Open the document by pressing here
Transcription
Open the document by pressing here
FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO – SMOKVICA OF PAN-EUROPEAN CORRIDOR X FINAL REPORT April 17th 2007 Prepared by: Marios Miltiadou, Transport Engineer Scientific Advisor: Socrates Basbas, Dr. Transport Engineer External Advisor: Lazaros Lazaridis, Civil Engineer FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X TABLE OF CONTENTS EXECUTIVE SUMMARY 5 1. PREFACE 11 2. SCOPE, OBJECTIVES AND CONTENT OF THE WORK 13 3. METHODOLOGY AND BACKGROUND INFORMATION 17 3.1 3.2 REVIEW OF EXISTING STUDIES AND OTHER AVAILABLE INFORMATION EVALUATION OF AVAILABLE INFORMATION AND DATA UPDATES 17 REQUIREMENTS AND DESIGN OF DATA COLLECTION PROCESS 17 3.3 DATA COLLECTION SURVEYS AND COOPERATION WITH STAKEHOLDERS IN THE F.Y.R. OF MACEDONIA 3.4 TOOLS 3.4.1 TOOLS FOR THE TRAFFIC FORECASTS 3.4.2 TOOLS FOR THE EVALUATION OF VARIOUS ALTERNATIVES OF THE PROJECT 3.4.3 TOOLS FOR THE ECONOMIC ANALYSIS (NPV, IRR, B/C RATIO) 18 18 18 18 18 4. 20 PRESENTATION OF THE PROJECT 4.1 EXISTING SITUATION 4.1.1 PAN-EUROPEAN ROAD CORRIDOR X 4.1.2 GENERAL DESCRIPTION OF PROJECTS ON ROAD CORRIDOR X IN THE FORMER YUGOSLAV REPUBLIC OF MACEDONIA 4.1.3 EXISTING ROAD GEOMETRICAL CHARACTERISTICS 4.1.3.1 Length of section 4.1.3.2 Cross section 4.1.3.3 Horizontal alignment 4.1.3.4 Design speed 4.1.3.5 Vertical alignment 4.1.3.6 Pavement 4.1.3.7 Structures 4.1.3.8 Intersections 4.1.3.9 Traffic signs 4.1.3.10 Lighting 4.1.3.11 Road facilities 4.1.3.12 Traffic counters and toll stations 4.1.4 EXISTING ROAD OPERATIONAL CHARACTERISTICS 4.1.4.1 Traffic flows 4.1.4.2 Traffic flows characteristics 4.1.4.3 Accidents EGNATIA ODOS S.A. APRIL 2007 20 20 22 26 26 26 27 28 28 29 29 30 30 30 30 30 30 30 33 39 2 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 4.2 ALTERNATIVES OF INFRASTRUCTURE DEVELOPMENT (ROAD PHYSICAL AND OPERATIONAL CHARACTERISTICS INCLUDING TOLL STATIONS) 4.2.1 ALTERNATIVE A: DO MINIMUM 4.2.2 MOTORWAY CONSTRUCTION (ALTERNATIVES B, C, D) 4.2.2.1 General description – Design speeds and typical cross-sections 4.2.2.2 Length of section 4.2.2.3 Horizontal alignment 4.2.2.4 Vertical alignment 4.2.2.5 Pavement 4.2.2.6 Structures 4.2.2.7 Traffic interchanges 4.2.2.8 Environmental protection equipment 40 41 41 41 45 45 46 47 47 48 49 5. 50 TRAFFIC FORECASTS 5.1 PRESENTATION OF THE TOOL FOR TRAFFIC FORECASTS 5.1.1 METHODOLOGY OF THE DEVELOPMENT OF THE FORECASTING TOOL 5.1.1.1 Data collection – Construction of the base year database 5.1.1.2 Methodological issues and constraints 5.1.1.3 Adopted methodology and assumptions for the scenarios’ development 5.1.2 THE SCENARIOS 5.1.3 ESTIMATION OF THE PASSENGER AND FREIGHT FLOWS 5.1.3.1 Estimation of the international passenger and freight flows on Corridor X 5.1.3.2 The model 5.1.3.3 Estimation of local traffic and assignment of road Corridor X 5.2 FORMULATION OF SCENARIOS (TIME HORIZONS) 5.3 TRAFFIC FORECASTS 5.3.1 EVALUATION OF TRAFFIC PROJECTIONS 5.3.1.1 General conclusions of the traffic flows forecasting of the Technical Secretariat of Corridor X 5.3.1.2 Results and evaluation of results of the various available traffic flows forecasting exercises 5.3.1.3 Traffic projection to various target years 5.4 EVALUATION OF ALTERNATIVES LEVEL OF SERVICE IN FUNCTION WITH 6. 50 50 50 50 50 51 52 52 55 57 57 58 58 58 59 60 THE FORECASTED TRAFFIC FLOWS 66 ECONOMIC ANALYSIS 67 6.1 PARAMETERS OF THE ANALYSIS 6.1.1 DETERMINATION OF EXPECTED COST ELEMENTS 6.1.1.1 Construction cost 6.1.1.2 Operational expenses (annual and periodical maintenance) 6.1.2 DETERMINATION OF EXPECTED BENEFIT ELEMENTS 6.1.2.1 Time savings 6.1.2.2 Benefits form the vehicle operational costs reduction 6.1.2.3 Benefits from time savings as far as the vehicle users are concerned 6.1.2.4 Benefits from the reduction in the number of road accidents 6.1.2.5 Residual value of the project 6.1.2.6 Installation and operation of toll stations 6.1.3 CONSIDERATION OF ELEMENTS WHICH CANNOT BE QUANTIFIED EGNATIA ODOS S.A. APRIL 2007 67 68 68 69 70 71 72 73 74 76 77 77 3 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 6.1.3.1 Consumer surplus 6.1.3.2 Spatial and regional development aspects 6.1.3.3 Employment impacts 6.2 ENVIRONMENTAL CONSIDERATIONS 6.3 FINANCING ASPECTS 6.3.1 TOLL REVENUES 6.3.2 CASH FLOW 6.4 RESULTS OF THE ECONOMIC ANALYSIS 6.5 SENSITIVITY ANALYSIS – COMPARATIVE EVALUATION OF ALTERNATIVES 77 78 78 80 82 83 85 87 6.6 AND RANKING CONCLUSIONS CONCERNING THE ECONOMIC ANALYSIS 90 94 7. RECOMMENDATIONS 95 BACKGROUND DOCUMENTS – REFERENCES 97 ANNEXES 99 A. B. 99 99 ISSUES DISCUSSED AT THE TECHNICAL MEETING IN SKOPJE (01.03.2007) RESULTS OF THE ECONOMIC ANALYSIS EGNATIA ODOS S.A. APRIL 2007 4 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X EXECUTIVE SUMMARY The feasibility study for the improvement of the road section between Demir Kapija – Udovo – Smokvica, part of the Main Axis of Pan-European Transport Corridor X in the Former Yugoslav Republic of Macedonia, has been carried out by Egnatia Odos S.A. (E.O.A.E.) at the request of the Greek Ministry of Foreign Affairs. The methodology followed for the current study is fully aligned with the standards set by the Greek Ministry of Environment, Physical Planning and Public Works and the European Commission. The project appraisal has been carried out in socio-economic level with the Cost Benefit Analysis. The road section of the existing E-75 (M-1) road between Demir Kapija and Smokvica has a total length of 35.834km. The examined alignments for motorway construction are two: Alignment 1 is the one proposed and designed in detail by Scetauroute International in 2000, also approved by the local government, and foresees the transformation of the existing M-1 road to motorway profile. The total length of Alignment 1 is 32.15km, which can be divided into two subsections: Subsection Demir Kapija – Udovo, 19.9km through the “gorge” and the subsection Udovo – Smokvica, 12.25km through the valley southwards of the “gorge”. Alignment 2 foresees the construction of a totally new motorway on the west bank of the Vardar River. The total length of Alignment 2 is 28.05km The construction period is six (6) years for Alignment 1 and three (3) years for Alignment 2. Therefore, with start of construction works in 2008, the foreseen completion of the project is the end of 2013 and 2010, respectively. The motorway will be completely open to traffic in 2014 in the case of Alignment 1 and in 2011 in the case of Alignment 2. Four options are examined in the cost benefit analysis. The “Do minimum” alternative (Alternative A) concerns the upgrading of the existing road. Three alternatives of motorway construction are examined for both alignments: Alternative B examines the construction of a motorway with cross-section width of 22.6m; Alternative C examines the construction of a motorway with cross-section width of 24.6m; and Alternative D examines the construction of a motorway with the cross-section widths proposed by the designs of the two alignments: For Alignment 1 the cross section on the easy parts (Udovo – Smokvica) is 27.6m wide and in the gorge is 26.4m. For Alignment 2 the cross section is 28.2m along the entire motorway. The traffic analysis has exploited traffic statistics from the period 1989 – 2002, which includes the period of crisis in the region, and some recent data of the years 2005EGNATIA ODOS S.A. APRIL 2007 5 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 2006. The last year’s increase of traffic was more than 25%; however, such growth is not expected to occur continuously over the entire analysis period. The average annual traffic growth rate used in the study during the entire period of analysis is 4%, with the realistic assumption of higher growth factor of 5% in the initial years of analysis to represent the anticipated increase of traffic to reach the levels of 1990 by the years between 2015 and 2020 (depending on the upgrading alternative) and taking into consideration the dynamic of a developing country in the region of the Western Balkans in their E.U. direction. Annual traffic growth rates of 4% and 3% (for the next two decades, respectively) are considered realistic to be retained even after a prospective EU enlargement within the following years, due to the simplification (or even elimination) of border crossing procedures and the diversion of traffic from other competitive European routes (e.g. bypass of international traffic through Romania and Bulgaria). Addition of traffic applied for the motorway solutions is 15%. It is assumed that this percentage represents the generated traffic, as well as the traffic diverted from other Pan-European Corridors in the area and from other national and regional roads (M-5 and M-6 to/from Strumica and Dojran). Traffic forecasts have been reduced after the introduction of tolls, with diversion of 7.7% of traffic, mainly local, to the alternative road network (diversion of 9% of private cars, 3% of buses and 5% of heavy trucks). Especially for Alignment 2 an additional 14.8% of the traffic (almost triple in total compared to traffic diversion in the case of Alignment 1) was considered intermediate local traffic around Udovo and was subtracted, due to the fact that an interchange is not foreseen at Udovo. In summary the weighed average AADT along the proposed motorway of Alignment 1 from Demir Kapija to Smokvica is estimated at 5,881 veh/day (8,230 PCUs/day) in 2015, 8,789 veh/day (12,300 PCUs/day) in 2025, and 11,926 veh/day (16,691 PCUs/day) in 2035. For Alignment 2 the forecast is 4,901 veh/day (7,108 PCUs/day) in 2015, 7,324 veh/day (10,623 PCUs/day) in 2025, and 9,939 veh/day (14,414 PCUs/day) in 2035. Total costs for the various alternatives of motorway construction are summarised for the two alignments in the following table: Alignment 1 2 Economic construction cost (€) Alternative B Alternative C Alternative D 152,613,331 156,621,546 144,501,616 114,829,350 125,149,748 107,989,433 The costs of the alternatives of narrower sections, compared to the costs of Alternatives D are lower at 2.6% and at 7.7% for the cases (respectively) of Alternatives C and B of Alignment 1, while for Alignment 2 the respective reduction is of 8.25% and 13.7%. EGNATIA ODOS S.A. APRIL 2007 6 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Construction costs, operational and maintenance costs have been compared with quantified impacts used in the socioeconomic analysis of the project, which include: Benefits from vehicle operating costs reduction Benefits from time savings Benefits from accidents reduction Residual value of project These benefits were examined for the expected traffic with or without the project. Consumer surplus benefits expected from the additional traffic were not included in the economic analysis that would cause higher values of the economic indices. The results of the socioeconomic analysis for the motorway Alternative D for the period 2008 – 2032 (25 years after the commencement of construction works) are as follows: Alignment 1 Economic Internal Rate of Return (EIRR) Net Present Value (NPV) – Discount rate 8% Net Present Value (NPV) – Discount rate 6% Net Present Value (NPV) – Discount rate 4% Benefits over Costs ratio (B/C) 1.91% -68,486,440 € -56,714,117 € -36,349,902 € 0.36 Alignment 2 Economic Internal Rate of Return (EIRR) Net Present Value (NPV) – Discount rate 8% Net Present Value (NPV) – Discount rate 6% Net Present Value (NPV) – Discount rate 4% Benefits over Costs ratio (B/C) 5.87% -21,681,005 € -1,573,624 € 28,638,824 € 0.77 Respectively for alternatives B and C the results of socioeconomic analysis are: Alignment 1 Economic Internal Rate of Return (EIRR) Net Present Value (NPV) – Discount rate 8% Net Present Value (NPV) – Discount rate 6% Net Present Value (NPV) – Discount rate 4% Benefits over Costs ratio (B/C) Alternative B 2.33% -59,456,895 € -47,430,231 € -27,013,094 € 0.40 Alternative C 2.05% -65,523,614 € -53,644,360 € -33,220,670 € 0.37 Alternative B 7.06% -8,442,372 € 11,501,944 € 41,109,817 € 0.90 Alternative C 6.49% -14,290,808 € 5,584,182 € 35,252,837 € 0.84 Alignment 2 Economic Internal Rate of Return (EIRR) Net Present Value (NPV) – Discount rate 8% Net Present Value (NPV) – Discount rate 6% Net Present Value (NPV) – Discount rate 4% Benefits over Costs ratio (B/C) EGNATIA ODOS S.A. APRIL 2007 7 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Finally, for the “Do minimum” alternative (Alternative A) the economic analysis results NPV of -19,589,010 € and B/C ratio of 0.10. The IRR is not defined. The analysis included the costs for an upgrade in 2008 and rehabilitation in 2023, as well as the annual operational and maintenance costs of the existing E-75 road. Sensitivity analysis for alteration of critical parameters (construction costs, operational costs and traffic), carried out for the three motorway alternatives of each alignment, resulted the following: Alignment 1 Initial EIRR value Increase of construction costs by 10% Reduction of construction costs by 10% Increase of operational costs by 10% Reduction of operational costs by 10% Increase of traffic by 10% Reduction of traffic by 10% Increase of traffic by 20% Reduction of traffic by 20% Economic Internal Rate of Return (EIRR) Alternative B Alternative C Alternative D 2.33% 2.05% 1.91% 1.70% 1.42% 1.29% 3.05% 2.75% 2.60% 2.25% 1.96% 1.81% 2.42% 2.13% 2.00% 2.83% 1.83% 3.32% 1.30% 2.52% 1.56% 2.99% 1.06% 2.38% 1.42% 2.85% 0.92% Alignment 2 Initial EIRR value Increase of construction costs by 10% Reduction of construction costs by 10% Increase of operational costs by 10% Reduction of operational costs by 10% Increase of traffic by 10% Reduction of traffic by 10% Increase of traffic by 20% Reduction of traffic by 20% Economic Internal Rate of Return (EIRR) Alternative B Alternative C Alternative D 7.06% 6.49% 5.87% 6.17% 5.63% 5.05% 8.09% 7.48% 6.83% 6.98% 6.40% 5.78% 7.13% 6.57% 5.96% 7.96% 6.13% 8.85% 5.17% 7.35% 5.60% 8.20% 4.69% 6.70% 5.03% 7.51% 4.16% Other unquantifiable impacts, such as the environmental, spatial – regional and employment impacts have been considered. EGNATIA ODOS S.A. APRIL 2007 8 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Concerning the environmental impacts of the project, it must be stressed that the Demir Kapija canyon is a very sensitive region; special attention should be paid for any of the qualified motorway alignment/ alternative. The environmental impacts of each of the two alignments examined are currently being studied and it is very crucial to be taken fully into consideration before the final decision for the project realisation. According to the assurance of the designers of the new alignment (Alignment 2) on the west side of Vardar River, this solution is more environmentally friendly compared to Alignment 1. The design of the new alignment avoids extensive cuts and embankments, sites of archaeological interest and the offence of Bela Voda Cave, while it has no conflict with a future dam to be constructed in Vardar River. Concerning direct employment impacts, it is expected that the realisation of Alignment 1 would result around to 2,190 jobs (13,150 man-years) during the construction period and around to 55 jobs for the annual maintenance and operation of the motorway. Further labour needs of 1,100 man-years are also expected for the periodical maintenance of the motorway during the analysis period. The respective figures for Alignment 2 are 3,700 jobs (11,150 man-years) during the construction period, around to 45 jobs for annual maintenance and operation and around to 900 man-years for periodical maintenance. Indirect employment is expected due to the increase of labour force employment at enterprises providing material and equipment during the construction and operation/ maintenance of the project. Additional jobs are also expected with the development of motorway service areas along the entire Corridor X in the F.Y.R. of Macedonia. In conclusion the project realisation should be considered, apart from the technoeconomic point of view, in combination with its expected social, regional and spatial benefits, taking also into account the following EU transport policy related considerations: The project is a part of the backbone of the South East Transport Core Network, the Pan-European Corridor X and on the South Eastern European priority axis defined by the HLG of EC/ DG TREN chaired by ex Commissioner de Palacio. The project is a significant missing link of the Main part of Corridor X motorway and with its construction the completion of a 1,450km motorway will be achieved by 2012 (according to the existing national plans and commitments, a motorway which serves international transit flows of goods and passengers from Central Europe to Turkey and Asia and vice-versa. The project contributes to the arsis of the isolation of the Western Balkans, regional development and cohesion of a future region of the European Union. The project contributes to the strengthening of the bilateral relations of Greece and the Former Yugoslav Republic of Macedonia through the facilitation of trade and tourism by improving the access between Skopje and Thessaloniki and the Central Macedonia region. EGNATIA ODOS S.A. APRIL 2007 9 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Finally, it gives improved access to the Former Yugoslav Republic of Macedonia to the sea and specifically to the port of Thessaloniki, which also contributes to the increase of the regional and international role of the port. Therefore, the realisation of the project is subjected to a political and not only technoeconomic decision. EGNATIA ODOS S.A. APRIL 2007 10 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 1. PREFACE The feasibility study for the improvement of the road section between Demir Kapija, Udovo and Smokvica, part of the Main Axis of Pan-European Transport Corridor X in Former Yugoslav Republic of Macedonia, has been carried out by Egnatia Odos S.A. (E.O.A.E.) at the request of the Greek Ministry of Foreign Affairs. The road section under study, 35.834km of existing infrastructure, is of major importance for both the Former Yugoslav Republic of Macedonia and the Republic of Greece. For this reason the Government Former Yugoslav Republic of Macedonia has shown interest in applying for financial support for the improvement of this road section, under the special financial aid program of the Greek Ministry of Foreign Affairs called “Hellenic Plan for the Economic Reconstruction of the Balkans” (Hi.P.E.R.B.). In 2002, the Former Yugoslav Republic of Macedonia submitted to the Greek Ministry of Foreign Affairs two unofficial applications for financial support for the motorway construction of Tabanovce – Kumanovo and Demir Kapija – Gevgelija. In 2004, a new unofficial application was submitted for motorway construction of Demir Kapija – Smokvica, since the financing of the southern section between Smokvica and Gevgelija was secured by the European Bank for Reconstruction and Development. Most recently, in November and December 2006, intensive negotiations took place between the Secretariat for European Affairs, responsible authority for the implementation of the Hi.P.E.R.B. in the Former Yugoslav Republic of Macedonia, and the Greek Ministry of Foreign Affairs. Those negotiations concluded to the immediate speed up of the procedures for the technical documentation of the project and the submission of a respective official application for Hi.P.E.R.B. During the above-mentioned negotiations, the immediate elaboration of a feasibility study was agreed, which would be the update of the feasibility study elaborated by Scetauroute in 1999 (for the section Demir Kapija – Gevgelija), and would also comprise the examination of an alternative alignment designed at preliminary level, simultaneously with the feasibility study, by E.O.A.E. and the Fund for National and Regional Roads (F.N.R.R.) of the Former Yugoslav Republic of Macedonia. In this aspect, the Secretariat for European Affairs has submitted part of the technical documentation already prepared by Scetauroute International, namely the feasibility study and the detailed design studies for the basic alignment. Finally it is noted that, the bilateral agreement includes also the examination of alternative types of technical interventions on the entire section, in order to secure the economic feasibility of the project and give the potential for co-financing of the project. Hence, this feasibility study attempts to make a comparative examination of alternative motorway solutions, as well as the new alignment put on table by the F.N.R.R. on the west side of the Vardar River. EGNATIA ODOS S.A. APRIL 2007 11 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X ACKNOWLEDGEMENTS The authors would like to acknowledge the support of the following Institutions, Authorities and individuals: The Secretariat for European Affairs of the Former Yugoslav Republic of Macedonia, primarily the Head of the Sector for Foreign Aid Coordination, Mr. Jovan Despotovski. The Director and the staff of the Fund for National and Region Roads of the Former Yugoslav Republic of Macedonia. The Technical Secretariat of the Steering Committee for the Pan-European Transport Corridor X. Their consultation, provision of data and information contributed the most in the elaboration of the present study. EGNATIA ODOS S.A. APRIL 2007 12 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 2. SCOPE, OBJECTIVES AND CONTENT OF THE WORK Pan-European Road Corridor X is one of the ten priority Corridors in the wider European area and the backbone of the Transport Core Network of Southeast Europe. It coincides with the Southeast Priority Axis as defined in November 2005 by the EC/ DG TREN High Level Group, chaired by the memorable ex Commissioner Mrs. Loyola de Palacio. Corridor X is the north-south Corridor running through the territory of the Former Yugoslav Republic of Macedonia with a total length of 332.28km of existing infrastructure, while Corridor VIII is the west-east Corridor. Both Corridors are of major importance for the country, since their development will ensure better service of its domestic and international traffic and will enhance trade, economic development and regional cohesion in Europe. Corridor X, and mainly the Main Axis of the Corridor, is the first priority for the government, proved by the fact that substantial progress has been made during the last years, while its completion is anticipated in the forthcoming years. Source: Fund for National and Regional Roads Map 2.1: Pan-European Corridors of interest in the Former Yugoslav Republic of Macedonia EGNATIA ODOS S.A. APRIL 2007 13 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Source: Fund for National and Regional Roads Map 2.2: Constructed motorways along the Pan-European Corridors VIII and X in the Former Yugoslav Republic of Macedonia (in green colour) Furthermore, Corridor X is of significant importance to Greece, being the traditional route connecting Greece with Central Europe. Due to the war crisis in the region in the 1990’s, infrastructures have been damaged and neglected. The service of the freight and passenger (incl. tourist) traffic flows to and from Greece became more complicated with the creation of four new states along the route; six additional border stations were introduced on the main Corridor. Both countries, in the framework of their intensive cooperation, target the revitalisation of Corridor X. Their common will is also confirmed by their cooperation through their agreement for the implementation of the Hellenic Plan for the Economic Reconstruction of the Balkans (Hi.P.E.R.B.), the Memorandum of Understanding for Cooperation on Corridor X and the signed Protocol for the improvement of border-crossings along Corridor X. The general objective of the present study is to contribute to the upgrading of the most critical part of the national road network and Corridor X in the Former Yugoslav Republic of Macedonia, enhancing domestic and international trade and passenger flows, leading to lower economic transport costs and economic efficiency gains. The scope of the current study is to examine the feasibility of various technical alternatives for the improvement of the road section of Pan-European Corridor X in EGNATIA ODOS S.A. APRIL 2007 14 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X the Former Yugoslav Republic of Macedonia, namely the section from Demir Kapija to Smokvica, close to the borders with Greece. Within the scope of the study is the determination of the maturity degree of a project to be financed by the Greek Government through the Hi.P.E.R.B. The content of works includes the following actions: exploitation of existing traffic data and formulation of traffic forecast scenarios for the sections under consideration, for the identification of existing or potential future bottlenecks, including details on the share of heavy vehicles, seasonality, etc. identification of a set of technical project alternatives in terms of design standards and technical variants, which will ensure a homogeneous level of service between Demir Kapija and Smokvica, taking into account the particular terrain characteristics and their influence on cost, environmental aspects, and traffic demand on the respective sections. The considered alternatives encompass the transformation of the existing carriageway to a motorway, as well as the construction of a completely new motorway on the opposite (west) side of the River Vardar. evaluation of the economic feasibility of each considered alternative and provision of a ranking of possible schemes. Of course, the proper elaboration of the study presupposed and depended on specific coordination requirements, and namely on the full co-ordination with all the concerned institutional parties and stakeholders in the Former Yugoslav Republic of Macedonia and ascertainment that their requirements are duly taken into account. The parties and stakeholders to consult include the following: the Greek Ministry of Foreign Affairs, to examine the requirements of the Greek Government; the Secretariat for European Affairs of the Former Yugoslav Republic of Macedonia (National Coordinator for the Hi.P.E.R.B); and the Fund for National and Region Roads of the Former Yugoslav Republic of Macedonia to obtain all necessary data and information, get advice and assistance for the preparation of the feasibility study and the fulfilment of the legal, technical and administrative requirements. The activities of E.O.A.E. can be grouped as follows: Fact finding and data collection: Review of all relevant documentation (feasibility studies, designs, etc.), meetings with all the parties and stakeholders (in order to gather information) and analysis of existing data. EGNATIA ODOS S.A. APRIL 2007 15 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Technical project definition: Establishment of alternative engineering proposals for the road sections and assessment of various cross-sections for the two alignments considered for a future motorway. Economic feasibility determination: Based on cost estimates for the alternatives considered and including land acquisition, construction and maintenance costs, and assessment of the benefits of vehicle operating cost, time savings and accidents reduction, the economic feasibility, as indicated by the Internal Economic Rate of Return determination for each alternative. Construction in phases is not examined as bilaterally agreed. Financial assessment: Financial implications for each alternative, including construction and maintenance costs, the options of toll levying and the effects on traffic. Ranking of Schemes: Overall comparison of proposed alternatives, according to economic, environmental and financial criteria, and ranking establishment enabling decision by the competent authorities. Finally, the expected results and deliverables of E.O.A.E. are: By the 8th week after the project assignment: Delivery of the Draft Final Report By the 10th week after the project assignment: Delivery of the Final Report (feasibility study), with traffic data analysis and projections for the relevant road sections and with the assessment of the feasibility of the alternatives for improvement, based on technical, environmental and financial criteria and with recommendation of a preferred alternative. EGNATIA ODOS S.A. APRIL 2007 16 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 3. METHODOLOGY AND BACKGROUND INFORMATION The methodology of the study includes the inventory and evaluation of available data and the collection of the necessary supplementary data, in cooperation with stakeholders in the Former Yugoslav Republic of Macedonia and the Technical Secretariat of Corridor X. 3.1 Review of existing studies and other available information The methodology included the review of all the relevant technical documentation and information, which evidently was the cornerstone of the study. The technical documents made available were the feasibility study and the detail design, prepared by Scetauroute in 2000, as well as traffic statistics for the national road network. Those documents were submitted to the Greek Ministry of Foreign Affairs in December 2006. Furthermore, E.O.A.E. had access to the Road Database and the archive of the Technical Secretariat of the Steering Committee for Pan-European Corridor X. The Database of Corridor X contains useful data regarding the physical and operational aspects of the entire Corridor, such as road category, dimensions of cross section, design and operational speeds, dimensions concerning horizontal and vertical alignment, annual traffic per section and at borders crossings, traffic composition, delays at borders etc. It should be noted that information contained in the Database is based on information and data submitted by the participating countries of the Steering Committee of the Corridor. Relevant studies provide useful traffic flow forecasts for the current study: The Transport Infrastructure Regional Study (TIRS by Luis Berger S.A.), the Regional Balkans Infrastructure Study (REBIS by COWI) and the traffic flows forecasting along Corridor X exercise of the Technical Secretariat of the Steering Committee for Pan-European Corridor X. Additionally, the feasibility study delivered recently for the Tabanovce – Kumanovo motorway (by Balkan Konsalting DOOEL) was taken into consideration, in terms of exploiting data and expertise of a local firm. 3.2 Evaluation of available information and data updates requirements and design of data collection process The feasibility study and detail design, contained valuable and useful information and were fully exploited in the current study. After detailed examination of the available references and the definition of the followed methodology of the study, the specification of the supplementary data requirements have been made possible. After the first examination, a first contact with the responsible authority in the Former Yugoslav Republic of Macedonia (Secretariat for European Affairs – National EGNATIA ODOS S.A. APRIL 2007 17 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Coordinator for Hi.P.E.R.B.) was made, in order to obtain additional data and information, as there have been various issues for clarification. Then a technical meeting was scheduled in order to obtain the necessary information, with interviews and the use of an appropriately formulated questionnaire. The thematic sessions discussed during the meetings are attached in Annex A of the present study. 