study on phuoc an bridge construction project
Transcription
study on phuoc an bridge construction project
STUDY ON ECONOMIC PARTNERSHIP PROJECTS IN DEVELOPING COUNTRIES IN FY2010 STUDY ON PHUOC AN BRIDGE CONSTRUCTION PROJECT ON CAI MEP - THI VAI INTER-PORT ROAD IN THE SOCIALIST REPUBLIC OF VIETNAM FINAL REPORT March 2011 Prepared for: The Ministry of Economy, Trade and Industry Prepared by: Ernst & Young Shin Nihon LLC Japan External Trade Organization (JETRO) CHODAI Co.,LTD. NIPPON KOEI Co.,LTD. KAJIMA CORPORATION Reproduction Prohibited PREFACE This report describes the study on the Economic Partnership Project in Developing Counties in FY2010 for Phuoc An Bridge Construction Project in Vietnam. The study was carried out in accordance with the contract between Ernst & Young Shin Nihon LLC (SNC), the Client, and the study team formed by Chodai Co., Ltd. (the leader), Nippon Koei Co., Ltd. and Kajima Corporation. This study, namely “Study on Phuoc An Bridge Construction Project on Cai Mep – Thi Vai Inter-port Road in the Socialist Republic of Vietnam,” reviews and updates as appropriate the project report entitled “Report on Investment Construction Project of Cai Mep – Thi Vai Inter-port Road, Ba Ria – Vung Tau and Dong Nai Province” prepared by a Vietnamese consultant in 2009. In addition, applicability of the STEP scheme of Japanese ODA to this Project is also examined. We hope that this report will contribute to the promotion of the Project and become a useful reference document for relevant authorities and groups involved in this Project. March, 2010 Chodai Co., Ltd., Nippon Koei Co., Ltd. Kajima Corporation N HANOI Project Location DA NANG HCMC 200km 0 10 Bien Hoa 20 (km) HCMC N Long Thanh Airport Express Highway National Highway Ben Luc Industrial Aria Ben Luc-Long Thanh Exp. Phuoc An Bridge Cai Mep-Thi Vai Inter-Port Road Cai Mep-Thi Vai Inter-Port Vung Tau TABLE OF CONTENTS Preface Abstract (under preparation) Chapter 1 Outline of Vietnam and Related Sectors ······································································ 1-1 1.1 Economic and Financial Background of Vietnam ································································· 1-1 1.1.1 Economic Background···························································································· 1-1 1.1.2 Financial Background ····························································································· 1-7 1.1.3 Economic Relationship with Japan········································································ 1-10 1.2 Outline of Sectors for the Project ······················································································· 1-10 1.3 Present Conditions of Project Areas ··················································································· 1-10 1.3.1 Outline of Ports ···································································································· 1-10 1.3.2 Current Conditions of Existing Roads ···································································· 1-11 1.3.3 Construction Conditions of Port/Industrial Facilities ············································· 1-12 1.3.4 Present Status of North-South Highway through Cai Mep-Thi Vai Port ················· 1-13 1.3.5 Construction Point of Phuoc An Bridge································································· 1-14 Chapter 2 Study Method ············································································································· 2-1 2.1 Study Contents ···················································································································· 2-1 2.1.1 Bridge Plan And Design ························································································· 2-1 2.1.2 Traffic Demand Forecast ························································································ 2-1 2.1.3 Road Planning ········································································································ 2-1 2.1.4 River and Natural Conditions·················································································· 2-2 2.1.5 Environmental and Social Considerations ······························································· 2-2 2.1.6 Construction Schedule and Cost Estimate ······························································· 2-2 2.1.7 Financial and Economical Analysis ········································································· 2-2 2.2 Study Method and Organization ·························································································· 2-3 2.2.1 Work Description ··································································································· 2-3 2.2.2 Study Team Organization ························································································ 2-5 2.3 Assignment Schedule ·········································································································· 2-6 2.4 Site Investigation Schedule ································································································· 2-7 2.5 Persons Interviewed ············································································································ 2-8 Chapter 3 Contents of the Project and Technical Feasibility ··················································· 3-1 3.1 Background and Necessity of the Project ············································································· 3-1 i 3.1.1 Scope of Project ·································································································· 3-1 3.1.2 Necessity of the Project ·························································································· 3-2 3.2 Basic Policy of Host Country for Implementation of the Project ········································· 3-3 3.3 3.4 3.2.1 Location of the Project ························································································ 3-3 3.2.2 Outline of plan of Cai Mep- Thi Vai Inter-port road ··············································· 3-4 3.2.3 Outline of plan of the road to Phuoc An port ······················································· 3-8 Considerations necessary for Determination of Project Contents ······································· 3-11 3.3.1 Traffic Demand Forecast······················································································ 3-11 3.3.2 Project Location and Natural Conditions ····························································· 3-16 3.3.3 Engineering Study ······························································································ 3-23 Outline of project ············································································································ 3-30 3.4.1 Concept for Determination for Contents of the Project ········································ 3-30 3.4.2 Design Concept and Specifications for Bridge····················································· 3-30 3.4.3 The contents of proposed project········································································· 3-35 3.4.4 Technical Issues and Solutions ············································································ 3-36 Chapter 4 Considerations on Natural and Social Environments ···················································· 4-1 4.1 Status Analysis on Current Conditions of Natural and Social Environmental Aspects ··········· 4-1 4.1.1 Outline of the Project Area······················································································ 4-1 4.1.2 Project site and Environmental Conditions ······························································ 4-2 4.1.3 Alignment of Inter-Port Road and Phuoc An Bridge················································ 4-3 4.1.4 Bridge Types and Road Specification ······································································ 4-4 4.1.5 Environmental Impact Assessment (EIA) ································································ 4-4 4.1.6 Prospects of future environment·············································································· 4-5 4.2 Environmental Improvement by Implementation of the Project ············································ 4-6 4.2.1 General ·················································································································· 4-6 4.2.2 Estimate of CO2 Emission ······················································································ 4-6 4.3 Impacts on Natural and Social Environments due to Implementation of the Project ·············· 4-9 4.4 Overview of Regulations/Laws for Natural and Social Environments of Host Country ······· 4-16 4.5 Required Actions of Host Country and/or Relevant Groups for Implementation of the Project4-20 Chapter 5 Financial and Economic Feasibility ············································································· 5-1 5.1 Conclusion of Cost Estimate and Construction Work Plan···················································· 5-1 5.2 Estimate of Project Cost ······································································································ 5-1 5.2.1 Basic Conditions ···································································································· 5-1 ii 5.2.2 Estimated Items ······································································································ 5-1 5.2.3 Calculation Of Construction Expense······································································ 5-2 5.2.4 Calculation of Project Cost ····················································································· 5-3 5.2.5 Calculation of Ratio of material, equipment and others of Japan origin ···················· 5-4 5.2.6 Maintenance Cost ··································································································· 5-5 5.2.7 Comparison of construction costs ··········································································· 5-5 5.3 Overview of Preliminary Financial/Economic Analysis ······················································· 5-7 5.3.1 Economic Analysis ································································································· 5-7 5.3.2 Financial Analysis ································································································· 5-11 5.3.3 Conclusion ··········································································································· 5-17 Chapter 6 Implementation Schedule of the Project ······································································ 6-1 6.1 Calculations of Total Project Schedule ················································································· 6-1 6.1.1 Procedures until Feasibility Study Review ······························································ 6-1 6.1.2 Feasibility Study Review, Basic and Detailed Design, and Bidding Preparation ······· 6-1 6.1.3 Construction Work·································································································· 6-1 6.2 Outline of Construction Work Plan ······················································································ 6-5 6.2.1 General Item··········································································································· 6-5 6.2.2 Construction of Approach Bridge Substructure························································ 6-5 6.2.3 Erection of Approach Bridge Superstructure ··························································· 6-6 6.2.4 Construction of Substructure and Tower of Main Bridge ········································· 6-6 6.2.5 Construction of Superstructure Main Bridge ··························································· 6-6 Chapter 7 Ability of Implementation Authorities in Vietnam ······················································· 7-1 7.1 Outline of Implementation Authorities ················································································· 7-1 7.2 Project Implementation Organization··················································································· 7-1 7.3 Ability Evaluation and Necessary Countermeasures····························································· 7-1 Chapter 8 Superiority of Japanese Firm in Technology ································································ 8-1 8.1 International Competitiveness and Possibility for order in take for Japanese Firm ················ 8-1 8.1.1 Project Features ······································································································ 8-1 8.1.2 International Competitiveness and Possibility for order in take for Japanese Firm ··· 8-1 8.2 Content of Material & Equipment and Cost to be Procured from Japan ······························ 8-10 8.2.1 Content of Material & Equipment to be Procured from Japan ································ 8-10 8.2.2 Cost Estimation for Japanese Technology ······························································ 8-11 8.3 Necessary Measure of Japanese firms to receipt of orders ··················································· 8-11 iii Chapter 9 Conclusions and Recommendations ············································································ 9-1 9.1 Conclusions ························································································································ 9-1 9.2 Recommendations ··············································································································· 9-2 iv List of Figures Figure 1-1 GDP Change for Past 10 Years ················································································· 1-4 Figure 1-2 Structural Ratio by Industry (2000) ·········································································· 1-4 Figure 1-3 Structural Ratio by Industry (2009) ·········································································· 1-5 Figure 1-4 Population Ratios in Vietnam ··················································································· 1-5 Figure 1-5 Port Locations in Vietnam ······················································································· 1-11 Figure 1-6 Current Conditions of Existing Roads ···································································· 1-12 Figure 1-7 Present Construction Status of Port/Industrial Facilities ·········································· 1-12 Figure 1-8 Present Status of North-South Highway through Cai Mep-Thi Vai Port ··················· 1-13 Figure 1-9 Present Status of Phuoc An Bridge ········································································· 1-14 Figure 3-1 Scope of Project ······································································································· 3-1 Figure 3-2 Industrial Parks near Ho Chi Minh City ···································································· 3-2 Figure 3-3 Location of the project ····························································································· 3-4 Figure 3-4 Outline of the rout ···································································································· 3-5 Figure 3-5 Typical Cross Section (Component No.1~No.2)······················································ 3-6 Figure 3-6 Typical Cross Section (Component No.3~No.8)······················································ 3-6 Figure 3-7 Typical Cross Section (Phase No1 of Component No.9) ··········································· 3-7 Figure 3-8 Typical Cross Section (Phase No2 of Component No.9) ··········································· 3-7 Figure 3-9 Interchange Plan ······································································································ 3-8 Figure 3-10 Road Profile ········································································································· 3-8 Figure 3-11 Outline of the Plan ································································································· 3-9 Figure 3-12 Typical Cross Section ··························································································· 3-10 Figure 3-13 Traffic Volume in 2020························································································· 3-12 Figure 3-14 Traffic Volume in 2030························································································· 3-12 Figure 3-15 Project Location ··································································································· 3-16 Figure 3-16 Scenery of Project Site ························································································· 3-16 Figure 3-17 Soil Profile (Vung Tau Side)················································································· 3-17 Figure 3-18 Location of Phuoc An Bridge ··············································································· 3-19 Figure 3-19 Daily Tidal Fluctuation in Vung Tau (Sample) ······················································ 3-20 Figure 3-20 Monthly Tidal Fluctuation in Vung Tau (Sample) ················································· 3-20 Figure 3-21 Seismic Classes and Record of Major Earthquakes in South Viet Nam ·················· 3-22 Figure 3-22 Control point for Abutments location···································································· 3-25 Figure 3-23 Consideration of Side Span Length······································································· 3-27 Figure 3-24 Proposal for alternative location of Dong Nai side pylon ······································ 3-29 v Figure 3-25 General View (1) ·································································································· 3-33 Figure 3-26 General View (2) ·································································································· 3-34 Figure 3-27 Location of the Project ························································································· 3-35 Figure 4-1 Distant View of the Project Area ·············································································· 4-1 Figure 4-2 Schematic Diagram of Roads and Facilities in the Project Area································· 4-1 Figure 4-3 Estimate of Emission of CO2 In and Around the Project Area from Vehicles ············· 4-8 Figure 4-4 Number of Vehicles Passing Phuoc An Bridge, NR51 and BV Expressway ··············· 4-8 Figure 4-5 Effect of CO2 Emission by the Implementation of the Project ··································· 4-9 Figure 4-6 Procedure of land acquisition ················································································· 4-19 Figure 5-1 Traffic Volume (With Case) in 2020 ········································································· 5-9 Figure 5-2 Traffic Volume (Without Case) in 2020 ···································································· 5-9 Figure 5-3 Traffic Volume (With Case)-(Without Case) in 2020 ················································· 5-9 Figure 6-1 Temporary Yard ······································································································· 6-5 Figure 7-1 Organization Chart of BVPPC·················································································· 7-1 Figure 7-2 Departments and Boards of BVPPC ········································································· 7-2 Figure 7-3 Schematic Organization Chart for Project Implementation ········································ 7-3 Figure 8-1 Yabegawa Grand Bridge ·························································································· 8-3 Figure 8-2 Conceptual Illustration for VCM ·············································································· 8-4 Figure 8-3 Comparison of Ground Improvement Method between Surcharge method and VCM 8-5 Figure 8-4 Transition for Actual Achievement of VCM ····························································· 8-5 Figure 8-5 Illustration of Screwed Steel Pile ·············································································· 8-6 Figure 8-6 Tip of Screwed Pile ·································································································· 8-6 Figure 8-7 Schematic of HMS ··································································································· 8-8 Figure 8-8 Case of HMS for Akashi-Kaikyo Bridge (Japan) ······················································ 8-9 vi List of Tables Table 1-1 Macroeconomic Indexes in Vietnam ········································································ 1-2 Table 1-2 GDP Structure by Industry (Real figures) ································································· 1-3 Table 1-3 Domestic Direct Investment Statistics (by Country/Region) ····································· 1-6 Table 1-4 Domestic Direct Investment Statistics (by Sector) ···················································· 1-7 Table 1-5 Export Statistics (by Country/Region) ······································································ 1-8 Table 1-6 Export Statistics (by Item) ······················································································· 1-8 Table 1-7 Import Statistics (by Country/Region) ······································································ 1-9 Table 1-8 Import Statistics (by Item) ······················································································· 1-9 Table 1-9 Scale and Results of Japan’s ODA Grants to Vietnam ············································· 1-10 Table 2-1 Members of the Study Team ···················································································· 2-5 Table 2-2 Assignment Schedule······························································································· 2-6 Table 2-3 Site Investigation Schedule ······················································································ 2-7 Table 2-4 List of Persons Interviewed ······················································································ 2-8 Table 3-1 Japanese Companies Operated in Industrial Parks near HCM City···························· 3-3 Table 3-2 Forecast Result (project was executed)··································································· 3-13 Table 3-3 Forecast Result (project was not executed) ····························································· 3-13 Table 3-4 The forecasted traffic volume in Ben Luc-Long Thanh ··········································· 3-13 Table 3-5 TCXDVN104-2007 Article 8.2.2 ··········································································· 3-14 Table 3-6 Number of Lanes Required of This Route ······························································ 3-15 Table 3-7 Summary of Soil Investigation Result (Vung Tau Side) Table 3-8 Summary of Meteorological Conditions ································································· 3-18 Table 3-9 Water Level for Phuoc An Bridge ·········································································· 3-21 Table 3-10 Major Seismic Activities Recorded in South Vietnam ············································· 3-21 Table 3-11 Wind Velocity and Direction at Project Area··························································· 3-23 ······································ 3-17 Table 3-12 Navigation Clearance for Phuoc An Bridge ···························································· 3-23 Table 3-13 Comparison of Bridge Types ·················································································· 3-26 Table 3-14 Selection of Approach Bridge Foundation Types ···················································· 3-28 Table 3-15 Technical Issues and Solutions ··············································································· 3-36 Table 4-1 Land use of Phuoc Hoa Commune ··········································································· 4-2 Table 4-2 Status of Implementation of EIA in Cai Mep-Thi Vai Inter-Port Road Project ········· 4-5 Table 4-3 Estimate of Traffic Volume ······················································································ 4-6 Table 4-4 Running Speed of Vehicle ························································································ 4-7 Table 4-5 Emission Coefficient of CO2 ···················································································· 4-7 Table 4-6 Emission of CO2 in and around the Project Area from Vehicle ···································· 4-7 vii Table 4-7 Estimate of Reduction of CO2 Emission by the Implementation of the Project ········· 4-9 Table 4-8 Environmental Checklist: 16. Roads, Railways and Bridges ······································ 4-11 Table 4-9 Major Laws and Regulations Concerning Environmental Protection in Vietnam ······· 4-16 Table 4-10 Major Laws and Regulations Concerning Procedures of Land Acquisition·············· 4-18 Table 5-1 Preliminary Construction Expense ············································································· 5-3 Table 5-2 Preliminary Total Project Cost ··················································································· 5-4 Table 5-3 Annual Maintenance Cost ·························································································· 5-5 Table 5-4 Comparison of Locations of Main Bridge Towers ······················································ 5-6 Table 5-5 Comparison of Foundation Pile·················································································· 5-6 Table 5-6 Time saving cost ······································································································· 5-8 Table 5-7 Vehicle operating cost ······························································································· 5-8 Table 5-8 Results of cost benefit analysis ················································································ 5-10 Table 5-9 Cost and Benefit ······································································································· 5-11 Table 5-10 Result of sensitivity analysis ·················································································· 5-12 Table 5-11 STEP loan condition ······························································································ 5-14 Table 5-12 Revenue by Year ···································································································· 5-14 Table 5-13 Financial analysis ·································································································· 5-16 Table 5-14 Result of sensitivity analysis ·················································································· 5-17 Table 6-1 Total Project Schedule (Tentative) ············································································· 6-2 Table 6-2 Project Schedule before Design Phase (Tentative) ······················································ 6-3 Table 6-3 Construction Schedule (Tentative) ··········································································· 6-4 Table 8-1 Major Achievement for Concrete Cable Stayed Bridges ············································· 8-2 Table 8-2 Comparison Result ···································································································· 8-4 Table 8-3 Comparison Result for Screwed Steel Pile and Bored Pile ·········································· 8-7 Table 8-4 Actual Achievements of SHMS ················································································· 8-9 Table 8-5 Material & Equipment List to be Procured from Japan ············································· 8-10 Table 8-6 Cost Estimate for Japanese Technology····································································· 8-11 Table 9-1 Project Costs Summary······························································································ 9-1 Table 9-2 Results of Preliminary Economic Analysis ································································· 9-1 viii APPENDIX APPENDIX-1: BRITEC F/S (Report on Investment Construction Project of Cai Mep – Thi Vai Inter-port Road, Ba Ria – Vung Tau and Dong Nai Province) 1-1 Original Vietnamese Version (Cover page and the Table of Contents) 1-2 English Translation of the Table of Contents APPENDIX-2: Decision No. 2669/QD-UBND (BVPPC approved BRITEC F/S) 2-1 Original Vietnamese Version (the first page only) 2-2 English Translation (Excerpt) APPENDIX-3: Letter No. 614/CHHVN-KHDT (Instruction for navigation clearance issued by the Maritime Bureau of MOT) 3-1 Original Vietnamese Version 3-2 English Translation APPENDIX-4: Announcement No. 255/UBND-TB (Conclusions of the meeting between BVPPC and DNPPC regarding CM-TV Inter-port Road Investment Project) 4-1 Original Vietnamese Version 4-2 English Translation APPENDIX-5: Data for Construction Costs APPENDIX-6: JBIC Screening Form ( for social and environmental considerations) APPENDIX-7: Data for Geological/Topographic Conditions ix Abbreviations and Acronyms Abbreviation /Acronym Full Names ADB Asian Development Bank B/C Ratio Cost-Benefit Ratio B/D Basic Design BH-VT Bien Hoa – Vung Tau BL-LT Ben Luc – Long Thanh BRITEC BVPPC Bridge & Tunnel Engineering Joint Stock Company Report on Investment Construction Project of Cai Mep – Thi Vai Inter-port Road, Ba Ria – Vung Tau and Dong Nai Province Ba Ria – Vung Tau Provincial People’s Committee D/D Detailed Design CM-TV Cai Mep – Thi Vai DNPPC Dong Nai Provincial People’s Committee DONRE Department of Natural Resources and Environment DOT Department of Transportation DWT Dead Weight Tonnage EIA Environmental Impact Assessment EIRR Economic Internal Rate of Return EL Elevation Level E/N Exchange of Notes FDI Foreign Direct Investment FIRR Financial Internal Rate of Return F/S Feasibility Study GDP Gross Domestic Product GL Ground Level GNI Gross National Income GOJ Government of Japan GOV Government of Vietnam HLTD HCMC - Long Thanh - Dau Giay HCMC Ho Chi Minh City HMS Health Monitoring System HWL High Water Level IEE Initial Environmental Evaluation JBIC Japan Bank of International Cooperation BRITEC Report JETRO Japan External Trade Organization JICA Japan International Cooperation Agency JPC Japan Port Consultants, Ltd. JPY Japanese Yen L/A Loan Agreement MONRE Ministry of Natural Resources and Environment MOT Ministry of Transportation M/P Master Plan NH National Highway NK Nippon Koei Co., Ltd. NOx Nitrogen Oxide NPV Net Present Value N-value N-value OD Origin Destination ODA Official Development Assistance ORBITEC Orbit Engineering Design Consultants Joint Stock Company PC Prestressed Concrete PCU PMU POATCOAST Passenger Car Unit Project Management Unit Portcoast Consultants PVD Prefabricated Vertical Drain PVN PVNPAPIC PetroVietnam Petro Vietnam Phuoc An Port Investment and Operation Joint Stock Company ROW Right of Way RR Ring Road QV Quantity Velocity SAPROF Special Assistance for Project Formation SEIA Strategic Environmental Impact Assessment SNC Ernst & Young Shin Nihon LLC SP Stated Preference SPM Suspended Particulate Matter SPT Standard Penetration Test STEP Special Terms for Economic Partnership TEDI Transport Engineering Design Incorporated TEDI South Transport Engineering Design Incorporated South TEU Twenty-foot Equivalent Unit TOR Terms of Reference USD U.S. Dollar VAT Value-Added Tax VCM Vacuum Consolidation Method VINALINES Vietnam National Shipping Lines VITRANSS2 National Transport Development Strategy Project in Vietnam VND Vietnamese Dong VOC Vehicle Operating Cost WACC Weighted Average Cost of Capital WB World Bank STUDY ON ECONOMIC PARTNERSHIP PROJECTS IN DEVELOPING COUNTRIES IN FY2010 STUDY ON PHUOC AN BRIDGE CONSTRUCTION PROJECT ON CAI MEP - THI VAI INTER-PORT ROAD IN THE SOCIALIST REPUBLIC OF VIETNAM FINAL REPORT EXECUTIVE SUMMARY March 2011 Prepared for: The Ministry of Economy, Trade and Industry Prepared by: Ernst & Young Shin Nihon LLC Japan External Trade Organization (JETRO) CHODAI Co.,LTD. NIPPON KOEI Co.,LTD. KAJIMA CORPORATION Reproduction Prohibited Executive Summary 1. Background and Necessity of the Project 1.1 Background of the Project The Socialist Republic of Viet Nam (hereinafter referred to as “Vietnam”) enacted the Doi Moi (Renovation) Policy in 1986 and began obtaining its effects around 1989. After that, economic growth in Vietnam continued as high as 9% for the years of 1995 and 1996. In 1997, however, tendencies such as slow-down of the growth rate decreased under the impact of the Asian economic crisis, thereby decreasing the growth rate to 4.8% in 1999. After that, the growth rate gradually recovered and the rate of 5.3%, which was the second highest rate in the ASEAN region, was achieved through 2009. The Government set an economic growth goal to 6.5% for the fiscal year of 2010. Vietnam has a coastline of approximately 3,260km facing the South China Sea and there are more than 150 ports along the coastline, of which 6 ports, Northern, Central North, Central, Central South, Ho Chi Minh City and Mekong, are designated as the most important port areas. Hai Phong International Port (Northern), Van Phong International Port (Central South) and Cai Mep-Thi Vai International Port (Ho Chi Minh City) are designated as strategically important ports (international gateways). There are a number of port facilities in the environs of Ho Chi Minh City, but a plan to remove their functions to the Cai Mep-Thi Vai International Port is in progress due to the many problems such as traffic congestion in Ho Chi Minh City (running of large vehicles is permitted only at nighttime), aged facilities, and poor dredging of navigational channels. It is expected that the future cargo handling volume can be secured and the above problems can be solved by collecting the port facilities at the Cai Mep-Thi Vai Port where the water is deep. This project is planned at the end of the Cai Mep – Thi Vai Inter-port Road (Refer to Figure S1). Figure S1 Project Location 0 10 20km S-1 1.2 Necessity of the Project This project is located at north-end of the Cai Mep – Thi Vai Inter-port Road, along which various developments are ongoing at Cai Mep – Thi Vai International Port. When this project is completed, the road is a shortcut to nearby industrial parks and Ho Chi Minh City. Therefore, the Project is expected to contribute considerably to the business activity of the port facilities. Photo-S1 shows an aerial view of the northern part of the international port and the location of Phuoc An Bridge. This photo was taken several years ago. At the present time, however, numerous port facilities and factories are under construction everywhere in the area as shown in Photos S2 and S3. Photo S1 Northern Part of Cai Mep – Thi Vai International Port and Location of Phuoc An Bridge Phuoc An Bridge Phuoc An Port Gas facility My Xuan Port Petro Vietnam Facility Thi Vai River Thi Vai Port Inter-port Road Photo S2 Construction of Cai Mep – Thi Vai International Port (1) S-2 Photo S3 Construction of Cai Mep – Thi Vai International Port (2) The Phuoc An bridge of this project is a part of the Cai Mep- Thi Vai Inter-port road, and it is located on the east side of Cai Mep- Thi Vai international port. The Phuoc An bridge is located on the north side of the Cai Mep- Thi Vai Inter-port road, goes across the Thi Vai river, and is connected with the road to a Phuoc An industrial port that is the opposite bank. The road to a Phuoc An industrial port is connected with the Ben Luc- Long Thanh expressway on the north side further. The south of the Thi Vai river is Ba Ria-Vung Tau Province, and the north side is Dong Nai Province. The Phuoc An bridge is located in the province border. The section to connected interchange on the road to a Phuoc An industrial port is in charge of the Ba Ria-Vung Tau Province. According to the construction schedule of the two provinces, road construction to a Phuoc An industrial port of the Dong Nai Province aims at the completion in 2013 and the Phuoc An bridge construction of the Ba Ria-Vung Tau Province aims at completion in 2015. Both routes assume it is very important in the economic development strategy and are placed by the most important project of the two provinces. The scope of the Project is shown in Figure S2. Figure S2 Scope of the Project N Km 21+360 Km 18+100 0 500 1000 m S-3 2. Basic Policy for Implementation of the Project 2.1 Basic Policy of Vietnam for Implementation of the Project 2.1.1 Outline of Cai Mep – Thi Vai Inter Port Road (Ba Ria – Vung Tau Province) The large-scale port construction is actively ongoing in Cai Mep- Thi Vai international port now. However, there is no road that passes this area while the port construction is large-scale now. As for the BVDOT (Ba Ria – Vung Tau Province Department of Transportation), it is admitted that road works are late compared with the ports construction, and is hoped for the completion at the early stage of this route. The route divides into nine components and component No.2 in that is under construction by ODA. The object of this project is component No.9. There is no plan to make the route and the Phuoc An bridge a pay system, and it has the plan of the income by the port facilities use fee and the ship reach shore fee, etc. according to the hearing of BVPPC. Figure S3 shows the outline of the route. Figure S3 Outline of Cai Mep – Thi Vai Inter-port Road 0 2.5 5.0 km A feasibility study was carried out by BRITEC in 2009 and the results have been approved by BVPPC in August 2009. The title of the report is “Report on Investment Construction Project of Cai Mep – Thi Vai Inter-port Road, Ba Ria – Vung Tau and Dong Nai Province” (hereinafter referred to as BRITEC Report). This study reviews and updates, as appropriate, the BRITEC Report. S-4 2.1.2 Outline of the Project Phuoc An Bridge and the approach bridges are described in a part of BRITEC Report. Results of the review and additional information on the Project are described below: (1) Route Length The route length is 21.3km from the south of Cai Mep- Thi Vai international port of the Ba Ria-Vung Tau Province to the road to the Phuoc An industrial port of the Dong Nai Province . Phase No.1 and Phase No.2 (2) Component No.9 is divided into Phase No.1 and Phase No.2. The Phase No.1 length is about 1.55km from Km 18+100 to Km19+650, and the road of Phase No.1does not cross the Thi Vai river. The Phase No.2 length is about 3.26km from Km 18+100 to Km 21+360. And Phuoc An bridge, the approach road/bridge and grade-separated interchange at the end of alignment are included in the content of Phase No.2. Component No.0-No.8 and Phase No.1 of component No.9 schedules the completion in 2012, and Phase No.2 schedules the completion in 2015. Section of this study is this Phase No.2. (3) Design Standard, Classification, Design Speed Standard TCXDVN 104: 2007 (Urban Road Specifications for Design) Urban road classification: Main urban road Design speed (V) V=70km/ h Width of Right of Way (W) W=50m (4) Cross section of the road Typical cross sections are shown in Figures S4 and S5. Figure S4 Cross Section for Component No.9 (Phase 1) (source: BRITEC Report ,2009) S-5 Figure S5 Cross Sections for Component No.9 (Phase No2) (source: BRITEC Report ,2009) Approach Bridge Phuoc An Bridge (5) Interchange plan at the end of alignment The end of component No.9 that is the end of the Cai Mep- Thi Vai Inter-port road is connected with the road to Phuoc An industrial port by the interchange of the trumpet type (Refer to Figure S6). The BRITEC Report on the Cai Mep- Thi Vai Inter-port road is completed, and a part of section is under construction now. However, there is only this simple drawing for the interchange at the end of alignment now. Figure S6 Proposed Interchange at the End of the Project (source: BRITEC Report) S-6 The road profile is shown in Figure S7. Figure S7 Road Profile (source: BRITEC Report) 2.1.3 Outline of Plan of the Road to Phuoc An Port (Dong Nai Province) As for the construction of the road to a Phuoc An industrial port, the subsidiary company(Phuoc An port Investment Exploitation Petro Company) of Vietnam Petro who is the donor of the Phuoc An port project plans to execute it. A part of Phuoc An port and the road to a Phoc An industrial port schedule the opening in 2013. And, the F/S report by the PORTCOAST consultant will be completed soon. There are a railway plan and an existing gas pipeline in the approach bridge section. In hearing with DNPPC (Dong Nai Provincial People’s Committee), it is said that there is no specific program of the railway at all. The existing gas pipeline (The size of the pipe seems to be Φ200mm) is laid to the Phuoc An industrial port schedule ground. There is no concrete relocation plan now. It is necessary to secure the distance from the gas pipe by both sides 12.5m for each according to the safety standard in Vietnam. The distance on safety is secured by 25m for each in the FS report by the PORTCOAST consultant. The outline of the plan of Dong Nai Province is shown in Figure S8. S-7 Figure S8 Outline of the Plan of Dong Nai Province 0 2.5 5.0 km The cross section of the road to Phuoc An Industrial Port is shown in Figure S9. The half section is scheduled to be constructed in Phase No.1. The width of 19m on both sides contains the frontage road space in the future. Figure S9 Typical Cross Section of the Road to Phuoc An Industrial Port (Source: Dong Nai Provincial People’s Committee) 2.2 Basic Policy for Implementation of the Project 2.2.1 Traffic Demand Forecast There is no description that used the numerical value for traffic in the future in BRITEC Report report. In hearing with the BV-DOT and BV-consultant, the adoption of the number of four lanes is assumed to have followed the content that the government referred in the past. In this study, to confirm traffic and the number of lanes in the future, the traffic demand forecast was done. S-8 “The Comprehensive Study on the Sustainable Development of Transport System (VITRANSS 2)”, JICA Study, was conducted from July, 2007 to Sep, 2009. This study prepared person OD tables for 2008 by vehicle type based on the existing traffic pattern. In addition, it prepared person OD tables by vehicle type for 2010 and 2020 based on future socio-economic indicators, including population, number of jobs, etc., for each traffic zone. Afterwards, the zone was dropped from Province to District in "Survey & FS of Dau Giay - Phan Thiet Expressway Project". Thereafter, the study for Missing Road of Ho Chi Minh City was conducted. In this study, a peripheral road plan was reviewed as FS review of VITRANSS 2, and the traffic demand forecast for the years of 2030 and 2020 was done. In this study, the Cai Mep-Thi Vai international port zone is made as an independent zone by using the above-mentioned final network. And, the traffic demand forecast for the year of 2030 and 2020 was conducted being divide the amount of the freight in the future of Cai Mep - Thi Vai port and Vung Tau port. Based on the traffic demand forecast, it is considered reasonable to assume the required number of lanes is four (4) for Cai Mep - Thi Vai Inter-port road. As a result, the total lane number including the mixed lane is six (6). 