 147.0 FUNCTIONAL REQUIREMENTS: The purpose of the safety relief valve is to prevent over pressuring of pipe systems of vessels either through leaking valves or due to thermal expansion. Safety Relief Valves may either spring-loaded or pilot operated. Pilot operated safety relief valves shall be of the fail open type. Safety relief valves may be either of the conventional or balanced type and be of the enclosed spring type. Conventional type may be used if the backpressure and build-up backpressure does not exceed 5% of the set point pressure. Bonnet of conventional type safety relief valves shall be vented to the discharge side of the valve. Capacity conversions for safety relief valves shall be determined by application of the formulae in Appendix XI of ASME Boiler and Pressure Vessel Code Section VIII, Division. 1. The safety relief valve may not leak even after several discharges. The valve shall have soft seals. The blow-down of the safety relief valves may not exceed 5% of the set pressure. 147.1 DESIGN and DATA: The relief valve body and all other items shall be designed to the same pressure rating. The steel used for relief valve body, bonnet etc. shall conform to the standards stated in ASME Boiler and Pressure Vessel Code, Section VIII or other material standards equivalent to these. As a minimum relief valve body shall be carbon steel with stainless steel trim. The hydraulic test pressure of the valve body etc. shall be at least 1.5 times the maximum allowable working pressure of the safety relief valve. Main inlet and outlet connections shall either be flanges in accordance with ANSI B16.5 (RF) or up to 3/4" NPT threading may be used. Relief valves shall have springs suitable for a range of adjustment of plus or minus 5% of the set pressure. Each safety valve shall be provided with a nameplate in accordance with pressure vessel Section VIII, Division 1. It shall also show the instrument tag number. 147.2 DATA 2” Ø x ANSI 600 RF Relief Valve . Regulator/Relief Body Pilot Spring Pr. Range : Carbon Steel (Nickel Plated/ Zinc plated) : 400-650 Psig. 2” Ø x ANSI 300 RF Relief Valve. Regulator/Relief Body Pilot Spring Pr. Range Gas RMS Bib-III : Carbon Steel (Nickel Plated/ Zinc plated) : 120-300 Psig 278 148 QUALITY CONTROL: 148.1 Type test: The complete safety relief valve, if required, be subject to a type test and be provided by a recognized test institution. The test shall be as stated in ASME Boiler and pressure Vessel Code, section VIII. 148.2 Factory Test: Each relief valve shall be bench tested and set to the required set point. The set point adjustment shall be sealed. Each valve shall have a tag stating the set point pressure. The manufacture shall issue a test certificate stating the adjusted set point and the test method. At all times during which work on the order is being carried out the Employer or his representative shall have free access to those parts of the Contractor/manufactures premises which concern the manufacture and testing of the items ordered. 149 DOCUMENTATION: 149.1 The documentation shall be in accordance with “Vendor data requirements” DELIVERY: The delivery is not considered fulfilled until all the items and the associated documentation and certificates are received. T. Specification: Valves (Ball Valves, Check Valves, Glove Valves). 150. Ball valves (Full Bore) Ball Valves to be used for Natural Gas having Sp. gr. 0.6 (At air = 1), to be side entry type, split body , forget steel, field repairable, solid ball, Double Block & Bleed antistatic device, blow out prove system, double seal design with high integrity shut-off, detailed description and specifications of the valves to be as follows: : 300/600 Class Rating Valve design and Manufacturing : As per API 6D Flange dimension and Drilling : As per ANSI B16.5 Face to Face dimension : As per ANSI B16.10 Materials of construction (a) Body, Bonnet & Cover : Forged steel ASTM A 105 . (b) Ball : Forged steel ASTM A 105 with 0.003'' Electro less Nickel plating. (C) Stem : Forged steel ASTM A105 with 0.003'' Electro less nickel plating . (d) Seat : (e) Seat Retainer : ASTM A182.- F-316 Gas RMS Bib-III PTFE. 279 (f) Bolting : (g) Seal : Primary seals electro less Nickel coated, Secondary nit rile O-rings (Double Block and Bleed ). Valve construction : Valves shall have Bolted Body. Valve shall be equipped with secondary seals between the ball and the seals should be resistant to aromatic hydrocarbon. Ball Arrangement : Trunnion Type for 4"Ø and above with double block & bleed system. ASTMA193-B7 and ASTM A194-2H for Bolts and Nuts respectively. Floating type for up to 3"Ø : 4"Ø & above sizes to be Gear Operated with wheel. Operation Up to 3"Ø sizes to be lever operated. Valve Testing : As per API 6D (598 and 607/6FA ). Fire safe design certificate (API607/6Fa) issued by internationally recognized authority i.e. ABS, Llyods, BV & DNV shall have to be submitted. Valve Marking : The identification marking on Valves shall be as per API 6D (latest edition) including the following. (a) Manufacturer's trade mark on both body and name plate. (b) API Monogram on name Plate. 151. 152. Check Valve Rating Ends Materials Trim Seats Bolting Face- to- Face Dim Design & Test : : : : : : : : 300/ 600 Class RF Flanged ANSI B16.5 Carbon Steel 13% Chromium Soft Seat Renewable Studs ASTM A 193 Gr. B7; Nuts A 194 Gr. 2H API 6D API 6D Rating : 300 /600Class Ends : RF Flanged ANSI B16.5 Bonnet & Stem : Bolted Bonnet Material Trim Seats Bolting Face- to- Face Dim Design & Test Operation : : : : : : : Carbon Steel 316 Stainless-Steel Renewable. Studs ASTM A 193 Gr. B7; Nuts A 194 Gr. 2H ANSI B16.10 Test API 598, Design API 6D Wheel (Gear) operated, Mechanical type indicator to show the percentage of opening. Globe Valves: Gas RMS Bib-III 280 U. 153. Specifications: Instrumentation Panels References: 153.1 Standards: In this specification reference is made to subsequent standards. EN 50020 154. Electrical apparatus for potentially explosive atmospheres; intrinsic safety. EN 50022 Low voltage switch gear and control gear for