3.3 Data collection surveys and cooperation with stakeholders in the F.Y.R. of Macedonia As previously mentioned the data collection process included the formulation of a questionnaire for structured interviews for use during the organised technical meeting in Skopje on March 1st 2007 with the co-responsible authorities and the specialists of the Funds for National and Regional Roads. Various issues were discussed and clarified during the meeting. Other issues were confronted a posteriori via e-mail, while others, and mainly those concerning the results of the environmental impact studies and the accidents statistics at section level, remained pending up to the day of completion of this study. 3.4 3.4.1 Tools Tools for the traffic forecasts Traffic forecasts for future years have been derived exploiting the traffic model developed by the Technical Secretariat of Corridor X in 2003. These forecasts (until the year 2015 – long term horizon of the traffic model as developed) have been assessed using the most recent data available. For the rest of the period of analysis forecasts have been derived using appropriate growth factors. 3.4.2 Tools for the evaluation of various alternatives of the project The exercise of the evaluation of the level of service of the examined alternatives of development of the road section according to projected traffic was performed on the basis of the Highway Capacity Manual 2000 for two-lane highways (for the existing infrastructure) and multilane highways (for the motorway construction alternatives). 3.4.3 Tools for the economic analysis (NPV, IRR, B/C ratio) Various alternatives of infrastructure development are examined, comprising the “Do minimum alternative” of lower cost interventions for the upgrade of the existing infrastructure and the toll-motorway alternatives of two alignments (the one as proposed by the detail design and the other recently examined at preliminary level) with various cross sections’ widths and hence different design speeds. The economic analysis of each alternative under consideration (calculation of Net Present Value, Internal Rate of Return and Benefit over Cost Ratio) was performed EGNATIA ODOS S.A. APRIL 2007 18 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X based on the estimates of cost (construction cost, maintenance cost, operational cost etc.) and benefits (time savings, reduction of vehicle operational cost, accidents reduction) at each year of operation of the project. A comparative analysis of the economic evaluations of the alternatives followed and the alternatives were ranked, so that the most appropriate alternative is defined. Various sensitivity tests were performed for each alignment/ alternative examined. EGNATIA ODOS S.A. APRIL 2007 19 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 4. 4.1 4.1.1 PRESENTATION OF THE PROJECT Existing situation Pan-European Road Corridor X Pan-European Corridor X is a traditional route linking South-Eastern Europe with Central Europe, which had served transportation in the area for many decades. Before the 1990’s this Corridor was fully operational and more or less developed in terms of road and rail infrastructure. The unfortunate events in former Yugoslavia have caused a significant drop in traffic along the Corridor and have also influenced the status of infrastructures and facilities, adding at the same time new international borders along the Corridor, between the four former Yugoslavian countries. The multimodal Pan-European Transport Corridor X (Main Axis and four branches), as defined by the Helsinki declaration, connects: Salzburg, Ljubljana, Zagreb, Belgrade, Nis, Skopje, Veles and Thessaloniki; Graz with Maribor and Zagreb (Branch A); Budapest with Novi Sad and Belgrade (Branch B); Nis with Sofia [to Istanbul via Corridor IV (Branch C)]; and Veles with Bitola and Florina [and via Egnatia with Igoumenitsa port (Branch D)]. The alignment of the road infrastructure of Corridor X is represented in Map 4.1. More specifically, Corridor X refers not only to the road and rail infrastructure, but also to interconnection points for inland waterways, air, maritime, intermodal and in particular combined transport infrastructure, including ancillary installations such as signalling, the installations necessary for traffic management, access links, border crossing stations, service stations, freight and passenger terminals and warehouses along the route of the Corridor. Concerning the road Corridor X, its total length is 2,299.6km and at present consists of 61.5% multilane motorways and 38.5% highways and other main roads. The main part of Road Corridor X linking Salzburg and Thessaloniki through Ljubljana, Zagreb, Belgrade and Skopje is 1,451.4km long and consists of multilane motorways at a percentage of 80% of its length. The maximum permitted speed along the Main Axis is 120km/h at most of its sections, and generally the infrastructure is in good condition. The percentage of the multilane motorways is foreseen to reach 90% of the Axis by 2008, with construction of all the Slovenian and Croatian sections to full motorway profile. The remaining sections of the main part of Corridor X in Serbia and F.Y.R.O.M. that need reconstruction are the Leskovac (Grabovnica) – F.Y.R.O.M. border (102.13km) and Tabanovce – Kumanovo (7.4km) and Demir Kapija – Smokvica section (33km) in F.Y.R.O.M. EGNATIA ODOS S.A. APRIL 2007 20 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Recently, the negotiations of the Former Yugoslav Republic of Macedonia with the World Bank ended up with an agreement for the financing of the Tabanovce – Kumanovo motorway. Furthermore, the construction of the Leskovac – Presevo motorway is foreseen by 2012, with Greek financial assistance (21% of total construction cost) through the Hi.P.E.R.B., as well as the construction of the Belgrade bypass. Hence, according to the above-mentioned scheduled projects, after five years the only remaining non-motorway section would be the section under study. Branch A, from Graz to Zagreb via Maribor, is 163.4km long and consists of multilane motorways at 55% of its length. This Branch is foreseen to be fully constructed in motorway profile by 2012. SALZBURG BUDAPEST # Y Ξ AUSTRIA # Y [ % GRAZ # HUNGARY # # # SZEGED MARIBOR # # Y # # LJUBLJANA ROMANIA # Y # SUBOTICA # [ % # # SLOVENIA ZAGREB # [ % # CROATIA Ξ # Ξ # Y NOVI SAD # # Ξ # # # # BELGRADE [ % # # Ξ # BOSNIA-HERZEGOVINA # [ % Ξ BULGARIA NIS # SARAJEVO ## Y # ## # # SERBIA-MONTENEGRO SOFIA # # # [ % # # # # ITALY Ξ SKOPJE %[ # # # VELES # F.Y.R.O.M. # # # # # [ % TIRANE ALBANIA Source: Corridor X Technical Secretariat # # GREECE # Y FLORINA # THESSALONIKI # Y Ξ Map 4.1: Road Corridor X alignment On Branch B, the 41% of the 352.9km are parts of the M5 motorway in Hungary. The construction of motorways on the rest of the Branch is foreseen by 2011, through a recently signed concession for the Horgos – Pozega motorway. Branch C (191.8km) is consisted by highways at 71% and two-lane main roads at the rest of its length. EGNATIA ODOS S.A. APRIL 2007 21 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Finally, Branch D is 140.1km long and consists of highways and other two-lane main roads. Rehabilitation plans exists for the Greek part of the Branch by 2007 and also for the section Veles – Prilep in mid-term time horizon. Concerning all the Corridor, Main Axis and Branches, since 2001 246.96km of motorways have been constructed, out of sections of total length of 382.59km. The length of constructed sections corresponds to 64.5% and by the end of the year 2007 will reach 67.7% of planned transformation of highways to motorways (Table 4.1). Table 4.1: Progress of motorways’ construction along Corridor X since 2001 Part of Corridor X Country Section Slovenia Slovenia Bic – Obrezje Vrba – Naklo Velika Kopanica – Zupanja – Lipovac Zagreb – Bregana Belgrade bypass Gradsko – Demir Kapija – Udovo – Gevgelija Maribor – Gruskovje Kiskunfelegyhaza – Szeged – Roszke 75.5 20.9 53.56 54.4 4.3 53.56 Length of sections planned to be constructed in 2007 (km) 7.9 3.7 - 13.0 45.33 75.5 13.0 16.8 42.5 - 38.8 2,4 0.6 60.0 60.0 - Total 382.59 Croatia Main Axis Croatia Serbia F.Y.R. Macedonia Branch A Slovenia Branch B Hungary Grand Total Total length (km) Constructed length (km) A= 12.2 64.5% A + B = 259.16km (67.7%) 246.96 B= 3.2% Source: Corridor X Technical Secretariat 4.1.2 General description of projects on road Corridor X in the Former Yugoslav Republic of Macedonia The road section under study is a part of the main Axis of the Pan-European Corridor X, linking Skopje with Belgrade in the north and Thessaloniki in the south. Also, Veles in the northwest is the nodal connection point of the Main Axis and Branch D to Bitola and Florina (and the vertical axis of Egnatia Odos to Kozani). At present the Main Axis of Corridor X in the Former Yugoslav Republic of Macedonia is constructed in motorway standards from Kumanovo to Demir Kapija and from Smokvica to Gevgelija and the Greek borders (Bogorodica cross border station). The total length of Main Corridor X in F.Y.R. of Macedonia is 174.34km and the percentage of motorways reaches 75.4%, after the recent transformation of Negotino – Demir Kapija road to a motorway. It should be noted that the above figures are affected by the fact that at the motorway section between Katlanovo and Veles the two carriageways follow a totally different EGNATIA ODOS S.A. APRIL 2007 22 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X alignment and hence the motorway length is also different by 5.07km. The following table and map give a very clear view of the current situation of the Main Corridor X, as well as the profile of each motorway section (where emergency lane has been constructed). Table 4.2: State of play of Corridor X Main Axis in F.Y.R. of Macedonia Section Section close to Serbian border Tabanovce – Kumanovo Kumanovo – Miladinovci Miladinovci – Petrovec Petrovec – Katlanovo Katlanovo – Veles (right carriageway) Katlanovo – Veles (left carriageway) Veles – Gradsko Gradsko – Negotino Negotino – Demir Kapija Demir Kapija – Udovo Udovo – Smokvica Smokvica – Gevgelija Gevgelija – Greek border Length (km) 1.084 7.052 21.782 5.846 6.979 27.157 22.087 25.139 16.044 16.525 22.270 13.564 11.228 4.582 Length of motorway (km) 1.084 21.782 5.846 6.979 27.157 22.087 25.139 16.044 16.525 11.228 4.582 Source: Fund for National and Regional Roads Source: Fund for National and Regional Roads Map 4.2: Representation of Corridor X Main Axis in the F.Y.R. of Macedonia EGNATIA ODOS S.A. APRIL 2007 23 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The existing road on the section Demir Kapija – Udovo – Smokvica has been constructed during the period 1960-1964 and has been periodically renewed at some sections. Rehabilitation, including total repavement of the entire section, was performed in 1990-1991 through financing of $9million by the World Bank within the rehabilitation of Gradsko – Gevgelija project. The following paragraphs provide details of the current status of the road between Demir Kapija and Smokvica [2]. i. Demir Kapija – Udovo (22.27km) The road section between Demir Kapija and Udovo was built in 1964. The last rehabilitation took place in 1990, which included total repavement. The road condition is good, with one, 3.5m wide, lane per direction and 1m wide stable shoulders. The condition of the pavement is reported as medium, while the level of vertical and horizontal signing is not satisfactory, since it is described as damaged and insufficient. According to the approved detail design of Scetauroute (2000) it is envisaged that this section will be transformed to a motorway, with two lanes per direction, 3.5m wide each, and design speeds of minimum 80km/h and maximum 100km/h. Also, a second alignment bypassing Udovo has been examined at preliminary level by E.O.A.E. and F.N.R.R. for the construction of a new motorway on the west bank of River Vardar, with design speed of 120km/h. Photo 4.1: Road section Demir Kapija – Udovo Photo 4.2: Road section Demir Kapija – Udovo EGNATIA ODOS S.A. APRIL 2007 24 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Photo 4.3: Road section Demir Kapija – Udovo Source: Fund for National and Regional Roads Photos 4.4 and 4.5: Tunnels on Demir Kapija – Udovo road ii. Udovo – Smokvica (13.564km) The road section between Udovo and Smokvica was built in 1960. The last rehabilitation took place in 1991, which included total repavement. The road condition is good, with one, 3.5m wide, lane per direction and 1m wide stable shoulders. The condition of the pavement is reported as medium, while the level of vertical and horizontal signing is not satisfactory, since it is described as damaged and insufficient. According to the approved detail design of Scetauroute (2000) it is envisaged that this section will be transformed to a motorway according, with design speed of 120km/h. The same design speed is also foreseen by the second alignment examined by E.O.A.E. and F.N.R.R. that bypasses Udovo by following the west bank of River Vardar. EGNATIA ODOS S.A. APRIL 2007 25 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Photo 4.6: Road section Udovo – Smokvica Photo 4.7: Road section Udovo – Smokvica The entire section under study is 35.834km long. Data described in the following paragraphs were derived from the available documents (the feasibility study by Scetauroute), the Road Database of the Technical Secretariat of Corridor X and information submitted by the Funds for National and Regional Roads of the Former Yugoslav Republic of Macedonia. 4.1.3 Existing road geometrical characteristics 4.1.3.1 Length of section The total length of the section is 35.834km. The alignment is presented in Map 4.3 with the respective toponyms. Sub-section Demir Kapija – Udovo Udovo – Smokvica Total Length (km) 22.27 13.564 35.834 4.1.3.2 Cross section The cross section as described in the Database of Road Corridor X, is 9.70m wide and described and represented as follows: Two traffic lanes, 3.50m wide each Two shoulders, 1.00m wide each Two verges, 0.35m wide each EGNATIA ODOS S.A. APRIL 2007 26 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Figure 4.1: Typical cross section of existing M-1 road Axios Map 4.3: Alignment of existing E-75 road 4.1.3.3 Horizontal alignment Bendiness along the entire section under study is considered high, mainly along the “gorge” section between Demir Kapija and Udovo. EGNATIA ODOS S.A. APRIL 2007 27 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Source: Google Earth (2007 TerraMetrics) Map 4.4: Landscape of surrounding area (direction from D. Kapija to Udovo) Cross falls Minimum super-elevation is 2.5% and maximum super-elevation in curve is 7%. Curvature Minimum horizontal curve radius is 350m. 4.1.3.4 Design speed The design speed of the existing alignment is 80km/h from Demir Kapija to Udovo and varies between 80 and 100km/h between Udovo and Smokvica. 4.1.3.5 Vertical alignment Altitude The level of the M-1 road from Gevgelija to Udovo before the construction of the motorway sub-section Gevgelija – Smokvica varied between 52 and 80m above the sea level, while the land type is flat and mountainous while moving to the northern parts. From Udovo to Demir Kapija, through a mountainous terrain, level varies between 80 and 122m above the sea level. EGNATIA ODOS S.A. APRIL 2007 28 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Gradients Gradients along the existing road do not exceed 2.2%. 4.1.3.6 Pavement Pavement condition along the entire section from Smokvica to Demir Kapija is considered medium. The last maintenance was performed in 1990-91 and included total repavement of the road. 4.1.3.7 Structures Bridges The following table lists the existing bridges along the section Gevgelija – Demir Kapija. F.N.R.R. Bridge number 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 Total Name Vardar River Iberliska River Gorge Kosaracha River Lutkova River Vodisir gorge Gradeshka River Mushtenica gorge Gorge Gorge Arazliska River Loop Udovo Anska River Marvinci River Vardar River at Miletkovo village Railway Skopje - Gevgelija Road P-103 Local road 19 Number of spans 3 1 1 2 5 9 10 7 5 3 12 1 3 3 1 5 3 3 1 Length Description 163.32 7.60 8.40 16.60 101.40 187.60 209.20 153.50 101.20 36.00 252.40 15.78 33.98 24.40 8.38 220.10 31.40 33.05 29.60 1,633.91 Bridge Bridge Bridge Bridge Bridge Bridge Bridge Bridge Bridge Bridge Bridge Underpass Bridge Overpass Underpass Bridge Underpass Overpass Overpass There are nineteen existing bridges and have total length of 1633.91m. Eleven of them (F.N.R.R. numbers 117-127) are on the Demir Kapija – Udovo section, which correspond to a length of 1,237m. EGNATIA ODOS S.A. APRIL 2007 29 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 4.1.3.8 Intersections No at-grade intersections exist along the Demir Kapija – Udovo road. There is only one multilevel intersection along this section, where the road crosses with railway Corridor X. Concerning the Udovo – Gevgelija section, before the motorway construction from Smokvica to Gevgelija, there were three multilevel and one at-level intersections. The two multilevel crossings were at the crossings of the M-1 road with the Skopje – Thessaloniki railway line. 4.1.3.9 Traffic signs As previously mentioned, the level of horizontal and vertical signing was reported to the Technical Secretariat as not satisfactory (in 2001), due to the fact that it was damaged and incomplete. 4.1.3.10 Lighting Lighting along the Demir Kapija – Udovo section is considered satisfactory. Lighting is not continuous but isolated at tunnels. Lighting along Udovo – Smokvica section is not satisfactory. 4.1.3.11 Road facilities On the old road from Gevgelija to Udovo there were six parking areas and two service stations. No emergency telephones are installed. On the sub-section from Udovo to Demir Kapija there are two service stations, no emergency telephones, while seven parking areas exist. 4.1.3.12 Traffic counters and toll stations Three traffic counters are installed along the road section between Demir Kapija and the Greek border: Automatic counter 11/C is installed at Demir Kapija, Manual counter 8-1/P at Udovo and Automatic counter 19/C at Gevgelija. The closest toll booth is at Stobi (close to Gradsko at Demir Kapija northwards). 4.1.4 Existing road operational characteristics 4.1.4.1 Traffic flows Available traffic data was derived from the Corridor X Database (only for the years 1998, 1999 and 2003), from the traffic data officially submitted by the Fund for National and Regional Roads of F.Y.R. Macedonia and also from the Scetauroute study (for the period 1989-2002 and the years 2005 and 2006). EGNATIA ODOS S.A. APRIL 2007 30 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The following table presents traffic data for various years since 1990 and until the year 2006. The traffic volumes peaked in 1990 (weighted average AADT was over 6,000 veh/day). However, the crisis in the former Yugoslavia saw a drastic reduction with daily traffic falling to just 1,835 veh/day in 1994. As stability in the region improves traffic volumes have started rising. In 2006 weighted traffic volumes was recorded at 3,571 veh/day. It is worth noting that the 2006 traffic volume is only 59% of the traffic volume that was recorded in 1990. Year 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2005 2006 Annual Average Daily Traffic (veh/day) D. Kapija–Udovo Udovo–Gevgelija Weighted traffic 4,644 5,036 4,851 6,300 5,856 6,066 5,357 5,128 5,236 2,858 2,400 2,617 2,779 2,846 2,814 1,496 2,139 1,835 1,647 2,280 1,981 2,142 2,825 2,502 2,315 3,021 2,687 1,922 3,387 2,694 1,869 4,121 3,056 2,754 3,334 3,060 2,300 3,265 2,808 2,119 3,412 2,800 2,671 2,916 2,800 3,596 3,548* 3,571 Source: Corridor X Technical Secretariat – Fund for National and Regional Roads * Estimation Traffic flows along the sections were reduced by 56% during the period 1990 – 1998 (70% on D. Kapija – Udovo and 42% on Udovo – Gevgelija). Increase of traffic was observed after the year 2000 but remained at low levels with fluctuations, at about 50% less than the traffic in the year 1990. The Graph 4.1 presents the annual traffic along Corridor X Main Axis in the F.Y.R. of Macedonia in various years since 1989. It shows that traffic flows gradually increase but irregularly, so that the extraction of a safe conclusion and a mean annual growth factor is impossible. EGNATIA ODOS S.A. APRIL 2007 31 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Annual Average Daily Traffic along Corridor X in F.Y.R.O.M. in the period 1989 – 2006 16000 14000 1989 AADT (veh/day) 12000 1990 10000 1998 8000 1999 6000 2002 2001 2005 4000 2006 2000 ic a og or od lij a lij a -B -G ev ge vo G ev ge U do ap i ja -U do vo ap ij a K K N eg ot in o D em ir o ds k G ra -D em ir -N eg G ra d s- el e V ot in o o sk es -V el ec Pe tr ov no v ci - Pe tr ov ec i di no vc M ila di -M ila ov o um an K Ta ba no v ce -K um an ov o 0 Section Graph 4.1: Annual Average Daily Traffic along Corridor X in F.Y.R.O.M. in the period 1989 – 2006 In any case, the trends of traffic along the sections of interest are anodic, as shown in Graph 4.2. Only in 2006 the traffic recorded an increase by 27.5% compared to traffic in 2005. Annual Average Daily Traffic changes per sub-section in the period 1989 – 2006 7000 AADT (veh/day) 6000 5000 4000 3000 2000 1000 0 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2005 2006 Year Demir Kapija - Udovo Udovo - Gevgelija Weighted traffic Graph 4.2: Annual Average Daily Traffic changes per sub-section in the period 1989 – 2006 EGNATIA ODOS S.A. APRIL 2007 32 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Annual Average Daily Traffic considered for the scope of the study in the base year 2006 per section is: 3,596 veh/day on the section Demir Kapija – Udovo 3,548 veh/day on the section Udovo – Smokvica Weighted Annual Average Daily Traffic along the entire section under study in 2006 is 3,571 veh/day. 4.1.4.2 Traffic flows characteristics Traffic composition Annual average daily traffic can be analysed in vehicle categories and reduced to passenger car units (PCUs). From the analysis of the year 2001, for which traffic separation is made to light and heavy vehicles, it is concluded that heavy traffic was around 30%. In the Scetauroute feasibility study, which included traffic counts that were used in traffic projections, the following shares of vehicles were registered for year 1998: Road section Demir Kapija – Udovo (Prdejci) Smokvica – Gevgelija Passenger cars Buses Vans/ pickups Light trucks Medium trucks Heavy trucks Articulated trucks 58% 4% 7% 4% 4% 6% 17% 67% 4% 7% 4% 5% 7% 5% Traffic composition has changed since 1998. If one studies the available F.N.R.R. traffic statistics for 2005 and 2006, presented in the following tables, the traffic composition along the Demir Kapija – Udovo road is more or less the same as the traffic composition along the Udovo – Gevgelija road. Section Demir Kapija – Udovo Udovo – Gevgelija EGNATIA ODOS S.A. APRIL 2007 A Motorcycles 27 1.01% 18 0.62% B Cars and light loaded vehicles 2,003 74.99% 2,332 79.97% C Heavy loaded vehicles 588 22.01% 467 16.02% D Buses 53 1.98% 99 3.40% Total 2,671 100.00% 2,916 100.00% 33 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X More specifically, traffic composition along Demir Kapija – Udovo section in the year 2006 was recorded as follows: A Section Demir Kapija – Udovo Motorcycles 34 0.95% B Cars and light loaded vehicles 2,877 80.01% C Heavy loaded vehicles 611 16.99% D Buses 74 2.06% Total 3,596 100.00% Therefore, along Demir Kapija – Udovo section the share of light vehicles is 81%, the percentage of buses is 2% and of heavy loaded vehicles 17%. For the section Udovo – Smokvica the shares are assumed to be the same with the northern road section, confirmed by