URR 15-008 - City of Canby
Transcription
URR 15-008 - City of Canby
RESOLUTION NO. URR 15-008 A RESOLUTION APPROVING AN AGREEMENT FOR CONSTRUCTION PHASE SERVICES AND CONSTRUCTION MANAGMEMENT SERVICES BETWEEN THE CANBY URBAN RENEWAL AGENCY AND TRIPLETT WELLMAN, INC. FOR THE NEW LIBRARY/CIVIC BUILDING PROJECT WHEREAS, the Canby City Council established the Canby Urban Renewal Agency (“Agency”) as an urban renewal agency to function within the City pursuant to Ordinance 1032 passed October 6, 1999; and WHEREAS, the Agency has been directed to undertake development of a new Library and Civic Building east of Ivy St. on NW 2nd Avenue; and WHEREAS, the Agency issued a Request for Proposals on March 6, 2015, soliciting the services of a Construction Manager/ General Contractor to construct the Library/Civic Building for a Guaranteed Maximum Price (“GMP”); and WHEREAS, The RFP anticipated a two-stage contracting process for the selected proposer, with Stage One including Design Assistance services, and stage two including Construction Phase Services and Construction Management Services; and WHEREAS, on May 6, 2015 the Urban Renewal Agency approved the appointment of Triplett Wellman, Inc. to act as the Project Construction Manager/General Contractor, and to provide Stage One Preconstruction Services for the project; and WHEREAS, the project is now set to proceed to the construction phase, requiring the approval of the balance of the scope of work of the contract between the Urban Renewal Agency and Triplett Wellman Contractors, including Construction Phase Services and Construction Management Services; and WHEREAS, the Agency staff and Triplett Wellman, Inc. have agreed to terms and conditions for Construction Phase Services and Construction Management Services as described in the RFP and as expressed in the Agreement attached to this Resolution as Exhibit A and by this reference incorporated herein. NOW THEREFORE, IT IS HEREBY RESOLVED by the Canby Urban Renewal Agency as follows: 1. The Urban Renewal Agency authorizes Construction Phase Services and Construction Management Services, in an amount not to exceed seven million dollars ($7,000,000), between the Agency and Triplett Wellman Inc., with services to be performed in a manner consistent with the Agreement attached as Exhibit A; and RESOLUTION NO. URR 15-008 PAGE 1 2. The Agency Director is authorized and directed to execute the Agreement on behalf of the Agency, including the execution of early work amendments, guaranteed maximum price amendments, change orders, and other documents as required, and to carry out such necessary actions to complete the Agency’s obligations under said Agreement. This Resolution shall take effect on September 16, 2015. ADOPTED this 16th day of September 2015, by the Canby Urban Renewal Agency. ____________________________________ Tim Dale Chair ATTEST: _______________________________ Kimberly Scheafer, MMC City Recorder RESOLUTION NO. URR 15-008 PAGE 2