industrial use; Mounting rails: Top hat rails 35 mm wide for snap-on mounting of equipment. EN 55011 Limits and methods of measurement of radio disturbance characteristics of industrial scientific and medical (ISM) radio frequency equipment. EN 55013 Limits and methods of measurement of radio disturbance characteristics of broadcast receivers and associated equipment. EN 55014 Limits and methods of measurement of radio disturbance characteristics of electrical motor operated and thermal appliances for household and similar purposes, electric tools and similar purposes and similar electric apparatus. EN 55015 Limits and methods of measurement of radio disturbance characteristics of electrical lighting and similar equipment. EN 55020 Immunity from radio interference or broadcast receivers and associated equipment. EN 55022 Limits and methods of measurement of radio interference characteristics of information technology equipment. IEC 417.B Graphical symbols for use on equipment. Index, survey and compilation of the single sheets. IEC 8O1-1 Electromagnetic compatibility for industrial process measurement and control equipment; Part 1 : General introduction. IEC 801-2 Electromagnetic compatibility for industrial process measurement and control equipment; Part 2: Electrostatic discharge requirements. IEC 801-3 Electromagnetic compatibility for industrial process measurement and control equipment; Part 3: Radiated electromagnetic field requirements. IEC 801-4 Electromagnetic compatibility for industrial process measurement and control equipment; Part 4: Electrical fast transient/burst requirements. Definitions and Abbreviations: In this specification the following definitions are applicable: Auxiliary Equipment Rack: Compartment: Connection diagram: Disconnect fuse: Emission: Immission: Inquiry: Instrument earth: Gas RMS Bib-III A (turning) part within a panel in which electronic equipment such as supply units, 19 inch cards and the like are installed. A part of a panel provided with front and / or back doors. A diagram showing the electrical connections between field instrumentation equipment and panel terminal strips. A fuse in a special holder which can be used to interrupt an electrical circuit. Emitted electromagnetic radiance. Received electromagnetic radiance A request for quotation. An earthing system designed to minimize electrical interference upon transmitted signals. 281 Instrumentation panel: Safety earth : System panel: EMC: 155. A closed housing in which components are installed needed for interfacing, marshalling, controlling, safeguarding and/or signaling functions and which is part of an instrumentation installation. An earthing system designed for personal safety A standard panel delivered by control system manufacturer. Electromagnetic compatibility. REQUIREMENTS: 155.1 Electromagnetic Compatibility: All electrical and instrumentation systems installed on locations of Purchaser/Employer shall meet the European electromagnetic compatibility (EMC) guidelines. Immission requirements are stated in IEC 801-4.IEC 801-3 and IEC 801-4. Immission requirements are stated in EN 55011, EN 55013, EN 55014, EN 55015, EN 55020 And EN 55022. 155.1.1 Immission: IEC 801 distinguishes four environmental levels in which equipment is erected. Requirements for the equipment are dependent on the environmental level. This implies that all applied electrical and instrumentation equipment shall remain in correct operation (Shall not be influenced) at immissions occurring in a level 3 environment. Explanation: If immissions occur according the allowable intensity for a level 3 environment : The electrical and instrumentation system shall not react by initiating alarms, trips and the like; the measured value given by a sensor shall not deviate from the value corresponding with the process (within the accuracy of the equipment). 155.1.2 Emission: European standard regarding emission mention requirements for maximum allowable emission values. Products shall be designed and installed in such a manner that the electromagnetic emission level is as low as possible in order to guarantee a proper functioning of other electrical or electronic products or installations and to guarantee that radio services are not disturbed. 155.2 Mechanical Design: The mechanical design shall meet the following conditions: The construction, chassis, doors and the like shall be designed such that all wiring, instruments, terminals and the like are easily accessible for inspection, maintenance adjustment and repair: Functional separation shall be provided; • Terminal strips shall preferably be installed in a separate compartment which may be part of the panel; • Sufficient space shall be provided to allow spare capacity of at least 30% (instruments, terminals, voltage distribution components and the like) The construction of an instrumentation panel shall be of sheet steel. The minimum sheet thickness shall be 1.5 mm while the mounting plate, if used, shall have a minimum thickness of 3 mm. Doors shall have a minimum sheet thickness of 2mm. As a minimum the structure is to meet IP40. Gas RMS Bib-III 282 The panel shall be fitted with dismountable eye baits for transportation. Provisions should be made for blanking the holes after removal of the eyebolts. Before painting, all metal parts shall be thoroughly cleaned by means of grit blasting or by immersion in a solvent. Directly after cleaning and drying all metal parts shall be primed and subsequently painted. The minimal dry film thickness (DFT) shall be 60 micron (in total). The colour of the panel shall be RAL 7032 (gray). The colour of the plinths and the consoles will be mentioned in the inquiry. The doors of individual panels shall be hinged to swing through 1800 . It should be possible to lift the doors off their hinges. The type of doors for consoles will be mentioned in the inquiry. Doors shall be opened by a clip down handle with a push button insert (no key locks). Panels shall be installed in a plinth. Panels wider than 2500 mm shall be provided with one plinth