2.2.2 Natural Conditions (1) Geographical and Geological Conditions The project area is located approximately 40km southeast of Ho Chi Minh city, where the Quaternary geology sediment, which is likely to seen at delta area, is mainly distributed since the location is outer Mekong Delta Area. The soil properties of the area are mostly composed of alluvial deposits, and the geological epoch is relatively young. Stretch of mangrove forest is covering over natural low-lying area around the project area. In general, low-lying area near a river mouth tends to show some particular phenomena due to the influences of ebb and flow and/or ocean waves, such as (i) repeatedly fluctuation of pore water pressure due to ground water level change, (ii) erosion due to water flow and waves, (iii) softening of soil due to permeation and water exposure, (iv) eluviation and deposition of sodium, and (v) deflation and hardening of soil. (2) Seismic Activities In regard to the seismic activities in the south VietNam, sixty four (64) times of seismic activities have been observed since the beginning of the seismic observation started 1903. The depth for seismic center is relatively shallow; around 10km to 20 km from ground elevation, whereas not any earthquakes have been recorded near the project area. Referring to Figure 3-21 extracted from Vietnamese standard of “SPECIFICATION for BRIDGE DESIGN (22TCN-272-05)”, the seismic class for this project shall be specified as Class 6. S-9 (3) Navigation Clearance The navigation clearance for this project, which was approved by VietNam Maritime Department by a letter 614/CHHVN-KHDT dated in April 3rd, 2009 (refer to Appendix-3), is shown in below table. Table S1 Navigation Clearance for Phuoc An Bridge Class of Vessel 30,000DWT Navigation Height(H) Mmax1%(+1.60m)+ 55.0m Navigation Width(B) 120m(for one way flow) 239m(for two ways flow) (Reference:BRITEC Report, 614/CHHVN-KHDT) (4) Other Natural Conditions Data and information for other natural conditions, such as for climate/weather, river characteristics, wind velocity/direction, were collected during the site survey. This study considered the data and information. 2.2.3 Engineering Study (1) Selection of Bridge Type of Phuoc An Bridge The following three types are compared for Phuoc An Bridge based on the navigation requirement of the width of 239m. The center span length is assumed to be 360m or more considering the foundation size and the allowance. Type 1: Cable Stayed Bridge Type 2: Suspension Bridge Type 3: Arch Bridge The comparison results are shown in Table S2. Based on the comparison, a cable stayed bridge (Type1) is selected due to economic efficiency and control of maintenance. Figure S10 shows the general view of Phuoc An Bridge and the approach bridges. S-10 Bridge Type S-11 Type1 Type2 Type3 Economic 1.20 Because a large horizontal force Constructive operate on Foundation, the foundation dimension broaden Maintenance Because the arch rib is a steelmade, it is required to repaint painting though the concrete girder. There are a lot of numbers of materials, and the operation and Economic 1.25 Because a large horizontal force Constructive operate on Anchorage, the foundation dimension broaden Maintenance Because the girder is a steel, it is required to repaint the painting of the girder though the concrete Pylon. 【recommended practice】 Estimation Economic 1.00 Due to structural feature, a Constructive Large horizontal force doesn't operate on foundation . Maintenance Because Girder and Pylon are concretes, The repainting painting are unnecessary. Table S2 Comparison of Bridge Types <― To Vung Tau To Dong Nai ―> Figure S10 General View S-12 3. Scale of the Project 3.1 Construction Cost Table S3 shows the construction cost based on the preliminary calculations. The construction cost is approximately 21.2 billion JPY, or 4,986 billion VND. Assuming 10% of the construction cost for each of the consultant fee and the contingency, the total cost is approximately 25.5 billion JPY, or 5,938 billion VND. Table S3 Preliminary Construction Expense Item JPY(Mill.) VND(Mill.) Equivalent JPY(Mill.) 233 Equivalent VND(Mill.) 233 161 458,522 2,129 496,004 5,963 1,127,364 10,801 2,516,696 5,533 117 437,599 20,945 7,411 207 1,726,693 48,121 87 45,905 284 66,105 61 11,920 1,192 1,192 14,305 80,243 2,170,577 217,058 217,058 2,604,693 405 21,236 2,124 2,124 25,484 94,432 4,948,051 494,805 494,805 5,937,661 General Item L=2,478.5m Approach Bridge W=23.5m Main Bridge L=746m Accessories L=3,260m Km18+100 to Approach Road Km18+378.97 L≒280m Interchange 1 Lot Construction Cost Consultant Fee Contingency Total 3.2 10% 10% Calculation of Ratio of Material, Equipment and Others of Japan Origin Table S4 shows the calculation of a ratio of material, equipment and others of Japan origin based on the guidelines prepared by relevant ministries of Japan. As shown in the table, the 30% condition for STEP scheme is satisfied. Table S4 Ratio of material, equipment and others of Japan origin Item Cost for Japanese Technology Material Machine t Stay cable Wind tunnel test Cast in pile Cost JPY( Mill.) Remark 2,511 225 812 10 Sub total (ii) estimated in Table 8-5 Procured from Japan Stay Cables (Material and installation cost) Contain test Model 1,676 D=2.5m for Main bridge (Material and installation cost) 10% of Construction cost (assumption) - General and administrative cost: 7% - Site office overhead: 3% About 73 hundred-millions Engineering Total (i) 2,124 7,357 Total Project Cost (ii) Ratio 21,236 34.6% About 212 hundred-millions >30.0% (i)/(ii) *: Material const shown in table 8-3 is exclusive of the material cost for stay cables. *: Engineering cost is assumed as a summation of General and Administrative cost (7%) and Site Office Overhead (3%: remuneration for Japanese engineers). S-13 3.3 Overview of Preliminary Economic/Finance Analysis 3.3.1 Economic Analysis In order to evaluate the effectiveness of this project from the viewpoint of the national economy, a comparative analysis of economic cost and benefit both in the case of executing the project (With the project) and not executing the project (Without the project) is carried out. As the evaluation index, Economic Internal Rate of Return (EIRR), Benefit Cost Ratio (B/C Ratio) and Net Present Value (NPV) are applied. The results of the analysis based on the assumed benefits and costs are shown in Table S5. As all the index values for the evaluation are at a good level, this project is considered to be economically feasible. Table S5 Results of cost benefit analysis (Discount Rate=15%) B/C Ratio Net Present Value (NPV) EIRR 1.83 185.40 million US$ 27.5 % In the elements assumed for the economic analysis, variable factors are included in each element and some elements are based on simple assumptions. As a sensitivity analysis, some margin will be given in accordance with such variable factors and by finding out how the result of the analysis will vary; the stability of the feasibility of this project will be confirmed. The result of the sensitivity analysis is shown in Table S6. Table S6 Result of Sensitivity Analysis on Economic Analysis Benefit 20% 10% 0% -10% -20% -20% 38.0% 35.6% 33.1% 30.4% 27.5% -10% 34.8% 32.5% 30.1% 27.5% 24.8% Cost 0% 32.0% 29.8% 27.5% 25.1% 22.5% 10% 29.6% 27.5% 25.3% 22.9% 20.5% 20% 27.5% 25.5% 23.3% 21.1% 18.7% From the results of analysis shown in the above table, the value of EIRR exceeds 15% even in the case of 20% cost increase or 20% benefit decrease so the possibility of realization of this project is high. 3.3.2 Financial Analysis The FIRR of the Project is 3.37% when the toll is assumed to be 2US$/PCU in the year of 2030. As the value of 3.37% exceeds the standard value of 2.89% calculated based on the assumed proportion of invested JPY and VND, the Project is considered to be financially viable. In the elements assumed for this analysis (Investment cost and revenue), unknown factors are included. Some margin will be added to each element corresponding to each unknown factor, the variation of the S-14 result of the analysis is observed and the financial stability of this project will be verified. The result of the sensitivity analysis on the financial analysis is shown in Table S7. From the table, it is found that the value of FIRR does not satisfy the standard value by WACC in case of 10% cost increase and 10% revenue decrease. Accordingly, the project shall be executed based on the proper construction plan and operation plan. More specifically, the application of low interest and long term finance such as STEP special Yen credit is an essential condition. Table S7 Result of Sensitivity Analysis on Financial Analysis -20% Revenue 20% 10% 0% -10% -20% 6.02% 5.42% 4.79% 4.11% 3.37% Construction cost -10% 0% 5.22% 4.64% 4.03% 3.37% 2.66% 4.52% 3.96% 3.37% 2.73% 2.04% 10% 20% 3.91% 3.37% 2.79% 2.17% 1.49% 3.37% 2.84% 2.28% 1.66% 1.00% 3.3 Considerations on Natural and Social Environments The Project for development of Cai Mep-Thi Vai International Port is now progressing. The Cai Mep-Thi Vai Inter-Port Road Construction Project which includes the Phuoc An Bridge Construction Project is considered as a part of the Project for development of Cai Mep-Thi Vai International Port. The EIA study for the Cai Mep-Thi Vai International Port Project has already been conducted by the project proponent and approved by MONRE and DONRE. According to the EIA report for the port development project above mentioned, potential impacts on the environment, both natural and social, arising from the implementation of the project are concluded to be not serious one. Apart from the EIA study for the Cai Mep-Thi Vai International Port Project, EIA studies for the Component No.9 of the Inter-port road are also required according to the Vietnamese environmental related laws and regulations. The EIA for the Phuoc An Bridge construction project has not been conducted yet. Due to the reason that the Phuoc An Bridge stretches over two provinces, Ba Ria-Vung Tau and Dong Nai, the EIA report prepared is appraised and approved by MONRE. This study is conducted in the earliest phase of the decision making process. The major objective of “Environmental and social considerations” in project formation studies is to provide data to determine whether the project should be taken to the next phase, and to clearly identify a broad range of items to be investigated in the next phase, if the project goes forward, from an environmental and social standpoint. According to the JBIC guidelines, all proposed projects are to be classified into three categories, namely those likely to have a significant environmental and social impact (Category A), those likely to have a less adverse environmental and social impact than that of Category A projects (Category B), and those likely have a minimal or no adverse environmental and social impact (Category C). Based on the conclusion of the EIA of the Cai Mep International Port development project, the Project of Phuoc An Bridge can be classified into Category B project. Although submission of EIA reports to JBIC is not a mandatory S-15 requirement for Category B project, it is recommended that the project proponent should submit the EIA reports and environmental permit certificates issued by the government of Vietnam or other appropriate authority following Category A projects. In this study, major impacts on natural and social environments are reviewed in accordance with the JBIC screening formats. The results are attached in the main report of this study. 4. Implementation Schedule A tentative schedule from the present time to completion of the construction is shown in Table S8. At the beginning, implementation method is discussed among relevant authorities in Vietnam. When the implementation by Japanese ODA is selected, GOV (Government of Vietnam) request to JICA Hanoi for the ODA application followed by bilateral discussion and investigation on the Project. In Table S8, it is assumed that SAPROF (Special Assistance for Project Formation) is carried out because of the immature level of BRITEC Report. When both countries agreed, the L/A (Loan Agreement) is signed by the two countries based on the agreed TOR (Terms of Reference) of the ODA. A required period for the said process varies depending on the contents of a project. Based on the information of the past similar projects, the time of the L/A is assumed to be January 2013. After the L/A, works including selection of the consultant, the design phase and bidding for contractors are carried out. The period of the design phase is assumed to be 11 months including F/S review, B/D (Basic design) and D/D (Detailed Design). The commencement time of the construction is assumed to be October 2015. The construction would require 41 months based on the study resulted in the completion time of the end of February 2019. 5. Feasibility on ODA Request and Implementation The Project is currently planned by BVPPC although it has been included in the traffic master plan of HCMC region. The first step for BVPPC is to request the MOT for probability of ODA implementation. Funding by GOV is not likely because of the large project scale. Private sectors may be reluctant to invest on the Project because of the large scale and the low FIRR. In addition to these financial problems, the Project requires the state-of-the-art technology on the design and construction of a cable stayed bridge. The technology has not fully established in Vietnam. Because of these reasons, BVPPC hope that Phuoc An Bridge is constructed by Japanese ODA having high reputation on the quality and schedule management. Therefore, no serious obstacle are found for the ODA implementation. Many foreign countries, such as China, Korea and Switzerland, are investing on the port facilities and factories in nearby industrial parks. Under the situation, Japan is expected to provide advice and assistance for the implementation of the Project. This would be a good opportunity for Japan to impress people with its existence. S-16 Table S8 Entire Project Schedule (tentative) S-17 6. Superiority of Japanese Firms in Technology As stated foregoing, design and construction of a cable stayed bridge of which center span is 360m requires not only sophisticated knowledge but also high-developed equipment and materials. Japan has vast of overseas experiences and lead the state-of-the-art technology in this area. Moreover, the Japanese technologies and experiences for wind tunnel tests and wind-resistant stability design are also leading the edge of the world. Additionally, some other Japanese technologies, which are applicable to the Project, such as Vacuum Consolidation Method (VCM) for soft ground improvement, Screwed Steel Pile foundation and Structural Health Monitoring System (SHMS) are also quite unique and competitive technologies. Based on the above, it is quite apparent that Japanese firms have enough competitive power and a possibility of participation to the Project. As stated above, Japanese firms have sufficient competitiveness in terms of economic efficiency, quality control and resolution of technical difficulties, etc. Consequently, application of the technologies, which make the participation of Japanese firms who are familiar to the leading-edge technologies developed by Japan dominantly, is essential to this project. It is recommended to propose and exhibit above competitiveness of Japan working on the cutting edge of bridge engineering. This approach would also provide Japanese firms and technologies with good opportunities of orders. 7. Specific Schedule until L/A and Potential Risks for Implementation Table S9 shows a tentative schedule from the present time to L/A. No considerable risks are found in the schedule because the counterpart wish to complete the Project under STEP scheme of Japanese ODA. Many large scale road/bridge projects are simultaneously ongoing in Vietnam, in some of which the schedule is behind the original one. The main reason is the resettlement and land procurement. In this Project, however, almost no people are living in the area. Therefore, social problem could be solved relatively easy once compensation for fishery and shrimp farming is smoothly agreed. One little concern may be a possible delay of the process due to negotiation and administrative procedures among the two countries, which could be managed by close communication and cooperation. In Table S9, the time of L/A is assumed to be January 2012. A potential risk to decelerate the implementation schedule may be an internal factor of the two countries. 8. Project Location Map Figure S11 shows the project location. S-18 Table S9 Tentative Schedule from Present to L/A and Design Phase S-19 N HANOI Figure S11 Project Location DA NANG HCMC 0 200km Bien Hoa Long Thanh Airport HCMC Express Highway National Highway Ben Luc Industrial Aria Ben Luc-Long Thanh Exp. Phuoc An Bridge Cai Mep-Thi Vai Inter-Port Road 0 10 20km Cai Mep-Thi Vai Inter-Port S-20 Vung Tau Chapter 1 1.1 Outline of Vietnam and Related Sectors Economic and Financial Background of Vietnam 1.1.1 Economic Background (1) Macroeconomic Situation The Socialist Republic of Viet Nam (hereinafter referred to as “Vietnam”) enacted the Doi Moi (Renovation) Policy in 1986 and began obtaining its effects around 1989. After that, economic growth in Vietnam continued as high as 9% for the years of 1995 and 1996. In 1997, however, tendencies such as slow-down of the growth rate surfaced and foreign direct investment abruptly decreased under the impact of the Asian economic crisis, thereby decreasing the growth rate to 4.8% in 1999. After that, the growth rate continued to recover to 6.7% in 2000, 7.2% in 2003, 8.4% in 2005 and 8.5% in 2007. Especially, the Corporation Law enacted in 2000 (the revised Law was enacted in November 2005) simplified the procedure of establishing a private company and accelerated the establishment of corporations, resulting in the recovery of the national economy. In recent years, Vietnam has promoted the market economy and integration with the international economy and it became a WTO member officially in January 2007. However, the chronic foreign trade deficit and causes of concern including immature investment environment remain. The economic growth rate in 2008 decelerated to 6.3% under the effect of impacts such as the high inflation rate (19.9% over the previous year) and the global economic crisis. In 2009, the growth rate in the first quarter further slowed down to 3.1% under the global economic crisis. However, the growth rate in the 4th quarter recovered to 6.9%, the level before the crisis, because the governmental policies of economic stimulus and monetary easing worked well, and private consumption and domestic investment levered up the economy. A growth rate of 5.3%, which was the second highest rate in the ASEAN region, was achieved through 2009. The Government set an economic growth goal to 6.5% for the fiscal year of 2010. 1-1 Table 1 – 1 Macroeconomic Indexes in Vietnam As of November 2010 (Units: Local currency = dong; Rate = %) Year Real GDP growth rate Total nominal GDP (dong) Total nominal GDP (dollar) Total nominal GDP - Remarks GDP per head (nominal) (dollar) Consumer price increase rate Consumer price increase rate - Remarks Unemployment rate Unemployment rate - Remarks Current balance (international basis) (dollar) Trade balance (dollars) Foreign exchange reserves (dollar) Foreign debt balance (dollar) Exchange rate (against dollar) – Interim mean value Exchange rate (against dollar) – Term-end value Money supply growth rate Exports (dollar) Exports (dollar) - Remarks Exports to Japan (dollar) Exports to Japan (dollar) - Remarks Imports (dollar) Imports (dollar) - Remarks Imports from Japan (dollar) Imports from Japan (dollar) - Remarks Direct investment received (dollar) Direct investment received (dollar) Remarks Year Real GDP growth rate Total nominal GDP (dong) Total nominal GDP (dollar) Total nominal GDP - Remarks GDP per head (nominal) (dollar) Consumer price increase rate Consumer price increase rate - Remarks Unemployment rate Unemployment rate - Remarks Current balance (international basis) (dollar) 2000 2001 6.79 441,646,000,000,000 31,172,737,989 6.89 481,295,000,000,000 32,685,124,820 2002 7.08 535,762,000,000,000 35,064,105,501 2003 7.34 613,443,000,000,000 39,552,470,728 2004 7.79 715,307,000,000,000 45,427,854,693 402 -1.6 Previous year =100 6.42 413 -0.4 Previous year =100 6.28 440 3.9 Previous year =100 6.01 489 3.1 Previous year =100 5.78 554 7.8 Previous year =100 5.60 Urban areas Urban areas Urban areas Urban areas Urban areas 1,107,000,000 -1,153,800,000 3,416,510,000 682,000,000 -1,188,800,000 3,674,570,000 -673,000,000 -3,039,500,000 4,121,050,000 -1,931,000,000 -5,106,500,000 6,224,180,000 -1,564,000,000 -5,483,800,000 7,041,460,000 12,825,000,000 12,585,000,000 13,344,000,000 14,100,000,000 15,266,000,000 14,167.7000 14,725.2000 15,279.5000 15,509.6000 15,746.0000 14,514.0000 35.4 14,482,700,000 15,084.0000 27.3 15,029,200,000 15,403.0000 13.3 16,706,100,000 15,646.0000 33.1 20,149,300,000 15,777.0000 31.0 26,485,000,000 2,575,200,000 2,509,800,000 2,437,000,000 2,908,600,000 3,542,100,000 15,636,500,000 16,218,000,000 19,745,600,000 25,255,800,000 31,968,800,000 2,300,900,000 2,183,100,000 2,504,700,000 2,982,100,000 3,552,600,000 2,838,900,000 Incl. new expansion on registered capital base 2005 3,142,800,000 Incl. new expansion on registered capital base 2006 2,998,800,000 3,191,200,000 4,547,600,000 Incl. new expansion on registered capital base 2007 Incl. new expansion on registered capital base 2008 Incl. new expansion on registered capital base 2009 8.44 839,211,000,000,000 52,917,352,401 8.23 974,266,000,000,000 60,913,325,372 8.46 1,143,715,000,000,000 71,015,703,100 6.18 1,485,038,000,000,000 91,093,772,044 637 8.3 Previous year =100 5.31 724 7.5 Previous year =100 4.82 835 8.3 Previous year =100 4.64 1,048 23.0 Previous year =100 4.65 5.32 1,658,389,000,000,000 97,180,151,303 Presumed value 1,068 6.9 Previous year =100 4.60 Urban areas Urban areas Urban areas Urban areas Urban areas -560,000,000 -163,000,000 -6,992,000,000 -10,705,000,000 -7,400,000,000 Trade balance (dollars) Foreign exchange reserves (dollar) -4,314,000,000 9,050,560,000 -5,064,900,000 13,384,100,000 -14,203,300,000 23,479,400,000 -18,028,700,000 23,890,300,000 -12,852,500,000 16,447,100,000 Foreign debt balance (dollar) Exchange rate (against dollar) – Interim mean value Exchange rate (against dollar) – Term-end value Money supply growth rate Exports (dollar) Exports (dollar) - Remarks Exports to Japan (dollar) Exports to Japan (dollar) - Remarks 17,200,000,000 19,100,000,000 23,200,000,000 29,400,000,000 36,600,000,000 15,858.9000 15,994.3000 16,105.1000 16,302.3000 17,065.1000 15,916.0000 30.9 32,447,100,000 16,054.0000 29.7 39,826,200,000 16,114.0000 49.1 48,561,400,000 16,977.0000 20.7 62,685,100,000 4,340,300,000 5,240,100,000 6,090,000,000 8,467,800,000 17,941.0000 n.a. 57,096,300,000 Presumed value 6,291,800,000 Presumed value Imports (dollar) Imports (dollar) - Remarks Imports from Japan (dollar) Imports from Japan (dollar) - Remarks Direct investment received (dollar) Direct investment received (dollar) Remarks 36,761,100,000 44,891,100,000 62,764,700,000 80,713,800,000 4,074,100,000 4,702,100,000 6,188,900,000 8,240,300,000 6,839,800,000 Incl. new expansion on registered capital base 12,004,000,000 Incl. new expansion on registered capital base 21,347,800,000 Incl. new expansion on registered capital base 71,726,000,000 Incl. new expansion on registered capital base 69,948,800,000 Presumed value 7,468,100,000 Presumed value 23,107,300,000 Incl. new expansion on registered capital base [Source] JETRO Website “Information by country/region” (J-FILE) Real GDP growth rate, total nominal GDP, consumer price increase rate, unemployment rate, trade balance, export/import amount, export/import to/from Japan, direct investment received, GDP structure by industry, and total domestic expenditure breakdown: General Statistics Office of Vietnam Website: http://www.gso.gov.vn/default_en.aspx?tabid=491 Current balance and foreign debt balance: World Bank "A World Bank Economic Update for the East Asia and Pacific Region" GDP per head: IMF "World Economic Outlook Database" Foreign exchange reserves and exchange rate: IMF "IFS" CD-ROM Money supply growth rate: IMF "International Financial Statistics Yearbook" Note: Money supply growth rate: “Broad Money” in IMF "International Financial Statistics Yearbook 2010" was stated as money supply growth rate. 1-2 (2) Outline of Industry According to the statistics for the past 10 years on the structure by industry of the gross domestic product (GDP) of Vietnam, the total GDP amount grew by a factor of about 1.9 over 10 years. [273,666 ×1 billion dong (2000) ~ 516,678×1 billion dong (2009)]. The yearly growth rate was a little more than 8%. The GDP value by industry surely increased, but the growth rate decreased from 26% to 23% in the primary industries (agriculture and fishery) and from 8% to 5% in the secondary industries (mining industry). Instead, the third industries (manufacturing and service industries) showed a remarkable growth. development. The above decrease can be recognized as a characteristic of economic Figures 1-1 through 1-3 show the GDP structure by industry in Table 1-2 in graphs. Table 1 – 2 GDP Structure by Industry (Real figures) Unit: 1 billion dong Sector Agroforestry 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 57,037 58,169 60,480 62,350 64,717 66,707 68,752 70,585 73,795 74,828 Fishery 6,680 7,449 7,872 8,477 9,200 10,181 10,972 12,132 12,792 13,340 Mining 18,430 19,185 19,396 20,611 22,437 22,854 22,397 21,904 21,065 22,669 Manufacturing 51,492 57,335 63,983 71,363 79,116 89,338 101,269 113,801 124,935 128,386 6,337 7,173 7,992 8,944 10,015 11,247 12,361 13,485 14,842 16,181 Construction 20,654 23,293 25,754 28,481 31,053 34,428 38,230 42,875 42,712 47,563 Trade 44,644 47,779 51,245 54,747 59,027 63,950 69,418 75,537 80,654 86,847 Utilities Hotel/restaurant business Transportation/ warehousing/ communication services 8,863 9,458 10,125 10,646 11,511 13,472 15,145 17,086 18,579 19,005 10,729 11,441 12,252 12,925 13,975 15,318 16,870 18,793 21,031 22,815 Real estate industry 12,231 12,631 13,106 13,796 14,396 14,816 15,252 15,872 16,268 16,684 Total (incl. others) 273,666 292,535 313,247 336,242 362,435 393,031 425,373 461,344 490,458 516,568 [Source] JETRO Website “General Statistics Office of Vietnam” [Note] Base year: 1994 The figures in 2009 are tentative values. 1-3 Figure 1-1 GDP Change for Past 10 Years Unit: 1 billion dong 600,000 500,000 400,000 300,000 200,000 100,000 0 2000 2001 2002 2003 2004 2005 2006 2007 2008 Figure 1-2 Structural Ratio by Industry (2000) Transportation/ warehousing/ communication services 5% Real estate industry 5% Agroforestry 23% Hotel/restaurant business 4% Trade 19% Fishery 3% Mining 8% Construction 9% Manufacturing 21% Utilities 3% 1-4 2009 Figure 1-3 Structural Ratio by Industry (2009) Transportation/ warehousing/ communication services 5% Real estate industry 4% Agroforestry 17% Fishery 4% 3% Mining 5% Trade 19% Construction 11% Manufacturing 28% 4% Utilities (3) Population in Vietnam The population in Vietnam is approximately 85,790,000 (according to the census as of April 1, 2009). The yearly rate of increase of population is 1.2% (average for past 10 years). The population ratios form a pyramid structure, most of which are people younger than the thirties and the forties. This means that Vietnam has a plentiful work force and has a high consuming population and a sufficient number of people who will shoulder the future economic growth. Figure 1-4 Population Ratios in Vietnam [Source]: General Statistics Office of Vietnam Website http://www.gso.gov.vn/default_en.aspx?tabid=491 1-5 (4) Foreign Direct Investment The total number of applications for investment in Vietnam was 85 million and amounted to 124 billion US dollars. The applications implemented amounted to nearly 48 billion US dollars. The amount of FDI (Foreign Direct Investment) accounted for 25 to 30% of the total amount of investment, and exports showed a growth rate of more than 25%. In one year this was 56%, and the number in the workforce is 1.7 million. Approximately 2.5 billion US dollars were received into the national budget in 2009. According to the evaluation by Foreign Investment Agency (FIA), Ministry of Planning and Investment (MPI), the FDI influenced the change of economic structure, promoted technological transfer and contributed to the national budget. In addition, the FDI had much influence on a wide range of other economic activities to improve the administrative procedures. Actually, however, the structure of FDI funds has changed. According to the statistics by Foreign Investment Agency, Ministry of Planning and Investment, the FDI structure showed a large change over the years from 2001 to 2009. The FDI funds in Industrial and construction sectors accounted for 85% of the total investment until the beginning of the 2000’s, but the FDI in these sectors decreased to 22% of the total investment up to 2009. Conversely, investment in the service sector increased from 7% to 77% over the same period. In comparison with the “FDI procurement standard” recommended by IMF, which is applicable to the long-term investments in the high-tech processing industry sector, Vietnam is surely backward. Japan and the countries of the EU which have modern technology contributed only a small percentage of the FDI. The U.S.A ranked in first place in 2009 by making large scale investments mainly in the hotel business and real estate industry. Table 1-3 Domestic Direct Investment Statistics (by Country/Region) Unit: million dollars, % and case 2008 2009 Invested Amount Percentage Number of Cases Invested Amount Percentage Growth Rate U.S.A. 1,914 2.9 43 5,948 36.4 210.8 Korea 4,020 6.0 204 1,598 9.8 △60.3 Taiwan 8,879 13.4 53 1,356 8.3 △84.7 U.K. 584 0.9 33 1,074 6.6 84.1 Hong Kong 678 1.0 39 742 4.5 9.5 5,245 7.9 98 469 2.9 △91.1 573 0.9 48 180 1.1 △68.5 15,074 22.7 29 151 0.9 △99.0 7,654 11.5 77 138 0.8 △98.2 Australia 196 0.3 24 90 0.6 △54.1 France 633 1.0 32 88 0.5 △86.1 3,933 5.9 19 77 0.5 △98.0 66,500 100.0 839 16,345 100.0 △75.4 Singapore China Malaysia Japan Thailand Total (incl. others) 1-6 [Note]: New investment on an approval base, excluding of expansion investments. The U.K. includes Virgin Islands, Cayman Islands, and Saint Christopher and Nevis. [Source]: JETRO Website: Prepared based on the materials of Ministry of Planning and Investment (MPI). Table 1-4 Domestic Direct Investment Statistics (by Sector) Unit: Million dollars, % and cases 2008 2009 Amount Percentage Cases Amount Percentage Growth Rate 23,067 34.7 39 7,372 45.1 △68.0 Hotel/Restaurant Business 2,606 3.9 32 4,983 30.5 91.2 Processing/ Manufacturing 35,043 52.7 245 2,220 13.6 △93.7 69 0.1 6 397 2.4 475.4 Construction 452 0.7 74 388 2.4 △14.2 Art/Entertainment 587 0.9 12 292 1.8 △50.3 Retailing/Repair 126 0.2 115 192 1.2 52.4 86 0.1 16 129 0.8 50.0 507 0.8 26 110 0.7 △78.3 76 0.1 148 89 0.5 17.1 2,438 3.7 63 68 0.4 △97.2 272 0.4 16 62 0.4 △77.2 66,500 100.0 839 16,345 100.0 △75.4 Real Estate Mining Lifeline Transportation/ Warehousing Chemical Engineering Information/ Communications Agriculture, Forestry and Fishery Total (incl. others) [Note]: New investments on approval base, excluding of expansion investments. [Source]: JETRO Website: Prepared based on the materials of Ministry of Planning and Investment (MPI) 1.1.2 Financial Background In the export statistics (by country/region), exports to the U.S.A. and Japan ranked high, accounting for 19.9% and 11.0% respectively, but decreased compared with the previous year. Instead, exports to China and Korea increased. In the export statistics (by item), sewing products, crude oil, marine products and shoes ranked high in this order, but decreased below the previous year. Instead, computer and electronic products and parts therefor increased though a little higher. In the import statistics (by country/region), China ranked in the highest place, followed by Japan, Korea, Taiwan, Thailand in the Asian region, but the imports from those countries decreased except China. In the import statistics (by item), machinery and equipment and parts therefor ranked highest, followed by oil products, and iron and iron scraps, but those items decreased. Total exports decreased from 62,685 million dollars in 2008 to 57,096 million dollars, and total imports also decreased from 80,714 million dollars in 2008 to 69,949 million dollars in 2009. Imports were higher than exports, but the balance decreased. 1-7 Table 1-5 Export Statistics (by Country/Region) Unit: Million dollars, % 2008 2009 Amount Amount Percentage Growth Rate U.S.A. 11,869 11,356 19.9 △ 4.3 Japan 8,538 6,292 11.0 △ 26.3 China 4,536 4,909 8.6 8.2 Australia 4,225 2,277 4.0 △ 46.1 Singapore 2,660 2,076 3.6 △ 22.0 Korea 1,784 2,065 3.6 15.8 Germany 2,073 1,885 3.3 △ 9.1 U.K. 1,581 1,329 2.3 △ 15.9 Thailand 1,349 1,266 2.2 △ 6.2 62,685 57,096 100.0 △ 8.9 Total (FOB) [Source]: JETRO Website Statistic Materials: General Statistics Office of Vietnam and General Department of Custom of Vietnam. [Note]: The above figures are on a customs clearance base and the figures in 2009 are tentative values. Table 1-6 Export Statistics (by Item) Unit: Million dollars, % 2008 2009 Amount Amount Percentage Growth Rate 9,120 9,066 15.9 △ 0.6 10,357 6,195 10.9 △ 40.2 Marine Products 4,510 4,251 7.4 △ 5.7 Shoes 4,768 4,067 7.1 △ 14.7 Computer and Electronic Products/Parts 2,638 2,763 4.8 4.7 793 2,732 4.8 244.5 Rice 2,894 2,664 4.7 △ 7.9 Woods/Wooden Products 2,829 2,598 4.6 △ 8.2 Coffee 2,111 1,731 3.0 △ 18.0 Coal 1,388 1,317 2.3 △ 5.1 62,685 57,096 100.0 △ 8.9 Sewing products Crude Oil Jewelry/Precious Metals Total (FOB) [Source]: Vietnam. JETRO Website Statistic Materials: General Statistics Office of Vietnam and General Department of Custom of [Note]: The above figures are on a customs clearance base. The figures in 2009 are tentative values. 1-8 Table 1-7 Import Statistics (by Country/Region) Unit: Million dollars, % 2008 2009 Amount Amount Percentage Growth Rate China 15,652 16,441 23.5 5.0 Japan 8,241 7,468 10.7 △ 9.4 Korea 7,066 6,976 10.0 △ 1.3 Taiwan 8,363 6,253 8.9 △ 25.2 Thailand 4,906 4,514 6.5 △ 8.0 Singapore 9,393 4,248 6.1 △ 54.8 U.S.A. 2,635 3,009 4.3 14.2 Germany 1,480 1,587 2.3 7.2 970 1,415 2.0 45.9 80,714 69,949 100.0 △ 13.3 Russia Total (CIF) [Source]: JETRO Website Statistic Materials: General Statistics Office of Vietnam and General Department of Custom of Vietnam. [Note]: The above figures are on a customs clearance base. The figures in 2009 are tentative values. Table 1-8 Import Statistics (by Item) Unit: Million dollars, % 2008 2009 Amount Amount Percentage Growth Rate Machinery and Equipment/Parts therefor 13,994 12,673 18.1 △ 9.4 Oil Products 10,966 6,255 8.9 △ 43.0 Iron and Iron Scrap 6,721 5,361 7.7 △ 20.2 Textiles/Clothing Materials 4,458 4,226 6.0 △ 5.2 Automobile Parts 1,918 1,802 2.6 △ 6.0 Chemical Products 1,604 1,580 2.3 △ 1.5 Fertilizers 1,473 1,415 2.0 △ 3.9 Automobiles (Cars, Trucks, etc.) 1,040 1,269 1.8 22.0 Medicines and Drugs 864 1,097 1.6 27.0 Bicycle Parts 625 621 0.9 △ 0.6 80,714 69,949 100.0 △ 13.3 Total (CIF) [Source]: JETRO Website Statistic Materials: General Statistics Office of Vietnam and General Department of Custom of Vietnam. [Note]: The above figures are on a customs clearance base. The figures in 2009 are tentative values. 