UMF CHP LP Gas Tank 00 01 01 – 1 Title Page SECTION 00 01 01

Transcription

UMF CHP LP Gas Tank 00 01 01 – 1 Title Page SECTION 00 01 01
SECTION 00 01 01
SPECIFICATIONS and REFERENCE DRAWINGS
FOR
UMF CENTRAL HEATING PLANT LP GAS TANK SYSTEM
UNIVERSITY OF MAINE AT FARMINGTON
FARMINGTON, MAINE
October 9, 2015
Prepared by:
Competitive Energy Services, LLC
Dirigo Architectural Engineering, LLC
END OF SECTION 00 01 01
UMF CHP LP Gas Tank
00 01 01 – 1
Title Page
SECTION 00 01 10
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP
# of Pages
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
Introductory Information
00 01 01
Project Title Page
1
00 01 10
Table of Contents
2
00 01 11
Request for Proposal
6
Procurement Requirements
00 11 13
Advertisement for Bids
1
00 21 13
Instructions to Bidders
2
00 41 13
Bid Form
1
00 43 13
Bid Security Form
1
Contracting Requirements
00 51 00
Notice of Award
1
00 52 13
Construction Contract Agreement Form
2
00 61 13.13 Performance Bond Form
1
00 61 13.16 Payment Bond Form
1
00 62 16
G715 Supplemental Attachment for ACORD Certificate of Insurance
1
00 62 16.10 Certificate of Liability Insurance (ACORD)
2
00 62 16.11 Commercial General Liability Coverage Form (ISO CG 00 01 12 04)
15
00 62 16.12 Additional Insured – Owners, Lessees or Contractors – Scheduled Person or
Organization (ISO CG 20 10 07 04)
1
00 62 16.13 Additional Insured – Owners, Lessees or Contractors – Completed Operations
(ISO CG 20 37 07 04)
1
00 62 16.14 Designated Location(s) General Aggregate Limit (ISO CG 25 04 03 97)
2
00 62 73
G703 Schedule of Values Form (Continuation Sheet)
1
00 62 76
G702 Application for Payment Form
1
00 62 76.13 Sales Tax Form
1
00 62 76.16 G707A Consent of Surety to Reduction in or Partial Release of Retainage Form
1
00 62 79
Stored Material Form
2
00 63 14
G716 Request for Information Form
1
00 63 33
G710 Architect’s Supplemental Instructions Form
1
00 63 46
G714 Construction Change Directive Form
1
00 63 57
G709 Work Changes Proposal Request Form
1
00 63 63
G701 Change Order Form
1
00 65 16
G704 Certificate of Substantial Completion Form
1
00 65 19
Certificate of Completion Form
1
00 65 19.13 G706 Contractor’s Affidavit of Payment of Debts and Claims Form
1
00 65 19.16 G706A Contractor’s Affidavit of Release of Liens Form
1
00 65 19.17 Waiver of Lien
1
00 65 19.19 G707 Consent of Surety to Final Payment Form
1
00 72 00
A201 General Conditions of the Contract for Construction
38
00 73 00.01 Supplementary Conditions to the A201-2007 General Conditions of the Contract
9
00 73 00.11 Schedule of Liquidated Damages
1
00 73 46
Wage Determination Schedule
1
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00
Summary of Work
01 14 00
Work Restrictions
01 23 00
Alternates
01 29 00
Payment Procedures
01 31 00
Project Management and Coordination
01 31 13
Project Coordination
01 33 00
Submittal Procedures
01 40 00
Quality Requirements
01 70 00
Project Execution
UMF CHP LP Gas Tank
00 01 10 – 1
1
1
1
4
6
3
2
6
4
Table of Contents
01
01
01
01
74
77
78
78
19
00
23
36
Construction Waste Management
Closeout Procedures
Operations and Maintenance Data
Warranties and Guarantees
MATERIAL SPECIFICATIONS
23 11 27
LP Gas Piping
23 13 00
Above Ground LP Tanks
23 18 10
LP Gas Vaporizer
5
5
8
2
8
7
2
REFERENCE DRAWINGS
C101
CENTRAL HEATING PLANT PROPOSED SITE PLAN
PL100
CENTRAL HEATING PLANT PLUMBING PIPING PLAN
END OF SECTION 00 01 10
UMF CHP LP Gas Tank
00 01 10 – 2
Table of Contents
University of Maine System
REQUEST FOR PROPOSALS (RFP)
RFP # 23-16
Central Heating Plant Liquid Propane Gas Tank System
University of Maine at Farmington
ISSUE DATE:
October 13th, 2015
PROPOSALS MUST BE RECEIVED BY:
November 5th, 2015 – 2:00 PM
REQUEST FOR PROPOSALS
SUMMARY
The University of Maine System on behalf of the University of Maine at Farmington (“University”) is
soliciting proposals for a propane storage and delivery system with stanchion and vaporizer from
qualified Suppliers.
SCOPE
This RFP is intended to solicit proposals to furnish and install propane storage and delivery equipment,
including but not limited to:
1. The supplier firstly recognizes that this RFP is paired with the ongoing installation of UMF’s new
biomass central heating plant, scheduled for completion in January of 2016. As such, the
supplier can expect a significant amount of coordination will be required for both technical
aspects of the installation and logistical access to the site to enable the scope included herein.
2. Detailed arrangement drawings showing all system components drawn to scale for coordination
and shall be submitted for Owner review and approval prior to starting work. Plans to be sealed
by a Maine licensed professional engineer as required.
3. Product material submittals for Owner review and approval on:
a. LP Gas Tank
b. Vaporizer
c. Stanchion
d. Gas Piping
e. Leak Detection System
4. Filing all required local, state and federal permit applications required for the installation,
including all fees. Including, but not limited to:
a. Maine Fuel Board
b. Town of Farmington
5. Provide a Fire Safety Analysis for the installation, per NFPA 58. Coordinate with Owner for
review by Authority Having Jurisdiction and the Town of Farmington Fire Chief.
6. One (1) new 18,000 gallon water capacity propane storage tank including:
a. Indicating dial thermometer
b. 0-300 psi gauge
c. Magnitel, liquid and vapor shut-off valves
d. Nitrogen-activated internal valves and relief valves with 7' risers and weather caps.
7. One (1) Algas Q480V water bath vaporizer, or approved equal, capable of providing up to 40
MMBtu/hr. of liquid-free gas at a delivery pressure of 10 PSI.
8. One (1) new transport unload stanchion in accordance with the latest edition of NFPA Pamphlet
58 specifications for vapor return and liquid fill lines. The stanchion would be installed
approximately 10' from the tank, and sized accordingly.
9. All mechanical piping associated with connection of the tank, vaporizer and fill-station stanchion
10. All gas piping (3” diameter) from the tank, to the vaporizer, to the central heating plant, and
terminating at the building entrance, as specified in site plans. This includes all regulators,
reducers, valves and other appurtenances are required by code. Also includes excavation,
proper backfill material, and burial marking tape.
2|Page
11. Paint all exposed gas piping OSHA Safety Yellow, and label as “LP Gas”.
12. All electrical wiring association with the connection of the vaporizer, leak detection system, and
signal back to UMF. Also includes all grounding, dielectric couplers, etc. as required by code.
13. Structural concrete foundation required to support tank, including site work (excavation and
backfill)
14. 6’ high chain link fence with doors for access, egress and tank filling.
15. Traffic bollards around tank, spacing per updated Maine Fuel Gas Code (3’-0” MAX spacing).
Bollards to be primed steel pipe filled with concrete and embedded in a concrete Sonotube
foundation to a depth below frost line. Provide replaceable yellow plastic slip covers for each
bollard.
16. Emergency shut down system with nitrogen-activated pneumatic releases and two (2) shut-offs.
One (1) shut-off shall be located at the stanchion and one (1) shut-off will be located at a
distance of 25’ but no greater than 100’ from the tank.
17. Metering devices for monitoring by University staff, which can be remotely monitored by the
campus building management system. Meters should be capable of retrofit to provide data
output via the BACnet communication protocol connected to a Tracer SC system.
The Supplier will be required to design and install the proposed facility and shall perform its obligations
under this Agreement in full compliance with all Federal, State, and local laws, rules, and regulations,
including but not limited to those laws, rules, and regulations stated herein:
•
•
•
•
•
•
•
•
•
Maine Public Utilities Commission Regulations, Chapters 420 and/ or 421
49CFR192 and/ or 49CFR193 of the Code of Federal Regulations
NFPA 54, 55, 58, and 101
Maine Uniform Building and Energy Code
Maine Fuel Board Rules
OSHA Safety regulations with regards to construction and operations
MDOT and Federal regulations regarding transport, delivery, and unloading of heating fuel
products
University of Maine System and Campus requirements and stipulations regarding design and
construction on these campuses
Any other code, regulation or local ordinance that may bear on this scope of work
Subsequent Sections of the RFP include additional technical data, material specifications, and Central
Heating Plant Drawings for reference and incorporation into the Supplier’s proposal.
The University will also entertain proposals for alternative but comparable equipment which meets all of
the requirements outlined above and contained in this solicitation package.
Regardless of the proposal, the form of this contract will be a construction contract in the form provided
in accompanying sections. All costs of the installation will be paid according to the terms of the
construction contract.
SITE VISIT
A mandatory pre-bid site visit will be held on Thursday, October 22nd, 2015 at 10:00 AM. Meet at UMF
Parking Lot 9 on Quebec Street.
3|Page
COMMUNICATION WITH THE UNIVERSITY
It is the responsibility of the supplier to inquire about any requirement of this RFP that is not
understood. Responses to inquiries, if they change or clarify the RFP in a substantial manner, will be
forwarded by addenda to all parties that have received a copy of the RFP. Addenda will also be posted
on our web site, www.maine.edu/strategic/upcoming_bids.php. The University will not be bound by oral
responses to inquiries or written responses other than addenda.
Inquiries must be made via email to:
Thomas W. Perkins, PE
[email protected]
Designated Owner’s Representative for
Office of Strategic Procurement
University of Maine System
16 Central Street
Bangor, Maine 04401
EVALUATION CRITERIA
Proposals will be evaluated on many criteria deemed to be in the University’s best interests, including,
but not limited to, cost, technical merit, quality and responsiveness of the proposal, quality of the
proposed installation, company history and experience, and best computed overall value to the
University. The University will not consider non-responsive proposals, i.e., those with material
deficiencies, omissions, errors or inconsistencies.
AWARD OF PROPOSAL
Presentations may be requested of two or more suppliers deemed by the University to be the best
suited among those submitting proposals on the basis of the selection criteria. After presentations have
been conducted, the University may select the proposal which, in its opinion, is the most responsive and
most responsible and may award the contract to that supplier. The University reserves the right to
waive minor irregularities. Scholarships, donations, or gifts to the University, will not be considered in
the evaluation of proposals. The University reserves the right to reject any or all proposals, in whole or
in part and is not necessarily bound to accept the lowest cost proposal if that proposal is contrary to the
best interests of the University. The University may cancel this RFP or reject any or all responses in
whole or in part. Should the University determine in its sole discretion that only one supplier is fully
qualified, or that one supplier is clearly more qualified than any other under consideration, a contract
may be awarded to that supplier without further action.
AWARD PROTEST
Suppliers may appeal the award decision by submitting a written protest to the University of Maine
System’s Director of Strategic Procurement within five (5) business days of the date of the award notice,
with a copy of the protest to the successful supplier. The protest must contain a statement of the basis
for the challenge.
4|Page
CONFIDENTIALITY
The information contained in proposals submitted for the University's consideration will be held in
confidence until all evaluations are concluded and an award has been made. At that time, the winning
proposal will be available for public inspection. Pricing and other information that is an integral part of
the offer cannot be considered confidential after an award has been made. The University will honor
requests for confidentiality for information of a proprietary nature to the extent allowed by law. Clearly
mark any information considered confidential. The University must adhere to the provisions of the
Maine Freedom of Access Act (FOAA), 1 MRSA §401, et seq. As a condition of accepting a contract
under this section, a contractor must accept that, to the extent required by Maine FOAA, responses to
this solicitation, and any ensuing contractual documents, are considered public records and therefore
are subject to freedom of access requests.
COSTS OF PREPARATION
Supplier assumes all costs of preparation of the proposal and any presentations necessary to the
proposal process.
DEBARMENT
Submission of a signed proposal in response to this solicitation is certification that your firm (or any
subcontractor) is not currently debarred, suspended, proposed for debarment, declared ineligible or
voluntarily excluded from participation in this transaction by any State or Federal department or agency.
Submission is also agreement that the University will be notified of any change in this status.
PROPOSAL UNDERSTANDING
By submitting a proposal, the supplier agrees and assures that the specifications are adequate, and the
supplier accepts the terms and conditions herein. Any exceptions should be noted in your response. .
Notwithstanding a Supplier’s apparent low bid price or any provision to the contrary herein, any
conditions or exceptions that Supplier places upon the University’s terms and conditions shall be
weighed as part of the evaluation criteria for bid award.
PROPOSAL SUBMISSION
A SIGNED original and 5 COPIES of the proposal must be submitted to the Facilities Management Office
at UMF, in a sealed envelope by 2:00 PM on November 5th, 2015. to be date stamped by the Facilities
Management office in order to be considered. Other bid submission requirements are also applicable,
per subsequent sections of this RFP. Normal business hours are 8:00 a.m. to 5:00 p.m., Monday through
Friday. The ELECTRONIC COPY of the proposal must be provided on CD or flash drive with the complete
proposal submission in Adobe Acrobat PDF format. Suppliers may wish to check
http://www.maine.edu/alerts/ to determine if University operations have been suspended. Proposals
received after the due date will be returned unopened. There will be no public opening of proposals
(see Confidentiality clause). In the event of suspended University operations, proposals will be due the
next business day. Suppliers are strongly encouraged to submit proposals in advance of the due date to
avoid the possibility of missing the due date because of unforeseen circumstances. Suppliers assume
the risk of the methods of dispatch chosen. The University assumes no responsibility for delays caused
by any package or mail delivery service. Postmarking by the due date WILL NOT substitute for receipt of
5|Page
proposal. Additional time will not be granted to any single vendor, however additional time may be
granted to all vendors when the University determines that circumstances require it. FAXED OR E-MAIL
PROPOSALS WILL NOT BE ACCEPTED. The envelope must be clearly identified on the outside as follows:
Name of Supplier
Address of Supplier
Due Date
RFP #23-16
TIMEFRAME
The timeframe for this proposal is as follows:
RFP Advertisement and Solicitation:
October 15, 2015
RFP Due Date:
November 5, 2015
RFP Selection:
November 12, 2015
Installation Start:
December 1, 2015
Installation Complete:
January 1, 2016
6|Page
SECTION 00 11 13
ADVERTISEMENT FOR BIDS
Sealed Bids in envelopes plainly marked: UMF Central Heating Plant LP Gas Tank System
addressed to:
University of Maine at Farmington
Office of Facilities Management
c/o Jeffrey McKay, Director of Facilities Management
Farmington Falls Road
Farmington ME 04938
will be received until 2:00 PM on Thursday, November 5th, 2015, at which time the Bids will be opened and
read aloud in UMF Facilities Management Conference Room, Farmington Falls Road, Farmington Maine. Bids
received after the stated time will not be considered and will be returned unopened.
