Agenda
Transcription
Agenda
Agenda • Arrival/Welcome • Safety Orientation • Facility Tour • Presentation on Basic Wellhead and API Requirements • Lunch • Stack-up of MBU-LR Speed Head System/Conventional Wellhead System/Overview of Frac Tree Equipment • Discussion | Q&A Conventional Assemblies • Include the casing head, casing hangers, spool sections, tubing head, tubing hanger, valves and fittings • Provides safe and adequate means for supporting and attaching blowout control equipment during drilling • Provides sealing between casing strings and a connection for the Christmas tree • Requires manipulation of BOP’s with each added section • Tubulars suspended on “slips” Casing Heads O-Ring Groove Test Port C2 Casing Head (With FPO’s) C2-BP Casing Head (With Two Lockscrews) Available with Threaded or Slip-on and Welded bottoms C2 Casing Head (With LP Outlets and Baseplate) Tubing Heads Test Port CTH Tubing Head (With Secondary Bushing) CTH Tubing Head (With integral bottom) Slip Type Casing Hangers C2 Casing Hanger. Standard automatic sliptype casing hanger. Used to suspend medium casing loads (50% joint strength) in C2 & C2BP Casing Heads C1 Casing Hanger and H Plate. Non-Automatic sliptype hanger. Used to suspend light to medium casing loads in C2 & C2BP Casing Heads C9 Casing Hanger. Heavy duty automatic slip-type casing hanger. Used to suspend high casing loads in C9 & C9BP Casing Heads Mandrel Hangers One Piece Mandrel Hanger Fluted Mandrel Hanger Tubing Hangers and Tubing Head Adapters BPV Threads BPV Threads CTH-2W CTH-2W wrap around hanger with BO2 coupling and BO2 tubing head adapter CTH-EN with EN tubing head adapter BPV Threads T40 Hanger with T40 tubing head adapter Multi-bowl Wellhead Systems 11” 10M 11” 5M MBS MBU Multi-bowl Wellhead Systems Lock-Ring Threaded-on Flange 2” LP 3” LP Landing Ring 20” Casing 13-3/8” Casing 9-5/8” Casing 5-1/2” Casing MBU-T MBU-LR ‘HPS’ Elastomer Secondary Seals Interference fit provides pressure energized seal. No plastic packing required. Springs in corners prevent extrusion Large ID interference provides sealing on rough casing Type ‘P’ Elastomer Seal Metal retainer rings prevent extrusion Seal energized against casing with plastic packing injection ‘Dovetail’ Elastomer Seals Commonly used as test plug and large O.D. seals Dovetail shape locks seal into groove Tapered edges help prevent extrusion Wide seal surface provides improved sealing Type ‘S’ Elastomer Seal Metal springs in corners to prevent extrusion OD bump provides interference fit allowing seal to be pressure energized Lockscrews Threaded Lockscrew Integral Lockscrew API Ring Gaskets R Gasket 5,000 PSI RX Gasket 5,000 PSI BX Gasket 10,000-15,000 PSI Frac Valve Comparison • • DS-BSFC 7-1/16” 10M Valve Two Seat Seal Rings An Inner and Outer Seal Ring That are Both Lip Sealed and Pressure and Spring Energized CW FL-R 7-1/16” 10M Valve Frac Valves Detail of Seat with Seals 7-1/16” 10M Detail of Seat with Seals Wellhead/Christms Tree Safety Potential Leaks • Bonnet/Body • Stem • Body Fittings Wellhead/Christmas Tree Safety “Line of Fire” • Test or injection fittings • Lockscrews Wellhead/Christmas Tree Safety Hidden Pressure Wellhead/Christmas Tree Safety One-Piece for lower pressures Two-Piece for higher pressures Wellhead/Christmas Tree Safety Back Pressure Valves Wellhead/Christmas Tree Safety Body Fitting API Flange Bolting • Flanges under pressure see a separation force equal to the pressure times the area inside the ring gasket. F=PxA • This separation force is contained by the flange bolting. Thus, larger flanges and higher pressure flanges have larger bolts and/or more bolts. • As the bolt diameter increases the amount of make up torque goes up. • API 