1-9 1.1.3 Economic Relationship with Japan (1) Scale and Results of Japan’s ODA Grants Economic cooperation with Japan was restarted in November 1992. Japan is the largest assistance country for Vietnam in the world, and the ODA loan in 2009 amounted to 1465.6 billion yen (on an exchange of notes base), the highest value ever in the past. Table 1-9 Scale and Results of Japan’s ODA Grants to Vietnam FY2000 FY2001 FY2002 FY2003 FY2004 FY2005 FY2006 FY2007 FY2008 ODA loan 709.04 743.14 793.30 793.30 820.00 908.20 950.78 978.53 832.01 Grant Aid 80.67 83.65 52.37 56.50 49.14 44.65 30.97 21.18 26.63 Technical Cooperation 74.32 79.09 67.08 55.77 57.11 56.51 52.75 51.98 59.65 [Source]: Ministry of Foreign Affairs Website /http://www.mofa.go.jp/mofaj/area/vietnam/data.html [Note]: “Fiscal Year” is based on the signatory date of the exchange of notes for loans (ODA loans) and the budgetary year for grand aids and technical cooperation. The amount is on an exchange of notes basis for loans and grant aid and on an actual expense basis for technical cooperation. 1.2 Outline of Sectors for the Project This Project is intended for the Department of Transportation (DOT) under the control of the Ba Ria-Vung Tau Provincial People’s Committee (hereinafter referred to as “BVPPC”). The BVPPC is also the counterpart for this Study. BVPPC is carrying out activities for infrastructure development and welfare improvement. Small and medium scale road construction and rehabilitation have been undertaken by BVPPC independently, but large scale projects such as the construction of Phuoc An Bridge have been implemented under the command of the Ministry of Transportation. 1.3 Present Conditions of Project Areas 1.3.1 Outline of Ports Vietnam has a coastline of approximately 3,260km facing the South China Sea and there are more than 150 ports along the coastline, of which 6 ports, Northern, Central North, Central, Central South, Ho Chi Minh City and Mekong, are designated as the most important port areas. Hai Phong International Port (Northern), Van Phong International Port (Central South) and Cai Mep-Thi Vai International Port (Ho Chi Minh City) are designated as strategically important ports (international gateways). There are a number of port facilities in the environs of Ho Chi Minh City, but a plan to remove their functions to the Cai Mep-Thi Vai International Port is in progress due to the many problems such as traffic congestion in Ho Chi Minh City (running of large vehicles is permitted only at nighttime), aged facilities, and poor dredging of navigational channels. It is expected that the future cargo handling volume can be secured and the above problems can be solved by collecting the port facilities at the Cai Mep-Thi Vai Port where the water is deep. 1-10 Figure 1-5 Port Locations in Vietnam People's Republic of China N HANOI Northern Central North Central DA NANG Central Central South South HCMC HCMC Mekong 0 100 200 km Source: IBC Ports & Logistics 2008(Ho-Kim-Law) SEAPORT SYSTEM IN THE SOUTHERN KEY AREA OF VIETNAM: PRESENT STATUS AND DEVELOPMENT STRATEGIES 1.3.2 Current Conditions of Existing Roads The National Highway Route No. 51 is provided with 2 lanes (one lane on each side) and there are housing areas scattered along it. As it is subject to chronic traffic congestion, widening work on the entire route is making progress at present. Along with the construction of port facilities, access roads from National Highway Route 51 to port areas are under construction. 1-11 Figure 1-6 Current Conditions of Existing Roads Congestion on Route No. 51 1.3.3 Access road connecting Route No. 51 to port facilities Construction Conditions of Port/Industrial Facilities The present construction status of the port/industrial facilities is shown in Figure. 1-7 (photographed on December 1, 2010). Figure 1-7 Present Construction Status of Port/Industrial Facilities 1-12 1.3.4 Present Status of North-South Highway through Cai Mep-Thi Vai Port The present status of the north-south highway running through Cai Mep-Thi Vai Port is shown in Figure. 1-8 (photographed on December 1, 2010). Figure 1-8 Present Status of North-South Highway through Cai Mep-Thi Vai Port Component 5 except the median strip has been completed and put into use. Other components are as follows: Component 1: Planned to start construction work within 2011. Component 2 (ODA section): Under construction Component 3: Under construction Component 4: Under construction Component 6: Planned to start construction work within 2011. Component 7: Under design Components 8 and 9: Under review Some plants have been completed and the premises of each plant have been paved using their own funds. [The photo left shows the facility of POSCO company in Korea).] 1-13 (iron-manufacturing 1.3.5 Construction Point of Phuoc An Bridge The present status of the construction point of Phuoc An bridge is shown in Figure. 1-9 (photographed on December 1, 2010). Figure.1-9 Present Status of Phuoc An Bridge On the right bank side, there is a mangrove wood at present. It is planned to construct the Phuoc An port on the left side of the above photo. On the left bank side, there are a mangrove wood and a wetland. It is planned to construct the VINALINES facilities under the planned construction point of the bridge. 1-14 Chapter 2 Study Method 2.1 Study Contents This study is for Phuoc An Bridge Construction Project on Cai Mep – Thi Vai Inter-port Roads (hereinafter referred to as “the Project”) and the Counterpart is Ba Ria – Vung Tau Provincial People’s Committee (hereinafter refereed to as “the Counterpart” or “BVPPC”).. The Project Manager and each study member carried out survey and study for the following items for the Project. (1) Technical feasibility (2) Cost estimate and scheduling (3) Social and environmental consideration (4) Economic and financial feasibility (5) Applicability of Special Terms for Economic Partnership (hereinafter referred to as “STEP”) scheme of Official Development Assistance (hereinafter referred to as “ODA”) of Japan. Main activity of each study member is described below. 2.1.1 Bridge Plan And Design Information for design standards and regulations are collected and reviewed. Design conditions including navigation requirements of the Thi Vai River at the bridge site are reviewed and confirmed. Referring to existing relevant documents and geographic/topographic data in addition to the investigation and review on the conditions at the proposed bridge location, studies on bridge plan, type and outline design are carried out. Throughout the study, applicability of Japanese technology for the Project is considered. 2.1.2 Traffic Demand Forecast The traffic demand forecast is carried out by data collection and analysis on the social and economic conditions, traffic condition, existing and future traffic network, traffic volume data and relevant existing information. In addition, the conditions of the project area and traffic conditions of major roads including the vicinity of the Project are confirmed. 2.1.3 Road Planning Data collection and the analysis are carried out for existing information including the status of transport infrastructure and traffic master plan at the study area in addition to the natural conditions including geographic/topographic conditions, the river and the climate. Road design standards and technical feasibility for the proposed road plan are confirmed. The implementation plan and the progress of the nearby projects are also conformed. At the road planning, reduction of the project costs, the connection to nearby roads and consistency with relevant regional development plans are considered. 2-1 2.1.4 River and Natural Conditions River navigation conditions are examined because large ships are operated along the Thi Vai River where many port facilities and industrial parks are constructed or planned in the future. A boring test cannot be carried out at the bridge location because the project area is covered with muddy mangrove forest. Therefore, existing information and data obtained from nearby projects, including the test results, are collected and reviewed to confirm geological and soil conditions. The results of the review and analysis on the natural conditions and the river characteristics are reflected on the bridge design and project implementation plan. 2.1.5 Environmental and Social Considerations Screening and selection of potential problems on the environment are carried out based on the JBIC Environmental and Social Considerations Guidelines. Review and study are conducted for relevant environmental laws and regulations, implementation process of Environmental Impact Assessment (hereinafter referred to as “EIA”), and existing data. A hearing is conducted from relevant local authorities about land acquisition and resettlement plans. The effects and influences are investigated when reduction of contaminated materials and/or greenhou8se gas are expected from the traffic demand forecast. 2.1.6 Construction Schedule and Cost Estimate Project costs are estimated based on construction equipments and ability of contractors, the unit prices, cost data in similar project in Vietnam, the quarterly construction indices published by the Ministry of Transportation of Vietnam A proper implementation schedule is proposed based on the review of the plan proposed by Vietnamese consultants. Costs required for the bridge maintenance are also estimated. 2.1.7 Financial and Economical Analysis Based on the basic idea on economical and financial analysis, a cost-benefit analysis is conducted assuming with and without the Project. Economical feasibility of the Project is evaluated by calculating the economic internal rate of return (EIRR), the net present value (NPV) and the benefit-cost ratio (BCR). The analysis considers the application of STEP conditions reviewing the situation of the implementation authorities for fund raising and financial conditions. 2-2 2.2 Study Method and Organization 2.2.1 Work Description (1) 1) Work Items Works in Japan a) Preparative works Survey planning and collection and analysis of existing information/data b) Planning and design Verifying bridge route; examining design standards; bridge plan; bridge outline design; road plan; traffic demand forecast c) River and natural conditions Climate, topography, and soil conditions at the project area; river characteristics of the Thi Vai River d) Environmental evaluation and analysis Evaluation for environmental and social considerations; examination of environmental aspects e) Summary project costs and implementation schedule Project cost estimate; calculation of maintenance costs; study on construction plan; study on implementation plan f) Financial and economic analysis Cost-benefit analysis; economical and financial feasibility of the Project 2) Works in Vietnam a) Site investigation and information collection Verifying local conditions through on-site surveys; meeting/hearing with related authorities, consultants and project staff; confirmation of the traffic master plan and the port master plan; collection of related development plans: information collection of economic, financial and social issues; data collection for climate, topography, soil conditions, hydrological data, river characteristics, navigation requirements, ship operation, social/environmental data, traffic conditions, design standards and cost estimate, b) Review and analysis of collected information Social economy; environmental and social considerations; bridge route: road and traffic; bridge planning; bridge outline design; bridge maintenance; construction plan; project costs 2-3 (2) 1) Report preparation and reporting to related authorities/groups Reporting to Ernst & Young Shin Nihon LLC (SNC) and Japan External Trade Organization (JETRO) 2) a) Intermediate report meeting: 24 December 2010 b) Final report meeting: scheduled at the beginning of February 2011 Reporting to related authorities/groups During the second study trip to Vietnam, scheduled in the middle of January 2011, the Study Team will report and explain the results of the study to the following groups; a) Ba Ria – Vun Tau Provincial People’s Committee and the Department of Transportation (the Counterpart) 3) b) Ministry of Transportation of Vietnam c) Japan International Cooperation Agency (JICA), Hanoi Office d) Japanese Embassy in Hanoi e) JETRO Hanoi Office and Ho Chi Minh Office Report preparation The report and the submittals are prepared and submitted in accordance with the Guidelines for Contract/Cost Liquidation and the Guidelines for Report Preparation. The submission schedule is as follows; a) Draft Report submission: 11 January 2011 b) Final Report submission: 21 February 2011 2-4 2.2.2 Study Team Organization Members of the Study Team are shown in Table 2-1 Table 2-1 Members of the Study Team Name Assignment Company Takayuki ISHIZUKA Project Manager /Bridge Plan & Design I Chodai Co., Ltd. Akira ARIKADO Bridge Plan & Design II Chodai Co., Ltd. Road/Traffic Nippon Koei Co., Ltd. Kei KATAYAMA Natural Conditions Chodai Co., Ltd. Shinsuke SATO Environment/Social Nippon Koei Co., Ltd. Ken KICHIYA Tomohiko KASHIWAMURA Naoshi OKAMURA Ho Thai Hung Construction Plan /Cost Estimate Economic/Financial Analysis Assistance/Coordination 2-5 Kajima Corporation Chodai Co., Ltd. (Almec Corporation) Chodai Co., Ltd. Hanoi Representative Office 2.3 Assignment Schedule The assignment schedule is shown in Table 2-2. Table 2-2 Assignment Schedule 2010 November 2011 December January February Work in Vietnam PM/Bridge I Bridge II Road/Traffic Natural conditions Environment/Social Construction/Estimate Economy/Finance Assistance/Coordination Interpreter Reporting Work in Japan PM/Bridge I Bridge II Road/Traffic Natural conditions Environment/Social Construction/Estimate Economy/Finance Assistance/Coordination Final ▼ Intermediate ▼ Reporting Draft 1/11 Submission of Report 2-6 Final 2/21 2.4 Site Investigation Schedule The investigation schedule is shown in Table 2-3. Table 2-3 Site Investigation Schedule Activity Date 2010 AM 11/26 (Fr) PM Move from Tokyo to HCMC 11/27 (Sa) Team meeting Move from HCMC to Vung Tau 11/28 (Su) Holiday Holiday Meeting with Ba Ria – Vung Tau Provincial People’s Committee & Department of Transportation Meeting with PMU85 and the Consultant Team of Cai Mep – Thi Vai Ports Construction Project Site investigation/ Meeting with the Consultant of Cai Mep – Thi Vai Ports Construction Project 11/29 (Mo) Team meeting 11/30 (Tu) Meeting with Ba Ria – Vung Tau Consultant 12/1 (We) Site investigation 12/2 (Th) Data collection/review 12/3 (Fr) Data collection/review; Move from Bung Tau to HCMC 12/4 (Sa) Data collection/review Data collection/review 12/5 (Su) Holiday Holiday 12/6 (Mo) Team meeting 12/7 (Tu) 12/8 (We) 12/9 (Th) Data collection/review; Group meeting Meeting with TEDI South and BRITEC Data collection/review Meeting with Dong Nai Provincial People’s Committee & the Department of Transportation Data collection/review Move from HCMC to Tokyo 2-7 Site investigation (North-South Expressway Construction Project) Data collection/review Meeting with Portcoast Consultant Data collection/review Team meeting (Wrap-up Meeting) 2.5 Persons Interviewed Persons with whom the Study Team interviewed are listed in Table 2-4. Table 2-4 List of Persons Interviewed Name of Organization/Group Name/ Position JETRO Ho Chi Minh Office Mr. Satoshi Kitashima (Director) Ba Ria – Vung Tau Provincial People’s Committee (BVPPC) Mr. Vu Ngoc Thao (Director) Department of Transportation (BVPPC) Cai Mep – Thi Vai Inter-port Road PMU Mr. Nguyen Van Trinh (Director) Mr. Duong Ngoc Chau (Specialist of Planning & Engineering Department) Ba Ria – Vung Tau Consultants Mr. Kieu Anh Man (General Manager) Mr. Tran Vang Tiem (Depyuty General Manager) Mr. Vu (Chief of Business Department) Mr. Hung (Geological Engineer) Mr. Sang (Design Engineer) Mr. Tam (Cai Mep – Thi Vai Inter-port Road Manager) PMU85 (CMTV Internatipnal Constructio(n ODA Project) Ports Mr. Nguyen Thanh Tra (Deputy Project Manager) Mr. Dang Van Hai (Project Staff) Consultant Team (CMTV International Ports Construction ODA Project; JV of JPC+NK+Portcoast) Mr Masahiro Hayashi (PK-1, Resident Engineer) Mr. Hiroaki Watanabe (Senior Port Engineer) Mr. Yukinori Uchimura (Senior Road & Bridge Engineer) TEDI South Mr. Bui Van Moc (General Director) ORBITEC Engineering Design Consultants Joint Stock Company Mr. Tran Dai Minh (Chairman) Mr. Nguyen Quoc Cuong (Director) Ho Chi Minh Institute of Technology Professor Dr. Nguyen Danh Thao (Head of External Relations Office, Port & Coastal Engineering) PORTCOAST Consultant Corporation Mr. Pham Anh Tuan (Deputy General Director) Mr. Nguyen Ngoc Thuy (Project Manager of Phuoc An Port Project) Mr. Nam (Deputy Project Manager of Phuoc An Port Project) North-South Expressway Construction Project, HCMC – Long Thanh – Dau Giay Section (I) Mr. Takuya Funahara (Resident Engineer (PK-1a/1b)) Mr. Yasumitsu Watanabe (Resident Engineer (PK-2)) North-South Expressway Construction Project, HCMC – Long Thanh – Dau Giay Exoressway Technical Assistance Project (Km0-Km4 and RR2 I/C) Mr. Akira Magario (Deputy Team Leader/Sr. Highway Engineer) Mr. Hiroshi Kudo (Sr. Strucrure/Bridge Engineer) Ms. Sawako Tomioka (Structural Engineer 1) HCMC Urban Railway Construction Project, Ben Thanh – Suoi Tien Section (Line 1) Mr. Tatsuya Masuzawa (Project Manager) Mr. Nguyen Xuan Hiep (Deputy Project Manager) Mr. Gentaku Goto (Office Manager) Department of Transportation, Dong Nai Provincial People’s Committee Mr. Nguyen Ngoc Dung (Deputy Director) Mr. Nguyen Thanh Dam (Chief of Planning Department) 2-8 Chapter 3 Contents of the Project and Technical Feasibility 3.1. Background and Necessity of the Project 3.1.1. Scope of the Project BRITEC, a Vietnamese consulting company, carried out a study and prepared a report in 2009 on Cai Mep Thi Vai Inter-port Road. The title of the report is “Report on Investment Construction Project of Cai Mep – Thi Vai Inter-port Road (Refer to Appendix 1, Hereinafter referred to as “BRITEC Report”). Contents of BRITEC Report have been approved by Ba Ria – Vung Tau Provincial People’s Committee (BVPPC) in August 2009 (Refer to Appendix 2). According to BRITEC Report, the Project is located from Km18+100 to Km21+360 on the Cai Mep – Thi Vai Inter-port Road. The length is 3.26km. (Refer to 3.2.2 for the details of the Cai Mep – Thi Vai Inter-port Road). This study assumes the same project length as approved by BVPPC. The Project consists of the following elements: - Earthwork Road (approximately 280m from Km18+100) - Main Bridge (Prestressed concrete cable-stayed bridge) - Approach Bridge (planned by Super-T girder) - Interchange with Phuoc An Port Industrial Road (at the end of the Project) Figure 3-1 shows the scope of the Project. Figure 3-1 Scope of the Project N Km 21+360 Km 18+100 0 500 1000 km 3-1 The study team reviewed BRITEC Report and updated and complemented the contents as appropriate for the following items. - Preliminary design of Phuoc An Bridge - Project costs - Preliminary economic/financial analysis - Project implementation schedule - Natural and social considerations 3.1.2. Necessity of the Project The Project will be an essential factor to the ports in the area including Cai Mep Port, Thi Vai Port and Phuoc An Port as well as to vehicles for the port facility of these ports, factories, power stations, etc. Upon the completion of Phuoc An Bridge, above ports and HCMC is connected 15km to 20km shorter compared with the other routes. Cai Mep Port, Thi Vai Port and a part of the Cai Mep- Thi Vai Inter-port road are currently constructed by Japanese ODA targeting to complete in the year of 2012. The value of these facilities will be significantly enhanced by the Project. Many industrial parks are constructed near HCMC shown in Figure 3-2. In these areas, many Japanese companies are operated or will be operated. Phuoc An Bridge is expected to support and encourage business activity of these activity and result in considerable positive impact. Figure 3-2 Industrial Parks near Ho Chi Minh City J K B 51 N i H A Long Thnah Airport G C F Phuoc An Bridge Cai Mep Thi Vai International Gateway 2020: 475million TEUs M D E E 51 0 10 20 km 3-2 L Table 3-1 Japanese Companies Operated in Industrial Parks near Ho Chi Minh City A Tan Thuan Industrial Zone (57 companies including JUKI(Sewing )) B Sai Gon High Techno Park (NIHON DENSAN) C Nhon Rach Industrial Zone (YOKOHAMA TIRE) D Cai Mep Industrial Zone (MORISHITA) E Dong Xuyen Industrial Zone (HIKOSEN PLANNING) F Phu My Industrial Zone (SHIN NIPPON STEEL, ITOUCHU-MARUBENI STEEL, HANWA INDUSTRY, NITTETU COMMERCIAL, KYOEI STEEL, MITSUI PRODUCT & KYUSYU ELECTRIC POWER & SUMITOMO COMMERCIAL, TEPCO) G My Xuan Industrial Zone (3 companies including SUMITOMO CORPORATION) H Long Thanh Industrial Zone (OLYMPAS) I Amata Industrial Zone (28 companies including KAO) J Long Binh Industrial Zone (12 companies including SHIRASAKI International) K Bien Hoa Industrial Zone (10 companies including HISAMITU) L Cai Mep Port (Being constructed by Japanese ODA) M Thi Vai Port (Being constructed by Japanese ODA) When the Project will not be implemented, vehicles in this area will use existing NH51 or Bien Hoa – Vung Tau Expressway, which will be constructed in the near future. The length of port facilities along the Thi Vai River is equivalent to the length from Haneda and Urayasu in Japan. Abovementioned two roads will not be sufficient for the traffic volume forecast in the near future. As a result, environmental negative impact increases on these roads resulting traffic jams and pollution such as noise and air contamination. 3.2. Basic Policy of Vietnam for Implementation of the Project 3.2.1. Location of the Project The Phuoc An bridge of this project is a part of the Cai Mep- Thi Vai Inter-port road, and it is located on the east side of Cai Mep- Thi Vai international port. The Phuoc An bridge is located on the north side of the Cai Mep- Thi Vai Inter-port road, goes across the Thi Vai river, and is connected with the road to a Phuoc An industrial port that is the opposite bank. The road to a Phuoc An industrial port is connected with the Ben Luc- Long Thanh expressway on the north side further. The south of the Thi Vai river is Ba Ria-Vung Tau Province, and the north side is Dong Nai Province. The Phuoc An bridge is located in the province border. The section to connected interchange on the road to a Phuoc An industrial port is charge of the Ba Ria-Vung Tau Province. According to the construction schedule of the two provinces, road construction to a Phuoc An industrial port of the Dong Nai Province aims at the completion in 2013 and the Phuoc An bridge construction of the Ba Ria-Vung Tau Province aims at completion in 2015. Both routes are considered to be 3-3 very important in the economic development strategy and are ranked as the first priority project of the two provinces. Figure 3-3 shows the location of the project. Figure 3-3 Location of the project 0 25 50 km Source: The planning on development of communications and transport in Ho Chi Minh city up to 2020 and an after 2020 vision 3.2.2. Outline of plan of Cai Mep- Thi Vai Inter-port road (Ba Ria - Vung Tau Province) The large-scale port construction is being constructed at Cai Mep- Thi Vai international port. However, there is no road that passes this area while the port facilities have been constructed to some extent. As for the DOT of BVPPC, it is admitted that road works are delayed compared with the ports construction, and is hoped for the completion at the early stage of this route. The route is separated into nine components and Component-2 in that is under construction by ODA. The object of this project is Component-9. According to the hearing of BVPPC, there is no plan to make the route and the Phuoc An bridge a toll road, and income is expected from fees from port facilities and ship moorage, etc.. Figure 3-4 shows the outline of the route. 3-4 Figure 3-4 Outline of the Route Source: BRITEC Report (1) Route length The route length is 21.3 km from the south of Cai Mep- Thi Vai international port of the Ba Ria-Vung Tau Province to the road to the Phuoc An industrial port of the Dong Nai Province . (2) Phase-1 and Phase-2 Component-9 is divided into Phase-1 and Phase-2. The Phase-1 length is about 1.55 km from Km18+100 to Km19+650, and the road of Phase-1does not cross the Thi Vai river. The Phase-2 length is about 3.26km from Km18+100 to Km21+360. And Phuoc An bridge, the approach road/bridge and grade-separated interchange at the end of alignment are included in the content of Phase-2. Components-0 to 8 and Phase-1 of Component-9 schedules the completion in 2012, and Phase-2 schedules the completion in 2015. Section of this study is this Phase-2. (3) Design Standard, Classification, Design Speed Standard TCXDVN 104: 2007 (Urban Road Specifications for Design) Urban road classification: Main urban road Design Speed V=70km/ h R.O.W. W=50m (4) Cross section of the road Typical cross sections are shown below. 3-5 Figure 3-5 Typical Cross Section (Components-1 and -2) Source: BRITEC Report Figure 3-6 Typical Cross Section (Components-3 to 8) Source: BRITEC Report 3-6 Figure 3-7 Typical Cross section (Phase-1 of Component-9) (The upper part of W=26m is a space of Phase-2. ) Source: BRITEC Report Figure 3-8 Typical Cross Section (Phase-2 of Component-9) Approach Bridge Source: BRITEC Report Phuoc An Bridge Source: BRITEC Report 3-7 (5) Interchange plan at the end of alignment The end of Component-9 that is the end of the Cai Mep- Thi Vai Inter-port road is connected with the road to Phuoc An industrial port by the interchange of the trumpet type. Refer to Figure 3-9 and Figure 3-10. Figure 3-9 Interchange Plan Source: BRITEC Report Figure 3-10 Road Profile Source: BRITEC Report The F/S on the Cai Mep- Thi Vai Inter-port road is completed, and a part of section is under construction now. However, there is only the above-mentioned simple drawing for the interchange at the end of alignment now. 3-8 3.2.3. Outline of Plan of the Road to Phuoc An Port (Dong Nai Province) As for the construction of the road to a Phuoc An industrial port, the subsidiary company(Phuoc An port Investment Exploitation Petro Company) of Vietnam Petro who is the donor of the Phuoc An port project plans to execute it. A part of Phuoc An port and the road to a Phoc An industrial port schedule the opening in 2013. And, the F/S report by the PORTCOAST consultant will be completed soon. There are a railway plan and an existing gas pipeline in the approach bridge section. In hearing with DNPPC, it is said that there is no specific program of the railway at all. The existing gas pipeline (The size of the pipe seems to be Φ200mm) is laid to the Phuoc An industrial port schedule ground. There is no concrete relocation plan now. It is necessary to secure the distance from the gas pipe by both sides 12.5m for each according to the safety standard in Vietnam. The distance on safety is secured by 25m for each in the FS report by the PORTCOAST consultant. The outline of the plan in Dong Nai Province is shown in Figure 3-11. Figure-3-11 Outline of the Plan 0 2.5 5 km Source: Dong Nai Provincial People’s Committee (1) Design Standard, Design Speed Standard TCVN 4054: 2005 ( Highway-Specifications for Design) Design Speed V=100km/ h (The urban area on the north side of the Ben Luc Long Thanh expressway V=80km/ h. ) R.O.W. W=99m 3-9 (2) Cross section of the road Typical cross section is shown below. Figure 3-12 Typical Cross Section of Road to Phuoc An Industrial Port Source: Dong Nai Provincial People’s Committee The half section is scheduled to be constructed in Phase-1. The width of 19m on both sides contains the frontage road space in the future. (3) Connection with the Cai Mep - Thi Vai Inter-port road According to the construction schedule, the road to a Phuoc An industrial port of the Dong Nai Province aims at the completion in 2013, and is earlier than that of 2015 that is the planned completion date of the Phuoc An bridge of the Ba Ria - Vung Tau Province. The DNPPC assumes that the connecting location and the form etc. of both routes are still undecided, and the connection with the Cai Mep - Thi Vai Inter-port road is not considered in the F/S report that will be completed soon. 3-10 3.3. Considerations Necessary for Determination of Project Contents 3.3.1. Traffic Demand Forecast (1) Current Situation Cai Mep- Thi Vai international port has the plan that amount the 9.5 million tons, 4.75 million TEUs of the freight will handle the distribution scale by 2020. In a present plan, the number of roads connected from this region with NH-51st is four. (One in four is existing road. Another one is under construction by ODA. Two remainders are being planned.) On the other hand, the traffic of NH-51exceeds already 30,000PCU/the day in 2008 and causes chronic congestion. Moreover, the traffic growth rate of the national road 51 which is under construction to widen now has indicated a nearby big value during 5%/year. Environmental problems by the atmosphere, the noise, and the vibration, decreases in the distribution function because of the occurrence of the traffic jam, and increases in the amount of the CO2 exhaust due to the fuel cost deterioration, etc. are feared along NH-51. Therefore, measures by the improvement of the road network are important problems. (2) Traffic Demand Forecast 1) Methodology There is no description that used the numerical value for traffic in the future in BRITEC Report. In hearing with the BV-DOT and BV-consultant, the adoption of the number of four lanes is assumed to have followed the content that the government referred in the past. In this study, to confirm traffic and the number of lanes in the future, the traffic demand forecast was done. “The Comprehensive Study on the Sustainable Development of Transport System (VITRANSS 2)”, JICA Study, was conducted from July, 2007 to Sep, 2009. This study prepared person OD tables for 2008 by vehicle type based on the existing traffic pattern. In addition, it prepared person OD tables by vehicle type for 2010 and 2020 based on future socio-economic indicators, including population, number of jobs, etc., for each traffic zone. Afterwards, the zone was dropped from Province to District in "Survey & FS of Dau Giay-Phan Thiet Expressway Project". Thereafter, the study for Missing Road of Ho Chi Minh City was conducted. In this study, a peripheral road plan was reviewed as FS review of VITRANSS 2, and the traffic demand forecast for the years of 2030 and 2020 was done. In this study, the Cai Mep-Thi Vai international port zone was made an independent zone by using the above-mentioned final network. And, the traffic demand forecast for the years of 2030 and 2020 was conducted being divide the amount of the freight in the future of Cai Mep-Thi Vai port and Vung Tau port. 2) Forecast Result The forecasted traffic volume on Cai Mep- Thi Vai Inter-port Road is 36 thousand PCUs/day in 2020 as shown in Figure 3-13. In 2030, traffic demand is estimated to be 39 thousand PCUs/day. In 3-11 VITRANSS 2, the forecast of motorcycles and bicycles was not executed. Motorcycles and bicycles are included in the PCU value of NH-51 in 2008. Figure 3-13 Traffic Volume in 2020 (Unit: 20,000pcu/dot) LEGEND : ( Mode: + 1 + 2 + 3 ) Traffic Flow VCR<1.00 VCR<1.20 VCR<1.50 1.50<VCR scale: 1mm =20000(pcu) Ben Luc-Long Thanh Exp. Phuoc An Bridge NH-51 Bien Hoa-Vung Tau Exp. Source: Phuoc An Bridge Construction Project Study Team Figure 3-14 Traffic Volume in 2030 (Unit: 20,000pcu/dot) LEGEND : ( Mode: + 1 + 2 + 3 ) Traffic Flow VCR<1.00 VCR<1.20 VCR<1.50 1.50<VCR scale: 1mm =20000(pcu) Ben Luc-Lomg Thanh Exp. Phuoc An Bridge NH-51 Source: Phuoc An Bridge Construction Project Study Team 3-12 Bien Hoa-Vung Tau Exp. Table 3-2 Forecast Result (with the Project) Route 2008 (PCU/day) 2020 (PCU/day) 2030 (PCU/day) Open Year Cai Mep-Thi Vai ------ 35,900 38,800 2015 NH-51 24,700 (30,300) 14,000 19,500 In Operation BH-VT Expressway ------ 25,500 63,300 2017 Source: Phuoc An Bridge Construction Project Study Team. Figure in parenthesis includes motorcycles and bicycles. The traffic demand forecast when this project was not executed was done, and the result is shown in Table 3-3. Table3-3 Forecast Result (without the Project) Route 2008 (PCU/day) 2020 (PCU/day) 2030 (PCU/day) Open Year Cai Mep-Thi Vai ------ ------ ------ ------ NH-51 24,700 (30,300) 18,600 21,000 In Operation BH-VT Expressway ------ 51,000 96,500 2017 Source: Phuoc An Bridge Construction Project Study Team. Figure in parenthesis includes motorcycles and bicycles The traffic forecast result shows that the traffic of NH-51 is greatly reduced by the opening to traffic of this route. Therefore, environmental problems by the atmosphere, the noise, and the vibration, decreases in the distribution function because of the occurrence of the traffic jam, and increases in the amount of the CO2 exhaust due to the fuel cost deterioration, etc. are improved along the NH-51. The forecasted traffic volume in Ben Luc-Long Thanh expressway project is shown in Table 3-4 as another reference. Table3-4 The Forecasted Traffic Volume in Ben Luc-Long Thanh Area 2016 2026 2036 Cai Mep-Thi Vai 29,831 40,853 51,530 Source:: BL-LT Traffic、ADB TA-7115-VIE PPTA of BenLuc-Long Tanh Expressway Construction Project 8,2009 3-13 3) Number of Lanes TCXDVN104-2007 stipulated the method of determining number of lane as follows: Table 3-5 TCXDVN104-2007 Article 8.2.2 Number of lanes on the cross-section is integral, number of lane is determined by type of planned road and use the formula as follow: nlx N yc Z .Ptt to calculate the construction phase and check traffic possibility. In which: - nlx: required lanes - Nyc: designed volume of vehicle by hour in accounted year according to the article 5.2.3 - Z: Traffic possibility factor, Article 6.2.3 - Ptt: Calculated traffic possibility of one lane (vehicle/h, PCU/h) in article 5.4.1 Note: - Z.Ptt: service volume: means vehicle volume matching with given level of service while designing. - As for accommodation lanes, for example lane for bus, vehicle volume and traffic possibility are indentified by bus. Source: TCXDVN104-2007 Article 8.2.2 Design Annual Vehicle Volume (Nan) of this route for 2020-2030 is forecasted. Design Hourly Vehicle Volume (Nyc) is calculated with the ration of 0.12-0.14 of Nan, in accordance with Article 5.2.3. Traffic Possibility Factor (Z) is 0.70-0.80 in accordance with Article 6.2.3. Highest Traffic Possibility (Ptt) is 1800 pcu/hour/lane in accordance with Article 5.4.1. Number of lanes required was calculated as shown in Table 3-6. 3-14 Table 3-6 Number of Lanes Required of This Route Year 2020 2030 NAN 36,000 39,000 NYC(1) 0.12 4,300 4,700 NYC(2)0.14 5,000 5,500 Z(1) 0.7 0.7 0.7 Z(2) 0.8 0.8 0.8 PTT 1,800 1,800 1,800 NLX-0.12-0.7, lane 4 4 NLX-0.12-0.8, lane 3 4 NLX-0.14-0.7, lane 4 5 NLX-0.14-0.8, lane 4 4 Source: Phuoc An Bridge Construction Project Study Team As mentioned above, it is considered that the lane number of four (4) is appropriate for this route. The above traffic forecast does not include motorcycles. The total lane number including the outside motorcycle/bicycle/pedestrian lane is six (6). The lane composition and the width is the same as those proposed by BRITEC Report and approved by BVPPC (Refer to Appendix 2). 