Bids must be accompanied by a satisfactory Bid Bond for 5% of the Bid (checks will not be accepted) which
shall be in conformity with the form of Bond contained in Section 00 43 13 of the Specifications. The
University reserves the right to waive all formalities and reject any or all bids or to accept any bids.
The successful Bidder will be required to furnish a 100% Performance Bond and a 100% Payment Bond to
cover the execution of the Contract which shall be in conformity with the form of Bonds contained in Sections
00 61 13.13 and 00 61 13.16, respectively, of the Specifications and shall be for the Contract amount.
All Bidders must attend a mandatory pre-bid meeting at the Project Site, located at Parking Lot 9 at University
of Maine at Farmington, on Thursday, October 22, 2015 at 10:00 AM. Attendance at this meeting by Bidders
or qualified representative is a mandatory prerequisite for the acceptance of a bid. This will be the only time the
site will be available for inspection. Copies of solicitation documents will not be available at the pre-bid
meeting. Acquiring or reviewing those documents prior to the meeting is advised.
Project Summary: Furnish and install one (1) 18,000 Gallon LP Gas Propane Tank System and appurtenances,
which will provide backup fuel to the new Central Heating Plant, current scheduled to go online in January
2016.
The electronic documents (.pdf) may be examined and downloaded at the following site:
http://www2.umf.maine.edu/facilities/advertisements/
In complying with the letter and spirit of applicable laws and pursuing its own goal of diversity, the University
of Maine System shall not discriminate on the grounds of race, color, religion, sex, sexual orientation, including
transgender status or gender expression, national origin, citizenship status, age, disability, genetic information,
or veterans status in employment, education, and all other areas of the University System. The University
provides reasonable accommodations to qualified individuals with disabilities upon request. General
contractors, subcontractors, and product suppliers bidding on this project must subscribe and adhere to same.
UNIVERSITY OF MAINE AT FARMINGTON
Laurie Gardner, Chief Business Officer, for
University of Maine System Board of Trustees
END OF SECTION 00 11 13
UMF CHP LP Gas Tank
00 11 13 – 1
Advertisement for Bids
SECTION 00 21 13
INSTRUCTIONS TO BIDDERS
1.
At the time of the opening of bids, each bidder will be presumed to have inspected the site and to have read
and to be thoroughly familiar with the plans and contract documents, including all addenda. The failure or
omission of any bidder to receive or examine any form, instrument, or document shall not relieve any
bidder from any obligation in respect to the bid. The Owner reserves the right to accept or reject any or all
bids as may best serve the interests of the University of Maine System.
2.
Subject to the University System’s right, reserved herein, to accept or reject any or all bids, the General
Contractor will be selected on the basis of the sum of the lowest base bid, plus such of the alternates as the
University System desires to use.
3.
The University System is exempt from the payment of Federal Excise Taxes on articles not for resale and
the Federal Transportation Tax on all shipments. The Contractor shall quote less these taxes. Upon
application, exemption certificates will be furnished when required.
4.
No proposal may be withdrawn during a period of thirty (30) calendar days immediately following the
opening thereof.
5.
No contract may be assigned, sublet or transferred without the written consent of the University of Maine
System.
6.
All individuals not residents of this State must comply with the provisions of 14 MRSA §704-A.
7.
The successful bidder, or bidders, will be required to furnish 100% Contract Bonds to cover the execution
of the contract, in accordance with Article 11 of the AIA Document A201 – 2007 General Conditions of the
Contract for Construction.
8.
Contractors may be required to furnish a statement of their business experience, record of accomplishments,
and financial responsibility, at the discretion of the University System.
9.
The base bid shall be based on the materials, methods, equipment and products, as specified.
10. Bidders shall submit the bid on the Bid Form provided in the Specifications, Section 00 41 13.
11. Any materials, methods, equipment and products not herein specified, but worthy of consideration by any
General or Subcontractor, may be introduced by a separate letter attached to the regular bid. The Bidder
shall state the cost comparison with the specified materials, methods, equipment and products, and the
reason for the suggested substitution. It shall be understood by all bidders that the attached letter proposing
substitutions shall not be used to determine the low bidder and that all bids are based on specified products.
12. Telegraphic or facsimile proposals will not be considered, but modification of proposals already submitted
will be considered if received prior to the hour set for receipt of proposals. If the telegram or facsimile
discloses the amount of the proposal, the proposal will be declared invalid. The bidder bears full
responsibility to assure that the correction is delivered to the proper location and within the time required.
13. Where a bidder wishes a product to be considered an “approved equal” for bidding purposes, the product,
along with all supporting documentation, shall be submitted to the architect for review a minimum of 10
calendar days prior to the bid opening date or the file bid due date, if file bids are required on the project.
Products which are determined to be an “approved equal” for bidding purposes shall be listed in an
addendum issued so as to be received by bidders no less than 72 hours prior to the bid date or the file bid
due date if file bids are required.
14. Where the Bid Form requires the tabulation of subcontractors other than “File Bidders,” the Bidder shall
list the name of the firm the bidder intends to use in the event the bidder receives the contract award.
UMF CHP LP Gas Tank System
00 21 13 – 1
Instructions to Bidders
15. Bidders may appeal the award decision by submitting a written protest to the University of Maine System
Director of Facilities within five (5) business days of the date of the award notice (Notice of Award) with a
copy of the protest to the successful bidder. The protest must contain a statement of the basis for the
challenge.
END OF SECTION 00 21 13
UMF CHP LP Gas Tank System
00 21 13 – 2
Instructions to Bidders
SECTION 00 41 13
BID FORM – SHORT FORM
BIDDER:
Physical/Street Address
City, State ZIP
University of Maine at Farmington
Office of Facilities Management
c/o Jeffrey McKay, Director of Facilities Management
Farmington Falls Road
Farmington ME 04938
Having carefully examined the form of contract, general conditions and plans and specifications contained therein for
UMF Central Heating Plant LP Gas Tank System, as well as the premises and conditions affecting the work, we the
undersigned propose to furnish all labor, equipment and materials necessary for and reasonably
incidental to the construction and completion of this contract for the sum of
Dollars ($
).
Alternate prices as follows:
Alternate 1 DEDUCT FOR LEAK DETECTION SYSTEM
$
Alternate 2 DEDUCT FOR WOOD POST BOLLARDS
$
Alternate 3 DEDUCT FOR CONCRETE BARRICADES IN LIEU OF BOLLARDS $
This proposal includes the cost of 100% Performance Bond plus 100% Payment Bond.
The receipt of the following addenda to plans and specifications is hereby acknowledged:
ADDENDUM #
DATED
ADDENDUM #
DATED
ADDENDUM #
DATED
DATED
ADDENDUM #
Any material or materials not specified in the bidding document but worthy of consideration may be introduced by the
bidder by a separate letter attached to this Bid. A cost comparison must be included giving the comparison with the
Material specified and the reason for the suggested substitution. The basic bid shall be as specified.
The undersigned agrees, if this Bid is accepted to sign a contract and deliver it, along with the bonds and affidavits for all
insurance specified within twelve (12) calendar days after the date of notification of such acceptance, except if the 12th
day falls on a Saturday, Sunday or holiday, then the conditions will be fulfilled if the required documents are received
before 12 o’clock noon on the day following the holiday, or the Monday following the Saturday or Sunday, and as a
guarantee thereof, herewith submits a bid bond as required.
The undersigned agrees, if awarded the Contract, to complete the work on or before
.
The undersigned also agrees, if awarded the Contract, that no more than 80% of the contract amount will be sublet to
other contractors.
Signed (by individual authorized to sign contract)
By (printed name & title)
Phone
PO Box (if applicable)
Email
NOTE: If bidder is a corporation, write State of Incorporation, and if a partnership, give full names of all partners.
END OF SECTION 00 41 13
UMF CHP LP Gas Tank System
00 41 13 – Page 1
October 10, 2015
SECTION 00 43 13
BID SECURITY FORM
KNOW ALL BY THESE PRESENTS, THAT WE, the undersigned, as PRINCIPAL
, and
as SURETY, are hereby held and firmly bound unto the Treasurer
of the UNIVERSITY OF MAINE SYSTEM in the penal sum of
for the payment of which, well and truly to
be made, we hereby jointly and severally bind ourselves, our heirs, executors, administrators, successors and
assigns, signed this
day of
, 20
.
The condition of the above obligation is such that whereas the Principal has submitted to UNIVERSITY OF
MAINE AT FARMINGTON a certain proposal, attached hereto and hereby made a part hereof, to enter into a
contract in writing for the UMF CHP LP Gas Tank System.
NOW THEREFORE,
(a) If said proposal shall be rejected, or, in the alternate
(b) If said proposal shall be accepted and the Principal shall execute and deliver a contract in the form of
contract attached hereto (properly completed in accordance with said proposal) and shall furnish a bond for
faithful performance of said contract, and for the payment of all persons performing labor or furnishing
materials in connection therewith, and shall in all other respects perform the agreement created by the
acceptance of said proposal, then this obligation shall be void, otherwise the same shall remain in force and
effect: It being expressly understood and agreed that the liability of the surety for any and all claims
hereunder shall, in no event, exceed the penal amount of this obligation as herein stated.
The Surety, for value received, hereby stipulates and agrees that the obligation of said Surety and its bond shall
be in no way impaired or affected by any extension of the time within which the principal may accept such
proposal: and said Surety does hereby waive notice of any such extension.
In the event suit is brought upon this bond by the Treasurer of the UNIVERSITY OF MAINE SYSTEM, Surety
shall pay reasonable attorneys’ fees and costs incurred by the Treasurer of the UNIVERSITY OF MAINE
SYSTEM in such suit.
IN WITNESS WHEREOF, the Principal and Surety have hereunto set their hands and seals, and such of them
as are corporations have caused their corporate seals to be hereto affixed and these presents to be signed by their
proper officers, the day and year first set above.
PRINCIPAL:
By:
L.S.
SURETY:
SURETY ADDRESS:
By:
L.S.
**DO NOT ALTER LANGUAGE**
END OF SECTION 00 43 13
UMF CHP LP Gas Tank System
00 43 13
Page 1
June 26, 2015
SECTION 00 51 00
NOTICE OF AWARD
DATE
[Contractor]
[Company]
[address]
[City ST ZIP]
RE:
NOTICE OF AWARD – NAME OF PROJECT
UNIVERSITY OF MAINE AT FARMINGTON, FARMINGTON, MAINE
Dear [Contractor]:
You are hereby notified that the University of Maine at Farmington, acting on behalf of the University of Maine
System, accepts your Bid of $??.00 for the above named project, subject to final resolution of any bid protests
and the parties’ ability to establish and confirm final terms, as well as the execution of a written contract and
your furnishing satisfactory bonds within twelve (12) calendar days as provided in the bidding documents.
This Notice of Award will permit you to proceed with the ordering of materials and scheduling the work so that
the project can be completed on time. Should you fail to execute a contract or furnish satisfactory bonds within
the stipulated time, the bid bond accompanying your proposal will be forfeited to the University of Maine
System as liquidated damages.
Enclosed are four (4) originals of your contract agreement for signature. Further, please have your surety
provide four (4) originals each of the Performance Bond and the Payment Bond, as prescribed in Sections 00 61
13.13 and 00 61 13.16 of the bid document, and a properly executed “Power of Attorney.” Please advise your
surety agent that the bonds should carry the same date as this Notice of Award and the Contract Agreement. All
originals of the signed contract, bonds and insurance certificates should be forwarded directly to Jeffrey
McKay in the Office of Facilities Management at the address listed on this letterhead. Once they are
completely signed, a bound copy of the contract will be returned for your use.
Prior to the start of any work on the construction site, Facilities Management must receive Certificates of
Liability Insurance as specified in Article 11 of the AIA Document A201 – 2007 General Conditions of the
Contract for Construction and Section 00 73 00.01 University of Maine Supplementary Conditions. Please
advise your surety that the certificate holder should be as follows: University of Maine System; 16 Central
Street; Bangor, Maine 04401.
The day-to-day administrative and technical details of this project will be handled by the Architect, [Architect];
[Address]; [Phone]. All correspondence relative to the day-to-day administration of the project should be
directed to [Architect].
A pre-construction conference on this project will be scheduled as soon as possible. This conference must be
attended by your firm’s authorized representative as well as your project superintendent.
Sincerely,
Laurie Gardner
Executive Director for Finance and Administration
Enclosures
cc: UM System Office
END OF SECTION 00 51 00
SECTION 00 52 13
UNIVERSITY OF MAINE SYSTEM
CONSTRUCTION CONTRACT AGREEMENT
THIS AGREEMENT made the
day of
, in the year Two Thousand and
, by and between the
Contractor
and the University of Maine System, acting by and through the University of Maine at
Farmington, Office of Facilities Management, Farmington Falls Road, Farmington ME 04938, hereinafter called the
Owner.
WITNESSETH: That the Owner and the Contractor for the considerations hereinafter named agree as follows:
ARTICLE 1: SCOPE OF THE WORK
The Contractor shall furnish all of the materials and perform all of the work described in the Contract Documents
entitled UMF CHP LP GAS Tank System by Competitive Energy Services, LLC and Dirigo Architectural
Engineering, LLC, Dirigo is acting as and in these Contract Documents entitled by Owner’s Representative, and
Architect/Engineer as it relates to non-design related and contractual items.
ARTICLE 2: START AND TIME OF COMPLETION
The date of commencement of work shall be the date of this Agreement or the following date
and shall be
subject to adjustments as
substantially completed on or before
January 1, 2016
provided in the Contract Documents.
