RECAPP Facility Evaluation Report Edmonton School District No. 7 Ottewell Junior High School B3239A Edmonton Report run on: March 31, 2010 10:18 AM Edmonton - Ottewell Junior High School (B3239A) Facility Details Building Name: Ottewell Junior High School Address: 9435 - 73 Street Location: Edmonton Building Id: Gross Area (sq. m): Replacement Cost: Construction Year: B3239A 6,686.90 $17,817,397 1960 Evaluation Details Evaluation Company: Francis Ng Architect Ltd. Evaluation Date: June 16 2009 Evaluator Name: Francis Ng Total Maintenance Events Next 5 years: 5 year Facility Condition Index (FCI): $1,448,013 8.13% General Summary: This school for Grades 7 through 9 was originally built in Edmonton in 1960. The school faces four streets - 94B Avenue on the North, Ottewell Road on the East, 94 Avenue on the South and 73 Street on the West. It is under the jurisdiction of Edmonton School District No. 7. The current student enrollment is 766. The original 5,270.60 square metres school was built in 1960. An addition of 1,416.30 square metres was built in 1973. Total building area is 6,686.90 square metres. Major renovations / upgrading completed in the past includes, fire code upgrading (1992), new Computer Rooms (1994), Library upgrading (1994), new corridor flooring (1998) and complete re-roofing (1999 and 2001). Both 1960 Original Building and the 1973 Addition were modernized in 2003. Room No. Indicated in this report is based on the Edmonton School Board Plans. ABC Group A Division 2 - School. The 1960 Original Building is a single storey. The 1973 Addition is a single storey. Both 1960 Original Building and 1973 Addition have non-combustible and combustible construction and are sprinklered. Structural Summary: (1960) Original Building has wood deck on wood joists on glulam beams on steel columns on concrete foundation on concrete piles; crawl space; concrete slab on grade. (1973) Addition has metal deck on open web steel joists on load bearing concrete block on concrete grade beams on concrete piles; concrete slab on grade. Recommendations for future action: repair concrete slab in one classroom. Overall structural system rating is 4 (acceptable). Envelope Summary: (1960) Original Building has SBS roofing; horizontal metal siding fascia, concrete blocks, PVC windows, steel framed storefronts, metal siding fascia, painted plywood soffit, metal doors. (1973) Addition has SBS roofing and built-up roofing; striated and standard concrete blocks, PVC windows, metal siding fascia, painted plywood soffit, metal doors. Recommendations for future action include: replace broken window glass; repair concrete block, replace Boiler windows; repaint plywood window header and soffit; repair brick chimney; replace 1973 Northwest doors. Overall envelope system rating is acceptable. Interior Summary: (1960) Original Building has concrete blocks interior partitions; fibrous ceiling tiles and wood strip flooring in Gymnasiums; fibrous ceiling tiles and wood strip flooring in Stage; fibrous ceiling tiles and vinyl tile flooring in Classrooms; suspended T-bar ceiling and sheet vinyl flooring in Corridors; drywall ceiling and ceramic wall tiles and mosaic flooring in Washrooms; plaster ceiling and concrete floor in Boiler Room; fibrous ceiling tiles and wood parquet flooring in Industrial Arts; fibrous ceiling tiles and carpet in Administration area; whiteboards, tackboards, Chalkboards, smart boards and projection screens in Classrooms. (1973) Addition has interior prefinished gypsum board wood stud partitions in offices; open metal deck and OWSJ in Industrial Arts, Music Room, Exercise Room; suspended T-bar ceiling system and carpet in Library and Music Room; suspended T-bar ceiling, and vinyl tiles in Science Rooms; whiteboards, tackboards, chalkboards and projection screens in Classrooms; wood doors and metal frames. Report run on: March 31, 2010 10:18 AM Page 2 of 48 Edmonton - Ottewell Junior High School (B3239A) Recommendations for future action include: provide fire stopping material to wall penetration area; repair concrete blocks; repair wood floor in Stage; remove VAT and replace with sheet vinyl; replace fibrous ceiling tiles; replace millwork; provide handicapped platform. Overall interior system rating is 4 (acceptable). Mechanical Summary: The four ventilation systems were upgraded in 2004 and are in good condition. The heating system upgraded to hot water in 2006. Minor recommended upgrades include upgrading of plumbing fixtures. Overall rating is acceptable (4). Electrical Summary: The school was modernized in 2004. A 1200A, 120/208V, 3 phase, 4 wire service has been provided and is obtained from a pad mounted transformer. All lighting is fluorescent and is of the energy efficient type with T8 lamps and electronic ballasts. The fire alarm system is of the addressable type and is the product of Simplex, Model 4100U. Call system is the product of Bogen and is complete with telephones in each classroom. Overall, the electrical systems are in good condition. Condition Rating 1 - Critical 2 - Poor 3 - Marginal 4 - Acceptable 5 - Good 6 - Excellent Rating Guide Performance Unsafe, high risk of injury or critical system failure. Does not meet requirements, has significant deficiencies. May have high operating/maintenance costs. Meets minimum requirements, has significant deficiencies. May have above average operating maintenance costs. Meets present requirements, minor deficiencies. Average operating/maintenance costs. Meets all present requirements. No deficiencies. As new/state of the art, meets present and foreseeable requirements. Report run on: March 31, 2010 10:18 AM Page 3 of 48 Edmonton - Ottewell Junior High School (B3239A) S1 STRUCTURAL A1010 Standard Foundations* (1960) (1960) Original Building - has concrete foundation walls on concrete plies along perimeter; concrete foundation walls on strip footings along Corridors. Rating Installed Design Life Updated 4 - Acceptable 1960 100 MAR-10 A1010 Standard Foundations* (1973) (1973) Addition - has concrete grade beams on concrete piles. Rating Installed Design Life Updated 4 - Acceptable 1973 100 MAR-10 A1030 Slab on Grade* (1960) (1960) Original Building (Gymnasium 17 and Space under Stage 20) - has 125 mm concrete slab on 300 mm compacted gravel fill and 4 mil polythene. (1960) Original Building (Main Floor Classrooms) - has 150 mm concrete slab above crawl space. (1960) Original Building (Main Floor Corridors) - has 165 mm concrete slab above duct space. Rating Installed Design Life Updated 3 - Marginal Event: 1960 100 MAR-10 Repair concrete slab. (approx. 50 square metres) Concern: Classroom 75 has uneven floor. Recommendation: Repair concrete slab. (approx. 50 square metres) Type Year Cost Priority Repair 2011 Low $10,000 Updated: MAR-10 A1030 Slab on Grade* (1973) (1973) Addition - has concrete slab on grade. Rating 4 - Acceptable Installed Design Life Updated 1973 100 MAR-10 A2020 Basement Walls (& Crawl Space)* (1960) (1960) Original Building - has crawl space. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 100 MAR-10 Page 4 of 48 Edmonton - Ottewell Junior High School (B3239A) B1010.01 Floor Structural Frame (Building Frame)* (1960) (1960) Original Building (Typical Main Floor) - has glulam beams on steel pipe columns. (1960) Original Building (Gymnasium 17 and Stage 20) - has glulam beams on steel columns. Rating 4 - Acceptable Installed Design Life Updated 1960 100 MAR-10 B1010.01 Floor Structural Frame (Building Frame)* (1973) (1973) Addition - has Load bearing concrete block walls and open web steel roof joists. Rating 4 - Acceptable Installed Design Life Updated 1973 100 MAR-10 B1010.02 Structural Interior Walls Supporting Floors (or Roof)* (1960) (1960) Original Building (Typical Main Floor) - has glulam beams on steel pipe columns. (1960) Original Building (Gymnasium 17 and Stage 20) - has glulam beams on steel columns. Rating 4 - Acceptable Installed Design Life Updated 1960 100 MAR-10 B1010.02 Structural Interior Walls Supporting Floors (or Roof)* (1973) (1973) Addition - has concrete block wall. Rating 4 - Acceptable Installed Design Life Updated 1973 100 MAR-10 B1010.03 Floor Decks, Slabs, and Toppings* (1960) (1960) Original Building - has concrete slab. Rating 4 - Acceptable Installed Design Life Updated 1960 100 MAR-10 B1010.03 Floor Decks, Slabs, and Toppings* (1973) (1973) Addition - has concrete slab. Rating 4 - Acceptable Installed Design Life Updated 1973 Report run on: March 31, 2010 10:18 AM 100 MAR-10 Page 5 of 48 Edmonton - Ottewell Junior High School (B3239A) B1010.05 Mezzanine Construction* (1960) (1960) Original Building (Mezzanines - Storage Rooms 25, 27) - has structural wood frame supported on concrete block walls. (1960) Original Building (Stage 20) - has 19 mm Maple flooring on 9.5 mm ply sheathing on 38x 89 mm laminated flooring. Rating 4 - Acceptable Installed Design Life Updated 1960 100 MAR-10 B1010.05 Mezzanine Construction* (1973) (1973) Addition (Mezzanine - Fan Room 105, Fan Room 8) - has concrete slab on concrete block. Rating 4 - Acceptable Installed Design Life Updated 0 100 MAR-10 B1010.06 Ramps: Exterior* (1960) Original Building (East side of Industrial Arts 10) - has a concrete ramp to public sidewalk along 94B Avenue. (installed in 2003) (1960) Original Building (Southwest Exit near Classroom 86) - has an asphalt paved ramp between entrance concrete slab and concrete sidewalk. (installed in 2003) (1960) Original Building (Southeast Exit near Classroom 47) - has an asphalt paved ramp between entrance concrete slab and concrete sidewalk. (installed in 2003) (1960) Original Building (East Exit near Classroom 34) - has an asphalt paved ramp between entrance concrete slab and concrete sidewalk. (installed in 2003) Rating 4 - Acceptable Installed Design Life Updated 2003 40 MAR-10 B1010.09 Floor Construction Fireproofing* No floor construction fireproofing observed. Rating 4 - Acceptable Installed Design Life Updated 1960 50 MAR-10 B1010.10 Floor Construction Firestopping* No floor construction firestopping observed. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 50 MAR-10 Page 6 of 48 Edmonton - Ottewell Junior High School (B3239A) B1020.01 Roof Structural Frame* (1960) (1960) Original Building (Typical Main Floor) - has diagonal shiplap on 38 x 140 mm wood joists at 400 mm o.c. on 19 x 64 mm strapping on glulam beams on steel pipe columns. (1960) Original Building (Gymnasium 17 and Stage 20) - has diagonal shiplap on 38 x 286 mm wood joists at 400 mm o.c. on 19 x 64 mm strapping on glulam beams on steel I columns. (1960) Original Building (Typical Corridors) - has diagonal shiplap on 38 x 235 mm wood joists on glulam beams on steel pipe columns. Rating 4 - Acceptable Installed Design Life Updated 1960 100 MAR-10 B1020.01 Roof Structural Frame* (1973) (1973) Addition - has steel deck on open web steel joists. Rating 4 - Acceptable Installed Design Life Updated 1973 100 MAR-10 B1020.04 Canopies* (1960) Original Building (West Main Entrance, Southwest Exit, Southeast Exit, East Exit, Northeast Exit) - has recessed canopies c/w wood frame construction and painted plywood soffit. (1973) Addition (Northwest Area - West Exit, North Exit) - has recessed canopies c/w wood frame construction and painted plywood soffit. (1973) Addition (South Area - Southwest Exit, Southeast Exit) - has recessed canopies c/w wood frame construction and painted plywood soffit. Rating 4 - Acceptable Installed Design Life Updated 1960 50 MAR-10 B1020.06 Roof Construction Fireproofing* (1960)(1973) Concrete block fire walls extend past the roof. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 50 MAR-05 Page 7 of 48 Edmonton - Ottewell Junior High School (B3239A) S2 ENVELOPE B2010.01.02.02 Concrete Block: Ext. Wall Skin* (1960) Original Building - standard concrete blocks, single wythe with loose fill insulation. Administration area exterior walls are coloured concrete bricks. (1973) Addition - single wythe striated and standard concrete blocks with loose fill insulation. Rating Installed Design Life Updated 3 - Marginal Event: 0 75 MAR-10 Repair concrete block. (approx. 3 square metres) Concern: (1960) Original Building (West Main Entrance) - has damaged concrete block. Recommendation: Repair concrete block. (approx. 3 square metres) Type Year Cost Priority Repair 2011 Low $6,000 Updated: MAR-10 B2010.01.06.03 Metal Siding** (1960)(1973) - have horizontal metal siding fascia. (1960) Original Building (Gymnasium above low roof) - has vertical metal siding. (Including 1973 addition because of small areas) Rating Installed Design Life Updated 4 - Acceptable Event: 1960 40 MAR-10 Replace metal siding. (approx. 200 square metres) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $30,000 Updated: MAR-10 B2010.01.09 Expansion Control: Exterior Wall Skin* Between (1960) and (1973) buildings - has expansion control. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 75 MAR-10 Page 8 of 48 Edmonton - Ottewell Junior High School (B3239A) B2010.01.11 Joint Sealers (caulking): Ext. Wall** Between (1960) and (1973) buildings - expansion control has caulking. (Including 1973 addition because of small areas) Rating Installed Design Life Updated 4 - Acceptable Event: 1960 20 MAR-10 Replace joint sealers (caulking). (approx. 20 linear metres) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $5,000 Updated: MAR-10 B2010.01.13 Paints (& Stains): Exterior Wall** (1960) Original Building - All concrete block surfaces and concrete window sills are painted. (1973) Addition - All concrete block surfaces are painted. (Including 1973 addition because of small area) Rating Installed Design Life Updated 3 - Marginal Event: 1960 15 MAR-10 Repaint concrete block. (approx. 1800 sqaure metres) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $135,000 Updated: MAR-10 Event: Repaint soffit above windows. (approx. 1000 linear metres) Concern: Paint of plywood soffit above window headers has peeled off. Recommendation: Repaint plywood soffit at headers of windows. (approx. 1000 linear metres) Type Year Cost Priority Repair 2011 Low $75,000 Updated: MAR-10 B2010.02.03 Masonry Units: Ext. Wall Const.* (1960)(1973) - have single wythe concrete block walls. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 100 MAR-10 Page 9 of 48 Edmonton - Ottewell Junior High School (B3239A) B2010.02.03 Masonry Units: Ext. Wall Const.* - Brick (1960) Original Building (Boiler Room 32) - has brick chimney on the roof. Rating Installed Design Life Updated 3 - Marginal Event: 1960 100 MAR-10 Repair brick chimney. (1 chimney) Concern: (1960) Original Building (Boiler Room 32) - chimney has poor mortar joints. Recommendation: Repair brick chimney. (1 chimney) Type Year Cost Priority Repair 2011 Low $10,000 Updated: MAR-10 B2010.03 Exterior Wall Vapor Retarders, Air Barriers, and Insulation* (1960)(1973) - have loose fill insulation. (1973) walls at infill areas - have 38 mm rigid insulation down to the ceiling levels. Rating 4 - Acceptable Installed Design Life Updated 1960 100 MAR-10 B2010.06 Exterior Louvers, Grilles, and Screens* (1960) Original Building (North wall of Boiler Room 32) - has aluminum louvre and grille. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 50 MAR-10 Page 10 of 48 Edmonton - Ottewell Junior High School (B3239A) B2010.09 Exterior Soffits* (1960)(1973) Exits - have painted recessed plywood soffits. (1960) Original Building (Classrooms) - has painted plywood soffit along windows. Rating Installed Design Life Updated 3 - Marginal Event: 1960 50 MAR-10 Refinish all soffits at entrances. (appeox. 30 square metres) Concern: Paint is peeling from all plywood soffit surfaces. Recommendation: Refinish soffits and canopy facias with prefinished metal on strapping. Provide air/vapour barrier membrane seal. Type Year Cost Priority Repair 2011 Low $9,000 Updated: MAR-10 B2020.01.01.02 Aluminum Windows (Glass & Frame)** (1960) Original Building (Boiler Room 32) - has original aluminum windows c/w wired glass. Rating Installed Design Life Updated 3 - Marginal Event: 1960 40 MAR-10 Replace aluminum windows. (approx. 3 windows) Concern: (1960) Original Building (Boiler Room 32) - original aluminum windows are outdated and have broken glass. Recommendation: Replace aluminum windows. (approx. 3 windows) Type Year Cost Priority Failure Replacement 2011 Low $9,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 11 of 48 Edmonton - Ottewell Junior High School (B3239A) B2020.01.01.06 Vinyl, Fibreglass &Plastic Windows** (1960) Original Building (Classrooms 34, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 85, 86, 87, 88, 89, 90, 91, 92) - has PVC windows between existing wood frames and existing painted concrete sills. Windows incorporate red colour exterior caps, sealed double glazing and awning sections with screens. (installed in 2003) (1960) Original Building (Gymnasium 17) - has PVC windows at high level. (installed in 2003) (1960) Original Building (West wall of IA 10, partial West wall of Home Economics 4) - existing windows had been sealed with painted plywood where infill walls of (1973) have been erected against them. (1973) Addition (Northwest - Home Economics 6) - has PVC windows. (1973) Addition (South - Music 81) - has PVC windows. Rating Installed Design Life Updated 4 - Acceptable Event: 2003 35 MAR-10 Replace PVC windows. (approx. 