3-15 3.3.2. Natural Conditions (1) Geographical and Geological Conditions The project area is located approximately 40km southeast of Ho Chi Minh city, where the Quaternary geology sediment, which is likely to seen at delta area, is mainly distributed since the location is outer Mekong Delta Area. The soil properties of the area are mostly composed of alluvial deposits, and the geological epoch is relatively young. Stretch of mangrove forest is covering over natural low-lying area around the project area, of which scenery is represented by a figure 3-16. Regarding to the geological situation at Vung Tau side of riverbank, very sensitive clay is thickly deposited from ground surface to GL-30m, of which natural water content (Wn) is higher than a liquidity limit (Wl), moreover, liquidity index exceeds 100 percent (refer to table 3-7 & figure 3-17 and Appendix-7). Subsequently, relatively hard clayey soil layer, of which N-value is 20 to 30, lies at the depth GL-30m to GL-40m. Following the layer, consolidated and very hard clay with N-value of 30 to 50, and weathered rock with gravel and clay are distributed at the depth GL-40 to GL-60m and deeper than GL-60m respectively. As for Dong Nai side of riverbank, soil profiles are almost similar with an exception at GL-30m to GL-40mm, at where sandy layer with N-value of 10 to 30 is discovered. In general, low-lying area near a river mouth tends to show some particular phenomena due to the influences of ebb and flow and/or ocean waves, such as (i) repeatedly fluctuation of pore water pressure due to ground water level change, (ii) erosion due to water flow and waves, (iii) softening of soil due to permeation and water exposure, (iv) eluviation and deposition of sodium, and (v) deflation and hardening of soil. Figure 3-15 Project Location N Project Location 架橋位置 Figure 3-16 Scenery of Project Site 3-16 (Reference:BRITEC Report) 3-17 5.0 - 10.0 10.0 - 20.0 >20 Ñeán (m) Töø (m) Sample No. Borehole No. Lab. No. C9 Average Total Average Layer 4: Clay with grey-white C9 Average Total Average Layer 2 : Clay loam C9 Average Total Average 2.4 Layer1 Clay mud mix organic with grey. 2.0 - 5.0 1.2 2.9 0.0 1.0 - 2.0 0.8 1.5 0.0 0.0 0.5 - 1.0 1.8 5.7 0.0 0.1 0.25 - 0.5 0.1 - 0.25 0.1 0.4 0.05 - 0.1 37.7 37.3 0.01 -0.05 5.4 6.9 Clay (%) Specific Gravity Dry unit weight (g/cm³) Wet unit weight (g/cm³) Water content (%) <0.005 0.005 - 0.01 1.8 3.2 68 Porosity (%) 48.1 39.9 9.4 9.6 44 97 Degree of saturation (%) 92 95.5 91 96.5 Liquid Limit - WL (%) 46.3 39.5 38.0 72.2 69.7 Plastic Limit - W p (%) 22.9 23.8 23.2 37.4 35.3 23.4 15.7 14.8 34.8 34.4 Shear stress t (kG/cm²) (With each load level) 0.25 kG/cm² 0.125 kG/cm² 0.13 0.34 0.19 1.19 Figure 3-17 Soil Profile (Vung Tau Side) 0.102 1.25 0.076 0.088 0.099 Liquid index - IL 4.8 31.5 28.09 1.908 1.492 2.712 0.822 45.00 92.00 51.43 23.69 27.74 0.16 7.6 36.8 25.83 1.929 1.533 2.713 0.770 40.1 15.5 5.9 23.4 29.11 1.921 1.495 2.703 0.822 44.5 43 3.9 52.9 78.67 1.498 0.843 2.629 2.144 68.0 6.0 49.1 78.33 1.500 0.841 2.624 2.120 Initial void ratio 5.5 17.5 34.6 14.5 6.8 21.4 26.00 1.924 1.527 2.698 0.767 0.0 0.1 Silt (%) 0.50 kG/cm² Sand (%) 3.00 kG/cm² 0.622 0.951 1.279 0.530 0.691 1.106 1.00 kG/cm² Gravel (%) Plastic index - I p Shear Test 2.00 kG/cm² Atterberg limits Angle of Cohesiv interior e force friction 0.334 0.293 0.403 0.200 0.066 0.066 Consolidation test 0.56 0.84 0.13 0.11 0.10 0.09 The nearest boring log 18°16' 18°12' 13°55' 16°04' 2°23' 2°35' j ñoä Physical properties Cc Particle size distribution (mm) CR Depth (m) 2 C kG/cm (kG/cm²) Pc -3 (cm/s) -7 kv x 10 2 (cm /kG) Cv x 10 Table 3-7 Summary of Soil Investigation Result (Vung Tau Side) 2 Mv (cm /kG) According to the circumstances around the project area, the following examinations for bridge foundations will be recommended; (a) Settlement and deformation of foundation ground due to decrement of soil stiffness, (b) degradation of bearing resistance of foundation piles due to decrement of effective stress, and (c) change of sensitiveness of soil. (2) Meteorological Conditions Vung Tau area is belonging to Tropical Monsoon Area according to Koppen-Geiger climate classification, and the season there can be divided into rainy season (from middle of may to end of November) and dry season (from end of November to middle of May). The highest averaged monthly temperature was recorded 35.8 Celsius (April 1958), and the lowest one is 15.0 Celsius (September 1934). The amount of rainfall for each month of dray season is around 10mm per month. Meanwhile the amount is around 180mm per month for rainy season. Ninety (90) percent of the total amount of rainfall precipitates in the rainy season. Additionally, based on the datum for the insolation duration and amount of evaporation, of which are 250 hr per month and 140mm per month in dry season respectively, it can figure out the degree of dry environment in the dry season. Above meteorological conditions are summarized in below table 3-8. Table 3-8 Summary of Meteorological Conditions Descriptions JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Amount of Rainfall(mm) 2.2 0.6 4.6 33 188 206 213 177 214 215 69 23 Max. Temperature(℃) 32.9 32.8 34.2 35.8 35.7 34.5 33.5 33.5 33.1 32.6 33.3 32.3 Min. Temperature(℃) 16.8 18.4 16.8 21.0 18.7 17.9 20.0 18.2 18.6 19.0 17.1 15.0 Ave. Temperature(℃) 25.6 26.3 27.8 28.9 28.9 28.0 27.4 27.4 27.2 27.1 26.9 25.5 Ave. Humidity(%) 75 76 74 75 77 80 82 81 83 82 79 76 Insolation duration(hr) 264 261 293 274 239 179 221 198 185 190 216 230 Amount of Evaporation (mm) 136 141 168 151 119 103 93 97 76 83 99 112 (Reference:BRITEC Report) 3-18 (3) Overall Conditions of River Thi Vai River, of which approximate length is 76km, runs through the project area. The river goes through natural low-lying area with mangrove forest and flow into Cai Mep river together with Go Gia river. The width of the river is around 500m to 600m in general, and averaged depth is -15m to -20m with the exception of foregoing confluence of the river, at where the depth reaches approximately - 60m. The characteristics of the river is related to its estuarine basin, of which tidal fluctuation is around 4m in maximum, and the stream regime is depending on tidal table; the maximum current speeds observed in the past study are 1.3m/sec at river mouth of Thi Vai river in rainy season and 1.5m/sec at approach navigation of Vung Tau in dry season. The directions of streams depend on ebb and flow*. (*Reference:Report for Basic Design for Cai Mep - Thi Vai International Port Construction Project, by JICA dated February 2006) Figure 3-18 Location of Phuoc An Bridge Bridge Location Thi Vai River Go Gia River Cai Mep River Vung Tau 3-19 A samples for a daily and a monthly tidal fluctuations based on NDL are shown in figure 3-19 and 3-20 respectively. As the figures indicating, although the daily fluctuation is large and depending on lunar age, the monthly fluctuation for averaged highest and lowest water level is almost stable. Figure 3-19 Daily Tidal Fluctuation in Vung Tau (Sample) Sample of Tide Table 8.00 7.00 2007.Jan. 3 2007.Jan. 11 Height (m) 6.00 5.00 4.00 3.00 2.00 1.00 0.00 0 5 10 15 20 25 Hour (24h) Table 3-20 Monthly Tidal Fluctuation in Vung Tau (Sample) Fluctuation of Water Height 8.00 HighWater Low Water 7.00 Height (m) 6.00 5.00 4.00 3.00 2.00 1.00 0.00 0 2 4 6 Month 8 10 12 (Reference:Hydrometeorological Center, 2007) In regard to a quantity of flow and water lever at the project area, it is reported that the values at Vung Tau Observation Station is similar to the project site and applicable to this project based on the datum recorded in 2000 whereas the distance between both location is a little far to each other. Therefore, according to the water elevations for design of this project, it is decided to utilize the water elevations at Vung Tau as those for this project (summarized in Table 3-9, CDL basis). Incidentally, a relationship between the Chart Datum Line (CDL) at Vung Tau and National Datum Line (NDL) at Hon Dau shall be defined with below equation; CDL=NDL-2.887m(Vung Tau) 3-20 Table 3-9 Water Level for Phuoc An Bridge 8,186 (m3/s) Quantity of Flow for Design High Water Level(1% return period) + 1.600 (m) High Water Level(4% return period) + 1.520 (m) High Water Level(5% return period) + 1.500 (m) Low Water Level(95% return period) - 3.280 (m) (Reference:BRITEC Report) (4) Seismic Activities In regard to the seismic activities in the south Vietnam, sixty four (64) times of seismic activities have been observed since the beginning of the seismic observation started 1903. According to the record summarized in table 3-10 and figure 3-21, the depth for seismic center is relatively shallow; around 10km to 20 km from ground elevation, whereas not any earthquakes have been recorded near the project area. Table 3-10 Major Seismic Activities Recorded in South Vietnam No. Year Lat. Long. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 1917 1918 1921 1923 1923 1924 1926 1935 1936 1936 1938 1950 1955 1957 1960 1960 1960 1960 1960 1962 1962 1962 1963 1963 1963 1963 1963 1963 1963 1964 1964 1964 15.00 9.00 15.00 10.10 10.10 14.00 14.00 10.00 14.21 14.26 14.65 13.10 11.10 14.50 11.10 9.10 12.00 11.90 11.90 12.20 12.60 12.30 10.01 11.40 12.00 12.20 12.28 12.25 11.90 11.60 11.70 11.60 111.00 110.00 111.00 109.00 109.00 109.00 109.00 111.00 109.14 109.01 109.04 109.30 108.40 108.50 109.10 108.30 109.00 109.80 109.40 109.10 109.50 109.20 109.20 109.60 109.00 109.26 109.17 109.20 109.40 109.30 109.60 109.60 Depth(Km) Magnitude No. 0 0 0 17 10 0 0 0 10 13 15 15 15 15 15 10 15 15 15 15 12 9 23 6 15 11 13 6 15 0 15 15 0.0 5.0 5.0 6.1 5.1 5.0 5.0 0.0 5.1 4.0 4.1 4.8 3.4 4.8 4.1 5.1 4.8 4.8 4.8 4.0 0.5 0.1 0.0 3.9 4.8 4.5 4.0 4.0 4.8 0.0 4.8 4.8 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 Year Lat. Long. 1964 1964 1964 1964 1964 1964 1964 1964 1964 1964 1964 1964 1964 1964 1964 1964 1964 1964 1965 1965 1965 1965 1966 1966 1967 1967 1967 1968 1970 1970 1972 1977 11.80 11.20 11.80 11.10 11.70 11.40 12.19 10.80 9.50 9.27 11.50 12.59 10.60 9.60 12.28 12.20 12.50 12.26 12.16 11.80 12.30 9.90 12.80 12.80 11.80 12.00 12.80 12.19 13.40 13.39 13.57 10.60 109.70 109.60 109.90 109.60 109.80 109.60 109.25 109.60 109.50 109.28 109.60 109.26 109.60 108.90 109.30 109.20 109.19 109.21 109.18 109.80 109.30 108.90 109.90 109.90 109.80 108.70 109.30 109.19 108.90 109.19 109.14 108.30 Depth(Km) Magnitude 15 15 15 15 15 15 0 15 15 0 15 5 15 15 8 15 35 10 4 15 16 15 18 16 15 15 0 5 0 13 13 15 4.8 4.8 4.8 4.8 4.8 4.8 3.5 4.8 4.8 0.0 4.8 0.0 4.8 4.8 0.0 0.0 1.1 0.0 1.4 4.8 0.0 4.8 3.3 3.3 4.8 4.0 0.0 0.4 3.0 5.3 5.3 2.7 (Reference:”Probabilistic Seismic Hazard Assessment Along the Southeastern Coast of Vietnam”, Nguyen Hong Phuong,2000) Referring to Figure 3-21 extracted from Vietnamese standard of “Specifications for Bridge Design (22TCN-272-05)”, the seismic class for this project shall be specified as Class 6. 3-21 Figure 3-21 Seismic Classes and Record of Major Earthquakes in South Vietnam (Reference: ”Probabilistic Seismic Hazard Assessment Along the Southeastern Coast of Vietnam”, Nguyen Hong Phuong,2000) Note: On the above figure, circles indicate record of earthquake are dotted. Bridge Location (5) Wind Velocity and Direction Directions and velocity of wind observed in Ba Ria - Vung Tau area is summarized in Tabl3-11. The annual mean wind velocity is 3.1m/s, and the maximum velocity of ten (10) second average is 26m/s in June 1976. According to the observed records, the monthly mean wind velocities for rainy season; highlighted figures, are relatively stronger than those observed in dry season in general. 3-22 Table 3-11 Wind Velocity and Direction at Project Area Velocity JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Mean V(m/s) 3.2 4.6 4.7 3.8 2.7 3.2 2.8 2.9 2.3 2.0 2.4 2.1 Max V(m/s) 15 15 15 15 20 26 20 19 18 14 16 14 Wind E E E E SW SW SW SW NH NW E E (Reference:BRITEC Report) (6) Navigation Clearance The navigation clearance for this project, which was approved by Vietnam Maritime Department by a letter 614/CHHVN-KHDT dated in April 3rd, 2009 (refer to Appendix-3), is shown in below table. Table3-12 Navigation Clearance for Phuoc An Bridge Class of Vessel 30,000DWT Navigation Height(H) Mmax1%(+1.60m)+ 55.0m Navigation Width(B) 120m(for one way flow) 239m(for two ways flow) (Reference:BRITEC Report, 614/CHHVN-KHDT) 3.3.3. (1) – Engineering Study Means for Crossing Over Thi Vai River TUNNELS: A tunnel plan affects to all the existing plans and facilities because this project has been started based on a bridge plan. A tunnel plan is not practical solution because it is not only technically difficult but physically taking enormous time for consistent with access roads plans and the development plan for the industrial area, whereas those planes have been implemented. – FERRIES: A ferry plan might give solution for expected bottleneck at Thi Vai river on planed road against predicted traffic volume, however the vast number of ferries for dissolve the bottleneck problem also makes newly bottleneck on Thi Vai river in terms of vessels crossing the ferries. Therefore, a ferry plan is not realistic. Above all, the means for crossing over Thi Vai river should be a bridge plan. (2) Determination of bridge length Bridge length shall be decided with respect to below view points; – Consistencies with relevant existing plans such as Cai Mep – Thi Vai Inter-Port Road Project. 3-23 1) – Gradient of approach bridge – Proposed height of bridge above navigation clearance – Geological conditions at project area – Height of bridge structures and embankment of approach road Consistencies with relevant existing plans The route and alignment for this project should accord with ”Investment for Construction Project of Cai Mep – Thi Vai Inter-port Road (BRIDGE & TUNNEL ENGINEERING CONSULTANT JOINT STOCK COMPANY, No HDKT)” in general. 2) Gradient of alignment The maximum gradient shall be 5.0 %, which comply with the Vietnamese specification written in TCXD VN 104-07, 3) Proposed height of bridge above Navigation Clearance The navigation clearance shall be 55.0m in height, of which base elevation is +1.60m (EL+56.5m). The proposed height above this navigation clearance shall be determined based on a height of superstructure. 4) Geological conditions at project area As for geographic characteristics, very soft clayey soil is widely deposited at the project area width a thickness of 30m from ground elevation. Regarding to the criteria for determination of bridge length, the height of embankment behind the abutments should be restricted approximately 7m from original ground elevation in order to maintain the stability of the embankment on soft ground. The illustration for proposed abutment and embankment, and bridge length accordingly determined are shown in figure 3-22. 3-24 Figure 3-22 Control point for Abutments location Bridge Length 3,226m River Width = appox. 450m End of bridge Beginning of bridge EL+6.466m 6.8m 7.4m Proposed height ▽existing ground elevation (3) Determination of Bridge Type and Span Arrangement 1) Determination of Bridge Type for Main Bridge In this section, bridge types preferable for crossing over Thi Vai river are studied. The following three types are compared for Phuoc An Bridge based on the navigation requirement of the width of 239m. The center span length is assumed to be 360m or more considering the foundation size and the allowance. Type 1: Cable Stayed Bridge Type 2: Suspension Bridge Type 3: Arch Bridge The comparison results are shown in Table 3-13. Based on the comparison, a cable stayed bridge (Type1) is selected due to economic efficiency and control of maintenance.. 3-25 Bridge Type 3-26 Type1 Type2 Type3 Economic 1.20 Because a large horizontal force Constructive operate on Foundation, the foundation dimension broaden Maintenance Because the arch rib is a steelmade, it is required to repaint painting though the concrete girder. There are a lot of numbers of materials, and the operation and Economic 1.25 Because a large horizontal force Constructive operate on Anchorage, the foundation dimension broaden Maintenance Because the girder is a steel, it is required to repaint the painting of the girder though the concrete Pylon. 【recommended practice】 Estimation Economic 1.00 Due to structural feature, a Constructive Large horizontal force doesn't operate on foundation . Maintenance Because Girder and Pylon are concretes, The repainting painting are unnecessary. Table 3-13 Comparison of Bridge Types 2) Determination of Span arrangement for Main Bridge The side span length doesn't have the constrained condition though the center span of cable stayed bridge that is determined navigation clearance. The following effects can be expected by a part of the approach bridge (the right and left 43m span) with the side span of the cable stayed bridge. - The bending moment balance at the dead load of the pylon is improved. - A negative reaction force in the end support (on the side pier) is improved. - The amount of the counter weight in the side span can be reduced. It is possible to be to a cost reduction with an improvement of durability according to such alteration. In the basic design stage, the side span length and the middle pier position shall be considered. Figure 3-23 Consideration of Side Span Length 3-27 (4) Studies for Foundation and Substructure 1) Selection of Foundation Type According to the assumption of bearing stratum elevation for bridge foundation, GL-60m can be bearing layers. The pylons of cable stayed bridge are planed in river, at which depth is approximately 10m, relatively deep (max. depth of riverbed is approx. 20m). The foundations of approach bridges are planed on land referring to existing drawings. Based on the above conditions and due considerations regarding procurement of construction materials and equipment, hypostyle bored pile (cast-in-place pile) foundation and bored pile foundation are recommended for pylons of the cable stayed bridge and other substructures respectively. As for a referential abstract, “Selection of Foundation Types (Specifications for Highway Bridges, Japan Road Association) “, is attached herewith as Table 3-14. Incidentally, since it is not mentioned in the table 3-14, the screwed steel pile foundation method, of which actual achievement has been increasing recently in Japan, has also applicability and is recommendable to the approach bridges. This method has advantage in terms of construction speed and quality control over a bored pile, moreover the selection of this method result application of Japanese Technology. In regard to economic efficiency, this pile is more sensitive than bored pile in terms of geological conditions, so that it is necessary to implement further study about applicability of this pile to the soil conditions at project area with additional soil investigations. Table 3-14 Selection of Approach Bridge Foundation Types 3-28 2) Location of Pylons Both of the pylons proposed by Vietnam are located in river (option 1). However, the pylon near Dong Nai side is close to right riverbank, to which distance form the objected pylon is around 40m. So, as for an alternative option, bridge center is shifted Dong Nai direction 40m (option2) and apply the on land construction to the Dong Nai side pylon. Since detailed comparison is expected to be carried out in the subsequent design stage, the benefits of option 2 are summarized as follow; – Facilitation of pylon construction can economize construction cost approximately 430 million JPY and shorten construction period (refer to Table 5-4). – Navigation center can be run at deepest riverbed. – Access to the pylon on land is easier than that in water when maintenance activity is carried out. Figure 3-24 Proposal for Alternative Location of Dong Nai Side Pylon ドンナイ側 To Dong Nai Option 1 Option 2 3-29 3.4. Outline of Project 3.4.1. Concept for Determination for Contents of the Project This project, which is a part of “Cai Mep – Thi Vai Inter-port Road Project” of which length is 21.3km and some part of the project has been moved on its construction stage, includes a cable stayed bridge crossing over Thi Vai river, approach bridges and an interchange. The road width is 23.5m with respect to Cai Mep – Thi Vai Inter-port Road Project. The main bridge is a concrete cable stayed bridge, of which actual achievement in Vietnam has been increasing. The length of its center span is determined with respect to navigation clearance (w=239m, h=55m), scale of pylon and its clearance from navigation. As for approach bridges, there are not any structures controlling its span arrangement, providing that crossing pipe line and railway. Therefore Super-Tee girder (ordinal span length is 40m) is adopted because of its plenty of experiences in the country. Accordingly, as for the foundation type, hypostyle pile foundation and pile foundation by using bored pile, which is commonly used in Vietnam, are selected for pylons and other substructures respectively. 3.4.2. Design Concept and Specifications for Bridge (1) Main Bridge (Cable Stayed Bridge) 1) Design Conditions – Ground elevation: Vung Tau Side EL +0.3m~+0.8m Dong Nai Side EL -2.0m~-0.30m In water EL -1.0m~-26.0m – Elevation of Bearing layer: EL-50.0m ~-60.0m – Characteristics of bearing Layer: Weathered rock with gravel – Construction yard: Material and Production yard at both riverbank – Navigation clearance w=239m、h=55.0m (EL+56.5m) (Reference: No. 614/CHHVN-KHDT, 3rd April, 2009) Note: navigation clearance during construction shall be confirmed. – Structural Type: superstructure :5span continuous concrete cable stayed bridge Substructure :(Pylon) hypostyle Bored pile, D=2.5m (Piers) bored pile, D=2.0m – Span Arrangement: 746m (43 + 150 + 360 + 150 + 43) – Road width: 23.5m – Deign Loads :Vietnamese standard (HL-93) – Gradient :longitudinal gradient max. 4%, Standard cross slope 2.0% 3-30 2) Conceptual Design – Height of girder: The height of superstructure is 2.5m referring to the existing data base for same type bridge – Stay cable: Double-plane cable is proposed to the Phouc An bridge, and the limited value for member force of the cable is initially determined as 0.4σu. – Pylon: A ration between a height of a pylon for a cable stayed bridge and a length of a center span is around 1/4 to 1/5 in general. The height of the pylon for this bridge is 85m (from bridge surface to top elevation of anchorage for stay cable) based on the actual achievements. The shape of the pylon is determined as H shape. – Foundation: Due to the deep riverbed, construction of pile cap at riverbed is difficult in terms of structure of cofferdam. Therefore, hypostyle foundation is selected. Additionally, in order to reduce the number of piles, penetration depth of pile tip to bearing stratum is deepened with respect to the pile length feasible for construction. 3) Drawing In accordance with foregoing design conditions, the General Views of main bridge are prepared in figure 3-25 & 3-26. (2) Approach Bridge 1) Design Conditions – Ground elevation: Vung Tau Side EL -0.5m~+1.40m Dong Nai Side EL -2.0m~+1.20m In water EL -1.0m~-26.0m – Elevation of Bearing layer: EL-50.0m ~-60.0m – Characteristics of bearing Layer: Weathered rock with gravel – Construction yard: – Structural Type: superstructure :Continuous Super Tee girder bridge Material and Production yard at both riverbank Substructure : Bored pile foundation, D=1.2m – Span Arrangement: 40m (for typical spans) – Road width: 23.5m 3-31 – Deign Loads :Vietnamese standard (HL-93) – Gradient :longitudinal gradient max. 4% Standard cross slope 2.0% 2) Conceptual Design – Height of girder: The height of superstructure is 1.75m referring to the existing data base for same type bridge – Foundation: Pile foundation is selected due to the depth of bearing stratum. The number of pile for a substructure is designed with respect to Negative Friction to be caused by consolidation of very soft clayey soil layer distributed at the depth around GL-0m to GL-30m. 3) Drawing In accordance with foregoing design conditions, the General Views of main bridge are prepared in figure 3-25 & 3-26. 3-32 <― To Vung Tau To Dong Nai ―> Figure 3-25 General View (1) 3-33 Figure 3-26 General View (2) 3-34 3.4.3. Technical Issues and Solutions There are two types of bridges are proposed in the the Phuoc An Bridge project, namely, 5 spans continuous PC cable stayed bridge, which cross over Thi Vai river, and Continuous Super-Tee girder bridges, that is proposed to be adopted for approach bridges. According to the actual achievement for PC cable stayed bridges constructed in Japan, the largest center span length is 261m whereas that for the cable stayed bridge proposed to this project is 360m. However, counting oversea project into experiences of Japanese firms, the center span has reached to 430m, and it can be said that there are not any technical issues. Moreover, regarding Super-Tee girder bridges, this type of bridge has been utilized in Vietnam, and not any technical issues exist. In the meantime, there are some technical matters, to which further studies shall be carried out during the subsequent design stage, as shown below. The recommendable solutions to the matter are also described. Table 3-15 Technical Issues and Solutions Technical issues Solutions There are only two (2) boring logs To implement further geotechnical survey in available to this project now. So that the following accuracy of estimation regarding soil comprehend conditions is low. design the stages in order characteristics of to soil conditions in detail. Amount of bored piles is huge whereas the Application of Screwed Steel Pile (steel pipe construction period is short. So that pile with wing) can shorten the construction difficulties in terms of quality control and period and increase quality controllability. construction schedule control are concerned. Soft soil deposited at project area is very Application of Vacuum Consolidation Method sensitive and thick, so that the period can shorten the period and improve the before onset of expected soil strength after reliability of soil strength to be treated. ground improvement might be taken longer time and influenced to construction schedule. Wind resistant stability of cable stayed The stability can be verified by wind tunnel bridge during construction and operation test. shall be confirmed. The shape of girder-end of Super Tee Change of the shape (without cut-off ) can girder, at which cut-off is commonly increase the durability and reliability of the adopted in Vietnam. Super Tee girder against heavy traffic. 3-35 Chapter 4 Considerations on Natural and Social Environments 4.1. Status Analysis on Current Conditions of Natural and Social Environmental Aspects 4.1.1 Outline of the Project Area Figure 4-1 Distant View of the Project Area Phuoc An Bridge Thi Vai River Figure 4-2 Schematic Diagram of Roads and Facilities in the Project Area Ben Luc-Long Thanh Expressway Bien Hoa-Vung Tau Expressway Industrial zone Phuoc An Bridge Commercial /Residential zone Inter-Port Road NH 51 Can Gio Mangrove Biosphere Reserve Thi Vai River Port facility Figures mentioned above show the distant view and the schematic diagram of roads and facilities in the Project area. The proposed Phuoc An Bridge including the approach bridge is to be constructed in the Cai Mep-Thi Vai Port developing project area, and forms the part of the Cai Mep-Thi Vai Inter-Port Road which runs north and south through the Cai Mep-Thi Vai International Port. The Cai Mep-Thi Vai International Port, which is port 4-1 group No.5, is one of the 3 strategic important port facilities as an international port in Vietnam together with the Hải Phòng International Port and Van Phong International Port. The area of the Cai Mep-Thi Vai International port is located on left bank of the Thi Vai River and Ban Thach canal, and about 30km from its mouth at Vung Tau cape. The Cai Mep International Port is composed of Cai Mep International Container Port and Thi Vai International Multipurpose Port. The two ports are the large ports group in the Thi Vai Vung Tau deep water port system. The Cai Mep Container Port and the Thi Vai multipurpose port are about 7km and 3km far from the National Highway No.51 (NH51) respectively. The NH51 is important main road from Ho Chi Minh City to Vung Tau. As shown in Fig. 4-2 above, industrial zones, which are now under constructing, are located between the Cai Mep-Thi Vai International Port and NH51, and commercial and/or residential zones spread out along NH51. Although the NH51 is functioning as transportation road for the port at present, the NH51 is bothered with traffic congestion chronically. In this meaning, the opening of the Cai Mep-Thi Vai Inter Port Road including the Phuoc An Bridge is expected to play vital role as a port distribution system. 4.1.2 Project site and Environmental Conditions (1) Project site The proposed project area of the Phuoc An Bridge is located in the Phuoc Hoa commune of the Tan Thanh district of Ba Ria-Vung Tau province. Phuoc Hoa commune includes 6 hamlets: Song Vinh, Ong Trinh, Phuoc Loc, Hai Son, Lam Son, and Phuoc Son. Based on the statistic data in 2002, the population of Phuoc Hoa commune is about 17,200 people living in a total area of 8,324.7ha. Distribution of land use in Phuoc Hoa commune is summarized below: Table 4-1 Land use of Phuoc Hoa Commune No. Type of Land Use Area (ha) Percentage (%) Total area of Phuoc Hoa 8,324.7 1 Agriculture 2,897.47 34.8 2 Aquaculture 190 2.3 3 Industrial zone 430.93 5.2 4 Residential area 82.73 1.0 (Source: EIA Report for Cai Mep-Thi Vai International Port Project, 2003) The agriculture land includes the area for rice, crops, long term tree cultivation. The mangrove forest is dominant in Phuoc Hoa. The mangrove forest mainly locates in the Thi Vai river bank. The other land areas are canals, ponds, roads, etc. The Phuoc An Bridge is to be constructed at the current swampy mangrove area above mentioned. Although there are no residents and no commercial activities in the proposed project area, a few facilities such as VINALINE are planned to be constructed. Considering the current conditions of the project site and the contents of the Project, it is required to start a consultation over a matter of land acquisition with the concerned organizations of the project sites. 4-2 (2) Environmental Conditions The proposed Phuoc An Bridge is to be constructed over the Thi Vai River connecting Tan Thanh district, Ba Ria–Vung Tau province to Nhon Trach district, Dong Nai province. The topographic conditions of the construction site is generally swampy mangrove forest. Mangrove forest region is one of the main primary producers in the coastal and estuarine regions providing nutrients, foods, shelter and habitat to many species of fish and shellfish. As shown in Fig. 4-2, the buffer zone of mangrove forest region of Can Gio Mangrove Biosphere Reserve, not the core zone of Can Gio Mangrove Biosphere Reserve, spread out at the opposite bank of the project site across the Thi Vai River. This biosphere Reserve region is considered one of the most important mangrove forest regions in Vietnam. Although Can Gio Mangrove Biosphere Reserve is not included in the project area, careful attention should be paid to avoid and/or to minimize potential serious impacts caused by the implementation of the Phuoc An Bridge Construction Project. Figure 4-3 Condition of Project around aria (1) The climate of the Ba Ria–Vung Tau is typical of the monsoon weather pattern, and the weather is divided into two seasons, dry and rainy. The rainy season usually start from the middle week of May and extend to the middle week of November, and can extend to the end of November with wind in South – West direction. West-South monsoon appears with thunderstorm and heavy rain in afternoon. And have some storms go through this area. Dry season usually start from November, and extend to the middle week of May in next year with North-West wind direction. In this season, rainfall is not much, even, some months have no rain. Humid seasonal winds from the southwest prevail from May to October, and dry winds from the northeast from November to March. These two periods show a very distinct rainy season, which is associated with heavy tropical downpours. 4-3 Figure 4-4 Condition of Project around aria (2) 4.1.3 Alignment of Inter-Port Road and Phuoc An Bridge The Cai Mep - Thi Vai Inter Port Road has a total length of 21.3 km, connecting seaport system and industrial zones along Cai Mep – Thi Vai river, Tan Thanh district of Ba Ria - Vung Tau province and Nhon Trach district of Dong Nai province. The start point is from Cai Mep Ha General and Container Terminal, and the end point is from the Phuoc An port, Nhon Trach district, Dong Nai. The alignment of the Inter-Port road is separated into 9 components as follows (2669/QD-UBND, Item 15.2): Component No.1 : Km0+000 – Km1+893.03 (Implementation period = 2010 to 2012) Component No.2 : Km1+898.03 – Km7+199.25 (Implemented by PMU85) Component No.3 : Km7+199.25 – Km9+612.64 (Implementation period = 2009 to 2011) Component No.4 : Km9+612.64 – Km11+698.78 (Implementation period = 2010 to 2012) Component No.5 : Km11+698.78 – Km14+424.98 (Implementation period = 2010 to 2012) Component No.6 : Km14+424.98 – Km15+561.31 (Implementation period = 2009 to 2012) Component No.6 : Km14+424.98 – Km15+561.31 (Implementation period = 2009 to 2012) Component No.7 : Km15+561.31 – Km17+271.13 (Implementation period = 2010 to 2012) Component No.8 : Km17+271.13 – Km18+100 (Implementation period = 2009 to 2012) Component No.9 : Km18+100 – Km21+360.94 Among the components above, component No.9 can be divided into two phases, namely phase 1: Km18+100 – Km19+650 (frontage road, implementation period = 2010 to 2012) and phase 2: Km18+100 – Km21+360.94 (Phuoc An Bridge and the approach bridge including grade separated interchange at the end). As mentioned above, the Phuoc An Bridge Construction Project corresponds to phase 2 of the component No.9. The Phuoc An Bridge is located at the northernmost part of the Inter-Port Road, and passes over the Thi Vai River and connects Tan Thanh district of Ba Ria–Vung Tau province and Nhon Trach district of Dong Nai province. The Department of Transport under the Ba Ria-Vung Tau provincial people’s committee is assigned as investor of this project. Construction schedule is planned to start by 2012 and be completed by 2015. 4-4 4.1.4 Bridge Types and Road Specification (1) Bridge type ■ Main Bridge : Prestressed Concrete Cable-stayed Bridge (Center Span = 360m) ■ Approach Bridge : Super-T Girder (Span lengths vary from 25 to 40m) ■ Total Length = 3,254.5m (including abutments) (2) Road specification ■ Urban Road Classification : Main urban road ■ Function : Main axis road industry zones ■ Design Speed (Vd) : Vd = 70km/hr ■ Total bridge width : 23.5m ■ Navigation Clearance at the Center Span of the Main Bridge : 239m (W) x 55m (H) 4.1.5 Environmental Impact Assessment (EIA) According to the Vietnamese Law on Environmental Protection (Law NO. 52, new LEP), Environmental Impact Assessment (EIA) for development projects is compulsory at present. The project for Cai Mep-Thi Vai Inter-Port Road also required the implementation of EIA. Process and procedures of EIA in Vietnam are prescribed by EIA related laws and regulations such as Decree No. 175/CP. Legal basis of EIA in Vietnam are shown in the section 4.4. As for the implementation of EIA for the Cai Mep-Thi Vai Inter-Port Road Project, Ministry of Natural Resources and Environment (MONRE), which is the responsible agency for EIA, approved to conduct EIAs by each divided component previously mentioned due to the reason that the investor or the executor and the time of implementation are differ from by the divided component projects. Current status of the implementation of EIA for the Cai Mep Inter-Port Road project by component is summarized below: Table 4-2 Status of Implementation of EIA in Cai Mep-Thi Vai Inter-Port Road Project Component No. Status 1 2 3 4 5 EIA report submitted to DONRE, Under appraisal Approved by DONRE Approved by DONRE Not required (Existing road) Not required (Existing road) 6 7 8 Not required (Existing road) Under implementation Not implemented yet Not implemented yet, planned to be implemented in 2011, to be appraised and approved by MONRE 9 The Phuoc An Bridge passes over the Thi Vai River and stretches over two provinces, Ba Ria-Vung Tau and Dong Nai. Therefore, MONRE instructed that the EIA report prepared for the component No.9 should be appraised and approved by MONRE. 4-5 4.1.6 Prospects of future environment The Cai Mep-Thi Vai International Port Development Project is now under progressing. For the Port Project, establishment of the road system is indispensable factor. Comparing the progress of the development of the port project, development of road constructions in the port area is left behind as of December 2010. The port development project is not completed yet and not operated fully, goods handled in the port and the industrial areas are mainly transferred to the outside of the areas using the NH51 which runs eastern side of the port area. Although the NH51 is functioning as transportation road for the port at present, the NH51 is bothered with traffic congestion chronically. If the Cai Mep-Thi Vai Inter-Port Road Construction Project including the construction of the Phuoc An Bridge is opened to traffic, the Inter-Port Road contribute the transportation of goods in the Cai Mep-Thi Vai International Port as an industrial road. Together with the construction of the Inter-Port Road, opening of the Bien Hoa - Vung Tau Expressway and the Ben Luc-Long Thanh Expressway are expected in near future near the project area. If this transportation system is established, the current situation of road transportation system in and around the project area will be drastically changed. Considerable amount of goods transported in the port and the industrial zone will be converted to the Inter-Port Road from the NH51. This leads to ease traffic congestion and to reduce traffic accident, noise and air pollutants in the NH51. As a result of the reduction of traffic congestion and the traffic volume in NH51, generation of carbon dioxide (CO2) from the vehicle will be reduced in and around the project area as a whole. Degree of the reduction of CO2 with the implementation of the project is to be discussed in next section “4.2 Environmental Improvement by Implementation of the Project”. 4.2 Environmental Improvement by Implementation of the Project 4.2 1 General The Cai Mep-Thi Vai Inter-Port Road including the Phuoc An Bridge connects the port system and the industrial zones along the Thi Vai river. At present, there are no roads except NH51 to transport the goods in the port and the industrial zones along the Thi Vai river. Considering the current conditions of NH51, which is congested chronically with cars, it is difficult that NH51 will function as an industrial road in this area. If the Cai Mep-Thi Vai Inter-Port Road including the Phuoc An Bridge is constructed, the road and the bridge will play important role as an industrial road in this area. Besides the construction of the Cai Mep-Thi Vai Inter-Port Road, Bien Hoa-Vung Tau Expressway is planned to start operation in 2017. The use of these road systems will lead to ease the current traffic congestion of NH51 and to reduce noise, vibration and discharge of atmospheric pollutants by cars. 4-6 4.2.2 Estimate of CO2 Emission 1. Premises ■ Area to be evaluated: Area which covers the Phuoc An Bridge, NH51 and Bien Hoa-Vung Tau Expressway ■ Year: 2008, 2020 and 2030 ■ Cases evaluated: With and without the construction of Phuoc An Bridge are to be evaluated ■ Traffic volume Estimate of the number of vehicles passing each road is shown below: Table 4-3 Estimate of Traffic Volume Year Case 4,500 8,100 24,700 Passenger car Large sized car Total in PCU/day ■ 2020 2030 With Without With Without NR51 (Link: 2421) 3,400 3,500 5,200 5,600 4,200 6,100 5,700 6,200 14,000 18,600 19,500 21,000 2008 Passenger car Large sized car Total in PCU/day Bien Hoa-Vug Tau Exp. (H3202) 0 4,000 6,600 10,400 0 8,600 17,800 21,200 0 25,500 51,100 63,300 11,700 33,900 96,500 Passenger car Large sized car Total in PCU/day 0 0 0 Phuoc An Bridge 3,500 0 1,700 13,000 0 14,900 35,900 0 38,800 0 0 0 Running speed of cars Table 4-4 Running Speed of Vehicle (Unit: km/h) ■ Year Case 2008 NH51 Phuoc An Bridge Bien Hoa-Vung Tau Expr. 30 With 60 - 70 100 2020 Without 40 100 With 40 70 100 2030 Without 30 100 Emission coefficient of CO2 by car running speed Table 4-5 Emission Coefficient of CO2 Emission coefficient (g-CO2/vehicle/km) Passenger car Bus, Truck 30 175.5 962.9 40 151.7 835.5 Running Speed (km/h) 50 60 70 137.4 130.3 129.2 750.0 706.3 704.5 100 158.3 949.5 (Source: Technical Guidelines for Calculation of Emissions of GHGs for Road Construction Project (Draft)) 4-7 ■ Calculation of emission of Carbon Dioxide (CO2) Emission of Carbon Dioxide (CO2) from vehicles per 1km running per year can be calculated using the formula below: Emission of CO2 (Ton-CO2/year/km) = (Traffic volume: Number of vehicle/day) X (Emission coefficient) X 365 X 1/106 2. Results of the calculation Result of the calculation is shown below: Table 4-6 Emission of CO2 in and around the Project Area from Vehicle (Unit: Ton-CO2/year/km) Year Case 2008 288 2,847 3,135 Passenger car Large sized car (1) Total (T-CO2/km/Year) 2020 2030 With Without With Without NR51 (Link: 2421) 162 194 288 359 1,083 1,860 1,738 2,179 1,244 2,054 2,026 2,538 Passenger car Large sized car (2) Total (T-CO2/km/Year) Bien Hoa-Vug Tau Exp. (H3202) 0 231 381 601 0 2,980 6,169 7,347 0 3,212 6,550 7,948 676 11,749 12,425 Passenger car Large sized car (3) Total (T-CO2/km/Year) 0 0 0 Phuoc An Bridge 165 0 80 3,343 0 3,831 3,508 0 3,912 0 0 0 Total of Emission of CO2 in and around the Project Area Year Case (1)+(2)+(3) Total (T-CO2/km/Year) 2008 3,135 2020 With Without 7,964 8,604 2030 With Without 13,886 14,962 Figure 4-5 Estimate of Emission of CO2 In and Around the Project Area from Vehicles Estimate of CO2 Emission In and Around the Project Area 16,000 15,000 CO2 Emission (T-CO2/km/Year) 14,000 13,000 12,000 11,000 10,000 9,000 8,000 With Case Without Case 7,000 6,000 5,000 4,000 3,000 2,000 2005 2010 2015 2020 2025 2030 2035 Year As mentioned above, Bien Hoa-Vung Tau Expressway is to be constructed in near future, planned to open in 2017, together with the construction of the Cai Mep - Thi Vai Inter-Port Road. The establishment of these road systems will lead the traffic conditions to dissolution of traffic congestion and to reduction of noise, 4-8 vibration and accidents caused by vehicles in and around the project areas. In the other hand, this also leads the traffic conditions to increase of number of vehicles passing in these roads in the future. In accordance with the increase of vehicles, amount of automobile exhaust gases increases. Figure below shows an estimate of total number of vehicles passing the Phuoc An Bridge, NH51 and Bien Hoa-Vung Tau Expressway up to 2030. Figure 4-6 Number of Vehicles Passing Phuoc An Bridge, NH51 and BV Expressway Number of Vehicles Passing PA Bridge, NR51 and BV Exp. 142,000 Number of Vehicles (PCU/day) 122,000 102,000 82,000 With Case Without Case 62,000 42,000 22,000 2,000 2005 2010 2015 2020 2025 2030 2035 Year The result of the estimate of CO2 emission above shows that: ■ Amount of CO2 emission of the With case will be reduced about 640 and 1,100 ton-CO2/km/year in 2020 and 2030 respectively comparing than those of the Without case. ■ It should be noted that the increased amount of CO2 emission caused by the increase of number of vehicles is offset by the reduction of amount of CO2 emission caused by dissolution of the traffic congestion on NH51. It should be also noted that the Bien Hoa-Vung Tau Expressway contributes dissolution of the traffic congestion on NH51 even in case of the Without case. ■ If the traffic congestion of NH51 is left continuously as it is to the future, the more amount of CO2 will be emitted from vehicles. (Traffic congestion Case) ■ Effect of CO2 reduction by the implementation of the Project is considered to be the difference amount of CO2 emission between the With case and the Traffic congestion case above mentioned. Total amount of CO2 emitted in the case of Traffic congestion can be estimated as follows: Table 4-7 Estimate of Reduction of CO2 Emission by the Implementation of the Project Year Case Total (T-CO2/km/Year) Difference (T-CO2/km/Year) 2008 3,135 - 2020 With Without Congestion 7,964 8,604 9,766 0 1,802 2030 With Without Congestion 13,886 14,962 15,799 0 1,913 Table above shows that as a result of the implementation of the Project, amount of CO2 emission will be reduced about 1,800 ton/km/year and 1,900 ton/km/year in 2020 and 2030 respectively. Figure below shows the effect of reduction of CO2 emission schematically. 