The Contractor and the Contractor’s Surety, if any, shall be liable for and shall pay the Owner the following
stipulated liquidated damages for each calendar day of delay after the date established for Substantial Completion
until the Work is substantially complete: $675.00 per day
ARTICLE 3: THE CONTRACT SUM
The Owner shall pay the Contractor for the performance of the Contract as follows
Dollars ($
)
The Contract Sum is based upon the following alternatives and Unit Prices, if any, which are described in the
Contract Documents and are hereby accepted by the Owner:
Alternate (1)
Alternate (2)
Alternate (3)
Unit Prices:
Item: N/A
Item: N/A
Price:
Price:
Final payment shall be made after completion and acceptance of the work as provided in the Contract Documents.
ARTICLE 4: THE CONTRACT DOCUMENTS
.1
.2
.3
.4
.5
.6
This Agreement.
AIA Document A201 – 2007 General Conditions of the Contract for Construction, as modified by
University of Maine System 00 73 00.01 Supplementary Conditions to A201 – 2007.
The Specifications as outlined in the Project Manual
The Drawings as listed in the Project Manual.
The Addenda – (List the addenda and dates issued).
Other documents, if any: (List any other documents that are intended to be part of the Contract).
UMF CHP LP Gas Tank
System
00 52 13
Page 1
October 10, 2015
ARTICLE 5 : OWNE R’ S REPRESENTATIVES
The Owner’s Representative on this project will be Laurie Gardner, Chief Business Officer, who is authorized to sign
contracts and other legal documents related to this project on behalf of the Owner.
The Owner’s Project Manager on this project will be Thomas W. Perkins, PE, Dirigo A/E
The Owner and the Contractor hereby agree to the full performance of the covenants herein.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement in
and year first above written.
UNIVERSITY OF MAINE SYSTEM
quadruplicate
on the day
CONTRACTOR
By:
By:
Laurie Gardner
Chief Business Officer
University of Maine at Farmington
Name
Title
Witness
Witness
END OF SECTION 00 52 13
UMF CHP LP Gas Tank
System
00 52 13
Page 2
October 10, 2015
SECTION 00 61 13.13
PERFORMANCE BOND FORM
_______________________________
Bond No.
KNOW ALL BY THESE PRESENTS THAT (1)
(2)
of
and State of
and (3)
a corporation duly organized under the laws of the State of
having a usual place of business in
and firmly bound unto the University of Maine System in the sum of
, as PRINCIPAL,
,
and
, as SURETY, are held
Dollars
($
), to be paid said Treasurer of the University of Maine System, or successor
in office, for which payment well and truly to be made, Principal and Surety bind themselves, their heirs,
executors and administrators, successors and assigns, jointly and severally by these presents.
The condition of this obligation is such that if the Principal shall promptly and faithfully perform the Contract
entered into on the (4)
day of
, A.D., 20
for the
construction of (5)
then this obligation shall be null and
UMF CHP LP Gas Tank System
void; otherwise, it shall remain in full force and effect.
The Surety hereby waives notice of any alteration or extension of time made by the University of Maine
System.
Signed and sealed this (4)
WITNESSES:
day of
, 20
.
SIGNATURES:
LS
LS
LS
Bonding Company Agent:
Company:
Street:
City, State, Zip:
Telephone:
(1) Correct name of Contractor.
(2) A corporation, a partnership, or an individual, as the case may be.
(3) Correct name of Surety.
(4) Same date as that of contract.
(5) Name of Project as designated in contract.
If Contractor is a partnership, all partners should execute bond. A Power of Attorney document, together with a
statement that it still is in effect shall be provided by the person executing this bond. Bond must be
countersigned by a Resident Maine Agent.
**DO NOT ALTER LANGUAGE**
END OF SECTION 00 61 13.13
SECTION 00 61 13.16
PAYMENT BOND FORM
_______________________________
Bond No.
KNOW ALL BY THESE PRESENTS THAT (1)
(2)
of
and State of
and (3)
a corporation duly organized under the laws of the State of
having a usual place of business in
and firmly bound unto the University of Maine System in the sum of
, as PRINCIPAL,
,
and
, as SURETY, are held
Dollars
($
), for the use and benefit of claimants* as herein below defined, for the
payment whereof Principal and Surety bind themselves, their heirs, executors and administrators, successors
and assigns, jointly and severally by these presents.
The condition of this obligation is such that if the Principal shall promptly satisfy all claims and demands
incurred for all labor and materials, used or required by the Principal in connection with the work contemplated
in the Contract entered into on the (4)
day of
, A.D., 20
for the
UMF CHP LP Gas Tank System
construction of (5)
and shall fully reimburse the
obligee for all outlay and expense which said obligee may incur in making good any default of said
principal, then this obligation shall be null and void; otherwise, it shall remain in full force and effect.
*A Claimant is defined as one having a direct contract with the Principal or with a subcontractor of the
Principal for labor, material, or both, used or reasonably required for use in the performance of the contract.
Signed and sealed this (6)
WITNESSES:
day of
, 20
.
SIGNATURES:
LS
LS
LS
Bonding Company Agent:
Company:
Street:
City, State, Zip:
Telephone:
(1) Correct name of Contractor.
(2) A corporation, a partnership, or an individual, as the case may be.
(3) Correct name of Surety.
(4) Same date as that of contract.
(5) Name of Project as designated in contract.
(6) Same date as that of Contract.
If contractor is a partnership, all partners should execute bond. A Power of Attorney document, together with a
statement that it still is in effect shall be provided by the person executing this bond. Bond must be
countersigned by a Resident Maine Agent.
**DO NOT ALTER LANGUAGE**
END OF SECTION 00 61 13.16
SAMPLE
UMF Lockwood Hall
UMF Science Laboratory Renovation
Phase 1 Kitchen Renovation
00 62 16
00Page
62 116 - 1
June 26, 2015
Supplemental Attachment for ACORD
Certificate of Insurance Form
00 62 16.10
ACORD
TM
DATE (MM/DD/YY)
CERTIFICATE OF LIABILITY INSURANCE
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
PRODUCER
INSURERS AFFORDING COVERAGE
INSURED
INSURER A:
INSURER B:
INSURER C:
INSURER D:
INSURER E:
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR
LTR
TYPE OF INSURANCE
POLICY EFFECTIVE
DATE (MM/DD/YY)
POLICY NUMBER
POLICY EXPIRATION
DATE (MM/DD/YY)
GENERAL LIABILITY
COMMERCIAL GENERAL LIABILITY
CLAIMS MADE
OCCUR
AUTOMOBILE LIABILITY
pl
ANY AUTO
ALL OWNED AUTOS
SCHEDULED AUTOS
HIRED AUTOS
GARAGE LIABILITY
ANY AUTO
EXCESS LIABILITY
OCCUR
CLAIMS MADE
DEDUCTIBLE
RETENTION
Sa
m
NON-OWNED AUTOS
$
EACH OCCURRENCE
$
FIRE DAMAGE (Any one fire)
$
MED EXP (Any one person)
$
PERSONAL & ADV INJURY
$
GENERAL AGGREGATE
$
PRODUCTS - COMP/OP AGG
$
e
GEN’L AGGREGATE LIMIT APPLIES PER:
PROPOLICY
LOC
JECT
LIMITS
WORKERS COMPENSATION AND
EMPLOYERS’ LIABILITY
COMBINED SINGLE LIMIT
(Ea accident)
$
BODILY INJURY
(Per person)
$
BODILY INJURY
(Per accident)
$
PROPERTY DAMAGE
(Per accident)
$
AUTO ONLY - EA ACCIDENT
$
OTHER THAN
AUTO ONLY:
EA ACC
$
AGG
$
EACH OCCURRENCE
$
AGGREGATE
$
$
$
$
WC STATUTORY LIMITS
OTHER
E.L. EACH ACCIDENT
$
E.L. DISEASE - EA EMPLOYEE $
E.L. DISEASE - POLICY LIMIT
$
OTHER
DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES/EXCLUSIONS ADDED BY ENDORSEMENT/SPECIAL PROVISIONS
University of Maine System is named an additional insured under General Liability.
Project: UMF Science Laboratory Renovation
CERTIFICATE HOLDER
ADDITIONAL INSURED; INSURER LETTER:
CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL
University of Maine System
16 Central Street
Bangor ME 04401
DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
REPRESENTATIVES.
AUTHORIZED REPRESENTATIVE
ACORD 25-S (7/97)
UMF Science Laboratory Renovation
c ACORD CORPORATION 1988
O
00 62 16.10 - 1
Certificate of Insurance Form
00 62 16.10
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
Sa
m
pl
e
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
ACORD 25-S (7/97)
UMF Science Laboratory Renovation
00 62 16.10 - 2
Certificate of Insurance Form
00 62 16.11
COMMERCIAL GENERAL LIABILITY
CG 00 01 12 04
COMMERCIAL GENERAL LIABILITY COVERAGE FORM
e
b. This insurance applies to "bodily injury" and
"property damage" only if:
(1) The "bodily injury" or "property damage" is
caused by an "occurrence" that takes place
in the "coverage territory";
(2) The "bodily injury" or "property damage"
occurs during the policy period; and
(3) Prior to the policy period, no insured listed
under Paragraph 1. of Section II – Who Is
An Insured and no "employee" authorized by
you to give or receive notice of an "occurrence" or claim, knew that the "bodily injury"
or "property damage" had occurred, in whole
or in part. If such a listed insured or authorized "employee" knew, prior to the policy period, that the "bodily injury" or "property
damage" occurred, then any continuation,
change or resumption of such "bodily injury"
or "property damage" during or after the policy period will be deemed to have been
known prior to the policy period.
c. "Bodily injury" or "property damage" which
occurs during the policy period and was not,
prior to the policy period, known to have occurred by any insured listed under Paragraph 1.
of Section II – Who Is An Insured or any "employee" authorized by you to give or receive notice of an "occurrence" or claim, includes any
continuation, change or resumption of that
"bodily injury" or "property damage" after the
end of the policy period.
d. "Bodily injury" or "property damage" will be
deemed to have been known to have occurred
at the earliest time when any insured listed under Paragraph 1. of Section II – Who Is An Insured or any "employee" authorized by you to
give or receive notice of an "occurrence" or
claim:
(1) Reports all, or any part, of the "bodily injury"
or "property damage" to us or any other insurer;
(2) Receives a written or verbal demand or
claim for damages because of the "bodily injury" or "property damage"; or
(3) Becomes aware by any other means that
"bodily injury" or "property damage" has occurred or has begun to occur.
Sa
m
pl
Various provisions in this policy restrict coverage.
Read the entire policy carefully to determine rights,
duties and what is and is not covered.
Throughout this policy the words "you" and "your" refer
to the Named Insured shown in the Declarations, and
any other person or organization qualifying as a
Named Insured under this policy. The words "we", "us"
and "our" refer to the company providing this insurance.
The word "insured" means any person or organization
qualifying as such under Section II – Who Is An Insured.
Other words and phrases that appear in quotation
marks have special meaning. Refer to Section V –
Definitions.
SECTION I – COVERAGES
COVERAGE A BODILY INJURY AND PROPERTY
DAMAGE LIABILITY
1. Insuring Agreement
a. We will pay those sums that the insured becomes legally obligated to pay as damages because of "bodily injury" or "property damage" to
which this insurance applies. We will have the
right and duty to defend the insured against any
"suit" seeking those damages. However, we will
have no duty to defend the insured against any
"suit" seeking damages for "bodily injury" or
"property damage" to which this insurance does
not apply. We may, at our discretion, investigate
any "occurrence" and settle any claim or "suit"
that may result. But:
(1) The amount we will pay for damages is
limited as described in Section III – Limits Of
Insurance; and
(2) Our right and duty to defend ends when we
have used up the applicable limit of insurance in the payment of judgments or settlements under Coverages A or B or medical
expenses under Coverage C.
No other obligation or liability to pay sums or
perform acts or services is covered unless explicitly provided for under Supplementary Payments – Coverages A and B.
CG 00 01 12 04
© ISO Properties, Inc., 2003
Page 1 of 15
†
00 62 16.11
e
c. Liquor Liability
"Bodily injury" or "property damage" for which
any insured may be held liable by reason of:
(1) Causing or contributing to the intoxication of
any person;
(2) The furnishing of alcoholic beverages to a
person under the legal drinking age or under
the influence of alcohol; or
(3) Any statute, ordinance or regulation relating
to the sale, gift, distribution or use of alcoholic beverages.
This exclusion applies only if you are in the
business of manufacturing, distributing, selling,
serving or furnishing alcoholic beverages.
d. Workers' Compensation And Similar Laws
Any obligation of the insured under a workers'
compensation, disability benefits or unemployment compensation law or any similar law.
e. Employer's Liability
"Bodily injury" to:
(1) An "employee" of the insured arising out of
and in the course of:
(a) Employment by the insured; or
(b) Performing duties related to the conduct
of the insured's business; or
(2) The spouse, child, parent, brother or sister
of that "employee" as a consequence of
Paragraph (1) above.
This exclusion applies:
(1) Whether the insured may be liable as an
employer or in any other capacity; and
(2) To any obligation to share damages with or
repay someone else who must pay damages because of the injury.
This exclusion does not apply to liability assumed by the insured under an "insured contract".
Sa
m
pl
e. Damages because of "bodily injury" include
damages claimed by any person or organization
for care, loss of services or death resulting at
any time from the "bodily injury".
2. Exclusions
This insurance does not apply to:
a. Expected Or Intended Injury
"Bodily injury" or "property damage" expected or
intended from the standpoint of the insured.
This exclusion does not apply to "bodily injury"
resulting from the use of reasonable force to
protect persons or property.
b. Contractual Liability
"Bodily injury" or "property damage" for which
the insured is obligated to pay damages by reason of the assumption of liability in a contract or
agreement. This exclusion does not apply to liability for damages:
(1) That the insured would have in the absence
of the contract or agreement; or
(2) Assumed in a contract or agreement that is
an "insured contract", provided the "bodily
injury" or "property damage" occurs subsequent to the execution of the contract or
agreement. Solely for the purposes of liability assumed in an "insured contract", reasonable attorney fees and necessary litigation expenses incurred by or for a party
other than an insured are deemed to be
damages because of "bodily injury" or
"property damage", provided:
(a) Liability to such party for, or for the cost
of, that party's defense has also been
assumed in the same "insured contract";
and
(b) Such attorney fees and litigation expenses are for defense of that party
against a civil or alternative dispute resolution proceeding in which damages to
which this insurance applies are alleged.