the available statistics for 2005, considering also that higher volumes of local trips emerge after the village Prdejci, 3km south of Smokvica. Summarizing, and incorporating also the percentages registered in the year 1998, the following shares per type of vehicle are extracted and used in the present study: Motorcycles: 1% Passenger cars: 69% Vans and pickups: 7% Buses: 2% Light trucks: 4% Medium trucks: 4% Heavy trucks: 6% Articulated trucks: 7% Traffic in private car units in the base year (2006) for traffic projection is estimated at 4,928 PCUs/day. International traffic International traffic has been drastically reduced since 1990. Annual average daily traffic of vehicles with foreign registration plates in 1990 at Nis toll booth on Corridor X in Serbia was 4,065 veh/day, while in 2001 it was 916 veh/day (including vehicles from ex Yugoslavian countries that are now considered as international traffic). These figures highlight the significant drop of international traffic after the crisis in former Yugoslavia. They also indicate the growth potential of international trips as the political stability of the region steadily improves. In the previous feasibility study by Scetauroute, it is estimated that international traffic in 1998 represented 20% of the AADT along the section Demir Kapija – Gevgelija. In order to approach the share of international traffic it was considered useful to exploit available statistics at the cross border of Bogorodica that were officially submitted to the Technical Secretariat of Corridor X by the authorities of F.Y.R. of Macedonia in 2003. EGNATIA ODOS S.A. APRIL 2007 34 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Year 1997 1998 1999 2000 2001 2002 Cars Foreign 135,010 116,122 72,729 132,682 82,047 140,849 73.01% Domestic 129,676 46,786 72,527 157,017 103,520 101,091 53.22% Buses Foreign 12,270 10,419 4,872 18,954 9,438 9,160 4.75% Domestic 1,620 309 973 22,431 976 952 0.50% Trucks Subtotals Foreign Domestic 40,452 81,521 35,666 83,237 41,815 87,660 37,909 44,862 39,528 78,361 42,919 87,914 22.25% 46.28% Annual average 2002 Total Foreign 187,732 162,207 119,416 189,545 131,013 192,928 Domestic 212,817 130,332 161,160 224,310 182,857 189,957 400,549 292,539 280,576 413,855 313,870 382,885 529 520 1,049 In 2002, 382,885 vehicles crossed the borders of F.Y.R. of Macedonia with Greece, which approximates 1,049 vehicles per day in both directions. About half of them (529 veh/day) are vehicles with foreign registration plates and the composition of this traffic flows is 73% passenger cars, 4.75% buses and 22.25%. These shares are similar to the composition of AADT on the section under study mentioned in the previous paragraphs. The 529 veh/day represent the 18.9% of the AADT of the year 2002, which approximates the 20% estimated by Scetauroute for the year 1998. Therefore, for the scope of this study, it is assumed that 20% of the traffic is international, which for 2006 is estimated at 714 veh/day (1,100 PCUs/day) in both directions. Annual entrances per vehicle category at Bogorodica road cross border station 90,000 80,000 70,000 1997 60,000 1998 50,000 40,000 1999 30,000 2001 20,000 2002 2000 10,000 0 Foreign Private Cars Domestic Private Cars Foreign Buses Domestic Buses Foreign Trucks Domestic Trucks Graph 4.3: Annual entrances per vehicle category at Bogorodica road cross border station in the period 1997 – 2002 EGNATIA ODOS S.A. APRIL 2007 35 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Annual exits per vehicle category at Bogorodica road cross border station 90,000 80,000 70,000 60,000 1997 50,000 40,000 1999 30,000 20,000 2001 1998 2000 2002 10,000 0 Foreign Private Cars Domestic Private Cars Foreign Buses Domestic Buses Foreign Trucks Domestic Trucks Graph 4.4: Annual exits per vehicle category at Bogorodica road cross border station in the period 1997 – 2002 Traffic irregularities Seasonality From data collected in 2001 at the (old) counter points 12/A at Demir Kapija and 13/A at Gevgelija, as expected, the average monthly traffic flows are higher during the months of the vernal period. Peak month at Demir Kapija – Udovo was July (2,680 veh/ day) and at Udovo – Gevgelija (3,326 veh/day). Month January February March April May June July August September October November December D. Kapija - Udovo Average monthly daily traffic (veh/ day) 1,920 2,095 2,011 2,093 2,173 2,378 2,680 2,633 2,539 2,488 2,296 2,282 EGNATIA ODOS S.A. APRIL 2007 Comparison to Annual Average Daily Traffic 83.48% 91.09% 87.43% 91.00% 94.48% 103.39% 116.52% 114.48% 110.39% 108.17% 99.83% 99.22% Udovo - Gevgelija Average monthly daily traffic (veh/ day) 2,562 2,948 2,855 3,023 3,795 3,175 3,336 3,468 3,684 3,509 3,396 3,444 Comparison to Annual Average Daily Traffic 78.44% 90.26% 87.41% 92.55% 116.19% 97.21% 102.14% 106.18% 112.79% 107.43% 103.97% 105.44% 36 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Summer average daily traffic (SADT) in 2001 was 2,564 veh/day (11% higher than AADT) on Demir Kapija – Udovo and 3,326 veh/day on Udovo – Gevgelija (2% higher than AADT), while winter average daily traffic (WADT) was 2,077 veh/day and 2,952 veh/day, respectively, which correspond to 90% of the AADT. It should be mentioned at this point that at Udovo – Gevgelija section the SADT in 1989 was 8,153 veh/day, 62% higher than AADT, while WADT was 3,573 veh/day (71% of AADT). Traffic seasonality in 2001 is also presented in the following graph. Monthly Average Daily Traffic in 2001 4000 3500 Veh/day 3000 2500 D. Kapija - Udovo MADT D. Kapija - Udovo AADT 2000 Udovo - Gevgelija MADT 1500 Udovo - Gevgelija AADT 1000 500 Ja nu Fe ary br ua r M y ar ch A pr il M ay Ju ne Ju A ly Se ugu pt st em b O er ct N ob ov e r em D ec ber em be r 0 Month Graph 4.5: Monthly Average Daily Traffic in 2001 Peak days and hours Information concerning the peak days and hours are available for the period 1999 – 2002 (Source: F.N.R.R.). On the section from Demir Kapija to Udovo the maximum daily traffic load was recorded on the working day of 31/7/2000 with 6,023 vehicles (218% of AADT of year 2000). In the following years traffic on peak days was much closer to the annual average daily traffic. EGNATIA ODOS S.A. APRIL 2007 37 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Year 1999 2000 2001 2002 Section: Demir Kapija – Udovo Maximum working day Maximum non-working day Average day Maximum working day Maximum non-working day Average day Maximum working day Maximum non-working day Average day Maximum working day Maximum non-working day Average day Date 6/7/1999 24/7/1999 22/10/1999 31/7/2000 29/7/2000 23/5/2000 1/8/2001 28/7/2001 26/2/2001 30/8/2002 16/11/2002 6/12/2002 Day traffic 3,019 2,917 1,867 6,023 5,319 2,670 3,638 3,168 2,302 3,408 3,491 2,127 Morning Peak hour 8h and 12h 12h 11h 8h 9h 12h 9h 6h 12h Afternoon peak hour 15h and 18h 18h and 20h 16h and 21h 18-20h 16h and 22h 20h 17h and 20h 20h 13h and 19h 12-14h - On the road from Udovo to Gevgelija the maximum daily traffic load was recorded on the working day of 13/4/1999 with 12,207 vehicles (three times higher than AADT of year 1999). In the following years traffic on peak days was close to half of this value. Year 1999 2000 2001 2002 Section: Udovo – Gevgelija Date Day traffic Morning Peak hour Maximum working day 13/4/1999 12,207 9h Maximum non-working day Average day Maximum working day 11/4/1999 11/9/1999 2/2/2000 9,588 4,093 5,096 11h 9h 10-11h Maximum non-working day 23/2/2000 3,912 - Average day Maximum working day Maximum non-working day Average day 15/5/2000 20/9/2001 19/5/2001 17/9/2001 3,335 6,801 6,103 3,263 Maximum working day 27/2/2002 6,779 Maximum non-working day Average day 29/9/2002 12/2/2002 7,451 3,412 8h 12h 4-6h and 1115h 9h 8h EGNATIA ODOS S.A. APRIL 2007 Afternoon peak hour 13h, 16h and 20h 19h 16h and 21h 15-16h and 2122h 16h and 22h 14h and 19h 14h and 19h 13h 19h 13h 17h and 22h 38 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 4.1.4.3 Accidents Data for accidents is not available on road section basis. From the Database of the Technical Secretariat of Corridor X the only information available is on country basis, for the years 1995 – 1998. Year 1995 1996 1997 1998 Accidents 2,436 2,505 2,293 2,184 Deaths 179 154 170 187 Injuries 3,421 3,397 3,199 3,019 Source: Corridor X Technical Secretariat The persons killed in road accidents in F.Y.R. of Macedonia were 216 in 1999 and 162 in 2000 (Eurostat). Eight persons were killed in road accidents per 100,000 inhabitants in 2000, while in 1999 the same index was eleven, in 1997 and 1998 nine, and finally in 1997 eight. From the above statistics, the mean annual number of accidents is 2,355, of injuries 3,259 and deaths in road accidents 178. Road accidents in F.Y.R. of Macedonia 2000 1999 1998 Injuries Deaths Road accidents 1997 1996 1995 0 500 1000 1500 2000 2500 3000 3500 4000 Year Graph 4.6: Road accidents in F.Y.R. of Macedonia in the period 1995 – 2000 Another statistic concerning accidents is the number of accidents per 1,000 vehicles in 1999, reported by the Ministry of Transport and Communications of the F.Y.R. of Macedonia: 6.9 accidents, 0.6 deaths and 9.3 injuries per 1,000 vehicles. EGNATIA ODOS S.A. APRIL 2007 39 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Accidents along the existing road under study were expected from the responsible Ministry of Interior of the F.Y.R. of Macedonia. Up to the date of completion of the current study, the submission of the required data is still pending. 4.2 Alternatives of infrastructure development (road physical and operational characteristics including toll stations) The alternatives of infrastructure development are formulated in such a way that the qualification of the most suitable, in economic and technical terms, solution is made possible. The first alternative (Alternative A) is the lowest cost solution, where the entire section is upgraded in order to increase the road safety and facilitate the traffic of both private cars and commercial vehicles. Rehabilitation according to the authorities is required every 15 years, and thus the upgrade should be performed immediately. Therefore, for the scope of the study upgrade is considered to take place in the period 2008 -2009 and rehabilitation in 2023. The second and the third alternatives (Alternatives B and C) examine the motorway construction with narrower cross-section widths compared to those proposed by the existing detail and preliminary designs of the two alignments under study, in order to examine more economic solutions, while still serving the existing and forecasted traffic with an acceptable level of service. Finally, the motorway construction alternatives as proposed by the existing designs are examined (Alternative D). The alternatives of infrastructure development are summarised in the following table: Alternative Description Year of realisation A (“Do minimum”) Upgrade of the existing road 2008 – 2009 Motorway construction with cross section width of 22.60m (traffic lanes 3.25m wide) along the entire section Motorway construction with cross section width of 24.60m (traffic lanes 3.50m wide) along the entire section Alignment 1 Motorway construction with cross section width of - 27.60m (traffic lanes 3.75m wide) at the “easy” sections - 26.40m (traffic lanes 3.50m wide) at the “gorge” section 2008 – 2013 (Alignment 1) B C D Or 2008 – 2010 (Alignment 2) Alignment 2 Motorway construction with cross section width of 28.20m (traffic lanes 3.75m wide) along the entire section EGNATIA ODOS S.A. APRIL 2007 40 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 4.2.1 Alternative A: Do minimum The “Do minimum” alternative is the lower cost alternative of upgrading of the existing M-1 road that could include various minor interventions for the better utilisation of the existing infrastructure and the facilitation of traffic. Minor interventions could be the formulation of climbing lanes and parking lots at given spots along the hilly and difficult parts of the road (along the “gorge” section), in order to give more passing opportunities to passenger cars, as the percentage of heavier vehicles is considered high (19%). Climbing lanes increase the level of service of the road, and also contributes to accidents reduction, travel time and vehicle costs savings. Also, for the increase of road safety, the provision of emergency escape ramps and arrester beds could be examined at long downhill sections or other cases of increased possibility of a vehicle driver losing control. 4.2.2 Motorway construction (Alternatives B, C, D) Alternatives B, C and D are variants of motorway construction which differ in the formulated typical cross-section and in the design speed of a future motorway, in order to examine the best techno-economic alternative. The following elements of the analysis are considered to remain constant for all motorway cross-section widths within each alignment (Alternatives B, C, D): Traffic projections (vary only in different alignments). The median type, which is formulated with metal barriers. The case of establishment of New Jersey median is not examined. The omission of the emergency lanes at bridges longer than 50m and tunnels. The considered percentage of accidents reduction after the motorway construction. The construction costs are estimated on the basis of the estimation performed by the F.N.R.R. for the wider cross sections (27.6m and 26.4m in the case of Alignment 1 and 28.2m in the case of Alignment 2). 4.2.2.1 General description – Design speeds and typical cross-sections Alternative B: Motorway construction with a cross-section of 22.60m for design speed of 90-110km/h Alternative B is the alternative of motorway construction with two lanes per direction, separated by a median with guardrails, for design speed of 90-110km/h: Traffic lanes: Central reserve: Emergency lanes: Marginal strips towards central reserve: Marginal strips towards emergency lanes: Shoulders: EGNATIA ODOS S.A. APRIL 2007 4 (2 per direction), each 3.25m wide 2.00m wide 2 (1 per direction), each 2.00m wide 2 (1 per direction), each 0.30m wide 2 (1 per direction), each 0.50m wide 2 (1 per direction), each 1.00m wide 41 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 9.30 7.30 0.50 2.00 0.50 1.00 1.00 Figure 4.2: Alternative B typical motorway cross section (Vd= 90-110km/h) More specifically, for Alignment 1 the design speed will be between 80 and 100km/h for the subsection Demir Kapija – Udovo, while for the remaining section between Udovo and Smokvica will be 110km/h. For Alignment 2 the design speed will be 110km/h along the entire section. Reduction of the cross section is also foreseen at tunnels and bridges longer than 50m. The reduction of the cross section at tunnels and bridges is achieved through the removal of the emergency lane. The width of tunnel is 8.7m with two traffic lanes of 3.25m each, two verges of 0.35m each and two service footpaths of 0.75m each. Alternative C: Motorway construction with a cross-section of 24.60m for design speed of 90-110km/h Alternative C foresees the motorway construction with two lanes per direction, separated by a median with guardrails, for design speed of 90-110km/h, with cross section of 24.60m, as follows: Traffic lanes: Central reserve: Emergency lanes: Marginal strips towards central reserve: Marginal strips towards emergency lanes: Shoulders: 4 (2 per direction), each 3.50m wide 3.00m wide 2 (1 per direction), each 2.00m wide 2 (1 per direction), each 0.50m wide 2 (1 per direction), each 0.30m wide 2 (1 per direction), each 1.00m wide 9.80 7.80 0.30 1.00 2.00 0.50 3.00 0.50 3.50 3.50 0.30 3.50 3.50 1.00 2.00 Figure 4.3: Alternative C typical motorway cross section in the case of Alignment 2 and of section from Udovo to Smokvica of Alignment 1 (Vd= 90-110km/h) EGNATIA ODOS S.A. APRIL 2007 42 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X In the case of Alignment 1 the design speed will be between 80 and 100km/h along the motorway between Demir Kapija and Udovo, while for the rest of the motorway between Udovo and Smokvica will be 110km/h. For Alignment 2 the design speed will be 110km/h along the entire section. Additionally, as in the case of Alternative B, the reduction of the cross section is also foreseen at tunnels and bridges longer than 50m. This reduction is achieved through the removal of the emergency lane. The width of tunnel is 9.2m with two traffic lanes of 3.50m each, two verges of 0.35m each and two service footpaths of 0.75m each. Alternative D Alignment 1 Motorway construction for design speed of 120km/h Motorway construction with a cross-section of 27.60m for design speed of 120km/h and 26.40m for design speed of 80-100km/h This alternative examines the case of the cross sections as proposed by the detailed design. The following table and Figures 4.4 and 4.5 illustrate the cross-section. Traffic lanes: 4 (2 per direction), each 3.75m/ 3.50m wide Central reserve: 4.00m wide Emergency lanes: 2 (1 per direction), each 2.50m wide Marginal strips towards central reserve: 2 (1 per direction), each 0.50m/ 0.35m wide Marginal strips towards emergency lanes: 2 (1 per direction), each 0.35m/ 0.30m wide Shoulders: 2 (1 per direction), each 1.00m wide 10.80 8.30 0.30 1.00 2.50 0.50 4.00 0.50 3.75 3.75 0.30 3.75 3.75 1.00 2.50 Figure 4.4: Alignment 1 – Alternative D typical cross section of the motorway section from Udovo to Smokvica (Vd= 120km/h) EGNATIA ODOS S.A. APRIL 2007 43 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 10.20 7.70 0.35 1.00 2.50 0.35 4.00 0.35 3.50 3.50 0.35 3.50 3.50 1.00 2.50 Figure 4.5: Alignment 1 – Alternative D typical cross section of the motorway section from Demir Kapija to Udovo (Vd= 80-100km/h) It should be mentioned that the central reserve is normally 4m but is frequently narrower and reduced to barely 3m when necessary. The width of tunnel is 9.2m with two traffic lanes of 3.50m each, two verges of 0.35m each and two service footpaths of 0.75m each. Alignment 2 Motorway construction with a cross-section of 28.20m for design speed of 120km/h This alternative examines the case of the cross sections as proposed by the preliminary design. The following table and Figure 4.6 illustrate the cross-section of this alternative: Traffic lanes: Central reserve: Emergency lanes: Marginal strips towards central reserve: Marginal strips towards emergency lanes: Shoulders: 4 (2 per direction), each 3.75m wide 3.50m wide 2 (1 per direction), each 2.50m wide 2 (1 per direction), each 0.50m 2 (1 per direction), each 0.30m wide 2 (1 per direction), each 1.50m wide in cut and 2.00m in fill 10.85 8.35 0.35 1.50 2.50 0.50 3.50 0.50 3.75 3.75 0.35 3.75 3.75 1.50 2.50 Figure 4.6: Alignment 2 – Alternative D typical cross section of the motorway section from Udovo to Smokvica (Vd= 120km/h) EGNATIA ODOS S.A. APRIL 2007 44 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The width of tunnel is 9.7m with two traffic lanes of 3.75m each, two verges of 0.35m each and two service footpaths of 0.75m each. 4.2.2.2 Length of section The total length of the motorway section in the case of Alignment 1 is 32.15km, while for Alignment 2 is 28.05km. In the case of Alignment 1, the foreseen motorway can be divided into two subsections: Between Demir Kapija and Udovo (19.9km) and between Udovo and Smokvica (12.15km). 4.2.2.3 Horizontal alignment Alignment 1 adopts the alignment of the existing M-1 road for most sectors. Between Demir Kapija and Udovo the new carriageway would be on the left (east) bank of the Vardar River, following as much as possible the existing M-1 road. The percentage of the second carriageway following the existing M-1 alignment is 80% (F.N.R.R.). Alignment 2 foresees the construction of a completely new motorway section between Demir Kapija and Smokvica, which follows the west bank of the Vadrar River, bypassing Udovo. The total length of this alignment is 28.05km. The position of the aforementioned alignments is roughly presented in the following map: Legend Alignment 1 Alignment 2 Map 4.5: Alternative motorway Alignments 1 and 2 EGNATIA ODOS S.A. APRIL 2007 45 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Curvature In Alignment 1 the minimum horizontal curve radius for design speed of 120km/h is 750m and for design speed of 100km/h is 450m. For design speed of 80km/h the minimum radius is 250m. In Alignment 2 the minimum curve used is 900m, which actually corresponds to a design speed of 130km/h. 4.2.2.4 Vertical alignment Vertical alignment along sub-sections with design speed of 120km/h foresees minimum radii of 16,000m in convex curves and bigger than 11,266m (2/3 of convex radius) in concave curves. Along sub-sections with design speed of 100km/h minimum vertical radii are 7,600m in both convex and concave curves. Finally, for the design speed of 80km/h the minimum radii is 3,025m. Altitude The altitude of the motorway of Alignment 1 from Demir Kapija to Gevgelija lies between 54 and 112m. In the case of Alignment 2 the motorway altitude lies between 75 and 350m. Next to the river and for 8km the altitude is between 110 – 140m, in the mountains and for 15km altitude reaches 350m and then drops to 150m, and finally, in the plain, for the rest of its length (5km), is gradually reduced to 75m, where it is connected to the already constructed motorway between Gevgelija and Smokvica. Gradients Gradients along the entire section under study are reserved lower than 5% for all design speeds. Especially in the case of Alignment 2, the maximum longitudinal slope is 4.0% with an exception of a sector of 1,400m where it reaches 4.6%, due to the mountainous landscape. The maximum slope in the tunnels was kept below 2.5%. EGNATIA ODOS S.A. APRIL 2007 46 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 4.2.2.5 Pavement The pavement structure used on roads in the F.Y.R. of Macedonia is the following: For new carriageways: - wearing course (polymerised asphalt) - bearing course (3-4% bitumen) - blanket course - stabilised road base in cut - stabilised road base in fill 5 12-14 25-35 30-40 60 cm cm cm cm cm For connecting roads at interchanges: - wearing course (polymerised asphalt) - bearing course (3-4% bitumen) - blanket course 4 cm 8-10 cm 25-35 cm For local roads: - bearing course (3-4% bitumen) - blanket course 7 cm 25-35 cm 4.2.2.6 Structures Bridges Alignment 1 The bridges foreseen in Alignment 1 are summarised in the following table, prepared by the F.N.R.R.: Demir Kapija – Udovo Bridge on River Vardar Bridge on Kkosareska River Bridge on Lutkova River Bridge on Vodosir River Bridge on Gradeska River Bridge on Mustenica River Bridge on Arazliska River Subtotal EGNATIA ODOS S.A. APRIL 2007 Length (m) 124 15 101 169 202 136 237 983 Udovo – Smokvica Underpass 1132+757 Underpass 1132+337 Overpass 1133+484 Overpass 1134+420 Overpass 1138+236 Bridge on Anska River Overpass 1140+540 Underpass 1141+460 Bridge on Vardar River Underpass 1142+760 Subtotal Total Length (m) 8.7 13 46 46 46 45.5 46.0 8.7 504 8.7 773 1,756 47 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Alignment 2 The bridges foreseen in Alignment 2 are summarised in the following table, prepared by E.O.A.E.: Name S1-Bosava S2-Rail S3 S4 S5 S6-Javorica S7 S8 S9-Petruska Starting km point 900 1400 3260 5000 7100 8800 10100 14300 21275 Ending km point 1000 1600 3440 5040 7200 9140 10400 14700 21425 Total Length (m) 100 200 180 40 100 340 300 400 150 1,810 Tunnels Alignment 1 The foreseen tunnels concern only the section between Demir Kapija and Udovo: Three of them are single-tube and the other two are double-tube tunnels. Their location and lengths are listed in the following table: Tunnel T1 and T2 T3 T4 T7 Location Demir Kapija Kisalder Ilovski Kamen Starting km point 1112+934 – 1114+428 1117+336 – 1117+540 1122+822 – 1123+326 1128+269 – 1128+892 Total Length (m) 1,494 204 504 623 2,825m Alignment 2 The foreseen tunnels are two: Tunnel T1 T2 Starting km point 1830 8180 Ending km point 3080 8580 Total Length (m) 1,250 400 1,650m 4.2.2.7 Traffic interchanges The construction and operation of interchanges is foreseen in order to connect the future motorway with the rest of the road network, with regional and municipal centres. The foreseen interchanges in the case of Alignment 1 are at Udovo and at Smokvica. As already mentioned, in the case of Alignment 2 only one interchange is foreseen, however its exact position has not yet been defined; potential places for construction of interchange are Smokvica and Miletkovo. EGNATIA ODOS S.A. APRIL 2007 48 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 4.2.2.8 Environmental protection equipment Costs for the environmental impact mitigation measures are currently being estimated for each of the two examined alignments of the project, therefore they are not included in the costs of the projects. EGNATIA ODOS S.A. APRIL 2007 49 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 5. 5.1 5.1.1 5.1.1.1 TRAFFIC FORECASTS Presentation of the tool for traffic forecasts Methodology of the development of the forecasting tool Data collection – Construction of the base year database The construction of the base year Database has been achieved through extensive questionnaire based-surveys followed by on-site visits of expertise at the network in the countries of Corridor X (Austria, Slovenia, Croatia, Hungary, Serbia, Bulgaria, F.Y.R.O.M. and Greece). The necessary information, collected via the questionnaires and via various National and International Organizations (National Statistic Services, Eurostat, World Bank, United Nations, World Trade Organization, World Tourism Organization, Organization for the Economic Cooperation and Development etc.) concerns physical and operational characteristics of the network (e.g. traffic flows, operational speed, road category, duration of trips, delays at cross-borders etc.) and various demand parameters (e.g., socioeconomic characteristics, population, Gross Domestic Product, imports and exports of goods, tourism etc.). 5.1.1.2 Methodological issues and constraints Objectively, it is difficult to obtain reliable estimations of the future transport demand and the respective realistic volumes’ assignment on the transport network because of the highly uncertainty of the socioeconomic status of the countries composing the area of Corridor X. In the mean time the representation of the current status is insufficient, due to the lack of data, their incompatibility from country to country and from period to period, because of the new borders and the creation of new independent states after 1990 in the area of the Western Balkans (former Yugoslavia). Due to the political changes, the technical structures and administration systems also collapsed, and among those, the organisations of systematic data collection and processing of transport demand and supply. Obviously, the confusion produced was enjoined by the border changes, given the fact that substantial part of relative data is referred at certain «screenline stations», which are the countries’ various border stations. Many of them did not exist before 1990 but they were created afterwards and not simultaneously. Far from the partial data reliability, comparability issues raise from year to year and also from independent state (pre-existing or new) to independent state. The reliability problem does not concern only the transport data, but also demographic data, macroeconomic indicators, industrial production and external trade. 