4-9 Figure 4-7 Effect of CO2 Emission by the Implementation of the Project Estimate of Emission of CO2 in and around the Project Area 18,000 With Case Without Case Congestion Emission of CO2 (Ton-CO2/km/Year) 16,000 14,000 Without Case CO2 reduction effect by the implementation of 12,000 Continuous tarffic congestion 10,000 With Case 8,000 6,000 4,000 2,000 2005 2010 2015 2020 2025 2030 2035 Year 4.3 Impacts on Natural and Social Environments due to Implementation of the Project The Project for development of Cai Mep-Thi Vai International Port is now progressing. The Cai Mep-Thi Vai Inter-Port Road Construction Project which includes the Phuoc An Bridge Construction Project is considered as a part of the Project for development of Cai Mep-Thi Vai International Port. The EIA study for the Cai Mep-Thi Vai International Port Project has already been conducted by the project proponent and approved by MONRE and DONRE. According to the EIA report for the port development project above mentioned, potential impacts on the environment, both natural and social, arising from the implementation of the project are concluded to be not serious one. Apart from the EIA study for the Cai Mep-Thi Vai International Port Project, EIA studies for the Component No.9 of the Inter-port Road are also required according to the Vietnamese environmental related laws and regulations. The status of implementation of EIA for the component projects of the Inter-Port Road Project are shown in Table 4-2 of section 4.1. The EIA for the Phuoc An Bridge construction project has not conducted yet. Due to the reason that the Phuoc An Bridge stretches over two provinces, Ba Ria - Vung Tau and Dong Nai, the EIA report prepared is appraised and approved by MONRE. This study is conducted in the earliest phase of the decision making process. The major objective of “Environmental and social considerations” in project formation studies is to provide data to determine whether the project should be taken to the next phase, and to clearly identify a broad range of items to be investigated in the next phase, if the project goes forward, from an environmental and social standpoint. According to the JBIC guidelines, all proposed projects are to be classified into three categories, namely those likely to have a significant environmental and social impact (Category A), those likely to have a less adverse environmental and social impact than that of Category A projects (Category B), and those likely have a minimal or no adverse environmental and social impact (Category C). Based on the conclusion of the EIA of the Cai Mep International Port development project, the Project of Phuoc An Bridge can be classified into Category B project. Although submission of EIA reports to JBIC is not a mandatory requirement for Category B project, it is recommended that the project proponent should submit the EIA reports and environmental 4-10 permit certificates issued by the government of Vietnam or other appropriate authority following Category A projects. Following shows the environmental reviews to identify major impacts on natural and social environments using the JBIC screening formats. 4-11 Table 4-8 Environmental Checklist: 16. Roads , Railways and Bridges Category Environment al Item (1) EIA and Environmenta l Permits 1 Permits and Explanation (2) Explanation to the Public Main Check Items Confirmation of Environmental Considerations ① Have EIA reports been officially completed? ② Have EIA reports been approved by authorities of the host country’s government? ③ Have EIA reports been unconditionally approved? If conditions are imposed on the approval of EIA reports, are the conditions satisfied? ④ In addition to the above approvals, have other required environmental permits been obtained from the appropriate regulatory authorities of the host country’s government? ① Are contents of the project and the potential impacts adequately explained to the public based on appropriate procedures, including information disclosure? Is understanding obtained from the public? ② Are proper responses made to comments from the public and regulatory authorities? ① Is there a possibility that air pollutants emitted from various sources, such as vehicle traffic will affect ambient air quality? Does ambient air quality comply with the country’s ambient air quality standards? ② Where industrial areas already exist near the route, is there a possibility that the project will make air pollution worse? 1, 2, 3 EIA procedures of the project have not conducted yet. 4. No 1, 2 No. As mentioned above, EIA procedures of the project have not conducted yet. The project area is located in swampy mangrove forest region, and there are no residents in this area. Construction of a shipyard of VINALINES is planned. Discussion on the project should be made between the project proponent and VINALINES 1. - (1) Quality Air 2. 2 Mitigation Measures (2) Water Quality ① Is there a possibility that soil runoff from the bare lands resulting from earthmoving activities, such as cutting and filling will cause water quality degradation in downstream water areas? ② Is there a possibility that surface runoff from roads will contaminate water sources, such as groundwater? ③ Do effluents from various facilities, such as stations and parking areas/service areas comply with the country’s effluent standards and ambient water quality standards? Is there a possibility that the effluents will cause areas that do not comply with the country’s ambient water quality standards? 1. - - 4-12 Yes The EIA procedure to be conducted will clarify the degree of the impacts on air quality caused by the implementation of the project. The EIA report will also propose mitigation measures to avoid and/or minimize serious negative impacts on air quality. The mitigation measures are also included in the tender documents and the contracts. Major items to be included in the EIA report and the tender/contract documents are: Recommendation of planting trees at the road sides, Control of exhaust gas and dust emission during construction phase, Ban on trucks with over exhaust gas to use the road during operation phase Carrying out of regular maintenance of road and bridge pavement, Water spraying regularly on road surface at least 10 days/time in dry season, Taking care of trees and landscape along the road/bridge, Carrying out of ambient air quality monitoring, Adjoining the alignment of Inter-Port Road, industrial zone is now under constructing in the Cai Mep International Port area, the project has a potential to worsen the air quality. But the influence of the project on air quality is considered site specific. Yes But the project area is generally swampy mangrove forest. The EIA procedure to be conducted will clarify the degree of the impacts on water quality caused by the implementation of the project. The EIA report will also propose mitigation measures to avoid and/or minimize serious negative impacts on water quality. The mitigation measures are also included in the tender documents and the contracts. Major items to be included in the EIA report and the tender/contract documents are: Establish design criteria applicable for the project section with hydrogical regimes, Perimeter cut-off drains to direct off-site water around the site shall be constructed and internal temporary drainage works and erosion and sediment control facilities implemented at the start of site establishment Formation of plan for works to minimize surface excavation works during the rainy season where Category Environment al Item Main Check Items Confirmation of Environmental Considerations practicable Use of channels, earth bunds, netting, tarpaulin and/or sand bag barriers on site to manage surface water runoff and minimize erosion - Completion of all exposed earth areas and re-vegetation as soon as possible after completion of earthworks 2. Yes Followings should be included in the report/documents of EIA, Tender and Contract - Construction of drainage system and retention ponds to collect and treat surface runoff from road/bridge prior to discharge to the local surface water bodies - - (3) Noise and Vibration (1) Protected Areas (2) Ecosystem and biota 3 Natural Environment (3) Hydrology (4) Topography and Geology ① Do noise and vibrations from vehicle and train traffic comply with the country’s standards? ① Is the project site located in protected areas designated by the country’s laws or international treaties and conventions? Is there a possibility that the project will affect the protected areas? ① Does the project site encompass primeval forests, tropical rain forests, ecologically valuable habitats (e.g., coral reefs, mangroves, or tidal flats)? ② Does the project site encompass the protected habitats of endangered species designated by the country’s laws or international treaties and conventions? ③ If significant ecological impacts are anticipated, are adequate protection measures taken to reduce the impacts on the ecosystem? ④ Are adequate protection measures taken to prevent impacts, such as disruption of migration routes, habitat fragmentation, and traffic accident of wildlife and livestock? ⑤ Is there a possibility that installation of roads will cause impacts, such as destruction of forest, poaching, desertification, reduction in wetland areas, and disturbance of ecosystems due to introduction of exotic (non-native invasive) species and pests? Are adequate measures for preventing such impacts considered? ⑥ In cases where the project site is located at undeveloped areas, is there a possibility that the new development will result in extensive loss of natural environments? ① Is there a possibility that alteration of topographic features and installation of structures, such as tunnels will adversely affect surface water and groundwater flows? ① Is there a soft ground on the route that may cause slope failures or landslides? Are adequate measures considered to prevent slope failures or landslides, where needed? ② Is there a possibility that civil works, such as cutting and filling will cause slope failures or landslides? Are adequate measures considered to 4-13 Construction of retention pond to treat runoff water if necessary 3. Once the proposed mitigation measures to be strictly applied and well controlled, there is no possibility. 1. Construction machines, trucks and other machines generate noise and vibration during construction phase. Good maintenance of equipment/machine, careful construction program are required. 1. No. But it should be noted that Can Gio Mangrove Biosphere Reserve spread out at the opposite bank of the project site across the Thi Vai River, and the project site is also generally covered with the swampy mangrove forest. Careful attention should be paid to reduce or minimize the impacts on the mangrove forest in and around the project area caused by the implementation of the project. 1., 2, 3, 4, 5 The project site is generally covered with the swampy mangrove forest. Mangrove forest region is one of the main primary producers in the coastal and estuarine regions providing nutrients, foods, shelter and habitat to many species of fish and shellfish. It is considered that implementation of the project will exert some influences upon the fishery industry around the project site as well as the natural environment. Detailed influences should be studied in the EIA to be conducted, and countermeasures such as compensation of fishery rights should be proposed in the EIA report if necessary. 1. Although there is a possibility to alter the topographic features and surface water flows in the project area, it is anticipated that the influences upon the environment is not significant. 1. The project area is generally swampy mangrove forest. Slope failures or landslides are not likely to be induced. 2. The bridge is planned in the mangrove forest areas, and therefore, occurrence of large-scale slop failures or landslides are not anticipated. 3. The following measures are proposed to prevent soil Category Environment al Item Main Check Items prevent slope failures or landslides? ③ Is there a possibility that soil runoff will result from cut and fill areas, waste soil disposal sites, and borrow sites? Are adequate measures taken to prevent soil runoff? Confirmation of Environmental Considerations runoff from earthwork sites, waste soil disposal sites, and borrow sites: - Contractors will be obligated to minimize exposition of soil surface caused by excavation works during the rainy season where practicable. - The material stockpile sites, the earthwork sites where exposed land surface is vulnerable to runoff, etc. should be consolidated and/or covered; - The material stockpile sites should be far away from surface water bodies and areas prone to surface run-off. Loose materials should be bagged and covered. Open ditch should be built around the stockpile sites to intercept wastewater. Channels, earth bunds, netting, tarpaulin and/or sand bag barriers shall be used on site to manage surface water runoff and minimize erosion; (1) Resettlement 4 Social Environment (2) Living and Livelihood ① Is involuntary resettlement caused by project implementation? If involuntary resettlement is caused, are efforts made to minimize the impacts caused by the resettlement? ② Is adequate explanation on relocation and compensation given to affected persons prior to resettlement? ③ Is the resettlement plan, including proper compensation, restoration of livelihoods and living standards developed based on socioeconomic studies on resettlement? ④ Does the resettlement plan pay particular attention to vulnerable groups or persons, including women, children, the elderly, people below the poverty line, ethnic minorities, and indigenous peoples? ⑤ Are agreements with the affected persons obtained prior to resettlement? ⑥ Is the organizational framework established to properly implement resettlement? Are the capacity and budget secured to implement the plan? ⑦ Is a plan developed to monitor the impacts of resettlement? ① Where roads or railways are newly installed, is there a possibility that the project will affect the existing means of transportation and the associated workers? Is there a possibility that the project will cause significant impacts, such as extensive alteration of existing land uses, changes in sources of livelihood, or unemployment? Are adequate measures considered for preventing these impacts? ② Is there a possibility that the project will adversely affect the living conditions of inhabitants other than the affected inhabitants? Are adequate measures considered to reduce the impacts, if necessary? ③ Is there a possibility that diseases, including communicable diseases, such as HIV will be introduced due to immigration of workers associated with the project? Are adequate considerations given to public health, if necessary? 4-14 - All exposed earth areas shall be completed and re-vegetated as soon as possible after completion of earthworks. 1., 2., 3., 4., 5., 6., 7 No. There are no households or residents in and around the project site. 1. 2. 3. 4. Construction of the Inter-Port Road and the Phuoc An Bridge will change the current road transportation system in Cai Mep-Thi Vai International Port. Although the Cai Mep-Thi Vai International Port is under developing, transportation of goods and products in this area is rested with the NH51 currently. After the completion of the Inter-Port Road and the Phuoc An Bridge, the function of transportation of NH51 in this area will be converted to the Inter-Port Road and the Phuoc An Bridge. This will reduce the traffic congestion, noise, accidents, and discharge of atmospheric pollutants such as nitrogen oxides. As mentioned, the greater part of the project site is covered with swampy mangrove forest. Although implementation of the project has a possibility to affect impacts on the ecological system of the mangrove forest and the aquaculture in and around the project site, the impacts are anticipated to be not so serious and site-specific ones. No, there are no residents in the project site. During construction phase, there is a possibility to increase traffic congestions and accidents on the Category Environment al Item (3) Heritage (4) Landscape (5) Ethnic Minorities and Indigenous Peoples (6) working conditions Main Check Items Confirmation of Environmental Considerations ④ Is there a possibility that the project will adversely affect road traffic in the surrounding areas (e.g., by causing increases in traffic congestion and traffic accidents)? ⑤ Is there a possibility that roads and railways will cause impede the movement of inhabitants? ⑥ Is there a possibility that structures associated with roads (such as bridges) will cause a sun shading and radio interference? NH51 and neighboring roads, due to the concentration of construction vehicles using these roads to access to construction sites. Mitigation measures are to be recommended in the EIA report prepared such as the followings: - Carefully prepare the construction plan in order to minimize the area and period of road occupation/closure, and avoid concentration of construction vehicles; - Prior notice local residents on the road occupation/closure through sign boards and mass media; - Allocate personnel at place vulnerable to traffic congestion to instruct detour. 5. The bridge and the approach bridge do not impede the movement of inhabitants due to no inhabitants in the project site. As for the ship navigation under the bridge, sufficient bridge height and the navigation clearance at the center span width are to be secured. 6. Influence if the bridge on radio interference not sure at present, but unlikely anticipated. ① Is there a possibility that the project will damage the local archeological, historical, cultural, and religious heritage sites? Are adequate measures considered to protect these sites in accordance with the country’s laws? ① Is there a possibility that the project will adversely affect the local landscape? Are necessary measures taken? ① Where ethnic minorities and indigenous peoples are living in the rights-of-way, are considerations given to reduce the impacts on culture and lifestyle of ethnic minorities and indigenous peoples? ② Does the project comply with the country’s laws for rights of ethnic minorities and indigenous peoples? ① Is the project proponent not violating any laws and ordinances associated with the working conditions of the country which the project proponent should observe in the project? ② Are tangible safety considerations in place for individuals involved in the project, such as the installation of safety equipment which prevents industrial accidents, and management of hazardous materials? ③ Are intangible measures being planned and implemented for individuals involved in the project, such as the establishment of a safety and health program, and safety training (including traffic safety and public sanitation) for workers etc.? ④ Are appropriate measures being taken to ensure that security guards involved in the project do not violate safety of other individuals involved, or local residents? 1. No. There are no local archeological, historical, cultural, and religious heritage sites in the project site. 4-15 1. No. It is anticipated that the landscape of the bridge will be well blended into the surrounding area. 1. The Project area is far away from the living habitats of ethnic minorities. There are no indigenous people in the Project area. 2. Not applicable 1, 2, 3, 4 The project proponent will take care not to violate any laws and ordinances associated with the working conditions of the country. Category Environment al Item (1) Impacts during Construction 5 Others (2) Monitoring Reference to Checklist of Other Sectors 6 Note Note on Using Environmenta l Checklist Main Check Items ① Are adequate measures considered to reduce impacts during construction (e.g., noise, vibrations, turbid water, dust, exhaust gases, and wastes)? ② If construction activities adversely affect the natural environment (ecosystem), are adequate measures considered to reduce impacts? ③ If construction activities adversely affect the social environment, are adequate measures considered to reduce impacts? ① Does the proponent develop and implement monitoring program for the environmental items that are considered to have potential impacts? ② Are the items, methods and frequencies included in the monitoring program judged to be appropriate? ③ Does the proponent establish an adequate monitoring framework (organization, personnel, equipment, and adequate budget to sustain the monitoring framework)? ④ Are any regulatory requirements pertaining to the monitoring report system identified, such as the format and frequency of reports from the proponent to the regulatory authorities? ① Where necessary, pertinent items described in the Forestry Projects checklist should also be checked (e.g., projects including large areas of deforestation). ② Where necessary, pertinent items described in the Power Transmission and Distribution Lines checklist should also be checked (e.g., projects including installation of power transmission lines and/or electric distribution facilities). ① If necessary, the impacts to transboundary or global issues should be confirmed, if necessary (e.g., the project includes factors that may cause problems, such as transboundary waste treatment, acid rain, destruction of the ozone layer, or global warming). Confirmation of Environmental Considerations 1. 2, 3 Type and degree of impacts are to be identified in the EIA report. Measures to be taken to reduce or mitigate the impacts are also recommended in the EIA report. According to these studies, an Environmental Management Plan (EMP) is to be prepared. The EMP is to be utilized duly to ensure the implementation of these measures. 1. 2, 3 No. The EIA for the Project has not implemented yet. The monitoring program including its procedures and framework are to be proposed through the process of the EIA. 4. Although there are no regulatory requirement for the monitoring report system, the project proponent has a responsibility for reporting periodically to the relevant governmental agencies as well as public. It is recommended to examine this issue in more detail in the EIA. 1. The establishment of new road system will lead to the reduction of Greenhouse Gasses (GHGs) within the road system in and around the project site as a whole. 1) Regarding the term “Country’s Standards” mentioned in the above table, in the event that environmental standards in the country where the project is located diverge significantly from the World Bank Safeguard Policy as a general rule, or the International Finance Corporation Performance Standards for private sector limited or non-recourse project finance cases, or other standards established by other international financial institutions, or other internationally recognized standards or good practices established by developed countries such as Japan regarding environmental and social considerations, the background and rationale for this deviation, and the measures to rectify it if necessary, are to be confirmed. In cases where local environmental regulations are yet to be established in some areas, considerations should be based on comparisons with international standards such as the World Bank Safeguard Policy, and appropriate standards of other countries(including Japan). 2) Environmental checklist provides general environmental items to be checked. It may be necessary to add or delete an item taking into account the characteristics of the project and the particular circumstances of the country and locality in which it is located. 4-16 4.4 Overview of Regulations/Laws for Natural and Social Environments of Host Country 1. Laws and Regulation System In order to manage and avoid and/or minimize negative impacts on the natural and social environment with the implementation of various development projects as well as to promote the positive impacts, the Government of Vietnam has established the environmental related law system. The basic and principle environmental law, namely the Law on Environmental Protection (LEP), had been issued on December 1993. This law was amended to the new LEP on 2005. The LEP: a) Identifies the responsibilities of the state center, provinces, organizations and individuals to prevent and remedy environmental deterioration and pollution and carry out specified environmental protection functions; b) Provides for the development of environmental standards and submission of environmental impact assessment reports on new and existing facilities; c) Provides for responsible parties to pay compensation for environmental damage; d) Establishes the right of individuals and organizations to petition for enforcement of environmental regulations; e) Calls for civil and criminal penalties for violations; and f) Encourages international environmental co-operation. Based on the LEP, Environmental Impact Assessment (EIA) for major development projects including the Phuoc An Inter-Port Construction Project is compulsory at present in Vietnam. In order to implement the LEP, the Government has issued the Decree No. 175/CP on October 1994 in which guidelines on EIA are included. The LEP and the Decree No. 175/CP made EIA procedures compulsory to obtain approval for major development projects. After the enforcement of the LEP and the Decree No. 175/CP, several regulatory documents were issued by governmental agencies to support the implementation of EIA procedures. Major documents which regulate implementation of EIA and environmental protection including the LEP and the Decree No. 175/CP are summarized in the table below: Table 4-9 Major Laws and Regulations Concerning Environmental Protection in Vietnam NO. Law/Regulation Date 2 Law NO. 52, Order No. 29/2005/L-CTN (amended LEP from LEP of 1993) Decree No. 175/CP 3 Decree NO. 80/2006/ND-CP Aug. 2006 4 Decree NO. 21/2008/ND-CP 2008 5 Circular NO. TT-BTNMT 6 Decree NO. 81/2006/ND-CP 1 7 8 9 10 11 08/2006/ Circular NO. 490/1998/TT-BKHCNMT Circular NO. 05/2008/TT-BTNMT Decree NO. 16/2005/ND-CP Decree NO.197/2004/ ND-CP Circular NO. Nov. 2005 Oct. 1994 Sept. 2006 Aug. 2006 Apr. 1998 2008 Feb. 2005 Dec. 2004 Dec. 2004 Contents Vietnamese basic environmental protection law (New LEP, LEP 2005) Guidelines for the implementation of the LEP Particular stipulates and guidelines to carry out some article of LEP 2005 Revised Decree from Decree NO. 80/2006/ND-CP Guidelines to Strategic Environmental Assessment (SEA) and Environmental Impact Assessment (EIA) and Environmental Commitment Projection (ECP) On sanctioning of administrative violation in the domain of Environmental Protection Circular on appraisal of EIA report for investment projects Guidelines for the making and appraising EIA reports on Investment projects Regulation on Construction Investment projects Compensation, assistance and resettlement when the State revokes land Instructions to carry out the Decree NO. 197/2004/ ND-CP 4-17 NO. Law/Regulation Date 116/2004/TT-BTC 12 Circular NO. 13/2006/ TT-BTNMT Sept. 2006 13 Circular NO. 715/MTg Apr. 1995 14 Decision No.1806/QD-MTg Dec. 1994 15 Decision NO. 229/QD/TDC Mar. 1995 16 Decision QĐ-BXD 17 Sector standard 22/TCN-242-98 18 19 NO. 29/1999/ No. 21 No. 51/2001/QH10 No. 16/2003/QH11 Decree 109/2003/ND-CP Fisheries Law 22 Decree No.149/2004/ND-CP 20 24 1998 Nov. 2003 Nov. 2003 No. Circular NO. 12/2006/TT-BTNMT Decree NO. 12/2009/NĐ-CP 23 1999 Sept. 2003 Nov. 2003 Jul. 2004 2006 Dec. 2009 Contents of the government regarding to compensation, assistance and resettlement when the State revokes land Guidelines on the organization and function of SEA/EIA appraisal committee Guidelines for the making and appraising EIA reports on foreign investment projects Concerning the organization and activities of the EIA reports appraisal committee and the granting of environmental permits Concerning the issuance of the Vietnamese Environmental Quality Standards Regulation on environmental protection in construction sector Guidelines for EIA in the Feasibility Study and Design of Transport Construction projects which contain requirements for development of EIA for road infrastructure and inland waterways Land law (amended) Law on Construction Protection and sustainable development for wetlands Fisheries Law Agreement on digging, development, use of water resources, and wastewater discharge to water sources Circular on construction management Management of construction investment projects Besides the laws and regulations mentioned above, there are also several important regulatory documents relating to environmental considerations in the decision making process of transport projects. Among the laws and regulations, Vietnamese Standards for the Environment (TCVN) applied for the EIA for transport projects are shown below: ■ Ambient Air Quality Standard (TCVN 5937-1995), ■ Surface Water Quality Standard (TCVN 5942-1995), ■ Acoustic Standard (TCVN 5949-1998), ■ Industrial Effluent Standard (TCVN 5945-2005), ■ Permissible Nose Level for vehicles (TCVN 5948-1999), ■ Vibration and Shock Standards created by Construction and Industry (TCVN 6962-2001) Vietnamese Standards for the Environment were published by the former Ministry of Science, Technology and Environment (MOSTE) in 1995, 2000, 2001, and by MOSTE and MONRE in 2003 and 2005 applied to all socio-economic activities in territory of Vietnam. The environmental standards include acceptable limits of many air, water, and soil and noise parameters. Although the list of biophysical parameters is broad enough such that most monitoring programs can employ the standards as metrics of evaluation, it should be noted that there are some exceptions – for example, sediment and some other standards do not yet exist in Vietnam. In these cases, it is common practice for ODA projects to use standards from other countries or international organizations. 2. Land Acquisition 1) Laws and regulations 4-18 Land acquisition in the project area is one of the key issues for smooth implementation of the project. Although there are no residents, no commercial facilities and no factories in the project area of the component no.9 at present, lands in the area are owned by communes, local government, and a few private or state companies. Together with implementation of an EIA, land acquisition procedures in the project site should be started according to the competent laws and regulations. Following shows the laws and regulations which support the procedures of land acquisition. Table 4-10 Major Laws and Regulations Concerning Procedures of Land Acquisition NO. Law/Regulation Date 1 Decree No 197/2004/ND-CP Dec. 2004 2 No. 51/2001/QH10 Nov. 2003 3 Decree No 84/2007/ND-CP 2007 4 Decree No 69/2009/ND-CP Aug. 2009 5 Circular 14/2009/TT-BTNMT No Oct. 2009 6 Decision 13/2010/QD-UBND No 2010 Contents compensation, support and resettlement when government recover land Land law (amended) providing certificate of land use rights, land acquisition, implementation of land use rights, order and procedures for compensation, assistance and resettlement when government recover land and resolving claim on land supplement regulation on land using plan, land price, land acquisition, compensation, assistance and resettlement detail regulation of compensation, assistance, resettlement and order, procedures for land acquisition, land allocation, land lease issue regulation of some specific policies on compensation, assistance, resettlement when government recover lan in Ba Ria-Vung Tau province 4-19 2) Procedure of land acquisition Procedure of land acquisition is shown below: Figure 4-8 Procedure of land acquisition Unify the implementation of compensation work Establish compensation council, release land acqusition notification Hire measuring Consultants: Establish land acquisition border plan and list of owners Approval: - Land acquisition border plan (Natural Resource and Environment Department) - List of owners (Commune People’s Committee) Site inventory (Compensation Council) Provide legal land document (organization, and personal who had compensation land) Compensation and site clearance board make compensation option or hire Consultants Publicize the compensation option for comments, editing (if any) Project goes through more than 2 districts or foreign organization Project goes through 1 district and households Review compensation, site clearance options and preparing land acquisition documents as regulation (Natural Resource and Environment department) Review compensation, site clearance options and preparing land acquisition documents as regulation of Natural Resource and Environment department of district Decision of land acquisition (Provincial People’s Committee) Decision of land acquisition (Provincial People’s Committee) Approval Compensation, site clearance option (Provincial People’s Committee) Approval Compensation, site clearance option (Provincial People’s Committee) Publicize the decision to approve the compensation option Payment for compensation money (Investor, Compensation Council) Figure 4-3 Process and Procedures of Land Acquisition 4-20 4.5. Required Actions of Host Country and/or Relevant Groups for Implementation of the Project The Phuoc An Bridge Construction Project has only just started. As for the environmental aspects of the Project, the EIA, which is required for the commencement of the Project, has not yet carried out. In order to move forward the Project, the project proponent of Vietnamese side is required to conduct the following actions including the implementation of EIA in the field of the environmental aspects. ■ Implementation of the EIA for the Phuoc An Bridge Construction Project as soon as possible in accordance with the Vietnamese EIA laws and regulations. ■ The EIA includes below: - Implementation of detailed survey including: Forecast of noise level, concentrations of dust and atmospheric pollutants generated from vehicles along the project area during construction and in operation phases, Effects of the implementation of project on the fishery industry around the project area, Making of proposals of mitigation measures for the above and formation of monitoring and auditing plan for the above. ■ Formation of Environmental Management Plan (EMP) ■ Acquisition of the approval from MONRE for the above EIA. ■ Announcement of the implementation of the project to the public, discussion and formation of agreement with the concerned organizations on the project. ■ Acquisition of lands required for the project in accordance with the Vietnamese land acquisition laws and regulations 4-21 Chapter 5 Financial and Economic Feasibility 5.1 Conclusion of Cost Estimate and Construction Work Plan A total project cost is estimated based on information about capabilities and equipment of contractors, material and equipment costs, past experience records in Vietnam, the construction cost indice issued by Ministory of Transport. In calculating the construction cost, comparison is made for locations of the towers of the main bridge and for pile foundation types between Cast in place concrete piles and screwed steel piles, and the estimate was made based on the original tower location and Cast in place concrete pile. The construction cost increased to 21.2 billion yen from 12.2billion yen in BRITEC Report (VIII.2, Total Investment) but it is considered that those cannot be compared simply due to a rise in construction price indices caused by rapid growth in Vietnam, items not considered in the feasibility study, increases and decreases in quantities due to the more detailed design and fluctuation in foreign currency exchange rates (refer to Appendix5). Reasons for the cost increase are summarized in the table shown below. Item Cost increase i) Items not included in BRITIC Report ii) Escalation and Exchange Rate iii) Additional Costs (Temporary works, etc.) iv) Quantity increases from BRITEC Report Total 2.6 billion JPY 2.0 billion JPY 3.0 billion JPY 1.4 billion JPY 9.0 billion JPT (= 21.2 – 12.2 billion JPY) As for implementation schedule, a planned schedule mentioned in BRITECS Report IV. 10.10. 8 is 42 months. However, it was derived from interviews carried out locally that the schedule was assumed the project would be completed in 2015 and not based on the result of detailed study. Since no basis for the 42 month schedule had been made, the schedule was reviewed. Most optimized scheduling for implementation, and cost estimations for maintenance, management and others were carried out and the construction schedule was planned to be 41 months. 5.2 Estimate of Project Cost 5.2.1 Basic Conditions (1) Time of cost estimate The time of cost estimate is December 2010, when the study team came back to Japan. (2) Exchange Rate (End of November 2010) 1 JPY=233 VND 1US$=19,598VND 1US$=84.2700JPY 5-1 5.2.2 Estimated Items The project costs are estimated in the categories of construction expense (construction costs, consulting service costs and contingencies), land compensation costs, project administration costs and taxes (Value Added Tax and Import Tariff). 