over the whole width. The plinth height shall be 100 mm unless otherwise mentioned in the inquiry. Plinth shall be provided with the possibility of installing ventilation louvers for individual panels at the front side and (for double sided panels) at the backside. Folding lecterns and drawing holders shall be fitted to the inside of the doors; one on each panel compartment at the front side and / or the backside. Adequate provisions shall be made for ventilating the panel natural ventilation is preferred. Ventilation air should enter. The panel at the bottom and exit through the top of the panel. Forced draught ventilation should only be applied after consultation with Purchaser/Employer. For consoles, ventilation shall be implemented at the rear of the console. Heat radiation from one side shall be avoided for equipment fitted on mounting plates. In case dust filters are used, replacement of those filters shall be possible without switching off the installation. Terminal strips for external field wiring shall preferably be installed vertically. A gap of at least 200 mm shall be left between two terminal strips and between the terminal strip and the panel wall. The gap between mounting plate components terminal strips and the like and wire ducts shall be at least 40mm. All components with the possibility of mounting rail installation shall be installed on symmetrical mounting rail (non perforated steel 35 mm x 7.5 mm according to EN 50022) The supplier shall install perforated cable trays of galvanized steel or make similar provisions for the routing and installation of dabbles to the connector terminal boards. The cable entry shall preferably be at the bottom of the panel. Cable clamp bars shall be installed to provide strain relief at the cable entry-clamping bar shall preferably be fitted in the plinth of the panel. Specific requirements regarding dimensions, erection, accessibility and the like of the panels will be mentioned in the inquiry. 155.3 Electrical design: The electrical wiring within the panel, both external fields wiring and internal wiring, shall be installed in wire ducts with removable covers. Wire ducts shall be made of plastic having self-extinguishing properties and being non-toxic in case of fire. The dimensions of wire ducts for external field wiring shall be sufficient to allow wiring installation in loops. The wire ducts shall not be more than 50% full on delivery Recommended wire duct dimension are (width x height): 200mm x 80mm, 120 mm x 80 mm, 100mm x 80 mm and 80 mm x 50 mm. All wire ducts shall be fastened by means of non-metal (plastic) blind rivets. After completion of the wiring in ducts, provisions shall be made to insure that all wiring will remain in the ducts after removal of the covers. Gas RMS Bib-III 283 Wiring between the panel and movable parts of panels such as doors, auxiliary equipment racks and the like shall preferably be installed in flexible conduits. Other solutions shall be chosen in consultation with Purchaser/Employer. If flexible conduits are used, a pull wire shall be installed in the conduit. Unless otherwise mentioned in the inquiry each panel compartment shall be fitted with starteriess fluorescent lighting operated by limit switches on the doors and powered by separate 230 VAC mains voltage. For panels accessible from two sides fluorescent lighting fixtures shall be installed at the front and rear The limit switches shall be installed in such a way that terminals and the like are accessible at all times. The fluorescent lighting fixtures shall have a rim-earthed socket connected to the 230 VAC mains supply. Voltages equal to or greater than 120 VDC and equal to or greater than 50 Vac should be treated as dangerous and shall be covered by a plate where risk of touch is present. Terminal strips and equipment with position signaling facilities (for example switches) carrying the above mentioned voltages shall be covered with a transparent plate. Plates covering switching devices shall be provided with holes in order to remain operable. Where external inductive loads can occur a suppresser diode shall be used in terminal strips. 24 VDC supply units shall preferably be installed in auxiliary equipment racks. Signal isolators, converters, amplifiers and the like shall preferably be installed in 19 inch racks housed in auxiliary equipment racks. The use of connections with crimp contacts is preferred. Other connection systems shall only be used after consultation with Purchaser/Employer. Spare slots in 19-inch racks shall be fitted in blanking plates. the pre wiring of spare slots shall be executed in consultation with Purchaser/Employer. 155.4 External Connections: Terminals shall be applied for external field connections unless otherwise specified. Connector and terminal boards and / or terminals shall be used for connection to other system parts or panels. Multi core cables shall be used for all connection via connectors. All cores and screens shall be connected at the plugs. The cores shall be adequate cross section and shall incorporate screening. A cable core cross section of 0.5 mm2 (flexible) according to cable specification is preferred (for power circuits like solenoids 1.5 mm2 is preferred). The cables shall contain numbered or coloured cores. In order to avoid a rigid connection between a multi core cable and a connector, a flexible sleeve shall be installed between the cable sheath and the strain relief of the connector. The flexible sleeve shall have a minimum length of 300mm. The polarization code for connector plugs and sockets shall be different for ex(i) and non Ex(i) cables and shall be indicated in the loop drawings. 