5.1.1.3 Adopted methodology and assumptions for the scenarios’ development The traffic forecasting approach of the Technical Secretariat of Corridor X is based on best practices (TIRS and REBIS/ approved by the EC and the WB/EIB), which were also based on the TINA and NEA study. EGNATIA ODOS S.A. APRIL 2007 50 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X In the Corridor X traffic forecasting, a marginal expression of generalized time was used, which was extracted by real data and comprises trip durations and delays for various reasons, of which (and mainly) the delays at border crossings. The reference network is Corridor X, i.e. the main axis and its four branches. It is composed by existing infrastructures, with reduced operability due to lack of maintenance, investments and also desolation or war disasters. Corridor X is part of a greater grid, which also comprises Corridors IV, V, VII and VIII. The network refers to land transport, with respect to rail and road transport, passenger and freight transport and, finally, local (domestic) and international transport. The primary discrimination is based on the mean travel – transport distance, where, according to TIRS, the line between local and long distance trips is 100km, while the biggest part of international inland transport does not exceed 400km. Additionally, the increase rate of local mobility, which mainly depends on the private car ownership indicator, is significantly higher than the increase rate of international mobility in the area. The reference network is inscribed in an area separated in zones, for the needs of trip generation and spatial distribution. The available, from national and international organisations, demographic and macroeconomic information, usually refer at country level and not to smaller geographic – administrative divisions. This is the reason why each Corridor X’s country consists a zone. Given that the current decade is a commutative period, it was intended that the scenarios and mainly their quantitative projections to have as target year the year 2015. The country grouping was combined to the perspective of accession of those countries to the E.U. and the accession time for each one, which of course is not absolutely defined and for some countries is absolutely unknown. The accession perspectives obviously affect the scenarios definition because the external trade, and therefore the freight transport, in relation to the accession, tends to liberization and the same happens with the free movement of persons. At the same time, the enlargement of the E.U. with these countries affects the heading to European integration in global level (globalisation) but to some extend diverts from it. 5.1.2 The scenarios Three scenarios of development were formulated: the basic-medium (realistic) and two scenarios of low and high development, namely the pessimistic and optimistic scenario, respectively. The scenarios’ definition ends up with the application of annual change rates on variables affecting directly the passenger and goods flows. The annual change rates of the socioeconomic, demographic and other (arrivals of visitors/ tourists at borders) characteristics used, had been extracted from relevant studies carried out by the OECD, the World Bank and other international organizations. EGNATIA ODOS S.A. APRIL 2007 51 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Annual growth rates of various demand parameters per zone and scenario Zone Albania Bulgaria Czech Rep. Hungary Poland Romania Slovakia Slovenia Greece France Italy Austria Baltic States Spain – Portugal Germany, Belgium, Luxemburg, Holland United Kingdom – Ireland Scandinavia Switzerland Turkey Serbia/ Montenegro Bosnia/ Herzegovina Croatia F.Y.R.O.M. Russia and former Russian States Low 1.00 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.30 0.30 0.30 0.30 0.30 0.30 Med 1.00 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.30 0.30 0.30 0.30 0.30 0.30 High 1.00 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.30 0.30 0.30 0.30 0.30 0.30 Gross Domestic Product % Low Med High 5.00 6.50 8.00 3.00 4.00 5.00 3.00 4.00 5.00 3.00 4.00 5.00 3.00 4.00 5.00 3.00 4.00 5.00 3.00 4.00 5.00 3.00 4.00 5.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 3.00 4.00 5.00 2.00 2.00 2.00 Low 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 1.25 1.25 1.25 1.25 2.50 1.25 Med 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 2.50 2.50 2.50 2.50 5.00 2.50 High 7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50 3.75 3.75 3.75 3.75 7.50 3.75 Arrivals at borders % All scenarios 8.00 5.00 4.00 4.00 4.00 4.00 4.00 4.00 1.00 1.00 1.00 1.00 5.00 1.00 1.25 2.50 3.75 1.00 0.30 0.30 0.30 2.00 2.00 2.00 1.25 2.50 3.75 1.00 0.30 0.30 0.30 2.00 2.00 2.00 1.25 1.25 2.50 2.50 2.50 2.50 2.50 2.50 2.50 5.00 5.00 5.00 5.00 5.00 3.75 3.75 750 7.50 7.50 7.50 7.50 1.00 1.00 8.00 5.00 5.00 4.00 5.00 0.30 0.30 1.50 0.50 0.50 1.00 0.50 0.30 0.30 1.50 0.50 0.50 1.00 0.50 0.30 0.30 1.50 0.50 0.50 1.00 0.50 2.00 2.00 3.00 3.50 3.50 4.00 3.00 2.00 2.00 4.00 4.30 4.40 4.40 3.70 2.00 2.00 5.00 6.00 5.50 5.00 5.00 1.25 2.50 3.75 4.00 0.30 0.30 0.30 3.50 3.50 3.50 International Trade % Population % Additionally to the basic socioeconomic variables, on the various target years and scenarios, reduction coefficients are used to simulate the running times caused mainly by the development of the installations and procedures at cross borders, representing the smoothing out of the bilateral relations between the Balkan countries (and therefore the countries participating in Corridor X). 5.1.3 Estimation of the passenger and freight flows 5.1.3.1 Estimation of the international passenger and freight flows on Corridor X Given the different development and the different values of the change parameters of domestic and international flows, the international flows are distinguished from the total traffic. In such a way, the four stages of the classic procedure of transport planning concern the international transport, which do not experience the limitation of data heterogeneity for the areas and zones, like domestic flows. EGNATIA ODOS S.A. APRIL 2007 52 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Additionally, it should be mentioned that the models used concern only the road international transport, separately for passenger and freight, taking into account the existing modal split (share of international transport by road 78%). The estimation of the domestic transport was produced by the use of growth factors. Passenger transport For the estimation of the generation of passenger transport an exponential equation was produced by linear regression. In this equation the independent variable is the GDP and the dependent variable is the number of trips per person per year. The journeys per person per year, which are used for the creation of the equation, were obtained by pilot studies of Eurostat and DG TREN, where the passengers travelling various distances using all modes and their behaviour are examined. Estimation of road long distance trips per year Country F.Y.R.O.M. Albania Bosnia/ Herzegovina Romania Bulgaria Serbia & Montenegro Croatia Hungary Slovenia Slovakia Turkey Greece Austria 1,089,238,78 1,631,768,72 % persons travelling long distance 7.024 6.743 Road long distance trips/ year 76,504 110,028 0.78 1,605,693,19 6.515 104,614 16,706,277,75 6,775,542,91 0.78 0.78 13,030,896,64 5,284,923,47 7.203 7.473 938,551 394,950 10,645,200 5,932,656,02 0.78 4,627,471,70 6.617 306,181 4,381,400 10,005,300 1,990,100 5,402,500 65,784,000 10,565,000 8,121,000 3,465,064,44 13,991,889,98 4,193,550,76 7,044,341,93 52,548,658,53 21,953,126,64 41,964,172,61 0.78 0.78 0.78 0.78 0.78 0.78 0.78 2,702,750,26 10,913,674,18 3,270,969,59 5,494,586,70 40,987,953,65 17,123,438,78 32,732,054,64 7.346 9.245 11.460 8.950 7.371 11.368 21.023 198,556 1,008,986 374,854 491,749 3,021,332 1,946,673 6,881,265 GDP/ capita (2000) Trips/ person/ year Trips/ year % road trips Population Road trips/ year 4,400 3,000 0.69 0.60 2,031,100 3,500,000 1,396,459,97 2,092,011,18 0.78 0.78 1,700 0.52 3,922,205 2,058,581,01 5,200 6,300 0.74 0.83 22,430,500 8,149,500 2,300 0.56 5,800 11,500 15,600 10,800 5,900 15,460 24,570 0.79 1.40 2.11 1.30 0.80 2.08 5.17 EGNATIA ODOS S.A. APRIL 2007 53 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The attractions are calculated in respect to the arrivals of visitors at the borders of each zone - country. The necessary data were obtained by Eurostat and the World Tourism Organization. Arrivals of visitors at borders (in thousands) Country Albania Croatia F.Y.R.O.M. Serbia/ Montenegro Bulgaria Czech Republic Estonia Hungary Latvia Lithuania Moldavia Poland Romania Slovakia Slovenia Turkey 1994 340 18,441 3,189 101,140 1,900 39,836 1,944 2,369 1995 304 16,100 2,628 5,284 98,061 2,110 39,240 1,633 2,055 74,253 5,898 21,868 3,339 6,671 82,244 5,445 27,301 3,184 7,727 1996 288 18,085 2,156 6,811 109,405 2,435 39,833 1,750 3,499 1,066 87,439 5,205 33,113 3,594 8,537 1997 119 22,624 2,078 152 7,543 107,884 2,618 37,315 1,842 3,702 1,125 87,817 5,149 31,742 3,828 9,713 1998 184 24,379 1,848 239 5,240 102,844 2,909 33,624 1,788 4,287 1,198 88,592 4,831 32,735 3,297 9,431 1999 371 28,211 2,223 351 5,056 100,832 3,181 28,803 1,738 4,454 1,229 89,118 5,224 30,757 3,000 7,487 2000 317 35,961 2,865 448 4,922 104,247 3,310 31,141 1,882 4,092 1,240 84,515 5,264 28,769 3,179 10,428 The Eurostat data concern total arrivals at borders, e.g. entrances in the country, so they include arrivals by all modes of transport. For this reason, the arrivals at road cross border stations were obtained from the World Tourism Organization, where the arrivals at the borders are discriminated per mode according to the national statistic services. Arrivals of tourists at borders (in thousands) Country Albania Croatia F.Y.R.O.M. Serbia/ Montenegro Bulgaria Czech Republic Estonia Hungary Latvia Lithuania Moldavia Poland Romania Slovakia Slovenia Turkey 1996 2,914 136 2,795 4,558 665 20,674 556 832 1,054 4,088 762 951 832 7,888 1997 4,178 121 2,980 4,976 730 17,248 626 1,012 1,111 3,923 833 814 974 9,063 1998 4,499 157 2,667 5,482 825 2,871 567 1,416 1,182 3,562 810 896 977 8,638 1999 354 3,805 181 2,491 5,610 950 2,789 489 1,422 1,214 3,178 795 975 884 6,893 2000 5,832 224 2,785 4,666 1,200 452 1,083 1,216 3,122 867 1,053 1,090 9,586 Finally, from these data the arrivals of the visitors of the same date were identified, which mainly consist of transit visitors, in order to avoid overestimation of international transport. For the countries grouped to a zone, the trips between them were estimated and they were abstracted. Also, for the zones bordering with EGNATIA ODOS S.A. APRIL 2007 54 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X countries out of the study area (Turkey, Russia – former socialistic republics) the passenger flows were adjusted to the observed traffic volumes at borders within the study area. Freight transport The produced freight flows were considered, based on the TIRS experience, by the total tonnage of the transported goods by road. The calculation was made possible under the assumption that the goods transported by road are at a high percentage commodities of categories 6 (construction and raw materials and minerals) and 9 (machinery, manufactured products, transport equipment etc.) of NSTR (Nomenclature uniforme des marchandises pour les Statistiques de Transport, Révisée e.g. Nomenclature of statistical data in use by Ε.U. since 1st January 1967). Those categories are directly related to the GDP but could not be reliably distributed between the zones of the study area with GDP criteria, not with the GDP of the destination country but also not with the GDP of the origin country. Due to the existence of a complete origin–destination matrix of road transport in tonnage between E.U. countries and countries of the PHARE zone, it was preferred to extend and complete this O-D with data for the extra zones of the study area, so that the calibration and trip distribution preserve the existing bilateral trade relations. Therefore, the danger of producing trade flows that do not correspond to reality, and could came up if the GDP was used for the distribution, was avoided. As for the case of passenger transport, for the countries grouped to a zone, the trips between them were estimated and they were abstracted. Also, for the zones bordering with countries out of the study area (Turkey, Russia – former socialistic republics) the freight flows were adjusted to the observed traffic volumes at borders within the study area. The attractions were automatically calculated through the use of the complete O-D matrix. 5.1.3.2 The model The forecast of international traffic flows on the various road sections of Corridor X was based on the creation of models with the use of TRIPS (TRansport Improvement Planning System) software for transport planning. Two models were constructed; one for the modelling of passenger transport and one for freight transport. The simulations concerned the stages of trip distribution to zones and trip assignment on the network. Traffic zones and road network Due to the fact that Corridor X crosses and serves a big part of the Balkan Peninsula, the study area was set to be the Balkan countries and their main road network. Each Balkan country considered as a unique traffic zone with trip productions and attractions with the capital as centroid. Several external zones were used, in order to EGNATIA ODOS S.A. APRIL 2007 55 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X include the trips from and to the rest of the European countries in the simulation of international traffic on Corridor X. The definition of the external zones was based on the socioeconomic characteristics of the various countries, on their geographic position and the road network connecting them with the Balkans. In total 24 traffic zones were defined. The codification of the road network was performed based exclusively on the road sections characteristics (Link Based Network). Primarily the nodes are defined and then the connections between them are defined too. Then, for each road section the capacity, the distance, the road category, the running time and other indicators are defined. The representation of the delays observed at the cross border stations was simulated by adding time charging/penalties (in TRIPS the additional travel time and economic charges are simulated as tolls) at the respective points of the network. The hierarchy of the road network and therefore the calculation of the capacity of traffic lanes per hour are based on the Great Britain’s standings (Department of Transport, DOE Advice Note 1A, 1971), which are compatible with the TRIPS structure. The examination of the digitized network and the calibration was performed for each pair of traffic zones (using AVROAD application), the best routes were defined with "all or nothing" method and then tested. After the network calibration a cost matrix was calculated using the AVROAD based on the generalised cost function used in TRIPS. Generalised cost The calculation of the optimum routes and generally of the travel cost per pair of zones, was performed based on the relation of generalized cost. Time was selected to be the expression of generalised cost. The cost of tolls used in the generalised cost equation represents the delays at cross borders. Model for trip distribution to zones The trip distribution was based on the methodology of gravity models. For the model calibration two matrices were used: an O-D of freight transport for the year 2000, and cost matrix (time-distances) between the zones. Having the gravity model calibrated and using the results of the trip generation stage (trip ends) the O-D matrices for each scenario and target year were estimated. EGNATIA ODOS S.A. APRIL 2007 56 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Traffic assignment The trip assignment was performed using the TRIPS AVROAD application with “all or nothing” method, where for each pair of origin-destination one and only optimum route (depending on generalized time) is calculated. No issues of capacity limitations are examined, because the assignment refers only to international traffic and obviously no volumes close to capacity are expected. Each origin-destination matrix of the scenarios was distributed to the road network and the traffic assignment of the various sections of Corridor X occurred. 5.1.3.3 Estimation of local traffic and assignment of road Corridor X Following the assignment of the international flows on the study network and Corridor X, the traffic volumes are abstracted from the observed respective volumes, in order to estimate the local traffic for the base year. For the various target years and scenarios the local traffic was calculated by applying an annual growth rate of 1.25 on the annual growth rate of GDP of each country. Hence, the total assignment for the various target years and scenarios is achieved by the distribution of the international traffic and the addition of the each time estimated local traffic. 5.2 Formulation of scenarios (time horizons) The time horizons for the economic analysis, and therefore for the traffic projections, are formulated depending on the construction and operation period of the project. The first year of the analysis period is set to be the year 2008. For Alignment 1 the construction period is from six to eight years, while for the scope of the study the construction is considered to take six (6) years, in the period 2008-2013. In the case of Alignment 2 the construction period is three to four years. For the scope of the study the construction period is three (3) years, i.e. 2008-2010. Therefore, the first year of operation of pay-toll motorway between Demir Kapija and Smokvica is 2014 in the case of upgrading the existing road to a motorway (Alignment 1) and 2011 in the case of construction of a totally new motorway (Alignment 2). The usual period of economic analysis of a project is 25 years, despite the fact that project’s life cycle is undoubtedly longer than that. However, traffic estimations for longer time horizons would be arbitrary; one could doubt even for a shorter projection of traffic is such a sensitive and uncertain, also complex in terms of economic development, region. For the scope of the study, traffic estimations are EGNATIA ODOS S.A. APRIL 2007 57 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X made for each year during the 25-years period of analysis, in order to estimate the economic benefits from the reduction of vehicles operational costs, from the reduction of accidents and also to estimate the revenues from the charge of motorway users. 5.3 Traffic forecasts 5.3.1 Evaluation of traffic projections 5.3.1.1 General conclusions of the traffic flows forecasting of the Technical Secretariat of Corridor X The development priorities of the Corridor X’s infrastructure, experience the infrastructure development criteria at Pan-European, and not only national, level. Priorities are not defined only by the demand-supply relation, but also by their involvement in development projects of strategic character, where among their other aims are also the arsis of the Western Balkans’ area isolation and the securing of the consecutiveness of the structural and operational characteristics of the infrastructures. Transport policy, as expressed by the Directorate General for Energy and Transport of the European Commission, is interpreted to the effort of the PanEuropean and Trans-European Networks implementation, and to the definition of a Western Balkans Core Network based on REBIS. The national strategies are from now on adjusted to the same direction, which is of course the most appropriate way for securing international financing. The most important result arising from the forecasting process is that international traffic flows, despite the increasing trends, will not be the, at least in the short-term, the main component of traffic volumes: In the medium-realistic scenario, by the year 2005 the road international transport in Corridor X’s countries – at national level – of commercial vehicles will increase by 1328% and of passenger vehicles by 18-28%. By 2010 – compared to 2000 – the international flows of commercial vehicles will increase by 28-63% and of passenger vehicles by 18-69%. Finally by 2015, the international flows of commercial vehicles will increase by 45-108% and of passenger vehicles by 31-235%. The lowest values refer to Austria, whilst the highest ones refer to the Balkan countries. In the low scenario, the international freight transport flows will increase by 6-13% by 2005, by 13-28% by 2010 and by 20-45% by 2015. Respectively, the international passenger transport flows will increase by 8-24% by 2005, by 18-57% by 2010 and by 31-102% by 2015. Finally, in the high scenario, the international freight transport flows will increase by 20-44% by 2005, by 45-106% by 2010 and by 74-196% by 2015. Respectively, the international passenger transport flows will increase by 8-32% by 2005, by 18-85% by 2010 and by 31-192% by 2015. Furthermore, on road Corridor X, bottlenecks are not expected to appear, except near big cities or the capitals of the countries (for example near Belgrade), only in the case that bypasses’ construction plans won’t be implemented, and at some links, where also motorways construction plans exist. EGNATIA ODOS S.A. APRIL 2007 58 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 5.3.1.2 Results and evaluation of results of the various available traffic flows forecasting exercises There are various traffic projections available, derived by traffic flows forecasting exercises in the past. The results of the traffic forecasting tool of Technical Secretariat for Corridor X in the moderate scenario are presented in the following table: Demir Kapija – Udovo Udovo – Gevgelija Demir Kapija – Gevgelija (weighted) AADT 2000 (veh/day) AADT 2005 (veh/day) Average of annual traffic growth factor 2000-2005 AADT 2015 (veh/day) Average of annual traffic growth factor 2005-2015 Average of annual traffic growth factor 2000-2015 2,754 3,711 5.1% 5,476 4% 4.7% 3,334 4,955 6.8% 7,430 4.1% 5.5% 3,060 4,366 4.6% 6,506 4.1% 5.2% The table below details traffic forecasts of the Technical Secretariat and REBIS for 2005, as well as the actual recorded AADT: Section Demir Kapija – Udovo Udovo – Gevgelija Demir Kapija – Gevgelija (weighted) Forecasted AADT for 2005-06 in veh/day Technical REBIS (2006) Secretariat (2005) Actual AADT in 2005 (veh/day) Actual AADT in 2006 (veh/day) 3,711 2,877 2,671 3,596 4,955 4,084 3,368 4,098 4,366 3,513 3,038 3,860 Compared to the actual traffic flows it is concluded that the forecast of the Technical Secretariat is higher. However, traffic growth within one year, between 2005 and 2006, was very high, that one may rationally allege that any attempt for traffic forecast might easily proved unsuccessful. It is considered that this high increase is a result of the stabilization of the situation in the wider region; however, traffic is not expected to continue growing with the same high rates. Hence, for the scope of the present study, it is considered that more or less the same traffic volumes are expected by the year 2015, no matter if that will be the result of stable increase or a jump in the first years. Average annual growth factor of the forecast of the Technical Secretariat during the entire period 2000-2015 is 5.2%. EGNATIA ODOS S.A. APRIL 2007 59 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The estimation of REBIS for the year 2006 is 3,513 veh/day along the section from Demir Kapija to the Gevgelija. REBIS estimates 5,561 veh/day for the year 2015 and 8,770 veh/day for the year 2025. Average annual growth factors calculated by the projections of REBIS are 4.58% in the period 2001-2006, 5.24% in the period 2006-2015 and 4.66% in the period 2015-2025. Average annual growth factor of REBIS forecast during the entire period 2001-2025 is 4.86%. Section Demir Kapija – Udovo Udovo – Gevgelija Demir Kapija – Gevgelija (weighted) Forecasted AADT for 2015 in veh/day Technical Secretariat REBIS TIRS 5,476 4,554 n.a. 7,430 6,465 n.a. 6,506 5,561 4,450 Based on the above considerations, an annual traffic growth factor of 5% is considered a realistic and achievable assumption for the next years until 2015. This level of growth would mean that depending on the type of intervention (do nothing, upgrade, motorway construction), in some year between 2015 and 2020 the traffic volumes on the corridor would be back at the levels they were in 1990 (i.e. immediately before the regional crisis), at about 6,000 veh/day. Finally, it is considered unlikely that traffic will continue growing at the same rates indefinitely. Over the period 2015 – 2025 traffic is assumed to grow at a reduced rate of 4% per annum and from 2025 onwards at a rate of 3% annually. 