5.2.3 Calculation of Construction Expense Construction costs (bridge and road construction), consulting service costs (detailed design, construction supervision, etc.) and contingencies are considered. (1) Construction costs The quantities for the following major work items are calculated and the construction costs are estimated by multiplying unit rates established taking into consideration to past experience of bridge and road construction in the area. Preparation, Temporary Work: Engineer’s Office, Soil Investigation, Test Piles, Temporary Yard, Girder Fabrication Yard, Concrete Plant, Material and Equipment Stockyard, Temporary Jetties, etc. Superstructure Work: Girder erection, Girder fabrication, Stay cable erection, Surface work (Handrail, Pavement etc.) Tower (Pylon): Construction of Towers Stay Cable Work: Erection of stay cable for Stay Cable Bridge, Tensioning of stay cable Substructure Work: Foundation pile, Pier, Abutment, etc. Earthwork: Approach road section, Interchange section (Embankment work, Pavement work, Drainage work, Retaining wall work, Slope protection work, etc.) (2) Consulting Service Cost Consulting service for this project generally consists of Pre-feasibility study, basic design, detailed design, bidding preparation work and construction supervision service. Bridge design (superstructure, substructure and foundation), road design, facility design and cost estimate will be carried out during the design phase, and a design report, drawings, project cost estimation data, bidding documents will be produced during the detailed design. After the detailed design, the Consulting Engineer will carry out preparation for bidding, prequalification of bidders, technical evaluation and price evaluation and offer technical support until the contractor is selected. Once construction is started, the Consulting Engineer will check work schedules, temporary work plans and construction work plans submitted by the contractor, approve of materials and give guidance on safety management as construction supervision service. Construction supervision service organization will consist of an onsite supervising consulting engineer who will manage the whole service, specialists who have knowledge and experience on design and construction of bridges and roads, and assistant for the said specialists, and moreover, civil engineers, administrative staff and 5-2 drivers hired locally. Ten (10) % of Construction costs for the above mentioned services are considered as Consultant service cost. (3) Contingencies Ten (10) % of the sum of the construction costs and the consultant service costs is considered as contingencies. A Preliminary construction expense is shown in Table 5-1. Table 5-1 Preliminary Construction Expense Item JPY(Mill.) VND(Mill.) Equivalent JPY(Mill.) 233 Equivalent VND(Mill.) 233 161 458,522 2,129 496,004 5,963 1,127,364 10,801 2,516,696 5,533 437,599 7,411 1,726,693 117 20,945 207 48,121 87 45,905 284 66,105 General Item L=2,478.5m Approach Bridge W=23.5m Main Bridge L=746m Accessories Approach Road Interchange L=3,260m Km18+100 to Km18+378.97 1 Lot Construction Cost 61 80,243 405 94,432 11,920 2,170,577 21,236 4,948,051 Consultant Fee 10% 1,192 217,058 2,124 494,805 Contingency 10% 1,192 217,058 2,124 494,805 14,305 2,604,693 25,484 5,937,661 Total 5.2.4 Calculation of Project Cost (1) Land compensation costs It is the compensation cost of the land acquired for construction of bridge and road and the amount is considered by the local implementation agency. However, it is an outstanding item for future investigation since the data are not obtained at this moment. (2) Project administration cost The costs are for the local implementation agency to operate and manage the project and 5% of the construction expense is considered. (3) Tax and others Value added tax in Vietnam is 10% for the most of taxable items in relation to construction and 10% of material and equipment costs are considered. Import tariff on construction materials varies on items according to “Export-Import Tariff and Value Added Tax on Imports”, HCM General Publisher, the latest issued June 2010. In detail, different rates shall be applied to different materials but import tariff rate of 10% is applied uniformly at this moment since it ranges from 0% to 20% and accordingly a 10% of the total amount roughly calculated for imported materials is considered. 5-3 A preliminary total project cost is shown in Table 5-2. The preliminary total project cost is estimated approximately 29.6 billion yen (6 trillion 886.0 billion Vietnam Dong) Table 5-2 Preliminary Total Project Cost Item JPY(Mill.) General Item VND(Mill.) Equivalent JPY(Mill.) Equivalent VND(Mill.) 233 233 161 458,522 2,129 496,004 Approach Bridge L=2,478.5mW=23.5m 5,962 1,127,364 10,800 2,516,510 Main Bridge L=746m 5,533 437,599 7,411 1,726,693 Accessories L=3,260m 117 20,945 207 48,121 Km18+100 to Approach Road Km18+378.97 L≒280m 87 45,905 284 66,105 Interchange 61 80,243 405 94,432 11,920 2,170,577 21,236 4,948,051 1 Lot Construction Cost Consultant Fee 10% 1,192 217,058 2,124 494,805 Contingency 10% 1,192 217,058 2,124 494,805 14,305 2,604,693 25,484 5,937,661 - - - - Sub Total Land Acquisition Administration Cost 5% - 296,883 1,274 296,883 Value Added Tax (VAT) 10% - 593,766 2,548 593,766 Import Tax 10% - 57,963 249 57,963 Sub Total Total - 948,613 4,071 948,613 14,305 3,553,306 29,555 6,886,273 Value Added Tax is considered to be exempted for projects funded by Japanese Yen Loan in the country. However, in this report, Value Added Tax is considered in the Total Project. 5.2.5 Calculation of Ratio of material, equipment and others of Japan origin This Project is intended to be implemented under STEP scheme of Japanese ODA. The STEP loan provides favorable conditions for a borrower such as a low refund interest with a long repayment term. In order to have the condition, the Project shall satisfy that; “More that 30% of the loan amount shall be used for procurement of Japanese origin products and services.” The details are described in “Change in specific applicable conditions Special Terms for Economic Policies” issued 20 October 2006, Ministry of Foreign Affairs, Ministry of Finance and Ministry of Economy, Trade and Industry. With respect to the condition, the project costs are calculated in accordance with the above document. As a result, the Project satisfies this 30% condition. The calculation result is shown in Figure 8-6. 5-4 5.2.6 Maintenance Cost An annual maintenance cost necessary for the section covered by this project is calculated anticipating the following activities. (1) Maintenance and management items (a) Ordinary Inspection Checking, investigation, cleaning, and replacing road lighting, light repair of pavement, etc. (b) Scheduled Inspection Improvement of pavement, repair and improvement of road lighting and accessories, repair of expansion joint, painting steel members such as handrails, improvement of drainage and slope protection, etc. (2) Annual maintenance cost An annual maintenance cost is shown in Table 5-3. The routine repair costs converted to the annual costs by dividing by year of interval of repairs. A life cycle cost is shown in the table with conditions that the design life length of the bridge and roads is 100 years. Table 5-3 Annual Maintenance Cost Portion Bridge Road Total/Year Total/Life(100 Year) Cost (Mill. VND)/Year Ordinary Scheduled Inspection Inspection 637 2,546 42 313 678 2,859 67,824 285,902 Total Remarks 3,183 355 3,537 JPY 16,000,000.00 353,726 JPY 1,600,000,000.00 5.2.7 Comparison of construction costs (1) Comparison of Locations of Main Bridge Towers A comparison of construction costs between the case two Towers of Main Bridge are constructed in river (Original plan) and the case one Tower of Main Bridge is constructed on land by shifting the location of the bridge by 40m (Alternative Plan 1) is shown in Table 5-4. In terms of construction cost, Alternative Plan 1 has an advantage but the detail will be decided during Basic Design. The plan is based on the original one in this report. 5-5 Table 5-4 Comparison of Locations of Main Bridge Towers Item General Item Approach Bridge Main Bridge Accessories L=2,478.5 m L=746m L=3,260m Km18+100 to Approach Road Km18+378.9 7 Interchange 1 Lot Total Both Towers in River One Tower on Land Difference Equivalent Equivalent Equivalent VND(Mill. VND(Mill. JPY(Mill.) JPY(Mill.) JPY(Mill.) JPY(Mill.) JPY(Mill.) ) ) 233 233 161 458,522 2,129 161 458,522 2,129 5,963 1,127,364 10,801 5,963 1,127,364 10,801 - 5,533 117 437,599 20,945 7,411 207 5,131 117 430,600 20,945 6,979 207 432 - 87 45,905 284 87 45,905 284 - 61 11,920 80,243 2,170,577 405 21,236 61 11,519 80,243 2,163,579 405 20,804 432 (2) Comparison of foundation piles Piles are planned for all bridge foundation. Construction of foundation is carried out simultaneously for Main Bridge and Approach bridges on both shore sides. Cast in place concrete piles are planned for Main Bridge. As for piles of Approach Bridges, negative friction on pile will appear since embankment is constructed on soft ground. Therefore, the construction costs for Cast in Place Concrete Pile (Original Plan) and Steel Pipe Pile (Alternative Plan 1) are compared. The result is shown in Table 5-5. In terms of construction cost, Cast in Place Concrete (Original Plan) has an advantage. Therefore, Cast in Place Concrete Pile is considered in this report. Table 5-5 Comparison of Foundation Pile General Item Approach Bridge L=2,478.5m Main Bridge L=746m Accessories L=3,260m Km18+100 to Approach Road Km18+378.97 L≒280m Interchange 1 Lot Total Concrete Bored Pile Steel Pipe Pile Difference Equivalent Equivalent Equivalent JPY(Mill.) VND(Mill.) JPY(Mill.) JPY(Mill.) VND(Mill.) JPY(Mill.) JPY(Mill.) 233 233 161 458,522 2,129 174 457,934 2,139 -10 5,963 1,127,364 10,801 9,287 806,790 12,750 -1,949 5,533 437,599 7,411 5,629 424,742 7,452 -42 117 20,945 207 117 20,945 207 87 45,905 284 87 45,905 284 - 61 11,920 80,243 2,170,577 405 21,236 61 15,355 80,243 1,836,559 405 23,237 -2,001 5-6 5.3 Overview of Preliminary Economic/Financial Analysis 5.3.1 Economic Analysis (1) Method of analysis and evaluation In order to evaluate the effectiveness of this project from the viewpoint of the national economy, a comparative analysis of economic cost and benefit both in the case of executing the project (With the project) and not executing the project (Without the project) is carried out. As the evaluation index, Economic Internal Rate of Return (EIRR), Benefit Cost Ratio (B/C) and Net Present Value (NPV) are applied. (2) Premise 1) Benefit items to be analyzed As various long term benefits created in the regional society due to the execution of the project, time saving benefit and vehicle operating cost saving benefit will be the object of analysis. Vehicle operating cost saving benefit Vehicle operating cost will be saving by the introduction of Phuoc An Bridge. In order to measure it, the total vehicle operating cost by with the project and without the project is calculated and compares two costs. Time saving benefit Saved time for the same passenger for the same origin and destination (OD) by the introduction of the project will be converted into economic value. In order to measure it, the total passenger hour by with project and without project is calculated and is converted into economic value with time saving cost. 2) Cost item to be analyzed O&M cost is 16 million yen per year. 3) Period for analysis Total 35 years including 4 years construction period from 2015 to 2018 and from 2019, the year of starting operation, until 2049, when 35 years will have passed from inauguration. 4) Social discount rate As the opportunity cost of capital, 15% per annum is assumed as the social discount rate. 5) Exchanging rate (at 2010Nov.) 1JPY = 233VND 1US$ = 19,598VND 1US$ = 84.27JPY 5-7 (3) Benefit of the project The benefit of the project to introduce a bridge is as follows: 1) Effective transport of container from/to CMTV Port 2) Time saving for passengers between HCMC and Vung Tau The parameters for measurement of the benefit are shown in blow. Time value is analyzed by stated preference survey (SP) for the F/S of Expressway from Dau Giay – Phan Thiet near HCMC followed VITRANSS2. Vehicle operating cost for measuring parameters is given by speed and type of vehicle. Table5-7 shows vehicle operating cost by type of road and its typical speed. Table 5-6 Time saving cost (USD/hour) 2009 2010 2020 2030 Car 3.36 3.50 4.63 7.08 Bus 2.02 2.11 2.32 3.54 Truck(owner) 2.76 2.88 3.81 5.82 Source: WTP survey conducted in July 2009. Table 5-7 (USD/1000km/Veh) Vehicle operating cost Car Bus Truck Expressway (80km/h) 80 393 333 NH (40km/h) 85 338 359 NH (30km/h) 99 396 425 Source: VITRANSS 2 The following figures are shown the traffic volume in project area by with the project and without the project and the difference between two. The figure of the difference is displayed the increase with red and the decrease with blue, the link with the project is red and the path to the destination is traced by blue links in case of without the project. 5-8 Figure 5-1 Traffic Volume (With Case) in 2020 LEGEND : ( Mode: + 1 + 2 + 3 ) Traffic Flow VCR<1.00 VCR<1.20 VCR<1.50 1.50<VCR scale: 1mm =20000(pcu) Figure 5-2 Traffic Volume (Without Case) in 2020 LEGEND : ( Mode: + 1 + 2 + 3 ) Traffic Flow VCR<1.00 VCR<1.20 VCR<1.50 1.50<VCR scale: 1mm =20000(pcu) Figure 5-3 Traffic Volume (With Case)-(Without Case) in 2020 5-9 (4) Project cost 1) Investment cost All the prices applied are economic prices as of the year 2009. As it is difficult to estimate the cost inflation during the 35 years of the analysis period, it will be omitted from the items for analysis. As to the depreciation of assets after the life time, the initial investment amount will be re-appropriated at the following year. Non-depreciated portion of depreciated assets to be found at the last year of the project will be appropriated as a negative investment cost by calculating its residual value. (5) Cost benefit analysis 1) Results of analysis The results of the analysis based on the assumed benefits and costs are shown in Table 5-9. As all the index values for the evaluation are at a good level, this project is considered to be economically feasible. Table 5-8 Results of cost benefit analysis (Discount Rate=15%) B/C Ratio N.P.V EIRR 1.83 185.40 million US$ 27.5 % 5-10 Table 5-9 Cost and Benefit (Unit: million $US) Cost 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 Amount 0.00 59.62 149.05 89.43 0.00 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 303.42 Benefit Time Saving VOC 93.78 93.78 86.72 79.66 72.60 65.53 58.47 51.41 44.34 37.28 30.22 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 23.15 1,176.89 74.46 74.46 67.67 60.88 54.09 47.31 40.52 33.73 26.94 20.16 13.37 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 6.58 645.23 Total 168.24 168.24 154.39 140.54 126.69 112.84 98.99 85.14 71.29 57.44 43.59 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 29.74 1,822.12 Discounted Cost Benefit 51.84 112.70 58.80 0.00 0.09 0.07 0.06 0.06 0.05 0.04 0.04 0.03 0.03 0.02 0.02 0.02 0.02 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 223.99 0.00 0.00 0.00 0.00 83.65 72.74 58.04 45.94 36.01 27.89 21.28 15.91 11.59 8.12 5.36 3.18 2.76 2.40 2.09 1.82 1.58 1.37 1.19 1.04 0.90 0.79 0.68 0.59 0.52 0.45 0.39 0.34 0.30 0.26 0.22 409.39 2) Sensitivity analysis In the elements assumed for the economic analysis, variable factors are included in each element and some elements are based on simple assumptions. As a sensitivity analysis, some margin will be given in accordance with such variable factors and by finding out how the result of the analysis will vary; the stability of the feasibility of this project will be confirmed. 5-11 Table 5-10 Result of Sensitivity Analysis Cost Benefit -20% -10% 0% 10% 20% 20% 38.0% 34.8% 32.0% 29.6% 27.5% 10% 35.6% 32.5% 29.8% 27.5% 25.5% 0% 33.1% 30.1% 27.5% 25.3% 23.3% -10% 30.4% 27.5% 25.1% 22.9% 21.1% -20% 27.5% 24.8% 22.5% 20.5% 18.7% From the results of analysis shown in the above table, the value of EIRR exceeds 15% even in the case of 20% cost increase or 20% benefit decrease so the possibility of realization of this project is high. 5.3.2 Financial Analysis (1) Method of analysis The objective of the financial analysis is to evaluate to what extent this project is profitable and whether sound operation as a public entity is possible or not. As the index for project evaluation, Financial Internal Rate of Return (FIRR) is calculated. FIRR is a discount rate with which the total of investment amount, expenditure and income all converted into net present value becomes zero and is calculated by the following formula. ∑t=0 (Bt – Ct –It) (1 + FIRR)t = 0 Where n : Period of analysis (First year t=0) Bt : Income in each year Ct : Expenditure in each year It : Investment cost in each year (2) Premises 1) Period of analysis A total of 35 years is assumed as the period of analysis including construction period from 2015 to 2018, starting year of operation in 2019 to the year 2049, after 35 years of operation. 2) Inflation As it is difficult to estimate the inflation for the period of 35 years (Period of analysis), it is not considered in this analysis. 5-12 3) Investment cost The cost of domestic materials is the market price including taxes and the cost of imported materials and equipment. The price is the CIF price plus inland transportation cost and other expenses excluding import taxes. All the prices are as of the year 2009. 4) Depreciation As to the assets of which life time occurs during the project life, re-investment of the same amount will considered to be done. Non-depreciated portion of the depreciated assets to be found in the last year of the project will be appropriated as negative investment cost by calculating its residual value. 5) Finance source plan Using the special Yen credit, STEP from Japan Government is considered in principle. Eighty five percent (85%) of the total project cost comes from STEP loan and the remaining fifteen percent (15%) is financed by the local government. The conditions of the STEP loan are as follows; Table 5-11 STEP loan condition Item Remarks Interest rate 0.75%/year Payment period 35 years (including grace period of 10 years) Maximum loan amount 85% of total project cost 6) Exchange rate (2010Nov.) 1JPY = 233VND 1US$ = 19,598VND 1US$ = 84.27JPY Investment cost This Project is intended to be implemented under STEP scheme of Japanese ODA. The STEP loan provides favorable conditions for a borrower such as a low refund interest with a long repayment term. In order to have the condition, the Project shall satisfy that; (3) The total project cost is the construction cost calculated in Chapter 5.1 plus interest during construction. (4) Revenue and expenditure 1) Revenue Toll revenue will be considered. One (1) $US/PCU in 2020 as VITRANSS2 is used and it’s 2 times and 3 times toll will be considered also. 5-13 Table 5-12 Revenue by Year Year Toll Revenue (mil$US/year) 2020 1 $US/PCU 13.11 1 $US/PCU 13.66 2 $US/PCU 26.01 3 $US/PCU 39.01 2030 2) Expenditure O&M cost is 17 million yen per year. (5) Result of financial analysis 1) Financial Internal Rate of Return For the evaluation of financial viability of this project, the value considering WACC (Weighted Average Cost of Capital) as shown hereunder is applied. STEP Special Yen Credit Vietnam’s own fund 85% X 0.75 15% X 15 + = 2.89% As the value of FIRR of this project is 3.37%, toll level will become 2 times at in 2030, which exceeds the standard value of 2.89% calculated by the above formula, it is considered to be financially viable. The analysis is shown in Table 5-13 5-14 Table 5-13 Expense 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 Amount 0.00 70.14 175.35 105.21 0.00 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 -227.77 128.63 Dept STEP 59.62 208.67 298.10 298.10 298.10 298.10 298.10 298.10 298.10 298.10 298.10 285.68 273.26 260.84 248.42 236.00 223.58 211.16 198.74 186.32 173.90 161.48 149.06 136.64 124.22 111.80 99.38 86.96 74.54 62.12 49.70 37.28 24.86 12.44 0.02 Local 10.52 35.28 49.51 47.96 46.41 44.87 43.32 41.77 40.22 38.67 37.13 35.58 34.03 32.48 30.93 29.39 27.84 26.29 24.74 23.19 21.65 20.10 18.55 17.00 15.45 13.91 12.36 10.81 9.26 7.71 6.17 4.62 3.07 1.52 -0.03 Financial analysis Interest STEP Local 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.24 2.14 2.05 1.96 1.86 1.77 1.68 1.58 1.49 1.40 1.30 1.21 1.12 1.02 0.93 0.84 0.75 0.65 0.56 0.47 0.37 0.28 0.19 0.09 0.00 27.95 1.58 5.29 7.43 7.19 6.96 6.73 6.50 6.27 6.03 5.80 5.57 5.34 5.10 4.87 4.64 4.41 4.18 3.94 3.71 3.48 3.25 3.01 2.78 2.55 2.32 2.09 1.85 1.62 1.39 1.16 0.92 0.69 0.46 0.23 -0.00 129.34 Dept-repay STEP Local 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.66 14.56 14.47 14.38 14.28 14.19 14.10 14.00 13.91 13.82 13.72 13.63 13.54 13.44 13.35 13.26 13.17 13.07 12.98 12.89 12.79 12.70 12.61 12.51 12.42 338.45 3.13 6.84 8.97 8.74 8.51 8.28 8.05 7.81 7.58 7.35 7.12 6.88 6.65 6.42 6.19 5.96 5.72 5.49 5.26 5.03 4.79 4.56 4.33 4.10 3.87 3.63 3.40 3.17 2.94 2.71 2.47 2.24 2.01 1.78 1.54 183.52 Revenue 13.11 13.11 14.40 15.69 16.98 18.27 19.56 20.85 22.14 23.43 24.72 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 26.01 722.44 2) Sensitivity analysis In the elements assumed for this analysis (Investment cost and revenue), unknown factors are included. Some margin will be added to each element corresponding to each unknown factor, the variation of the result of the analysis is observed and the financial stability of this project will be verified. 5-15 Table 5-14 Result of sensitivity analysis Construction cost Revenue -20% -10% 0% 10% 20% 20% 6.02% 5.22% 4.52% 3.91% 3.37% 10% 5.42% 4.64% 3.96% 3.37% 2.84% 0% 4.79% 4.03% 3.37% 2.79% 2.28% -10% 4.11% 3.37% 2.73% 2.17% 1.66% -20% 3.37% 2.66% 2.04% 1.49% 1.00% From the above table, it is found that the value of FIRR does not satisfy the standard value by WACC in case of 10% cost increase and 10% revenue decrease. Accordingly, the project shall be executed based on the proper construction plan and operation plan. 5.3.3 Conclusion By the analysis so far carried out, the internal rate of return of this project was found as EIRR =27.5% and FIRR=3.37% both of which are considered as feasible. EIRR was found by focusing on the time saving effect and the operating cost saving effect as benefit. Actually, various other extensive benefits are expected in aspects pertaining the environment and society such as the reduction of noise and exhaust gas due to the reduction of NH-51 and the decrease of traffic accidents. For the value of FIRR to slightly exceed the standard value of WACC, the application of low interest and long term finance such as STEP special Yen credit is an essential condition. 5-16 Chapter 6 Implementation Schedule of the Project 6.1 Calculations of Total Project Schedule It is assumed that this project will be implemented by ODA of Japan. Firstly, meeting and negotiation between GOV (Government of Vietnam) and GOJ (Government of Japan) will be carried out. The total project schedule includes the GOV-GOJ negotiation, the design phase and the construction phase. A planned total project schedule is shown in Table 6-1. Construction starts from preparation work such as construction of temporary yard, mobilization of equipment and materials, soil investigation and construction of site offices, followed by construction of Main Bridge and Approach Bridges simultaneously and subsequently construction of the approach roads and interchange, surface work, pavement work, and demobilization will be carried out. 6.1.1 Procedures until Deign Phase Based on the past experience, a tentative schedule for the procedures and the required periods until the design phase start is prepared (refer to Figure 6-2). Activities are making this report, a request from Vietnamese government to JICA, concurrence by JICA, Loan Agreement, signing on Exchange of Notes, etc. 6.1.2 Design Phase and Bidding Preparation Contents of design work vary depending on the scope of work and implementation/non-implementation of SAPROF. In this study, the design phase is assumed to include F/S review, Basic Design (B/D) and Detailed Design (D/D). It is assumed that the commencement of the design phase will be in November 2013. After the approval of the Detailed Design, preparation for bidding (making bidding documents, etc.), prequalification of contractors, bidding and evaluation are followed. A contract is made between the awarded contractor and local implementation agency. It is assumed that the commencement of the construction will be in October 2015. 6.1.3 Construction Work The total section length of this project is 3.26km including the main bridge, the approach bridges on both sides, the earth work and the interchange at the end of the Project. Construction of the bridges is on the critical path. The planned bridge has 3 sections, Prestressed Concrete Cable Stayed Bridge and Prestressed Precast Concrete Girder Bridges. It is expected to take about 41 months assuming carrying out construction of all bridges simultaneously resulting the completion date is at the end of February 2019. Tentative construction schedule is shown in Table 6-3. 6-1 6-2 6-3 6-4 6.2 Outline of Construction Work Plan 6.2.1 General Item Engineer’s offices, environmental monitoring, soil investigation, test piles and others are included. Phase 2 is the target in this study and embankment in Vung Tau side is supposed to be completed in Phase 1. However, embankment of permanent roads and temporary roads is considered in this study for a safer side. Temporary work includes working platforms for construction of Approach Bridge substructure, temporary access roads, unloading jetties, facilities necessary for this project (Concrete Plant, Fabrication Yard for Prestressed Concrete, Rebar and form fabrication yard, Material and Equipment stock yard, Mechanical shop and Site Office). Those temporary work and facilities will be established on both shore sides of the main bridge. Arrangement of the temporary yard (200m x 400m) is shown in Drawings 6-1. Additional 3m high embankment on the top of the embankment of which required height is 3m is considered according to construction experience around the area. A similar plan is considered for Dong Nai side as well. Figure 6-1 Temporary Yard 6.2.2 Construction of Approach Bridge Substructure The bridge is divided into Vung Tau side and Dong Nai side by Thi Vai River. Therefore, construction of Approach Bridges is planned separately for the left shore and the right shore. Cast in Place Concrete Pile Foundation is planned for all bridge foundation. Foundation of Main Bridge and Approach Bridges on both sides of river will be constructed simultaneously. Piles of Approach Bridges are constructed on land as normal but Reverse Circulation Drilling Method is planned taking into consideration the pile length of 60m and soft soil ground. Three (3) sets of 6-5 drilling machines are considered for each side. Temporary shoring with sheet pile is installed for construction of pile caps taking into consideration soft soils and ground water. Climbing forms are planned for construction of piers in consideration for height of 50m. Beams on piers will be constructed supported by steel brackets. 6.2.3 Erection of Approach Bridge Superstructure Since the precast girder will be installed on land, either launching girder method or crane method is feasible. However, the launching girder method is planned taking into consideration that the locations for the girders to be installed are 50m high from the ground as well as soft soil conditions. The precast girders will be fabricated in the precast yard, hauled to the locations by trailer and installed to the positions using launching girder. After that the precast concrete forms will be set on the girders and the deck slabs will be constructed. 6.2.4 Construction of Substructure and Tower of Main Bridge Piles Foundations for Main Bridge Towers in the sea will be constructed from temporary jetties constructed on the sea or barges. Reverse Circulation Drilling Method is planned for construction of piles taking into consideration the pile length of about 90m. However, Rotary Casing Drilling Method may be considered depending on the result of soil investigation in the future. One (1) set of drilling machine will be used taking into consideration transferring it from one foundation to another. Precast concrete forms will be used for construction of pile caps of Tower on the sea. Precast concrete form will be installed utilizing the piles. After that, installation of rebar and concrete are repeated taking into consideration concrete supply capacity and construction of pile cap will be completed in several lifts. Tower legs are constructed using climbing form up to the lower cross beam and the lower cross beam will be constructed with bracket supports. Subsequently up to the cross beam the tower will be constructed using climbing form. Construction of Stay Cable Anchorage part is planned to use ordinal scaffolding for convenience of tensioning work of stay cable. 6.2.5 Construction of Superstructure Main Bridge (Stayed Cable Bridge) Since the bridge is on the sea, construction is planned by cast in situ concrete cantilever construction using form travelers. At first, Pier Tables are constructed in order to install form travelers. Then, the tower and the girder will be temporary fixed and erection of stay cable and construction of girders will be carried out in turn. After closure of side spans are carried out, the center span will be closed. Two (2) pairs, that is, four (4) sets of form travelers will be used for construction. 6-6 Chapter 7 Ability of Implementation Authorities in Vietnam 7.1 Outline of Implementation Authorities This Project is currently planned and studied by the Department of Transportation belonging to Ba Ria – Vun Tau Provincial People’s Committee (hereinafter referred to as “BVPPC”). At the implementation stage, however, this kind of project is generally managed directly by the Ministry of Transportation of Vietnam (hereinafter referred to as “MOT”). Several cable-stayed bridges were already constructed or are under construction in Vietnam. Therefore, the required technology has been gradually accumulated to some extent. All the cable-stayed bridges except Rach Mieu Bridge, are constructed by financial and technical assistance of foreign countries, namely Japan and Australia. Rach Mieu Bridge, which spans over one of Mekong Rivers at the south of Ho Chi Minh City, was designed and constructed by Vietnamese companies. Figure 7-1 shows the organization chart of BVPPC. A provincial people’s committee manages a province as the municipal government. The organization is similar to that of the central government. Figure 7-1 Organization Chart of BVPPC Ba Ria・Vung Tau People’s Committee (BVPPC) Chairman:Mr. Tran Minh Sanh District People’s Committee Departments, Boards and Other related Departments (-> For more detail, refer to Figure 7-2) Offices and Branches belong to Government Associations and Unions Project Management Unit Figure 7-2 shows departments and boards of BVPPC. The Department of Transportation (DOT) is the counterpart of this study. Approximately 50 members are working in the DOT. 7-1 Figure 7-2 Departments and Boards of BVPPC Departments, Boards and Other Related Departments Department of Home-Affairs Department of Private Law Department of Investment and Planning Department of Finance Department of Industry and Trade Department of Agriculture and Rural Development Department of Transportation (Director; Mr. Vu Ngoc Thao) Vice Director Administrative and Accounting Office Planning Office Traffic Management Office Vice Director Driver’s License Office Quality Assurance of Traffic Works Office Project Management Units Driving School Provincial Inspector Vehicle Quality Inspection Office Traffic Violation Handling Office Traffic Safety Office Department of Construction Department of Natural Resources and Environment Department of Labor and Social Affairs Department of Culture, Sports and Tourism Department of Science and Technology Department of Education and Training Department of Health Department of Foreign Affairs 7-2 7.2 Project Implementation Organization In general, this kind of bridge project is actually implemented and managed by a Project Management Unit (hereinafter referred to as “PMU”) appointed by the MOT as shown in Figure 7-3. Figure 7-3 Schematic Organization Chart for Project Implementation Ministry of Project Transportation Management Unit (MOT) (PMU) Consultants Contractors When the project scale is large, a PMU directly belonging to the MOT is appointed. For example, Nhat Tan Bridge in Hanoi is currently implemented by PMU85, and Can Tho Bridge over the Mekong River was implemented by PMU My Thuan. However, Binh Bridge in Hai Phong was implemented by the PMU belonging to Hai Phong City. The PMU will be selected by the MOT based on the ability and experience in addition to various situations in Vietnam. 7.3 Ability Evaluation and Necessary Countermeasures Phuoc An Bridge is a long-span bridge which requires a large amount of costs, the state-of-the-art technology and good workmanship to construct a quality structure. In addition, BVPPC have insufficient experience for managing a large-scale bridge construction such as Puhoc An Bridge because the bridge will be the first cable-stayed bridge in the province. Therefore, not only financial assistance but also technical assistance from Japan must be needed when the Project is implemented by ODA of Japan. Especially, when the PMU belonging to Department of Transportation of BVPPC is selected for the implementation, it is preferable that a Japanese consultant is involved from the planning stage. 7-3 Chapter 8 Superiority of Japanese Firms in Technology 8.1 International Competitiveness and Possibility for order in take for Japanese Firm 8.1.1 Project Features This project is located in low-lying area covered with mangrove forest along Thi Vai river. In accordance with this project, this area is expected to be a industrial area with heavy traffic which come-and-go to ports under construction. A concrete cable-stayed bridge was selected as a main bridge for crossing over Thi Vai River after comparison study with respect to economic efficiency, maintenability, feasibility, etc. The center span for the cable stayed bridge is 360m, which is longer than domestic experiences of 260m. In order to accomplish the economical design and planning of safe construction, it is required to study about structure of anchorages for stay cables, wind-resistant stability during construction and operation phases, foundation on very soft soil supporting heavy structure, etc, by experienced and highly-developed Japanese engineers. The bridge foundation type for cable stayed bridge is planed with bored piles (cast-in-place pile). Although the type thereof is commonly used in Vietnam, there is some difficulty for design and construction by Vietnamese engineer in terms of the length (depth) required for the bridge, in-water construction at deep riverbed, etc. As for the construction of cable stayed bridge, all the elements such as bridge deck, pylon and stay cable affect irritably one another for controlling of camber, deformation and displacement, and high accuracy is necessitated. Therefore, skilled and experienced Japanese supervisors are required. According to the approach bridges, of which length is nearly 2.5km, all the structures can be on-land construction. The superstructure and foundation type for the bridges is Super-Tee girder-bridge and bored piles respectively. Those are selected after consideration of economic-spans, facility of construction and procurement. In terms of a number of substructures for approach bridges and short construction period, construction of substructure and its foundation should be implemented with quite large number of teams at the same time. Therefore, it will be a key point for a selection of contractor, who has enough management ability for quality, safety, schedule and procurement. 8.1.2 International Competitiveness and Possibility for order in take for Japanese Firm As stated foregoing, design and construction of a cable stayed bridge of which center span is 360m requires not only sophisticated knowledge but also high-developed equipment and materials. Although the chances to design and construction of such huge scale of concrete cable stayed bridge has not arisen in Japan, we have vast of overseas experiences and lead this firm to the world. Moreover, the Japanese technologies and experiences for tunnel tests and wind-resistant stability design are also leading edge firm in the world. Additionally, some other Japanese technology, of which applicability will be studied later, such as Vacuum Consolidation Method (VCM) for soft ground improvement, Screwed Steel Pile foundation and Structural Health Monitoring System (SHMS) are also quite unique and competitive technologies. 8-1 Based on above, it is determined that Japanese firm has enough competitive power and a feasibility of participation to this project. Table 8-1 Major Achievement for Concrete Cable Stayed Bridges Bridge Name Center Span Year of Completion Location (Japan) Bridge Name Center Span Year of Completion Location (International) Yabegawa Grand Br. 261 2008 Fukuoka Pref. Can Tho Br. 550 2010 Viet Nam Ikara Br. 260 1996 Tokachi Br. 251 1995 Yobik Br. 250 Ikina Br. 350 Kagoshima Pref. Hokkaido Pref. Bai TraiBr 435 2006 Viet Nam BangkockRing Road 398 2006 Thailand 1989 Saga Pref. Kien Br. 200 2003 VietNam (2011) Ehime Pref. Neak Loeung Br. 330 (2015) Cambodia (1) Japanese Technology (a) Concrete Cable Stayed Bridge 1) History of Concrete Cable Stayed Bridge The Japanese history for cable stayed bridge has started with Shimada Bridge, of which center span is 39.7m, completed in 1963. Since then a center span has been widened in parallel with social demands, and currently the longest center span is reached to 261m according to Yabegawa Bridge completed in 2008. As for the overseas experience, the longest center span reaches 435m in Bai Trai bridge (Vietnam, 2006), which was supervised and constructed by Japanese company. 2) Advantages of Concrete Cable Stayed Bridge – Preferable for long span bridge in terms of structural and economical view points. – Applicability of cantilever construction, which has less limitation to maintenance of navigation clearance during construction period. 3) Advantage of Japanese Technology The technology for cable stayed bridge is one of the world-leading technologies of Japan. – According to the experiences of 124 cable-stayed bridges constructed in Japan, we have plenty of knowledge for technologies and high-developed construction equipment and materials. – Japan has specialized standards for design and construction of cable stayed bridge pioneering the world. 