Improving performance on Thameslink and Southern

Transcription

Improving performance on Thameslink and Southern
Improving performance
on Thameslink and
Southern
2
Govia Thameslink Railway (GTR), Southern and Network Rail are working together
to improve performance on Thameslink and Southern.
3
Improving performance on Thameslink
and Southern
We know that passengers have endured poor reliability on Thameslink and Southern
in recent months, and that we need to put this right. There are many factors that have
led to this situation. Some are failings on our part, and others involve circumstances
beyond our control.
We run trains on a network that is under ever-increasing pressure. With London’s
runaway success more people use the railway to get to work and do business.
The number of passengers on Thameslink has grown by 40% over the past five years,
and by 32% on Southern.
So train companies have added more and longer trains to the timetable. And the
infrastructure upgrades have proved to be insufficient to cope with the growth in
passenger numbers. This has all led to congestion and a noticeable decrease in
performance of the train service.
The Thameslink Programme will solve many of these problems, but it was always
going to cause disruption, particularly in the current phase – the major works at
London Bridge.
During the upgrades we can only use three of the four approach tracks, and our
drivers and signallers had to err on the side of caution until they were familiar with
the new layout. This all had an effect on the punctuality of the trains. And while
we tried to timetable as many services as possible – 22 an hour in the peak – so
passengers did not lose out, we have discovered that this number is not feasible
during the works.
In addition, when GTR took over the Thameslink service, we found that there were
too few drivers. There have also been problems with the infrastructure on the
Brighton Main Line, and upgrades on the Midland Main Line have caused
some disruption.
And finally, there have been an unusual number of one-off incidents that are out of
our control, such as high numbers of fatalities and trespassers on the line, and the
water mains leak at Farringdon.
While these are all genuine reasons for the current problems, we know that you want
to be assured that we are going to solve them. This updated report explains how
we in the rail industry are urgently working together to turn things around for our
passengers, and the targets we have set to improve our performance.
1
Performance
Thameslink and Southern performance Nov 12 - Dec 14
92
PPM Moving Annual Average*
90
88
86
84
82
80
2012
2013
2014
2015
Date
*MAA is the average performance
for the preceding year to date
Southern Route MAA Thameslink Route PPM MAA
The decline in performance has been going on for the past three years. On Thameslink
it has gone down from 90.35% to 82.93% and on Southern 90.21% to 83.72%.
How are we going to solve it?
We are acutely aware that you simply want to see the service return to one passengers
can rely on to go about their lives as planned. So what are we going to do to solve it?
We are working in partnership across the industry to improve performance on
Thameslink and Southern. GTR, Southern and Network Rail have formed an alliance
and we are working together to deliver a recovery plan with realistic targets.
2
Key areas of improvement
There are six key areas where we are making changes to improve performance.
You can find further details about these on pages 8 to 11.
Infrastructure
Fleet
Timetable
Drivers
Day-to-day
Customer experience
management of
operations
Time frame
We have set out a realistic time frame, delivering the improvement schemes over
three periods:
• Short term: to May 2015
• Medium term: to December 2015
• Long term: to December 2018
Holding us to account
We are committed to working with our stakeholders to improve the service for all our
passengers. We will keep you informed at all stages, with four-weekly updates on
our websites about our progress in meeting the targets and delivering the initiatives
described in this document.
3
Immediate actions
Removing the
Midland Main Line
speed restrictions
Removing most peak train
coupling and uncoupling
at London Bridge
Additional staff at London
Bridge to help passengers
and dispatch trains
Timetable changes so we
do not exceed available
capacity at London Bridge
Extra remote
monitoring equipment
at Bricklayers Arms
Points
renewed at
Sydenham
£5.75 million invested
in London Bridge
diversion route
Points
renewed at
Haywards
Heath and
Keymer
We are also increasing our response, maintenance and support staff to reduce the
time it takes to fix infrastructure failures.
4
Improving performance in 2015
We have already made a raft of improvements that have stopped our
performance deteriorating. It has levelled out at around 80% on Southern
and 81% on Thameslink.
However, we are now operating in a new environment caused by the works at
London Bridge. The fact that we can only use three tracks rather than four until
2017 means that we have to run fewer trains, and if something goes wrong it is
likely to have a greater effect on subsequent services.
In addition, we are still working to stabilise the evening peak period as we have
less capacity in the evening than the morning at London Bridge. This is because
it takes longer to dispatch full trains than empty ones, and while all trains are full
in the evening, over 30% of the morning trains are not in service when they leave
the station.
All this will inevitably have an impact on our performance over the next three
years. So the performance improvements you will see over the coming months are
measured against a new baseline – where we are now rather than where we were
before the London Bridge works.
Recent improvements
We reviewed our train schedule and made changes to the timetable, which have
brought noticeable improvements to the punctuality of our trains.
