Downloads - 21st Century Construction

Transcription

Downloads - 21st Century Construction
Introduction
Founded 2010 in Liverpool, 21st Century Construction Ltd acquired UK franchise for a new
patented innovative composite permanent formwork system.
Having spent 4 years developing the system, we are now successfully delivering several
projects across multiple field sectors.
Our Team
Introducing 21st Century System
System is protected by global patent rights
Simple, fast and economical
Compatible with any design, low and high rise projects and architectural requirements
Panels produced in factory conditions
Pre-fabricated modular system forming load bearing & non-load bearing walls
Remote progress monitoring via bar code system
Erected on site forming a pre-decorated wall
Introducing 21st Century System
Installation
Doesn’t require a crane to load onto the project, a panel can be lifted by two
operatives.
Forms the structural solution through reinforced steel starter bars that tie the
panels together and into the slab.
Installation
First fix mechanical and electrical installations can be installed within the panel on
or off site.
Once the concrete is poured, vibrated and set the structure can continue its vertical
ascension.
Quality Control
Deep scanning system used to check the integrity of the wall
All panels bar coded to allow remote progress monitoring via internet and
mobile application for international partners and investors
Benefits to the Developer
Complies with Euro, British, Irish, American and Australian Building Codes.
ARUP approved
Build times reduced by up to 50%, Fast clean method of building.
Time related prelims costs reduced
Superior fire protection when compared to steel and timber.
Superb acoustic properties.
Benefits to the End User
A durable strong quality construction that will last for generations.
Virtually maintenance free.
Easy to extend in the future
High end finish without the high end price.
Multiple design options.
Benefits to the Developer
Wet Trades eliminated, Minimal Wastage.
Easy for conventional builders to adapt and use.
High quality durable finish.
No specialised equipment required for erection, Minimal use of scaffolding, Light simple and easy to install
Construction & Design Benefits
The form work system alleviates the need for plasterboards.
A flexible system that allows for any radius to be created as well as formed openings in the structure.
Spacers hold re-bars in correct position, no time consuming rebar tie wires.
First fix electrical and plumbing completed prior to concrete pour.
Unlimited exterior cladding loads can be carried, allowing for varying aesthetic finishes.
Comparison
Traditional Concrete Technology
• Erect first face of formwork
• Steel fixing
• Erect second face of formwork.
• Complete falsework
• Casting concrete
• Striking formwork
• Finishing stage:
• Rough coat render
• MEP installation
• Stud partition & slab board installation
• Tape & joint or spray plaster
Precast Concrete Technology
• Erect large mass precast wall panels
• Steel fix connection details
21st Century
Construction
Erect modular wall & slab panels
Connection details
Slab rebar
• Form connection details
• Grout/ cast concrete
• Erect precast floor planks
MEP installation
Concrete casting
Finishing stage:
Tape & joint
• Pour floor screed
• MEP installation
• Finishing stage:
Stud partition & slab board installation
Tape & joint or spray plaster
Bespoke Spray finish applied directly
onto wall & slab panels
The Paramount, Liverpool
21st Century construction system is currently being erected at Paramount project in Liverpool, this
project is a fresh, contemporary piece of architecture, adding a bold statement to Liverpool city
centre and rejuvenating a very prominent site in the city.
The project consists of 448 en-suite student bedrooms, Health Suite including a swimming pool
and retail space. The scheme will form an impressive gateway to Liverpool City. Our system is
being used in this instance as the main structure interconnecting with a steel podium, Our
system rises from the 1st floor up to the 10th.
The Quadrant, Liverpool
The Quadrant is a purpose build student accommodation development consisting on 240 student
units in a seven storey build.
The structure is being constructed using our system, from basement level to seventh floor,
including lift shafts and stair cores. The Quadrant features an attractive solid sandstone cladding
that will be hung from the system.
Spectrum, Sheffield
The 21st Century System is being erected at Spectrum apartments, Sheffield. Spectrum is a
seven storey project comprising 152 student units.
on this project we will be installing our system to be used from the ground floor to the first floor
to act as the building podium.
Conclusion
A design and build system, which cuts construction time by up to 50%.
All materials brought onto site are used, reducing waste & creating a safe clean working environment.
Advanced construction process, rooms ready for first fix M&E.
Taped and jointed walls reducing finishing trades.
Exposure to the client is reduced due to the speed of construction.
ANY QUESTIONS?