155.5 Internal Connections and wiring: The internal wiring shall be executed in flexible wire with a minimum cross section of 0.75 mm2 , the tails finished with insulated sleeves. For power circuits like solenoids, minimum cross section of 1.5 mm2 shall be used. Only one wire shall be fitted to each terminal. The wiring within the panel shall be of adequate length and shall be in one piece. Joints in the wiring are not allowed. Loose wiring within the panel shall be of adequate length and shall be in one piece. Joints in the wiring are not allowed. Loose wiring in the panel will not be allowed. Wiring used for analog signals shall be twisted. Wiring used for pulse signals shall be screened or twisted. Gas RMS Bib-III 284 The colour coding used for the wiring shall be as follows: Intrinsically safe circuits blue • 0-120 VDC positive red negative White switch wire gray • 50-1000 VAC phase brown or black neutral light blue switch wire black • Analog and pulse signals orange • Externally contact powered • Lamps and the like transparent • Safety earth green/yellow • Instrument earth yellow/black Note : Colour coding for deviation voltages will be mentioned in the inquiry. Separate terminal strips shall be used for different voltages and signals. If this is not possible, partitions shall be fitted. The internal wiring of analog and digital signals, except those carrying intrinsically safe signals, shall be installed in the same cable duct. The internal wiring of power signals shall be routed separately to prevent interference due to input and / or output control signals or electrical and/or electromechanical fields emanating from other sources. Connection wiring between elements mounted on a clamping rail (e.g. logic elements, circuit breakers) shall be of adequate length and installed within wire ducts. 155.6 Intrinsic Safety: Terminals, wiring, cabling, cable ducts and covers for intrinsically safe signals Shall be coloured blue and shall be physically separated at a sufficient distance from other wiring and cables. Consult EN 50020 for distances. For terminal connections, solder connections and plug connections no specific requirements are made for materials, however the direct environment of the connection shall be coloured blue (e.g. blue terminals, blue sleeve around solder or crimp connection). 155.7 Electrical Supplies: 165.7.1 230 VAC Supply Voltage: The 230 VAC supply voltage shall be conditioned (filtering, protecting against over-voltages and the like) in accordance with EMC requirements as stated in clause 4.1 in case components are applied which do not comply with EMC requirements. The panel shall incorporate circuit breakers for the external 230 Vac supply voltage. A separate 230 VAC circuit will be available for panel lighting and supplying wall sockets. The panel shall incorporate an earth leakage circuit breaker (30 ma) for this supply. 155.7.2 24 VDC Power Supply Units: The panel shall incorporate 24 VDC power supply unit to supply the panel, including external loads. The backup 24 VDC power supply which is connected to the UPS power source shall be capable of supporting the normal operating load. The proper operation of the power supplies shall be assured in case of mains voltage fluctuations of : + 20% of the mains voltage on a continuous basis; + 20% of the mains voltage for 50 ms; + 25 of the mains voltage for 20 ms; Gas RMS Bib-III 285 total interruption of the mains voltage for 20 ms; presence of higher harmonics up to maximum of 5% of the nominal mains voltage superimposed on the above mains voltage limits : Variations of the mains frequency ranging between 98% and 102% of the nominal value. The 24 VDC system shall be subdivided with disconnect fuses. The disconnect fuses which protect the individual circuits shall be easily accessible. If auxiliary equipment racks are used, the disconnect fuses shall preferably be installed on the front of these racks. The panel shall incorporate a signal lamp (multiple type) for each 24 VDC power supply unit to indicate malfunction of a power supply unit. In case a power supply units has an open structure, a cover shall be provided over the top of the power supply unit to prevent small object (screws and the like) falling inside. 155.7.3 Voltage Distribution: The voltage distribution within the system shall meet the following minimum requirements: The fuses and circuit breakers shall be selective Note: For the 24 VDC voltage distributions, disconnect fuses shall be used (maximum rating 4A fast acting). -Switching off in individual parts of circuits shall be possible (to be accomplished by disconnect fuses). -Looping of circuits is not permitted on power output such as solenoids. -Blown fuse and circuit breaker warnings shall result in an alarm. -The rating of components shall be adequate to permit for future expansion of 30 % The Supplier/Contractor is responsible for the correct circuit arrangement for power to the individual circuits. Any other power supply required shall be equipped with systems for detecting high and low voltage. The detection system shall be arranged in such a way that resetting is automatic after a detected high or low voltage returns to an acceptable level. 155.8 Earthing: The panel shall incorporate earthing rails for the safety earth and instrument earth suitable for at least 125 A. The safety earthing rails shall be electrically connected to the chassis. The instrument earthing rail shall be isolated from the chassis . Both rails shall be provided with threaded holes of suitable diameter and a sufficient number of clamping bolts cable Armour and shield (see annex A). The earthing rails shall preferably be mounted at the bottom of the panel on the mounting plate and shall be positioned so as not to obstruct the cable inlet to the wire ducts. The earthing rails for the safety earth and instrument earth shall be spaced at least 50mm apart. The safety earth is to serve as connection point for the field cable Armour. The Armour of the field instrumentation cables for intrinsic safe signals shall be connected to the safety earth. The drain wire (shield) on instrument cables shall be connected to the instrument earth. The supplier shall provide sufficient clamping bolts. The panel doors and auxiliary equipment racks shall be earthed to the chassis with a braided copper strap. 