In addition, we have stopped most of the coupling and uncoupling of trains at
London Bridge to help the station run more efficiently. And the recent work we
have done on the infrastructure has greatly improved its reliability.
We have installed new information screens at London Bridge and improved the
way train crew and station staff communicate with passengers, so reducing delays
at stations.
Drivers and signallers are now familiar with the changes to the layout at
London Bridge, so trains can run a little faster and signallers can solve problems
more quickly.
5
Our targets for improvement
80%
Over the next five years we aim to improve performance on Thameslink and Southern
by 6.4% and have set targets for year on year progress.
The increase is calculated from the difference between our baseline in 2015/16 and
75%
our target in 2018/19.
We have
set the baseline
as our performance
in early
2015
2014/15
2015/16
2016/17
2017/18
2018/19
with the new infrastructure in place at London Bridge. This means that the figures will
Date
reflect the real improvements in reliability and punctuality that you will experience
Key
Expected actual performance
Baseline
MAA target
over the coming years.
Year end MAA
2014/15
2015/16
2016/17
2017/18
2018/19
Target
-
81.3%
82.7%
83.9%
86.6%
Baseline
82.8%
80.2%
80.2%
80.2%
80.2%
There are three key factors that will make a significant contribution to this increase
in performance:
• The new timetable in December 2015
• Our review of train scheduling in December 2017
• The re-opening of the fourth track at London Bridge in 2017
In addition, we are committed to a further 33 improvement schemes, which are
either already underway or planned to start in the next few years. The overall budget
for these is £200 million.
You will notice real improvements from now onwards in the punctuality and reliability
of our trains. And this trend will continue upwards as we deliver more improvement
schemes over the next few years.
6
Thameslink and Southern combined performance 2014 – 2019
90%
85%
80%
75%
2014/15
2015/16
2016/17
2017/18
Date
Expected actual performance
Year end MAA
2014/15
2015/16
2016/17
Baseline
2017/18
Moving
annual
average
figures
81.3%
82.7%
83.9%
Target
2018/19
Key
MAA target
2018/19
86.6%
The
reason the figures
show a decline
start of 2015/16
82.8%
80.2% in performance
80.2% at the 80.2%
80.2%
Baseline
is due to the figure the rail industry uses to calculate performance − the
Moving Annual Average (MAA). This is made up of an average of performance
for the year previous to the given date. For example, the figure for May 2015 will
average out our performance from June 2014 to May 2015.
This method of calculation means that in general any small or uncharacteristic
fluctuations are ironed out, but in our case it does mean that until a full year on
from our 2014 deterioration in performance, that decline will be included in the
calculation. So our actual performance in May 2015 will be higher than the
projected MAA figure.
Expected actual performance
The expected actual performance shows the improvements in punctuality and
reliability we have predicted for the next few years. The drop in performance in
autumn is standard across all train operators – it is because of the effect of seasonal
weather conditions.
7
Infrastructure
We are taking actions to reduce problems caused by the infrastructure.
These include:
• Additional nighttime working for maintenance crews to remove
infrastructure defects
• A dedicated team to inspect and improve the infrastructure at 38 key locations
• Removing the Midland Main Line speed restrictions
• Introducing the first UK mobile maintenance trains to reduce the time it takes
to do maintenance work and improve staff safety
• Schemes to improve drainage and reduce flooding
• Reinstatement of the fourth approach track at London Bridge in 2017
Fleet
One of the keys to good performance is the train fleet. Older trains need more
maintenance to keep them running on time. So we are making changes to the fleet
now that will give passengers more comfortable and reliable journeys.
We are already running the first of our brand new, air conditioned class 387 trains
on the Bedford to Brighton route − this January we were able to lengthen two
over-crowded morning services from Brighton. By May all 29 new trains will
be in service.
We have also hired three extra class 319 units so that we are able to run the
scheduled length of trains on the Bedford to Brighton services.
We are modifying all of Thameslink’s and some of Southern’s class 377s, and also
Southern’s class 171s to improve reliability.
From next year we will start to introduce the new Siemens trains on Thameslink.
Siemens train
8
Timetable
The timetable is critical to running a reliable service on the Brighton Main Line. The
off peak changes planned for December 2015 will remove many of the problems
in the current schedule. The timing between trains will be more evenly spaced so
if there is a problem with one service it is less likely to have a knock on effect on the
following ones.
We have made some
changes recently so that
passengers can rely on the
published timetable and
plan accordingly. At present
this includes removing
some peak Southern
services between
London Bridge and
West Croydon.
We are also concerned that
reliability of the evening
peak services is somewhat
fragile at the moment
due to the problems with
capacity at London Bridge.
