Station Update - Peoples Natural Gas

Transcription

Station Update - Peoples Natural Gas
PRODUCTION COMPRESSOR UPDATES
AS OF:
02/09/2015
STATION
RUNNING
Armbrust
OFF
Arnold
OFF
Belknap
#2
Creekside
OFF
Egry
YES
Gibson
OFF
Girty
#1, #4
Latrobe
OFF
Mendon
OFF
Merwin
OFF
Redbank
OFF
Roaring Run
OFF
Shady Plain
OFF
Valley
OFF
#1 is not needed.
Reassembly is almost complete. Need to set oil tank & install bearing
temp sensor.
Work will resume on reassembly. Approx 1 week of work is needed.
#2, #3 are not needed.
Low suction
Unit is down with lubricator sensor problem. Will be on-line as soon as
possible.
Not needed.
The entire station is down today for piping revisions & orifice plate
inspections. #1 & #4 will be back on later today. #5 is still down for
repairs – waiting on exhaust header.
PEOPLES GAS EGC STATIONS
Limestone
Fisher
Village
Atwood
Crooked Creek
Shoemaker
Creighton
#2
YES
YES
YES
YES
YES
YES
Unit #1 is down to control the BTU level.
OTHER NOTES:
1. The temporary compressor at Valley is decommissioned as of Monday 2/9. The operating
permit expired and unit #3 will be ready soon.
2. Repairs are in progress for the Creekside compressor crankshaft replacement. Reassembly is
almost complete.
3. We are waiting for an exhaust header for Valley #5. Ignition upgrade is in progress while the
unit is down.
Pigging Schedule
Pipeline
Pig Type
Date
Description
Pipeline Construction Schedule
Pipeline
Date
Description
Line / System Down-Rating Schedule
Line/System
MAOP
Regulator Set Pt
Time
Please be advised
Peoples Natural Gas has posted a “Meter Tap Process” document and “Meter Tap Request” form on the
Gathering Website under “Guidelines and Procedures”. Please refer to them for future tap requests.