5.3.1.3 Traffic projection to various target years Following the review of the available traffic forecasts presented in the above, the projection of traffic for the period of economic analysis of the project is performed, based on the assumption that traffic flows will grow faster within the next decade (by 5% annually), slower in the period 2015 – 2025 with annual growth factor of 4% and after 2025 with annual growth factor of 3%. These assumptions are considered conservative for a developing country, while in EU countries annual traffic growth is between 2-3%. Generated and diverted traffic on a future motorway (alternatives B, C, D) Generated traffic occurs on the first year of operation of the motorway, when is given to traffic. The new infrastructure with higher level of service has a direct impact on traffic. Therefore, apart from the traffic growth represented in the model by the increased mobility (and car ownership) due to the improvement of the economic status and potential of the residents of the F.Y.R. of Macedonia and of the residents of all the other considered traffic zones and countries in the form of GDP increase, an additional increase of traffic by 10% is considered realistic to expect after the motorway opening to traffic. EGNATIA ODOS S.A. APRIL 2007 60 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Furthermore, additional traffic is expected as a result of the completion of the entire motorway from Skopje to the Greek border, which would cause diversion of traffic from the M-5 and M-6 roads from/ to Strumica and Dojran (See Map 5.1). This percentage is considered to be an additional 5%, i.e. around to 200 veh/day. The introduction of tolls along the new motorway will cause traffic volumes decrease. In the present study, the diverted traffic is estimated with the use of respective percentages per vehicle category, as estimated for Serbian motorways. Diverted traffic to the alternative road network would be around 7.7% of the traffic estimated for the last year of construction: Diverted traffic to the alternative road network Small cars Buses Heavy trucks Articulated trucks 9% 3% 5% 0% The above percentages are applied in the case of Alignment 1, where the new motorway offers direct connection to Udovo and the connecting links to Miravci and Valandovo. In the case of Alignment 2, the direct access to Udovo and the connecting roads R-103 to Miravci and R-110 and R-116 to Valandovo is disturbed (See Map 5.1). Therefore, the diversion of forecasted traffic to the existing M-1 road (serving as alternative road in this case) would be higher. Source: Fund for National and Regional Roads Map 5.1: Adjacent and alternative road network EGNATIA ODOS S.A. APRIL 2007 61 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Through the examination of the traffic assignment performed by Scetauroute for the year 1998, it is estimated that a percentage of 25% of the traffic between Demir Kapija and Udovo is directed to Valandovo and Miravci. Thus, it is assumed that upon the opening to traffic of the new motorway section on the west bank of Vardar River a direct loss of additional traffic volumes will occur along the motorway. In the case of Alignment 2 the following percentages of diverted traffic per vehicle category are assumed: Diverted traffic to the alternative road network Small cars Buses Heavy trucks Articulated trucks 27% 9% 15% 0% Forecasted traffic is estimated with the application of annual growth factors, addition of the generated traffic on the first year of operation and subtraction of the diverted traffic in the first year of operation and introduction to the pay-toll system: Alignment 1 Alignment 2 First year of operation – addition of generated traffic 2014 2011 Introduction of tolls – subtraction of diverted traffic to alternative network 2014 2011 In the following tables the annual projected traffic of the section under examination are presented for the “Do Minimum” Alternative A and the motorway alternatives for each one of the two examined alignments. EGNATIA ODOS S.A. APRIL 2007 62 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Traffic forecast along Demir Kapija – Smokvica section “Do minimum” Alternative Year Motorcycles Private cars Vans and Buses pickups Light Medium Heavy Articulated trucks trucks trucks trucks Total PCUs 2006 36 2,464 250 71 143 143 214 250 3,571 4,928 2007 37 2,587 262 75 150 150 225 262 3,750 5,174 2008 39 2,717 276 79 157 157 236 276 3,937 5,433 2009 41 2,852 289 83 165 165 248 289 4,134 5,705 2010 43 2,995 304 87 174 174 260 304 4,341 5,990 2011 46 3,145 319 91 182 182 273 319 4,558 6,289 2012 48 3,302 335 96 191 191 287 335 4,785 6,604 2013 50 3,467 352 100 201 201 301 352 5,025 6,934 2014 53 3,640 369 106 211 211 317 369 5,276 7,281 2015 55 3,822 388 111 222 222 332 388 5,540 7,645 2016 58 4,014 407 116 233 233 349 407 5,817 8,027 2017 60 4,174 423 121 242 242 363 423 6,049 8,348 2018 63 4,341 440 126 252 252 377 440 6,291 8,682 2019 65 4,515 458 131 262 262 393 458 6,543 9,029 2020 68 4,695 476 136 272 272 408 476 6,805 9,391 2021 71 4,883 495 142 283 283 425 495 7,077 9,766 2022 74 5,078 515 147 294 294 442 515 7,360 10,157 2023 77 5,282 536 153 306 306 459 536 7,654 10,563 2024 80 5,493 557 159 318 318 478 557 7,961 10,986 2025 83 5,713 580 166 331 331 497 580 8,279 11,425 2026 86 5,941 603 172 344 344 517 603 8,610 11,882 2027 89 6,119 621 177 355 355 532 621 8,869 12,239 2028 91 6,303 639 183 365 365 548 639 9,135 12,606 2029 94 6,492 659 188 376 376 565 659 9,409 12,984 2030 97 6,687 678 194 388 388 581 678 9,691 13,373 2031 100 6,887 699 200 399 399 599 699 9,982 13,775 2032 103 7,094 720 206 411 411 617 720 10,281 14,188 2033 106 7,307 741 212 424 424 635 741 10,590 14,614 2034 109 7,526 764 218 436 436 654 764 10,907 15,052 2035 112 7,752 786 225 449 449 674 786 11,234 15,504 Average traffic for the operational period 2008 – 2032 is estimated at 6,936 veh/day (9,572 PCUs/day). For comparison to the motorway alternatives the average traffic for the periods of operation of the two motorway solutions (alignments) are the following: 2014 – 2032 (Alignment 1): 7,717 veh/day (10,650 PCUs/day) 2011 – 2032 (Alignment 2): 7,460 veh/day (10,295 PCUs/day) EGNATIA ODOS S.A. APRIL 2007 63 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Traffic forecast along Demir Kapija – Smokvica motorway section Motorway Alignment 1 Year Motorcycles Private cars Vans and Buses pickups Light Medium Heavy Articulated trucks trucks trucks trucks Total PCUs 2006 36 2,464 250 71 143 143 214 250 3,571 4,928 2007 37 2,587 262 75 150 150 225 262 3,750 5,174 2008 39 2,717 276 79 157 157 236 276 3,937 5,433 2009 41 2,852 289 83 165 165 248 289 4,134 5,705 2010 43 2,995 304 87 174 174 260 304 4,341 5,990 2011 46 3,145 319 91 182 182 273 319 4,558 6,289 2012 48 3,302 335 96 191 191 287 335 4,785 6,604 2013 50 3,467 352 100 201 201 301 352 5,025 6,934 2014 55 3,810 386 118 231 231 346 425 5,601 7,838 2015 58 4,000 406 124 242 242 363 446 5,881 8,230 2016 61 4,200 426 130 254 254 381 468 6,175 8,642 2017 63 4,368 443 135 264 264 397 487 6,422 8,988 2018 66 4,543 461 140 275 275 412 506 6,679 9,347 2019 68 4,725 479 146 286 286 429 527 6,946 9,721 2020 71 4,914 498 152 297 297 446 548 7,224 10,110 2021 74 5,110 518 158 309 309 464 570 7,513 10,514 2022 77 5,315 539 164 322 322 482 592 7,813 10,935 2023 80 5,527 561 171 335 335 502 616 8,126 11,372 2024 83 5,748 583 178 348 348 522 641 8,451 11,827 2025 87 5,978 606 185 362 362 543 666 8,789 12,300 2026 90 6,217 631 192 376 376 564 693 9,140 12,792 2027 93 6,404 650 198 388 388 581 714 9,415 13,176 2028 96 6,596 669 204 399 399 599 735 9,697 13,571 2029 98 6,794 689 210 411 411 617 757 9,988 13,978 2030 101 6,998 710 216 423 423 635 780 10,288 14,398 2031 104 7,208 731 223 436 436 654 804 10,596 14,830 2032 108 7,424 753 229 449 449 674 828 10,914 15,274 2033 111 7,647 776 236 463 463 694 852 11,241 15,733 2034 114 7,876 799 243 477 477 715 878 11,579 16,205 2035 118 8,112 823 251 491 491 736 904 11,926 16,691 Average traffic for the analysis period 2008 – 2032 is estimated at 7,297 veh/day (10,192 PCUs/day). For the operational period 2014 – 2032 average traffic is estimated at 8,192 veh/day (11,465 PCUs/day). EGNATIA ODOS S.A. APRIL 2007 64 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Traffic forecast along Demir Kapija – Smokvica motorway section Motorway Alignment 2 Private Vans Light Medium Heavy Articulated trucks trucks trucks trucks Total PCUs 250 3,571 4,928 225 262 3,750 5,174 157 236 276 3,937 5,433 165 165 248 289 4,134 5,705 87 174 174 260 304 4,341 5,990 268 95 178 178 267 367 4,032 5,848 2,772 281 100 187 187 281 385 4,234 6,140 2,911 295 105 196 196 295 404 4,445 6,447 44 3,056 310 110 206 206 309 425 4,668 6,769 2015 47 3,209 326 116 217 217 325 446 4,901 7,108 2016 49 3,369 342 122 227 227 341 468 5,146 7,463 2017 51 3,504 355 127 237 237 355 487 5,352 7,762 2018 53 3,644 370 132 246 246 369 506 5,566 8,072 2019 55 3,790 385 137 256 256 384 527 5,789 8,395 2020 57 3,942 400 142 266 266 399 548 6,020 8,731 2021 59 4,099 416 148 277 277 415 570 6,261 9,080 2022 62 4,263 433 154 288 288 432 592 6,511 9,443 2023 64 4,434 450 160 299 299 449 616 6,772 9,821 2024 67 4,611 468 167 311 311 467 641 7,043 10,214 2025 70 4,796 487 173 324 324 486 666 7,324 10,623 2026 72 4,988 506 180 337 337 505 693 7,617 11,047 2027 74 5,137 521 186 347 347 520 714 7,846 11,379 2028 77 5,291 537 191 357 357 536 735 8,081 11,720 2029 79 5,450 553 197 368 368 552 757 8,324 12,072 2030 81 5,614 569 203 379 379 568 780 8,574 12,434 2031 84 5,782 587 209 390 390 585 804 8,831 12,807 2032 86 5,955 604 215 402 402 603 828 9,096 13,191 2033 89 6,134 622 222 414 414 621 852 9,369 13,587 2034 92 6,318 641 228 426 426 640 878 9,650 13,995 2035 94 6,508 660 235 439 439 659 904 9,939 14,414 and Buses Year Motorcycles 2006 36 2,464 250 71 143 143 214 2007 37 2,587 262 75 150 150 2008 39 2,717 276 79 157 2009 41 2,852 289 83 2010 43 2,995 304 2011 38 2,640 2012 40 2013 42 2014 cars pickups Average traffic for the analysis period 2008 – 2032 is estimated at 6,194 veh/day (8,948 PCUs/day). For the operational period 2011 – 2032 average traffic is estimated at 6,474 veh/day (9,389 PCUs/day). EGNATIA ODOS S.A. APRIL 2007 65 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 5.4 Evaluation of alternatives level of service in function with the forecasted traffic flows The tool for the calculation of the level of service is the Highway Capacity Manual (HCM) 2000 for two-lane and multi-lane highways. The basic traffic parameter taken into consideration for the definition of the Level of Service is the 50th maximum hourly traffic. The 50th maximum hourly traffic for multi-lane highways is defined by multiplying the Annual Average Daily Traffic by 0.14 for unfavourable conditions. The 15-min passenger-car equivalent flow rate (pc/hr/lane) is estimated with the assumption of 50%-50% (2001 data) distribution of traffic between opposite directions. For each subsection of the section under study the Volume over Capacity (V/C) ratio is calculated for every traffic projection annually in the analysis period. It occurs that the 15-min passenger-car equivalent flow rate (pc/hr/lane) is retained below 1,400pc/h/lane in the entire period of analysis, which is the Free Flow Speed (FFS) upper limit under low volume conditions [10]. It is estimated that the level of service will be retained at Level A for almost the entire period of analysis due to the low levels of traffic. At this point it should be mentioned that the recommended level of motorway utilisation is LOS D and maximum level of utilisation is LOS B. Concerning the existing M-1 road, taking into consideration the 50th maximum hourly traffic (AADT*0.12) it is concluded that, according to the existing and forecasted traffic, the LOS (if consider 0% of permitted overtaking) will reach LOS E in at least fifteen years. EGNATIA ODOS S.A. APRIL 2007 66 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 6. ECONOMIC ANALYSIS The following include the evaluation of benefits in relation to the construction and operational costs of the road section in the Former Yugoslav Republic of Macedonia, which connects Demir Kapija with Smokvica. As it was reported in previous chapters this road axis is classified as part of the main and most important corridor of the national road network of the country, while at the same time it constitutes a section of the Pan-European Road Corridor X. Accordingly, the technical and economical evaluation of the project concerning the upgrade of the geometrical and operational characteristics of this road section has a particular importance, not only for F.Y.R Macedonia, but also for the wider area of the Balkans and Europe. A comparative technical and economical evaluation is separately carried out for two motorway projects. In total seven (7) alternatives concerning the road construction are examined, i.e. the “Do minimum” alternative (alternative A) that concerns upgrading of the existing road and also the other three alternatives, B, C and D that concern the motorway construction (separated carriageways) for each of the two alignments. The two under study alignments are the following: Alignment 1 Alignment 2 Length 32.15km 28.05km The time schedule for the completion of the construction of the two alignments (independently of the alternative) is presented below: Alignment 1 Alignment 2 Construction period 2008 – 2013 2008 – 2010 Years in construction 6 years 3 years First year of full operation 2014 2011 The period of analysis for each section was considered equal to 25 years. The year 2008 was considered as the "base year" since it constitutes the year of beginning of the construction works and hence the year for the payment of the first expenses. The period of analysis for the whole project is 25 years, from year 2008 to year 2032. 6.1 Parameters of the analysis All the costs and benefits were valued in constant prices of the current year for the purpose of the economical and technical evaluation of the project. EGNATIA ODOS S.A. APRIL 2007 67 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The construction cost as well as the operational cost (expenses for the annual and periodical maintenance etc.), are considered as the costs of the project. Benefits include the reduction of the vehicles' operational cost, the reduction of the road accidents (benefits expressed in monetary values) and the reduction in travel time (taking into account the value of time). Tolls are examined only in the framework of the cash flow analysis and were not taken into consideration in the economic analysis for the calculation of the Internal Rate of Return (IRR) and the Net Present Value (NPV). Benefits and expenses should be valued using economic (real) prices, i.e. the market prices (monetary prices), according to the approved specifications of the Ministry of Environment, Physical Planning and Public Works concerning feasibility studies for road projects in Greece (Approved Decision of the Direction for the Study of Highway Projects, DMEO/a/O/1885/8-7-1996, paragraph 5.2). Taxes, VAT, assets depreciation, employers' share etc., should be deducted from the market prices in order that economic indicators (IRR, NPV) will result from "clearly economic" prices. The construction cost included in the budget of the present study is reduced by 20% taking into account the above-mentioned directive. This reduction is considered that it includes the participation of the previously mentioned parameters in the budget of the construction projects. Economic prices are equal to financial prices minus taxes (20%), hence it is estimated as 80% of the financial prices. 6.1.1 Determination of expected cost elements The expenses which are associated to the under study project refer to the construction cost and to the maintenance and operational cost of the road (annual and periodical maintenance). 6.1.1.1 Construction cost The following presents the costs included in the budget of the project and which are associated with the improvement of the geometrical and operational characteristics of the road section under study. It must be clarified at this point that alternative D concerns the transformation of the existing road into separated motorway with a cross-section of 27.6m or 28.2m, guardrail that separates the two directions, and two lanes per direction (of 3.75m width each one), in the case of Alignment 1 (detail design) and in the case of Alignment 2 (preliminary design), respectively. Alternatives B and C are lower cost solutions with lower geometrical and operational characteristics (compared to Alternatives D), as described in Chapter 4. EGNATIA ODOS S.A. APRIL 2007 68 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The economic construction costs for Alternative D of each of the two alignments have been provided by the F.N.R.R. The economic construction costs of Alternatives B and C were estimated on the basis of the costs of Alternative D. Costs used in the economic analysis for each alternative are the following: Alignment 1 Alignment 2 Length (km) 32.15 28.05 Economic construction cost (€) Alternative B Alternative C 152,613,331 144,501,616 107,989,433 114,829,350 Alternative D 156,621,546 125,149,748 In the case of Alignment 1 the cost of Alternative C is 2.6% lower than the cost of Alternative D, while the cost of Alternative B is 7.7% lower than the cost of Alternative D. In the case of Alignment 2 the respective percentages are 8.25% and 13.7%. Comparing the costs of the base alternatives (D) of the two alignments, the cost of Alignment 2 is 25% less. The construction costs per kilometre are 4.9 mo€/km in the case of Alignment 1 and 4.5 mo€/km in the case of Alignment 2. For the alternatives of motorway construction the costs are distributed in time as follows: Alignment 1 Alignment 2 2008 17% 25% 2009 17% 40% 2010 17% 35% 2011 17% 2012 2013 17% 15% In operation 6.1.1.2 Operational expenses (annual and periodical maintenance) Alternative A: Existing M-1 road The last rehabilitation of the existing road was performed in 1990. According to the F.N.R.R., roads should be rehabilitated every fifteen years. Therefore, the upgrade of the existing road is considered that should take place immediately and such works should include the repair of damages, the pavement rehabilitation (surfacing), the rehabilitation of bridges and replacement and improvement of the traffic and technical equipment. In the 25-years study period the road should be rehabilitated after fifteen years, in 2023. The economic cost of upgrade works is estimated on the basis of unit costs provided by the F.N.R.R. for such works at 25,747,916 €. Concerning the annual economic cost for maintenance and operation of existing M-1 road in the entire period of analysis, it is estimated at 8,622 €/km, which results 308,961 €/year for the existing M-1 road (estimated on the basis of unit costs provided by the F.N.R.R.). EGNATIA ODOS S.A. APRIL 2007 69 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Alternatives B, C and D: Motorway construction The operational expenses taken into consideration are the following: the annual expenses of the road operation and maintenance (e.g., lighting, enforcement, road signing and marking, road equipment etc). the periodical maintenance expenses, which concern important maintenance interventions in the road network (e.g. new pavement). The economic cost of rehabilitation (periodical maintenance) works of the motorway used in the present study is based on the unit cost of 491,000 €/km estimated in the feasibility study for the “gorge” section between Grdelica and Grabovnica in Serbia [7]. For Alignment 1, taking into account the increased length of tunnels, this cost is considered to be 5% higher. Alignment 1 Alignment 2 Length (km) 32.15 28.05 Cost/ km 515,550 € 491,000 € Total Cost 16,574,933 € 13,772,550 € The unit cost of 22,000 €/km estimated in the feasibility study for the “gorge” section between Grdelica and Grabovnica in Serbia is used for the annual operation and maintenance costs of the motorway. As in the case of rehabilitation costs, it is considered that the operational and maintenance costs for the motorway in the case of Alignment 1 would be 5% higher. Alignment 1 Alignment 2 Length (km) 32.15 28.05 Annual cost per km 23,100 € 22,000 € Annual cost 742,665 € 617,100 € It is considered that rehabilitation will take place in 15 years after opening to traffic. More specifically, the years considered for the purpose of reconstruction are the year 2028 for Alignment 1 and the year 2025 for Alignment 2. 6.1.2 Determination of expected benefit elements Benefits result from: the reduction of the vehicle operational expenses the time savings due to travel time reduction and increase of operational speed the reduction in the cost of road accidents due to the reduction in the number of these accidents the residual (economic) value of the project Benefits that result from tolls are not considered in the economic analysis. The traffic volumes, which are associated to the section under study in each examined alignment/ alternative, are those that were forecasted as average of the operational period during the period of analysis. EGNATIA ODOS S.A. APRIL 2007 70 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Hereinafter, the description of the main parameters of the technical and economical analysis is presented. All the calculations of the analysis that are described below are presented in “special sheets of analysis” which are included in the Annex B of the present Technical Report. 6.1.2.1 Time savings For the assessment of the benefits due to time savings, the estimation of the mean operational speed of each section is based on the assumption, based on experience gained from other projects, that it represents on average the 80% of the free flow speed. For light vehicles it is considered that: mean speed of 48km/h corresponds to maximum (cruising) speed of 60km/h; mean speed of 65km/h to maximum speed of 80km/h; mean speed of 80km/h to maximum speed of 100km/h; mean speed of 90km/h to maximum speed of 110km/h; and mean speed of 95km/h to maximum speed of 120km/h. For heavy vehicles the above values are reduced by 15%. It is assumed that mean speed will remain relatively stable throughout the analysis period, given the fact that at motorways – especially low traffic motorways, mean speed is reducing very slowly in time, still not affecting the V/C ratio for Level of Service C (0.5). The following tables present the running times for light vehicles in each alternative examined: Alternative A Existing M-1 road Sub-section Demir Kapija – Udovo Udovo – Smokvica Total Average operational speed (km/h) 56 65 59.1 Length (km) Running time (min) 22.27 13.564 35.834 23.9 12.5 36.4 Upgraded existing M-1 road For the examination of Alternative A, the upgrade of the existing M-1 road is assumed that would result an increase of operational speed by 10%, thus operational speed in that case along the entire section would be 65km/h and the respective running time 33.1 minutes. EGNATIA ODOS S.A. APRIL 2007 71 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Alternatives B and C Alignment 1 Sub-section Demir Kapija – Udovo Udovo – Smokvica Total Average operational speed (km/h) 76.6 90 81.2 Length (km) Running time (min) 19.9 12.25 32.15 15.6 8.2 23.8 Alignment 2 Section Demir Kapija – Smokvica Total Average operational speed (km/h) 90 90 Length (km) 28.05 28.05 Running time (min) 18.0 18.7 Alternative D Alignment 1 Sub-section Demir Kapija – Udovo Udovo – Smokvica Total Average operational speed (km/h) 76.6 95 82.7 Length (km) Running time (min) 19.9 12.25 32.15 15.6 7.8 23.4 Length (km) Running time (min) 28.05 28.05 17.7 17.7 Alignment 2 Section Demir Kapija – Smokvica Total Average operational speed (km/h) 95 95 6.1.2.2 Benefits form the vehicle operational costs reduction Benefits from the reduction of the vehicle operational cost come from the comparison made with and without the project: Fuel savings Savings due to the fact that vehicles will cover fewer kilometers in the road network and thus they will be used for less time (this leads to the fact that the vehicle will not lose its value so fast as in the past) The parameters that were taken into consideration for the analysis of these three categories are presented in the following: EGNATIA ODOS S.A. APRIL 2007 72 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Fuel savings It is considered that fuel savings are due to improvements of the road operational characteristics. The conditions of driving will change in the case of a motorway compared to the case of the existing situation (driving in quite difficult conditions will be replaced by driving under good conditions). This saving is estimated to be equal to 0.01 lt/veh*km for the passenger cars and 0.02 lt/veh*km for the diesel trucks and Heavy Goods Vehicles (HGVs). These values resulted from the examination of the vehicles' manufacturer specifications (official documents from vehicle manufacturers concerning representative passenger cars and HGVs). The cost of the unleaded petrol is considered equal to 0.97 €/litre and the cost of diesel is considered equal to 0.81 €/litre. These values are the current market prices in the Former Yugoslav Republic of Macedonia. The use of these values was preferred to cover the possibility of increase, which does not follow inflation, but depends mainly to world oil market and to political decisions. Savings due to distance reduction It is considered that part of the operational cost depends on the distance covered by the vehicle (that is to say is proportional with the distance). The value of vehicle operation for passenger cars is considered equal to 0.03 €/veh*km. This value is based on the approved specifications of the Ministry of Environment, Physical Planning and Public Works concerning feasibility studies for road projects in Greece. Savings due to the reduction of time at which vehicles are in operation It is considered that part of the vehicle operational cost depends on the time spend to cover the distance. The value of the vehicle operation (as far as time is concerned) is considered equal to 0.08 €/veh*hour for passenger cars and 0.09 €/veh*hour for trucks. These values are based on the approved specifications of the Ministry of Environment, Physical Planning and Public Works concerning feasibility studies for road projects in Greece. 6.1.2.3 Benefits from time savings as far as the vehicle users are concerned In order to calculate the time savings (and express them in monetary values) for the vehicle users, the expected value of the average hourly income in the country is used according to the approved specifications of the Ministry of Environment, Physical Planning and Public Works concerning feasibility studies for road projects in Greece. In the framework of the present study the value of time for different trip purposes are considered, based on the estimation performed in the feasibility study for Tabanovce – Kumanovo motorway in January 2007, that the value of time for a business trip is 2.35 €/hour. On the basis of this value, a working hour rate of 3.40 €/hour was estimated to represent the average values of working time during the operational period for each motorway alternative, considering an annual increase of income by 2%. EGNATIA ODOS S.A. APRIL 2007 73 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The following values are formulated: for trips made in the framework of work (e.g., salesman) and for professional drivers the value of time is considered equal to 3.40 €/hour for trip purpose “to and from work” the value of time is considered equal to 1.70 €/hour (which is equal to 50% of the average daily salary) for trips with other purposes is considered equal to 0.85 €/hour Vehicle occupancy rates taken into consideration in the framework of the present study are: Vehicle type Passenger cars Vehicle occupancy 2 Trucks 1.2 Buses 45 Trip purpose To and from work, in the framework of work, other purposes In the framework of work To and from work, in the framework of work, other purposes The following table presents the % distribution of trip purpose (all trip purposes are concerned) in respect to the vehicle type, as it was taken into consideration in the respective calculations. Vehicle type Passenger cars Trucks Buses Trip purpose 35%: to and from work 45%: in the framework of work & professional drivers 20%: other purposes 100 %: in the framework of work 65%: to and from work 5%: in the framework of work & professional drivers 30%: other purposes 6.1.2.4 Benefits from the reduction in the number of road accidents The values of human life cannot be expressed in monetary terms. However, the very important problem of road safety worldwide led to the establishment of various approaches for the estimation of the consequences from the loss of a life in road accidents. These approaches are based on various parameters such as lost production, the funeral expenses, the human pain etc. Another approach is based on the amount of money the insurance companies pay or the juridical decisions for compensation because of fatal road accidents. The value of human life in the developed countries can range from a minimum of 400,000 € and can reach even 2,000,000 €. Medical expenses, pain and loss production must be expressed in monetary values in the case of injuries which take place in traffic accidents. Pain can constitute up to 50% of the total expenses associated to an injury. The estimation of loss of production is based on the conditions concerning the injured person that existed before the accident. The average cost of a light injury in a traffic accident is estimated to be in the area of 15,000 – 20,000 € in Great Britain. EGNATIA ODOS S.A. APRIL 2007 74 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The Faculty of Transport and Traffic Engineering of the University of Belgrade estimates that motorway projects result a 40% reduction in the number of traffic accidents, based on their experience from other motorway projects in Serbia. This moderate percentage of reduction is also used in the current study (in cases of motorway construction in other European countries the percentage of reduction is between 50 and 70%). For the alternatives of motorway construction with narrower cross sections the reduction of accidents applied in the economic analysis is the same, since it is considered that the separation of opposite direction traffic is the main factor for accidents reduction. Road safety is subjected to the geometry of each alternative, and therefore narrower cross sections (and traffic lanes) could have lower accident savings. Apart from the fact that this effect is not quantifiable, it is also considered very