Foundry Modernization of OJSC “MAZ” (first stage)
Transcription
Foundry Modernization of OJSC “MAZ” (first stage)
А. Project opportunity description А1. Project name: Foundry Modernization of OJSC “MAZ” (first stage) А1а. Short name: Foundry modernization А1b. Full name: Foundry Modernization of OJSC “MAZ” (first stage) А1c. Summary description: Modernization of foundry allows to achieve in 2015 the production of steel castings in the volume 19,3 thousand tons and iron castings in the volume of 18,6 thousand tons; it will ensure the implementation of modern equipment and technology which will allow to improve quality and reduce cost of castings manufacture as well as to increase export potential of Belarus. А2. Project status: The technologies of castings production were developed; the production plan was approved; layout solution of a new production building was preliminary worked out, the processing equipment specifications were developed and the equipment purchasing documents are being prepared; the approximate main costs were specified, a preliminary business-plan is being worked out, the requirements in production areas were estimated. А3. Organization involved and their roles: - OJSC “Minsk Automobile Plant” with 100% government share in the authorized fund; 2, Socialisticheskaya str. 220021, Minsk – the project implementing organization .- Director General Alexander Vassilievich Borovsky, tel. +375(17) 217 96 01; -Deputy Director General of Technical Development Coordination – Dmitry Viktorovich Korotkevich, tel. +375(17)217 96 02. - Ministry of Industry of the Republic of Belarus: 2, Partizanski ave., block 4, 220033 Minsk – public authority, tel.+375(17) 224 61 12. - Unitary Enterprise “Institute Belpromproyect” – construction project documentation developer А4. Project description: The existing casting production facilities at OJSC “MAZ” does not enable to provide the required quality. The project provides for the foundry re-equipment in melting, forming, molding-sand preparation, core sand mixture and thermal treatment production areas. This will make it possible to catch up with the backlog of production facilities, significantly improve castings quality and reduce their weight and machining costs. New technologies and equipment allow to considerably lower the work content and manufacturing costs. The project stipulates the capacities creation for high-grade grey cast iron and steel production as well as production of 2 casting for die tooling. А4а. Project cost, USD million: 54,2 А5. Background /history/overall programe/related or similar projects: Background of offer to modernize the foundry shall be the Program of Development of Automobile Industrial Sector of Belarus for 2007-2010 years, approved by the Council of Ministers Resolution № 1777 of December18, 2007 and Resolution of Council of Ministers № 248 of February 22, 2010 “According the measures to increase of fuel and energy resources efficiency till 2012 year”. А6. Environmental impact summary: The technologies intended to minimize the environmental impact shall be used. А7. Possible obstacles/problems/risk degree: The short time for project implementation presupposes a parallel design and construction works. Due to the introduction of the new foundry equipment it is necessary to fabricate a full set of pattern equipment for grey cast iron and steel. А8. Time period for project implementation and pay-back period (years): 7,2 А9. Project branch: Automobile manufacturing В. Capital cost Items В1. Project physical component: В2. Capital cost USD million Capital costs excluding VAT (equipment (without customs duties) + erection and design works) Total (sum should be equal С2+ D4) B3. Sub-project by location 54,2 54,2 B4. Capital cost USD million С. Capital Resources Available (owner, associates, sponsors etc.) С1. Resources, grants, investments, С2. Sum, equipments, equity/ownership etc. USD million D. Required Investment, Deficient Funds D1 Necessary Financing, Required Type of Financial Participation: Borrowed funds 3 D2 Source of finance D3. Type of Investment D4. Amount USD million External investments Е. Demand (Users) and Revenues Е1. Type of Users, Volumes, Pricing, Revenues, Estimated Profit/Savings OJSC «МAZ», engineering enterprises Е2. Financing Sources Е3. Revenues (Sales) Cost reduction due to saving the cost of materials, energy, etc. 7,4 USD million (20102020) F. Transaction and Operating Costs F1. Costs Components, Capital Allowance Policy, Industrial Engineering etc. F2. Сost item: F3. Amount Materiel cost, remuneration of labor, taxes etc. G. Net Income Value G1. Net Income Value: G2. Amount Energy resources saving 7,4 USD million (20102020) Н. Project Information Source: Н1. This form was completed by (name, appointment): Dmitry ViktorovichKorotkevich, Deputy Director General of Technical Development Coordination Н2. Organization: Open Joint Stock Company “Minsk Automobile Plant”, Minsk, 2 Socialisticheskaya str. Н3. Tel./ Fax/E-mail: теl. 375 17 217 96 45 Fax. 375 17 217 22 11, www.maz.com.by Н4. Date: May, 2010 Н5. Supreme organization: Ministry of Industry of the Republic of Belarus 4
Similar documents
Development of cabin production for new generation “MAZ” vehicle
Е. Demand (Users) and Revenues Е1. Type of Users, Volumes, Pricing, Revenues, Estimated
More information