Westmoreland Presentation
Transcription
Greater Boston Solutions Study High Level Cost Estimate Presented by: Electrical Consultants, Inc. November 18, 2014 Electrical Consultants, Inc. ♦ Full Service Utility Engineering & EPC Firm ♦ History of Firm > 40 Years; Organized as ECI in 1985 ♦ ~400 Design Professionals ♦ Large EPC Provider to the Utility & Energy Industry Electrical Consultants, Inc. Office Locations Electrical Consultants, Inc. Experience and Qualifications ♦ Major utility clients include AEP, MidAmerican Energy, ATC, FPL & OG&E ♦ Approximately $65M in engineering fees & $50M in EPC completed work in 2013 ♦ Performs engineering design for substation, overhead transmission, underground transmission, distribution, environmental, ROW, permitting & studies services for clients Electrical Consultants, Inc. Experience and Qualifications ♦ Carry out construction and EPC contracts through our subsidiary, EPC Services Company ♦ Service provided to electric utilities, renewable energy, industrial, municipality, etc. Experience in System Planning Studies Mid American Energy Various Electric Cooperatives American Transmission Co. Various Renewable Energy Developers Madison Gas & Electric PacifiCorp City/County of San Francisco PUC NRG Energy Chelan County PUD Bonneville Power Administration ECI Tasks for ISO New England ECI to develop “High Level” conceptual cost estimate for the design, engineer, construct and commissioning of the 10 projects based on project scope information provided by ISO-NE. AC Plan ♦ Scobie- Tewksbury 345 kV Line ♦ Reconductor Y-151 kV NU border to Dracut Jct. ♦ Wakefield – Woburn 345 kV UG cable plus 2 reactors ♦ Bifurcate a new Woburn – Mystic 115 kV cable with the existing cable AC Plan HVDC Plan ♦ HVDC submarine cable and two (2) terminals ♦ Seabrook 345 kV Interconnection for HVDC ♦ Mystic 115 kV Interconnection for HVDC ♦ Reconductor Y-151 kV NU border to Dracut Jct. ♦ Reconductor Sandy Pond – Tewksbury 345 kV ♦ Bifurcate Mystic – North Cambridge 345 kV HVDC Plan Project Information ECI performed “High Level” cost estimate based on: 1. “Available” information on project scope. 2. ECI past experiences in similar projects. 3. Industry data search. Project Information ECI performed “High Level” cost estimate based on: 4. ECI obtained budgetary quotes from vendors/contractors where necessary to verify estimates. 5. Project budget did not allow for in-depth site visit or survey to evaluate physical conditions of each project. 6. ECI recognized cost estimating information provided by most TO’s was based on conceptual design without detailed engineering; thus the estimates would be “high level” and “conceptual” with possible variances once detailed engineering was completed at a later stage. Project Information ECI performed “High Level” cost estimate based on: 7. All Quotes are in 2014 dollars. 8. Items not included in cost estimates: Common Projects Easements Real Estate Permitting Environmental Mitigation Standard Utility Burden Work Process 1. At the start of the project, there was very limited written description of each project and breaker diagram. In order to get an understanding of the routing of each project, ECI developed route maps of all projects using tools such as ECI’s data base of utility substation locations, Google map, etc. 2. ECI also developed local permitting and environmental information for reference. 3. ECI then developed conceptual idea of how each project can be constructed. Work Process 4. “High Level” budgetary material take-off and construction estimates were performed to put together base case “True-Up” estimates for each project. 5. Subsequently, some project routing information and conceptual engineering details were provided by TO’s. ECI modified its initial cost estimates several times to reflect the additional available information. 6. Work involved specialized engineering disciplines in substation, UG & OH transmission, submarine underwater transmission and environmental & permitting. AC Plan Cost Estimate AC Plan ECI Project # Description Scobie – Tewksubry 345 kV Line Length (miles) ECI Base Cost 25 A-1 $123.2M Reconductor Y-151 kV NU border to Dracut Jct. 9 A-2 Wakefield – Woburn 345 kV UG cable plus 2 reactors 8 $100.9M A-3 Bifurcate a new Woburn – Mystic 115 kV cable with the existing cable 8 $68.8M Total $292.9M AC Plan; Project A-1 Estimate Scope ♦ Tewksbury Upgrade: 345 kV breakers, switches, bus, etc. ♦ Scobie Pond Upgrade: 345 kV breakers, switches, bus, CCVT, etc. ♦ Scobie-Tewksbury 345 kV Line: Install new 345 kV line, relocating two 230 kV lines and two 115 kV lines, relocating one 13.8 kV line over a total of 25 miles. ♦ Y-151 Reconductor from NU Border to Dracut Jct.: Replace most of the structures, shield wire, hardware, conductor, etc. for approximately 9.3 miles of 115 kV Y151 AC Plan; Project A-1 Estimate Scope Total estimated cost for AC Plan Project A-1 $123.2M AC Plan; Project A-2 Estimate Scope ♦ Woburn Substation: bus, etc. Add shunt reactor, GIS breakers, ♦ Wakefield