small to affect the economic analysis and therefore the same percentage of accidents reduction is used for all the motorway alternatives in the present study. For the estimation of the benefits due to the reduction of accidents after the realisation of the project, unit costs per type of accident are used. Considering the fact that the motorway users are partially EU nationals and locals, the European unit costs could not be applied directly to the number of accidents. The unit costs used in the current study are half of the European with the assumption that 20% of the road users are EU residents. The assumption that international transit traffic is 20% of the total traffic is based on the statistics of entrances and exits at border crossing Bogorodica. The unit costs are calculated with the multiplication of the estimated value of one hour of business travelling (3.40 €/h) by the following factors: for deaths: 43,000 for heavy injuries: 5,100 for light injuries: 400 The above factors are recommended by the United Nations Economic Committee for Europe (UNECE) recommendations through the report “A Set of Guidelines for socioeconomic cost – benefit analysis of transport infrastructure project appraisal“ (2003) in the case of lack of reliable data. The unit costs per type of accident are presented in the following table: Type of accident Fatal accidents Accidents with severe injuries Accidents with light injuries Accidents with damages * Source: [6] EGNATIA ODOS S.A. APRIL 2007 Average unit cost in European countries* 1,000,000 € 125,000 € 38,462 € 4,739 € Accident unit cost in F.Y.R.O.M. 146,200 € 17,340 € 1,360 € 170 € Accidents unit cost used in the study 316,960 € 38,872 € 8,780 € 1,084 € 75 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The unit costs used in the present study are weighted values according to the proportion of domestic and international traffic (80% - 20%, respectively). Concerning the estimation of the number of accidents in the base year 2007 along the section under study, it was based on the indices extracted based on the registered accidents in 2005 along the M-1 road in Serbia between Grabovnica and F.Y.R.O.M. borders, and more specifically, on the Grdelica “gorge”, a national road with very similar characteristics, as well as drivers’ behaviour. The number of accidents used for the base year 2007 is estimated with the assumption of low increase of accidents by 2% annually. In the following table, the annual numbers of various types of accidents per kilometre are presented: Annual number per km Accidents with damages only Fatalities Serious injuries 0.58 0.04 Light injuries 0.06 0.47 In order to compare the benefits due to reduction of accidents costs after the project realisation the projection of accidents during the analysis period was performed. The annual growth factor of 2% was also used for this projection. The use of this relatively low growth factor is based on the assumption of conservative accidents increase due to the annual increase of traffic and therefore increased density and lower operational speeds which result lower accidents probabilities. This low factor was also preferred in order to avoid overestimation of the benefits from accidents reduction. The number of accidents according to their severity used in the present study are the following: Average annual number of accidents with damages only 27 Average annual number of fatalities Average annual number of serious injuries 2 Average annual number of light injuries 3 22 6.1.2.5 Residual value of the project The residual value of the project is estimated using the following formula: Y = (A/X)*(X-v)*f that is determined by the respective specifications and the bibliography. In the above formula: A is the initial value of the project, X is the duration of the physical life of the project, v is the period of analysis EGNATIA ODOS S.A. APRIL 2007 76 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X f is a coefficient which is equal to one or smaller than one and which expresses the estimate for the usefulness of the project after the expiration of its economic life. It provides significant margins for the estimations. The duration of the physical life of the various elements of the project is considered to be equal to: 40 years for earth works and pavement/asphalt works 75 years for the bridges and tunnels 30 years for the road equipment (lighting, vertical signing) The period of analysis, as it was mentioned above, is considered to be equal to 25 years and the value of the coefficient f is considered to be equal to one for all the categories. Residual value of the project for the various motorway construction alternatives (economic prices) is presented in the following table. Alignment Alignment 1 Alignment 2 Alternative B 88,692,519 62,611,109 Residual value (€) Alternative C 93,913,740 66,537,951 Alternative D 96,413,585 72,278,632 6.1.2.6 Installation and operation of toll stations The case of tolls introduction, as it was mentioned above, was taken into consideration for the purposes of the financial analysis only. The road pricing system to be used in the immediate forthcoming years will be open. Through a loan of the World Bank an EU interoperable system will be introduced, which foresees three passing lanes per direction: one for cash payment, one for prepayment and one for transmitters usage. The construction cost of one toll station of the new toll system according to the F.N.R.R. is 650,400 € and its annual operational cost for personnel, maintenance etc. is estimated at 100,000 €/year, while for the existing system it is around 200,000 €/year. The installation of tolls is considered to be the last year of construction. The revenues from the operation of the toll station begin from year 2011 in the case of new alignment and from year 2014 in the case of the alignment of the detail design. Details concerning road pricing in F.Y.R. Macedonia and toll revenues estimations from the project are described in Chapter 6.3.1. 6.1.3 Consideration of elements which cannot be quantified 6.1.3.1 Consumer surplus Additionally to the benefits mentioned in the above and were included in the economic analysis of the project, benefits of consumer surplus are also expected. The consumer surplus benefits come from the additional traffic after the project realisation and apply both for new passenger and freight traffic. EGNATIA ODOS S.A. APRIL 2007 77 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X In the present study there are no secure information concerning the private (social) cost in the F.Y.R. of Macedonia, and therefore consumer surplus benefits are not quantified and hence were not included in the economic analysis. Higher values of the economic indices would be expected if those benefits were included in the economic analysis. 6.1.3.2 Spatial and regional development aspects The project is situated along the Pan-European Corridor X, backbone of the Southeast Europe Transport Core Network and of the South-eastern Axis, as defined by the High Level Group of the Directorate General for Energy and Transport of the European Commission. The realisation of the project would mean the completion the road Corridor X main axis in the Former Yugoslav Republic of Macedonia, given the under-way realisation of the Tabanovce – Kumanovo motorway section, and will offer efficient infrastructures with substantial time and vehicle operating costs savings. It would maximize the benefits along the entire Corridor X by improving the level of service, ensuring at the same time homogenous infrastructure and operation, facilitation of international passengers and trade flows, including transit traffic, if also accompanied with measures for border crossing facilitation. Therefore, the project would contribute to the better connection of major urban, industrial and commercial centres along Corridor X, to the improvement of economic exchange and cooperation between these centres, and also to the strengthening of the multilateral relations between the countries of the wider region of the Balkans and their residents. Furthermore, the project would contribute to regional development and cohesion in the weaker, “less favoured”, wider area of the Western Balkans, promoting the level of access of the Former Yugoslav Republic of Macedonia from the south with Greece, and give access to the port of Thessaloniki. The project should be considered, if it is not already, as a basic component of an integrated national strategy, which comprises measures and policies for regional and spatial development. 6.1.3.3 Employment impacts According to other motorway construction projects, 45% of the economic cost of the project concerns labour costs and the rest 55% material costs. Furthermore, 30% of the material costs refer to imported stock (machinery and equipment) and 70% to domestic material. Monthly gross average income for specialised and non-specialised work in the F.Y.R. of Macedonia is 390 € and the respective annual average income is estimated at 4,680 €. EGNATIA ODOS S.A. APRIL 2007 78 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Based on the above-mentioned assumptions, and after deducting the land acquisition cost from the economic cost of the project, the number of jobs created directly or indirectly during the construction period is possible. During the operational period of the project, costs refer to maintenance material for periodical pavement, signs and medians replacement and signalling, whilst operational costs refer to electric lighting and irrigation. Direct employment Direct employment is expressed by the number of direct employees during the construction and operation/ maintenance of the project. Jobs are estimated as equivalents of labour costs. Differences appearing between the estimations for the two alignments are due to the different construction and operational periods. For the construction period direct employment is estimated by the division of 45% of the economic construction cost by the annual average income, at 13,150 man-years for Alignment 1 and 11,150 man-years for Alignment 2. For the construction period of each one of the two alignments, the number of jobs created are estimated based on the estimated average annual income of the period respective periods 2008 – 2013 and 2008 – 2010. The estimation of the average annual income of the period is performed with the projection of current net income with foreseen growth of 2% (recorded in the last years) at 5,170 €. The number of jobs created is estimated around to 2,190 jobs in the case of Alignment 1 and around to 3,700 jobs in the case of Alignment 2. The reason that the number of jobs created in the case of Alignment 2 is higher is the shorter (half) construction period. For the operation/ maintenance period direct employment is estimated by the division half of the economic annual maintenance cost by the annual average income, to 55 jobs for Alignment 1 and 45 jobs for Alignment 2. Further labour needs are also expected for the periodical maintenance of the motorway during the period of analysis. Rough estimation of the expected employment anticipated for such works is 1,100 man-years during the period of analysis in the case of Alignment 1 and 900 man-years in the case of Alignment 2. Indirect employment Apart from the direct employment anticipated during the construction and operation of the motorway, indirect employment is also expected in terms of increase of labour force employment at enterprises providing material and equipment during the construction and operation/ maintenance of the project. Additional employment is also expected after the operation of the new motorway and development of the related facilities such as motels, petrol stations, garages etc. Indirect employment due to the increase of labour force employment at enterprises providing material and equipment during the construction and operation/ EGNATIA ODOS S.A. APRIL 2007 79 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X maintenance of the project, as well as indirect employment due to the creation of future incomes and the caused trend for reinvestment, consisting additional employment for the entire life of the project, are not examined in the present study. 6.2 Environmental considerations There are numerous sensitive ecosystems, biotopes and localities along the existing axis of the project. In the previous feasibility study, Scetauroute International estimated their degree of sensitivity according to several criteria. The following description of the sensitivity of ecosystem, biotopes and localities are borrowed from the previous feasibility study and they should be taken into high consideration: River Boshava: It is important because specific algal communities (especially diatom) communities differentiate this river form the other rivers along the axis of the project. Irrigation value of lower flow of the river for Demir Kapija is very high, so any kind of pollution or destruction due to motorway construction/ operation should be avoided. River Anska and channels: They have extraordinary value for irrigation purposes in the Valandovo valley. The riverbed is channelled and many additional channels are connecting the Vardar and Anska Rivers, creating a sort of a network. River Petrushka: It is very important for the area around the villages of Miravci and Miletkovo. It is divided into numerous channels in the lower flow. Beside the economic value, it has biodiversity importance, since the best plane (platanus orientalis) community (real forest) is developing on a broad area in the lower flow of the river. The algal community and presence of rare species is also evident. Stagnant waters: They are very rich concerning species composition and particularly in the region of villages Davidovo and Miravci they are represented with well preserved aquatic communities. Their special importance comes from the fact that such ecosystems are endangered in the Former Yugoslav Republic of Macedonia. Alluvial deposits: Their special characteristics arise from their importance in the Demir Kapija gorge concerning the agricultural use. They are the only areas in the gorge where agricultural activities are possible. Sandstone cliffs: They are very interesting from archaeological point of view, but they are even more important as nesting places for numerous Merops apiaster populations. Spring tapes and wells: They are extraordinary important since the area of the project axis is characterised by the long dry period and quantity and quality of drinking water is not sufficient. Hot water springs: They are very particular phenomenon and they have extremely high economic value. Demir Kapija canyon: It is a protected area since 1960 in the category Monument of Nature (III category according to the International Union for the Conservation of Nature and Natural Resources – IUCN). It has extraordinary importance from the biodiversity point of view. River Iberliska: It is water gap cut into Demir Kapija Jurassic limestone. It is protected since 1963 as a category individual plant and animal species outside of natural reserves. Bela Voda cave: It is the longest cave in the Former Yugoslav Republic of Macedonia (955m). Plain woodland belts: They are the only high tree sites in the region of Demir Kapija gorge. They are characteristic for almost all dales and ravines on both slopes along the Vardar River. EGNATIA ODOS S.A. APRIL 2007 80 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Plain woodlands and forests: These biotope types are characteristic for the Valandovo – Gevgelija valley, especially for the lower flow of the rivers and springs in that area. Beside natural value they have economic value as well. Willow and plain forests: They have extraordinary importance. They are especially characteristic for the surrounding of village Grchishte (left side of river Vardar). They represent the remains from the real river bank vegetation, characteristic for the undisturbed sites along the river, which are almost absent nowadays. Dense pseudomaquis biotope type has low economic value particularly for the local population. It is important because it represents the real appearance of this type of shrubland community. Many rare species have found suitable habitat in this ecosystem. Sparse pseudomaquis has been changed due to the pronounced anthropogenous influence. It has even less (if any) economic value than the previous mentioned biotope, but rare species (like Canis aureus, Ophiosaurus apodus etc.) are present. Tamaris communities: There are many well preserved communities of tamaris along the lower part of the road, especially along the river Vardar. They are high sensitive since they are rare types of vegetation, due to their transformation into cultivable land. They should be protected since their abundance of rare species of fungi, plants and animals. Agricultural land: The term refers to high productive land (fields, gardens, meadows) in the Gevgelija – Valandovo valley. Its extraordinary importance comes from possibility for making two crops per year. Poplar plantations: These plantations are well developed and they have great economic value. Vineyard plantations are very important part of the local population activity. They are very characteristic for the area of the road corridor. Greenhouses represent one of the most important branches of economic activities in the area from Udovo to Gevgelija. Eolian soils: The only soils of this type in the Former Yugoslav Republic of Macedonia are represented next to the Vardar River, between villages Grchishte and Gjavoto, on the left side of the river. They are covered with Tamaris shrubland vegetation with different density. Surrounding of Udovo and Davidovo villages: The high sensitivity of this area arise form the presence of several valuable localities: archaeological locality “Turski grobishta” (Turkish graveyard), historic localities – chapel above the village Udovo and St. Ilija church above the village Davidovo. There is also well developed Tamaris community with rare species of fungi and swampy area close to the existing bridge on Vardar River. Archaeological localities Hisarkale, Dolna Crkva, Mramorot and Manastir are of extreme importance since they represent remains of antic (Roman or Greek) period. Some of them contain well preserved objects. Historic locality Church near the village Gradec and archaeological sites Tufka and Agova Cheshma – Vetka Crkva are less sensitive (but high) than previous localities, since they contain less archaeological material and the church is of a more recent time. Anyway, any direct interference with these objects during construction works should be strictly forbidden. The above description is intentionally not presented in the Annex of the current report. The purpose is to emphasise the sensitivity of the project area and its environmental importance. EGNATIA ODOS S.A. APRIL 2007 81 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Furthermore, and according to the Central & Eastern Europe, Caucasus, and Central Asia Environmental Information Programme the Demir Kapija gorge is among the richest ornithological reserves in Europe. The rare birds of pray include: griffin vulture (Gyps fulvus), Egyptian vulture (Neophron percnopterus), golden eagle (Aquila chrysaetos), shot-toed eagle (Circaetus gallicus), long-legged buzzard (Buteo rufinus), and different falcons (Falco peregrinus, Falco naumanni). Other rare and scientifically important bird species are also present in this area. In the Demir Kapija gorge, important mammal, reptile, and insect species are present as well as rare and endemic plant species (Caladonia macedonica, Lilium: heldreichii, Lilium martagon, Kitaibelia vitifolia etc.). Up to the day of completion of the present study the results of the assessment of the environmental impacts for the two motorway alignments have not been available, nor the costs for environmental mitigation measures, which were not included in the costs of the projects examined. In any case, it should be mentioned that according to the designers of Alignment 2 on the west side of Vardar River, this solution is considered more environmentally friendly compared to Alignment 1. The design of Alignment 2 avoids big cuts and embankments, sites of archaeological interest and the offence of Bela Voda Cave, while it has no conflict with a future dam to be constructed in Vardar River. 6.3 Financing aspects The financing of the project is under negotiation between the governments of the Former Republic of Macedonia and Greece, through a grant of maximum € 50 million by the Hellenic Plan for the Economic Reconstruction of the Balkans (Hi.P.E.R.B.). The financial plan of the project as initially presented by the local government involves funds from the Instrument for Pre-accession Assistance (IPA) of the European Community, own funds and the maximum of potential grant by the Greek government: HiPERB: 50 mil EUR and budget co-financing for HiPERB (10%) – 5 mil EUR IPA – 32 mil EUR and budget co-financing for IPA (25%) – 10,6 mil EUR, i.e. total of 97,6 mil EUR (82 mil EUR donations and 15,6 mil EUR co-financing from the national budget, according for the rules for awarding of certain donations), as follows: Source IPA 2007-2008 National contribution to IPA 2007-2008 Hi.P.E.R.B. National contribution to Hi.P.E.R.B. Total EGNATIA ODOS S.A. APRIL 2007 Amount (mo€) 32.0 10.6 50.0 5.0 97.6 82 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X According to the F.Y.R.O.M. Secretariat for European Affairs, IPA foresees financing of projects at 80% of Package III (Transport and Environment); that is the case for IPA 2007-2008, where, out of € 40 million, € 32 million were committed to Corridor X project as a first priority transport project in the country. Therefore, the rest of the required funds could be covered by the next IPA Package III in 2009, with potential of securing a respective amount to that of IPA 2007-2009. Taking into account the above considerations, the potential maximum financial plan without loans could be: Source IPA 2007-2008 IPA 2009 Subtotal IPA funds Hi.P.E.R.B. National contribution to Hi.P.E.R.B. National contribution to IPA 2007-2008 National contribution to IPA 2009 Subtotal national contribution Total Amount (mo€) 32.0 32.0 64.0 50.0 5.0 10.6 10.6 26.2 140.2 Therefore, the above financial plan could be sufficient for the realization of the project on the west bank of River Vardar, without need of loans. In line with the afore-stated and the initial analysis of the amount of finances needed for the project, in the case of need for additional finances, it is suggested by the F.Y.R. of Macedonia government that the financial construction would be completed with a loan from the European Investment Bank (EIB), as a financial institution for suitable for this purpose (offering the most compatible conditions for procurement and other conditions with the conditions of the afore-mentioned donations). 6.3.1 Toll revenues Tolls in the F.Y.R. of Macedonia are collected on the motorways of the country. According to the F.N.R.R. a new system for automatic collection of tolls will be introduced in toll booths on the highways across the country in 2007. The project is supported by the World Bank and the USAID and is foreseen to become fully operational in early 2008. Three lanes will operate per direction at the toll booths. One lane will be for cash payments, another for pay cards and the last for transmitters. According to the F.N.R.R. experts, the cost of construction of a toll booth is € 650,400 and the annual operation and maintenance cost is € 100,000 (reduced by 50% compared to existing costs after the introduction of the new toll system). EGNATIA ODOS S.A. APRIL 2007 83 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Vehicle classification Vehicle classification is performed according to the number of axles and the vehicle height on the first axle into four classes: Category I height below 1.7m, length less than 5.5m: passenger cars and motorcycles Category II height below 3.3m, length less than 9.5m: passenger cars with trailers, jeeps, mini buses and light trucks Category III height below 4.2m, length less than 10.5m: vehicles with trailers, trucks with 3 axles and midi buses Category IV height over 4.2m, length more than 10.5m: tractors with more than 3 axles and buses Toll rates applied are the same for domestic and foreign registered vehicles. The following table details the payments in Denars at the four toll stations along Corridor X in the Former Yugoslav Republic of Macedonia: Road section Station name Vehicle Category I II III IV EGNATIA ODOS S.A. APRIL 2007 Kumanovo – Miladinovci Petrovec – Veles Veles – Gradsko Romanovci Sopot Otovica Stobi 50 75 145 290 80 115 230 460 80 115 230 460 60 90 175 345 84 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X The toll rates used in the present study for the estimation of the annual cash flows are estimated on the basis of charge of the above table. More specifically, the charges per kilometre were calculated for the tolled motorways, presented in the following table: Length (km) Kumanovo - Miladinovci 21.782 Veles - Petrovec 34.136 Veles - Gradsko 25.139 Total 81.057 Average charges Section Charges per kilometre (€) I II III 0.038 0.056 0.109 0.038 0.055 0.110 0.039 0.059 0.114 IV 0.218 0.220 0.224 0.038 0.221 0.056 0.111 On the basis of charging 0.04 €/km for vehicles of category I, using the existing ratios between charges of category I and the rest of the categories, the following charges are calculated: Vehicle Category I II III IV Road pricing 0.04 €/km 0.06 €/km 0.12 €/km 0.23 €/km As a conclusion, it can be expected that traffic growth and the application of the above toll rates will ensure high revenues during the project lifetime, taking into consideration that apart from the toll station at Demir Kapija, another toll station is foreseen to be established, probably at Gevgelija. Therefore, revenues are expected to be more than double, considering the higher traffic as moving close to the Greek border, especially after Prdejci (south of Smokvica). Finally, it should be mentioned once more, that the toll revenues are not included in the economic analysis of the project, since it is considered that they are compensated by their inclusion also in the generalised (operational) cost as user charge. 6.3.2 Cash flow The cash flow diagram for each is formulated for each of the two alternative alignments examined, taking into account the following parameters in various time horizons until 2032: Annual construction costs Costs of tolls installation Annual operational and maintenance costs Annual toll station operation and maintenance cost Annual revenues from tolls collection Periodical maintenance/ rehabilitation after 15 years of start of operation EGNATIA ODOS S.A. APRIL 2007 85 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Cash flow diagramme 15 10 5 2030 2028 2026 2024 2022 2020 2018 2016 2014 2012 2010 -5 2008 Million euros 0 -10 -15 Costs -20 Revenues -25 Cash flow -30 Year Graph 6.1: Cash flow diagram Alignment 1 Cash flow diagramme 20 10 Million euros 2030 2028 2026 2024 2022 2020 2018 2016 2014 2012 2010 -10 2008 0 -20 -30 -40 Costs Revenues -50 Cash flow -60 Year Graph 6.2: Cash flow diagram Alignment 2 EGNATIA ODOS S.A. APRIL 2007 86 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X In the Cash flow diagrams the reduction in the columns of the years 2025 and 2028 are due to the periodical maintenance costs. Also, the cash flow does not include Hi.P.E.R.B. financial aid and IPA funds. It can be commented that toll revenues in the analysis period ensure the cover of the annual maintenance and operational expenses and the costs for periodical maintenance of the motorway. Furthermore, as previously mentioned, the introduction of a second toll station in the southern section between Gevgelija and Smokvica, will ensure high (more than double) revenues. 