155.9 Labeling: All instruments, power supplies, terminal strips relays and the like shall be properly labeled. Labeling shall be indelible. Use of dymo tape is not allowed. Gas RMS Bib-III 286 Labels shall be installed on fixed places to avoid losing or exchanging labels of panel parts due to maintenance or repair. In this way the labeling system is preserved in all situations. 155.9.1 Components: All equipment installed in the panels shall be provided with legend plates (white-black white laminated plastic) stating the tag number and/or functions and in case of switches, the meaning of the switch position. 155.9.2 Terminals: The terminals shall be provided with original indelible terminal numbers. The terminals shall be numbered on both sides, vertical from top to bottom in rising sequence or horizontal from left to right. The tag number of the terminal strip shall be clearly stated on the top of the terminal strip (in case of vertical mounting or on the left side in case of horizontal mounting). 155.9.3 Internal wiring: All internal wiring shall be labeled. The wiring connected to terminal strips and/or equipment shall be provided with the same coding as the terminal to which they are connected. A legend plate in white-black white laminated plastic giving the wiring colour code (see clause 4.5) shall be installed in the panel in a visible place. 155.9.4 Dangerous Voltage: Cover plates protecting against dangerous voltages (voltage equal to or greater than 120 VDC and equal to or greater than 50 VAC) shall be labeled with the international dangerous voltage symbol (IEC 417 B, Symbol 5036). 155.9.5 Panel: A legend plate stating the panel code shall be fitted on the front of each panel section (and on the rear of each panel section when the panel is accessible from bath sides). 155.10 Special Tools: Tools necessary for special connection (crimp, wire-wrap thermo-point and the like) shall be subject to a quality control system. This quality control system shall indicate when and how these tools are checked on a sound performance. Checks shall be executed periodically. For each individual tool, the date and the result of the last check shall be known. 156. Inspection and Testing: Procedures for inspection and testing shall be provided by the Supplier/Contractor /Manufacturer. V. 157. Specification: Uninterruptible Power Supply (UPS). Scope: Supplier/Contractor shall be responsible for final sizing of the uninterruptible power supplies in accordance with industry standards. The sizing calculation shall be submitted to Purchaser/Employer for review and approval. Gas RMS Bib-III 287 158. Definitions: The following words shall have the meaning indicated when used herein: Supplier/Contractor : Engineering, procurement and construction Supplier/Contractor selected by Purchaser/Employer to perform the RMS detailed design, procurement and construction on behalf of Purchaser/Employer. Vendor : UPS supplier, Fabricator and or Manufacturer. 159. Codes, Standards and Specifications : The Supplier/Contractor shall comply with the requirements of the applicable provisions of the latest edition of the following codes, standards and specifications: IEC 44 Instrument transformers IEC 76 Transformers IEC 146, 146A And 146-2 Semiconductor rectifiers & converters IEC 157-1 Low-voltage switchgear & control-gear IEC 185 Current transformers IEC 529 Classification of degrees of protection provided by enclosures IEC 726 Dry type power transformers IEC 947-2 Circuit breakers. IEE 587 Guide for Surge Voltage in Low – Voltage AC Power circuits. 160. Operating and design Conditions: The uninterruptible power supplies shall furnish continuous 24 VDC auxiliary power for vital electrical loads in the station or substation. Supplier/Contractor is responsible for sizing of the UPS during detail design. UPS system will consist of a rectifier, charger, batteries and distribution/supervision panel. The UPS/rectifier will be supplied with 220 VAC from public supply grid. Battery charger/rectifier: The rectifier shall be capable of recharging the batteries within 8 hours, under full load conditions after a failure of mains, while allowing simultaneous normal operation. 161. Detailed Requirements: 161.1 Rating: The output rating of uninterruptible power supplies shall be 24 VDC, supplied by maintenance free batteries. The equipment shall be suitable for 8 (eight) hours continuous operation at the full rated load in an ambient temperature range of 20 0 C to 40 0 C, and for intermittent operation at ambient temperatures up to of 50 0 C. The equipment shall be capable of carrying overloads, at the rated output voltage. All components shall be matched to the specified rating and the equipment shall be heavy-duty type for industrial applications. The DC outlets shall have fuses in both lines (positive and negative). The outlet terminals shall allow for cables up to 16mm to be connected. The terminals shall be of the screwed type, colo red through and unambiguous marked. The cable outlet shall be top of the cabinet. Over voltage protection shall protect the DC installations against dangerous voltage. As a general protection lightning arrestors shall be placed at a central point in front of the outlets. Good access and easy inspection is required. Under all operating conditions no dangerous over-voltage shall occur at the DC outlets. Also short circuits in the consumer cables following release of fuses shall be considered. The charger system shall be equipped with voltage sensing device that detects decreasing battery voltage and remove the load from the battery before the battery Gas RMS Bib-III 288 can be damaged. All incoming AC supply lines shall have such transient protection as will prevent lighting induced line transients from causing damage to components. 