PROJECT CAMEO MTU AMERICA DEVELOPMENT

Transcription

PROJECT CAMEO MTU AMERICA DEVELOPMENT
PROJECT CAMEO
MTU AMERICA DEVELOPMENT PROJEC T/ MTU AMERICA / AIKEN, SC
Project Value: $24,600,000
Key Project Features:
•
Precision Fuel Conditioning and Measurement
Project Overview:
Panel, controlling fuel pressure, temperature
ACS provided turnkey delivery, including the
and measurement.
design, construction, equipment fabrication and
•
integration and commissioning services for a new
equipment, test articles and support
engine research and development test center in
Aiken, South Carolina. The project consisted of
equipment.
•
a Development Building with two R&D test cells
as well as a new Mechanical/Electrical building
Driveline including high speed shafting and a
tandem (water brake & AC) dynamometer.
•
providing all new facility systems required to
support the test cells. The project will support the
3D CAD Model of entire test cell, test
Isolated Inertia Mass with dampening spring
system for vibration control.
•
research and development for MTU America’s S2000
Engine adapter system that accommodates
over 20 different engine types/models.
and S4000 series of diesel engines. The output range
•
Engine water cooling system skid.
of these engines is 550 kW up to a maximum of 4500
•
Combustion Air intake and Exhaust after
kW.
ACS Services:
ACS held a single-source contract for test facility
treatment systems with quick disconnects.
•
Data Acquisition and Control system.
•
Test Cell acoustics engineered to meet client
requirements
design and construction management; equipment
design and component specification, equipment
build, procurement, and contractor installation;
Project Duration: 18 months
integration of equipment, facility, and control
systems; and commissioning.
Completion Date: Spring 2013
Headquarters - Madison, WI - USA / Greenville, SC - USA / Troy, MI - USA / TEDA Tianjin, China / Leicester, UK / www.acscm.com / [email protected]