Page 2 of 15
© ISO Properties, Inc., 2003
CG 00 01 12 04
†
00 62 16.11
e
(d) At or from any premises, site or location
on which any insured or any contractors
or subcontractors working directly or indirectly on any insured's behalf are performing operations if the "pollutants" are
brought on or to the premises, site or location in connection with such operations
by such insured, contractor or subcontractor. However, this subparagraph
does not apply to:
(i) "Bodily injury" or "property damage"
arising out of the escape of fuels, lubricants or other operating fluids
which are needed to perform the
normal electrical, hydraulic or mechanical functions necessary for the
operation of "mobile equipment" or its
parts, if such fuels, lubricants or other
operating fluids escape from a vehicle
part designed to hold, store or receive
them. This exception does not apply if
the "bodily injury" or "property
damage" arises out of the intentional
discharge, dispersal or release of the
fuels, lubricants or other operating
fluids, or if such fuels, lubricants or
other operating fluids are brought on
or to the premises, site or location
with the intent that they be discharged, dispersed or released as
part of the operations being performed by such insured, contractor or
subcontractor;
(ii) "Bodily injury" or "property damage"
sustained within a building and
caused by the release of gases,
fumes or vapors from materials
brought into that building in connection with operations being performed
by you or on your behalf by a contractor or subcontractor; or
(iii) "Bodily injury" or "property damage"
arising out of heat, smoke or fumes
from a "hostile fire".
(e) At or from any premises, site or location
on which any insured or any contractors
or subcontractors working directly or indirectly on any insured's behalf are performing operations if the operations are
to test for, monitor, clean up, remove,
contain, treat, detoxify or neutralize, or in
any way respond to, or assess the effects of, "pollutants".
Sa
m
pl
f. Pollution
(1) "Bodily injury" or "property damage" arising
out of the actual, alleged or threatened discharge, dispersal, seepage, migration, release or escape of "pollutants":
(a) At or from any premises, site or location
which is or was at any time owned or occupied by, or rented or loaned to, any insured. However, this subparagraph does
not apply to:
(i) "Bodily injury" if sustained within a
building and caused by smoke,
fumes, vapor or soot produced by or
originating from equipment that is
used to heat, cool or dehumidify the
building, or equipment that is used to
heat water for personal use, by the
building's occupants or their guests;
(ii) "Bodily injury" or "property damage"
for which you may be held liable, if
you are a contractor and the owner or
lessee of such premises, site or location has been added to your policy as
an additional insured with respect to
your ongoing operations performed
for that additional insured at that
premises, site or location and such
premises, site or location is not and
never was owned or occupied by, or
rented or loaned to, any insured,
other than that additional insured; or
(iii) "Bodily injury" or "property damage"
arising out of heat, smoke or fumes
from a "hostile fire";
(b) At or from any premises, site or location
which is or was at any time used by or
for any insured or others for the handling,
storage,
disposal,
processing
or
treatment of waste;
(c) Which are or were at any time transported, handled, stored, treated, disposed of, or processed as waste by or
for:
(i) Any insured; or
(ii) Any person or organization for whom
you may be legally responsible; or
CG 00 01 12 04
© ISO Properties, Inc., 2003
Page 3 of 15
†
00 62 16.11
e
(5) "Bodily injury" or "property damage" arising
out of:
(a) The operation of machinery or equipment
that is attached to, or part of, a land
vehicle that would qualify under the
definition of "mobile equipment" if it were
not subject to a compulsory or financial
responsibility law or other motor vehicle
insurance law in the state where it is licensed or principally garaged; or
(b) the operation of any of the machinery or
equipment listed in Paragraph f.(2) or
f.(3) of the definition of "mobile equipment".
h. Mobile Equipment
"Bodily injury" or "property damage" arising out
of:
(1) The transportation of "mobile equipment" by
an "auto" owned or operated by or rented or
loaned to any insured; or
(2) The use of "mobile equipment" in, or while in
practice for, or while being prepared for, any
prearranged racing, speed, demolition, or
stunting activity.
i. War
"Bodily injury" or "property damage", however
caused, arising, directly or indirectly, out of:
(1) War, including undeclared or civil war;
(2) Warlike action by a military force, including
action in hindering or defending against an
actual or expected attack, by any government, sovereign or other authority using
military personnel or other agents; or
(3) Insurrection, rebellion, revolution, usurped
power, or action taken by governmental authority in hindering or defending against any
of these.
j. Damage To Property
"Property damage" to:
(1) Property you own, rent, or occupy, including
any costs or expenses incurred by you, or
any other person, organization or entity, for
repair, replacement, enhancement, restoration or maintenance of such property for any
reason, including prevention of injury to a
person or damage to another's property;
(2) Premises you sell, give away or abandon, if
the "property damage" arises out of any part
of those premises;
(3) Property loaned to you;
(4) Personal property in the care, custody or
control of the insured;
Sa
m
pl
(2) Any loss, cost or expense arising out of any:
(a) Request, demand, order or statutory or
regulatory requirement that any insured
or others test for, monitor, clean up, remove, contain, treat, detoxify or neutralize, or in any way respond to, or assess
the effects of, "pollutants"; or
(b) Claim or "suit" by or on behalf of a governmental authority for damages because of testing for, monitoring, cleaning
up, removing, containing, treating, detoxifying or neutralizing, or in any way
responding to, or assessing the effects
of, "pollutants".
However, this paragraph does not apply to
liability for damages because of "property
damage" that the insured would have in the
absence of such request, demand, order or
statutory or regulatory requirement, or such
claim or "suit" by or on behalf of a governmental authority.
g. Aircraft, Auto Or Watercraft
"Bodily injury" or "property damage" arising out
of the ownership, maintenance, use or entrustment to others of any aircraft, "auto" or watercraft owned or operated by or rented or loaned
to any insured. Use includes operation and
"loading or unloading".
This exclusion applies even if the claims against
any insured allege negligence or other
wrongdoing in the supervision, hiring, employment, training or monitoring of others by that
insured, if the "occurrence" which caused the
"bodily injury" or "property damage" involved the
ownership, maintenance, use or entrustment to
others of any aircraft, "auto" or watercraft that is
owned or operated by or rented or loaned to
any insured.
This exclusion does not apply to:
(1) A watercraft while ashore on premises you
own or rent;
(2) A watercraft you do not own that is:
(a) Less than 26 feet long; and
(b) Not being used to carry persons or property for a charge;
(3) Parking an "auto" on, or on the ways next to,
premises you own or rent, provided the
"auto" is not owned by or rented or loaned to
you or the insured;
(4) Liability assumed under any "insured contract" for the ownership, maintenance or use
of aircraft or watercraft; or
Page 4 of 15
© ISO Properties, Inc., 2003
CG 00 01 12 04
†
00 62 16.11
e
n. Recall Of Products, Work Or Impaired
Property
Damages claimed for any loss, cost or expense
incurred by you or others for the loss of use,
withdrawal, recall, inspection, repair, replacement, adjustment, removal or disposal of:
(1) "Your product";
(2) "Your work"; or
(3) "Impaired property";
if such product, work, or property is withdrawn
or recalled from the market or from use by any
person or organization because of a known or
suspected defect, deficiency, inadequacy or
dangerous condition in it.
o. Personal And Advertising Injury
"Bodily injury" arising out of "personal and advertising injury".
p. Electronic Data
Damages arising out of the loss of, loss of use
of, damage to, corruption of, inability to access,
or inability to manipulate electronic data.
As used in this exclusion, electronic data means
information, facts or programs stored as or on,
created or used on, or transmitted to or from computer software, including systems and
applications software, hard or floppy disks, CDROMS, tapes, drives, cells, data processing
devices or any other media which are used with
electronically controlled equipment.
Exclusions c. through n. do not apply to damage by
fire to premises while rented to you or temporarily
occupied by you with permission of the owner. A
separate limit of insurance applies to this coverage
as described in Section III – Limits Of Insurance.
COVERAGE B PERSONAL AND ADVERTISING
INJURY LIABILITY
1. Insuring Agreement
a. We will pay those sums that the insured becomes legally obligated to pay as damages because of "personal and advertising injury" to
which this insurance applies. We will have the
right and duty to defend the insured against any
"suit" seeking those damages. However, we will
have no duty to defend the insured against any
"suit" seeking damages for "personal and advertising injury" to which this insurance does not
apply. We may, at our discretion, investigate
any offense and settle any claim or "suit" that
may result. But:
(1) The amount we will pay for damages is
limited as described in Section III – Limits Of
Insurance; and
Sa
m
pl
(5) That particular part of real property on which
you or any contractors or subcontractors
working directly or indirectly on your behalf
are performing operations, if the "property
damage" arises out of those operations; or
(6) That particular part of any property that must
be restored, repaired or replaced because
"your work" was incorrectly performed on it.
Paragraphs (1), (3) and (4) of this exclusion do
not apply to "property damage" (other than
damage by fire) to premises, including the contents of such premises, rented to you for a period of 7 or fewer consecutive days. A separate
limit of insurance applies to Damage To Premises Rented To You as described in Section III
– Limits Of Insurance.
Paragraph (2) of this exclusion does not apply if
the premises are "your work" and were never
occupied, rented or held for rental by you.
Paragraphs (3), (4), (5) and (6) of this exclusion
do not apply to liability assumed under a sidetrack agreement.
Paragraph (6) of this exclusion does not apply
to "property damage" included in the "productscompleted operations hazard".
k. Damage To Your Product
"Property damage" to "your product" arising out
of it or any part of it.
l. Damage To Your Work
"Property damage" to "your work" arising out of
it or any part of it and included in the "productscompleted operations hazard".
This exclusion does not apply if the damaged
work or the work out of which the damage
arises was performed on your behalf by a subcontractor.
m. Damage To Impaired Property Or Property
Not Physically Injured
"Property damage" to "impaired property" or
property that has not been physically injured,
arising out of:
(1) A defect, deficiency, inadequacy or dangerous condition in "your product" or "your
work"; or
(2) A delay or failure by you or anyone acting on
your behalf to perform a contract or
agreement in accordance with its terms.
This exclusion does not apply to the loss of use
of other property arising out of sudden and accidental physical injury to "your product" or
"your work" after it has been put to its intended
use.
CG 00 01 12 04
© ISO Properties, Inc., 2003
Page 5 of 15
†
00 62 16.11
e
g. Quality Or Performance Of Goods – Failure
To Conform To Statements
"Personal and advertising injury" arising out of
the failure of goods, products or services to
conform with any statement of quality or performance made in your "advertisement".
h. Wrong Description Of Prices
"Personal and advertising injury" arising out of
the wrong description of the price of goods,
products or services stated in your "advertisement".
i. Infringement Of Copyright, Patent,
Trademark Or Trade Secret
"Personal and advertising injury" arising out of
the infringement of copyright, patent, trademark,
trade secret or other intellectual property rights.
However, this exclusion does not apply to infringement, in your "advertisement", of copyright, trade dress or slogan.
j. Insureds In Media And Internet Type
Businesses
"Personal and advertising injury" committed by
an insured whose business is:
(1) Advertising, broadcasting, publishing or
telecasting;
(2) Designing or determining content of websites for others; or
(3) An Internet search, access, content or service provider.
However, this exclusion does not apply to
Paragraphs 14.a., b. and c. of "personal and
advertising injury" under the Definitions Section.
For the purposes of this exclusion, the placing
of frames, borders or links, or advertising, for
you or others anywhere on the Internet, is not
by itself, considered the business of advertising,
broadcasting, publishing or telecasting.
k. Electronic Chatrooms Or Bulletin Boards
"Personal and advertising injury" arising out of
an electronic chatroom or bulletin board the insured hosts, owns, or over which the insured
exercises control.
l. Unauthorized Use Of Another's Name Or
Product
"Personal and advertising injury" arising out of
the unauthorized use of another's name or
product in your e-mail address, domain name or
metatag, or any other similar tactics to mislead
another's potential customers.
Sa
m
pl
(2) Our right and duty to defend end when we
have used up the applicable limit of insurance in the payment of judgments or settlements under Coverages A or B or medical
expenses under Coverage C.
No other obligation or liability to pay sums or
perform acts or services is covered unless explicitly provided for under Supplementary Payments – Coverages A and B.
b. This insurance applies to "personal and advertising injury" caused by an offense arising out of
your business but only if the offense was committed in the "coverage territory" during the policy period.
2. Exclusions
This insurance does not apply to:
a. Knowing Violation Of Rights Of Another
"Personal and advertising injury" caused by or
at the direction of the insured with the knowledge that the act would violate the rights of another and would inflict "personal and advertising
injury".
b. Material Published With Knowledge Of
Falsity
"Personal and advertising injury" arising out of
oral or written publication of material, if done by
or at the direction of the insured with knowledge
of its falsity.
c. Material Published Prior To Policy Period
"Personal and advertising injury" arising out of
oral or written publication of material whose first
publication took place before the beginning of
the policy period.
d. Criminal Acts
"Personal and advertising injury" arising out of a
criminal act committed by or at the direction of
the insured.
e. Contractual Liability
"Personal and advertising injury" for which the
insured has assumed liability in a contract or
agreement. This exclusion does not apply to liability for damages that the insured would have
in the absence of the contract or agreement.
f. Breach Of Contract
"Personal and advertising injury" arising out of a
breach of contract, except an implied contract to
use another's advertising idea in your "advertisement".
Page 6 of 15
© ISO Properties, Inc., 2003
CG 00 01 12 04
†
00 62 16.11
e
b. We will make these payments regardless of
fault. These payments will not exceed the applicable limit of insurance. We will pay reasonable expenses for:
(1) First aid administered at the time of an
accident;
(2) Necessary medical, surgical, x-ray and
dental services, including prosthetic devices;
and
(3) Necessary ambulance, hospital, professional nursing and funeral services.
2. Exclusions
We will not pay expenses for "bodily injury":
a. Any Insured
To any insured, except "volunteer workers".
b. Hired Person
To a person hired to do work for or on behalf of
any insured or a tenant of any insured.
c. Injury On Normally Occupied Premises
To a person injured on that part of premises you
own or rent that the person normally occupies.
d. Workers Compensation And Similar Laws
To a person, whether or not an "employee" of
any insured, if benefits for the "bodily injury" are
payable or must be provided under a workers'
compensation or disability benefits law or a
similar law.
e. Athletics Activities
To a person injured while practicing, instructing
or participating in any physical exercises or
games, sports, or athletic contests.
f. Products-Completed Operations Hazard
Included within the "products-completed operations hazard".
g. Coverage A Exclusions
Excluded under Coverage A.