6A publishes recommended make-up torques for API bolting. f = 0.07 Xylan Coated f = 0.13 Standard Lubricant Casing Effects During Frac Suspension point in wellhead Top of cement Initial Hanging Weight Cold frac fluid causes casing to contract increasing load on slip Pressure causes casing to balloon increasing load on slip Specification for Wellhead and Christmas Tree Equipment • API Specification 6A • Twentieth Edition, October 2010 • ISO 10423:2009 (Modified), Petroleum and Natural Gas Industries- Drilling and Production Equipment- Wellhead and Christmas Tree Equipment API 6A Basic Contents 435 Pages • Design and performance • Materials • Welding • Quality control • Equipment marking • Storing and shipping • Equipment specific requirements • Repair and remanufacture • Various Annexes covering purchasing guidelines, design, testing, etc. API 6A Product Specification What does it mean? 6A-U-EE-1.5-1-1 PR – Performance Requirement API Spec 6A Temperature Class Material Class PSL – Product Specification Level Temperature Class • Determined by the maximum flowing temperature in the wellhead or the mud circulating temperature and the minimum seasonal external temperature. • API Designations o K ………… -750F to 1800F o L ………… -500F to 1800F o N ……….. -500F to 1400F o P ………… -200F to 1800F o S ………… o T ………… o U ………… o V ………… o X ………… o Y ………… 00F to 1400F 00F to 1800F 00F to 2500F 350F to 2500F 00F to 3500F* 00F to 6500F* * Non-standard Ratings Material Class CO2 Partial Pressure H2S Partial Pressure 0 to < 0.05 psia 0.05 to 0.5 psia > 0.5 to 1.5 psia > 1.5 psia 0 to < 7 psia AA Non-sour Non-corrosive EE-0.5 or DD-0.5 Sour Non-corrosive EE-1.5 or DD-1.5 Sour Non-corrosive EE-NL or DD-NL Sour Non-corrosive 7 to 30 psia BB Non-sour Slightly Corrosive EE-0.5 Sour Slightly Corrosive EE-1.5 Sour Slightly Corrosive EE-NL Sour Slightly Corrosive > 30 to < 200 psia CC Non-sour Moderate to Highly Corrosive FF-0.5 Sour Moderate to Highly Corrosive FF-1.5 Sour Moderate to Highly Corrosive FF-NL Sour Moderate to Highly Corrosive > 200 psia CC or HH Non-sour Highly Corrosive FF-0.5 or HH-0.5 Sour Highly Corrosive FF-1.5 or HH-1.5 Sour Highly Corrosive FF-NL or HH-NL Sour Highly Corrosive Product Specification Level (PSL) • PSL 1, PSL2, PSL3, PSL3G, PSL4 • Quality control requirements such as material certifications, NDE, etc. that increase with the severity of service. • API 6A Annex A provides purchasing guidelines for selecting the proper PSL of Primary Equipment o Tubing Heads o Tubing Hangers o Tubing Head Adapters o Lower Master Valves Performance Requirement (PR) • Cycle testing of the designs • Cycles may include pressure, loads, open-close, etc. depending on product being tested • PR1 is minimum API cycle requirements found in the equipment section of the Specification 6A • PR2 adds additional cycles Standard Materials for API 6A Materials Classification Body, End and Outlet Connections Material Class Mandrel Hangers 2K, 5K, 10K 15K AA 4130 60K (CMS-102) 4130 75K (CMS-103) 4140 110K (CMS-106) BB 4130 60K (CMS-102) 4130 75K (CMS-103) 17-4 PH (CMS-303) CC 410SS (CMS-301) 410SS (CMS-301) 17-4 PH (CMS-303) 4130 80K (CMS-104) Or 4140 80K (CMS-105) DD 4130 60K (CMS-102) 4130 75K (CMS-103) EE-XX 4130 60K (CMS-102) 4130 75K (CMS-103) FF-XX 410SS (CMS-301) 410SS (CMS-301) 17-4 PH (CMS-303) Or Inconel 718 (CMS-304) HH-XX ------ ------ Inconel 718 (CMS-304) Bull Plugs, Valve Removal Plugs and Back-Pressure Valves 4130 60K (CMS-102) Product Plan - Quality Control Requirements for Wellhead Bodies and Assemblies The following chart details the Quality Control Requirements for all bodies. Applies to Casing and Tubing Heads, Cross-Over Connectors, Tubing Head Adapters, Top Connectors Tees