So while we will maintain
the current volume of
services, we are reviewing
the pattern and will make
further adjustments in the
coming weeks. We will
let you know about any
changes as soon as we can.
The major timetable
changes we will make
in December 2015 will reflect the lessons we have learnt now, as will the final
Thameslink Programme timetable in December 2018.
9
Drivers
We are actively recruiting drivers for Thameslink to make up the current shortfall.
While it takes 15 months to train a new driver, we already have 12 trainees who will
be fully qualified by May, and a further 10 by December. On Southern we are training
29 new drivers who will be ready to join our team by May. We are also training all
Thameslink drivers on our new rolling stock.
We have been relying on drivers to work voluntary overtime to cover shifts on
Thameslink, but we are now working to reduce this so that we always have enough
drivers for each shift.
Day-to-day management of operations
Our immediate concern is to make sure we have enough people on the front line
to manage the service on a minute-by-minute basis. This means we will be able to
respond faster to problems such as signal failure and return the services to normal
more quickly.
So we are looking to extend the shift patterns of operations coordinators to cover
longer periods, bringing forward the appointment of 10 station performance
managers, and creating new roles in our route operations centre.
In order to reduce delays on the route we are reviewing how signallers control the
flow of services. And we are going to introduce a new traffic management system.
We are looking into the feasibility of running class 387 trains at 110 mph
on the northern part of Thameslink to get back to normal service levels faster after
an incident.
10
Customer experience
We have brought forward the introduction of passenger service directors on our
routes. These directors have direct responsibility to passengers at a local level,
leading the delivery of our service.
Following passenger feedback, we have changed the method we use to calculate
Delay Repay on Thameslink. There is also an enhanced compensation package in
place for Thameslink and Southern season ticket holders – you can find details on
our websites.
At major London stations such as London Bridge and Victoria we will use advertising
screens to show information about delays and cancellations when there is disruption.
Network Rail will also train a group of customer service staff, which we will send to
major London stations when there is severe disruption to help passengers.
Our Twitter feed is now manned 24 hours a day, every day, and we are merging our
Thameslink and Southern social media teams so they can share information and
respond to passengers more efficiently. We are also introducing a new system that
will automatically update our station
screens, apps and websites from
a single information source, giving
passengers consistent, accurate
service details.
We have made improvements
to Thameslink’s website and
Thameslink’s and Southern’s apps,
such as banner alerts that pop up
automatically when trains are delayed
or cancelled; storing recent journey
searches so that next time the
information appears faster; and more
personalised filtering of search results
so passengers get the information
that is most relevant to them.
We are constantly working
to improve the way we display
information on our websites and
apps, and make it more personally
relevant to every passenger.
11
Governance
We have set up an Alliance Board to take responsibility for, and oversee the
improvement work that we have committed to. It includes Thameslink, Southern and
Network Rail directors and the heads of the Thameslink Programme, performance,
projects, timetabling and customer services.
Meeting every four weeks, it focuses on projects that we are working on together.
It has substantial decision-making powers, with the ability to sanction expenditure
and move resources around our organisations to make sure the initiatives have all the
necessary support.
The Department for Transport and the Office of Rail Regulation regularly review the
board’s activity and hold us to account for delivery of our improvement plan.
12
What we are doing and when
New trains on Bedford to
Brighton services
Hire three extra units
Remove Midland Main Line
speed restrictions
Increase remote monitoring
By
May
2015
Immediate timetable changes
41 more qualified drivers
Additional nighttime
maintenance work
Upgrade infrastructure at 38
key junctions
Extra operations shifts
More new class 387 trains
Innovative mobile
maintenance trains
New maintenance regime
By
December
2015
Reinstate fourth approach
track at London Bridge
2017
New timetable
10 more qualified drivers
Three Bridges depot
completed 2015
New Thameslink Siemens
trains from 2016
More flexible management
of infrastructure failures
Improve drainage
By
December
2018
Introduce new traffic
management system
Final timetable
Driver training for class 700s
starts 2015
13
Email: [email protected] or [email protected]
Twitter: @TLRailUK or @SouthernRailUK
Our apps: Thameslink On Track and Southern On Track. Download them for free from the
App Store or Google Play
Website: thameslinkrailway.com or southernrailway.com
Thameslink Customer Services: 0345 026 4700, 07:00 to 22:00 every day except
Christmas Day
Southern Customer Services: 03451 27 29 20, 24 hours a day except Christmas Day
Thameslink Textphone: 0800 975 1052
Southern Textphone: 03451 27 29 40
Thameslink Address:
Freepost RRBR-REEJ-KTKY
Thameslink
Customer Services Department
PO Box 443
PLYMOUTH, PL4 6WP
Southern Address:
PO Box 10240
ASHBY-DE-LA-ZOUCH
LE65 9EB
1
B/MKG205/GTR/0215
Contact us