8-2 Figure 8-1 Yabegawa Grand Bridge* (Japan, 2008) (b)Wind Tunnel Test i) Overview The wind tunnel test is a test for verification of wind-resistant stability of overall bridge. This test, which has been developed in parallel with the development of suspension bridges and cable-stayed bridges, shall generally be carried out to a bridge which have a susceptibility to wind. ii) Actual Achievements – There’s abundance of wind tunnel test laboratories in Japan. – Wind tunnel tests have been carried out to concrete cable stayed bridges constructed in Japan. (c)Vacuum Consolidation Method (VCM) i) Overview Vacuum consolidation method (hereinafter, VCM) is one of a soft ground improvement method mainly aimed to accelerate consolidation period and strengthen objected soil layer’s strength. A construction procedure for this method is; (i) establishing collecting head by using vertical drains to be installed from ground elevation and horizontal drains for connecting vertical drains, (ii) covering project area with air proof 8-3 seats, (iii) decompressing the area and suction the air under the sheet and groundwater. Figure 8-2 Conceptual Illustration for VCM Management unit of measurement Air water separation tank Settlement gauge [Primary separation tank] Vacuum drive unit Drainage Horizontal drain Drainage pipe Air water separation tank Pressure sheet Exhaust pipe [Secondary separation tank] Perforated water catchment pipe Water pipe Forced dehydration by high vacuum Vertical drain (Reference:HP of Vacuum consolidation method Association) ii) Comparison VCM to conventional method Comparison result between conventional method and VCM are summarized in below table. Table 8-2 Comparison Result Method Vacuum Consolidation Method Prefabricated Vertical Drain Method Pressure sheet, Horizontal drain, Perforated water catchment pipe e.t.c. Extra-Embankment Deep Cement Mixing Method Vacuum drive unit Figure Embankment Vertical drain Soft ground Overview Embankment Embankment Soft ground Vertical drain Soil improvement column Soft ground Accelerate a consolidation by Drain excess groundwater, Construct cement-mixed pile, enforcing suction by using which is caused by surcharge, by which ground strength is decompression (vacuuming) with vertical drainage improved. Specialized plant facilities are Specialized plant facilities are Specialized huge plant is not necessary not necessary necessitated Period 1.00 2.00 0.50 Cost 1.00 1.20 1.70 Evaluation good fair fair Construction (Reference:HP of Vacuum consolidation method Association) 8-4 iii) Advantage of VCM – One hundred (100) percent of primary consolidation can be possible by using proper surcharge. – Tendencies for deformation and settlement of ground to be improved by VCM (refer to below illustrations) is different from those by conventional method. VCM can improve objected ground rapidly with little residual settlement rapidly. – Due to the cracks to be occurred at ground surface can restrict deformation and displacement of neighboring ground. – VCM has higher environmental acceptability than cement deep mixing method, in terms of ground pollution. Figure 8-3 Comparison of Ground Improvement Method between Surcharge method and VCM Embankment Vacuum pressure 60~95KN/m² Upheaval Settlement Cracks on surface Settlement Outward deformation PVD Inward deformation VCM (Reference:Vacuum consolidation method Association) iv) Actual Achievement VCM, which was originally invented in Europe, has been continuously improved in Japan. Nowadays, Japan is a leading country of the method and thereof actual achievement is increasing. Regarding to the experience for the method in Vietnam, the method has been applied to the construction stage of South Highway Project. Total volume of construction (year) (Reference:Vacuum consolidation method Association) 8-5 ³) Total volume of construction(thousand m³) Annual volume of construction ³) Annual volume of construction(thousand m³) Figure 8-4 Transition for Actual Achievement of VCM (d)Screwed Steel Pile i) Overview Screwed steel pile is a foundation pile made of steel with steel plate at the tip (bottom), of which dia meter is 1.5 to 2.0 times larger than the steel pipe. This steel plate, called as “a wing”, generates higher resistance capacity by enlarged tip-sectional area. Moreover, the wing also generates penetration force, assisting and shortening a construction time, by rotating the shaft. Figure 8-5 Illustration of Figure 8-6 Tip of Screwed Pile Screwed Steel Pile (Enlarged tip section; a wing) ii) Comparison between Screwed Steel Pile and Bored Pile According to the comparison result, the rough cost estimation result shows that the cost for the screwed steel pile to this project is ten (10) percent higher than that for bored pile while quality controllability for the screwed pile has high advantage to bored pile. Incidentally, in terms of applicability of foundation piles to certain soil conditions, which affect to cost estimation, the screwed steel pile method generally requires more detailed information than that for bored piles. Therefore, it is recommended to carry out further study for selection of the screwed steel pile with additional soil investigation. 8-6 Table 8-3 Comparison Result for Screwed Steel Pile and Bored Pile Cast in Place Pile φ1.2m Screwed Steel Pile Steel Pileφ0.9m, Wingφ1.8 Dimension of Pile Foundation 15 1.00 day/Pile 1.67 -The construction party increases because there are a lot of numbers of the Pile. -The risk of The construction trouble is also high. 12 0.75 day/Pile 1.00 -The construction party decreases because there are a few of numbers of the Pile. -The risk of The construction trouble is also low. -Due to a lot of numbers of the construction simultaneously, the supervision work is difficult and uneasy for the quality control. - Due to a few of numbers of the construction simultaneously, the supervision work is simplicity and easy for the quality control. -The disposing facility of the industrial discharge and the slurry is necessary. -The disposing facility of the industrial discharge and the slurry is unnecessary. Pile No./foundation Constructio Construction Speed n work Ratio Constructability Supervision of works Environmental Construction Cost (ratio) 1.00 1.10 *above ratio for construction cost shall be referred to table 5-5 “Selection of Foundation Type” iii) Advantage of Screwed Steel Pile - Piles are prefabricated in a factory, so that quality of pile is always high, and shortening of construction period is feasible. - Simplified construction procedures also enable to shortening the construction period and facilitate quality controllability at site. - Resistance capacity of the pile is higher than bored pile; so that the number of piles can be reduced, and then construction period can be shorten. - Piles are screwed into ground with out excavation, so that industrial discharge (excavated soil) is ZERO. - Penetration torque for the pile is monitored timely; so that quality control in terms of bearing resistance is easy. - Driving this pile will not be affected by ebb and flow, which is one of a particular issue to this project. iv) Actual Achievement of Screwed Steel Pile The screwed steel pile method is one of a Japanese original technology, and actual achievement for this method has been increasing since 1998. 8-7 (e) HMS (Health Monitoring System) i) Overview Health Monitoring System (hereinafter, HMS) is a system mainly to facilitate maintenance activities for comprehensive of bridge structure by means of sophisticated analysis and automatic evaluation system for various types of datum accumulated through various sensors installed in place. An application of this system can detect changes of bridge behavior timely; not only chronological deterioration of members but also unexpected phenomena, and facilitate to prolong a bridge life span. Figure 8-7 Schematic of HMS GPS Monitoring Camera Thermometer Anemometer Rain Gauge Data Acquisition Room GPS:8 measurement stations, 2 ground station units, Monitoring camera:4, Thermometer:1, Fiber-Optic Cable Anemometer:2, Rain gauge:1 ii) Advantage of HMS - Automatic chronological structural monitoring (24hr) can reduce periodic labor maintenance costs and/or indicate suitable timing for maintenance - Facilitation for prompt recognition of unexpected troubles, unusual signs. - Improvement of safety and quality controllability for construction. (if HMS is started to be utilized during construction stage) - Detection and regulation of overloaded vehicles iii) Actual achievements for HMS Actual achievements for HMS are summarized in below table. As the table shows, Japan is a world-leading HMS country. Moreover, consecutive studies have been executed in order to meet demands of more 8-8 sophisticated and diversified society. Table 8-4 Actual Achievements of HMS 1 2 Bridge Name Bridge Type Country Akashi Kaikyo Bridge Suspension Japan Cable-stayed Japan Tatara Bridge 3 Seto Ohashi Bridge Suspension Japan 4 Onaruto Bridge Suspension Japan 5 Rainbow Bridge Suspension Japan 6 Tsurumi Tsubasa Bridge Cable-stayed Japan 7 Great Belt Bridge Suspension Denmark 8 Tsing Ma Bridge Suspension China(HKG) Cable-stayed China(HKG) 9 Kap Shui Mun Bridge 10 Ting Kau Bridge Cable-stayed China(HKG) 11 Sutong Bridge Cable-stayed China 12 Wenhui Bridge Cable-stayed China 13 Bai Chay Bridge Cable-stayed Vietnam Figure 8-8 Case of HMS for Akashi-Kaikyo Bridge (Japan) 8-9 8.2 Content of Material & Equipment and Cost to be Procured from Japan 8.2.1 Content of Material & Equipment to be Procured from Japan Construction materials such as stay cables, prestressing steels and steel casing pipes for hypostyle foundation shall be procured from Japan in terms of quality and reliability for durability and corrosion resistance. Regarding an installation methods of stay cables, sophisticated technology, to which Japanese firms are well known, are expected to be utilized. Table 8-5 Material & Equipment List to be Procured from Japan Cost Item JPY (Mill.) Material Prestressing steel & Steel rod 300 Cost (i) Bridge Bearing 118 Expansion Joint 139 Reinforcing bar 1,508 Cement 365 Steel Sheet Pile 81 Sub-total 1 2,511 Material Stay Cable 515 Cost (ii) Steel Casing 435 Sub-total 2 950 Total 3,461 8-10 8.2.2 Cost Estimation for Japanese Technology The cost for Japanese Technology consist of material cost, equipment cost and transportation cost, installation cost for stay cables, wind tunnel test cost and engineering costs relating to designing and planning for temporary facilities, construction supervision by Japanese engineers, etc. The total amount of such cost is more than 30 percent of total project cost and shown in table 8-6. Table 8-6 Cost Estimate for Japanese Technology Cost Item Remark JPY( Mill.) Material 2,511 Sub total (ii) estimated in Table 8-5 Machine t 225 Procured from Japan Stay cable 812 Stay Cables (Material and installation cost) Cost for Wind tunnel test Japanese Cast in pile Technology Engineering 10 1,676 Contain test Model D=2.5m for Main bridge (Material and installation cost) 10% of Construction cost (assumption) - General and administrative cost: 7% 2,124 Total (i) - Site office overhead: 3% 7,357 About 73 hundred-millions Total Project Cost (ii) 21,236 About 212 hundred-millions Ratio 34.6% >30.0% (i)/(ii) *: Material const shown in table 8-3 is exclusive of the material cost for stay cables. *: Engineering cost is assumed as a summation of General and Administrative cost (7%) and Site Office Overhead (3%: remuneration for Japanese engineers). 8.3 Necessary Measure of Japanese firms to receipt of orders This project connects newly developed international ports to NH51 heading to Ho Chi Minh, and the importance of this project is obvious for not only the ports area but also all the southern provinces including Vung Tau since the requirements to this project is quite high level in terms of geological conditions, geographical conditions and magnitude of bridge scale. In order to accomplish this project, the following the Japanese technologies are necessitated and expected to be adopted; Technologies and technical experiences: - Design and construction of very large scale cable stayed bridge - Technology for wind tunnel test and analysis method - Experiences of supervision for very large scale cable stayed bridge 8-11 - Experiences of supervision for deep foundation. - Experiences and technology for design of bridges on very soft soil Construction materials and equipment: - Stay cables and equipment for installation - Facilities of wind tunnel test - reinforcing steels - bridge bearings - devices for Structural Health Monitoring System - steel casing pipes for bored piles - material and equipment for screwed steel pipes (subject to further study) - material for Vacuum Consolidation Method (subject to further study) As stated above, this project has high compatibility of Japanese Technologies for optimizations in terms of economic efficiency, quality control and resolution of technical difficulties, etc. Consequently, application of the technologies, which make the participation of Japanese firms who are familiar to the leading-edge technologies developed by Japan dominantly, is essential to this project. In conclusion, it is recommended to propose above compatibility and necessity of Japanese technologies to Vietnamese implementing agency, and to urge adoption of the technology. That approaches would also lead Japanese firms to receipt of orders. 8-12 APPENDIX APPENDIX-1: BRITEC F/S (Report on Investment Construction Project of Cai Mep – Thi Vai Inter-port Road, Ba Ria – Vung Tau and Dong Nai Province) 1-1 Original Vietnamese Version (Cover page and the Table of Contents) 1-2 English Translation of the Table of Contents APPENDIX-2: Decision No. 2669/QD-UBND (BVPPC approved BRITEC F/S) 2-1 Original Vietnamese Version (the first page only) 2-2 English Translation (Excerpt) APPENDIX-3: Letter No. 614/CHHVN-KHDT (Instruction for navigation clearance issued by the Maritime Bureau of MOT) 3-1 Original Vietnamese Version 3-2 English Translation APPENDIX-4: Announcement No. 255/UBND-TB (Conclusions of the meeting between BVPPC and DNPPC regarding CM-TV Inter-port Road Investment Project) 4-1 Original Vietnamese Version 4-2 English Translation APPENDIX-5: Data for Construction Costs APPENDIX-6: JBIC Screening Form ( for social and environmental considerations) APPENDIX-7: Data for Geological/Topographic Conditions APPENDIX-1: BRITEC Report (Report on Investment Construction Project of Cai Mep – Thi Vai Inter-port Road, Ba Ria – Vung Tau and Dong Nai Province) 1-1 Original Vietnamese Version (Cover page and the Table of Contents) 1-2 English Translation of the Table of Contents People's Committee of Ba Ria - Vung Tau Department of Transportation Ba Ria - Vung Tau Investment construction project of Cai Mep – Thi Vai Inter-port Road Ba Ria – Vung Tau and Dong Nai province Volume I: Explanation (Repair following Decision 2669/QD-UBND dated August 10 th,2009 of People's Committee of Ba Ria Vung Tau) Contents of Explanation Investment construction project of Cai Mep – Thi Vai Inter-port Road Ba Ria – Vung Tau and Dong Nai province Chapter I: General Introduction ………………………………………………………....... I.1 Beginning ………………………………………………………............................. I.2 The basis for making investment projects I.3 The study scope of project I.3.1 Phase 1 of project I.3.2 Phase 2 of project I.3.3 To sum up whole project (Finish investing two Phases) I.4 Reference I.5 Time and organization research and form project I.5.1 Organization chart for project implementation I.5.2 project planning process Chapter II: Determine the need for investment in construction II.1 Current situation and planning Cai Mep – Thi Vai multi port belong to Port group No 5 II.1.1 Current situation of Cai Mep – Thi Vai Port II.1.2 Current situation of Industries along alignment II.1.3 Current situation of road traffic in Cai Mep – Thi Vai Port II.1.4 Current situation of Cai Mep – Thi Vai Inter port Road II.1.5 Planning of port group No 5 II.2 Development planning are traffic II.3 Forecast traffic flow II.3.1 calculating the bridge width and road width II.4 Conclusions about the necessity of investment II.4.1 Implementation of approved plan II.4.2 Meet urgent needs for transportation in Cai Mep – Thi Vai port group II.4.3 Unified management and investment planning Chapter III: Natural regional conditions Characteristics III.1 Topography regional routes III.1.1 Component I: III.1.2 Component II: III.1.3 Component III: III.1.4 Component IV: III.1.5 Component V: III.1.6 Component VI: III.1.7 Other remaining Components III.2 meteorological and hydrological characteristics III.3 III.2.1 Meteorological III.2.2 ground temperature III.2.3 Hydrological geological characteristics Chapter IV: Chosen design solution IV.1 Chosen infrastructure and investment options IV.1.1 Choose infrastructure scale IV.1.2 Clearance requirement IV.2 Choose technical standard IV.2.1 Standard, specification, rules application IV.2.2 Design standard IV.3 choose bridge location and alignment IV.3.1 Option for alignment position No 1 IV.3.2 Option for alignment position No 2 IV.3.3 Recommendation IV.4 Solution for designing alignment IV.4.1 Plan and direction IV.4.2 Alignment profile IV.4.3 Horizontal profile IV.4.4 Design sub-grade IV.4.5 Coat IV.4.6 Drainage system IV.4.7 Illumination system IV.4.8 Green tree system IV.4.9 Traffic safety system. IV.4.10 Interchange at the end of alignment IV.5 Solution for designing Vam Gui bridge IV.5.1 Bridge position IV.5.2 Plane and profile IV.5.3 Section IV.5.4 Structural option No 1 (with clearance Bxh=50x7m) IV.5.5 Structural option No 2 – Proposal (with clearance Bxh=25x3.5m) IV.5.6 Comparison and chosen IV.5.7 Construction organization proposed options IV.5.8 Ground site IV.5.9 Construction schedule IV.6 Solution for designing Ban Thach bridge IV.6.1 Bridge position IV.6.2 Plane and profile IV.6.3 Section IV.6.4 Structural option No 1 (proposal) IV.6.5 Structural option No 2 (comparison) IV.6.6 Comparison and chosen IV.6.7 Construction organization proposed options IV.6.8 Ground site IV.6.9 Construction schedule IV.7 Solution for designing bridge pass over water pipe of Phu My power station IV.7.1 Bridge position IV.7.2 Plane and profile IV.7.3 Section IV.7.4 Structural option IV.7.5 Construction organization IV.7.6 Ground site IV.7.7 Construction schedule IV.8 Solution for designing bridge pass over oil pipe of Phu My power station IV.8.1 Bridge position IV.8.2 Plane and profile IV.8.3 Section IV.8.4 Structural option No 1: Viaduct IV.8.5 Structural option No 2: Bypass IV.8.6 Structural option No 3: Creep down oil pipeline through the road IV.8.7 Comparison and chosen IV.8.8 Construction organization proposed options IV.8.9 Ground site IV.8.10 Construction schedule IV.9 Solution for designing Rach Muong bridge IV.9.1 Bridge position IV.9.2 Plane and profile IV.9.3 Section IV.9.4 Structural option No 1 IV.9.5 Structural option No 2 IV.9.6 Comparison and chosen IV.9.7 Construction organization proposed options IV.10 Solution for designing Phuoc An bridge IV.10.1Bridge position IV.10.2Plane and profile IV.10.3Section IV.10.4Option No 1: (Cable-stayed bridge with main span is 360m) IV.10.5 Option No 2: (Supension bridge with main span is 540m, gradient is 4%) IV.10.6 Option No 3: (steel pipe filled with concrete arch bridge with main span is 360m) IV.10.7Option No 4: (extradosed bridge with main span is 300m) IV.10. 9. Propose the structural option for Phuoc An bridge IV.10.10. Organize construction for proposed option ( Option No 01) IV.11. Other items Chapter V: Material V.1.1 Concrete V.1.2 Nonpre-stressed reinforcement V.1.3 Pre-stressing steel and accessories V.1.4 Plate steel and form steel V.1.5 Backfill soil, sand, stone V.1.6 Other material Chapter VI: Site clearance and resettlement works VI.1 Project position VI.2 Compensation mass for resettlement VI.3 Preliminary organization and compensation option for resettlement Chapter VII. Explanation sectors impact Environment VII.1 Background VII.2 Remark and proposal about environment Chapter VIII. Total investment, phasing of investment VIII.1 Total investment VIII.1.1Base for forming total investment VIII.1.2Total investment VIII.2 Funds VIII.3 Investment phasing VIII.3.1Phase I (from 2009 to 2012) VIII.3.2Phase II (from 2010 to 2015) Chapter IX. Conclusion and proposal IX.1 Project content IX.1.1 Design scope IX.1.2 Construction size IX.1.3 Technical standards IX.1.4 Alignment Component and construction on the alignment IX.1.5 Options for investment phasing IX.2 Total investment IX.2.1 Total investment IX.2.2 Funds IX.3 Organize, implement project IX.3.1 Implementation schedule IX.3.2 Departments implement project IX.4 Other problems need to notice Appendix and related documents APPENDIX-2: Decision No. 2669/QD-UBND (BVPPC approved BRITEC Report) 2-1 Original Vietnamese Version (the first page only) 2-2 English Translation (Excerpt) Ba Ria – Vung Tau provincial People’s Committee No. 2669/QD – UBND SOCIALIST REPUBLIC OF VIET NAM Independence – Freedom – Happiness Vung Tau province, August 10th 2009 DECISION on approval of investment for Cai Mep – Thi Vai Inter port construction project CHAIRMAN OF BA RIA – VUNG TAU PROVINCIAL PEOPLE’S COMMITTEE Pursuant to law on organization of People’s Committee and People’s Council dated November 26 th, 2003 Pursuant to Construction Law on November 26 th, 2003 Pursuant to Government’s Decree No. 99/2007/ND-CP of June 13th, 2007 on Management of construction investment expenditure. Pursuant to Government’s Decree No.03/2008/ND-CP dated January 7th, 2008 on amendment and supplement of some articles of Government’s Decree No.99/2007/ND-CP dated June 13th, 2007 on Management of construction investment expenditure. Pursuant to Government’s Decree No.12/2008/ND-CP dated February 12th, 2009 on Management of construction investment. Pursuant to Circular No.03/2009/TT-BXD dated March 26th,2009, detailing some contents of Government’s Decree No.12/2009/ND-CP dated February 12th,2009 on Management of construction investment. Pursuant to Government office’s document No.3990/VPCP-KTTH dated June 15 th,2009 on informing Prime Minister’s result including, DECIDES: Article 1. Approval of investment for Cai Mep – Thi Vai Inter port construction project including some main contents below: 1. Project name : Cai Mep – Thi Vai Inter port construction project Project type : Group A: 2. Client: Department of Transportation Ba Ria - Vung Tau 3. Organizational consulting projects : Bridge & Tunnel Engineering Consultant Joint Stock Company 4. Project manager: Mr. Nguyen Thanh Ha 5. The target of construction investment: Cai Mep-Thi Vai inter-port Road is invested for building infrastructure behind ports for transporting material, equipment in order to service construction and exploitation for all port system and industries in area. Synchronous investment for Cai Mep-Thi Vai inter-port road will meet the requirement of investors, implement the government’s commitment on investment projects outside the fence of the port, creating dynamic for developing socioeconomic of key economic area of the south and southern region. 6.Contents and scope of construction investment The total length of alignment is 21.3 Km, including, the new construction alignment is about 11.3km and bridge parts are 4.7 km. Total investment for items: Sub-grade and coat for road and bridge, drainage and water supply, illumination system, green tree, side walk, traffic signal system. + Phase 1. Investment for building nine segments from Km 0+00 to Km 19+650 (particular, segment No 2 from Km 1+898.03 to Km 7+19.25 is being invested by ODA fund, so it is not considered in this project and segments No 4 and No 5 are re-invested to other remaining items for completing alignment). + Phase 2: investment for building the approach road and Phuoc An bridge from Station Km 18+100 to Station Km 21+360.94 a) Working scale: – Road section of segment No 1 (from Km 0+00Km 1+898.03) 9.5 + 4.5 + 10 + 2 + 10 +4.5 + 9.5 = 50 m. – Road section of segment No 3 (from Km 7+199.25 Km 9+612.64) and segment No 6, No 7, No 8 (from Km 14+424.98 Km 18+100) 10 + 3 + 11 + 2 + 11 + 3 + 10 = 50m – Section of segment from Station Km 18+ 100 to Station Km 19+650 belong to segment No 9 (segment has Phuoc An bridge) 3 + 9 + 26 + 9 + 3 = 50m – Section of bridges on alignment ( Vam Gui bridge, Ban Thach bridge, Rach Muong bridge, bridges pass over oil pipeline and drainage water pipeline of Phu My hydropower plant) 0.5 + 11 + 2 + 11 + 0.5 = 25m – The section of Phuoc An bridge. 0.5 + 11+0.5+11 + 0.5 = 23.5 m – For upgrading segment and extension segment: + Segment No 4 (from Km 9+612.64 ÷Km 11+689.78): Investment for building coat, drainage system, sidewalk, green tree, illumination with section scale: 10 + 3 + 11 + 2 + 11 + 3 + 10 = 50m. b) Technical specification. - Design speed: Vtk = 70km/h. - The minimize elastic module Eyc = 173 Mpa Design load: single axle 120 KN. High level pavement A1 The bridge is designed with permanent structure by pre-stress concrete. Frequency design is P 1%. Level 6 earthquake region. Maximum longitudinal gradient I < 4% The limited-minimize curved radius in plan is 175m (R = 175 m) + The minimize curved radius on plan without superelevation is 2000m (R = 2000m) The maximum allowance gradient is 5% The minimize vertical curved radius: R = 2000 ( for coned curve), R = 1500 (for sag curve).The minimize vertical curved length is 60m. c) Clearance requirement. Name of bridge Height H (m) Width B (m) Vam Gui bridge 3.5 25 Ban Thach bridge 5 40 Rach Muong bridge No clearance requirement 120 ( for one way flow) Phuoc An bridge 55 239 (for two-ways flow Bridges pass over drainage water pipe and oil pipeline of Phu My hydropower plant Note Suitable with the fact Suitable with the fact Higher than current pipe peak about 0.5m Outside pipeline scope Following the requirement of The Maritime Bureau of Viet Nam Suitable with the fact d) Structural options. Name of bridge Span layout (m) Vam Gui bridge 39.15 + 5x40 + 29.15 Widt h (m) 25 Lbridge = 285.5 Ban Thach bridge 39.15 + 2x40 + (55.9+90+55.9)+ 2x40+ 39.15 25 superstructure substructure - Span is Super T girder, L = 40m - Approach road at two sides of bridge L = 70m. using reinforced concrete load reduction slab with baffle - Main span is continuous pre-stress concrete L = 90m, approach span is Super T girder L = 40m - Boring pipe D = 1.5m Foundation of load reduction slab is precasted reinforced concrete 45x45 cm - Main span is boring pipe D = 1.5m, approach bridge is boring pipe with D = Lbridge = 450.3 Bridge pass over drainage water pipeline of Phu My hydropower plant Bridge pass over oil pipeline of Phu My hydropower plant 12 + 38.3 + 12 Rach Muong bridge 39.15 + 5 x 40 + 39.15 - Approach road at two side of bridge is load reduction slab 25 Span is Super T girder, L= 40m 1.0m Foundation of load reduction slab is precasted reinforced concrete 45x45 cm Using boring pipe with D = 1.5m Lbridge = 68.5m 5 x 24 25 - Lbridge = 125.3 - 25 - Lbridge = 285.5 Phuoc An bridge - 32x40+(153+360 +153)+19x40+25 +31.7+46.5+31.8 +25+9x40. The total length is 3254.5m (Lbridge = 3254.5m) 23.5 Span is pre-stress concrete voided slab girder, L= 24 (m) Reinforced concrete retaining wall at two sides of bridge Span is Super T girder, L = 40m Approach road at two sides of bridge L = 20 m use load reduction slab Main span is pre-stress concrete cable-stayed bridge, L= 360m. Approach span is Super T girder L = (2540m) - - Using boring pipe with D = 1.0m Using driven pile (35x35 cm) for retaining wall Using boring pipe with D = 1.0m Using driven pile (35x35 cm) for load reduction slab Main span use boring pipe with Diameter 2.0m (D=2.0m) Approach span is boring pipe with Diameter 1.0 m(D=1.0m) e) Alignment and works on alignment. - New coat structure is designed with Eyc > 173 Mpa + Fine asphalt concrete with thickness is 5 cm + The coarse asphalt concrete with thickness is 10 cm + Grade aggregate category No1 with thickness is 30cm + Sand cement PC40 with thickness is 35cm + The upper base is fine soil base with density K > 0.98 to ensure E0> 50 Mpa - Profile: The control elevation of profile along bridge and water level of alignment I = 4%. At the points which have changing gradient with i= 1%, it need design vertical curve. Soft soil treatment follow option No.2 (by the reinforced soil cement pipe method) with segments have mud layer with the thickness is under 30 m ( <30m), follow the option No 1 (reinforced load reduction slab run directly) for segments have mud layer with the thickness is from 30 to 35m: the detail as below. Segment Station Length option Reinforce concrete slab, pre-cast driven Km 0+000.00Km L = 200.70m foundation pipe 0+200.70 45x45cm Reinforce concrete Segment I slab, pre-cast driven Km 0+556.22Km L = 243.78 m foundation pipe 0+800.00 45x45cm Reinforced soil Km 0 + 800.00Km L = 1 098.03 m cement pipe with 1+898.03 diameter D = 80 cm Reinforced soil Km 7+199.25Km 8 L = 636.28m cement pipe with + 835.53 diameter D = 80 cm Reinforce concrete slab, pre-cast driven Km 8 + 332.25Km Segment III L = 547.75m foundation pipe 8 +880.00 45x45cm Reinforced soil Km 8+880.00Km 9 L = 732.64m cement pipe with +612.64 diameter D = 80 cm Reinforced soil Km 14+424.98 Km Segment VI, VII, VII L = 2 970.72m cement pipe with 18+100.00 diameter D = 80 cm Reinforced soil Km 18+100.00Km L = 1100m cement pipe with 19+200.00 diameter D = 80 cm Segment IX Reinforce concrete slab, pre-cast driven Km 19+200Km L = 450m foundation pipe 19+650.0 45x45cm - f. Side walk structure: Lay bricks Terrazo M200 with dimension 30x30x3.5m, grout M 100, stone concrete curb 1x2 M250, blinding stone concrete 1x2 M100, M150; curb for protecting sidewalk is concrete stone 1x2 M 200 and it placed on blinding stone concrete 1x2 M150. g. Drainage system: + Storm-water drainage system: Using culvert head with types 600, 800, 1000, 1200, 1500, 2000 with load H10 on sidewalk and H30-XB 80 is on coat (pavement). Stormwater drainage direction extend to channel on alignment Storm-water collector: using directly water collector place on coat at curb by cast iron plate with hole + Manhole system: It is arranged with average distance is 50 m / manhole, manhole structure is concrete or reinforced concrete. It depend on each position h. Green tree. Using Sao Den tree, plant tree at two sides of road on the sidewalk, the average distance between two tree is 10m. Hole for planting tree is square shape (1.2 x 1.2m). On median strip, plant Cau Bung tree with average distance 6m/tree and plant grass. i. Lighting system. Arrange twin lamp post on median strip, the average distance 40m/lam post, lamp post is 12m height (including arm). Using underground cable and it runs under median strip. Electrical substation is three-phase electrical substation with capacity 3x15KVA and the average distance is 3km/station. j. Traffic signal system: Arrange traffic signal system following the regulation of “highway signal regulation 22TCN273-01” 7. Construction location. The location is in Tan Thanh district, Ba Ria-Vung Tau province and the grade-separated intersection is in Nhon Trach district, Dong Nai province - Beginning: Station Km 0+000, Cai Mep Ha container synthesis port is in Tan Thanh district, Ba Ria-Vung Tau province. Ending: Station Km 21+303.06, connect to Phuoc An port is in Nhon Trach district, Dong Nai province. 8. Used land area It is about 515 089 m2. The recovered land will actually be correct when it was approved by the competent authorities 9. Construction options. Basic design option attach with explanation of investment project report was amended following supporting ideal report of basic design of Ministry of transport No 4328/BGTVTKHDT date on June 29 th 2009. 10. Category and construction grade. According to the article No 1 of regulation, gradation, classification, construction work issue with Decree No 209/2004/ND-Cp date on December 16th 2004 of government, this work is main urban road, grade II. Function : major arterial road of industry 11. Compensation, Site clearance. Alignment go through land ecosystems of Mangrove, occupied residential land, a number of industrial facilities, public facilities, infrastructures have to move, a number of graves were relocated. Preliminary volume is around 515 089 m 2, the total compensation cost is 35.3 billion dong as temporary calculating. Area and compensation cost are only temporary calculating, the fact area will be correctly when competent authorities have recover decision. 12. Total investment of project: 6 381 120 million dong Including:: + Construction cost : 5 153 361 million VND (Vietnam Dong) + Project management cost: 43 524 million VND (Vietnam Dong) + Consultant cost: 113 271 million VND (Vietnam Dong) + Compensation cost: 35 283 million VND + Others cost: 203 361 million VND (Vietnam Dong) + contingency cost : 832 320 million VND (Vietnam Dong) 13. Investment capital. Using public bond fund 14. Project management type. Investor directly manage project 15. Time of implementing project. 15.1. Phasing investment of construction project. * Stage No 1: The total alignment is about 19.65km, the beginning of alignment at Station Km 0+00, it is near Cai Mep Ha general container port and the ending of alignment at Km 19+650, it is near Vinaline shipyard industry, including: - Segment No 2 is under construction with 2km length (don’t calculate in this project) - 8.232 km is new construction investment (including segments No 1;3;6;7;8;9) - Investment for building coat structure, drainage system, sidewalk, other accessories works, segment No 4 is about 2.1 Km (belong to road project which connect to Ba Son Shipyard and this road is implementing construction stage No1: Soft soil treatment and building temporary coat) - Investment for building sidewalk structure and other accessories works, segment No 5 is about 2.7km (due to alignment was invested all sub-grade, coat, longitudinal drainage system). - Investment for building 5 bridges on alignment with total length is 1 215m, including Vam Gui bridge, Ban Thach bridge, bridge passes over drainage water pipeline of Phu My hydropower plant, bridge passes over oil pipeline of Phu My hydropower plant, Rach Muong bridge Total investment Stage No 1: 2 837 988 million dong Including:: + Construction cost : 2 273 203 million VND (Vietnam Dong) + Project management cost: 24 227 million VND (Vietnam Dong) + Consultant cost: 68 431 million VND (Vietnam Dong) + Others cost: 66 672 million VND (Vietnam Dong) + Compensation cost: 35 283 million VND(Vietnam Dong) + contingency cost : 370 172 million VND (Vietnam Dong) Time of implementing project: As the planning, the project will commence in quarter IV 2009 and finish in 2012. * Stage No 2: The total length of alignment is about 3.26Km (Segment No 9). The beginning of this segment is at Station Km 18+100, the ending of this segment is Station Km 21+360.94 which connect to Phuoc An port, including: - Investment of Phuoc An bridge construction is 3254.5m - The approach road is about 262m and rehabilitate the plan of tapered junction segment to be suitable with scale of Phuoc An bridge. - Investment for building grade-separated interchange at the end of alignment connect to Phuoc An port in Nhon Trach district side of Dong Nai province. Total investment of Phase No 2: 3 543 132 million VND (Vietnam Dong) Including: + Construction cost : 2 880 158 million VND (Vietnam Dong) + Project management cost: 19 297 million VND (Vietnam Dong) + Consultant cost: 44 840 million VND (Vietnam Dong) + Others cost: 136 689 million VND (Vietnam Dong) + contingency cost : 462 148 million VND (Vietnam Dong) Time of implementing project: As the planning, the project will commence in 2012 and finish in 2015. 15.2 Divide the component project and implementing as phasing investment: Base on the basic of investment phasing of Cai Mep-Thi Vai inter-port Road was divided into 2 stages, to convenient for implementing project, Cai Mep-Thi Vai inter-port road was divided into 9 component project and was managed and implemented as an independent project, the detail as below: - Component project No 1: Segment No 1 (Km 0+00Km 1+898.03), the length is about 1.898Km, connect from Cai Mep Ha general container port to Cai Mep container port which is new construction, within, have Vam Gui bridge with 285.5 m length. Total investment: 576 373 million dong Time of implementing: As the planning, the project will commence in 2010 and finish in 2012. - Component project No 2: Segment No 2 (Km 1+898.03Km 7 + 199.25), the length is about 5.3 km, the road connect to Cai Mep Container port, is investing for building suitable with master plan of whole alignment, investor is Project Management Unit No 85 belong to Ministry of transport, the segment No 2 is not in Cai Mep-Thi Vai inter-port Road project - Component project No 3: Segment No 3 (Km 7+199.25 Km 9+612.64), the length is about 2.413 km, connect from Interflour port to Posco port and it is new construction, including Ban Thach bridg with 450.3 m length. Total investment: 727 682 million dong Time of implementing: As the planning, the project will commence in quarter IV 2009 and finish in 2011. - - - Component project No 4: Segment No 4(Km 9+612.64 Km 11+698.78), the length is about 2.086 km, connect from Posco port to Phu My steel factory port (Road run to Ba Son shipyard). It is constructing sub-grade and it is suitable with master plan of whole alignment. Continue investment for building coat structure, drainage system, sidewalk and also other accessories works. Total investment: 186 103 million dong Time of implementing: As the planning, the project will commence in 2010 and finish in 2012. Component project No 5: Segment No 5 (Km 11+698.78Km 14+424.98), the length is about 2.726 Km, connect from Phu My steel factory port to SITV port, and It was invested for building coat structure and drainage system which is suitable with master plan of whole alignment. Continue investment for building sidewalk and also other accessories works. Total investment: 69 793 million dong Time of implementing: As the planning, the project will commence in 2010 and finish in 2012. Component project No 6: Segment No 6 (Km 14+424.98Km 15+561.31), the length is about 1.136 Km, connect from SITV port to XH Holcim port, including, bridge passes over drainage water pipeline of Phu My hydropower plant with 68.5 m length ( road runs to Phu My crushing Clinker Holcim factory). - Total investment: 177 153 million dong - Time of implementing: As the planning, the project will commence in quarter IV 2009 and finish in 2012. - Component project No 7: Segment No 7 (km 15+561.31Km 17+271.13), the length is 1.709 Km, connect from XM Holcim port to My Xuan general international port, including, bride passes over oil pipeline of Phu My hydropower plant with 125.3 m length and Rach Muong bridge is 288.5m Total investment: 446 483 million dong Time of implementing: As the planning, the project will commence in 2010 and finish in 2012. - Component project No 8: Segment No 8 (Km 17 + 271.13 Km 18+100), the length is about 0.828 Km, connect from My Xuan general international port to An Phu shipyard, Total investment: 193 649 million dong Time of implementing: As the planning, the project will commence in 2010 and finish in 2012. - Component project No 9: Segment 9 (Km 18+ 100Km 21+360.94), the length is about 3.26 Km, belong to Tan Thanh district Ba Ria-Vung Tau province and Nhon Trach district Dong Nai province, connect from An Phu Shipyard to the road which go to Phuoc An port. + Phase No 1: From Km 18+100Km 19+650, the length is about 1.55km, belong to Tan Thanh district Ba Ria-Vung Tau province, connecting road from An Phu Shipyard to Vinalines Shipyard industry. Total investment : 460 752 million VND Time for implementing: As the planning, the project will commence in 2010 and finish in 2012. + Phase No 2: From Km 18+100 to Km 21+360.94, the length is about 3.26Km belong to Tan Thanh district Ba Ria-Vung Tau province and Nhon Trach district Dong Nai province, the approach road and Phuoc An bridge from An Phu Shipyard and grade-separated interchange at the end of alignment connect to Phuoc An port. Total investment: 3 543 132 million VND Time for implementing: As the planning, the project will commence in 2012 and finish in 2015. 