November 2009 - Fretz Construction
Transcription
November 2009 - Fretz Construction
A R C H I T E C T U R E , D E S I G N & E N G I N E E R I N G The Pavilion after Hurricane Ike, which left the fabric structure in tatters. IMAGE: JEFF YOUNG Teamwork, persistence, and the flexibility of tensile fabric and structural steel, combine to allow the replacement and expansion of a landmark amphitheatre in just 164 days. H urricane Ike — the third most destructive hurricane to ever make landfall in the United States — roared into the Texas Gulf Coast on September 13, 2008. It inundated Galveston Island with record flooding and left more than three million households without power for up to several weeks. The storm obviously wasn’t a patron of the arts. Eighty miles inland, the Teflon-coated fibreglass fabric roof over the reserved seating area of the Cynthia Woods Mitchell Pavilion was completely destroyed. This forced the remainder of the 2008 concert season to be abruptly cancelled. A combination of Ike’s strong winds and windborne debris shredded the roof, causing more than US$3m in damage. Yet the durable steel substructure survived intact. Taking advantage of the reconstruction process, the Pavilion’s board of directors decided to expand the roof structure, more than doubling the facility’s covered seating capacity from 2,479 to 6,387. With 9,653 lawn seats after the US$9.5m renovation and expansion project, the total capacity of the AUTUMN/FALL 2009 venue has grown to 16,040 seats. In the process, the fabric roof more than doubled in size from 30,000sqft to 82,000sqft. How could this all occur by May? Thanks to the dedication of a multi-disciplinary team of designers, fabricators, and erectors, the venue re-opened after a five month reconstruction project, twice as large and more hurricane-resistant than before, and in time for a rocking concert by the Dave Matthews Band. In reopening the fully replaced and expanded roof structure just 164 days after their first meeting, the design and construction team members took full advantage of the strength and flexibility of a composite fabric material and structural steel, outstanding teamwork, and the benefits of technology. The Pavilion is located 27 miles north of Houston in The Woodlands, and is owned by The Center for the Performing Arts at The Woodlands — a non-profit organization that focuses on enriching the culture of its local community. George Mitchell, who founded The Woodlands in 1974, and his wife, Cynthia Woods Mitchell, wanted to create a facility that would host performing arts, popular music, and community events. They achieved their goal in April 1990 when the Pavilion first opened. In recent years, the Pavilion has hosted approximately 75 events every season, March through November. These include ballet performances, a diverse range of music concerts, and high school graduations. Since 1992, the Pavilion has been the official summer home of the Houston Symphony. Educational outreach programs sponsored by The Center for the Performing Arts at The Woodlands have exposed approximately 40,000 students from seventeen area school districts to the performing and visual arts. Background Prior to the storm, the twenty-year-old Cynthia Woods Mitchell Pavilion was ranked for three consecutive years by Pollstar magazine as one of the top six amphitheatres in the world. PA N S TA D I A 82 A R C H I T E C T U R E , D E S I G N & E N G I N E E R I N G Plan view from 3D model of the expanded structure, with the structural components identified. IMAGE: WALTER P MOORE The venue was originally designed both architecturally and structurally by Horst Berger Partners in 1989. Fortunately, Horst Berger and his protégé, Joseph DeNardis of DeNardis Engineering in White Plains, New York, were also available to design the expanded fabric structure. Walter P Moore, headquartered in Houston, TX, was the designer of the steel substructure and the structural engineer-of-record, and FabriTec Structures — a brand of USA Shade & Fabric Structures, Inc. in Dallas, Texas — performed the fabric patterning and installation. Fabric Skin & Steel Skeleton Sheerfill II fabric, which is a composite material made of fibreglass and polytetrafluoroethylene (PTFE) with a Teflon coating, was used for both the original and expanded structures. The fabric, produced by Saint-Gobain Performance Plastics, has sufficient strength to withstand design wind loads in addition to having superior ability to transmit light without the heat gain associated with traditional glazing. This is especially important in the Houston area, where outside temperatures are commonly above 90 degrees Fahrenheit during the summer months. The Teflon coating of Sheerfill II protects it from staining, and the material maintains its original pre-stressed shape without relaxation throughout its typical lifespan of 25 or more years. The thirteen panels of Sheerfill II fabric used in the newly expanded Cynthia Woods Mitchell Pavilion weigh approximately 25,000lbs in total. Although the same type of fabric was used for both the original and the expanded structures, several design aspects of the expanded fabric structure make it more resilient to hurricane loads than when it was first constructed. These features include providing triangular fabric panels at the outer edges to avoid terminating ridge cables in edge catenary cables, and reinforcing the fabric with surface cables to act as rip stops. The surface cables panelise the new roof fabric at the seams to limit damage from windborne debris to localized areas. The expanded structure was also designed to withstand up to a three-second