Substation: Add shunt reactor, GIS breakers, bus, etc. ♦ Install new 345 kV underground line (XLPE) between Woburn and Wakefield Substations for a total approximate distance of 7.7 miles AC Plan; Project A-2 Estimate Scope Total estimated cost for AC Plan Project A-2 $100.9M AC Plan; Project A-3 Estimate Scope ♦ Mystic Substation: 115 kV GIS terminations relocation and associated work for bifurcating two lines ♦ Woburn Substation: Install new 115 kV series reactor and bifurcating the new 115 kV line terminations with existing line ♦ Install new 115 kV underground line (HPFF) from Woburn to Mystic over approximately 7.7 miles AC Plan; Project A-3 Estimate Scope Total estimated cost for AC Plan Project A-3 $68.8M HVDC Plan Cost Estimate HVDC Plan ECI Project # Description Length (miles) ECI Base Cost 68 $497.9M D-1 HVDC submarine cable and two (2) terminals D-2 Seabrook 345 kV Interconnection for HVDC NA $28.3M D-3 Mystic 115 kV Interconnection for HVDC NA $25.1M D-4 Reconductor Y-151 kV NU border to Dracut Jct. 9 $10.5M D-5 Reconductor Sandy Pond – Tewksbury 345 kV 16 $34.4M D-6 Bifurcate Mystic – North Cambridge 345 kV NA $14.7M Total $610.9M HVDC Plan; Project D-1 Estimate Scope ♦ Install approximately 50.2 miles 200 kV XLPE DC submarine cables from Seabrook, NH to Everett, MA ♦ Install approximately 15.3 miles 200 kV XLPE DC land cables from shore landing points to converter stations ♦ Install approximately 0.4 miles of 345 kV XLPE AC land cables for Seabrook interconnect HVDC Plan; Project D-1 Estimate Scope ♦ Install approximately 1.3 miles 115 kV XLPE AC land cables for Everett to Mystic interconnect ♦ Install two AC/DC converter stations, one at each end of the DC cables HVDC Plan; Project D-1 Estimate Scope Total estimated cost for HVDC Plan Project D-1 $497.9M HVDC Plan; Project D-2 Estimate Scope ♦ Modify existing Seabrook Sub to tie the converter station to the existing Seabrook Sub. Convert existing breaker into gas zone, install new breakers, GIS busses, etc. HVDC Plan; Project D-2 Estimate Scope Total estimated cost for HVDC Plan Project D-2 $28.3M HVDC Plan; Project D-3 Estimate Scope ♦ Mystic Substation: UG 115 kV air terminals, relocate 115 kV xfmrs, add new breaker, remove/reinstall breakers, install new GIS buses, terminate HVDC cables, etc. ♦ Relocate 115 kV underground lines (HPFF) to facilitate relocation of terminals HVDC Plan; Project D-3 Estimate Scope Total estimated cost for HVDC Plan Project D-3 $25.1M HVDC Plan; Project D-4 Estimate Scope ♦ Y-151 Reconductor from NU Border to Dracut Jct.: Replace most of the structures, shield wire, hardware, conductor, etc. for approximately 9.3 miles of 115 kV Y151 HVDC Plan; Project D-4 Estimate Scope Total estimated cost for HVDC Plan Project D-4 $10.5M HVDC Plan; Project D-5 Estimate Scope ♦ Temporary substation work to facilitate the reconductor of Sandy Pond – Tewksbury 345 kV overhead line ♦ Reconductor the 345 kV OH line 337 for approximately 15.7 miles HVDC Plan; Project D-5 Estimate Scope Total estimated cost for HVDC Plan Project D-5 $34.4M HVDC Plan; Project D-6 Estimate Scope ♦ North Cambridge Sub: Remove air insulated bus, install new gas insulated bus, plus associated work to facilitate bifurcating of two existing 345 kV underground HPFF lines ♦ Mystic Substation: Remove air insulated bus, install new gas insulated bus, plus associated work to facilitate bifurcating of two existing 345 kV underground HPFF lines ♦ North Cambridge and Mystic Substations: Move UG HPFF line 351 to new termination locations near line 358 terminations to allow for bifurcating the two lines HVDC Plan; Project D-6 Estimate Scope Total estimated cost for HVDC Plan Project D-6 $14.7M
Similar documents
Global High Voltage Direct Current (HVDC) Transmission Systems Market
High-voltage, direct current (HVDC) system is an electrical power transmission system which uses direct current for long distance electrical power transmission as opposed to more common alternating current power transmission systems. These systems are economical and offers better stability than AC line or AC cable and can be easily customized to specific function to improve the reliability of the network. HVDC systems can be applied at any voltage levels which makes it possible to connect the systems between two asynchronous networks. Demand for the HVDC systems is mainly from the countries where power stations are located at larger distance from consumer ends such as India & China and is less from the densely populated areas such as countries in Europe since the electrical losses are negligible at smaller distances. Global HVDC market is witnessing new product developments and large scale agreements, collaborations and partnerships across the value chain, with a number of tier-one companies globally. Currently large number of projects deployed uses line Commuted converter LCC technology, however focus on increasing the use of non-renewable energy sources has increased the demand for voltage Source Converter technology VSC.
More information