SUPPLEMENTARY PAYMENTS – COVERAGES A
AND B
1. We will pay, with respect to any claim we investigate or settle, or any "suit" against an insured we
defend:
a. All expenses we incur.
b. Up to $250 for cost of bail bonds required because of accidents or traffic law violations arising out of the use of any vehicle to which the
Bodily Injury Liability Coverage applies. We do
not have to furnish these bonds.
Sa
m
pl
m. Pollution
"Personal and advertising injury" arising out of
the actual, alleged or threatened discharge,
dispersal, seepage, migration, release or escape of "pollutants" at any time.
n. Pollution-Related
Any loss, cost or expense arising out of any:
(1) Request, demand, order or statutory or
regulatory requirement that any insured or
others test for, monitor, clean up, remove,
contain, treat, detoxify or neutralize, or in
any way respond to, or assess the effects of,
"pollutants"; or
(2) Claim or suit by or on behalf of a governmental authority for damages because of
testing for, monitoring, cleaning up, removing, containing, treating, detoxifying or neutralizing, or in any way responding to, or assessing the effects of, "pollutants".
o. War
"Personal and advertising injury", however
caused, arising, directly or indirectly, out of:
(1) War, including undeclared or civil war;
(2) Warlike action by a military force, including
action in hindering or defending against an
actual or expected attack, by any government, sovereign or other authority using
military personnel or other agents; or
(3) Insurrection, rebellion, revolution, usurped
power, or action taken by governmental authority in hindering or defending against any
of these.
COVERAGE C MEDICAL PAYMENTS
1. Insuring Agreement
a. We will pay medical expenses as described
below for "bodily injury" caused by an accident:
(1) On premises you own or rent;
(2) On ways next to premises you own or rent;
or
(3) Because of your operations;
provided that:
(1) The accident takes place in the "coverage
territory" and during the policy period;
(2) The expenses are incurred and reported to
us within one year of the date of the accident; and
(3) The injured person submits to examination,
at our expense, by physicians of our choice
as often as we reasonably require.
CG 00 01 12 04
© ISO Properties, Inc., 2003
Page 7 of 15
†
00 62 16.11
e
(b) Immediately send us copies of any demands, notices, summonses or legal papers received in connection with the
"suit";
(c) Notify any other insurer whose coverage
is available to the indemnitee; and
(d) Cooperate with us with respect to coordinating other applicable insurance available to the indemnitee; and
(2) Provides us with written authorization to:
(a) Obtain records and other information
related to the "suit"; and
(b) Conduct and control the defense of the
indemnitee in such "suit".
So long as the above conditions are met, attorneys'
fees incurred by us in the defense of that indemnitee, necessary litigation expenses incurred by us
and necessary litigation expenses incurred by the
indemnitee at our request will be paid as Supplementary Payments. Notwithstanding the provisions
of Paragraph 2.b.(2) of Section I – Coverage A –
Bodily Injury And Property Damage Liability, such
payments will not be deemed to be damages for
"bodily injury" and "property damage" and will not
reduce the limits of insurance.
Our obligation to defend an insured's indemnitee
and to pay for attorneys' fees and necessary litigation expenses as Supplementary Payments ends
when:
a. We have used up the applicable limit of insurance in the payment of judgments or settlements; or
b. The conditions set forth above, or the terms of
the agreement described in Paragraph f. above,
are no longer met.
SECTION II – WHO IS AN INSURED
1. If you are designated in the Declarations as:
a. An individual, you and your spouse are insureds, but only with respect to the conduct of a
business of which you are the sole owner.
b. A partnership or joint venture, you are an insured. Your members, your partners, and their
spouses are also insureds, but only with respect
to the conduct of your business.
c. A limited liability company, you are an insured.
Your members are also insureds, but only with
respect to the conduct of your business. Your
managers are insureds, but only with respect to
their duties as your managers.
Sa
m
pl
c. The cost of bonds to release attachments, but
only for bond amounts within the applicable limit
of insurance. We do not have to furnish these
bonds.
d. All reasonable expenses incurred by the insured at our request to assist us in the investigation or defense of the claim or "suit", including actual loss of earnings up to $250 a day
because of time off from work.
e. All costs taxed against the insured in the "suit".
f. Prejudgment interest awarded against the insured on that part of the judgment we pay. If we
make an offer to pay the applicable limit of insurance, we will not pay any prejudgment interest based on that period of time after the offer.
g. All interest on the full amount of any judgment
that accrues after entry of the judgment and before we have paid, offered to pay, or deposited
in court the part of the judgment that is within
the applicable limit of insurance.
These payments will not reduce the limits of insurance.
2. If we defend an insured against a "suit" and an
indemnitee of the insured is also named as a party
to the "suit", we will defend that indemnitee if all of
the following conditions are met:
a. The "suit" against the indemnitee seeks damages for which the insured has assumed the liability of the indemnitee in a contract or agreement that is an "insured contract";
b. This insurance applies to such liability assumed
by the insured;
c. The obligation to defend, or the cost of the
defense of, that indemnitee, has also been assumed by the insured in the same "insured contract";
d. The allegations in the "suit" and the information
we know about the "occurrence" are such that
no conflict appears to exist between the interests of the insured and the interests of the indemnitee;
e. The indemnitee and the insured ask us to conduct and control the defense of that indemnitee
against such "suit" and agree that we can assign the same counsel to defend the insured
and the indemnitee; and
f. The indemnitee:
(1) Agrees in writing to:
(a) Cooperate with us in the investigation,
settlement or defense of the "suit";
Page 8 of 15
© ISO Properties, Inc., 2003
CG 00 01 12 04
†
00 62 16.11
e
(b) Rented to, in the care, custody or control
of, or over which physical control is being
exercised for any purpose by
you, any of your "employees", "volunteer
workers", any partner or member (if you are
a partnership or joint venture), or any member (if you are a limited liability company).
b. Any person (other than your "employee" or
"volunteer worker"), or any organization while
acting as your real estate manager.
c. Any person or organization having proper temporary custody of your property if you die, but
only:
(1) With respect to liability arising out of the
maintenance or use of that property; and
(2) Until your legal representative has been
appointed.
d. Your legal representative if you die, but only
with respect to duties as such. That representative will have all your rights and duties under
this Coverage Part.
3. Any organization you newly acquire or form, other
than a partnership, joint venture or limited liability
company, and over which you maintain ownership
or majority interest, will qualify as a Named Insured
if there is no other similar insurance available to
that organization. However:
a. Coverage under this provision is afforded only
until the 90th day after you acquire or form the
organization or the end of the policy period,
whichever is earlier;
b. Coverage A does not apply to "bodily injury" or
"property damage" that occurred before you
acquired or formed the organization; and
c. Coverage B does not apply to "personal and
advertising injury" arising out of an offense
committed before you acquired or formed the
organization.
No person or organization is an insured with respect to
the conduct of any current or past partnership, joint
venture or limited liability company that is not shown
as a Named Insured in the Declarations.
SECTION III – LIMITS OF INSURANCE
1. The Limits of Insurance shown in the Declarations
and the rules below fix the most we will pay regardless of the number of:
a. Insureds;
b. Claims made or "suits" brought; or
c. Persons or organizations making claims or
bringing "suits".
Sa
m
pl
d. An organization other than a partnership, joint
venture or limited liability company, you are an
insured. Your "executive officers" and directors
are insureds, but only with respect to their duties as your officers or directors. Your stockholders are also insureds, but only with respect
to their liability as stockholders.
e. A trust, you are an insured. Your trustees are
also insureds, but only with respect to their duties as trustees.
2. Each of the following is also an insured:
a. Your "volunteer workers" only while performing
duties related to the conduct of your business,
or your "employees", other than either your
"executive officers" (if you are an organization
other than a partnership, joint venture or limited
liability company) or your managers (if you are
a limited liability company), but only for acts
within the scope of their employment by you or
while performing duties related to the conduct of
your business. However, none of these "employees" or "volunteer workers" are insureds
for:
(1) "Bodily injury" or "personal and advertising
injury":
(a) To you, to your partners or members (if
you are a partnership or joint venture), to
your members (if you are a limited liability company), to a co-"employee" while in
the course of his or her employment or
performing duties related to the conduct
of your business, or to your other "volunteer workers" while performing duties related to the conduct of your business;
(b) To the spouse, child, parent, brother or
sister of that co-"employee" or "volunteer
worker" as a consequence of Paragraph
(1)(a) above;
(c) For which there is any obligation to share
damages with or repay someone else
who must pay damages because of the
injury described in Paragraphs (1)(a) or
(b) above; or
(d) Arising out of his or her providing or
failing to provide professional health care
services.
(2) "Property damage" to property:
(a) Owned, occupied or used by,
CG 00 01 12 04
© ISO Properties, Inc., 2003
Page 9 of 15
†
00 62 16.11
e
2. Duties In The Event Of Occurrence, Offense,
Claim Or Suit
a. You must see to it that we are notified as soon
as practicable of an "occurrence" or an offense
which may result in a claim. To the extent possible, notice should include:
(1) How, when and where the "occurrence" or
offense took place;
(2) The names and addresses of any injured
persons and witnesses; and
(3) The nature and location of any injury or
damage arising out of the "occurrence" or
offense.
b. If a claim is made or "suit" is brought against
any insured, you must:
(1) Immediately record the specifics of the claim
or "suit" and the date received; and
(2) Notify us as soon as practicable.
You must see to it that we receive written notice
of the claim or "suit" as soon as practicable.
c. You and any other involved insured must:
(1) Immediately send us copies of any demands, notices, summonses or legal papers
received in connection with the claim or
"suit";
(2) Authorize us to obtain records and other
information;
(3) Cooperate with us in the investigation or
settlement of the claim or defense against
the "suit"; and
(4) Assist us, upon our request, in the enforcement of any right against any person or organization which may be liable to the insured because of injury or damage to which
this insurance may also apply.
d. No insured will, except at that insured's own
cost, voluntarily make a payment, assume any
obligation, or incur any expense, other than for
first aid, without our consent.
3. Legal Action Against Us
No person or organization has a right under this
Coverage Part:
a. To join us as a party or otherwise bring us into a
"suit" asking for damages from an insured; or
Sa
m
pl
2. The General Aggregate Limit is the most we will
pay for the sum of:
a. Medical expenses under Coverage C;
b. Damages under Coverage A, except damages
because of "bodily injury" or "property damage"
included in the "products-completed operations
hazard"; and
c. Damages under Coverage B.
3. The Products-Completed Operations Aggregate
Limit is the most we will pay under Coverage A for
damages because of "bodily injury" and "property
damage" included in the "products-completed operations hazard".
4. Subject to 2. above, the Personal and Advertising
Injury Limit is the most we will pay under Coverage
B for the sum of all damages because of all "personal and advertising injury" sustained by any one
person or organization.
5. Subject to 2. or 3. above, whichever applies, the
Each Occurrence Limit is the most we will pay for
the sum of:
a. Damages under Coverage A; and
b. Medical expenses under Coverage C
because of all "bodily injury" and "property damage" arising out of any one "occurrence".
6. Subject to 5. above, the Damage To Premises
Rented To You Limit is the most we will pay under
Coverage A for damages because of "property
damage" to any one premises, while rented to you,
or in the case of damage by fire, while rented to
you or temporarily occupied by you with permission
of the owner.
7. Subject to 5. above, the Medical Expense Limit is
the most we will pay under Coverage C for all
medical expenses because of "bodily injury" sustained by any one person.
The Limits of Insurance of this Coverage Part apply
separately to each consecutive annual period and to
any remaining period of less than 12 months, starting
with the beginning of the policy period shown in the
Declarations, unless the policy period is extended after
issuance for an additional period of less than 12
months. In that case, the additional period will be
deemed part of the last preceding period for purposes
of determining the Limits of Insurance.
SECTION IV – COMMERCIAL GENERAL LIABILITY
CONDITIONS
1. Bankruptcy
Bankruptcy or insolvency of the insured or of the
insured's estate will not relieve us of our obligations
under this Coverage Part.
Page 10 of 15
© ISO Properties, Inc., 2003
CG 00 01 12 04
†
00 62 16.11
e
When this insurance is excess, we will have no
duty under Coverages A or B to defend the insured against any "suit" if any other insurer has
a duty to defend the insured against that "suit".
If no other insurer defends, we will undertake to
do so, but we will be entitled to the insured's
rights against all those other insurers.
When this insurance is excess over other insurance, we will pay only our share of the amount
of the loss, if any, that exceeds the sum of:
(1) The total amount that all such other insurance would pay for the loss in the absence
of this insurance; and
(2) The total of all deductible and self-insured
amounts under all that other insurance.
We will share the remaining loss, if any, with
any other insurance that is not described in this
Excess Insurance provision and was not bought
specifically to apply in excess of the Limits of
Insurance shown in the Declarations of this
Coverage Part.
c. Method Of Sharing
If all of the other insurance permits contribution
by equal shares, we will follow this method also.
Under this approach each insurer contributes
equal amounts until it has paid its applicable
limit of insurance or none of the loss remains,
whichever comes first.
If any of the other insurance does not permit
contribution by equal shares, we will contribute
by limits. Under this method, each insurer's
share is based on the ratio of its applicable limit
of insurance to the total applicable limits of insurance of all insurers.
5. Premium Audit
a. We will compute all premiums for this Coverage
Part in accordance with our rules and rates.
b. Premium shown in this Coverage Part as advance premium is a deposit premium only. At
the close of each audit period we will compute
the earned premium for that period and send
notice to the first Named Insured. The due date
for audit and retrospective premiums is the date
shown as the due date on the bill. If the sum of
the advance and audit premiums paid for the
policy period is greater than the earned premium, we will return the excess to the first
Named Insured.
c. The first Named Insured must keep records of
the information we need for premium computation, and send us copies at such times as we
may request.
Sa
m
pl
b. To sue us on this Coverage Part unless all of its
terms have been fully complied with.
A person or organization may sue us to recover on
an agreed settlement or on a final judgment against
an insured; but we will not be liable for damages
that are not payable under the terms of this
Coverage Part or that are in excess of the applicable limit of insurance. An agreed settlement
means a settlement and release of liability signed
by us, the insured and the claimant or the claimant's legal representative.