110 windows sizes vary from 4 to 4.5 square metres) Type Year Cost Priority Lifecycle Replacement 2038 Unassigned $440,000 Updated: MAR-10 B2030.01.02 Steel-Framed Storefronts: Doors** (1960) Original Building (West Main Entrance; Entrance near IA 10) - has steel framed storefront c/w single metal doors with upper portion glazed, intermediate mullions and fixed glazed panels above doors. (installed in 2007) Rating Installed Design Life Updated 4 - Acceptable Event: 2007 30 MAR-10 Replace all entrance doors. (5 doors) Type Year Cost Priority Lifecycle Replacement 2037 Unassigned $5,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 12 of 48 Edmonton - Ottewell Junior High School (B3239A) B2030.02 Exterior Utility Doors** (1960) Original Building (Southwest Exit, Southeast Exit, East Exit near Classroom 34) - has metal doors with upper portion glazed and metal frames. (installed in 2007) (1960) Original Building (Boiler Room 32, IA 10) - has metal doors and metal frames. (installed in 2007) (1973) Addition (Northwest Area - West Exit, North Exit) - has original wood doors with upper portion glazed and metal frames. (1973) Addition (South Area - Southwest Exit, Southeast Exit) - has metal doors with upper portion glazed and metal frames. (installed in 2007) Rating Installed Design Life Updated 3 - Marginal Event: 2007 40 MAR-10 Replace exterior utility doors. (15 doors) Type Year Cost Priority Lifecycle Replacement 2047 Unassigned $15,000 Updated: MAR-10 Event: Replace with exterior metal doors. (4 doors) Concern: (1973) Addition (Northwest Area - West Exit, North Exit) original wood doors with upper portion glazed are damaged. Recommendation: Replace with exterior metal doors. (4 doors) Type Year Cost Priority Failure Replacement 2011 Low $4,000 Updated: MAR-10 B3010.01 Deck Vapor Retarder and Insulation* (1960) Original Building (North area including Gymnasium, Industrial Arts, Home Economics, Boiler Room, Classroom 34, 39) - has sloped EPS insulation. (installed in 1999) (1973) Addition (Northwest area - Home Economics, Exercise Room) - has sloped EPS insulation. (installed in 1999) (1960) Original Building (East and West Wings - Classrooms) - has sloped EPS insulation. (installed in 2002) (1973) Addition (South Area - Library, Music Room) - has rigid insulation. Rating 4 - Acceptable Installed Design Life Updated 1999 Report run on: March 31, 2010 10:18 AM 25 MAR-10 Page 13 of 48 Edmonton - Ottewell Junior High School (B3239A) B3010.04.01 Built-up Bituminous Roofing (Asphalt & Gravel)** (1973) (1973) Addition (South Area - Library, Music Room) - has built-up roofing. Rating Installed Design Life Updated 3 - Marginal Event: 1973 25 MAR-10 Replace with SBS roofing. (approx. 1000 square metres) Concern: (1973) Addition (South Area - Library, Music Room) - built-up roofing has blisters and ponding. Recommendation: Replace with SBS roofing. (approx. 1000 square metres) Type Year Cost Priority Failure Replacement 2011 Low $150,000 Updated: MAR-10 B3010.04.04 Modified Bituminous Membrane Roofing (SBS)** (1960) Original Building (North area including Industrial Arts, Home Economics, Boiler Room, Classroom 34, 39) - flat roof has 2 ply SBS roofing complete with sloped EPS insulation and internal drains. (installed in 1999) (1960) Original Building (North area- Gymnasium) - pitched roof has 2 ply SBS roofing complete with sloped EPS insulation and internal drains. (installed in 1999) (1960) Original Building (East and West Wings - Classrooms) - flat roof has 2 ply SBS roofing complete with sloped EPS insulation and internal drains. (installed in 2001) (1973) Addition (Northwest area - Home Economics, Exercise Room) - flat roof has 2 ply SBS roofing complete with sloped EPS insulation and internal drains. (installed in 1999) Rating Installed Design Life Updated 4 - Acceptable Event: 1999 25 MAR-10 Replace SBS roofing. (approx. 6210 square metres) Type Year Cost Priority Lifecycle Replacement 2024 Unassigned $931,500 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 14 of 48 Edmonton - Ottewell Junior High School (B3239A) B3010.08.02 Metal Gutters and Downspouts** (1960) Original Building (the low slope main Gymnasium roof) - has downspouts and gutters to drain on adjacent lower roofs. (1960) Original Building - has roof drains and internal drains. (installed in 1999) (1973) Addition - has roof drains and internal drains. (installed in 1999) Rating Installed Design Life Updated 4 - Acceptable Event: 1999 30 MAR-10 Replace roof drains and downspouts. (approx. 16 roof drains and 80 linear metres of downspouts) Type Year Cost Priority Lifecycle Replacement 2029 Unassigned $400,000 Updated: MAR-10 B3020.02 Other Roofing Openings (Hatch,Vent, etc)* (1960) Original Building (Jan 58, Utility Room 62) - has cat ladders and steel roof hatches. (1973) Addition (Utility 7) - has cat ladders and steel roof hatches. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 25 MAR-10 Page 15 of 48 Edmonton - Ottewell Junior High School (B3239A) S3 INTERIOR C1010.01 Interior Fixed Partitions* - Concrete Block (1960) (1960) Original Building (between Classrooms, along Corridors) - has 160 mm concrete block partitions. (1960) Original Building (Gymnasium) - has 250 mm concrete block. (1960) Original Building (along Corridor of Home Economics 4) - has 200 mm concrete block. Rating Installed Design Life Updated 4 - Acceptable 1960 100 MAR-10 C1010.01 Interior Fixed Partitions* - Concrete Block (1973) (1973) Addition - has concrete block. Rating Installed Design Life Updated 3 - Marginal Event: 1973 100 MAR-10 Repair concrete blocks. (approx. 30 square metres) Concern: (1973) Addition (South Area -FAN Room 105) - has damaged concrete block wall covered with duct tapes. Recommendation: Repair concrete blocks. (approx. 30 square metres) Type Year Cost Priority Failure Replacement 2011 Low $6,000 Updated: MAR-10 (1973) Addition Fan Room 105 has damaged concrete block wall covered with duct tapes. C1010.01 Interior Fixed Partitions* - Stud (1960) Original Building (Administration, Computer Room 54) - has steel stud walls with painted gypsum boards. (installed in 2003) (1973) Addition (Library 65) - has steel stud walls with painted gypsum boards. (installed in 2003) Rating 4 - Acceptable Installed Design Life Updated 2003 Report run on: March 31, 2010 10:18 AM 100 MAR-10 Page 16 of 48 Edmonton - Ottewell Junior High School (B3239A) C1010.05 Interior Windows* (1960) Original Building (Custodian Office 30 in Boiler Room) - has wood frame windows c/w single clear glazing. (1960) Original Building (Administration) - has PVC windows facing Main Lobby. (installed in 2003) (1973) Addition (South area - Library Office 68, Classroom 64) - has metal frame windows. (installed in 2003) (1973) Addition (Northwest area - IA 14) - has metal frame windows c/w wired glass. (installed in 2003) (1973) Addition (Northwest area - Office 13) - has metal frame window c/w clear glass. (installed in 2003) Rating Installed Design Life Updated 3 - Marginal Event: 2003 80 MAR-10 Repair glass. (6 windows) Concern: (1973) Addition (Northwest area - IA 14) - metal frame windows have broken wired glass. Recommendation: Repair glass. (6 windows) Type Year Cost Priority Repair 2011 Low $1,200 Updated: MAR-10 C1010.06 Interior Glazed Partitions and Storefronts* (2003) Large storefront type windows in the Library area Office, overlooking the Library area. Rating Installed Design Life Updated 4 - Acceptable 1960 80 MAR-10 C1010.07 Interior Partition Firestopping* (1960)(1973) Block walls in fire separations extend to underside of deck. Rating Installed Design Life Updated 3 - Marginal Event: 0 50 MAR-10 Provide firestopping materials. (approx. 30 linear metres) Concern: (1973) Addition Room 7 does not have firestopping; space was covered with duct tapes. Recommendation: Provide firestopping materials. (approx. 30 linear metres) Type Year Cost Priority Failure Replacement 2011 Low Updated: MAR-10 Report run on: March 31, 2010 10:18 AM $6,000 (1973) Addition Room 7 does not have firestopping; space was covered with duct tapes. Page 17 of 48 Edmonton - Ottewell Junior High School (B3239A) C1020.01 Interior Swinging Doors (& Hardware)* (1960) (1973) - have stained solid core wood doors and pressed steel frames. (installed in 2003) (1960) Original Building (Corridor near Boys Washroom 63; Corridor near Store 56, Corridor near Girls Washroom 50; Corridor near INF 2; Corridor near Home Economics 4) - has wood doors and metal frames. (installed in 2003) (1960) Original Building (Mezzanine - Storage 25, 27) - has double wood doors. Rating Installed Design Life Updated 3 - Marginal Event: 2003 40 MAR-10 Provide chains across the door opening. (2 doors) Concern: (1960) Original Building (Mezzanine - Storage 25, 27) - double wood doors open into Stage 20 and have safety issue. Recommendation: Provide chains across the door opening. (2 doors) Type Year Cost Priority Preventative Maintenance 2011 Low $1,000 Updated: MAR-10 C1020.03 Interior Fire Doors* (1960) Original Building (Corridor near Storage 28, Corridor near Classroom 74, Corridor near Girls Washroom 82) - has 3/4 hour fire rated metal doors and metal frames. (installed in 2003) (1960) Original Building (Transformer Room 33) - has metal door and metal frame. (1973) Addition (IA 14) - has metal door and metal frame. Rating Installed Design Life Updated 4 - Acceptable Event: 0 50 MAR-10 Replace fire doors in rooms requiring fire rating. (approx. 