wind gust with a speed of 110mph, which is a higher design wind load than the original structure. AUTUMN/FALL 2009 The steel substructure involves compressive loads being transferred to spread footings through A-frames, struts, and vertical masts, while tensile loads are transmitted through a network of ridge, valley, and catenary cables. Lateral loads are transferred through the compression and tension members to the stage house, where they are resisted by braced frames, and through diagonal cables anchored to new foundations. The requirement of creating a large open space using members with long spans made structural steel an ideal material for the project. Laced steel struts and columns were used in both the original and the expanded structures to further improve the feeling of openness under the canopy, to minimize impact on the sightlines, and for acoustical purposes. The original structure was supported by one row of A-frames and a series of struts and cables. The expansion of the roof area was accomplished by using a second row of A-frames with connecting struts and cables, while incorporating as much of the original structure as possible. The A-frames, which are trussed elements between the masts, create external supports for various peaks of the roof. The struts are nearly horizontal laced members in compression that offer support points at the perimeter edge of the structure and are critical for stability through the braced frames located at the stage house. All of the original masts and Aframes, along with several of the original struts, were re-used in the expanded structure. The new A-frames span up to a projected horizontal length of 130ft, while the new struts span up to 85ft. ASTM A586 structural strand cables of 5/8 in to 1 5/8 in diameter with Type A inner and outer coating were used throughout the structure, with breaking strengths of 48,000lbs to 324,000lbs. The stage house was extensively retrofitted to allow it to provide much of the lateral bracing for the expanded structure. The retrofits involved adding steel side plates to many wide flange members, adding bracing members, and exposing and retrofitting existing footings. In addition, several of the existing connections were strengthened. The retrofits were redesigned during the Ú PA N S TA D I A Image from the Sketch-Up model of an exterior mast in the second row. The 3D model was used extensively for coordination between consultants. IMAGE: LVJ SPECIALTY, INC. Structural steel erection nearing completion, prior to installation of the fabric. IMAGE: WALTER P MOORE Close-up of one of the second row masts. Three struts, two A-frames, and five cables connect to this interior mast. IMAGE: WALTER P MOORE Installation of a fabric panel showing temporary netting and beige fabric that will be bleached white by UV rays. IMAGE: WALTER P MOORE 83 A R C H I T E C T U R E , D E S I G N & E N G I N E E R I N G TATTERS TO FINE TUNES The first fabric panel installed. construction process as existing conditions were discovered that differed from the 1989 design drawings. to speed up the project delivery schedule. A mere seventeen days after design began, foundation construction drawings for the retaining walls were issued for construction. One week later, steel trunk drawings were issued to allow most of the steel to be ordered and the trunks to be fabricated while the design of the connections was underway. Four days later, cable drawings were issued so that the cables integral to the steel structure’s stability could be ordered. The remaining foundation drawings were issued on December 22, just six days after the cable drawings, to allow existing foundations to be retrofitted and new foundations constructed where needed. Once construction began on these critical-path elements by the general contractor, Fretz Construction Co. of Houston, the design team turned its attention to the stage house. Although the retrofit of the stage house was urgent, because it had adequate strength and stiffness to keep the entire structure stable during construction, its retrofit could wait until the expanded roof fabric was in place and full wind loads would be possible. Design continued apace through the Christmas and New Year holidays to allow the stage house retrofit package to be issued on January 4, 2009 — just 45 days after the start of design. This was the last structural engineering package issued. After this time, a few revisions were issued to incorporate the final wind tunnel test results, which were received on January 23. IMAGE: WALTER P MOORE Speedy Engineering Design Schedule Photo from underneath The Pavilion showing a second row exterior mast with connecting elements. IMAGE: WALTER P MOORE Abseilers working on connections at the A-frame peaks. Structural cables are connected at the A-frame peaks, while ridge and valley cables give the fabric its shape. IMAGE: JEFF YOUNG Image from the sold-out opening concert by the Dave Matthews Band. The most challenging aspect of the project was the fast-track schedule. On November 6, 2008, Walter P Moore’s structural engineers first visited the site to assess the existing condition of the hurricane-damaged structure. When the first meeting of the design team with the owner and general contractor was held on November 18, only 164 days remained before the planned grand reopening event, a sold-out concert by the Dave Matthews Band scheduled for May 1, 2009. To succeed and avoid the US$1m penalty, the project team had to compress structural assessment, redesign, fabrication, shipping, erection, and structural strengthening into those valuable 164 days. This