4. Other Insurance
If other valid and collectible insurance is available
to the insured for a loss we cover under Coverages
A or B of this Coverage Part, our obligations are
limited as follows:
a. Primary Insurance
This insurance is primary except when b. below
applies. If this insurance is primary, our obligations are not affected unless any of the other
insurance is also primary. Then, we will share
with all that other insurance by the method described in c. below.
b. Excess Insurance
This insurance is excess over:
(1) Any of the other insurance, whether primary,
excess, contingent or on any other basis:
(a) That is Fire, Extended Coverage,
Builder's Risk, Installation Risk or similar
coverage for "your work";
(b) That is Fire insurance for premises
rented to you or temporarily occupied by
you with permission of the owner;
(c) That is insurance purchased by you to
cover your liability as a tenant for "property damage" to premises rented to you
or temporarily occupied by you with
permission of the owner; or
(d) If the loss arises out of the maintenance
or use of aircraft, "autos" or watercraft to
the extent not subject to Exclusion g. of
Section I – Coverage A – Bodily Injury
And Property Damage Liability.
(2) Any other primary insurance available to you
covering liability for damages arising out of
the premises or operations, or the products
and completed operations, for which you
have been added as an additional insured
by attachment of an endorsement.
CG 00 01 12 04
© ISO Properties, Inc., 2003
Page 11 of 15
†
00 62 16.11
3.
e
4.
b. Any other land vehicle that is subject to a compulsory or financial responsibility law or other
motor vehicle insurance law in the state where it
is licensed or principally garaged.
However, "auto" does not include "mobile equipment".
"Bodily injury" means bodily injury, sickness or
disease sustained by a person, including death resulting from any of these at any time.
"Coverage territory" means:
a. The United States of America (including its
territories and possessions), Puerto Rico and
Canada;
b. International waters or airspace, but only if the
injury or damage occurs in the course of travel
or transportation between any places included
in a. above; or
c. All other parts of the world if the injury or damage arises out of:
(1) Goods or products made or sold by you in
the territory described in a. above;
(2) The activities of a person whose home is in
the territory described in a. above, but is
away for a short time on your business; or
(3) "Personal and advertising injury" offenses
that take place through the Internet or similar electronic means of communication
provided the insured's responsibility to pay damages is determined in a "suit" on the merits, in the
territory described in a. above or in a settlement we
agree to.
"Employee" includes a "leased worker". "Employee" does not include a "temporary worker".
"Executive officer" means a person holding any of
the officer positions created by your charter, constitution, by-laws or any other similar governing
document.
"Hostile fire" means one which becomes uncontrollable or breaks out from where it was intended to
be.
"Impaired property" means tangible property, other
than "your product" or "your work", that cannot be
used or is less useful because:
a. It incorporates "your product" or "your work"
that is known or thought to be defective, deficient, inadequate or dangerous; or
b. You have failed to fulfill the terms of a contract
or agreement;
if such property can be restored to use by:
a. The repair, replacement, adjustment or removal
of "your product" or "your work"; or
Sa
m
pl
6. Representations
By accepting this policy, you agree:
a. The statements in the Declarations are accurate
and complete;
b. Those statements are based upon representations you made to us; and
c. We have issued this policy in reliance upon
your representations.
7. Separation Of Insureds
Except with respect to the Limits of Insurance, and
any rights or duties specifically assigned in this
Coverage Part to the first Named Insured, this insurance applies:
a. As if each Named Insured were the only Named
Insured; and
b. Separately to each insured against whom claim
is made or "suit" is brought.
8. Transfer Of Rights Of Recovery Against Others
To Us
If the insured has rights to recover all or part of any
payment we have made under this Coverage Part,
those rights are transferred to us. The insured must
do nothing after loss to impair them. At our request,
the insured will bring "suit" or transfer those rights
to us and help us enforce them.
9. When We Do Not Renew
If we decide not to renew this Coverage Part, we
will mail or deliver to the first Named Insured
shown in the Declarations written notice of the nonrenewal not less than 30 days before the expiration
date.
If notice is mailed, proof of mailing will be sufficient
proof of notice.
SECTION V – DEFINITIONS
1. "Advertisement" means a notice that is broadcast
or published to the general public or specific market segments about your goods, products or services for the purpose of attracting customers or
supporters. For the purposes of this definition:
a. Notices that are published include material
placed on the Internet or on similar electronic
means of communication; and
b. Regarding web-sites, only that part of a website that is about your goods, products or services for the purposes of attracting customers
or supporters is considered an advertisement.
2. "Auto" means:
a. A land motor vehicle, trailer or semitrailer
designed for travel on public roads, including
any attached machinery or equipment; or
Page 12 of 15
5.
6.
7.
8.
© ISO Properties, Inc., 2003
CG 00 01 12 04
†
00 62 16.11
e
10. "Leased worker" means a person leased to you by
a labor leasing firm under an agreement between
you and the labor leasing firm, to perform duties
related to the conduct of your business. "Leased
worker" does not include a "temporary worker".
11. "Loading or unloading" means the handling of
property:
a. After it is moved from the place where it is
accepted for movement into or onto an aircraft,
watercraft or "auto";
b. While it is in or on an aircraft, watercraft or
"auto"; or
c. While it is being moved from an aircraft, watercraft or "auto" to the place where it is finally delivered;
but "loading or unloading" does not include the
movement of property by means of a mechanical
device, other than a hand truck, that is not attached
to the aircraft, watercraft or "auto".
12. "Mobile equipment" means any of the following
types of land vehicles, including any attached machinery or equipment:
a. Bulldozers, farm machinery, forklifts and other
vehicles designed for use principally off public
roads;
b. Vehicles maintained for use solely on or next to
premises you own or rent;
c. Vehicles that travel on crawler treads;
d. Vehicles, whether self-propelled or not, maintained primarily to provide mobility to permanently mounted:
(1) Power cranes, shovels, loaders, diggers or
drills; or
(2) Road construction or resurfacing equipment
such as graders, scrapers or rollers;
e. Vehicles not described in a., b., c. or d. above
that are not self-propelled and are maintained
primarily to provide mobility to permanently attached equipment of the following types:
(1) Air compressors, pumps and generators,
including spraying, welding, building cleaning, geophysical exploration, lighting and
well servicing equipment; or
(2) Cherry pickers and similar devices used to
raise or lower workers;
f. Vehicles not described in a., b., c. or d. above
maintained primarily for purposes other than the
transportation of persons or cargo.
However, self-propelled vehicles with the following types of permanently attached equipment are not "mobile equipment" but will be
considered "autos":
Sa
m
pl
b. Your fulfilling the terms of the contract or
agreement.
9. "Insured contract" means:
a. A contract for a lease of premises. However,
that portion of the contract for a lease of premises that indemnifies any person or organization
for damage by fire to premises while rented to
you or temporarily occupied by you with permission of the owner is not an "insured contract";
b. A sidetrack agreement;
c. Any easement or license agreement, except in
connection with construction or demolition operations on or within 50 feet of a railroad;
d. An obligation, as required by ordinance, to
indemnify a municipality, except in connection
with work for a municipality;
e. An elevator maintenance agreement;
f. That part of any other contract or agreement
pertaining to your business (including an indemnification of a municipality in connection
with work performed for a municipality) under
which you assume the tort liability of another
party to pay for "bodily injury" or "property
damage" to a third person or organization. Tort
liability means a liability that would be imposed
by law in the absence of any contract or
agreement.
Paragraph f. does not include that part of any
contract or agreement:
(1) That indemnifies a railroad for "bodily injury"
or "property damage" arising out of construction or demolition operations, within 50
feet of any railroad property and affecting
any railroad bridge or trestle, tracks, roadbeds, tunnel, underpass or crossing;
(2) That indemnifies an architect, engineer or
surveyor for injury or damage arising out of:
(a) Preparing, approving, or failing to prepare or approve, maps, shop drawings,
opinions, reports, surveys, field orders,
change orders or drawings and specifications; or
(b) Giving directions or instructions, or failing
to give them, if that is the primary cause
of the injury or damage; or
(3) Under which the insured, if an architect,
engineer or surveyor, assumes liability for
an injury or damage arising out of the insured's rendering or failure to render professional services, including those listed in (2)
above and supervisory, inspection, architectural or engineering activities.
CG 00 01 12 04
© ISO Properties, Inc., 2003
Page 13 of 15
†
00 62 16.11
e
16. "Products-completed operations hazard":
a. Includes all "bodily injury" and "property damage" occurring away from premises you own or
rent and arising out of "your product" or "your
work" except:
(1) Products that are still in your physical possession; or
(2) Work that has not yet been completed or
abandoned. However, "your work" will be
deemed completed at the earliest of the following times:
(a) When all of the work called for in your
contract has been completed.
(b) When all of the work to be done at the
job site has been completed if your contract calls for work at more than one job
site.
(c) When that part of the work done at a job
site has been put to its intended use by
any person or organization other than
another contractor or subcontractor working on the same project.
Work that may need service, maintenance,
correction, repair or replacement, but which
is otherwise complete, will be treated as
completed.
b. Does not include "bodily injury" or "property
damage" arising out of:
(1) The transportation of property, unless the
injury or damage arises out of a condition in
or on a vehicle not owned or operated by
you, and that condition was created by the
"loading or unloading" of that vehicle by any
insured;
(2) The existence of tools, uninstalled equipment or abandoned or unused materials; or
(3) Products or operations for which the classification, listed in the Declarations or in a policy schedule, states that products-completed
operations are subject to the General Aggregate Limit.
17. "Property damage" means:
a. Physical injury to tangible property, including all
resulting loss of use of that property. All such
loss of use shall be deemed to occur at the time
of the physical injury that caused it; or
Sa
m
pl
(1) Equipment designed primarily for:
(a) Snow removal;
(b) Road maintenance, but not construction
or resurfacing; or
(c) Street cleaning;
(2) Cherry pickers and similar devices mounted
on automobile or truck chassis and used to
raise or lower workers; and
(3) Air compressors, pumps and generators,
including spraying, welding, building cleaning, geophysical exploration, lighting and
well servicing equipment.
However, "mobile equipment" does not include any
land vehicles that are subject to a compulsory or
financial responsibility law or other motor vehicle
insurance law in the state where it is licensed or
principally garaged. Land vehicles subject to a
compulsory or financial responsibility law or other
motor vehicle insurance law are considered
"autos".
13. "Occurrence" means an accident, including continuous or repeated exposure to substantially the
same general harmful conditions.
14. "Personal and advertising injury" means injury,
including consequential "bodily injury", arising out
of one or more of the following offenses:
a. False arrest, detention or imprisonment;
b. Malicious prosecution;
c. The wrongful eviction from, wrongful entry into,
or invasion of the right of private occupancy of a
room, dwelling or premises that a person occupies, committed by or on behalf of its owner,
landlord or lessor;
d. Oral or written publication, in any manner, of
material that slanders or libels a person or organization or disparages a person's or organization's goods, products or services;
e. Oral or written publication, in any manner, of
material that violates a person's right of privacy;
f. The use of another's advertising idea in your
"advertisement"; or
g. Infringing upon another's copyright, trade dress
or slogan in your "advertisement".
15. "Pollutants" mean any solid, liquid, gaseous or
thermal irritant or contaminant, including smoke,
vapor, soot, fumes, acids, alkalis, chemicals and
waste. Waste includes materials to be recycled,
reconditioned or reclaimed.
Page 14 of 15
© ISO Properties, Inc., 2003
CG 00 01 12 04
†
00 62 16.11
e
21. "Your product":
a. Means:
(1) Any goods or products, other than real
property, manufactured, sold, handled, distributed or disposed of by:
(a) You;
(b) Others trading under your name; or
(c) A person or organization whose business
or assets you have acquired; and
(2) Containers (other than vehicles), materials,
parts or equipment furnished in connection
with such goods or products.
b. Includes
(1) Warranties or representations made at any
time with respect to the fitness, quality, durability, performance or use of "your product"; and
(2) The providing of or failure to provide warnings or instructions.
c. Does not include vending machines or other
property rented to or located for the use of others but not sold.
22. "Your work":
a. Means:
(1) Work or operations performed by you or on
your behalf; and
(2) Materials, parts or equipment furnished in
connection with such work or operations.
b. Includes
(1) Warranties or representations made at any
time with respect to the fitness, quality, durability, performance or use of "your work",
and
(2) The providing of or failure to provide warnings or instructions.
Sa
m
pl
b. Loss of use of tangible property that is not
physically injured. All such loss of use shall be
deemed to occur at the time of the "occurrence"
that caused it.
For the purposes of this insurance, electronic data
is not tangible property.
As used in this definition, electronic data means information, facts or programs stored as or on, created or used on, or transmitted to or from computer
software, including systems and applications software, hard or floppy disks, CD-ROMS, tapes,
drives, cells, data processing devices or any other
media which are used with electronically controlled
equipment.
18. "Suit" means a civil proceeding in which damages
because of "bodily injury", "property damage" or
"personal and advertising injury" to which this insurance applies are alleged. "Suit" includes:
a. An arbitration proceeding in which such damages are claimed and to which the insured must
submit or does submit with our consent; or
b. Any other alternative dispute resolution proceeding in which such damages are claimed
and to which the insured submits with our consent.
19. "Temporary worker" means a person who is furnished to you to substitute for a permanent "employee" on leave or to meet seasonal or short-term
workload conditions.
20. "Volunteer worker" means a person who is not your
"employee", and who donates his or her work and
acts at the direction of and within the scope of duties determined by you, and is not paid a fee, salary or other compensation by you or anyone else
for their work performed for you.
CG 00 01 12 04
© ISO Properties, Inc., 2003
Page 15 of 15
†
00 62 16.12
00 62 16.13
00 62 16.14
POLICY NUMBER:
COMMERCIAL GENERAL LIABILITY
CG 25 04 03 97
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
DESIGNATED LOCATION(S)
GENERAL AGGREGATE LIMIT
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
SCHEDULE
Designated Location(s):
b. Claims made or “suits” brought; or
c. Persons or organizations making claims
or bringing “suits”.
3. Any payments made under COVERAGE A
for damages or under COVERAGE C for
medical expenses shall reduce the Designated Location General Aggregate Limit for
that designated “location”. Such payments
shall not reduce the General Aggregate Limit
shown in the Declarations nor shall they reduce any other Designated Location General
Aggregate Limit for any other designated
“location” shown in the Schedule above.
4. The limits shown in the Declarations for Each
Occurrence, Fire Damage and Medical Expense continue to apply. However, instead of
being subject to the General Aggregate Limit
shown in the Declarations, such limits will be
subject to the applicable Designated Location
General Aggregate Limit.
Sa
m
pl
A. For all sums which the insured becomes legally
obligated to pay as damages caused by
“occurrences” under COVERAGE A (SECTION
I), and for all medical expenses caused by accidents under COVERAGE C (SECTION I), which
can be attributed only to operations at a single
designated “location” shown in the Schedule
above:
1. A separate Designated Location General
Aggregate Limit applies to each designated
“location”, and that limit is equal to the
amount of the General Aggregate Limit
shown in the Declarations.