8 doors) Concern: (1960) Original Building (Boiler Room 32, Gymnasium 17 to Corridors) - Original hollow metal doors and steel frames in fire separated rooms are of poor quality providing little or no fire protection. Hardware is original and parts are hard to find. Recommendation: Replace all hollow metal doors and steel frames with rated and labelled hollow metal doors, complete with new hardware. Type Year Cost Priority Code Repair 2011 Medium $1,600 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 18 of 48 Edmonton - Ottewell Junior High School (B3239A) C1020.05 Interior Large Doors* - Coiling Doors and Grilles (1960) Original Building (Pantry 55) - has prefinished steel rolling shutter. (installed in 2003) Rating Installed Design Life Updated 4 - Acceptable 2003 0 MAR-10 C1020.07 Other Interior Doors* (1960) Original Building (Utility 62, JAN 84) - has access doors to crawl space access. There are two steel crawl space door in service tunnel fire separations. Doors are not rated. Rating Installed Design Life Updated 4 - Acceptable 1960 0 MAR-10 C1030.01 Visual Display Boards** (1960) Original Building (Classrooms 34, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 53, 85, 86, 87, 88, 89, 90, 91, 92, Computer 54, Drama 74, SCI 75, 77, Home Economics 4, Staff 95) - has 23 smart boards, 76 whiteboards, 11 chalkboards, 19 tackboards and 4 projection screens. (1973) Addition (IA 14, Home Economics 6, Classroom 64, SCI 78, 80, Music 81) - has 2 smart boards, 8 whiteboards, 7 tackboards, 1 chalkboard and 2 projection screens. (Including 1973 addition because of small areas) Rating Installed Design Life Updated 4 - Acceptable Event: 1960 20 MAR-10 Replace visual display boards. (approx. 153 boards) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $153,000 Updated: MAR-10 C1030.02 Fabricated Compartments(Toilets/Showers)** (1960) Original Building (Girls Dressing Room 19, Boys Washroom 51, 59, 63, 82, Girls Washroom 50, 57, 61, 83, Washroom 31, Men Washroom 96, Women Washroom 94) - has prefinished metal toilet partitions. (20 partitions) (1960) Original Building (Girls Dressing Room 190) - has prefinished metal shower partitions. (3 partitions) Rating Installed Design Life Updated 4 - Acceptable Event: 1960 30 MAR-10 Replace all metal toilet partitions in Wash Rooms and add shower stalls in change Rooms. (23 partitions) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $23,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 19 of 48 Edmonton - Ottewell Junior High School (B3239A) C1030.08 Interior Identifying Devices* (1960)(1973) - All rooms have interior identifying devices. Rating Installed Design Life Updated 4 - Acceptable 1960 20 MAR-10 C1030.10 Lockers** (1960) (1960) Original Building (Corridor near Home Economics 4) - has prefinished single tier metal lockers. (14 lockers) Rating Installed Design Life Updated 3 - Marginal Event: 1960 30 MAR-10 Replace lockers . (approx. 14 lockers) Concern: Original metal lockers have been damaged and are starting to rust. Recommendation: Replace lockers . (approx. 14 lockers) Type Year Cost Priority Failure Replacement 2011 Low $14,000 Updated: MAR-10 C1030.10 Lockers** (2003) (1960) Original Building (Corridors) - has prefinished double tier metal lockers. (358 lockers) (installed in 2003) (1960) Original Building (Boys Dressing Room 18, Girls Dressing Room 19) - has prefinished triple tier metal lockers. (34 lockers) (installed in 2003). Rating Installed Design Life Updated 5 - Good Event: 2003 30 MAR-10 Replace lockers. (approx. 392 lockers) Type Year Cost Priority Lifecycle Replacement 2033 Unassigned $392,000 Updated: MAR-10 C1030.12 Storage Shelving* (1960) Original Building (Utility 62, Storage 35, Office 21, IA Storage 12, SCI Prep 76) - has wood shelves. (1973) Addition (Storage 15) - has wood shelves. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 30 MAR-10 Page 20 of 48 Edmonton - Ottewell Junior High School (B3239A) C1030.14 Toilet, Bath, and Laundry Accessories* (1960) Original Building (Boys Washroom 51, 59, 63, 82, Girls Washroom 50, 57, 61, 83, Washroom 31, Men Washroom 96, Women Washroom 94) - toilet accessories. (1960) Original Building (Boys Dressing Room 18, Girls Dressing Room 19, PEO Shower 37) - has shower accessories. Rating Installed Design Life Updated 4 - Acceptable 1960 20 MAR-10 C2010 Stair Construction* (1960) Original Building (Gymnasium 17) - has concrete stairs to Corridor and Change Rooms. (1960) Original Building (Boiler 32) - has steel grating landing and stairs. Rating Installed Design Life Updated 4 - Acceptable 1960 100 MAR-10 C2020.05 Resilient Stair Finishes** (1960) Original Building (Gymnasium 17) - concrete stairs have rubber tile treads and risers Rating Installed Design Life Updated 4 - Acceptable Event: 1960 20 MAR-10 Replace resilient stair finishes. (3 stairs) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $9,000 Updated: MAR-10 C2020.08 Stair Railings and Balustrades* (1960) Original Building (Gymnasium 17) - concrete stairs have wood handrails and metal balustrades. (1960) Original Building (Boiler 32) - steel landing and stairs have painted pipe handrails. Rating Installed Design Life Updated 4 - Acceptable 1960 40 MAR-10 C3010.02 Wall Paneling** (1960) Original Building (South wall of Gymnasium 17 around Stage 20) - has painted wood battens. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 30 MAR-10 Replace wall paneling. (approx. 100 square metres) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $10,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 21 of 48 Edmonton - Ottewell Junior High School (B3239A) C3010.06 Tile Wall Finishes** (1960) Original Building (Staff 95, Home Economics 4) - has ceramic wall tiles above counters. (installed in 2003) (1960) Original Building (Boys Washrooms 51, 59, 63, 82) - has ceramic wall tiles around urinals. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 40 MAR-10 Replace tile wall finishes. (approx. 30 square metres) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $6,000 Updated: MAR-10 C3010.09 Acoustical Wall Treatment** (1973) Addition (Music Room 81) - has fabric covered acoustic panels on walls. (installed in 2003) Rating Installed Design Life Updated 4 - Acceptable Event: 2003 20 MAR-10 Replace acoustical wall treatment. (approx. 170 square metres) Type Year Cost Priority Lifecycle Replacement 2023 Unassigned $25,500 Updated: MAR-10 C3010.11 Interior Wall Painting* (1960) (1973) - Except Industrial Arts area, Change Rooms, Boiler Room and other ancillary spaces, the entire building was repainted in 2003. Rating 5 - Good Installed Design Life Updated 1960 10 MAR-10 C3010.12 Wall Coverings* (1960) Original Building (North wall of Staff Room 95) - is covered with vinyl fabric. (installed in 2003) Rating 4 - Acceptable Installed Design Life Updated 2003 Report run on: March 31, 2010 10:18 AM 15 MAR-10 Page 22 of 48 Edmonton - Ottewell Junior High School (B3239A) C3010.14 Other Wall Finishes Wall decoration* (1960) Original Building (Walls in both Gymnasiums 17, 60) - has bright coloured paint stripe accents. (installed din 2003) (1960) Original Building (Corridor on Stage 20) - has large painted murals on the north walls of north corridor. (installed din 2003) Rating Installed Design Life Updated 5 - Good 2003 10 MAR-10 C3010.14 Other Wall Finishes* - Wall carpet (1960) Original Building (Time Out cubicles 99, 100) has carpet on walls. (installed in 2003) Rating Installed Design Life Updated 4 - Acceptable 2003 0 MAR-10 C3020.01.02 Paint Concrete Floor Finishes* (1960) Original Building (Boiler 32, Transformer Room 33) - has painted concrete floor. (1973) Addition (Mezzanine - Fan Room 105, Fan Room 8) - has unpainted concrete floor. Rating Installed Design Life Updated 3 - Marginal Event: 0 0 MAR-10 Repair and repaint concrete floor. (approx. 85 square metres) Concern: Boiler Room floor paint is starting to wear out. Recommendation: Repair and repaint concrete floor. (approx. 85 square metres) Type Year Cost Priority Failure Replacement 2011 Low $8,500 Updated: MAR-10 C3020.02 Tile Floor Finishes** (1960) Original Building (Boys Washrooms 51, 59, 63, 82) - has ceramic mosaic tiles in front of urinals. (1960) Original Building (boys Dressing Room 18, Girls Dressing Room 19) - has ceramic mosaic tiles in shower rooms. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 50 MAR-10 Replace tile floor finishes. (approx. 50 square emtres) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $7,500 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 23 of 48 Edmonton - Ottewell Junior High School (B3239A) C3020.04 Wood Flooring** - Gym (1960) Original Building (Gymnasium 17, 60) - has wood flooring. (installed in 2003) (1960) Original Building (Stage 20) - has wood flooring. (1960) Original Building (Mezzanine - Storage 25, 27) - has plywood floor. Rating Installed Design Life Updated 3 - Marginal Event: 2003 30 MAR-10 Replace wood flooring. (approx. 600 square metres) Type Year Cost Priority Lifecycle Replacement 2033 Unassigned $120,000 Updated: MAR-10 Event: Resand and refinish wood flooring. (approx. 80 square metres) Concern: (1960) Original Building (Stage 20) - wood flooring has not been refinished. Recommendation: Resand and refinish wood flooring. (approx. 80 square metres) Type Year Cost Priority Repair 2011 Low $12,000 Updated: MAR-10 C3020.04 Wood Flooring** - Industrial Arts (1960) Original Building (Duct Collector 16, Industrial Arts 10, Paint Booth 11, Storage 12) - has wood flooring. Rating Installed Design Life Updated 3 - Marginal Event: 1960 0 MAR-10 Refinish Industrial Arts parquet flooring. (approx. 180 square metres) Concern: Parquet flooring in Industrial Arts has several parquet blocks missing, extensive dents, scratches, paint and other stains. The floor has never been finished and the surface is worn out. Recommendation: Refinish Industrial Arts flooring. Extensive sanding required to remove as much blemishes as possible. Stain surfaces for smooth finish. Type Year Cost Priority Repair 2011 Low $27,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 24 of 48 Edmonton - Ottewell Junior High School (B3239A) C3020.07 Resilient Flooring** - Sheet Vinyl (1960) Original Building (Corridors, Pantry 55, SCI PREP 76) - has sheet vinyl flooring. (installed in 1998) Rating Installed Design Life Updated 4 - Acceptable Event: 1998 20 MAR-10 Replace sheet vinyl flooring in corridors. (approx. 950 square metres) Type Year Cost Priority Lifecycle Replacement 2018 Unassigned $95,000 Updated: MAR-10 C3020.07 Resilient Flooring** - Tiles (1960) Original Building (Home Economics 4, Kitchen 3, Storage 5, Gym Storage 24, 26, Office 21, 23, Classrooms 34, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 53, 85, 86, 87, 88, 89, 90, 91, 92, Storage 35, Offices 36, 38, Utility 52, 62, 84, Storage 28, Jan 29, Office 30, Jan 58, SCI 75, 77, Boys Dressing Room 18, Girls Dressing Room 19, Boys Washroom 51, 59, 63, 82, Girls Washroom 50, 57, 61, 83, Washroom 31, PEO Shower 37, Men Washroom 96, Women Washroom 94) - has VAT. (1960) Original Building (Second Floor - Storage 101; Storage 105; Storage 114; Storage 118) - has VAT. (1973) Addition (Exercise Room 9, IA 14, Office 13, Storage 15, Home Economics 6, JAN 72, SCI 78, 80) - has vinyl tile flooring. Replace resilient flooring. (approx. 700 square metres) Rating Installed Design Life Updated 3 - Marginal Event: 1960 20 MAR-10 Replace VAT flooring. (approx. 1100 square metres) Concern: (1960) Original Building - has VAT. Recommendation: Replace VAT flooring. (approx. 1100 square metres). Install heavy grade vinyl sheet flooring complete with rubber bases. Work can be done in stages. Type Year Cost Priority Hazardous Materials Abatement 2011 Low $220,000 Updated: MAR-10 Event: Replace resilient flooring. (approx. 700 square metres) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $70,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 25 of 48 Edmonton - Ottewell Junior High School (B3239A) C3020.08 Carpet Flooring** (1960) Original Building (Workroom 101, Staff Room 95, PRI 102, VP 104, Counsellor 103, Reading Rooms 99, 100, Administration 98, Computer Rooms 54, Server 66, Drama 74, INF 2) - has carpet. (installed in 2003) (1973) Addition (Classroom 64, LIB 65, Office 71, Librarian 68, Workroom 73, Music Room 81, Classroom 64) - has carpet. (installed in 2003) Rating Installed Design Life Updated 4 - Acceptable Event: 2003 15 MAR-10 Replace carpet flooring. (approx. 660 square metres) Type Year Cost Priority Lifecycle Replacement 2018 Unassigned $66,000 Updated: MAR-10 C3030.01 Concrete Ceiling Finishes (Unpainted)* (1960) Concrete ceilings under mezzanine slabs, painted. Rating Installed Design Life Updated 4 - Acceptable 1960 100 MAR-05 C3030.03 Plaster Ceiling Finishes (Unpainted)* (1960) Original Building (Boiler Room 32, Transformer Room 33) - has plaster ceiling which may contain asbestos. Rating Installed Design Life Updated 4 - Acceptable 1960 50 MAR-10 C3030.06 Acoustic Ceiling Treatment (Susp.T-Bar)** (1960) Original Building (Corridors, partial Staff Room 95, Pantry 55, Computer Office 67, Server 66, Workroom 101) has suspended T-bar ceiling system c/w acoustic ceiling tiles. (installed in 2003) (1973) Addition (Office 13, Storage 15, Home Economics 6, Utility 7, Classroom 64, LIB 65, Workroom 73, JAN 72, Office 71, Librarian 68, SCI 78, 80, PREP 79, Music 81) - has suspended T-bar ceiling system c/w acoustic ceiling tiles. (installed in 2003) Rating Installed Design Life Updated 5 - Good Event: 2003 25 MAR-10 Replace acoustic ceiling treatment (Susp.T-Bar). (approx. 910 square metres) Type Year Cost Priority Lifecycle Replacement 2028 Unassigned $45,500 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 26 of 48 Edmonton - Ottewell Junior High School (B3239A) C3030.07 Interior Ceiling Painting* (1960)Original Building (Boys Washroom 51, 59, 63, 82, Girls Washroom 50, 57, 61, 83, Washroom 31, Men Washroom 96, Women Washroom 94, Boys Dressing Room 18, Girls Dressing Room 19, PEO Shower 37, Utility 62, 84, JAN 29, 52, 58, Kitchen 3, Storage 5, Storage 12, Paint Booth 11, Gym Storage 24, 26, 28) - has painted drywall ceiling. (1973) Addition (Northwest - IA 14, Exercise 9) - has exposed metal deck and painted OWSJ. (1973) Addition (South - Music 81) - has exposed metal deck and painted OWSJ. Rating Installed Design Life Updated 4 - Acceptable 1960 20 MAR-10 C3030.09 Other Ceiling Finishes* (Fibrous Ceiling Tiles) (1960) Original Building (IA 10, Dust Collector Room 16, Home Economics 4, INF 2, Office 21, 23, portions of Staff Room95, Administration 98, PRI 102, VP 104, Counsellor 103, Classrooms 34, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 53, 85, 86, 87, 88, 89, 90, 91, 92, Drama 74, Storage 35, Offices 36, 38, Gymnasium 17, Gymnasium 60, Stage 20, Corridor near IN 10) - has original 300 x 300 mm perforated fibrous ceiling tiles under wood decking, between glulam beams. Rating Installed Design Life Updated 3 - Marginal Event: 1960 0 MAR-10 Replace with suspended T-bar ceiling system. (approx. 2850 square metres) Concern: (1960) Original Building has damaged and missing fibrous ceiling tiles such as Drama 74, Classroom 43. Recommendation: Replace with suspended T-bar ceiling system. (approx. 2850 square metres) Type Year Cost Priority Failure Replacement 2011 Low $142,500 Updated: MAR-10 C3030.09 Other Ceiling Finishes* - Trims (1960) (1973) - has painted drywall bulkhead / borders in corridor ceilings. (painted in 2003) (1973) Addition (Libary 65) - has painted lighted ceiling bulkhead in the middle of Library. (painted in 2003) Rating 4 - Acceptable Installed Design Life Updated 2003 Report run on: March 31, 2010 10:18 AM 0 MAR-10 Page 27 of 48 Edmonton - Ottewell Junior High School (B3239A) S4 MECHANICAL D2010.04 Sinks** Mainly single and two compartment Stainless steel sinks throughout school. Cast iron, wall mounted Janitor sink in custodian room. Some of the traps receiving wastes from the kitchen sinks and the garburators plug frequently. Replace traps at kichen sinks. Rating Installed Design Life Updated 4 - Acceptable Event: 2006 30 MAR-10 Replace 30 S/S sinks. Type Year Cost Priority Lifecycle Replacement 2036 Unassigned $15,000 Updated: MAR-10 D2010.05 Showers** Showers in boys and girls locker rooms with mixing valves & vandal proof heads. Showers are not being used. Rating Installed Design Life Updated 3 - Marginal Event: 1960 30 MAR-10 Replace 16 Shower stations. Concern: The showers in the boys and girls locker rooms are not used. Mixing valves are in questionable condition. Handles are missing. Recommendation: Replace Mixing valves and shower heads. Consequences of Deferral: No useable showers. Type Year Cost Priority Failure Replacement 2011 Low $24,000 Updated: MAR-10 D2010.08 Drinking Fountains / Coolers** (1960) (1973) Double wall hung drinking fountains with no coolers. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 35 MAR-10 Replace 4 Drinking Fountains. Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $5,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 28 of 48 Edmonton - Ottewell Junior High School (B3239A) D2010.10 Washroom Fixtures (WC, Lav, Urnl)** Throughout school, mainly: Floor mounted, recessed urinals with flush tanks with water saving timer device. Floor mounted flush valve & flush tank water closets. Stainless steel and enameled lavatories. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 35 MAR-10 Replace 16 WC's, 16 Lavs and 8 Urinals. Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $80,000 Updated: MAR-10 D2020.01.01 Pipes and Tubes: Domestic Water* Copper piping with soldered fittings. Rating Installed Design Life Updated 4 - Acceptable 1960 40 MAR-10 D2020.01.02 Valves: Domestic Water** Mainly gate valves - isolation service. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 40 MAR-10 Replace 25 Valves. Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $12,000 Updated: MAR-10 D2020.01.03 Piping Specialties (Backflow Preventors)** Backflow preventor in supply to boiler make up water line. Rating Installed Design Life Updated 4 - Acceptable Event: 1999 20 MAR-10 Replace backflow preventor. Type Year Cost Priority Lifecycle Replacement 2019 Unassigned $5,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 29 of 48 Edmonton - Ottewell Junior High School (B3239A) D2020.02.06 Domestic Water Heaters** Water heater - A.O.Smith model BTRC 180 118. 81 gal storage capacity / 152,000 Btuh input c/w fractional HP recirculation pump. Rating Installed Design Life Updated 5 - Good 2006 20 MAR-10 Event: Replace Domestic Water Heater & recirc pump. Type Year Cost Priority Lifecycle Replacement 2026 Unassigned $10,000 Updated: MAR-10 D2020.03 Water Supply Insulation: Domestic* Hot and cold piping is insulated and canvas covered. Rating 4 - Acceptable Installed Design Life Updated 1960 40 MAR-10 D2030.01 Waste and Vent Piping* Mostly cast iron drainage pipe. Vent piping is cast iron and copper. Rating 4 - Acceptable Installed Design Life Updated 1960 50 MAR-10 D2030.02.04 Floor Drains* Conventional, general purpose floor drains in Washrooms. Funnel floor drains in Mechanical room. Rating 4 - Acceptable Installed Design Life Updated 1960 50 MAR-10 D2040.01 Rain Water Drainage Piping Systems* Mostly cast iron roof drainage piping. Rating 4 - Acceptable Installed Design Life Updated 1960 50 MAR-10 D2040.02.04 Roof Drains* Conventional roof drains - dome strainers. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 40 MAR-10 Page 30 of 48 Edmonton - Ottewell Junior High School (B3239A) D3010.02 Gas Supply Systems* Schedule 40 steel gas supply to mechanical room and appliances in the home economics room. Rating Installed Design Life Updated 4 - Acceptable 1960 60 MAR-10 D3020.02.01 Heating Boilers and Accessories: H.W.** 3 RBI boilers model DB1500. Capacity: 1500 mbh input each. Separately vented up through roof. Rating Installed Design Life Updated 5 - Good Event: 2008 35 MAR-10 Replace 3 heating boilers & accessories. Type Year Cost Priority Lifecycle Replacement 2043 Unassigned $60,000 Updated: MAR-10 D3020.02.02 Chimneys (&Comb. Air): H.W. Boiler** Separately vented chimneys up through roof. Barometric damper on vents. No insulation on flues. Rating Installed Design Life Updated 5 - Good Event: 2008 35 MAR-10 Replace 3 boiler flues & combustion air duct. Type Year Cost Priority Lifecycle Replacement 2043 Unassigned $35,000 Updated: MAR-10 D3020.02.03 Water Treatment: H. W. Boiler* Chemical pot feeder installed on hydronic loop. Rating 4 - Acceptable Installed Design Life Updated 2006 Report run on: March 31, 2010 10:18 AM 30 MAR-10 Page 31 of 48 Edmonton - Ottewell Junior High School (B3239A) D3040.01.01 Air Handling Units: Air Distribution** Roof mounted, indirect gas fired Air Handling units c/w supply / return fans, filters, mixing sections, heating sections. Rating Installed Design Life Updated 5 - Good Event: 2006 30 MAR-10 Replace 4 roof mounted Air Handling Units. Type Year Cost Priority Lifecycle Replacement 2036 Unassigned $200,000 Updated: MAR-10 D3040.01.02 Fans: Air Distribution (Remote from AHU)* Ceiling mounted propellor fans in Gymnasium and Computer room. Install date estimated. Rating Installed Design Life Updated 4 - Acceptable 2006 30 MAR-10 D3040.01.04 Ducts: Air Distribution* Low velocity galvanized ductwork. Most of the ductwork was upgraded in 2004. Rating Installed Design Life Updated 5 - Good 2004 50 MAR-10 D3040.01.06 Air Terminal Units: Air Distribution (VAV Box)** - Dual Duct Dual duct terminal boxes in the Home Economics area and the Industrial Arts. Rating Installed Design Life Updated 4 - Acceptable Event: 1973 0 MAR-10 Replace 4 Dual Duct mixing boxes Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $10,000 Updated: MAR-10 D3040.01.07 Air Outlets & Inlets:Air Distribution* Mainly cone and grille diffusers throughout school. Rating 4 - Acceptable Installed Design Life Updated 2006 Report run on: March 31, 2010 10:18 AM 30 MAR-10 Page 32 of 48 Edmonton - Ottewell Junior High School (B3239A) D3040.03.01 Hot Water Distribution Systems** Piping is mixture of copper and schedule 40 steel. Solder & threaded joints, respectively. Heating water distributed by Taco & Armstrong pumps. Rating Installed Design Life Updated 5 - Good Event: 2006 40 MAR-10 Replace Hot Water Distribution System. Type Year Cost Priority Lifecycle Replacement 2046 Unassigned $500,000 Updated: MAR-10 D3040.04.01 Fans: Exhaust** Domed, centrifugal, roof mounted exhaust fans are used for washrooms and utility rooms. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 30 MAR-10 Replace 10 roof mounted exhaust fans. Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $15,000 Updated: MAR-10 D3040.04.02 Air Cleaning Devices: Exhaust* Torit dust collector & other Air filtration units in shop area. Models unknown. Rating Installed Design Life Updated 4 - Acceptable 2006 0 MAR-10 D3040.04.03 Ducts: Exhaust* Various low velocity galvanized exhaust ductwork throughout school, connecting grilles & hoods to roof mounted fans. Rating 4 - Acceptable Installed Design Life Updated 1960 50 MAR-10 D3040.04.05 Air Outlets and Inlets: Exhaust* Mostly "eggcrate" style, ceiling & wall mounted exhaust grilles. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 30 MAR-10 Page 33 of 48 Edmonton - Ottewell Junior High School (B3239A) D3050.01.02 Packaged Rooftop Air Conditioning Units (& Heating Units)** Lennox roof top ventilation unit (AS04) with mechanical cooling provides ventilation and cooling for the general office, staff room and the principals office. Rating Installed Design Life Updated 5 - Good Event: 2004 0 MAR-10 Replace roof top HVAC unit. Type Year Cost Priority Lifecycle Replacement 2034 Unassigned $20,000 Updated: MAR-10 D3050.01.04 Unit Air Conditioners** Mitsubishi ductless split system air conditioners in Library and Computer classroom. Ceiling mounted with roof mounted condensing units. Install date estimated. Rating Installed Design Life Updated 5 - Good Event: 2006 30 MAR-10 Replace 2 Ductless Split Air Conditioning units. Type Year Cost Priority Lifecycle Replacement 2036 Unassigned $20,000 Updated: MAR-10 D3050.05.03 Finned Tube Radiation** Perimeter Hot water radiation used throughout school - various enclosure types. Rating Installed Design Life Updated 4 - Acceptable Event: 2006 40 MAR-10 Replace 75m perimeter finned tube radiation. Type Year Cost Priority Lifecycle Replacement 2046 Unassigned $75,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 34 of 48 Edmonton - Ottewell Junior High School (B3239A) D3050.05.06 Unit Heaters** Vertical projection unit heaters in the gym. Rating Installed Design Life Updated 4 - Acceptable Event: 2006 0 MAR-10 Replace 2 unit heaters in gym. Type Year Cost Priority Lifecycle Replacement 2036 Unassigned $10,000 Updated: MAR-10 D3060.02.02 Pneumatic Controls** Space thermostats are pnumatic. Simplex air compressor was replaced in 2004. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 40 MAR-10 Replace Pneumatic Controls. Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $45,000 Updated: MAR-10 D3060.02.04 Self-Powered Controls* Self actuated control valves are used to control the radiation in the washrooms and the conference room. Rating Installed Design Life Updated 3 - Marginal Event: 2006 30 MAR-10 Replace self actuated controls in the conference room and washrooms. Concern: The self actuated controls in the conference room and the washrooms do not maintain adequate space temperature control. Recommendation: Replace the self actuated controls with pneumatic control valves and thermostats. Type Year Cost Priority Failure Replacement 2011 Low $14,913 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 35 of 48 Edmonton - Ottewell Junior High School (B3239A) D3060.02.05 Building Systems Controls (BMCS, EMCS)** EMCS system controls major mechanical systems. Invensys. Install date estimated. Rating Installed Design Life Updated 4 - Acceptable Event: 2000 25 MAR-10 Replace Building Systems Controls (BMCS, EMCS) Type Year Cost Priority Lifecycle Replacement 2025 Unassigned $100,000 Updated: MAR-10 D4010 Sprinklers: Fire Protection* The building is fully sprinklered. Wet pipe c/w fire department connection at exterior of building. System regularly checked and maintained. Rating 4 - Acceptable Installed Design Life Updated 1960 60 MAR-10 D4030.01 Fire Extinguisher, Cabinets and Accessories* Dry chemical fire extinquishers at several locations throughout building. Recessed cabinets and wall mounting brackets. Regularly checked. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 30 MAR-10 Page 36 of 48 Edmonton - Ottewell Junior High School (B3239A) S5 ELECTRICAL D5010.03 Main Electrical Switchboards (Main Distribution)** FPE main distribution centre is located in the electrical room, and is fed underground from a pad mounted transformer. The main distribution centre is rated at 1200a, 120/208V, 3 phase, 4 wire and is complete with a 1200A main breaker and a feeder breaker section, with feeder breakers. All feeder breakers are adequately identified. No spare breaker capacity exists in the main distribution centre. Rating Installed Design Life Updated 5 - Good Event: 2004 40 MAR-10 Replace Main Electrical Switchboards (Main Distribution). Type Year Cost Priority Lifecycle Replacement 2044 Unassigned $150,000 Updated: MAR-10 D5010.05 Electrical Branch Circuit Panelboards (Secondary Distribution)** Approximately 10 breaker panels have been provided in the service rooms and in the classroom wings that supply power to outlets, lighting, and equipment throughout the school. All breaker panels are complete with directories and have ample spare breaker capacity. Rating Installed Design Life Updated 4 - Acceptable Event: 2004 30 MAR-10 Replace Electrical Branch Circuit Panelboards (Secondary Distribution). Type Year Cost Priority Lifecycle Replacement 2034 Unassigned $40,000 Updated: MAR-10 D5010.07.02 Motor Starters and Accessories** Wall mounted starters have been provided for motor control. Starters are complete with pilot lights and selector switches and are located in the vicinity of the equipment being controlled. Approximately 5 starters have been provided. Rating Installed Design Life Updated 4 - Acceptable Event: 2006 30 MAR-10 Replace Motor Starters and Accessories. Type Year Cost Priority Lifecycle Replacement 2036 Unassigned $7,500 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 37 of 48 Edmonton - Ottewell Junior High School (B3239A) D5020.01 Electrical Branch Wiring* Wiring is copper and is installed in conduit. Rating Installed Design Life Updated 4 - Acceptable 2004 50 MAR-10 D5020.02.02.02 Interior Florescent Fixtures** Lighting fixtures are of the fluorescent type, and, depending on the ceiling system, are either surface mounted or recessed mounted. Fixtures are of the energy efficient type, complete with T lamps and electronic ballasts. Replacement cost based on the building area. Rating Installed Design Life Updated 5 - Good Event: 2004 30 MAR-10 Replace Interior Florescent Fixtures. Basis of estimate: Building Area. Type Year Cost Priority Lifecycle Replacement 2034 Unassigned $350,000 Updated: MAR-10 D5020.02.03.02 Emergency Lighting Battery Packs** Emergency lighting is provided by emergency lighting battery packs and remote heads. All paths and points of egress are well illuminated as required by the Alberta Building Code. Estimate based on approximately 20 battery packs. Rating Installed Design Life Updated 5 - Good Event: 2004 20 MAR-10 Replace Emergency Lighting Battery Packs. Type Year Cost Priority Lifecycle Replacement 2024 Unassigned $15,000 Updated: MAR-10 D5020.02.03.03 Exit Signs* Exit lights are of the LED type and have been over each required exit and along paths of egress. Rating 5 - Good Installed Design Life Updated 2004 30 MAR-10 D5020.03.01.04 Exterior H.P. Sodium Fixtures* Wall mounted fixtures have been provided around the perimeter of the building and over each door leading to the exterior. The fixtures are rated at 250 Watts. Rating 4 - Acceptable Installed Design Life Updated 2004 Report run on: March 31, 2010 10:18 AM 30 MAR-10 Page 38 of 48 Edmonton - Ottewell Junior High School (B3239A) D5020.03.02 Lighting Accessories: Exterior (Lighting Controls)* Exterior lighiting is photocell controlled and is integrated with the DDC system. Rating Installed Design Life Updated 4 - Acceptable 2004 30 MAR-10 D5030.01 Detection and Fire Alarm** A Simplex 4100U addressable fire alarm system has been provided and is complete with heat detectors, smoke detectors, manual pull stations, bell/strobe units. The main control panel is located in the general office, with a remote annunciator in the main entrance vestibule. The system is externally monitored and annually tested. Rating Installed Design Life Updated 5 - Good Event: 2004 25 MAR-10 Replace Detection and Fire Alarm. Type Year Cost Priority Lifecycle Replacement 2029 Unassigned $130,000 Updated: MAR-10 D5030.02.02 Intrusion Detection** Magnum Alert intrusion alarm system has been provided, complete with motion sensors, door contacts and key pads. The main control panel is located in the server room. The system is externally monitored. Rating Installed Design Life Updated 4 - Acceptable Event: 1991 25 MAR-10 Replace Intrusion Detection. Type Year Cost Priority Lifecycle Replacement 2016 Unassigned $75,000 Updated: MAR-10 D5030.04.01 Telephone Systems* Telephone service is underground and terminates in the server room. A Meridian telephone system has been provided. Rating 5 - Good Installed Design Life Updated 1998 Report run on: March 31, 2010 10:18 AM 25 MAR-10 Page 39 of 48 Edmonton - Ottewell Junior High School (B3239A) D5030.04.03 Call Systems** A Bogen Multicom 2000 call system has been provided. The head end equipment is located in the server room. Telephone sets have been provided in each classroom. The call system is interfaced with the telephone system. Ceiling mounted loudspeakers have been provided in each classroom, in the corridors and all common areas. Rating Installed Design Life Updated 5 - Good Event: 1998 0 MAR-10 Replace Call Systems. Type Year Cost Priority Lifecycle Replacement 2023 Unassigned $85,000 Updated: MAR-10 D5030.04.05 Local Area Network Systems* Cat 5 data cabling has been provided throughout, with outlets in each classroom and in the administration area. Main network located in the server room and is complete a data rack, patch panels, and switches. Rating 5 - Good Installed Design Life Updated 2003 Report run on: March 31, 2010 10:18 AM 15 MAR-10 Page 40 of 48 Edmonton - Ottewell Junior High School (B3239A) S6 EQUIPMENT, FURNISHINGS AND SPECIAL CONSTRUCTION E1020.02 Library Equipment* (1973) Addition (LIB 65) - has painted book shelves and display racks; book drop off cabin. (installed in 2003) Rating 5 - Good Installed Design Life Updated 2003 25 MAR-10 E1020.03 Theater and Stage Equipment* (1960) Original Building (Stage 20) - has stage curtains and tracks. (1960) Original Building (Gymnasium 17) - has sound system equipment, spot and track lighting. (installed in 1999) (1960) Original Building (Gymnasium 17) - has drapery over windows. Rating 4 - Acceptable Installed Design Life Updated 1960 25 MAR-10 E1020.07 Laboratory Equipment* (1960) Original Building (Boiler Room 32, IA 10) - has eye wash station. Rating 4 - Acceptable Installed Design Life Updated 2003 25 MAR-10 E1090.04 Residential Equipment* (1960) Original Building (Staff Room 95) - has dishwasher, fridge, microwaves, stove. (installed in 2003) (1960) Original Building (Pantry 55) - has coolers, freezer, microwaves. (installed in 2003) (1960) Original Building (Custodian Office 30) - has fridge, microwave. (1960) Original Building (Home Economics 4) - has stoves, microwaves, fridges, washer/dryer. (installed in 2003) (1973) Addition (Home Economics 6) - has fridges, microwaves, curtain and track. (installed in 2003) (1973) Addition (SCI Prep 79) - has fridge, microwave, dishwasher. Rating 4 - Acceptable Installed Design Life Updated 1960 10 MAR-10 E1090.07 Athletic, Recreational, and Therapeutic Equipment* (1960) Original Building (Main Gymnasium 17) - has six basketball hoops, two motorized. LED score board. Volleyball and badminton pole sockets and nets. Chair storage under Stage. (1960) Original Building (Gymnasium 60) - has large floor exercise mats, volleyball and badminton floor sockets, poles and nets. (1973) Addition (Exercise Room 9) - has weight lifting and cardio exercise equipment. Rating 5 - Good Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 15 MAR-10 Page 41 of 48 Edmonton - Ottewell Junior High School (B3239A) E2010.02 Fixed Casework** - Display Cases (1960) Original Building (Corridor near Utility 62) - has display case. (installed in 2003) Rating Installed Design Life Updated 4 - Acceptable Event: 2003 35 MAR-10 Replace display case. (approx. 