August 2015
Transcription
August 2015
August 2015 TODAY A monthly newsletter for employees of RailWorks Corporation and its subsidiaries SPECIAL EDITION It’s that time again for the annual RailWorks Today salute to our employees and their work for Class 1, short line and regional railroads; transit and port authorities; industrial facilities and any other setting where rail is found. In this edition, you’ll see examples of all types of track and transit construction and maintenance performed this summer throughout the United States and Canada. We dedicate this special edition to all employees, and we extend a special thanks to those who submitted the photos and background information for this issue. PNR RailWorks Canadian National Railway (CN) Near Brandon, Manitoba Track construction crews based in Cochrane, Alberta, have been out in force for CN this summer. Read about their work on page 2. 2 August 2015 PNR RailWorks Canadian National Railway (CN) Near Brandon, Manitoba Crews who work out of the Cochrane, AB, office are constructing 8 miles of new track with concrete ties and installing eight turnouts on CN’s main line on the Rivers Subdivision, between Winnipeg and Melville, Manitoba. So far they’ve installed six of the turnouts over three blocks, or outages, involving 30 track workers, 10 operators, four foremen and three superintendents. Three crews utilized seven back hoes on this installation in early August to position a #20 turnout and five 39-foot track panels. Under the direction of Project Manager Sushank Sharma, the installations were well planned, organized and executed without any delays or issues. Other project leaders include Project Engineer Teuta Berntson, Superintendents Gary Fahl, Troy Dunkin and Pat Russet as well as Foreman George Dwernychuk, Jose Andrade, Brenon DeRose and Bruce Barter. The project concludes in the fall. RailWorks Track Systems BNSF Railway Warm Springs, MT RailWorks Track Systems’ Chehalis-based production gang worked for eight weeks this summer on the Burlington Northern Santa Fe (BNSF) Railway in Big Sky Country (aka Montana). Crews rehabilitated BNSF’s Copper City Subdivision, located between Butte and Garrison, changing out 53,000 ties, rebuilding 13 crossings and surfacing, lining and dressing more than 277,000 linear feet of track. Led by Project Manager Mark Hornby, the project kept up to 35 employees busy during this peak period in early July near Warm Springs. The tie gang and following Quality Control crew worked in tandem while another crew upgraded a crossing. The large image of the tie gang working in the shadow of the Anaconda Mountain Range is one we are featuring in a new ad in August trade publications to introduce our maintenance-of-way services. 3 August 2015 RailWorks Track Systems Seaport Steel Airway Heights, WA Not far from RailWorks Track Systems’ Spokane office, a crew led by Project Manager Brian Wilson constructed a new rail spur connecting Seaport Steel’s new facility to Eastern Washington Gateway Railroad (EWG). Here, Operator Mike Kober moves the loader to stage concrete ties for the spur. Meanwhile, Foreman Casey Pardun maneuvers the excavator to reposition the ties as Laborer Bill Thompson signals the proper position. The crew constructed a total of 1837 feet of track – 500 in the facility and just over 1,300 to connect with EWG. L.K. Comstock National Transit Sound Transit SeaTac, WA Foreman Laurel Vredenburg (l) and Steward Stephen Koreiva coordinate with Crane Operator Neal Figgess (hidden by the pole) August 11 to set poles into position south of Seattle for the overhead catenary system (OCS) that will power Sound Transit’s new light-rail extension. L.K. Comstock will continue this work throughout August along the 1.6-mile elevated double-track guideway between the current SeaTac Airport station and South 200th Street. Project Manager Ben Neeley leads this project with support from Construction Manager Mike Akin. Once revenue service starts in 2016, L.K. Comstock will have completed installation of one 3 MW Modular traction power substation, the OCS, train control, signal and communications systems, as well as the systems interface with the existing light-rail transit systems. RailWorks Track Systems Miami International Airport (MIA) Terminal E Miami, FL RailWorks Maintenance of Way BNSF Railway (BNSF) Broken Bow, NE Grinding Supervisor Shea Swindall waters down the track where the grinder has just passed to douse any sparks and safeguard against a potential fire. Meanwhile, Operator Reymundo Moreno drives the grinder through this crossing on BNSF’s main line, in about the center of Nebraska. RailWorks began grinding services on BNSF in April and will continue working in Nebraska and Wyoming through the rest of the