6.4 Results of the economic analysis The results of the economic analysis of the project are presented in Annex B of the present technical report. The discount rate (the rate by which the costs and benefits are reduced or discounted each year when estimating the net present value [19] used in the present study in order to estimate the NPV is considered to be 8%. It is considered that this value diachronically express the opportunity cost of capital (the minimum rate of return required above which it is worthwhile, and below which is not worthwhile investing capital in a project. This is defined by the rate of return of the best project which could be financed if, but only if, the project does not proceed. Hence, the phrase opportunity cost of capital [19] in the F.Y.R. of Macedonia. The opportunity cost of capital is considered to be equal to the average bank long term interest rate return plus the inflation. The inflation rates in the period 1999 – 2006 as reported by the National Bank of F.Y.R. of Macedonia are the following: Period Inflation rates 1999 -1.0% 2000 6.0% 2001 5.0% 2002 2.0% 2003 1.2% 2004 -0.4% 2005 0.5% 2006 2.9%* Source: National Bank of F.Y.R. of Macedonia (April 2006) * Estimation The target for the year 2006 was for inflation to be retained at 1.8%. As for deposit interest rates, the National Bank of F.Y.R. of Macedonia reports that the nominal deposit interest rates in 2005 was between 5 – 5.5%, while in 2006, according to the U.S.A. embassy in Skopje [20], it was 4.6% (August 2006). EGNATIA ODOS S.A. APRIL 2007 87 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X It must be stressed at this point that the project evaluation should not be focused so much in the NPV but in the efficiency of the project based on the IRR (from where concrete results can be derived concerning the investment attractiveness). Additionally to the use of the discount rate of 8%, the projects in the present study are examined also with the use of other, lower discount rates of 2%, 4%, and 6%, in order to cover the case of improvement of the economy of the Former Yugoslav Republic of Macedonia, as well as to examine the impact of lower discount rates to the results of the economic analysis. In the following tables, the results of the economic evaluation of the project are summarised: Alignment 1 Alternative A (do minimum) Alternative B Alternative C Alternative D IRR (%) Not defined 2.33% 2.05% 1.91% B/C (2%) B/C (4%) B/C (6%) B/C (8%) 0.19 0.15 0.12 0.10 1.09 1.01 0.98 0.71 0.66 0.64 0.52 0.48 0.47 0.40 0.37 0.36 IRR (%) Not defined 7.06% 6.49% 5.87% B/C (2%) B/C (4%) B/C (6%) B/C (8%) 0.19 0.15 0.12 0.10 2.31 2.15 1.98 1.54 1.44 1.32 1.14 1.06 0.98 0.90 0.84 0.77 Alignment 2 Alternative A (do minimum) Alternative B Alternative C Alternative D The costs and benefits breakdown of the project, indicatively for the Alternative D, are presented in the following graphs for each of the two alignments. It can be commented that in the case of Alignment 1 the percentage of the residual value appears to be the most important benefit of the project (40%), since all other benefits are lower (time savings, vehicle operational costs reduction), due to the small reduction in the length of the proposed alignment compared to that of the existing road. On the contrary, in the case of Alignment 2, where the length of the proposed motorway is much shorter than the existing road, the benefits due to time savings and due to vehicle operational costs reduction are substantial and therefore their shares in the benefits breakdown are higher, reducing the residual value’s share at 24%. EGNATIA ODOS S.A. APRIL 2007 88 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Alignment 1 Operational cost 16% Construction cost 84% Graph 6.3: Costs breakdown of the project (Alignment 1 – Alternative D) Benefits from vehicle operational cost reduction 34% Benefits from time savings 23% Residual value 40% Benefits from accidents reduction 3% Graph 6.4: Benefits breakdown of the project (Alignment 1 – Alternative D) EGNATIA ODOS S.A. APRIL 2007 89 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Alignment 2 Operational cost 18% Construction cost 82% Graph 6.5: Costs breakdown of the project (Alignment 2 – Alternative D) Benefits from vehicle operational cost reduction 46% Residual value 24% Benefits from accidents reduction 2% Benefits from time savings 28% Graph 6.6: Benefits breakdown of the project (Alignment 2 – Alternative D) 6.5 Sensitivity analysis – Comparative evaluation of alternatives and ranking From the comparison of the results of the economic analysis of the alternatives examined within the study, the lowest cost alternative of motorway construction is ranked first. Apparently, the variations between the results of the three motorway construction alternatives are marginal due to the fact that in the case of the lower cost alternatives B and C the benefits are decreased as result of the speed reduction. Furthermore, a sensitivity analysis can be conducted of any problem to explore the effects of deviation from the original problem conditions. Since most engineering economic problems extend over a period of years, future cash flows are necessarily EGNATIA ODOS S.A. APRIL 2007 90 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X estimated. These estimations may be quite reliable, but it is often enlightening to observe how the attractiveness of alternatives varies as the initial estimates are altered [13]. The results that are presented in the sensitivity analysis in the framework of the present study were based on a number of assumptions concerning the necessary parameters. The elasticity of results concerning changes (marginal or not) in the values of basic parameters like the cost of the investment and the operational expenses and revenues is examined through the sensitivity analysis. Accordingly the undertaken risk concerning the specific investment is evaluated with the aid of the sensitivity analysis. The parameters that are examined in the sensitivity analysis include: The construction cost of the project The traffic flows The operational cost of the project The discount rates used in the sensitivity analysis include 8%, 6%, 4% and 2%. The alterations of the basic parameters, which are examined in the framework of the sensitivity analysis, are as follows: Alterations of the constructional cost by ±10% Alterations of traffic volumes (demand) by ± 10% and by ± 20% Alterations of the operational cost (annual and periodical maintenance) by ±10% The following tables present the results of the sensitivity analysis (actually the impact to IRR and the Net Present Value) of the project for the Do minimum alternative and for the three motorway alternatives of each motorway alignment. Alternative A Basic scenario Negatives Increase of construction cost by 10% Increase of operational cost by 10% Reduction of traffic volumes by 10% Reduction of traffic volumes by 20% Positives Reduction of construction cost by 10% Reduction of operational cost by 10% Increase of traffic volumes by 10% Increase of traffic volumes by 20% EGNATIA ODOS S.A. APRIL 2007 2% -16,380,539 NPV (€) 4% 6% -18,217,989 -19,168,114 8% -19,589,010 -18,880,096 -17,205,014 -17,595,692 -18,810,845 -20,646,139 -18,850,740 -19,167,336 -20,116,683 -21,528,416 -19,661,395 -19,924,908 -20,681,702 -21,884,778 -19,979,461 -20,203,537 -20,818,064 - -13,880,983 -15,556,065 -15,165,387 -13,950,234 -15,789,839 -17,585,239 -17,268,642 -16,319,295 -16,807,812 -18,674,833 -18,411,320 -17,654,525 -17,293,243 -19,198,560 -18,974,484 -18,359,957 - IRR - 91 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Alignment 1 Alternative B Basic scenario Negatives Increase of construction cost by 10% Increase of operational cost by 10% Reduction of traffic volumes by 10% Reduction of traffic volumes by 20% Positives Reduction of construction cost by 10% Reduction of operational cost by 10% Increase of traffic volumes by 10% Increase of traffic volumes by 20% NPV (€) 4% 6% -27,013,094 -47,430,231 8% -59,456,895 2.33% -6,578,438 5,219,976 -3,569,884 -14,064,771 -39,662,144 -28,217,107 -34,837,842 -42,662,589 -59,306,038 -48,293,649 -53,359,909 -59,289,586 -70,631,005 -60,085,666 -64,019,017 -68,581,139 1.70% 2.25% 1.83% 1.30% 20,428,446 8,630,032 17,419,892 27,914,779 -14,364,044 -25,809,081 -19,188,346 -11,363,599 -35,554,425 -46,566,814 -41,500,554 -35,570,877 -48,282,785 -58,828,124 -54,894,774 -50,332,652 3.05% 2.42% 2.83% 3.32% NPV (€) 4% 6% -33,220,670 -53,644,360 8% -65,523,614 2.05% -13,243,110 -837,556 -9,476,528 -19,971,416 -46,579,784 -34,531,233 -41,045,418 -48,870,165 -66,186,824 -54,584,186 -59,574,037 -65,503,715 -77,324,992 -66,208,029 -70,085,736 -74,647,858 1.42% 1.96% 1.56% 1.06% 15,279,828 2,874,275 11,513,247 22,008,135 -19,861,556 -31,910,108 -25,395,922 -17,571,175 -41,101,896 -52,704,534 -47,714,682 -41,785,005 -53,722,237 -64,839,200 -60,961,493 -56,399,371 2.75% 2.13% 2.52% 2.99% 2% -2,072,072 NPV (€) 4% 6% -36,349,902 -56,714,117 8% -68,486,440 1.91% -16,708,102 -4,154,319 -12,706,436 -23,340,800 -50,059,878 -37,820,289 -44,278,640 -52,207,377 -69,585,995 -57,768,556 -62,722,599 -68,731,081 -80,597,767 -69,254,320 -73,109,192 -77,731,944 1.29% 1.81% 1.42% 0.92% 12,563,958 10,174 8,562,291 19,196,655 -22,639,926 -34,879,515 -28,421,164 -20,492,426 -43,842,239 -55,659,678 -50,705,635 -44,697,152 -56,375,113 -67,718,561 -63,863,688 -59,240,937 2.60% 2.00% 2.38% 2.85% 2% 6,925,004 IRR Alternative C Basic scenario Negatives Increase of construction cost by 10% Increase of operational cost by 10% Reduction of traffic volumes by 10% Reduction of traffic volumes by 20% Positives Reduction of construction cost by 10% Reduction of operational cost by 10% Increase of traffic volumes by 10% Increase of traffic volumes by 20% 2% 1,018,359 IRR Alternative D Basic scenario Negatives Increase of construction cost by 10% Increase of operational cost by 10% Reduction of traffic volumes by 10% Reduction of traffic volumes by 20% Positives Reduction of construction cost by 10% Reduction of operational cost by 10% Increase of traffic volumes by 10% Increase of traffic volumes by 20% EGNATIA ODOS S.A. APRIL 2007 IRR 92 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X Alignment 2 Alternative B Basic scenario Negatives Increase of construction cost by 10% Increase of operational cost by 10% Reduction of traffic volumes by 10% Reduction of traffic volumes by 20% Positives Reduction of construction cost by 10% Reduction of operational cost by 10% Increase of traffic volumes by 10% Increase of traffic volumes by 20% 2% 85,645,948 NPV (€) 4% 6% 41,109,817 11,501,944 8% -8,442,372 7.06% 75,285,675 84,080,368 68,971,840 52,297,733 31,160,148 39,948,168 28,236,165 15,362,513 1,937,165 10,626,760 1,370,617 -8,760,711 -17,645,861 -9,111,840 -16,556,858 -24,671,343 6.17% 6.98% 6.13% 5.17% 96,006,221 87,211,528 102,320,056 118,994,163 51,059,486 42,271,466 53,983,469 66,857,121 21,066,724 12,377,128 21,633,272 31,764,599 761,117 -7,772,904 -327,887 7,786,599 8.09% 7.13% 7.96% 8.85% IRR Alternative C Basic scenario Negatives Increase of construction cost by 10% Increase of operational cost by 10% Reduction of traffic volumes by 10% Reduction of traffic volumes by 20% Positives Reduction of construction cost by 10% Reduction of operational cost by 10% Increase of traffic volumes by 10% Increase of traffic volumes by 20% 2% 80,091,942 NPV (€) 4% 6% 35,252,837 5,584,182 8% -14,290,808 6.49% 69,075,463 78,387,815 63,417,835 46,743,727 24,672,968 33,988,387 22,379,185 9,505,533 -4,586,419 4,631,548 -4,547,146 -14,678,473 -24,077,234 -15,019,521 -22,405,293 -30,519,779 5.63% 6.40% 5.60% 4.69% 91,108,422 81,796,070 96,766,050 113,440,157 45,832,706 36,517,286 48,126,489 61,000,141 15,754,782 6,536,816 15,715,509 25,846,837 -4,504,381 -13,562,095 -6,176,322 1,938,163 7.48% 6.57% 7.35% 8.20% 2% 74,552,898 NPV (€) 4% 6% 28,638,824 -1,573,624 8% -21,681,005 5.87% 62,546,302 72,599,386 57,543,106 40,533,314 17,108,079 27,189,333 15,505,999 2,373,173 -12,658,317 -2,665,667 -11,908,916 -22,244,208 -32,346,996 -22,516,358 -29,958,851 -38,236,698 5.05% 5.78% 5.03% 4.16% 86,559,494 76,506,410 91,562,690 108,572,482 40,169,569 30,088,315 41,771,649 54,904,475 9,511,069 -481,580 8,761,669 19,096,961 -11,015,014 -20,845,651 -13,403,158 -5,125,311 6.83% 5.96% 6.70% 7.51% IRR Alternative D Basic scenario Negatives Increase of construction cost by 10% Increase of operational cost by 10% Reduction of traffic volumes by 10% Reduction of traffic volumes by 20% Positives Reduction of construction cost by 10% Reduction of operational cost by 10% Increase of traffic volumes by 10% Increase of traffic volumes by 20% IRR Based on the above results and sensitivity tests the following conclusions concerning the project are formulated. EGNATIA ODOS S.A. APRIL 2007 93 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 6.6 Conclusions concerning the economic analysis As it was mentioned before, the calculation of the NPV requires the selection of a price for the discount rate, which is considered equal to the opportunity cost of capital (average long term interest rate plus the inflation). The inflation in the F.Y.R. of Macedonia is low; 0.5% in 2005 and 2.9% (est.) in 2006. The annual average interest rate is in the area of 5.0%. Therefore, the opportunity cost of capital in the F.Y.R. of Macedonia is considered to be around 8%. This is the reason that the NPV was calculated using the lower values for the discount rate of 6%, 4% and 2%. In a country where the opportunity cost of capital is in the area of 2% - 4% it results, according to the European Investment Bank and the World Bank, that: for IRR < 8%, a transport project is characterized by low probability of financing for IRR > 12%, a transport project is characterized by high probability of financing for IRR 8% - 12%, a transport project has probabilities of financing. However, a more analytic approach of various parameters is required. Despite the fact that the value of the IRR is relatively low and the NPV is not positive, the project is considered as attractive taking into account the national and international importance of the project. In the case where the opportunity cost of capital in the Former Yugoslav Republic of Macedonia would be smaller, then the specific IRR could characterize the investment as attractive enough. The differences in the values of IRR between the alternatives B, C and D are very small. This happens mainly due to the fact that there is not an important reduction of cost between the alternatives. That especially applies in the case of Alignment 1, where lower standards are already used in Alternative D for the biggest part of the section under study (19.9km at the “gorge”), that allows marginal reduction of construction costs. Despite the fact that Alternative B of Alignment 2 is the most “attractive” in terms of IRR, the difference with the economic results of Alternatives C and D are not significantly better. Consequently, Alternative D can be considered as the most prevailing one (among the three of them) because it refers to better geometrical and functional characteristics of the under study road project. It seems that parameters like the construction cost and the traffic volumes have an important impact to the final results (IRR, NPV) as it resulted from the sensitivity analysis. On the contrary, it seems that operational and maintenance costs do not particularly affect the IRR and NPV. In the case where the construction cost could be reduced without any impact to the quality of the project, the investment will become more attractive in terms of the IRR and the NPV. EGNATIA ODOS S.A. APRIL 2007 94 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 7. RECOMMENDATIONS In the authors’ view the financing and realisation of the project is recommended, even though the results are considered relatively low, due to the high values of the discount rate and not due to the project itself and its parameters. It must be mentioned that benefits like the consumer surplus, the quality of the trip as perceived by the users, the effect to the regional development (e.g., reduction of unemployment in the long term), the general improvement of the environment, the improvement of competitiveness at national level etc., were not taken into consideration in the framework of the economic analysis. However, the results of the environmental impact assessment study, as well as the costs of environmental mitigation measures, which could result an increase in the cost, are not yet available. Hence, it is considered that the environmental criterion is determinative for the project realisation. Apart from the economic results of the present feasibility study, the final decision for the project’s realisation should consider other important parameters, of neither economic nor technical nature: First of all, this project is situated along the backbone of the South-east Europe Transport Core Network and its implementation is in full alignment with the recently established South-eastern Axis, as defined by the High Level Group of the Directorate General for Energy and Transport of the European Commission, even not being a “soft” low-cost measure of infrastructure upgrade. The project would complete the road Corridor X main axis in the F.Y.R. of Macedonia, given the under-way realisation of the Tabanovce – Kumanovo motorway section, projects that will offer efficient infrastructures with substantial time and vehicle operating costs savings. Hence, the project would maximize the benefits along the entire Corridor X by improving the level of service along the Corridor, ensuring at the same time homogenous infrastructure and operation, facilitation of international passengers and trade flows, including transit traffic, if also accompanied with measures for border crossing facilitation. Taking into consideration the already constructed motorway sections between Negotino and Demir Kapija as well as of the one between Smokvica and the Greek border, the project would maximise the benefits of the above made investments, also in terms of revenues for the local government, since the use of the aforementioned new infrastructures is not yet charged. Finally, the project would contribute to regional development and cohesion in the weaker, “less favoured”, wider area of the Western Balkans, promoting the level of EGNATIA ODOS S.A. APRIL 2007 95 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X access of the Former Yugoslav Republic of Macedonia in the south with Greece, ensuring the country’s access to the sea via the port of Thessaloniki. EGNATIA ODOS S.A. APRIL 2007 96 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X BACKGROUND DOCUMENTS – REFERENCES 1. Aristotle University of Thessaloniki, Polytechnic School, Faculty of Rural and Surveying Engineering, Department of Transportation & Hydraulic Engineering: Passenger and freight flows forecasting for the documentation of the priorities and the needs for development of Pan-European Corridor X. Thessaloniki, August 2003. 2. Aristotle University of Thessaloniki, Polytechnic School, Faculty of Rural and Surveying Engineering, Department of Transportation & Hydraulic Engineering: Report of experts’ autopsy at the sections Tabanovce – Kumanovo and Demir Kapija – Smokvica of Pan-European Road Corridor X in F.Y.R.O.M., July 2006. 3. Aristotle University of Thessaloniki, Polytechnic School, Faculty of Rural and Surveying Engineering, Department of Transportation & Hydraulic Engineering: Support to international cooperation for development of PanEuropean Corridor X (Technical Secretariat of the Steering Committee), Interim Report. Thessaloniki, July 2006. 4. Balkan Konsalting DOOEL: Feasibility study National Road M-1 (E-75) Motorway Tabanovce – Kumanovo, January 2007. 5. COWI: Regional Balkans Infrastructure Study (REBIS). Final Report, July 2003. 6. Despontin, de Brucker, Coeck, Verbeke: The economic evaluation of road safety in E.U. DG VII, Luxemburg, 1998. 7. Egnatia Odos S.A.: Feasibility study for the upgrading of the road section Grabovnica (Lescovac) – Presevo (Serbian – F.Y.R.O.M. borders) of PanEuropean Corridor X, 2006. 8. European Commission – Eurostat: Statistical Yearbook on candidate and South-east European countries, 2002. 9. Fund for National and Regional Roads of F.Y.R. Macedonia: Traffic Data, December 2006. 10. Highway Capacity Manual (HCM) 2000. 11. Hi.P.E.R.B. (Unofficial document) Application for Assistance project Highway E-75 Demir Kapija – Gevgelija, 2002. 12. Hi.P.E.R.B. (Unofficial document) Application for Assistance project Highway E-75 Demir Kapija – Smokvica, 2004. 13. James L. Riggs, David D. Bedworth, Sabah U. Randhawa: Engineering Economics, 4th Edition, McGRAW-HILL International Editions, Industrial Engineering Series, 1998. 14. Louis Berger S.A.: Transport Infrastructure Regional Study (TIRS) in the Balkans. Final Report, January 2002. 15. Ministry of Environment, Physical Planning and Public Works: Decision of the Direction for the Study of Highway Projects, DMEO/a/O/1885/8-7-1996. 16. National Bank of FYROM: Annual Report 2005, April 2006. 17. Scetauroute International: PHARE CBC Programme MA-96061: E-75 Road Section Demir Kapija – Gevgelija, Feasibility Study, Final Report, 1999. 18. Scetauroute International: PHARE CBC Programme MA-96061: E-75 Road Section Demir Kapija – Gevgelija, Detailed Design, 2000. 19. Tim Powell: The Principles of Transport Economics, PTRC, 2001. EGNATIA ODOS S.A. APRIL 2007 97 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X 20. United States of America Embassy in Skopje: F.Y.R.O.M. Economy at a glance, October 2006. EGNATIA ODOS S.A. APRIL 2007 98 FEASIBILITY STUDY FOR THE UPGRADING OF THE ROAD SECTION DEMIR KAPIJA – UDOVO SMOKVICA OF PAN-EUROPEAN CORRIDOR X ANNEXES A. Issues discussed at the technical meeting in Skopje (01.03.2007) B. Results of the economic analysis - Alternative A - Alignment 1 (Alternatives B, C, D) - Alignment 2 (Alternatives B, C, D) EGNATIA ODOS S.A. APRIL 2007 99 ANNEX A ANNEX A - Issues discussed at the technical meeting in Skopje (01.03.2007) 1. Existing situation (physical – operational characteristics) Design and operational speeds (per subsection and per vehicle category) Traffic composition (vehicle categories: passenger vehicles, buses, light trucks, medium trucks and articulated trucks) Percentage of international traffic Rehabilitation economic cost (last rehabilitation – next rehabilitation) Accidents data Unit cost of accidents (for death, severe injury, light injury, damage only) 2. Future motorway (for both alternative alignments) Construction economic cost in current prices Cost breakdown per type of works (according to the table included in Hi.P.E.R.B. application form) Period of construction Cost annual allocation during the construction period First year of economic analysis (2008) Unit costs for traffic lanes, emergency lanes, earthworks, land acquisition, tunnels, bridges (for the estimation of cost savings of narrower cross sections) Annual maintenance and operational economic cost (during operation phase) Design speeds Alignment Number of toll booths along the new motorway section Cost of construction and annual operation of toll installations Toll system and rates per vehicle category. Planned revision Facilities along the new motorway Reduction of accidents after motorway construction 3. Economic parameters: Inflation rates GDP and GPD annual growth estimation Discount rate Exchange rate of denar to euro and USD Average monthly salary (for specialised and non-specialised work) Current fuel prices for various types of fuels (with and without taxes) Fuel consumption Framework (terms) of loans from IFIs (EBRD, EIB etc.), which include aspects as the following: duration, payback terms, percentage of loan etc. 4. Environmental impacts Environmental Impacts Assessment update (for Scetauroute alternative) Environmental Impacts mitigation measures and their cost Considerations of Environmental Impacts for alternative motorway alignment EGNATIA ODOS S.A. APRIL 2007 ANNEX B ANNEX B – Results of the economic analysis Alternative A PROJECT: DEMIR KAPIJA - UDOVO - SMOKVICA Α. CONSTRUCTION ELEMENTS Length (km, new situation) Mean operational speed (km/h, exisitng situation) Running time (min, existing situation) Design speed (km/h, new situation) Mean operational speed (Km/h, new situation) Running time (min, new situation) Β. TRAFFIC VOLUMES (AVERAGE IN THE OPERATIONAL PERIOD) 35.83 59 36.38 74 65 33.07 Private cars (P.C.) Light trucks Medium trucks Heavy trucks Articulated trucks Trucks total (reduced) Buses AADT (PCUs/day) 5,341 277 277 416 486 3,038 139 9,572 C. GENERAL ELEMENTS OF THE PROJECT Period of analysis (years) 25 Construction cost (€) 25,747,912 Residual value (€) 7,724,373 Operational costs (€/year, maintenance etc.) 308,961 1st periodical maintenance cost during the analysis period (€) 0 2nd periodical maintenance cost during the analysis period (€) 4,119,656 D. BENEFITS D1. BENEFITS FROM RUNNING TIMES REDUCTION (HUMAN TIME) Reduction of running time (min) 3.31 Public cars occupancy (passengers/ vehicle) 2.0 Trucks occupancy (passengers/ vehicle) 1.2 Buses occupancy (passengers/ vehicle) 45.0 Value of working time (€/ person/ hour) 3.40 Value of travelling time from/to work (€/ person/ hour) 1.70 Value of time for other purposes (€/ person/ hour) 0.85 Working days per month 25 Passengers/ day for work purposes 5,799 Passengers/ day from/ to work 8,865 Passengers/ day for other purposes 4,009 Benefits for passengers for work purposes (€ / year) 346,464 Benefits for passengers from/to work (€ / year) 269,328 Benefits for passengers for other purposes (€ / year) 60,998 Benefits subtotal 1 676,790 D2. BENEFITS FROM THE VEHICLES OPERATING COST REDUCTION (FUELS, OPERATING TIME, TRAVELLING DISTANCE ) Length (km, existing situation) 35.834 Length reduction (km) 0.000 Private cars fuel savings (lt/km/vehicle) 0.010 Heavy cars fuel savings (lt/km/vehicle) 0.020 Private cars fuel cost (€/lt) 0.97 Heavy cars fuel cost (€/lt) 0.81 Priavate cars operation unit value - time (€/hour/vehicle) 0.08 Heavy vehicles operation unit value - time (€/hour/vehicle) 0.09 Private cars & heavy vehicles operation unit value - distance (€/km/vehicle) 0.03 Benefits for private cars from fuel savings (€ / year) 0 Benefits for heavy vehicles from fuel savings (€ / year) 0 Benefits for private cars from operation reduction (€ / year) 8,596 Benefits for heavy vehicles from operation reduction (€ / year) 5,752 Benefits for private cars & heavy vehicles from distance reduction (€ / year) 0 Benefits subtotal 2 14,349 EGNATIA ODOS S.A. APRIL 2007 ANNEX B D3. BENEFITS FROM ACCIDENTS REDUCTION Average traffic volumes during the operational period WITHOUT project (AADT in PCUs/day) Length (km, existing situation) Annual vehicle-kilometres WITHOUT project (PCUs*year) Fatalities/ year Severe injuries/ year Light injuries/ year Damages/ year Annual vehicle-kilometres WITH project (PCUs*year) Fatalities/ year (vehicle-kilometres based estimation) Severe injuries/ year (vehicle-kilometres based estimation) Light injuries/ year (vehicle-kilometres based estimation) Damages/ year (vehicle-kilometres based estimation) Accidents reduction factor Reduction of fatalities/ year Reduction of severe injuries/ year Reduction of light injuries/ year Reduction of damages/ year Benefits from fatalities reduction (€/ year) Benefits from severe injuries