2. The Designated Location General Aggregate
Limit is the most we will pay for the sum of all
damages under COVERAGE A, except damages because of “bodily injury” or “property
damage” included in the “products-completed
operations hazard”, and for medical expenses
under COVERAGE C regardless of the number of:
a. Insureds;
e
(If no entry appears above, information required to complete this endorsement will be shown in the Declarations
as applicable to this endorsement.)
CG 25 04 03 97
Copyright, Insurance Services Office, Inc., 1996
Page 1 of 2
o
00 62 16.14
C. When coverage for liability arising out of the
“products-completed operations hazard” is provided, any payments for damages because of
“bodily injury” or “property damage” included in
the “products-completed operations hazard” will
reduce the Products-Completed Operations Aggregate Limit, and not reduce the General Aggregate Limit nor the Designated Location General Aggregate Limit.
D. For the purposes of this endorsement, the Definitions Section is amended by the addition of
the following definition:
“Location” means premises involving the same
or connecting lots, or premises whose connection is interrupted only by a street, roadway, waterway or right-of-way of a railroad.
E. The provisions of Limits Of Insurance (SECTION
III) not otherwise modified by this endorsement
shall continue to apply as stipulated.
Sa
m
pl
e
B. For all sums which the insured becomes legally
obligated to pay as damages caused by
“occurrences” under COVERAGE A (SECTION
I), and for all medical expenses caused by accidents under COVERAGE C (SECTION I), which
cannot be attributed only to operations at a single designated “location” shown in the Schedule
above:
1. Any payments made under COVERAGE A
for damages or under COVERAGE C for
medical expenses shall reduce the amount
available under the General Aggregate Limit
or the Products-Completed Operations Aggregate Limit, whichever is applicable; and
2. Such payments shall not reduce any Designated
Location General Aggregate Limit.
Page 2 of 2
Copyright, Insurance Services Office, Inc., 1996
CG 25 04 03 97
o
SAMPLE
SAMPLE
SECTION 00 62 76.13
SALES TAX FORM
DATE:
VENDOR:
Vendor Name
Vendor Address
Vendor City, State Zip
I hereby certify under penalties of perjury, that:
I am engaged in the performance of a construction contract on a project for the University of Maine System
which is a Sales Tax exempt organization under the Maine Sales and Use Tax Law, Section 1760, subsection 2
and 16:
This project is titled:
UMF CHP LP Gas Tank System
Project Title
The project is located at: UNIVERSITY OF MAINE AT FARMINGTON; FARMINGTON, MAINE
Campus Name or Town
This certificate is issued to cover purchases of materials that will be permanently incorporated into the real
property belonging to the exempt organization or government agency indicated above.
Signed:
Authorized Signature
Name &Title:
Firm Name:
Firm Address:
Firm City, State Zip
END OF SECTION 00 62 76.13
SAMPLE
00 62 79
STORED MATERIALS
University of Maine
5765 Service Building
Orono ME 04469-5765
Project Title:
UMF CHP LP Gas Tank System
Location:
University of Maine at Farmington;
Farmington ME
Contractor:
Materials and/or equipment (hereinafter “Materials”) that have not yet been incorporated into the work may be
delivered and suitably stored, at the site or some other location agreed upon by the Owner. The Materials listed
below have been estimated at 100% of the cost and will be stored at
. The
Owner will reimburse the Contractor based upon the prices included on the Schedule of Values Form, 00 62
73(AIA G703), less the cost of installation. The Contractor must complete sufficient copies of this Stored
Materials Form, 00 62 79, to accompany the Application for Payment. The Contractor shall secure the signature
of its bonding company on all forms and shall also provide a Power of Attorney from the bonding company.
SCHEDULE
Qty
Material/Equipment
Item in AIA G703
Item No
Unit Wholesale
Price
Extended
Wholesale Price
Unit Price
Total
Surety
Power of Attorney Must be Attached
By:
Attorney-in-Fact
Date:
BILL OF SALE
The Contractor,
, (will store/has stored) certain Materials (at the site
of this project/at an approved warehouse/at bonded warehouse) and will be paid in accordance with the provisions
of the General Conditions of the Contract for Construction. In consideration of the sum of $
paid to
the contractor by the Owner, and, incompliance with the provisions of the Contract, and, with the intention to be
legally bound, the Contractor does hereby grant, bargain, sell and deliver unto the Owner, it successors and
assigns, all and singular, the Materials described in the schedule above. The Contractor agrees that:
1. Contractor has good title to the Materials, free and clear of all liens and encumbrances, and title is granted
to the Owner;
2. The Materials will be used only in the construction of the above referenced project, under the provisions
of the Contract, and will not be diverted elsewhere without the prior written consent of the Owner;
UMS Form ver 1.0 06/02/2010
Page 1 of 2
00 62 79
3. The Materials have been delivered to and are at the places approved for storage, and they are clearly
marked and identified as the property of the Owner and are stored in a safe and secure manner to protect
from damage or loss;
4. The Contractor will pay all expenses in connection with the sale, delivery, storage, protection and
insurance of Materials granted to the Owner.
5. The Contractor will remain responsible for the Materials, which will remain under its custody and control
for all losses, and will fully indemnify the Owner for the cost of the Materials should the Materials be lost
or damaged or stolen, regardless of exclusions in insurance policies required under this document. The
contractor has insured the Materials against loss or damage by fire (with extended coverage), theft and
burglary, with loss payable to the Owner;
6. The Contractor agrees that the quantities of Materials set forth in the Schedule of Values Form represents
the maximum quantities for which it may be entitled to payment under the provisions of the contract;
7. The following information is included with this form:
(1) An Application for Payment;
(2) An invoice or copy of an invoice for Materials stored;
(3) Evidence of payment, or when payment has not been made, a letter on the Contractor’s
letterhead authorizing payment to be made jointly to the Contractor and the Supplier;
(4) Photographs showing the stored Materials and its location;
(5) a fire and theft insurance policy rider for the stored Materials.
(6) a warehouseman’s receipt acknowledging that the Materials being stored at the warehouse
are being held for the benefit of the Contractor or/or University.
Witness:
By:
(SEAL)
Principal/Contractor-Individual
Witness:
Principal/Contractor-Individual
(SEAL)
(SEAL)
(SEAL)
(SEAL)
Attest:
Principal/Contractor-Corporation
By:
Secretary
UMS Form ver 1.0 06/02/2010
President
Page 2 of 2
SAMPLE
SAMPLE
SAMPLE
SAMPLE
SAMPLE
SAMPLE
SECTION 00 65 19
CERTIFICATE OF COMPLETION FORM
(Final)
DATE:
PROJECT NAME:
UMF CHP LP Gas Tank System
SUBSTANTIAL COMPLETION DATE:
FINAL COMPLETION is defined, in accordance with Article 9 of the A201 General Conditions of the Contract
for Construction, as the date certified by the Architect when all the Work of the Project is fully complete, the
Close-Out requirements of Paragraph 9.10 of the General Conditions have been completed, including the CloseOut Meeting and approval of Close-Out by the Architect, in accordance with Subparagraph 9.10.2, and the
Contract fully performed in accordance with the Contract Documents, and the Contractor entitled to final
payment.
The CONTRACTOR certifies that the Work is fully completed and was completed on or before
20
, and submits herewith:
Application for Final Payment (AIA G702)
Affidavit of Payments (AIA G706)
Consent of Surety (AIA G707)
Releases of Liens (AIA G706A)
Waiver of Lien
CONTRACTOR:
By:
Date:
Name:
The ARCHITECT has inspected the Work and has determined that the Date of Final Completion was
, 20
.
ARCHITECT:
By:
Date:
Name:
The OWNER hereby accepts the Work as fully complete and will make final payment.
OWNER:
By:
Date:
Jeffrey McKay
Director of Facilities Management
University of Maine at Farmington
END OF SECTION 00 65 19
,
SAMPLE
SAMPLE
SECTION 00 65 19.17
WAIVER OF LIEN
DATE:
State of Maine
County of
TO:
Office of Facilities
University of Maine System
16 Central Street
Bangor ME 04401
SUBJECT:
Project Name:
UMF CHP LP Gas Tank System
Project Location:
UNIVERSITY OF MAINE AT FARMINGTON; FARMINGTON, MAINE
Upon receipt of the sum of
(being the
balance due us under the existing contract or subcontract agreement for work on the Subject Project) the
undersigned agrees that it will waive and release the University of Maine System from any and all lien or claim
or right to lien on the Subject Project under the Statutes of the state of Maine relating to liens for labor,
materials and/or subcontracts furnished for the Subject Project on premises belonging to the University of
Maine System.
Signed:
Title:
Firm Name:
NOTARY
Subscribed and sworn to before me this
day of
Signature Notary Public
END OF SECTION 00 65 19.17
, 20
.
SAMPLE
SECTION 00 73 00.01
UNIVERSITY OF MAINE SYSTEM
SUPPLEMENTARY CONDITIONS TO
AIA A201 2007 GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
§ 1.1.8 Add the following:
The Architect is the Initial Decision Maker for this Agreement.
§ 1.2.2 Add the following:
Where the Procurement Requirements include provisions that portions of the Work be File Bid in accordance
with the requirements of the Maine Bid Depository System, the subcontracts for these portions of the work will
cover the same scope of work as defined by the Procurement Requirements and the File Bid and shall have the
same contract amount as listed in the successful bid.
§ 1.5.1 Add the following:
The provisions of this section shall not be deemed to modify the contract between the University of Maine
System (the Owner) and the Architect under B102-2007 and B201-2007 and the University of Maine
Supplementary Requirements to those documents regarding the Instruments of Service.
§ 1.5.2 Add the following:
The provisions of this section shall not be deemed to modify the contract between the University of Maine
System (the Owner) and the Architect under B102-2007 and B201-2007 and the University of Maine
Supplementary Requirements to those documents regarding the Instruments of Service.
§ 2.1.1.1 Insert the following:
§ 2.1.1.1 For the purpose of this Contract, the Owner is defined as: University of Maine System; 16 Central
Street; Bangor, Maine 04401 acting through its duly authorized agent.
§ 2.2.1 Delete in its entirety.
§ 3.4.2.1 Insert the following:
§ 3.4.2.1 After the Contract has been executed, the Owner and Architect may consider a formal request for
substitution of products in place of those specified. The Owner shall deduct from the next payment made from
the Contract Sum amounts paid to the Architect to evaluate the Contractor’s proposed substitutions and to make
agreed-upon changes in the Drawings and Specifications made necessary by the Owner’s acceptance of the
substitutions.
By making requests for substitutions, the Contractor:
.1 Represents that the Contractor has personally investigated the proposed substitute product and determined it
is equal or superior in all respects to that specified;
.2 Represents that the Contractor will provide the same warranty for the substitution that the Contractor would
for that specified;
.3 Certifies that the cost data presented is complete and includes all related costs, and waives all claims for
additional costs related to the substitution which subsequently become apparent; and,
.4 Will coordinate the installation of the accepted substitute, making such changes as may be required for the
Work to be completed in all respects.
§ 3.4.4 Insert the following:
§ 3.4.4 If a wage scale prepared by the State of Maine Department of Labor, Bureau of Labor Standards, is
included in the Contract Documents, such wage scale represents the minimum wages that must be paid in each
category of labor employed on the project.
University of Maine System Supplementary Conditions to AIA A201-2007 ver 1.5 02/01/13
The provisions of Title 26 MRSA Chapter 15 Preference to Maine Workers and Contractors, apply to this project,
including but not limited to:
§ 1310. Wage and benefits rates to be kept posted
A clearly legible statement of all fair minimum wage and benefits rates to be paid the
several classes of laborers, workers and mechanics employed on the construction on the
public work must be kept posted in a prominent and easily accessible place at the site by
each contractor and subcontractor subject to sections 1304 to 1313.
§ 1311. Wage and benefit record of contractor
The contractor and each subcontractor in charge of the construction of a public work shall
keep an accurate record showing the names and occupation of all laborers, workers and
mechanics employed by them and all independent contractors working under contract with
them in connection with the construction on the public works. The record must also show
for all laborers, workers, mechanics and independent contractors the hours worked, the title
of the job, the hourly rate or other method of remuneration and the actual wages or other
compensation paid to each of the laborers, workers, mechanics and independent contractors.
A copy of such a record must be kept at the job site and must be open at all reasonable
hours to the inspection of the Bureau of Labor Standards and the public authority that let
the contract and its officers and agents. It is not necessary to preserve those records for a
period longer than 3 years after the termination of the contract. A copy of each such record
must also be filed monthly with the public authority that let the contract. The filed record is
a public record pursuant to Title 1, chapter 13, except that the public authority letting a
contract shall adopt rules to protect the privacy of personal information contained in the
records filed with the public authority under this section, such as Social Security numbers
and taxpayer identification numbers. The rules may not prevent the disclosure of
information regarding the classification of workers or independent contractors and the
remuneration they receive. Such rules are routine technical rules as defined by Title 5,
chapter 375, subchapter 2-A.
§ 3.4.5 Insert the following:
§ 3.4.5 If a wage scale prepared by the U.S. Department of Labor pursuant to the provision of the Davis-Bacon
Act is included in the Contract Documents, such wage scale represents the minimum wages that must be paid in
each category of labor on the project. The requirements and responsibilities within the Davis-Bacon Act apply to
this project if a Davis-Bacon wage scale is included.
§ 3.4.6 Insert the following:
§ 3.4.6 EQUAL EMPLOYMENT OPPORTUNITY
During the performance of this Contract, the Contractor agrees as follows:
§ 3.4.6.1 The Contractor will not discriminate against any employee or applicant for employment because of
race, color, religion, sex, sexual orientation, including transgender status or gender expression, national origin or
citizenship status, ancestry, age, disability, genetic information, or veteran’s status. Such action shall include, but
not be limited to, the following: employment, upgrading, demotions, transfers, recruitment or recruitment
advertising, layoffs or terminations, rates of pay or other forms of compensation, and selection for training,
including apprenticeship.
§ 3.4.6.2 The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the
Contractor, state that all qualified applicants will receive consideration for employment without regard to race,
color, religion, sex, sexual orientation, including transgender status or gender expression, national origin or
citizenship status, ancestry, age, disability, genetic information, or veteran’s status.