year. Work for the day has just concluded on the south guideway near the Terminal Station at MIA. In April, RailWorks began constructing the 1230-foot steel running surface and supporting posts for the new cable car system to carry passengers at Terminal E, the international terminal. The cable car vehicles will run on top of the beam shown here on the east end of the guideway with the control tower in the background. This new system will utilize the existing substructure from an automated people mover (APM) that had been operating on only one track at MIA’s Terminal E for the past 10 years or so. Scott Stark serves at project manager with support from Superintendent T.J. McChristy, Project Engineer Ben Bakkum and Quality Control Manager Tomas Ramos. The project wraps up at the end of the year. PNR RailWorks Canadian National Railway (CN) Northern British Columbia Nearly 1,800 km. (about 1,100 miles) northeast of Vancouver, a Pacific-region crew is hard at work relaying rail on CN’s Chetwynd Subdivision. Under the direction of Project Manager Julie Edgar, Superintendent Al Graham and Foreman Kevin Douglas, the crew has been working since June installing approximately 200,000 feet of rail on the CN main line. Using a Drapeau rail heater, the crew de-stressed rail prior to welding it together. The project wraps up this fall. 4 August 2015 RailWorks Maintenance of Way Puget Sound and Pacific Railroad (PSAP) Near Shelton, WA RailWorks is testing track geometry on this Genesee & Wyoming (G&W) short line this summer. It is one of more than 50 G&W short lines RailWorks has tested since last fall. Here, Geometry Operator Mark Wright drives a hi-rail vehicle equipped with SolidTrack technology to generate a detailed profile of the track’s conditions. Data is recorded in high resolution showing all urgent and warning defects in real time. Using this service, railroads are alerted to defects so they can be corrected immediately to improve track safety. RailWorks Track Services Ameren Meramec Power Plant St. Louis County, MO RailWorks Track Systems Canadian National Railway (CN) Northwest of Cedar Falls, IA In conjunction with the construction of a new highway interchange on U.S. Highway 218 (visible in the distance), RailWorks is relocating a 7,000-foot portion of CN mainline track that runs parallel to the highway, moving it about 1,000 feet further west. In this photo, Operator Kyle DeSantis lays continuous welded rail as part of the track relocation. Crews are also removing the old mainline track. They began work June 1 and anticipate finishing by September. Andrew Caulum is project engineer/estimator, and on-site superintendent is Bill Kadrlik. From left, Laborers A.J. Huett and Jordan Copeland; Operator Shawn Iman; Laborers Cordero Taylor and Jeff Downey; and Leadman Paul Shinabargar conduct a re-briefing after lunch at the plant, where they changed out and gauged 180 cross ties. The crew, under the direction of Project Manager Jerry Huffman and Foreman Charlie King, handled the job over a four-day period. RailWorks also has performed work recently at other Ameren coal plants in Franklin and Jefferson counties in Missouri. 5 August 2015 L.K. Comstock & Co. RailWorks Transit Second Avenue Subway Manhattan, NY During a track invert concrete pour in early July, RailWorks employees constructing the Second Avenue Subway work together in rapid succession. At street level above the tunnel, multiple mixers send grout and concrete through a slickline pipe to a German-made Rhomberg concrete hopper-finisher dispensing unit, used for disbursing concrete to form the track invert. The Rhomberg unit travels in the tunnel on hi-rail gear along skeletonized track, while distributing concrete around and underneath the ties. After a track section of about 75 linear feet is poured, workers then discontinue the concrete flow and remove the corresponding pieces of slickline piping. They then reattach the Rhomberg unit to the now-shorter slickline running from the concrete mixer to pour the next section. On this day, the process was repeated until concrete for approximately 600 feet of track invert was poured out. The concrete pour was part of the construction of the Second Avenue Subway, an 8.5-mile line between 105th Street and an existing subway station at 63rd Street on Manhattan’s East Side. Work on the project began in January 2012 and has an advertised completion date of late December 2016. Fred Haffner is the project manager; Doug Cullen is the general foreman. RailWorks Track Systems Metro Transit Near Big Lake, MN Along the Northstar commuter rail line serving the Minneapolis-St. Paul metropolitan area, RailWorks made winter walking safer by adding ballast to extend a walkway. The crew added ballast in a 1,200-foot area along the track shoulder, creating a safer winter pathway for railroad employees who had been unexpectedly stepping off the snow-covered shoulder. In this photo, Tamping Foreman Don Kilgore helps operator Terry Lindner steer clear of signal boxes. 