and Crosses, Adapter and Spacer Spools, Casing and Tubing Hangers, Flanged Connectors Threaded Connectors, Other End Connectors. Parameter PSL 1 PSL2 PSL3 Tensile Testing CMS-002 and Material Spec Impact Testing CMS-004 Chemical Testing CMS-002 and Material Spec Hardness Testing CIR-002 CIR-002 CIR-002 Process Router & EPS Dimensional CIR-001 CIR-001 CIR-001 Process Router & EPS CMS-002 and Material CMS-002 and Material Spec Spec Comments Compare MTR to Material Spec Section 8.0 & EPS CMS-004 CMS-004 Compare MTR to Material Spec CMS-002 and Material CMS-002 and Material Spec Spec CIR-004 or CIR-004 or CIR-004 or TTM-WI-7.5.1 TTM-WI-7.5.1 TTM-WI-7.5.1 Traceability Heat Traceable Heat Traceable Visual Exam CIR-003 CIR-003 --- CNT-002 or CNT-002 or Surface NDE --CNT-004 CNT-004 Thread Gauging Compare MTR to Material Spec End and Outlet Connection Threads Gauge 100% Heat Traceable & Heat PSL-1/2-Trace by heat numbers Lot PSL-3-Trace by serial numbers Process Router & EPS Volumetric NDE --- --- CNT-005 Prior to Machining Weld NDE --- CNT-008 CNT-008 Process Router & EPS, if applicable Marking MD Drawing MD Drawing MD Drawing Serialization --- --- Each component Hydrostatic Test CTS-001 CTS-001 CTS-001 Assembly Traceability CTS-001 CTS-001 CTS-001 Process Router & EPS Work Order-sequential number PSL-3 – Chart Recorder Required PSL-1/2- Record heat number of body PSL 3- Record heat and serial number Set Out Reports Assembly Serialization --- API Monogram TTM-MSP-A-1 Work Order-sequential Work Order-sequential number number TTM-MSP-A-1 TTM-MSP-A-1 Process Router Process Router & EPS Impact Testing Minimum Average Impact Value Transverse Direction - Ft-Lb (J) Temperature Classification Test PSL 1 PSL 2 PSL 3 K -75 (-60) 15 (20) 15 (20) 15 (20) L and N* -50 (-46) 15 (20) 15 (20) 15 (20) P -20 (-29) -- 15 (20) 15 (20) S 0 (-18) -- -- 15 (20) T 0 (-18) -- -- 15 (20) U 0 (-18) -- -- 15 (20) V 0 (-18) -- -- 15 (20) Cactus Record Requirements Bodies, End and Outlet Connections, Mandrel Tubing Hanger and Casing Hanger PSL-1 PSL-2 PSL-3* Material Test Reports: Chemical analysis, tensile test, impact test (if required) and hardness test X X X Weld Process Records: WPS, WPQR and WQR X X X Welding Process Records: Welder identification, weld procedures, filler material type, post-weld heat treatments X NDE personnel Qualification Records for Weld Metal Corrosion Overlay on Bodies X X X Hardness Test X X Actual Hardness Dimensional Inspection NDE Records: Surface NDE, Weld Volumetric NDE, and Repair Weld NDE Volumetric NDE Heat Treatment COC Non-Metallic Seals X PSL-1 X X X X X PSL-2 PSL-3 Batch Traceability, Cure date certification, Shelf-life expiration date certification Bullplugs, Valve-Removal Plugs and BackPressure Valves Assembled Equipment Records Pressure Test Records: Actual test pressure, holding period duration X Material Test Reports : Chemical analysis, tensile test, impact test, and hardness test PSL-1 PSL-2 PSL-3* X X Pressure Test Records: Hydrostatic Test Chart X Assembly Traceability Record X *All required records for PSL3 components & assemblies shall reference the specific part serial number. Records to be Furnished to Customer Bodies, End and Outlet Connections, Mandrel Tubing Hanger and Casing Hanger PSL-1 PSL-2 PSL-3* -- -- -- PSL-1 PSL-2 PSL-3 -- -- -- PSL-1 PSL-2 PSL-3* Certificate of Compliance – stating that equipment conforms to PSL 3 of API Spec 6A and the temperature and material class -- -- X Pressure Test Records: Actual test pressure, holding period duration -- -- X Pressure Test Records: Hydrostatic Test Chart -- -- X Assembly Traceability Record -- -- X No records are required Non-Metallic Seals No records are required Assembled Equipment Records