Phase 5 $8000000 - Town of North Topsail Beach
Transcription
Phase 5 $8000000 - Town of North Topsail Beach
Town of North Topsail Beach Shoreline Protection Presentation Future Planning November 1, 2012 Disposal Area 143 Cores collected from island in December 2011 Geotechnical analysis completed on 13 separate cores Only beach quality sand was considered Small lenses of silty material existed within prime sand Grain size analysis for each layer 52 separate samples taken and analyzed Volumes for each core layer were calculated Weighted Average calculated based on grain size statistics and represent separate stratigraphic layers within island Comparison to Native Sand Source % Fines % Carbonate % Granular % Gravel Mean (mm) Volume (cy) Acreage Native Beach 1.5 25.8 1.1 .4 0.23 N/A N/A State Cutoff 6.5 40.8 6.1 5.4 N/A N/A N/A DA‐143 3.7 7.0 .9 1.4 0.22 1,940,000 48 Native sand numbers from December 2009 EIS State Standard Allowance used as threshold for grain size parameters and characteristics Gravel is greater than or equal to 4.76 mm Granular is between 2 mm and 4.76 mm Fines are smaller than .0625 mm Calcium Carbonate testing done by USACE approved lab Completed for each sample collected Weighted averages for each core and entire island EXISTING PHASED PLAN Phases 1 & 2 Phases 4 & 3 Phase 5 Costs of Existing Plan EVENT 1 Construct Phase 1 $5,614,000 597,000 cy EVENT 2 Construct Phases 2 & 4 Nourish Phase 1 $18,916,000 1,493,300 cy 200,000 cy EVENT 3 Construct Phases 3 & 5 Nourish Phase 1,2, & 4 $17,265,000 806,200 cy 530,000 cy TOTAL CONSTRUCTION COST Through 2025 $41,795,000 DA 143 Material Can feasibly be used in Phases 1‐4 USACE & CAMA Permitting Modifying the EIS will require a supplemental document Main Hurdle is the Grain Size Restriction “Point of Intercept Design” Section 6.1 of EIS and associated permit conditions. Hard Bottom Profiles New Dune and Berm Construction 300’ October 2011 beach cross section from North Topsail Beach Monitoring Station 106+00, near N. Topsail Beach Fire Department 8 years of Historic Data from Figure 8 Island Direct or indirect impact from 6 separate tropical systems Ophelia, Ernesto, Andrea, Hanna, Earl, Irene 3 separate beachfill events (~900,000 CY total) All profiles tie in before impacts to hard bottom would occur 300’ buffer with new primary dune and berm construction Hard Bottom Profiles New Berm Construction 400’ October 2011 beach cross section from North Topsail Beach Monitoring Station 106+00, near N. Topsail Beach Fire Department 8 years of Historic Data from Figure 8 Island Direct or indirect impact from 6 separate tropical systems Ophelia, Ernesto, Andrea, Hanna, Earl, Irene 3 separate beachfill events (~900,000 CY total) All profiles tie in before impacts to hard bottom would occur 400’ Buffer with new berm construction only Hard Bottom Profiles New Berm Construction 450’ October 2011 beach cross section from North Topsail Beach Monitoring Station 106+00, near N. Topsail Beach Fire Department 2 years of Historic Data from Figure 8 Island 980,000 CY and 147,500 CY beachfill projects Hurricane Irene in August 2011 All profiles tie in before impacts to hard bottom would occur 450’ Buffer with new berm construction only Inlet Maintenance Crossroads Dredging USACE maintains inlet crossroads yearly While dredge is on site, address other areas of shoaling Improves overall navigation MOB cost is spread out over multiple projects Material is placed on North End of Topsail Island Specs do not dictate placement of material Control where material is disposed of on beach front Sand must remain in system between events Reduce amount of material lost back into inlet Cu rre nt P Ar lac ea em en t Additional Navigation Maintenance Working with the USACE Dredge Murden just added to USACE hopper fleet in late 2011 Shallow draft dredging capabilities of less than 10’ MLW Need to allow these dredges to access shoaling within New River Inlet Current authorized depths of ‐6+2’ MLW within Inlet Material is moved from shoal to nearshore surf zone Naturally distributed on beachface by wave activity Adds sand to beach’s sediment budget Great solution for moving inside shoaling from New River to Phase 5 nourishment area Costs of a Revised Plan Use of Disposal Area 143 $275,000 Permitting Engineering & Design $200,000 $ 75,000 Estimated Cost of Construction $15,900,000 Place 1,900,000 cy in Phase 2,3, & 4 Areas ($7.25/cy and $1,500,000 Mobilization) Construction Management & Surveys $15,300,000 $600,000 Phase 5 $8,000,000 700,000 cy through MOA USACE Hopper Fleet 500,000 cy utilizing Inlet Material and Pump Out Construction Management & Surveys $300,000** Revised Long Term Plan FEMA Compliance $40,000 Summary • Initial Construction Phases 2‐4 $16,175,000 Material to come from DA143 (2015) • Phase 1 Maintenance $150,000/yr AIWW & Cedar Bush Cut (cost differential) • Phase 5 $8,000,000 Maintenance Material from Inlet Cut Potentially over 4‐5 years 2014‐2018 • Long Term Maintenance from Inlet & Cross Roads • Offshore Borrow Areas Held in Reserve for Coastal Storm Events Partnering