6 August 2015 RailWorks Signals & Communications All Aboard Florida Ft. Lauderdale, FL Under the direction of Managers Timothy Woods and Jason Stingley, a crew re-cables a newly installed cantilever and crossing gate at West Broward Boulevard. The work is being performed for All Aboard Florida, which is upgrading the track and signals on the Florida East Coast Railroad in order to run high-speed commuter trains in Florida between Miami, Cocoa Beach and Orlando. RailWorks has completed similar work on 10 crossings between Ft Lauderdale and West Palm Beach over the past two months and will be closing out this phase of the project in August. RailWorks Track Services RailWorks Track Services Adams Branch Railroad North Adams, MA Canadian Pacific Railway (CP) Albany, NY RailWorks is rehabilitating 4 miles of an industrial siding track that will become the track for a tourist train through the Berkshire Hills/Hoosac Mountain Range in western Massachusetts. Here, the spiking and gauging crew is at work installing some of the 8,000 cross ties that are part of this project. Crews, led by Project Manager Scott Hoeffler and Superintendent Rocky Bradway, also will install 292 switch timbers, more than 9,300 feet of rail, six crossings and ballast as well as anchor and surface 4 miles of track. The rehab should wrap up this month for the Hoosac Valley Service, transporting passengers on a 25-minute ride between the Adams, MA, Visitors Center and Western Gateway Heritage State Park in North Adams. A crew prepares to install a #11 turnout for CP in Albany, where they also are installing a #9 turnout and a double-point, split-switch derail. They will finish installing 200 ties prior to constructing 2,400 feet of track and surfacing the track and turnouts. Superintendent is David Lafountain, and Scott Hoeffler is managing the project, with a target completion of mid-September. Phase 2 starts this month and calls for working in Kenwood Yard, also in Albany. RailWorks will construct eight turnouts and 3,000 feet of track using steel ties, as well as surfacing the track and turnouts. 7 August 2015 RailWorks Track Services L.K. Comstock National Transit San Ysidro Freight Rail Yard San Ysidro, CA Laborer Juan Maldonado (left), and Welder Julian Pinzon are in the process of pre-heating the first of eight thermite weld connections that will finalize the construction of this right-hand #9 turnout. RailWorks has been working off and on for about nine months with general contractor West Coast General Corporation to expand and reconfigure this U.S.-Mexico border yard for the San Diego Association of Governments and the Genesee and Wyoming Railroad. RailWorks’ scope of work includes construction of two new storage tracks, the reconfiguring of the existing yard to accommodate movements for these tracks and the demolition and reconstruction of existing track to upgrade the majority of the yard from 90-lb. to 115lb. rail. RailWorks also is adding a new #15 turnout, track and crossing upgrades in the Metropolitan Transit System trolley line. L.K. Comstock has performed overhead catenary system upgrades and modifications to the existing light rail trolley system. In the accompanying photo, an aerial fiber optics cable bundle upgraded by L.K. Comstock is visible above a manlift used to support the splicing of the existing fiber backbone cable. During weekend outages in late-August, RailWorks, L.K. Comstock and West Coast General are tying in the main line to the yard and performing other activities associated with the cutover. Ralph Berg (RailWorks Track Services) and Walt Stamirowski (L.K. Comstock National Transit) are project managers, Aaron Neeley is the construction manager, and Luis Branco is the onsite foreman. The target for completion is by the end of the year. RailWorks Track Systems Archer Daniels Midland (ADM) Milling Lincoln, NE Two crews out of the Fremont office are installing a new #9 crossover for ADM Milling as part of a comprehensive, three-year yard upgrade project at the milling facility. RailWorks completed Phase I last year. Now in Phase II, crews are removing 85 lb. rail, ties, turnouts, and other material, replacing a crossover and a turnout and adding about 1,000 feet of 133-lb. relay rail, new ties and other material. Jerod Jobson, shown here coordinating the removal of a turnout, and Jesus Baeza were foremen on the crossover installation project. Supervisors include Project Manager Ryan Karr, Project Engineer Steven Salzwedel and Track Inspector Gerald Boyer.