161.2 Solid-state Rectifier Unit: The rectifier shall be used to supply normal DC power to the consumers. The rectifier shall be voltage regulated, full wave silicon type. The rectifier shall be capable of carrying the continuous, short time (over load) and short circuit currents specified for the UPS system (to be determined during detail design). The rectifier output voltage shall be 24 VDC adjustable over a range. Status of main breakers of rectifier and the voltage output voltage shall be supplied to annunciator. The voltage regulation shall be less than ± 1% from no load to full load with a variation in supply voltage, the rectifier shall function as specified with a ± 3 percent variation in supply voltage frequency. The rectifier shall be isolated from the AC power systems by an isolating transformer. The rectifier shall be provided with disconnecting links or other approved means of isolating it from the auctioneering diodes. 161.3 Battery Charging: An automatic procedure to charge the battery shall be implemented. Up to an adjustable voltage the battery shall be charged with a constant current (1 characteristic). Above this limit a constant voltage (U characteristic) shall come in force. The rectifier shall be equipped with a manual charging function. In this mode the charging shall follow a W characteristic with adjustable voltage between 1.8 and 2.65 V/cell. The following pairs of values shall apply: • max current at 2.4 V/cell = 100% nominal current of rectifier • max current at 2.65 V/cell = 10% nominal current of rectifier. The rectifier shall be built into the cabinet. Also the instrumentation and signals listed below shall be integrated in this cabinet. Battery Charger Specifications: Input Voltage : 220 VAC (stabilizer required) Input frequency : 50 Hz (47-53 Hz range) Phase : single Output voltage : 24 VDC as required Output regulation : +/-0.5% no to full load; +/-10% input voltage variation Output limiting : current limiting during overload 90 to 125% of maximum adjustable Metering : DC voltmeter and DC ammeter Metering accuracy : 2% DC protection : DC breaker and blocking diode AC protection : AC circuit breaker Mounting : rack floor mountable Equalize : 24 hour timer Relays : Low DC voltage high DC voltage rectifier failure 161.4 Batteries: Type Case Mounting Gas RMS Bib-III : Closed maintenance free, nickel cadmium : Transparent, high impact : Spark or flame prove : heavy duty battery rack 289 161.5 Miscellaneous Requirements: These devices shall include but not be limited to the following: Provisions shall be available for testing operation of rectifier/charger while in operation without inadvertently cutting off power to the load; Supplier/Contractor shall state in his proposal how this function is accomplished. Bypass switch shall be provided for cutting out and isolating the various components of the system without interrupting service to the load. Instruments of Accuracy class 2 and of appropriate ranges shall be furnished for the following services: Voltmeters: One for UPS supply input, suitably fused, One for each battery input to equipment, suitably fused. One for rectifier out put, suitably fused. One for distribution panel input, suitably fused. Ammeters:One for UPS supply input, suitably fused. One for each battery input to equipment with suitable shunt. One for rectifier output with suitable shunt. One for distribution panel input with suitable current transformer. Frequency meter:One for rectifier input suitably fused. The following alarm contacts, shall be furnished for use with remote annuanciator : -Low DC battery input voltage; -High ambient air temperature inside the cabinet; -Failure of a cooling system (if applicable): -Rectifier failure, and; -Other alarms at the option of the manufactures. 161.6 Instruments : Instruments shall be rectangular type with a black finish. The meter dials shall be white with black scales, black figures and black pointers. Instrument potential coils shall be 500 V for AC and 300 VDC and AC current coils shall be 5 ampere. Current transformer shall have accuracy in accordance with IEC standards. The DC ammeters shall have 50 or 100 milli-volt shunts and the necessary shunt leads. The equipment may be convection or forced air cooled at manufacturers option. If it is forced air cooled, filters and redundant fans shall be furnished. Fan motors shall be induction type. If filters are used, each filter shall be provided with a differential pressure switch with contacts to close on excessive pressure or a flow switch with contacts to close on reduced airflow. Contact shall be wired to terminal blocks. The fans shall pressurize the cabinet. Each fan shall be furnished with a separate fused power feed. The equipment shall be constructed so that each component can be replaced from the front or rear of the enclosure without the use of a soldering iron or special tools. All cables shall be faced and or damped. All bolts shall be secured with lock washers and all steel hardware shall be cadmium plated. Provisions shall be made for periodically testing the semiconductor power switching devices for proper operation without disconnecting or removing the devices from the unit. Provisions shall be made for testing the control equipment independent of the power equipment without disconnecting or removing the equipment form the inverter. Test points shall be provided to allow easy adjustment and servicing of the controls. All adjustments and tests shall be possible with the use of a standard voltohm milli-ammeter and oscilloscope. Gas RMS Bib-III 290 162. 163. Performance Testing and Guarantees: The completely assembled equipment shall be given a simulated operational test at the factory in order to ensure compliance with the operational requirements of this specification. The tests, including extended burn-in run, shall be made by the Vendor on the completely assembled equipment, before shipment, to ensure that all electrical equipment and wiring furnished and installed by the Vendor is in proper, operating condition and that the wiring is in accordance with the wiring diagrams. The Supplier/Contractor shall be responsible for co-coordinating with the Vendor for performance testing. The input and output insulation levels shall be capable of withstanding a test potential of 1000 volts plus two times the line voltage between current-carrying and non-current carrying pads for one minute on the power circuits. The test results shall be submitted to Purchaser/Employer for review and approval Documentation: 163.1 Documentation for Tender: Vendor shall submit drawings with tender showing the proposed UPS design, complete with full description and material components identification. Vendor shall also submit an itemized list of Vendors deviations from Specification and a delivery schedule. 