hyper-schedule demanded activity durations measured not in months or weeks, but in days. In the process, the project team found ways to retrofit and re-use many existing structural members to save time and reduce costs. Even though a wind tunnel analysis was performed for the original structure, another was required to accurately predict wind loads acting on the new structure due to the significant changes in roof geometry and because current codes do not address wind loads on structures with shapes as complex as this. However, the six-week lead time for the analysis did not accommodate procurement deadlines for the fabric panels, structural steel, and especially the cables. Therefore, the design was carried out on the basis of preliminary wind loads from desktop studies performed by the Canadian wind engineering consultant, Rowan Williams Davies & Irwin, Inc., that would later be confirmed using the final wind tunnel test results. Less than two weeks after the initial project kick-off meeting, the results from the desktop studies were received by the design team on November 30, 2008. DeNardis Engineering provided the fabric interface geometry on December 8 and the fabric details on December 24. The construction drawings for the structure were issued in several packages An Equally Ambitious Construction Schedule The construction schedule maintained the same record pace as the engineering design schedule. Fabrication of the structural steel members and cables began almost as soon as the design drawings were issued. Communication was vital in maintaining the momentum of the project’s construction. Interaction between the structural and fabric engineers, the general contractor, and the steel detailer — LVJ Specialty, Inc. of Lafayette, LA — and fabricator — Alpha Fabricators, Inc. of Houston — occurred on nearly a daily basis to ensure that the project could proceed at maximum speed. Rey de la Reza Architects, Inc. of Houston managed the project for the owner. IMAGE: JEFF YOUNG AUTUMN/FALL 2009 PA N S TA D I A 84 A R C H I T E C T U R E , When construction began on December 1, it included seven-day working weeks. Later, construction crews were at work 24 hours a day. Demolition of the existing concrete from the uncovered reserved seating area and construction of a concrete foundation for installation of the tower crane occurred first. In midDecember, foundation retrofitting and new construction were performed. As many as thirteen lifts were used on the site at one time to erect 75 tons of steel in three weeks. During the week of February 1-7, the first row of masts, struts, pipe columns, tension cables, and A-frames were installed. The masts, pipe columns, and A-frames from the original structure were re-used, with new struts and tension cables. During the subsequent two weeks, the second row of masts, struts, pipe columns, tension cables, and A-frames were erected. Upon erection of the steel structure, retrofitting of the stage house was performed. Installation and tensioning of the fabric occurred during a 50-day period, which ended on April 26 — five days before the opening concert. At that point, just enough time was left to complete the seating, handrails, landscaping, and final painting. The completed restored and expanded structure. D E S I G N & E N G I N E E R I N G Technological Tools contractor and structural engineer to discuss modifications of structural steel connections. Application of the latest technologies enabled the project to be delivered ontime. As mentioned, wind pressures from a desktop computer study were utilized for design before the wind tunnel analysis could be performed. In addition, a specialty membrane and cable-net program was employed for analysis of the fabric roof, and an additional program was used to pattern the fabric for installation purposes. Results from the fabric roof analysis were imported into SAP 2000 for incorporation in the design of the structural members. Although AutoCAD was used for documentation, Google Sketch-Up was employed to create a three-dimensional model of the steel structure and fabric. This model was used by Walter P Moore to determine the connection geometry and cable lengths. Portions of the model were exported into AutoCAD to facilitate drafting structural details. When the fabric patterning shape was imported into the Sketch-Up model, which included the structural steel, potential interferences between the fabric and the steel structure were determined. The model was also used to facilitate discussions between the steel detailer and structural engineer regarding the orientation of the A-frames, and between the general A Standing Ovation for the Project The Cynthia Woods Mitchell Pavilion underwent a fast-tracked transformation after Hurricane Ike left its roof in tatters. With a concerted team effort, the expanded amphitheatre opened on time in May to begin its 2009 season as a prime venue like it was before Ike’s glancing blows. Horst Berger, the world-renowned designer of both the original and the expanded Pavilion, appreciates the success of the project team. “The space, in spite of its huge dimensions, has retained its sense of intimacy. I remember that, to my pleasure, sitting under this roof at the opening concert of the Houston Symphony [in 1990] felt as intimate as sitting in Carnegie Hall. I think the new space is even better,” he remarked. J About the authors: Tarek Ayoubi, P.E., is a principal and senior project manager at Walter P Moore. Rachel Calafell is a graduate engineer at Walter P Moore. They can be reached at +1 800.364.7300. IMAGE: JEFF YOUNG AUTUMN/FALL 2009 PA N S TA D I A 85