PDF Document

Transcription

PDF Document
VISOR
Visualisation of Real Time System Dynamics
using Enhanced Monitoring
Low Carbon Networks & Innovation Conference
October 2014
Mikel Urizarbarrena
ScottishPower Energy Networks
Project: VISOR
Visualisation of Real Time System Dynamics using Wide Area Monitoring
Aim: Reduce costs to UK consumers through
increased system efficiency and lower network
investment.
Cost: £7.44m Timeframe: Dec 2013 – Mar 2017
Savings: £50m per 100MW investment and £4m per
annum operational savings.
Background:
International consensus is the Transmission network
is changing and a new generation of monitoring and
controlling is required - SPEN intends to bring this
field forward.
Solution:
New monitoring will include time-stamped
synchronised measurements with greater visibility of
dynamic behaviour and sub-synchronous oscillations,
with easy data recall and analysis capability.
Low Carbon Networks & Innovation Conference 2014
2
VISOR –
“We will develop a system which is capable of monitoring and
modelling the behaviour of the transmission system at a level of
detail and sophistication never achieved before. The outputs will
be used to better inform transmission investment decisions and
to reduce network constraints”
Low Carbon Networks & Innovation Conference 2014
3
GB Transient Stability Boundary with Wind
P
B6 (Cheviot) Boundary
~ 3.5GW Transient Stability Limit (P)
~ 1.5GW Wind Capacity in Corridor
 Volatility in corridor capability
Low Carbon Networks & Innovation Conference 2014
4
GB Transient Stability Boundary with Wind
Expressing Limit as Angle
•
•
•
Low Carbon Networks & Innovation Conference 2014
Transient stability closely related
to angle difference
Define limits by Angle, not MW
alone
Possible future use of angle in
new HVDC control
5
Progress Summary
High level project progress
 Project
Direction Signed:
 Project Kick off:
 PDT spanning all three TOs:
 First academic output:
 Procurement arranged:
19-December-2013
20-December-2013
Appointed
1-April-2014
1-August-2014
Contract awarded to Alstom Grid
Low Carbon Networks & Innovation Conference 2014
6
Key Objectives
Synchronised measurements and real-time visualisation
Real-time visualisation of the power system for improved
Operation
Improved Monitoring for reduced uncertainty
Monitoring Sub-Synchronous Oscillations (SSO) using new
technology
Low Carbon Networks & Innovation Conference 2014
7
Key Challenges
Complex Project Delivery Organisation
 By its very nature, the project delivery responsibility is split between
multiple businesses and parties. While this adds considerable complexity
to the management and operational aspects of the project, it provides an
excellent opportunity for strong collaboration between the key industry
players.
Procurement Risk
 Software and hardware critical to the core elements of the project.
Procurement of services from Alstom-Psymetrix has successfully avoided
one of the largest risks to VISOR’s completion.
Technically Advanced Objectives
 Project is not simple from a technical perspective. Extra recruitment and
collaboration has brought sufficient expertise to the project to achieve our
targets.
Low Carbon Networks & Innovation Conference 2014
8
Next Steps
o
o
o
o
Delivery of first PMU devices
Factory acceptance testing by the end of the year
Firmware updates by Psymetrix-Alstom
Implementation of data infrastructure between SSE,
SP Energy Networks and National Grid
Low Carbon Networks & Innovation Conference 2014
9