163.2 Design documentation: Design documentation shall be supplied in accordance with requirements. This shall include, as a minimum, the following: - Completed data sheets; - Users reference list; - General arrangement and cross-sectional drawings complete with parts list, materials of construction and description; - Operating and maintenance manuals; - Price list of recommended commissioning spares; - Price list of recommended spare parts for two years operation; - Price list of special tools and - Weights. 163.3 Final documentation: A Manufacturing record book shall be complied concurrently with fabrication such that a full record of the fabrication, materials, and inspection and testing is available. All items in the Manufacturing Record Book shall be numbered. Contents shall include, but not be limited to, the following: - Front cover sheet detailing: Project Title, Equipment Title, and Equipment item No. - Index; - A list of all applicable codes, standards and specifications; - All drawings and data sheets, “as built” - All performance test results; - Photocopy of nameplate/nameplates, and; - Final signed quality plan. Document Marking: The following shall be consciously marked on all documents: Jalalabad Gas, Bangladesh Bibiyana-III, 400MW Combined Cycle Power Plant ,Habiganj. Item Number/Type. Gas RMS Bib-III 291 164. Warranty: Warranty provisions are specif e Standard Terms of Conditions t Supplier/Contractor, Vendor and to Vendor’s subcontractors and / or suppliers. 165. Marking and Tagging: The UPS shall have a tag number as indicated on the project drawings. Nameplates shall be die-stamped stainless steel plates permanently attached at an easily accessible point on the equipment. The UPS nameplate shall include the following information: - tag number; - vendor’s name; - catalogue number or type; - rectifier input voltage, amperage, frequency and number of phases; - rectifier output voltage and amperage; - inverter input voltage and amperage; - inverter output voltage, amperage, frequency and number of phases; - total load rating, and; - evidence of approval. W. 166 SCOPE: 166.1 167 Equipment Specification: Condensate Storage Tank This specification provides minimum requirements for buried pressurized Gas Liquid Storage Tank for the Bibiyana-III, 400MW Combined Cycle Power Plant RMS,Habiganj REFERENCES: 167.1 The Condensate Tank and its equipment shall comply with the requirements of the following documents: • ASME B 31.8 Guide for Gas Transmission and Distribution Piping system; • ASME Boiler and Pressure Vessel Code, Section VIII’ • “Environmental data”; • “Pressure gauges”. 168 PURPOSE: 168.1 169 The tank shall store liquefied gas condensate separated from sweet natural gas. The liquids will be stored under moderate pressure. The tank will be skid mounted and installed above the ground. FUNCTIONAL REQUIREMENTS: 169.1 The tank shall be suitable for storage of liquid gas condensate with a flash point below 21 o C (refer to ASTM D56-70) and the resultant high safety requirements. The condensate will be stored at a pressure of 10 to 14 bar (150 to 200 psig). The tanks shall have adequate facilities for collecting the liquids from the Knock-out Drum, Filter separators and liquid separators and for unloading to a drum/tank. The tank shall be equipped with suitable over-pressure protection and monitoring devices. Gas RMS Bib-III 292 170 DESIGN REQUIREMENTS: 170.1 The tank shall be designed, fabricated, tested and stamped in accordance with the ASTM Boiler and Pressure Vessel Code, section VIII and this specification. The tanks shall be designed for an over-pressure of 19 bars. All studs shall at the upper third of the shell. Welded studs shall have full penetration welds. Welding studs shall be welded from the inside and outside. The tank shall be equipped with two lifting lugs suitable for lifting the empty tank. Stiffening rings shall have full circumferential welds from both sides. On top and bottom the stiffener shall have an opening of at least 6 cm2 . The tank shall be equipped with the following studs and auxiliary equipment (not less than the items mentioned in ref. drawing JG/ Bibiyana-3, 400MW Combined Cycle Power Plant RMS, Condensate Tank): • 2" discharge pipe equipped with basket strainer, flame arrestor made of stainless steel, a spring closed valve wire operated from the loading bay of the road tanker. The wire shall have fusible string, which melts in case of fire and release the spring-closed valve. • An insulating flange connection with ex-prove spark gap. • A positive displacement meter with mechanical counter. The counter shall have manual reset to zero. Accuracy shall be + 1% or better. The counter shall indicate m3 and tenth of a m3 . The shaft revolution of the meter shall be transmitted via a gas tight magnetic drive unit. • A 2" Manual Control Valve, Gate Valve with V-port or Globe Valve ANSI 150 RF. • 2" Blind Flange ANSI 150 RF. A lug for connecting a 50 mm2 copper cable for bonding with the lorry. • Stud with level indicator and level switch high in accordance with relevant clause of bid document. The level switch shall be triggered at 2/3 of the max. Filling height and above. • 1" drain line connection from the high-pressure separators equipped with dip pipe. 1" Isolating Flange ANSI 300 RF with ex-prove spark gap. throttle orifice with 8 mm hole 1" metallic sealed Plug Valve ANSI 300 RF. 1" Weld Neck Flange ANSI 300 RF. Gas RMS Bib-III • 1" drain line connection from the low-pressure separators equipped with dip pipe. 1" isolating flange ANSI 150 RF with ex-prove spark gap. 1" metallic sealed plug valve ANSI 150 RF. 1" Weld Neck Flange ANSI 150 RF. • 1" breathing or blanket line