reduction (€/ year) Benefits from light injuries reduction (€/ year) Benefits from damages reduction (€/ year) Benefits subtotal 3 SOCIOECONOMIC ANALYSIS RESULTS Benefits/ Cost ratio (8%) Benefits/ Cost ratio (6%) Benefits/ Cost ratio (4%) Benefits/ Cost ratio (2%) Net Present Value (NPV) in €, discount rate 8% Net Present Value (NPV) in €, discount rate 6% Net Present Value (NPV) in €, discount rate 4% Net Present Value (NPV) in €, discount rate 2% Internal Rare of Return (IRR) SENSITIVITY TESTS INTERNAL RATE OF RETURN (IRR) 10% increase in construction costs 10% decrease in construction costs 10% increase in operational costs 10% decrease in operational costs 10% increase in traffic 10% decrease in traffic 20% increase in traffic 20% decrease in traffic EGNATIA ODOS S.A. APRIL 2007 9,572 35.83 125,197,564 2.00 3.00 22.00 27.00 125,197,564 2.00 3.00 22.00 27.00 0% 0.00 0.00 0.00 0.00 0 0 0 0 0 0.10 0.12 0.15 0.19 -19,589,010 -19,168,114 -18,217,989 -16,380,539 Not defined Not defined Not defined Not defined Not defined Not defined Not defined Not defined Not defined ANNEX B Alignment 1 – Alternative B Length (km, new situation) Mean operational speed (km/h, exisitng situation) Running time (min, existing situation) Design speed (km/h, new situation) Mean operational speed (Km/h, new situation) Running time (min, new situation) Β. TRAFFIC VOLUMES (AVERAGE IN THE OPERATIONAL PERIOD) 32.15 59 36.38 80-100 81 23.76 Private cars (P.C.) Light trucks Medium trucks Heavy trucks Articulated trucks Trucks total (reduced) Buses AADT (PCUs/day) 5,942 309 309 463 540 3,380 154 10,650 C. GENERAL ELEMENTS OF THE PROJECT Period of analysis (years) 25 Construction cost (€) 144,501,616 Residual value (€) 88,692,519 Operational costs (€/year, maintenance etc.) 608,124 1st periodical maintenance cost during the analysis period (€) 13,572,227 2nd periodical maintenance cost during the analysis period (€) 0 D. BENEFITS D1. BENEFITS FROM RUNNING TIMES REDUCTION (HUMAN TIME) Reduction of running time (min) 12.62 Public cars occupancy (passengers/ vehicle) 2.0 Trucks occupancy (passengers/ vehicle) 1.2 Buses occupancy (passengers/ vehicle) 45.0 Value of working time (€/ person/ hour) 3.40 Value of travelling time from/to work (€/ person/ hour) 1.70 Value of time for other purposes (€/ person/ hour) 0.85 Working days per month 25 Passengers/ day for work purposes 6,452 Passengers/ day from/ to work 9,863 Passengers/ day for other purposes 4,461 Benefits for passengers for work purposes (€ / year) 1,471,327 Benefits for passengers from/to work (€ / year) 1,143,754 Benefits for passengers for other purposes (€ / year) 259,038 Benefits subtotal 1 2,874,118 D2. BENEFITS FROM THE VEHICLES OPERATING COST REDUCTION (FUELS, OPERATING TIME, TRAVELLING DISTANCE ) Length (km, existing situation) 35.834 Length reduction (km) 3.684 Private cars fuel savings (lt/km/vehicle) 0.010 Heavy cars fuel savings (lt/km/vehicle) 0.020 Private cars fuel cost (€/lt) 0.97 Heavy cars fuel cost (€/lt) 0.81 Priavate cars operation unit value - time (€/hour/vehicle) 0.08 Heavy vehicles operation unit value - time (€/hour/vehicle) 0.09 Private cars & heavy vehicles operation unit value - distance (€/km/vehicle) 0.03 Benefits for private cars from fuel savings (€ / year) 1,296,450 Benefits for heavy vehicles from fuel savings (€ / year) 2,019,320 Benefits for private cars from operation reduction (€ / year) 36,506 Benefits for heavy vehicles from operation reduction (€ / year) 24,428 Benefits for private cars & heavy vehicles from distance reduction (€ / year) 938,335 Benefits subtotal 2 4,315,040 EGNATIA ODOS S.A. APRIL 2007 ANNEX B D3. BENEFITS FROM ACCIDENTS REDUCTION Average traffic volumes during the operational period WITHOUT project (AADT in PCUs/day) Length (km, existing situation) Annual vehicle-kilometres WITHOUT project (PCUs*year) Fatalities/ year Severe injuries/ year Light injuries/ year Damages/ year Annual vehicle-kilometres WITH project (PCUs*year) Fatalities/ year (vehicle-kilometres based estimation) Severe injuries/ year (vehicle-kilometres based estimation) Light injuries/ year (vehicle-kilometres based estimation) Damages/ year (vehicle-kilometres based estimation) Accidents reduction factor Reduction of fatalities/ year Reduction of severe injuries/ year Reduction of light injuries/ year Reduction of damages/ year Benefits from fatalities reduction (€/ year) Benefits from severe injuries reduction (€/ year) Benefits from light injuries reduction (€/ year) Benefits from damages reduction (€/ year) Benefits subtotal 3 SOCIOECONOMIC ANALYSIS RESULTS Benefits/ Cost ratio (8%) Benefits/ Cost ratio (6%) Benefits/ Cost ratio (4%) Benefits/ Cost ratio (2%) Net Present Value (NPV) in €, discount rate 8% Net Present Value (NPV) in €, discount rate 6% Net Present Value (NPV) in €, discount rate 4% Net Present Value (NPV) in €, discount rate 2% Internal Rare of Return (IRR) SENSITIVITY TESTS INTERNAL RATE OF RETURN (IRR) 10% increase in construction costs 10% decrease in construction costs 10% increase in operational costs 10% decrease in operational costs 10% increase in traffic 10% decrease in traffic 20% increase in traffic 20% decrease in traffic EGNATIA ODOS S.A. APRIL 2007 10,650 35.83 139,293,869 2.00 3.00 22.00 27.00 124,973,430 1.79 2.69 19.74 24.22 40% 0.72 1.08 7.90 9.69 227,499 41,851 69,324 10,502 349,176 0.40 0.52 0.71 1.09 -59,456,895 -47,430,231 -27,013,094 6,925,004 2.33% 1.70% 3.05% 2.25% 2.42% 2.83% 1.83% 3.32% 1.30% ANNEX B Alignment 1 – Alternative C PROJECT: DEMIR KAPIJA - UDOVO - SMOKVICA (ALIGNMENT 1) Α. CONSTRUCTION ELEMENTS Length (km, new situation) Mean operational speed (km/h, exisitng situation) Running time (min, existing situation) Design speed (km/h, new situation) Mean operational speed (Km/h, new situation) Running time (min, new situation) Β. TRAFFIC VOLUMES (AVERAGE IN THE OPERATIONAL PERIOD) 32.15 59 36.38 80-110 81 23.76 Private cars (P.C.) Light trucks Medium trucks Heavy trucks Articulated trucks Trucks total (reduced) Buses AADT (PCUs/day) 5,942 309 309 463 540 3,380 154 10,650 C. GENERAL ELEMENTS OF THE PROJECT Period of analysis (years) 25 Construction cost (€) 152,613,331 Residual value (€) 93,913,740 Operational costs (€/year, maintenance etc.) 661,941 1st periodical maintenance cost during the analysis period (€) 14,773,309 2nd periodical maintenance cost during the analysis period (€) 0 D. BENEFITS D1. BENEFITS FROM RUNNING TIMES REDUCTION (HUMAN TIME) Reduction of running time (min) 12.62 Public cars occupancy (passengers/ vehicle) 2.0 Trucks occupancy (passengers/ vehicle) 1.2 Buses occupancy (passengers/ vehicle) 45.0 Value of working time (€/ person/ hour) 3.40 Value of travelling time from/to work (€/ person/ hour) 1.70 Value of time for other purposes (€/ person/ hour) 0.85 Working days per month 25 Passengers/ day for work purposes 6,452 Passengers/ day from/ to work 9,863 Passengers/ day for other purposes 4,461 Benefits for passengers for work purposes (€ / year) 1,471,327 Benefits for passengers from/to work (€ / year) 1,143,754 Benefits for passengers for other purposes (€ / year) 259,038 Benefits subtotal 1 2,874,118 D2. BENEFITS FROM THE VEHICLES OPERATING COST REDUCTION (FUELS, OPERATING TIME, TRAVELLING DISTANCE ) Length (km, existing situation) 35.834 Length reduction (km) 3.684 Private cars fuel savings (lt/km/vehicle) 0.010 Heavy cars fuel savings (lt/km/vehicle) 0.020 Private cars fuel cost (€/lt) 0.97 Heavy cars fuel cost (€/lt) 0.81 Priavate cars operation unit value - time (€/hour/vehicle) 0.08 Heavy vehicles operation unit value - time (€/hour/vehicle) 0.09 Private cars & heavy vehicles operation unit value - distance (€/km/vehicle) 0.03 Benefits for private cars from fuel savings (€ / year) 1,296,450 Benefits for heavy vehicles from fuel savings (€ / year) 2,019,320 Benefits for private cars from operation reduction (€ / year) 36,506 Benefits for heavy vehicles from operation reduction (€ / year) 24,428 Benefits for private cars & heavy vehicles from distance reduction (€ / year) 938,335 Benefits subtotal 2 4,315,040 EGNATIA ODOS S.A. APRIL 2007 ANNEX B D3. BENEFITS FROM ACCIDENTS REDUCTION Average traffic volumes during the operational period WITHOUT project (AADT in PCUs/day) Length (km, existing situation) Annual vehicle-kilometres WITHOUT project (PCUs*year) Fatalities/ year Severe injuries/ year Light injuries/ year Damages/ year Annual vehicle-kilometres WITH project (PCUs*year) Fatalities/ year (vehicle-kilometres based estimation) Severe injuries/ year (vehicle-kilometres based estimation) Light injuries/ year (vehicle-kilometres based estimation) Damages/ year (vehicle-kilometres based estimation) Accidents reduction factor Reduction of fatalities/ year Reduction of severe injuries/ year Reduction of light injuries/ year Reduction of damages/ year Benefits from fatalities reduction (€/ year) Benefits from severe injuries reduction (€/ year) Benefits from light injuries reduction (€/ year) Benefits from damages reduction (€/ year) Benefits subtotal 3 SOCIOECONOMIC ANALYSIS RESULTS Benefits/ Cost ratio (8%) Benefits/ Cost ratio (6%) Benefits/ Cost ratio (4%) Benefits/ Cost ratio (2%) Net Present Value (NPV) in €, discount rate 8% Net Present Value (NPV) in €, discount rate 6% Net Present Value (NPV) in €, discount rate 4% Net Present Value (NPV) in €, discount rate 2% Internal Rare of Return (IRR) SENSITIVITY TESTS INTERNAL RATE OF RETURN (IRR) 10% increase in construction costs 10% decrease in construction costs 10% increase in operational costs 10% decrease in operational costs 10% increase in traffic 10% decrease in traffic 20% increase in traffic 20% decrease in traffic EGNATIA ODOS S.A. APRIL 2007 10,650 35.83 139,293,869 2.00 3.00 22.00 27.00 124,973,430 1.79 2.69 19.74 24.22 40% 0.72 1.08 7.90 9.69 227,499 41,851 69,324 10,502 349,176 0.37 0.48 0.66 1.01 -65,523,614 -53,644,360 -33,220,670 1,018,359 2.05% 1.42% 2.75% 1.96% 2.13% 2.52% 1.56% 2.99% 1.06% ANNEX B Alignment 1 – Alternative D PROJECT: DEMIR KAPIJA - UDOVO - SMOKVICA (ALIGNMENT 1) Α. CONSTRUCTION ELEMENTS Length (km, new situation) Mean operational speed (km/h, exisitng situation) Running time (min, existing situation) Design speed (km/h, new situation) Mean operational speed (Km/h, new situation) Running time (min, new situation) Β. TRAFFIC VOLUMES (AVERAGE IN THE OPERATIONAL PERIOD) 32.15 59 36.38 80-120 83 23.33 Private cars (P.C.) Light trucks Medium trucks Heavy trucks Articulated trucks Trucks total (reduced) Buses AADT (PCUs/day) 5,942 309 309 463 540 3,380 154 10,650 C. GENERAL ELEMENTS OF THE PROJECT Period of analysis (years) 25 Construction cost (€) 156,621,546 Residual value (€) 96,413,585 Operational costs (€/year, maintenance etc.) 742,665 1st periodical maintenance cost during the analysis period (€) 16,574,933 2nd periodical maintenance cost during the analysis period (€) 0 D. BENEFITS D1. BENEFITS FROM RUNNING TIMES REDUCTION (HUMAN TIME) Reduction of running time (min) 13.05 Public cars occupancy (passengers/ vehicle) 2.0 Trucks occupancy (passengers/ vehicle) 1.2 Buses occupancy (passengers/ vehicle) 45.0 Value of working time (€/ person/ hour) 3.40 Value of travelling time from/to work (€/ person/ hour) 1.70 Value of time for other purposes (€/ person/ hour) 0.85 Working days per month 25 Passengers/ day for work purposes 6,452 Passengers/ day from/ to work 9,863 Passengers/ day for other purposes 4,461 Benefits for passengers for work purposes (€ / year) 1,521,548 Benefits for passengers from/to work (€ / year) 1,182,794 Benefits for passengers for other purposes (€ / year) 267,880 Benefits subtotal 1 2,972,222 D2. BENEFITS FROM THE VEHICLES OPERATING COST REDUCTION (FUELS, OPERATING TIME, TRAVELLING DISTANCE ) Length (km, existing situation) 35.834 Length reduction (km) 3.684 Private cars fuel savings (lt/km/vehicle) 0.010 Heavy cars fuel savings (lt/km/vehicle) 0.020 Private cars fuel cost (€/lt) 0.97 Heavy cars fuel cost (€/lt) 0.81 Priavate cars operation unit value - time (€/hour/vehicle) 0.08 Heavy vehicles operation unit value - time (€/hour/vehicle) 0.09 Private cars & heavy vehicles operation unit value - distance (€/km/vehicle) 0.03 Benefits for private cars from fuel savings (€ / year) 1,296,450 Benefits for heavy vehicles from fuel savings (€ / year) 2,019,320 Benefits for private cars from operation reduction (€ / year) 37,752 Benefits for heavy vehicles from operation reduction (€ / year) 25,262 Benefits for private cars & heavy vehicles from distance reduction (€ / year) 938,335 Benefits subtotal 2 4,317,120 EGNATIA ODOS S.A. APRIL 2007 ANNEX B D3. BENEFITS FROM ACCIDENTS REDUCTION Average traffic volumes during the operational period WITHOUT project (AADT in PCUs/day) Length (km, existing situation) Annual vehicle-kilometres WITHOUT project (PCUs*year) Fatalities/ year Severe injuries/ year Light injuries/ year Damages/ year Annual vehicle-kilometres WITH project (PCUs*year) Fatalities/ year (vehicle-kilometres based estimation) Severe injuries/ year (vehicle-kilometres based estimation) Light injuries/ year (vehicle-kilometres based estimation) Damages/ year (vehicle-kilometres based estimation) Accidents reduction factor Reduction of fatalities/ year Reduction of severe injuries/ year Reduction of light injuries/ year Reduction of damages/ year Benefits from fatalities reduction (€/ year) Benefits from severe injuries reduction (€/ year) Benefits from light injuries reduction (€/ year) Benefits from damages reduction (€/ year) Benefits subtotal 3 SOCIOECONOMIC ANALYSIS RESULTS Benefits/ Cost ratio (8%) Benefits/ Cost ratio (6%) Benefits/ Cost ratio (4%) Benefits/ Cost ratio (2%) Net Present Value (NPV) in €, discount rate 8% Net Present Value (NPV) in €, discount rate 6% Net Present Value (NPV) in €, discount rate 4% Net Present Value (NPV) in €, discount rate 2% Internal Rare of Return (IRR) SENSITIVITY TESTS INTERNAL RATE OF RETURN (IRR) 10% increase in construction costs 10% decrease in construction costs 10% increase in operational costs 10% decrease in operational costs 10% increase in traffic 10% decrease in traffic 20% increase in traffic 20% decrease in traffic EGNATIA ODOS S.A. APRIL 2007 10,650 35.83 139,293,869 2.00 3.00 22.00 27.00 124,973,430 1.79 2.69 19.74 24.22 40% 0.72 1.08 7.90 9.69 227,499 41,851 69,324 10,502 349,176 0.36 0.47 0.64 0.98 -68,486,440 -56,714,117 -36,349,902 -2,072,072 1.91% 1.29% 2.60% 1.81% 2.00% 2.38% 1.42% 2.85% 0.92% ANNEX B Alignment 2 – Alternative B PROJECT: DEMIR KAPIJA - SMOKVICA (ALIGNMENT 2) Α. CONSTRUCTION ELEMENTS Length (km, new situation) Mean operational speed (km/h, exisitng situation) Running time (min, existing situation) Design speed (km/h, new situation) Mean operational speed (Km/h, new situation) Running time (min, new situation) Β. TRAFFIC VOLUMES (AVERAGE IN THE OPERATIONAL PERIOD) 28.05 59 36.38 110 90 18.70 Private cars (P.C.) Light trucks Medium trucks Heavy trucks Articulated trucks Trucks total (reduced) Buses AADT (PCUs/day) 4,730 286 286 429 589 3,398 153 9,389 C. GENERAL ELEMENTS OF THE PROJECT Period of analysis (years) 25 Construction cost (€) 107,989,433 Residual value (€) 62,611,109 Operational costs (€/year, maintenance etc.) 494,555 1st periodical maintenance cost during the analysis period (€) 11,037,576 2nd periodical maintenance cost during the analysis period (€) 0 D. BENEFITS D1. BENEFITS FROM RUNNING TIMES REDUCTION (HUMAN TIME) Reduction of running time (min) 17.68 Public cars occupancy (passengers/ vehicle) 2.0 Trucks occupancy (passengers/ vehicle) 1.2 Buses occupancy (passengers/ vehicle) 45.0 Value of working time (€/ person/ hour) 3.40 Value of travelling time from/to work (€/ person/ hour) 1.70 Value of time for other purposes (€/ person/ hour) 0.85 Working days per month 25 Passengers/ day for work purposes 5,565 Passengers/ day from/ to work 8,738 Passengers/ day for other purposes 3,960 Benefits for passengers for work purposes (€ / year) 1,791,993 Benefits for passengers from/to work (€ / year) 1,431,864 Benefits for passengers for other purposes (€ / year) 324,962 Benefits subtotal 1 3,548,819 D2. BENEFITS FROM THE VEHICLES OPERATING COST REDUCTION (FUELS, OPERATING TIME, TRAVELLING DISTANCE ) Length (km, existing situation) 35.834 Length reduction (km) 7.784 Private cars fuel savings (lt/km/vehicle) 0.010 Heavy cars fuel savings (lt/km/vehicle) 0.020 Private cars fuel cost (€/lt) 0.97 Heavy cars fuel cost (€/lt) 0.81 Priavate cars operation unit value - time (€/hour/vehicle) 0.08 Heavy vehicles operation unit value - time (€/hour/vehicle) 0.09 Private cars & heavy vehicles operation unit value - distance (€/km/vehicle) 0.03 Benefits for private cars from fuel savings (€ / year) 1,512,735 Benefits for heavy vehicles from fuel savings (€ / year) 3,449,608 Benefits for private cars from operation reduction (€ / year) 40,702 Benefits for heavy vehicles from operation reduction (€ / year) 34,377 Benefits for private cars & heavy vehicles from distance reduction (€ / year) 1,129,868 Benefits subtotal 2 6,167,289 EGNATIA ODOS S.A. APRIL 2007 ANNEX B D3. BENEFITS FROM ACCIDENTS REDUCTION Average traffic volumes during the operational period WITHOUT project (AADT in PCUs/day) Length (km, existing situation) Annual vehicle-kilometres WITHOUT project (PCUs*year) Fatalities/ year Severe injuries/ year Light injuries/ year Damages/ year Annual vehicle-kilometres WITH project (PCUs*year) Fatalities/ year (vehicle-kilometres based estimation) Severe injuries/ year (vehicle-kilometres based estimation) Light injuries/ year (vehicle-kilometres based estimation) Damages/ year (vehicle-kilometres based estimation) Accidents reduction factor Reduction of fatalities/ year Reduction of severe injuries/ year Reduction of light injuries/ year Reduction of damages/ year Benefits from fatalities reduction (€/ year) Benefits from severe injuries reduction (€/ year) Benefits from light injuries reduction (€/ year) Benefits from damages reduction (€/ year) Benefits subtotal 3 SOCIOECONOMIC ANALYSIS RESULTS Benefits/ Cost ratio (8%) Benefits/ Cost ratio (6%) Benefits/ Cost ratio (4%) Benefits/ Cost ratio (2%) Net Present Value (NPV) in €, discount rate 8% Net Present Value (NPV) in €, discount rate 6% Net Present Value (NPV) in €, discount rate 4% Net Present Value (NPV) in €, discount rate 2% Internal Rare of Return (IRR) SENSITIVITY TESTS INTERNAL RATE OF RETURN (IRR) 10% increase in construction costs 10% decrease in construction costs 10% increase in operational costs 10% decrease in operational costs 10% increase in traffic 10% decrease in traffic 20% increase in traffic 20% decrease in traffic EGNATIA ODOS S.A. APRIL 2007 9,389 35.83 122,808,017 2.00 3.00 22.00 27.00 96,131,185 1.57 2.35 17.22 21.13 40% 0.63 0.94 6.89 8.45 198,487 36,514 60,483 9,162 304,646 0.90 1.14 1.54 2.31 -8,442,372 11,501,944 41,109,817 85,645,948 7.06% 6.17% 8.09% 6.98% 7.13% 7.96% 6.13% 8.85% 5.17% ANNEX B Alignment 2 – Alternative C PROJECT: DEMIR KAPIJA - SMOKVICA (ALIGNMENT 2) Α. CONSTRUCTION ELEMENTS Length (km, new situation) Mean operational speed (km/h, exisitng situation) Running time (min, existing situation) Design speed (km/h, new situation) Mean operational speed (Km/h, new situation) Running time (min, new situation) Β. TRAFFIC VOLUMES (AVERAGE IN THE OPERATIONAL PERIOD) 28.05 59 36.38 110 90 18.70 Private cars (P.C.) Light trucks Medium trucks Heavy trucks Articulated trucks Trucks total (reduced) Buses AADT (PCUs/day) 4,730 286 286 429 589 3,398 153 9,389 C. GENERAL ELEMENTS OF THE PROJECT Period of analysis (years) 25 Construction cost (€) 114,829,350 Residual value (€) 66,537,951 Operational costs (€/year, maintenance etc.) 538,321 1st periodical maintenance cost during the analysis period (€) 12,014,352 2nd periodical maintenance cost during the analysis period (€) 0 D. BENEFITS D1. BENEFITS FROM RUNNING TIMES REDUCTION (HUMAN TIME) Reduction of running time (min) 17.68 Public cars occupancy (passengers/ vehicle) 2.0 Trucks occupancy (passengers/ vehicle) 1.2 Buses occupancy (passengers/ vehicle) 45.0 Value of working time (€/ person/ hour) 3.40 Value of travelling time from/to work (€/ person/ hour) 1.70 Value of time for other purposes (€/ person/ hour) 0.85 Working days per month 25 Passengers/ day for work purposes 5,565 Passengers/ day from/ to work 8,738 Passengers/ day for other purposes 3,960 Benefits for passengers for work purposes (€ / year) 1,791,993 Benefits for passengers from/to work (€ / year) 1,431,864 Benefits for passengers for other purposes (€ / year) 324,962 Benefits subtotal 1 3,548,819 D2. BENEFITS FROM THE VEHICLES OPERATING COST REDUCTION (FUELS, OPERATING TIME, TRAVELLING DISTANCE ) Length (km, existing situation) 35.834 Length reduction (km) 7.784 Private cars fuel savings (lt/km/vehicle) 0.010 Heavy cars fuel savings (lt/km/vehicle) 0.020 Private cars fuel cost (€/lt) 0.97 Heavy cars fuel cost (€/lt) 0.81 Priavate cars operation unit value - time (€/hour/vehicle) 0.08 Heavy vehicles operation unit value - time (€/hour/vehicle) 0.09 Private cars & heavy vehicles operation unit value - distance (€/km/vehicle) 0.03 Benefits for private cars from fuel savings (€ / year) 1,512,735 Benefits for heavy vehicles from fuel savings (€ / year) 3,449,608 Benefits for private cars from operation reduction (€ / year) 40,702 Benefits for heavy vehicles from operation reduction (€ / year) 34,377 Benefits for private cars & heavy vehicles from distance reduction (€ / year) 1,129,868 Benefits subtotal 2 6,167,289 EGNATIA ODOS S.A. APRIL 2007 ANNEX B D3. BENEFITS FROM ACCIDENTS REDUCTION Average traffic volumes during the operational period WITHOUT project (AADT in PCUs/day) Length (km, existing situation) Annual vehicle-kilometres WITHOUT project (PCUs*year) Fatalities/ year Severe injuries/ year Light injuries/ year Damages/ year Annual vehicle-kilometres WITH project (PCUs*year) Fatalities/ year (vehicle-kilometres based estimation) Severe injuries/ year (vehicle-kilometres based estimation) Light injuries/ year (vehicle-kilometres based estimation) Damages/ year (vehicle-kilometres based estimation) Accidents reduction factor Reduction of fatalities/ year Reduction of severe injuries/ year Reduction of light injuries/ year Reduction of damages/ year Benefits from fatalities reduction (€/ year) Benefits from severe injuries reduction (€/ year) Benefits from light injuries reduction (€/ year) Benefits from damages reduction (€/ year) Benefits subtotal 3 SOCIOECONOMIC ANALYSIS RESULTS Benefits/ Cost ratio (8%) Benefits/ Cost ratio (6%) Benefits/ Cost ratio (4%) Benefits/ Cost ratio (2%) Net Present Value (NPV) in €, discount rate 8% Net Present Value (NPV) in €, discount rate 6% Net Present Value (NPV) in €, discount rate 4% Net Present Value (NPV) in €, discount rate 2% Internal Rare of Return (IRR) SENSITIVITY TESTS INTERNAL RATE OF RETURN (IRR) 10% increase in construction costs 10% decrease in construction costs 10% increase in operational costs 10% decrease in operational costs 10% increase in traffic 10% decrease in traffic 20% increase in traffic 20% decrease in traffic EGNATIA ODOS S.A. APRIL 2007 9,389 35.83 122,808,017 2.00 3.00 22.00 27.00 96,131,185 1.57 2.35 17.22 21.13 40% 0.63 0.94 6.89 8.45 198,487 36,514 60,483 9,162 304,646 0.84 1.06 1.44 2.15 -14,290,808 5,584,182 35,252,837 80,091,942 6.49% 5.63% 7.48% 6.40% 6.57% 7.35% 5.60% 8.20% 4.69% ANNEX B Alignment 2 – Alternative D PROJECT: DEMIR KAPIJA - SMOKVICA (ALIGNMENT 2) Α. CONSTRUCTION ELEMENTS Length (km, new situation) Mean operational speed (km/h, exisitng situation) Running time (min, existing situation) Design speed (km/h, new situation) Mean operational speed (Km/h, new situation) Running time (min, new situation) Β. TRAFFIC VOLUMES (AVERAGE IN THE OPERATIONAL PERIOD) 28.05 59 36.38 120 95 17.72 Private cars (P.C.) Light trucks Medium trucks Heavy trucks Articulated trucks Trucks total (reduced) Buses AADT (PCUs/day) 4,730 286 286 429 589 3,398 153 9,389 C. GENERAL ELEMENTS OF THE PROJECT Period of analysis (years) 25 Construction cost (€) 125,149,748 Residual value (€) 72,278,632 Operational costs (€/year, maintenance etc.) 617,100 1st periodical maintenance cost during the analysis period (€) 13,772,550 2nd periodical maintenance cost during the analysis period (€) 0 D. BENEFITS D1. BENEFITS FROM RUNNING TIMES REDUCTION (HUMAN TIME) Reduction of running time (min) 18.66 Public cars occupancy (passengers/ vehicle) 2.0 Trucks occupancy (passengers/ vehicle) 1.2 Buses occupancy (passengers/ vehicle) 45.0 Value of working time (€/ person/ hour) 3.40 Value of travelling time from/to work (€/ person/ hour) 1.70 Value of time for other purposes (€/ person/ hour) 0.85 Working days per month 25 Passengers/ day for work purposes 5,565 Passengers/ day from/ to work 8,738 Passengers/ day for other purposes 3,960 Benefits for passengers for work purposes (€ / year) 1,891,751 Benefits for passengers from/to work (€ / year) 1,511,575 Benefits for passengers for other purposes (€ / year) 343,052 Benefits subtotal 1 3,746,378 D2. BENEFITS FROM THE VEHICLES OPERATING COST REDUCTION (FUELS, OPERATING TIME, TRAVELLING DISTANCE ) Length (km, existing situation) 35.834 Length reduction (km) 7.784 Private cars fuel savings (lt/km/vehicle) 0.010 Heavy cars fuel savings (lt/km/vehicle) 0.020 Private cars fuel cost (€/lt) 0.97 Heavy cars fuel cost (€/lt) 0.81 Priavate cars operation unit value - time (€/hour/vehicle) 0.08 Heavy vehicles operation unit value - time (€/hour/vehicle) 0.09 Private cars & heavy vehicles operation unit value - distance (€/km/vehicle) 0.03 Benefits for private cars from fuel savings (€ / year) 1,512,735 Benefits for heavy vehicles from fuel savings (€ / year) 3,449,608 Benefits for private cars from operation reduction (€ / year) 42,967 Benefits for heavy vehicles from operation reduction (€ / year) 36,290 Benefits for private cars & heavy vehicles from distance reduction (€ / year) 1,129,868 Benefits subtotal 2 6,171,468 EGNATIA ODOS S.A. APRIL 2007 ANNEX B D3. BENEFITS FROM ACCIDENTS REDUCTION Average traffic volumes during the operational period WITHOUT project (AADT in PCUs/day) Length (km, existing situation) Annual vehicle-kilometres WITHOUT project (PCUs*year) Fatalities/ year Severe injuries/ year Light injuries/ year Damages/ year Annual vehicle-kilometres WITH project (PCUs*year) Fatalities/ year (vehicle-kilometres based estimation) Severe injuries/ year (vehicle-kilometres based estimation) Light injuries/ year (vehicle-kilometres based estimation) Damages/ year (vehicle-kilometres based estimation) Accidents reduction factor Reduction of fatalities/ year Reduction of severe injuries/ year Reduction of light injuries/ year Reduction of damages/ year Benefits from fatalities reduction (€/ year) Benefits from severe injuries reduction (€/ year) Benefits from light injuries reduction (€/ year) Benefits from damages reduction (€/ year) Benefits subtotal 3 SOCIOECONOMIC ANALYSIS RESULTS Benefits/ Cost ratio (8%) Benefits/ Cost ratio (6%) Benefits/ Cost ratio (4%) Benefits/ Cost ratio (2%) Net Present Value (NPV) in €, discount rate 8% Net Present Value (NPV) in €, discount rate 6% Net Present Value (NPV) in €, discount rate 4% Net Present Value (NPV) in €, discount rate 2% Internal Rare of Return (IRR) SENSITIVITY TESTS INTERNAL RATE OF RETURN (IRR) 10% increase in construction costs 10% decrease in construction costs 10% increase in operational costs 10% decrease in operational costs 10% increase in traffic 10% decrease in traffic 20% increase in traffic 20% decrease in traffic EGNATIA ODOS S.A. APRIL 2007 9,389 35.83 122,808,017 2.00 3.00 22.00 27.00 96,131,185 1.57 2.35 17.22 21.13 40% 0.63 0.94 6.89 8.45 198,487 36,514 60,483 9,162 304,646 0.77 0.98 1.32 1.98 -21,681,005 -1,573,624 28,638,824 74,552,898 5.87% 5.05% 6.83% 5.78% 5.96% 6.70% 5.03% 7.51% 4.16%