2 linear metres) Type Year Cost Lifecycle Replacement 2038 Priority Unassigned $2,000 Updated: MAR-10 E2010.02 Fixed Casework** - Educational (1960) Original Building Classrooms) - has painted cabinets and cupboards with open shelving, painted. (repainted in 2003) (1960) Original Building (IA 10) - has large, heavy duty work tables (1960) Original Building (Computer 54) - has plastic laminated countertops. (installed in 1994) Rating Installed Design Life Updated 4 - Acceptable Event: 1994 0 MAR-10 Repair countertops. (approx. 10 linear metres) Concern: (1960) Original Building (SCI PREP 77) - has damaged countertops. (1973) Addition (SCI 80, SCI PREP 79) - has damaged countertops. Recommendation: Repair countertops. (approx. 10 linear metres) Type Year Cost Repair 2011 $10,000 Priority Low Updated: MAR-10 Event: Replace educational casework. (approx. 40 linear metres) Type Year Cost Lifecycle Replacement 2029 $40,000 Priority Unassigned Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 42 of 48 Edmonton - Ottewell Junior High School (B3239A) E2010.02 Fixed Casework** - Kitchen (1960) Original Building (Home Economics 4) - has 'U' shaped painted perimeter cabinets with plastic laminated countertops with sinks and painted cupboard. (1960) Original Building (Pantry 55) - has plastic laminated countertop and painted cupboards. (installed in 2003) (1960) Original Building (Staff Room 95) - has maple cabinets with drawers and cupboards and plastic laminated countertop with sink. (installed in 2003) Rating Installed Design Life Updated 3 - Marginal Event: 2003 0 MAR-10 Replace kitchen casework. (approx. 20 linear metres) Type Year Cost Priority Lifecycle Replacement 2038 Unassigned $20,000 Updated: MAR-10 Event: Replace kitchen millwork. (approx. 10 linear metres) Concern: (1960) Original Building (Home Economics 4) - has damaged 'U' shaped painted perimeter cabinets, plastic laminated countertops and drawers. Recommendation: Replace kitchen millwork. (approx. 10 linear metres) Type Year Cost Priority Failure Replacement 2011 Low $10,000 Updated: MAR-10 E2010.02 Fixed Casework** - Library (1973) Addition (Library Office 71, Librarian 68) - has oak built in work stations. (installed in 1994) Rating Installed Design Life Updated 4 - Acceptable Event: 1994 0 MAR-10 Replace library casework. (approx. 10 linear metres) Type Year Cost Priority Lifecycle Replacement 2029 Unassigned $10,000 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 43 of 48 Edmonton - Ottewell Junior High School (B3239A) E2010.02 Fixed Casework** - Reception Counters (1960) Original Building (Administration 98) - has oak reception counters. (installed in 2003) (1973) Addition (Library 65) - has plastic laminated reception counter. (installed in 2003) Rating Installed Design Life Updated 4 - Acceptable Event: 2003 35 MAR-10 Replace reception counters. (approx. 8 linear metres) Type Year Cost Priority Lifecycle Replacement 2038 Unassigned $8,000 Updated: MAR-10 E2010.02 Fixed Casework** - Vanities (1960) Original Building (Boys Washroom 51, 59, 63, 82, Girls Washroom 50, 57, 61, 83, Washroom 31, Men Washroom 96, Women Washroom 94) - has plastic laminated vanities. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 35 MAR-10 Replace vanities. (approx. 12 linear metres) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $12,000 Updated: MAR-10 E2010.03.01 Blinds** (1960) (1973) - all windows have venetian blinds. (Including 1973 addition because of small areas) Rating Installed Design Life Updated 4 - Acceptable Event: 1960 30 MAR-10 Replace blinds. (approx. 102 windows) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $40,800 Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 44 of 48 Edmonton - Ottewell Junior High School (B3239A) E2010.05 Fixed Multiple Seating** (1960) Original Building (Drama 74) - has a wood raised platform covered with carpet. Rating Installed Design Life Updated 4 - Acceptable Event: 1960 35 MAR-10 Repalce plaform. (approx. 20 square metres) Type Year Cost Priority Lifecycle Replacement 2013 Unassigned $8,000 Updated: MAR-10 F1020.03 Other Integrated Construction* - Industrial Arts (1960) Original Building (IA 10) - has jig saws, drill presses, band saw, wood lathes, scroll saw, table saws, squaring shear. (1960) Original Building (IA 10) - has a paint booth room. (1973) Addition (IA 14) - has metal lathe, metal chopper, wood shelves bolt lathe. Rating 4 - Acceptable Installed Design Life Updated 1960 50 MAR-10 F2020.01 Asbestos* A Hazardous Materials management Project for Asbestos Building Material Survey Report was completed for Edmonton Public Schools by PHH Environmental Limited on October 16, 2000. (see C3020.07 Resilient Flooring Tiles) Soil in crawl space and tunnels is contaminated with asbestos fiber of elbow debris. Doors to crawl spaces do not contain warning labels. Rating 4 - Acceptable Installed Design Life Updated 1960 0 MAR-10 F2020.02 PCBs* No PCBs are known or reported. Rating 4 - Acceptable Installed Design Life Updated 0 0 MAR-10 F2020.03 Mercury* No known mercury has been observed. Rating 4 - Acceptable Installed Design Life Updated 0 Report run on: March 31, 2010 10:18 AM 0 MAR-10 Page 45 of 48 Edmonton - Ottewell Junior High School (B3239A) F2020.04 Mould* No known mould has been observed. Rating 4 - Acceptable Installed Design Life Updated 1960 0 MAR-10 F2020.09 Other Hazardous Materials* No other hazardous materials have been observed. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 0 MAR-10 Page 46 of 48 Edmonton - Ottewell Junior High School (B3239A) S8 FUNCTIONAL ASSESSMENT K40 Current Code Issues (1960) Original Building (Gymnasium 17) - does not have a direct exit to outside. (1973) Addition (Northeast Area - Corridor between IA 14 and Exercise 9) - wood is being stored in a closed / unused hallway which has series of windows to adjacent room; has continuous windows at ceiling level in corridor walls; this may be a dead end corridor and raising safety issue. Rating Installed Design Life Updated 4 - Acceptable 1960 0 MAR-10 K4010.01 Barrier Free Route: Parking to Entrance* The front entrance is used for barrier free entrance from 73 Street. Parking area accommodates mostly Staff parking and rear entrance has ramp. Wheelchair users can use City sidewalk to go around the building to the front entrance. Rating Installed Design Life Updated 4 - Acceptable 2003 0 MAR-10 K4010.02 Barrier Free Entrances* (1960) Original Building (West Main Entrance) - has barrier free operable buttons on doors. Rating Installed Design Life Updated 4 - Acceptable 2003 0 MAR-10 K4010.03 Barrier Free Interior Circulation* (1960)(1973) - Corridors are wide enough for wheelchairs. Rating Installed Design Life Updated 3 - Marginal Event: 2003 0 MAR-10 Provide wheelchair platform. (1 platform) Concern: (1960) Original Building (Gymnasium 17) - does not have wheelchair ramp. Recommendation: Provide wheelchair platform. (1 platform) Type Year Cost Barrier Free Access Upgrade 2011 $10,000 Priority Low Updated: MAR-10 Report run on: March 31, 2010 10:18 AM Page 47 of 48 Edmonton - Ottewell Junior High School (B3239A) K4010.04 Barrier Free Washrooms* (1960) Original Building (Men Washroom 96, Girls Washroom 57) - has barrier free washrooms. Rating 4 - Acceptable Installed Design Life Updated 1960 0 MAR-10 K4020 Building Code ABC Group A Division 2 - School. The 1960 Original Building is a single storey. The 1973 Addition is a single storey. Both 1960 Original Building and 1973 Addition have non-combustible and combustible construction and are sprinklered. Rating 4 - Acceptable Installed Design Life Updated 1960 Report run on: March 31, 2010 10:18 AM 0 MAR-10 Page 48 of 48
Similar documents
RECAPP Facility Evaluation Report
Concern: There are damaged wood doors throughout the school which are unsightly and require replacing. Recommendation: Replace damaged wood doors throughout the school.
More informationRECAPP Facility Evaluation Report
Address: 51 Boudreau Road Location: St. Albert Building Id: Gross Area (sq. m): Replacement Cost: Construction Year:
More informationRECAPP Facility Evaluation Report
St. Albert - Lorne Akins Junior High School (B4072A) A2020 Basement Walls (& Crawl Space) - 1963 Section* The gymnasium is above crawl space. The floor is plywood subfloor on wood joists on wood b...
More informationRECAPP Facility Evaluation Report
1 - Critical 2 - Poor 3 - Marginal 4 - Acceptable 5 - Good 6 - Excellent
More informationNewbrook School B3827A - Alberta Infrastructure
1 - Critical 2 - Poor 3 - Marginal 4 - Acceptable 5 - Good 6 - Excellent
More information