connection equipped with : 1" Isolating Flange ANSI 150 RF with ex-prove spark gap. 1" metallic sealed Plug Valve ANSI 150 RF. 1" weld neck flange ANSI 150 RF. 293 • 2" line equipped with flame arrestor made of stainless steel 2" metallic sealed Plug Valve ANSI 150 RF. 2" Isolating Flange ANSI 150 RF with ex-prove spark gap. 2" Blind Flange ANSI 150 RF. • Vent line equipped with : Flame arrestor made of stainless steel. Safety Relief Valve ANSI 150 RF in accordance with ASME BVP Section VIII. The valve shall be sized assuming full upstream gas pressure at the 8 mm throttle orifice and all other line closed. The Relief Valve shall have stainless steel trim. The set point shall be adjustable for a least + 5%. The vent stack or the tip of the vent stack shall be sized for an exit velocity of at least 150 m/s at the maximum relief rate to provide good dispersion. Multiple valve arrangements with staggered stings may also be used. Reseating shall at 3% above maximum normal operation pressure. • 171 stud with instrument block valve and pressure indicator shall have a diameter of 160 mm, an accuracy of + 1% and be in accordance with relevant clause of bid document TESTING REQUIREMENTS: 171.1 In addition to the tests required in the ASME Boiler and Pressure Vessel Code, Section VIII the following test shall be carried out at the Manufacturer’s plant. • All stud welds shall be inspected for cracks by wet magnetic particle inspection. The examination procedure shall be in accordance with ASTM A275. Any linear indication must be removed and repair4d by a suitable repaired procedure. The repaired area shall be re-examined by the wet magnetic particle method. • The completed tank shall after the strength test be tightness tested to 1.1 times the design pressure. The test shall be performed using compressed air or inert gas. 172 INSPECTION AND CERTIFICATION: 172.1 173 PAINTING/COATING: 173.1 174 At all times during which work on the order is being carried out, the Employer or his representative shall have free access to those parts of the Contractor/Manufacturer’s premises where the separators are being manufactured and tested. Tank surfaces and other equipments shall be coated in accordance with the standard specification of “Painting” as applicable. DOCUMENTATION: 174.1 175. All documentation shall be in SI units and shall be in English. The Contractor shall submit the required documentation. IDENDIFICATION: 175.1 176 The tank shall be fitted with durable identification plates in accordance with the code or standard to which they are constructed. The text of such plates shall be in English and shall include the Employer’s Identification Number. DELIVERY: 176.1 Gas RMS Bib-III The Contractor shall not be deemed to have delivered the tank until the 294 Employer has received the tank and the associated documentation and certificates. After testing, tank shall be prepared for export shipment. All nozzles shall blank off and all flange faces shall be protected against corrosion and damages. Such protection shall be adequate for long-term storage (up to six months under site conditions). X. Specification of API pipes, Pipe materials and Fitting 177 These are the minimum specification of API pipes, Pipe materials and Fitting required for the RMS Construction. 16? Pipe 14? Pipe 10? Pipe DN : API 5LX52 Line Pipe, SCH/80, Seamless, MS, Uncoated, Beveled End (30° ), End Protector Cap, (equivalent to Sch-80). b) Length of each pipes : 12 ± 0.2m c) Hydrostatic Pressure Testing: 200 Bars. DN : API 5LX52 Line Pipe, SCH/80, Seamless, MS, Uncoated, Beveled End (30° ), End Protector Cap, (equivalent to Sch-80). b) Length of each pipes : 12 ± 0.2m c) Hydrostatic Pressure Testing: 200 Bars. DN : API 5LX52 Line Pipe, SCH/80, Seamless, MS, Uncoated, Beveled End (30° ), End Protector Cap, (equivalent to Sch-80). b) Length of each pipes : 12 ± 0.2m c) Hydrostatic Pressure Testing: 200 Bars. 8? DN Pipe : API 5LX52 Line Pipe, SCH/80, Seamless, MS, Uncoated, Beveled End (30° ), End Protector Cap, (equivalent to Sch-80). b) Length of each pipes : 12 ± 0.2m c) Hydrostatic Pressure Testing: 200 Bars. 6? DN Pipe API 5LX52 Line Pipe, SCH/80, Seamless, MS, Uncoated, Beveled End (30° ), End Protector Cap, (equivalent to Sch-80). b) Length of each pipes : 12 ± 0.2m c) Hydrostatic Pressure Testing: 200 Bars. API 5LX52, SCH/80 Seamless pipe, b) Length of each pipes : 12 ± 0.2m c) Hydrostatic Pressure Testing: 200 Bars. 4” DN Pipe 178. These are the minimum specification of pipe material and fitting required for the RMS Construction. Flange 10? Ø X 600 RF, 300 RF 8? Ø X 600 RF, 300 RF Weld neck, dimension and drilling in accordance with ANSI B.16.5. Materials to be forced carbon steel ASTM A105, EP: ANSI 16.25 8? Ø X 300 RF, 300 RF 6? Ø X 600 RF, 300 RF 4? Ø X 600 RF,300 RF 2? Ø X 300 RF Gas RMS Bib-III 295 14? Ø X 600 RF, 300 RF 12? Ø X 600 RF, 300 RF 16? Ø X 600 RF, 300 RF Blind Flange 10? Ø X 600 RF, 300 RF 8? Ø X 600 RF, 300 RF 8? Ø X 300 RF, 300 RF 14? Ø X 600 RF, 300 RF 12? Ø X 600 RF, 300 RF 16? Ø X 600 RF, 300 RF Metallic/Asbestos Gasket 600/300 class Elbow Reducer Tee Socket, Nipple, P lug 1/2´´Ø, 1´´Ø Stud Bolt Gas RMS Bib-III Materials to be forced carbon steel ASTM A105, dimension and drilling in accordance with ANSI B.16.5. EP: ANSI 16.25 Spiral wound stainless steel gasket according to ANSI B16.21 for use with RF flanges to ANSI B16.5. Short ANSI B 16.9 and ASTM A234 Gr. WPB Butt weld, Sch-40 ANSI B 16.9 ASTM A234 Gr. WPB Butt-welded, Concentric with guided bar, Butt Weld ANSI B 16.9 and ASTM A234, Sch-80 3000lb, ASTM A105, ANSI B 16.11 ANSI B 16.5/ ANSI B 18.2.2 296 Section 8: Particular Specifications Electrical Power: RMS Contractor shall make necessary arrangement for supply of electric power from 415 V system of the Power Station (to be finalized later) including cabling and supply and installation of necessary equipment; Gas RMS Bib -III 297 Section 9: Drawings [Attached Drawings in Hard Copy] Gas RMS Bib-III 298 Gas RMS Bib-III 299 Gas RMS Bib-III 300 Gas RMS Bib-III 301 Gas RMS Bib-III 302 Gas RMS Bib-III 303