16. The contents delivery to investor for implementing during making construction technical design and construction drawing design-total cost estimation of works - - Study clearly the direction for Phuoc An bridge during Stage No 2 following the ideas of Ministry of Transport at Document No 4328/BGTVT-KHDT dated on June 29th 2009 Bridge section of all bridges on alignment don’t need arrange median strip with 2 m width Additional study for drainage and water supply system of sewage for whole alignment. Study clearly the expansion the length of bridge or reduce the vertical radius in order to limit backfill behind abutment according to ideas of quality management Department of transport works (belong to Ministry of transport ) at Document No 531/CQLCLXD-TD2 date June October 2009 - - - - Study clearly hydrology for determining span, geometrical dimension, position of culvert on alignment and carry out the permanent suitable solution, to avoid local flood in future. Additional study on hard coat structure to choose coat which is suitable with future using and heavy vehicle load as ideas of Ministry of transport at Document No 4328/BGTVT-KHDT dated on June 29th 2009 Study reinforced concrete box culvert option for protecting oil pipeline of Phu My hydropower plant in order to reduce construction cost For the project which are invested on alignment, it need to work with current Investors for associating or unifying investment items, to avoid overlap when implementing project. Investor and consultants have responsibilities on precision in surveying, designing and establish the construction quantities in project. When finish construction, Investor have responsibility for transferring work items to Departments (units) which manage directly. Article No2: Transport department is Investor and have a responsibility for completing the next construction procedure to organize and implement project following the contents in Article No 1; responsible as the regulation at construction law. Decree No 12/2008/ND-CP dated on February 12th 2009 of government on construction investment project management and Decree No 99/2007/ND-CP date on June 13th 2007 of government on construction investment cost management; to organize management the quality of construction work in the below period as the regulation at Decree No 209/2004/ND-CP dated on December 16th 2004 of government. Article No3. Chief of provincial people’s committee , director of the Office: Planning and Investment, Transport, Construction, Finance, Natural Resources and Environment, Director of the State Treasury Ba Ria-Vung Tau province, Chairman of Tan Thanh district and head of related agencies to base for implementation APPENDIX-3: Letter No. 614/CHHVN-KHDT (Instruction for navigation clearance issued by the Maritime Bureau of MOT) 3-1 Original Vietnamese Version 3-2 English Translation Ministry of Transport The Maritime Bureau of Viet Nam ------- SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom - Happiness ---------- No.614/CHHVN-KHDT Hanoi, April 03, 2009 v/v: clearance requirement of Phuoc An and Vam Gui bridge Dear: Bridge & Tunnel Engineering consultant Joint Stock Company Vietnam Maritime Bureau received document No 134/TI.CB dated on March 10 th of the Bridge & Tunnel Engineering Consultant Joint Stock Company about “Providing the clearance data of Phuoc An bridge which cross over Thi Vai river and Vam Gui bridge which cross over Vam Gui channel”. After studying and reviewing. VietNam Maritime Department has comments as below. In document No 5974/BGTVT-KHDT dated September,19th 2007. Ministry of Transport has proposed the Prime Minister to allow studying and upgrading Go Dau channel in order to allow the ships which have weight up to 30.000DWT, can come and go on working base on tide. On October, 22nd 2007, government office has document No 6055/VPCP-CN inform the idea of Prime Minister approved about proposed principles of the Ministry of Transport at the document above. So, in the research process of Phuoc An bridge, your company need to calculate in order to ensure the 30.000DWT ship go through safety. Following the calculation of PORTCOAST COSULTANT in document No. 440/KTB-GDADA dated on March, 30 th 2009, the clearance is 55m height, 120m width for one-way flow and 239m for two-ways flow. However to know correct information about the width of Go Dau, your company need report to Ministry of Transport in order to give the directing comment to implement. For Vam Gui bridge. The clearance depend on the size and density inland waterway vehicles which come and go through Vam Gui channel, therefore recommended Company contact with local authority and inland waterway management department in order to unify clearance. Viet Nam Maritime Bureau inform to your company in order to know and implement APPENDIX-4: Announcement No. 255/UBND-TB (Conclusions of the meeting between BVPPC and DNPPC regarding CM-TV Inter-port Road Investment Project) 4-1 Original Vietnamese Version 4-2 English Translation BA RIA – VUNG TAU PROVINCE’S PEOPLE COMMITTEE SOCIALIST REPUBLIC OF VIETNAM Independence – Freedom – Happiness No: 255/UBND-TB Vung Tau, September 25th 2009 ANNOUNCEMENT Conclusion of Ba Ria - Vung Tau Province’s People Committee at the report meeting of Cai Mep – Thi Vai inter-port road investment project On August 13th 2009, at the office of Ba Ria - Vung Tau Province’s People Committee, Chairman of Ba Ria - Vung Tau Province’s People Committee – Tran Minh Sanh and deputy chairman of Dong Nai Province’s People Committee – Tran Van Vinh had cochaired the general report meeting of Cai Mep – Thi Vai inter-port road investment project from Ba Ria - Vung Tau Province to Dong Nai Province. The meeting’s audiences including: From Ba Ria - Vung Tau Province: - Mr. Tran Minh Sanh, Chairman of Ba Ria - Vung Tau Province’s People Committee and leaders of the following Departments: Transportation, Planning and Investment, Finance, Construction, Natural Resources and Environment, Province’s People Committee Office and leader of Tan Thanh District’s People Committee From Dong Nai Province: - Mr. Tran Van Vinh, Deputy Chairman of Ba Ria - Vung Tau Province’s People Committee and leaders of the following Departments: Transportation, Planning and Investment, Finance, Construction, Natural Resources and Environment, Province’s People Committee Office and leaders of two District’s People Committees: Nhon Trach and Long Thanh. After hearing Director of Ba Ria – Vung Tau Province’s Transportation Department – investor agency of Cai Mep – Thi Vai inter-port road - reporting the implementation status of the project, project’s basic design and the audiences’ opinions, leaders of the two provinces had agreed and concluded some following issues: 1. About investment preparation: Follow the investment policy of Ba Ria - Vung Tau Province’s People Committee in the document No. 1005/UBND-VP on February 25th 2009 on investment preparation for Cai Mep – Thi Vai inter-port road; Base on the document No. 672/TTg-KTN on May 6th 2009 of Prime Minister on assigning consultant contractor to survey to establish the investment project of Cai Mep – Thi Vai inter-port road, up to now the Department of Transportation has finished the project’s document. The inter-port road project has received the attention, agreement and approval of the Government, the concerned Ministries and Departments in the document No. 3990/VPCP-KHTH of the Government Office, the Prime Minister has approved of assigning the Ministry of Planning and Investment to add the inter-port road project to the list of projects funding by Government bond capital. The project will be started in the Fourth Quarter of 2009. 2. On construction scale + There are six bridges on the alignment which need invest construction including : Vam Gui bridge, Ban Thach bridge, the bridge across over the oil pipeline of Phu My power station, the bridge across over the water pipeline of Phu My power station and Phuoc An bridge. Phuoc An bridge connects Ba Ria-Vung Tau province and Dong Nai province and the length of Phuoc An bridge is 3.2545 km. 3. On investing Road: Inter-port Road is in the Port group No 5, and it has an important position, for ensuring transmission of goods for all Ports in Cai Mep-Thi Vai river of two provinces, especially for Ba Ria-Vung Tau province. As plan in Ba Ria-Vung Tau side, inter-port Road is connected to existing National Highway No 51 and Bien Hoa-Vung Tau expressway (will be built after 2015) by these Roads: No 46 (available), No 965 (ODA capital and being constructed, until 2012 will be finished), and No 911 and Phuoc An-Cai Mep road (still do not construct (on plan)). In Dong Nai side, inter-port Road will connect Ben Luc-Long Thanh and Cat Lai-Dau Giay inter-regional Expressway. Thus, when the inter-port Road finish all alignment in period 2012, there will be had two sides for transmitting goods, the alignment will be off-line National Highway No 51. With the large container goods will be not overload and traffic congestion while still do not build Bien Hoa-Vung Tau Expressway, other hand the distance of transmitting Goods in the southwestern provinces is shorter. Hence, during the investment process, there is not only invest Stage No1 in Ba Ria-Vung Tau side but also invest for all alignment including Phuoc An bridge and the Road in Dong Nai side. So, when finish inter-port Road (parallel with it, there are Ben Luc-Long Thanh and Cat Lai-Dau Giay Expressway) will be promoted effectively economic. 4. Dong Nai Department of Transportation works Investor of Ben Luc-Long Thanh inter-regional Expressway and the road go into Phuoc An port, report schedule of two projects and implementation commitments 5. Assign the two Departments of Transportation of Ba Ria – Vung Tau and Dong Nai to make document for the two Provinces’ leaders to sign, submit to the Government for permission to invest in the entire inter-port road. On behalf of Chairman Pp Chief of the Office Deputy Chief of the Office Phan Ngoc Duoc APPENDIX-5: Data for Construction Costs Construction Cost of the Project Unit Rate Item General Item Engineer's Office & Accommodation Maintenance Engineer's Office & Accommodation Envrionmental Monitoring Soil Investigation 100m x 10 + 70 m x 93 Test Pile 1.2m on ground Test Pile 2.5m on ground Pile Load Test Load Cell Pile Load Test Static Pile Load Test PDA Waterborne Traffic Maintenance Temporary Yard Temporary Access Approach Bridges L=2,488.5m, W=23.5m Abutment Driven Pile 35cm x 35cm Excavation Concrete 10MPa Lean Concrete Blinding Stone Concrete 30Mpa Abutment Concrete 30Mpa Approach Slab Concrete 30Mpa Slab on pile Reinforcing Steel SD390 Bearing Shoe Bored Pile D=1.2m Embankment Stone Masonry Super T Girders Excavation Concrete 10MPa Lean Concrete Blinding Stone Concrete 30Mpa Pilecap Concrete 30Mpa Pier Concrete 30Mpa Pierhead Reinforcing Steel SD390 Pilecap Reinforcing Steel SD390 Pier Reinforcing Steel SD390 Pierhead Bored Pile D=1.2m Bearing Shoe Super T Girder Concrete 30Mpa Diaphragm Concrete 30Mpa Deck Slab Reinforcing Steel SD390 Parapet Center Barier Handrail Expansion Joint Drainage Catch Basin Main Bridge L=746m Bored Pile D=2.5m In River Bored Pile D=2.0m Bored Pile D=1.2m Excavation Concrete 10MPa Lean Concrete Blinding Stone Concrete 30Mpa Pilecap in river Concrete 40Mpa Tower, Crossbeam Concrete 30Mpa Pilecap, Auxiliary Pier Concrete 30Mpa Pier, Auxiliary Pier Concrete 30Mpa Pierhead, Auxiliary Pier Reinforcing Steel SD390 Pilecap Reinforcing Steel SD390 Tower, Crossbeam Reinforcing Steel SD390 Pilecap, Auxiliary Pier Reinforcing Steel SD390 Pier, Auxiliary Pier Reinforcing Steel SD390 Pierhead, Auxiliary Pier Prestressing Steel (Strand) Grade270 Cross & Beam Tower Prestressing Steel (Bar) Cross & Beam Tower Stay Cable Bearing Shoe Lateral Bearing Shoe Concrete 45Mpa Girder, Diaphragm Reinforcing Steel SD390 Prestressing Steel (Strand) Grade270 Girder, Diaphragm Prestressing Steel (Bar) Girder, Diaphragm Curb Size Center Barier Handrail Expansion Joint Ladder in Pylon Drainage Catch Basin Accessories L=3,234.5m Pavement Marking Lighting Aviation Light Navigation Warning Light Approach Road L=262m 1 Organic Excavation 2 Concrete 3 Reinforcing Steel 4 Driven Pile 5 Embankment 50% Settlement in rate 6 Geotextile 7 Paper Drain 8 Sand Replacement 9 Subbase T=35cm Soil Cement 10 Base T=30cm Aggregate 11 Binder T=10cm 12 Surface T=5cm Miscellaenous 30% of (1,2,3,4,8,9,10,11) Interchange L=1,850m 1 Organic Excavation 2 Embankment 50% Settlement in rate 3 Geotextile 4 Paper Drain 5 Sand Replacement 6 Subbase T=35cm Soil Cement 7 Base T=30cm Aggregate 8 Binder T=10cm 9 Surface T=5cm Miscellaenous 30% of Total Total Construction Cost (JPY) Unit m2 months months m m m No No No Day m3 m3 m2 Quantities 5,000 44 44 7,510 130 94 1 3 5 1,080 466,560 460,000 58,480 JPY 233 VND Combined JPY 96 96 13,800,000 1,840,000,000 440,033,000 2,447,000 6,826,000 28,914,000 202,233,000 48,726,000 57,500,000 221,000 221,000 59,000 7,897,000 1,889,000 13,000 80,000 321,000 29,617,000 639,000 100,000 247,000 1,000 1,000 184,700 10,000 26,000 18,000 7,000 56,000 56,000 56,000 121,000 80,000 26,000 18,000 7,000 56,000 56,000 56,000 121,000 121,000 121,000 80,000 67,000 2,684,000 27,000 27,000 121,000 5,000 16,000 176,000 14,000 49,000 2,161 51,000 197,000 28,749,000 430,000 100,000 m m3 m3 m3 m3 m3 m3 t No. m m3 m2 8,080 1,555 29 59 1,116 82 475 201 3,000 21,000 7,000 4,000 23,000 23,000 23,000 90,000 1,650,000 1,158,000 2,598,000 700,000 7,732,000 7,732,000 7,732,000 7,211,000 1,500 51,000 6,826,000 m3 m3 m3 m3 m3 m3 t t t m No. No. m3 m3 t m m m m m No. 24,277 1,016 2,033 16,800 19,404 7,137 2,016 2,329 856 50,250 1,260 630 1,408 9,317 3,186 2,478 4,956 329 4,977 248 19,694 4,320 1,040 1,875 5,561 69 137 8,620 6,606 1,671 3,234 312 862 991 201 388 37 110 14 1,145 12 4 17,086 2,102 154 291 746 746 746 47 58 76 78,174 71,159 1,941 162 1 1 262 3,600 1,593 184 7,000 20,000 14,000 9,800 4,000 2,100 1,800 6,000 6,000 1 1,850 21,000 60,000 89,000 490,000 43,000 5,950 5,100 17,000 17,000 1 21,000 7,000 4,000 23,000 23,000 23,000 90,000 90,000 90,000 51,000 59,000 960,000 10,000 10,000 90,000 1,158,000 2,598,000 700,000 7,732,000 7,732,000 7,732,000 7,211,000 7,211,000 7,211,000 6,826,000 1,888,000 401,746,000 3,870,000 3,870,000 7,211,000 800 3,000 162,000 13,000 47,000 353,000 149,000 51,000 21,000 7,000 4,000 41,000 52,000 23,000 23,000 23,000 134,000 134,000 134,000 134,000 134,000 396,000 811,000 851,000 5,246,000 2,012,000 41,000 134,000 396,000 811,000 2,000 800 3,000 1,813,000 316,000 13,000 47,000 887,000 3,068,000 3,367,000 222,000 456,000 376,285 30,806,000 20,513,000 6,826,000 1,158,000 2,598,000 700,000 5,743,000 7,320,000 7,732,000 7,732,000 7,732,000 3,150,000 3,150,000 3,150,000 3,150,000 3,150,000 13,429,000 16,437,000 8,140,000 38,412,000 14,707,000 5,034,000 3,150,000 13,429,000 16,437,000 434,000 887,000 3,068,000 12,896,000 47,075,000 222,000 456,000 200 200 287,000 30,727,000 24,790,000 278,000 259,000 2,020,000 159,019,000 174,395,000 485,000 237,000 80,000 26,000 18,000 7,000 66,000 83,000 56,000 56,000 56,000 148,000 148,000 148,000 148,000 148,000 454,000 882,000 886,000 5,411,000 2,075,000 63,000 148,000 454,000 882,000 4,000 5,000 16,000 1,868,000 518,000 14,000 49,000 2,642 1,000 1,000 296,000 31,409,000 25,538,000 70 10,000 90,000 4,000 144 43 41 184 182 119 122 67 144,000 3,870,000 7,211,000 2,063,000 331,000 99,000 5,000 380,000 420,000 274,000 280,000 152,000 688 26,609 120,948 12,854 1,565 468 62 1,815 1,985 1,295 1,324 719 70 144 43 41 184 182 119 122 67 144,000 331,000 99,000 5,000 380,000 420,000 274,000 280,000 152,000 688 1,565 468 62 1,815 1,985 1,295 1,324 719 m m m m3 m3 m3 m3 m3 m3 m3 m3 t t t t t t t t No. No. m3 t t t m m m m t m No. m2 m2 No. LS LS m m3 m3 t m m3 m2 m m3 m3 m3 m2 m2 LS m m3 m3 m2 m m3 m3 m3 m2 m2 LS Amount Mill. JPY 161 16 7 19 29 1 1 45 44 5,963 24 33 0 0 26 2 11 18 77 510 7 8 386 446 164 181 210 77 2,563 74 605 14 93 287 2 15 53 65 12 5,533 1,525 155 96 117 0 1 353 344 38 74 7 116 133 27 52 5 44 11 974 63 8 701 282 61 236 1 1 2 85 18 4 117 14 0 46 31 25 87 0 16 17 28 3 1 0 1 0 0 1 0 20 61 1 9 4 20 8 1 1 2 1 14 11,920 Mill. VND 458,522 69,000 80,960 19,361 18,377 887 2,718 202 146 62,100 103,110 101,660 1,127,364 13,332 1,800 76 41 8,631 636 3,674 1,449 10,239 28,113 2,640 1,423 129,898 150,032 55,183 14,537 16,791 6,176 343,007 2,379 253,100 5,447 36,056 22,976 2,198 15,204 1,108 1,105 113 437,599 133,082 21,334 12,799 6,440 178 96 49,505 48,359 12,921 25,005 2,412 2,715 3,122 632 1,223 118 1,477 230 9,318 461 59 86,008 6,620 2,065 4,775 324 662 2,289 606 2,730 35 20,945 19,782 503 327 159 174 45,905 518 6,165 1,327 14,441 6,620 1,386 49 1,520 882 493 1,680 912 9,912 80,243 3,024 19,860 8,811 2,450 16,340 2,499 1,397 4,760 2,584 18,518 2,170,577 Combined Mill. JPY 2,129 296 347 83 95 10 30 30 2 1 267 487 480 10,801 81 40 1 0 63 5 27 24 120 630 18 14 944 1,090 401 244 282 104 4,035 85 1,691 37 248 385 11 80 58 69 12 7,411 2,096 247 151 144 1 1 566 551 94 182 18 127 146 30 57 6 50 12 1,014 65 8 1,070 310 70 256 3 3 12 88 30 4 207 99 3 48 31 26 284 2 42 22 90 31 7 1 7 4 2 8 4 62 405 14 94 42 31 78 12 7 23 12 94 21,236 Remarks APPENDIX-6: JBIC Screening Form ( for social and environmental considerations) (JBIC Screening Form) Screening Form Name of Projec t: St udy on Ph uoc An Bri dge Con str uct i on Pr oject on Ca i Mep -Thi Va i Int er Port Roa d Name of Projec t Exec uti on Or ganiz ati on: Departm en t of Tran sport ati on of Ba Ri a -Vun g Ta u Pr ovin ce Peopl es’ Comm it t ee Name of B or rower: Govern m ent of Vi et nam Please provide the name, department, job title, and contact details for the person who is responsible for filling out this form. (Prepared by JETRO Study Team based on the hearing at the Project site) Name: Engineer: Mr. Vu Ngoc Thao Department and title: Communication and Transport Department, Director Name of Company or Organization: Ba Ria-Vung Tau Provincial People’s Committee Telephone number: 84-64-3511769 Fax number: 84-64-3511769 E-Mail address: [email protected] Date: Nov. 29 – Dec. 3, 2010 Signature: Q ue stions 4. Q1. Please provide the address of the project site. Address of the project site: Tan Than district of Ba Ria-Vung Tau Province to Nhon Trach district of Dong Nai Provinve, Vietnam Q2. Please provide brief explanation of the project. Construction of Phuoc An Bridge and approach bridge as a part of Cai Mep-ThiVai Inter-Port Road. Cai Mep-Thi Vai inter-port road connect port system and industrial zones along Cai Mep-Thi Vai river, and it belong to Tan Thanh district, Ba Ria-Vung Tau province and Nhon Trach district, Dong Nai province. The total length of the Inter-Port Road is 21.36094km, and the portion of the project, namely the construction of Phuoc An Bridge and approach bridge is about 3.6km (Km18+100 – Km21+360.94). Q3. Will JBIC loan be applied to a new project or an executing project? In case of an executing project, please inform of strong claims by stakeholders such as local residents, as well as improvement guidance or cessation orders for construction work / operations, from environmental authorities. ☑ New Project □ Executing Project (without Claim etc.) □ Executing Project (with Claim etc.) □ Others(Please specify ) Q4. In case of this project, is it necessary to execute Environmental Impact Assessment (EIA) based on the laws or regulations of the country where the project is to be implemented? If necessary, please inform the progress of EIA. □ Required (completed ) ☑ Required (under planning) □ Not Required □ Others (Please specify ) Q5. In case that EIA is already completed, please inform whether EIA report is already approved based on the environmental assessment system of the country where the project is to be implemented or not. If EIA report is already approved, please provide the date and name of authorities of the approval. □ Approved (without condition) □ Under approval process □ Approved (conditional) ☑ Others (Please specify Not conducted yet) Date of Approval: Name of Authorities: Q6. If environmental permit(s) other than EIA is required, please provide the name of required permit(s). Have you obtained required permit(s)? □ Obtained □ Required, but not obtained yet ☑ Not required □ Others (Please specify) Name(s) of required permit(s): Q7. Will the loan be used for the undertaking that cannot specify the project at this stage (e.g. export or lease of machinery that has no relation with specific project, or Two Step Loan that cannot specify the project at the time of loan agreement)? (Yes / No) If you answered “Yes”, it is not necessary to reply to the following questions. If you answered “No”, please reply to the following questions. Q8. Are there any environmentally sensitive area shown below in and around project site? (Yes / No) If you answered “Yes”, please select applicable items by marking, and reply to following questions. If you answered “No”, please reply to questions 9 and after. ☑ (1) National parks, protected areas designated by government (coastal areas, wetlands, habitats of minorities or indigenous populations, heritage sites, etc.) (2) Primeval forests, tropical natural forests (3) Ecologically important habitats (coral reefs, mangrove, tidal flats, etc.) (4) Habitats of endangered species of which protection is required under local laws and international agreements. (5) Areas that have risks of large scale increase in soil salinity or soil erosion (6) Desertification areas (7) Areas with special values from archaeological, historical and/or cultural viewpoints (8) Habitats of minorities, indigenous populations, nomadic people with traditional life style, or areas with special social value Q9. Does the project involve following characteristics? (Yes / No) If you answered “Yes”, please describe the scale of applicable characteristics, and reply to the questions 10 and after. If you answered “No”, please reply to questions 11 and after. (1)Involuntary resettlement (Number of resettlers: (2)Pumping of groundwater (Scale: (3)Land reclamation, development and/or clearing (Scale: (4)Deforestation (Scale: ) m3/year) ha) ha) Q10. Under the environmental impact assessment system of the country where the project is to be implemented, do the applicable characteristics from (1) – (4) above and their scale serve as basis for executing an EIA for the project? □ They do □ Others (Please specify □ They do not ) Q11. Will JBIC share in the project be equal or less than 5% of the total project cost, or the total amount of JBIC loan equal or less than SDR 10 million? (In the case of additional support for a past project, this shall be the accumulated total amount) (Yes / No) If you answered “Yes”, it is not necessary to reply to the following questions. If you answered “No”, please reply to questions 12 and after. Q12. Does the project belong to either of the sectors that impact on the environment is deemed immaterial or is not anticipated under normal conditions (e.g. maintenance of the existing facilities, non-expansionary renovation project, acquisition of rights and interests without additional capital investment)? (Yes / No) If you answered “Yes”, it is not necessary to reply to following questions. If you answered “No”, please reply to the questions 13 and after. Q13. Does the project belong to the following sectors? (Yes / No) If you answered “Yes”, please specify the sector by marking, and reply to questions 14 and after. If you answered “No”, it is not necessary to reply to the following questions. (1) (2) (3) (4) (5) (6) (7) (8) Mining Oil and natural gas development Pipelines Iron and steel (projects that include large furnaces) Non-ferrous metals smelting and refining Petrochemicals (manufacture of raw materials; including complexes) Petroleum refining Oil, gas and chemical terminals (9) Paper and pulp (10) Manufacture and transport of toxic or poisonous substances regulated by international treaties, etc. Thermal power Nuclear power Hydropower, dams and reservoirs Power transmission and distribution lines involving large-scale involuntary resettlement, large-scale logging or submarine electrical cables ☑ (15) Roads, railways and bridges (16) Airports (17) Ports and harbors (18) Sewage and wastewater treatment having sensitive characteristics or located in sensitive areas or their vicinity (19) Waste management and disposal (20) Agriculture involving large-scale land-clearing or irrigation (21) Forestry (22) Tourism (construction of hotels, etc.) (11) (12) (13) (14) Q14. Please provide information on the scale of the project (project area, area of plants and buildings, production capacity, amounts of power generation, etc.) Further, pleased explain whether an execution of EIA is required on account of the large scale of the project in the country where the project is implemented. Outline: ■ Phuoc An Bridge pass over the Thi Vai River and connects Tan Thanh district of Ba Ria-Vung Tau Province and Nhon Trach district of Dong Nai Province. ■ Main Bridge: Prestressed concrete Cable-stayed Bridge (Center span = 360m) ■ Approach Bridge: Super-T Girder (Span lengths vary from 25 to 40m) ■ Total length = 3,254.5m (including abutments) ■ Total bridge width: 23.5m ■ Navigation clearance at the Center Span of the Main Bridge: Clearance = 239m (W) x 55m ■ EIA is required APPENDIX-7: Data for Geological/Topographic Conditions 0.22 Ly tr nh C6 6 4 Km15+649 Km15+721 C5 72.0 So hie u ho khoan 65.0 -63.04 N>30 52.5 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N=13 33.0 N=10 N=17 N=17 N=16 N=14 N=13 N=16 N=12 N=10 N=8 N=12 N=1 9.0 N=1 N=1 N=1 0.00 1.5 58.0 58.5 -56.28 N>30 N>30 N>30 -50.78 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N>30 -31.28 N=13 32.2 N=10 N=17 N=17 N=16 N=14 N=13 N=16 N=12 15.5 N=10 N=8 11.5 N=12 N=1 9.5-7.28 N=1 N=1 N=1 0.00 +1.72 -56.54 -30.24 2 -13.54 -9.54 -7.54 +1.96 Khoa ng ca ch HK(m) -75.00 -70.00 -65.00 -60.00 -55.00 -50.00 -45.00 -40.00 -35.00 -30.00 -25.00 -20.00 -15.00 -10.00 -5.00 +0.00 +5.00 3 542.0 1 D11 15.0 N=10 N=7 10.2 N=5 N=2 N=1 N=1 N=1 0.00 Km16+263 Fine Sand -15.69 -10.89 -0.69 1 377.0 9.5 C7 50.0 40.0 N>30 N>30 N>30 N>30 N>30 N=28 29.0 N=15 N=13 N=14 N=12 N=8 N=11 N=8 N=10 N=9 N=8 N=1 N=1 N=1 N=1 0.00 1.5 Km16+640 -49.62 -39.92 -28.62 -9.12 +0.38 -1.12 6 4 242.0 3 1 15.5 2 C8 50.0 39.0 N>30 N>30 N>30 31.5 N>30 N=25 N=14 N=16 N=12 N=13 21.0 N=8 N=7 N=8 N=11 N=10 N=7 9.0 N=2 N=1 N=1 N=1 0.00 Km16+882 -52.66 -41.66 -34.16 -23.66 -18.16 -11.66 -2.66 389.0 1 N=7 D12 33.0 N=21 N=19 N=18 N=17 N=17 N=15 N=12 19.5 N=5 14.5 N=1 N=1 N=1 N=1 N=1 N=1 0.00 Km17+271 -32.6 -19.1 -14.1 +0.40 569.0 1 D13 30.0 N=12 27.0 N=9 N=3 N=3 N=2 N=2 N=2 N=2 N=2 N=1 N=1 N=1 N=1 N=1 N=1 0.00 Km17+840 -29.52 -26.52 -0.77 421.0 1 -26.70 D14 25.0 N=5 N=4 20.8 N=2 N=2 N=2 N=2 N=1 N=1 N=1 N=1 N=1 N=1 0.00 Km18+261 4 -21.50 -1.70 1 1354.0 1 5 4 2 C9 65.0 60.5 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N>30 N=26 39.5 N=26 N=18 N=16 33.0 N=4 N=4 N=4 N=3 N=2 N=2 N=2 N=2 N=1 N=1 N=1 N=1 N=1 N=1 N=1 N=1 0.00 Km19+615 -65.40 -60.90 -39.90 -33.40 -0.40 Clay with Gravel Hard Clay Clay Loam Clay Mud 架橋位置 tha ng Ks. Buøi nh Ha i P. Gia m o c Vu ng Taøu , Ngaøy PRO_ENG. Phuøng H KCS KS- Tr nh Va n Ta ng u The i gia Ranh gi Ks- Ong Hie n Taøi i xa c Ranh gi Ks- Tra n Phi Huøng A CN i gia Ranh gi na m 2009 nh nh nh ac pPha - m i: o sa u a y l p p-m LE HIE U BA N VE TY KY SO PHU LU C: 3 BA N VE A CHA T A CHA T MC 2009 NG : 1/500 NGANG : 1/5000 MA T CA T KHA O SA T 1/1 So hie u ma u Tr so SPT N30 o sa u ma u 25.0 Chie u sa u ho khoan - m C1-1 N=1 1.5-2.0 a yl So hie u l 0.00 (Cao o mie ng ho khoan) ng e n Tra i: cao o a phong ho a ma nh maøu xa m xanh, n t ne , khe n t k n, ca u ta o kho i, o c ng ca p IV - VI TP. TN-K C HIE N TH 6 Se t maøu xa m xanh, sa n pha m a phong ho a ma nh ch a hoaøn toaøn, o i cho la n da m vaø cuo i. Se t maøu xa m tra ng, xa m vaøng, n c ng. 4 5 Ca t nho e n trung maøu xa m tra ng, xa m vaøng, cha t v øa. 3 a Se t pha maøu xa m tra ng, de o c c ng. 2 ng e n n Buøn se t maøu xa m xanh, xa m en. C 1 DA U HIE U QUY H NH TRU HO KHOAN C9 Te n co ng tr nh: ØNG LIE N CA NG CA I ME P - TH VA I øng k nh ho khoan: a ie m: Huye n Ta n Thaønh - Tænh BR - VT V tr ho khoan: Km19+615.0 (pha i tuye n 7.5m) M cn Cao o mie ng ho khoan: -0.40m Ngaøy ba t a u: 29/05/2009 Khoan ma y Ngaøy ke t thu c: 31/05/2009 o Th c sa u ty a y le l p (m) (m) Cao Be o a y daøy l p l p (m) (m) Khoan tay Co t Mo ta a ta ng a ta ng Ma u th nghie m Ky So hie u hie u o sa u a ma u ma u (m) ta ng c nga m: 0.0m Ke t qua th nghie m xuye n tie u chua n (SPT) o sa u SPT(m) So bu a/ 15cm Gia tr 15cm15cm15cm N30 01 02 C9-1 1.5 - 2.0 2.0 - 2.45 <1 <1 1 1 C9-2 3.5 - 4.0 4.0 - 4.45 <1 <1 1 1 C9-3 5.5 - 6.0 6.0 - 6.45 <1 <1 1 1 C9-4 7.5 - 8.0 8.0 - 8.45 <1 <1 1 1 C9-5 9.5 - 10.0 10.0 - 10.45 <1 <1 1 1 C9-6 11.5 - 12.0 12.0 - 12.45 <1 <1 1 1 C9-7 13.5 - 14.0 14.0 - 14.45 <1 <1 1 1 C9-8 15.5 - 16.0 16.0 - 16.45 <1 <1 1 1 C9-9 17.5 - 18.0 18.0 - 18.45 0 1 1 2 C9-10 19.5 - 20.0 20.0 - 20.45 1 1 1 2 C9-11 21.8 - 22.0 22.0 - 22.45 0 1 1 2 03 04 05 06 07 08 09 10 33.0 Buøn se t maøu xa m xanh, xa m en. 11 12 13 14 15 16 17 18 19 20 21 22 110mm o th th nghie m SPT 10 20 30 40 50 H NH TRU HO KHOAN C9 Te n co ng tr nh: ØNG LIE N CA NG CA I ME P - TH VA I øng k nh ho khoan: a ie m: Huye n Ta n Thaønh - Tænh BR - VT V tr ho khoan: Km19+615.0 (pha i tuye n 7.5m) M cn Cao o mie ng ho khoan: -0.40m Ngaøy ba t a u: 29/05/2009 Khoan ma y Ngaøy ke t thu c: 31/05/2009 o Th c sa u ty a y le l p (m) (m) Cao Be o a y daøy l p l p (m) (m) Khoan tay Co t Mo ta a ta ng a ta ng Ma u th nghie m Ky So hie u hie u o sa u a ma u ma u (m) ta ng o sa u SPT(m) c nga m: 0.0m Ke t qua th nghie m xuye n tie u chua n (SPT) So bu a/ 15cm Gia tr 15cm15cm15cm N30 23 Buøn se t maøu xa m xanh, xa m en. 24 C9-12 23.5 - 24.0 24.0 - 24.45 1 1 1 2 C9-13 25.5 - 26.0 26.0 - 26.45 1 1 2 3 C9-14 27.5 - 28.0 28.0 - 28.45 1 2 2 4 C9-15 29.5 - 30.0 30.0 - 30.45 1 2 2 4 C9-16 31.5 - 32.0 32.0 - 32.45 1 2 2 4 C9-17 33.8 - 34.0 34.0 - 34.45 5 7 9 16 C9-18 35.8 - 36.0 36.0 - 36.45 6 8 10 18 C9-19 37.8 - 38.0 38.0 - 38.45 5 11 15 26 C9-20 39.8 - 40.0 40.0 - 40.45 6 10 16 26 C9-21 41.8 - 42.0 42.0 - 42.45 7 14 20 >30 C9-22 43.8 - 44.0 44.0 - 44.45 16 26 25 26 27 33.0 28 o sa u 27.0-33.0m, se t maøu xa m xanh, tra ng tha i de o cha y 29 30 31 32 33 33.0 -33.4 34 35 36 6.5 Se t pha maøu xa m na u, xa m en, n a c ng. 37 38 39 39.5 -39.9 40 41 42 21.0 Se t maøu xa m vaøng, na u o , tra ng tha i n a c ng 43 44 110mm 5/ 3cm >30 o th th nghie m SPT 10 20 30 40 50 H NH TRU HO KHOAN C9 Te n co ng tr nh: ØNG LIE N CA NG CA I ME P - TH VA I øng k nh ho khoan: a ie m: Huye n Ta n Thaønh - Tænh BR - VT V tr ho khoan: Km19+615.0 (pha i tuye n 7.5m) M cn Cao o mie ng ho khoan: -0.40m Ngaøy ba t a u: 29/05/2009 Khoan ma y Ngaøy ke t thu c: 31/05/2009 o Th c sa u ty a y le l p (m) (m) Cao Be o a y daøy l p l p (m) (m) Khoan tay Co t Mo ta a ta ng a ta ng Ma u th nghie m Ky So hie u hie u o sa u a ma u ma u (m) ta ng o sa u SPT(m) So bu a/ 15cm Gia tr 15cm15cm15cm N30 C9-23 45.8 - 46.0 46.0 - 46.45 14 46 21 10/ >30 10cm 47 C9-24 47.8 - 48.0 48.0 - 48.45 15 48 24 7/ >30 6cm 49 C9-25 49.8 - 50.0 50.0 - 50.45 18 50 22 9/ >30 4cm 51 21.0 52 Se t maøu xa m vaøng, na u o , tra ng tha i n a c ng C9-26 51.8 - 52.0 52.0 - 52.45 17 24 7/ >30 3cm 53 C9-27 53.8 - 54.0 52.0 - 52.45 20 54 29 2/ >30 1cm 55 C9-28 55.8 - 56.0 52.0 - 52.45 18 56 28 3/ >30 2cm 57 C9-29 57.8 - 58.0 52.0 - 52.45 20 58 26 5/ >30 3cm 59 C9-30 59.8 - 60.0 52.0 - 52.45 18 60 61 62 4.5 63 64 66 65.0 -65.4 27 4/ 1cm 60.5 -60.9 T ø o sa u 60.5m tr xuo ng Se t maøu xa m xanh tra ng tha i c ng, sa n pha m a phong ho a ma nh ch a hoaøn toaøn, o i cho la n da m vaø cuo i. C9-31 61.5 - 62.0 C9-32 64.5 - 65.0 c nga m: 0.0m Ke t qua th nghie m xuye n tie u chua n (SPT) 45 65 110mm >30 o th th nghie m SPT 10 20 30 40 50 Lab. No. 1 Sample No. 3 Borehole No. 2 Töø (m) 4 Ñeán (m) 5 6 >20 C9 - 6 C9 - 8 C9 C9 C9 C9 242 253 2709 243 C9 - 9 C9 C9 C9 C9 C9 C9 C9 245 254 234 246 247 0.0 0.0 0.0 0.1 0.0 C9 C9 C9 249 250 251 C9 - 20 C9 - 19 C9 - 18 C9 - 17 1.5 5.7 C9 C9 C9 C9 C9 C9 C9 C9 C9 255 256 257 258 259 260 261 262 263 C9 - 30 C9 - 29 C9 - 28 C9 - 27 C9 - 26 C9 - 25 C9 - 24 C9 - 23 C9 - 22 C9 - 21 1.8 3.2 1.0 39.9 40.5 9.6 5.7 7.6 2.5 36.8 30.4 30.1 25.83 20.25 18.89 22.42 32.02 31.39 31.02 32.31 29.86 32.51 0.04 0.07 1.929 1.924 1.915 1.952 1.903 1.914 1.910 1.884 1.896 1.850 1.930 0.03 0.08 30.22 0.06 1.924 2.028 1.909 1.927 2.14 26.00 22.85 28.45 26.33 1.820 0.03 0.11 38.79 0.0 1.500 1.554 1.547 1.570 1.530 1.510 1.530 1.520 1.479 1.451 1.540 1.520 1.408 1.433 1.465 1.413 19 Wet unit weight (g/cm³) 8.9 78.33 69.12 0.14 1.8 2.9 1.9 30.3 31.8 31.8 32.4 32.3 33.4 30.5 32.2 21.4 27.7 21.9 25.7 18.3 49.1 52.4 61.0 Heä soá bieán ñoåi 0.8 9.2 5.3 6.8 4.9 9.9 4.9 3.5 6.3 3.4 3.9 6.8 5.4 6.4 6.4 5.4 6.0 3.0 1.5 3.68 1.2 3.7 36.8 11.2 15.8 9.9 11.2 6.9 10.1 10.7 6.9 14.5 16.2 17.8 14.2 13.7 6.9 3.5 2.0 74.04 Ñoä leäch chuaån 2.4 2.1 1.0 2.0 1.7 59.8 - 60.0 8.6 5.0 4.9 4.7 57.8 - 58.0 1.6 47.8 0.9 0.3 55.8 - 56.0 1.3 47.5 3.3 53.8 - 54.0 1.0 48.5 0.7 51.8 - 52.0 0.2 46.1 0.3 49.8 - 50.0 46.5 57.4 0.6 47.8 - 48.0 0.7 0.8 45.8 - 46.0 0.4 52.7 1.2 56.9 34.6 1.0 0.9 17.5 43.8 - 44.0 0.7 5.5 36.8 18.9 41.8 - 42.0 Trò Trung Bình C9 252 Lôùp 4: Seùùt xaùm traéng, xaùm vaøng, xaùm xanh, nöûa cöùng ñeán cöùng Heä soá bieán ñoåi Ñoä leäch chuaån 2.9 9.8 35.6 50.6 6.0 6.9 53.9 0.6 0.7 37.3 41.0 35.5 39.8 - 40.0 0.4 35.8 - 36.0 0.4 0.0 0.0 37.8 - 38.0 0.5 33.8 - 34.0 Trò Trung Bình C9 248 0.1 0.0 0.0 41.4 0.0 Lôùp 2: Seùùt pha xaùm traéng, xaùm vaøng, deûo cöùng ñeán nöûa cöùng. Heä soá bieán ñoåi Ñoä leäch chuaån 0.0 4.0 81.85 73.34 0.0 5.5 56.5 0.0 49.1 2.0 31.5 - 32.0 0.0 3.5 29.5 - 30.0 0.0 38.0 71.90 67.70 0.0 0.0 72.0 61.6 27.5 - 28.0 0.0 0.0 1.5 10.5 0.0 0.0 8.8 2.5 25.5 - 26.0 0.0 7.3 34.3 0.0 1.4 0.0 71.62 23.5 - 24.0 0.0 0.0 61.1 75.62 0.0 0.0 1.0 70.30 73.34 79.15 0.0 0.0 1.5 64.7 41.4 0.0 36.4 6.0 10.5 0.0 0.0 6.0 18.2 21.5 - 22.0 0.0 6.6 46.6 19.5 - 20.0 0.0 0.0 0.0 17.5 - 18.0 0.0 0.0 0.0 50.8 0.0 0.0 0.0 0.8 89.41 15.5 - 16.0 0.0 0.0 1.5 30.4 18 105.68 0.0 46.9 3.0 17 41.5 0.0 0.0 5.2 16 2.5 13.5 - 14.0 0.0 61.3 15 6.5 11.5 - 12.0 0.0 0.0 49.4 14 0.05 - 0.1 88.89 0.0 0.0 13 0.1 - 0.25 0.0 0.01 -0.05 0.0 0.0 12 0.25 - 0.5 0.0 <0.005 9.5 - 10.0 0.0 11 0.5 - 1.0 0.0 0.005 - 0.01 88.12 0.0 10 1.0 - 2.0 0.0 Clay (%) Water content (%) 5.5 - 6.0 3.5 - 4.0 9 0.0 8 10.0 - 20.0 7 2.0 - 5.0 1.5 - 2.0 Trò Trung Bình C9 - 16 C9 - 15 C9 - 14 C9 - 13 C9 - 12 C9 - 11 C9 - 10 C9 244 C9 - 7 C9 - 3 2710 233 C9 - 5 C9 232 C9 - 2 C9 240 C9 - 1 C9 239 Lôùp 1: Buøn seùt xaùm xanh, xaùm ñen. Silt (%) 20 Dry unit weight (g/cm³) 1.533 1.600 1.610 1.590 1.440 1.460 1.460 1.420 1.460 1.400 1.480 1.527 1.650 1.490 1.530 1.310 0.841 0.920 0.890 0.940 0.880 0.830 0.890 0.870 0.830 0.850 0.900 0.880 0.750 0.760 0.770 0.690 21 Specific Gravity 0.01 0.02 2.713 2.715 2.710 2.720 2.710 2.710 2.710 2.710 2.712 2.710 2.715 0.00 0.01 2.698 2.723 2.705 2.694 2.690 0.01 0.0 2.624 2.630 2.630 2.660 2.630 2.630 2.620 2.620 2.650 2.620 2.630 2.630 2.620 2.630 2.620 2.620 22 Initial void ratio 0.770 0.697 0.682 0.706 0.880 0.860 0.859 0.903 0.857 0.941 0.832 0.767 0.649 0.820 0.766 1.051 2.120 1.862 1.947 1.840 1.992 2.167 1.944 2.027 2.210 2.098 1.908 1.999 2.515 2.453 2.387 2.814 Porosity (%) 44 41 41 42 47 46 46 48 46 48 45 43 39 45 43 51 68 65 66 67 68 66 67 68 66 67 71 71 74 23 Degree of saturation (%) 92 79 75 86 99 99 98 97 94 94 99 91 96 94 93 99 97 98 99 98 98 99 97 98 95 89 97 96 93 94 98 98 24 25 Haïn ñoä chaûy - LL (%) 0.14 6.36 46.3 39.57 52.41 54.15 55.54 55.49 38.0 40.81 38.2 0.08 5.7 69.7 72.8 74.7 72.4 69.2 70.8 76.7 68.6 26 Haïn ñoä deûo - PL (%) 0.15 3.44 22.9 17.92 25.25 23.55 26.54 25.21 23.2 25 22.52 0.13 4.5 35.3 33.4 35.2 40.2 34.4 39.5 42.1 36.8 27 Chæ soá deûo - PI (%) 23.4 21.65 27.16 30.6 29 30.28 14.8 15.81 15.68 34.4 39.49 39.55 32.2 34.75 31.3 34.65 31.79 28 Ñoä seät 0.13 0.21 0.23 0.21 0.21 0.17 0.19 0.22 0.24 1.25 0.87 1.18 0.98 1.29 0.98 1.35 2.17 29 0.125 kG/cm² 0.096 0.096 30 0.25 kG/cm² 0.100 0.1075 0.1075 31 0.50 kG/cm² 0.26 0.0 0.076 0.096 0.0806 0.20 0.0 0.088 0.1075 0.18 0.0 0.099 0.121 0.121 0.0902 0.1037 0.071 0.1037 0.1094 0.073 0.060 0.0672 0.0768 0.0864 0.0634 0.0749 0.0864 0.0768 0.0922 0.1056 0.0768 0.0883 0.0845 0.0845 1.00 kG/cm² 2.00 kG/cm² 33 34 3.00 kG/cm² 0.710 1.344 0.960 0.03 0.02 0.691 0.15 0.16 1.106 0.768 0.960 1.0176 0.960 1.248 0.17 0.10 0.622 0.768 0.864 0.960 0.18 0.17 0.951 1.248 0.19 0.24 1.279 1.728 1.3632 1.8624 1.4784 1.9968 0.5184 0.7872 1.0752 0.5376 0.8064 1.0752 0.6528 0.5568 0.8352 1.1328 0.5568 0.7488 0.5376 0.7488 1.0368 1.3056 0.19 0.10 0.530 0.8064 1.0752 1.3248 0.8448 1.0944 0.480 0.4608 0.6912 0.9216 32 35 ñoä 0.230 0.066 0.083 0.094 0.200 0.550 0.352 18°12' 25°38' 0.293 0.288 26°32' 0.3648 27°24' 0.4416 15°33' 0.2368 15°03' 0.2688 16°34' 0.3584 16°04' 0.2656 11°24' 13°30' 0.2944 0.11 0.2 2.030 1.835 1.918 0.0582 1.933 15°33' 0.4736 16°04' 1.997 2.066 0.0493 2.112 0.058 0.052 14°01' 0.5952 14°32' 2.434 2.292 2.665 38 0.125 kG/cm² 0.0627 1.935 0.065 0.065 0.073 36 C kG/cm 2 13°30' 0.2368 12°58' 2°35' 2°51' 1°59' 3o31' 2°25' 2°12' 2°38' 3o18' 2°38' 2°25' 2°38' Löïc dính keát Heä soá roãng (öùng vôùi töøng caáp taûi troïng) 39 0.25 kG/cm² 0.19 0.13 0.707 0.13 0.2 1.939 1.815 1.896 1.890 2.069 1.971 2.036 1.876 2.366 2.214 2.557 40 0.50 kG/cm² 0.15 0.12 0.751 0.673 0.656 0.686 0.858 0.840 0.839 0.859 0.832 0.907 0.800 0.19 0.14 0.724 0.633 0.763 0.731 0.988 0.14 0.3 1.818 1.781 1.860 1.824 2.015 1.927 1.987 1.777 2.253 2.083 2.385 41 1.00 kG/cm² 0.15 0.11 0.730 0.657 0.640 0.671 0.836 0.822 0.823 0.831 0.810 0.880 0.775 0.20 0.13 0.687 0.623 0.737 0.700 0.929 0.15 0.3 1.667 1.722 1.797 1.713 1.931 1.847 1.900 1.624 2.067 1.882 2.133 42 2.00 kG/cm² 0.15 0.11 0.703 0.639 0.619 0.644 0.798 0.793 0.793 0.786 0.769 0.842 0.740 0.19 0.12 0.643 0.604 0.700 0.651 0.836 0.18 0.3 1.461 1.613 1.684 1.526 1.789 1.705 1.750 1.381 1.759 1.582 1.838 4.00 kG/cm² 0.18 0.12 0.669 0.595 0.581 0.605 0.733 0.744 0.739 0.717 0.698 0.781 0.680 0.17 0.10 0.585 0.571 0.649 0.577 0.706 43 8.00 kG/cm² 0.17 0.10 0.597 0.531 0.513 0.538 0.624 0.663 0.643 0.615 0.576 0.681 0.576 0.09 0.04 0.514 0.513 0.569 0.461 0.512 44 1.002 0.218 0.236 0.467 0.443 0.242 0.260 0.516 0.647 0.759 1.190 45 0.125 kG/cm² Heä soá neùn luùn a (cm²/kG) (öùng vôùi töøng caáp taûi troïng) THÍ NGHIEÄM NEÙN 0.129 0.732 0.160 0.177 0.347 0.342 0.206 0.235 0.468 0.548 0.623 0.870 46 0.25 kG/cm² ÖÙng suaát caét (kG/cm²) (öùng vôùi töøng caáp taûi troïng) Goùc ma saùt trong 0.064 0.049 0.052 0.039 0.045 0.041 0.039 0.088 0.050 0.068 0.064 0.099 0.031 0.115 0.071 0.127 0.453 0.137 0.141 0.263 0.215 0.176 0.198 0.396 0.450 0.522 0.687 47 0.50 kG/cm² THÍ NGHIEÄM CAÉT 0.042 0.032 0.032 0.031 0.043 0.035 0.033 0.055 0.045 0.054 0.049 0.073 0.021 0.053 0.062 0.117 0.316 0.117 0.127 0.221 0.168 0.160 0.174 0.306 0.373 0.403 0.503 48 1.00 kG/cm² Sand (%) 0.029 0.018 0.021 0.027 0.038 0.029 0.030 0.046 0.041 0.038 0.035 0.044 0.019 0.036 0.049 0.093 0.206 0.109 0.113 0.187 0.143 0.142 0.150 0.243 0.308 0.300 0.296 49 2.00 kG/cm² ÑOAÏN VII - VIII ( Lyù Trình: Km 15 + 649 -:- Km 19 + 615 ) 0.021 0.022 0.019 0.020 0.033 0.025 0.027 0.034 0.036 0.031 0.030 0.029 0.016 0.025 0.037 0.065 50 8.00 kG/cm² 0.015 0.016 0.017 0.017 0.027 0.020 0.024 0.026 0.030 0.025 0.026 0.028 0.014 0.020 0.029 0.048 51 58.9 75.7 85.6 83.8 54.7 72.8 66.5 52.1 49.5 60.3 57.6 37.7 97.3 66.7 44.5 28.2 12.4 23.7 22.6 12.8 18.0 18.2 17.2 9.1 8.7 7.7 6.7 52 P c (kG/cm²) 0.93 0.44 0.31 53 Consolidation test 55 56 57 58 Mv (cm2/kG) 0.794 0.074 0.085 0.036 0.047 0.884 0.117 0.149 0.154 0.121 0.827 0.193 0.106 0.099 0.112 54 Cc Atterberg limits CR TÍNH CHAÁT VAÄT LYÙ 4.00 kG/cm² Gravel (%) 5.0 - 10.0 MODUN TOÅNG BIEÁN DAÏNG E 1 -2 ( kG/cm²) 2 -3 Particle size distribution (mm) Cv x 10 (cm /kG) Depth (m) kv x 10 -7 (cm/s) Coâng trình: DÖÏ AÙN ÑAÀU TÖ XAÂY DÖÏNG COÂNG TRÌNH ÑÖÔØNG LIEÂN CAÛNG CAÙI MEÙP - THÒ VAÛI C u (kG/cm²) 0.19 59 C u' (kG/cm²) 0.17 60 CU Triaxial test 62 13°15' 15°50' 61 φu (Ñoä - Deg) BAÛNG TOÅNG HÔÏP KEÁT QUAÛ THÍ NGHIEÄM ÑAÁT TRONG PHOØNG φu' (Ñoä - Deg) COÂNG TY CP TÖ VAÁN ÑAÀU TÖ XD GIAO T HOÂNG TÆNH BAØ RÒA VUÕNG TAØU PHOØNG TN - KÑ LAS XD - 208 SOÁ:……… ………/KQTN C u (kG/cm²) 0.21 63 UU 0°56' 64 φu (Ñoä - Deg)