§ 3.4.6.3 The Contractor will send to each labor union or representative of the workers with which there is a
collective or bargaining agreement in place, or other contract or understanding, whereby labor is being furnished
for the performances of this Contract, a notice, as set forth in Attachment A attached hereto, to be provided by the
University of Maine System Supplementary Conditions to AIA A201-2007 ver 1.5 02/01/13
contracting department or agency, advising the said labor union or workers’ representative of the Contractor’s
commitment under the provisions of the Contract, and shall post copies of the notice in conspicuous places
available to employees and to applicants for employment.
§ 3.4.6.4 The Contractor will cause the foregoing provisions to be inserted in all contracts for any work covered
by this Agreement so that such provisions will be binding upon each subcontractor.
§ 3.4.6.5 Contractors and subcontractors with contracts in excess of $50,000 will also pursue in good faith
affirmative action programs.
§ 3.4.7 Insert the following:
§ 3.4.7 The Contractor and all subcontractors shall adhere to HP 960 LD 1314 and Sec 6 of Title 26 MRSA
§1043, sub §11, ¶E, regarding the definition of “Independent Contractor.”
§ 3.6.1 Insert the following:
§ 3.6.1 The University of Maine System is exempt from payment of taxes under the Maine Sales and Use Tax
Law Title 36 Section 1760 for taxes on materials that are permanently incorporated into the real property
belonging to the University of Maine System. The University of Maine System is also exempt from the payment
of Federal Excise Taxes on articles not for resale and from the Federal Transportation Tax on all shipments;
exemption certificates for these taxes will be furnished when required. All quotations shall be less these taxes.
The Contractor shall pay all other taxes that have been or are legally enacted.
§ 3.7.4 Replace existing § 3.7.4 with the following:
§ 3.7.4 Concealed or Unknown Conditions. If the Contractor encounters conditions at the site that are (1)
subsurface or otherwise concealed physical conditions that differ materially from those indicated in the Contract
Documents or (2) unknown physical conditions of an unusual nature, that differ materially from those ordinarily
found to exist and generally recognized as inherent in construction activities of the character provided for in the
Contract Documents, the Contractor shall promptly provide notice to the Owner and the Architect before
conditions are disturbed. The Architect will promptly investigate such conditions and, if the Architect determines
that they differ materially and cause an increase or decrease in the Contractor’s cost of, or time required for,
performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract
Time, or both. If the Architect determines that the conditions at the site are not materially different from those
indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect
shall promptly notify the Owner and the Contractor in writing, stating the reasons. If either party disputes the
Architect’s determination or recommendation, that party may proceed as provided in Article 15.
§ 3.10.1.1 Insert the following:
§ 3.10.1.1 The Contractor shall provide an updated Construction Schedule with each Application for Payment
reflecting actual construction progress and activities.
§ 3.12.11 Insert the following:
§ 3.12.11 The Architect’s review of the Contractor’s submittals will be limited to examination of an initial
submission and two (2) resubmittals. The Architect’s review of additional submittals will be made only with the
consent of the Owner after notification by the Architect. The Owner shall deduct from the next payment made
from the Contract Sum amounts paid to the Architect for evaluation of such additional submittals.
§ 3.15.3 Insert the following:
§ 3.15.3 Waste Management. The University is committed to a resource management strategy which reduces
to a minimum the production of waste material while reusing, recycling or composting as much as possible of the
remaining materials. Contractor should strive to identify opportunities to reduce, reuse or recycle waste from
renovations or new construction, and will submit a construction waste management plan for the project.
University of Maine System Supplementary Conditions to AIA A201-2007 ver 1.5 02/01/13
§ 4.1.1 Replace existing § 4.1.1 with the following:
§ 4.1.1 The Architect is a person or entity lawfully licensed to practice in the State of Maine. That person or
entity is identified in the Agreement and is referred to throughout the Contract Documents as if singular in
number. Whenever the prime professional designer for the Work is an Engineer, the term Architect, wherever
used in these documents shall have the term Engineer substituted for the term Architect. The Engineer shall be
lawfully licensed to practice engineering in the State of Maine or an entity lawfully practicing engineering
identified as such in the Agreement.
§ 4.2.1 Replace existing § 4.2.1 with the following:
§ 4.2.1 The Architect will provide administration of the Contract as described in the Contract Documents, and
will be an Owner’s representative during construction until the date the final payment is due, and from time to
time during the period for correction of Work described in Section 12.2, and until the date the Architect issues the
final Certificate for Payment. The Architect will have authority to act on behalf of the Owner only to the extent
provided in the Contract Documents.
§ 4.2.2 Replace existing § 4.2.2 with the following:
§ 4.2.2 The Architect will visit the site at intervals appropriate to the stage of construction, or as otherwise
agreed with the Owner, to become generally familiar with the progress and quality of the portion of the Work
completed, endeavor to guard the Owner against defects and deficiencies in the Work, and to determine in
general if the Work observed is being performed in a manner indicating that the Work, when fully completed,
will be in accordance with the Contract Documents. However, the Architect will not be required to make
exhaustive or continuous on-site inspections to check the quality or quantity of the Work. The Architect will not
have control over, charge of, or responsibility for, the construction means, methods, techniques, sequences or
procedures, or for the safety precautions and programs in connection with the Work, since these are solely the
Contractor’s rights and responsibilities under the Contract Documents, except as provided in Section 3.3.1.
§ 4.2.2.1 The Contractor shall reimburse the Owner for compensation paid to the Architect for additional site
visits made necessary by the fault, neglect as determined solely by the Owner, or request of the Contractor. The
reimbursement shall be deducted from the next payment made from the Contract Sum following the Owner’s
payment to the Architect.
§ 4.2.3 Delete the word “reasonably” from the first sentence.
§ 4.2.10 Replace existing § 4.2.10 with the following:
§ 4.2.10 If the Owner and Architect agree, the Architect will provide one or more project representatives to assist
in carrying out the Architect’s responsibilities at the site. The duties, responsibilities and limitations of authority
of such project representatives shall be as set forth in the contract between the Architect, AIA B102 and B2012007 and Supplementary Requirements to be incorporated in the Contract Documents and attached hereto as
Exhibit A.
§ 5.2.1 Insert the following:
§ 5.2.1.1 The Contractor shall provide the Owner a list of all subcontractors and independent contractors on the
job site and a record of the entity to whom that subcontractor or independent contractor is directly contracted and
by whom that subcontractor or independent contractor is insured. The list shall be presented at the preconstruction meeting and, when changes occur, at each requisition meeting as necessary.
§ 5.2.1.2 Where the use of the Maine Bid Depository was required by the Procurement Requirements,
Subcontractors included in the Contractor’s Proposal shall be the Subcontractors for the defined Work unless a
change has been approved by the Owner.
§ 7.1.4 Insert the following:
§ 7.1.4 The combined overhead and profit included in the total cost to the Owner of a change in the Work shall
University of Maine System Supplementary Conditions to AIA A201-2007 ver 1.5 02/01/13
be based on a previously agreed upon unit pricing or on the following schedule allowing for appropriate
allowances for contract duration:
.1 For the Contractor, for Work performed by the Contractor’s own forces, 20% of the cost.
.2 For the Contractor, for Work performed by the Contractor’s Subcontractors, 10% of the amount due the
Subcontractors.
.3 For each Subcontractor involved, for Work performed by the Subcontractor’s own forces, 20% of the cost.
.4 For each Subcontractor involved, for Work performed by the Subcontractor's Sub-subcontractors, 10% of the
amount due the Sub-subcontractor.
.5 Costs to which overhead and profit are to be applied shall be limited to the following:
.1 Costs of labor, including social security, old age and unemployment insurance, fringe benefits required
by agreement or custom, and workers’ compensation insurance;
.2 Costs of materials, supplies and equipment, including cost of transportation, whether incorporated or
consumed;
.3 Rental costs of machinery and equipment, exclusive of hand tools, whether rented from the Contractor
or others; and,
.4 Costs of premiums for all bonds, insurance, permit fees, and sales, use or similar taxes related to the
Work.
§ 7.1.5 Insert the following:
§ 7.1.5 When there is only an extension of Contract Time, the Contractor delay claim is limited to additional
costs related to supervision and field office personnel, which may be included in the overhead and profit
calculation.
§ 7.1.6 Insert the following:
§ 7.1.6 In order to facilitate checking of quotations, all proposals, except those so minor that their propriety can
be seen by inspection, shall be accompanied by complete itemization of costs including labor, materials and
Subcontracts. Labor and materials shall be itemized in the manner prescribed above. Where major cost items are
Subcontracts, they are to be itemized also. In no case will a change be approved without such itemization.
§ 9.3.1 Add the following:
The forms for application of payment, duly notarized, shall be the current authorized edition of AIA Document
G702, Application for Payment, supported by a current authorized edition of AIA G703, Continuation Sheet.
§ 9.3.1.3 Insert the following:
§ 9.3.1.3 The provisions of Title 5 MRSA § 1746, as amended, pertain to this project. The Owner shall retain
five percent (5%) of each payment due the Contractor as part of the security for the fulfillment of the Contract
Agreement by the Contractor, the Contractor shall not withhold a greater percentage from subcontractors. The
Owner may, if deemed expedient by the Owner, cause the Contractor to be paid temporarily or permanently from
time to time during the progress of the Work, such portion of the amount retained as the Owner deems prudent or
desirable.
§ 9.5.1 The word “shall” will be substituted for the word “may” in all places in § 9.5.1.
§ 9.5.1.1 Replace existing § 9.5.1 with the following:
§ 9.5.1.1 Defective Work, i.e. Work that does not conform to the requirements of the Contract, shall include, but
not be limited to, non-conforming Work, disputed Work, incomplete Work, and unacceptable Work, which is not
remedied.
§ 9.5.1.1.1 Insert the following:
§ 9.5.1.1.1 The Architect shall deduct and withhold from any certification for payment an amount equal to one
hundred and fifty percent (150%) of the value of any defective Work.
University of Maine System Supplementary Conditions to AIA A201-2007 ver 1.5 02/01/13
§ 9.6.8 Insert the following:
§ 9.6.8 All Progress Payments and Final Payment are subject to the requirements of the “Maine Prompt Pay Act”
Title 10 MRSA § 201-A, as amended. Payments shall be made on a timely basis in accord with the requirements
of this Statute; however, the Contractor waives interest on any late payment.
§ 9.10.1.1 Insert the following:
§ 9.10.1.1 Except with the consent of the Owner, the Architect will perform no more than three (3) site reviews
to determine whether the Work or a designated portion thereof has attained Final Completion in accordance with
the Contract Documents. The Owner shall be entitled to deduct from the Contract Sum amounts paid to the
Architect for any additional site reviews.
§ 9.11 Insert the following:
§ 9.11 The Contractor and the Contractor’s Surety, if any, shall be liable for and shall pay the Owner the sums
stipulated as liquidated damages in the Contract Documents for each calendar day of delay after the date
established for Substantial Completion in the Contract Documents until the Work is substantially complete.
§ 10.2.1 Add the following:
.4 If this Contract involves renovation, repair or preparation of surfaces for painting in pre-1978 apartments,
houses or spaces used by child care facilities, Contractor shall use certified workers who follow the lead-safe
work practices as required by the US Environmental Protection Agency’s Renovation, Repair and
Remodeling rule described in 40 CFR § 745.85. Notification of the tenants or users under this rule will be
the responsibility of the Owner.
§ 10.3.2 Replace existing § 10.3.2 with the following:
§ 10.3.2 Upon receipt of the Contactor’s written notice, the Owner shall obtain the services of a licensed
laboratory to verify the presence or absence of the material or substance reported by the Contractor and, in the
event such material or substance is found to be present, to cause it to be rendered harmless. When the material or
substance has been rendered harmless, Work in the affected area shall resume upon written agreement of the
Owner and the Contractor.
§ 11.1.3 Add the following:
§ 11.1.3 Certificates of Insurance filed with the University of Maine System shall indicate the Certificate Holder
as University of Maine System, 16 Central Street, Bangor, Maine 04401. The Project name, campus, and general
liability insurance required policy form and two required endorsements noted in Paragraph 11.1.5.1 below shall
be included on the Certificate. Contractor must provide renewal certificates at least 15 days prior to expiration.
§ 11.1.4 Add the following:
§ 11.1.4 Neither the Contractor nor any Subcontractors or Suppliers shall commence work at the project site
under this Contract until the Contractor has provided the University with a standard ACORD certificate with an
attached AIA Document G715-1991 listing all insurance coverages and limits required under this section. All
required insurance shall be maintained throughout the term of this Contract (including correction period, defined
in 12.2.2.1) and be on a primary basis, noncontributory with any other insurance carried by the Owner. All
required insurance shall be provided by companies that have a current A.M. Best insurance rating of A- or better
and that are licensed or approved to do business in the State of Maine.
§ 11.1.5 Insert the following:
§ 11.1.5 COVERAGE LIMITS – The required insurance and coverage limits are as follows:
§ 11.1.5.1 General Liability – Contractor shall provide General Liability insurance with coverage for premises
and operations, products and completed operations, explosion, collapse and underground hazards, broad form
University of Maine System Supplementary Conditions to AIA A201-2007 ver 1.5 02/01/13
property damage, contractual, personal and advertising injury liabilities. Insurance shall be provided on a
standard Insurance Services Office (ISO) Commercial General Liability Form CG 00 01 12 04 or equivalent and
shall include the following three endorsements or their equivalent: 1) Additional Insured—Owners, Lessees or
Contractors—Scheduled Person or Organization (CG 20 10 07 04) with the University of Maine System, 16
Central Street, Bangor, ME 04401 listed as additional insured; 2) Additional Insured—Owners, Lessees or
Contractors—Completed Operations (CG 20 37 07 04) with the University of Maine System, 16 Central Street,
Bangor, ME 04401 listed as additional insured; and, 3) Designated Construction Project General Aggregate Limit
(CG 25 03 03 97) as the Aggregate limits shall apply on a per location or job basis. The policy form and
endorsements must be included on the certificate of insurance. The below required minimum insurance limits
shall not be construed as a limitation of the Owner’s rights under any insurance with higher limits and no
insurance shall be endorsed to include such a limitation. General Liability insurance required minimum limits:
.1
.2
.3
.4
.5
.6
.7
General Aggregate
Products & Completed Operations Aggregate
Personal Injury Aggregate
Each Occurrence for Contracts Under $1 million
Each Occurrence for Contracts $1 million and above
Personal/Advertising Injury
Medical Payments (Any One Person)
$2,000,000
$2,000,000
$1,000,000
$1,000,000
$2,000,000
$1,000,000
$5,000
§ 11.1.5.2 Workers’ Compensation – Contractor including Independent Contractors shall provide Workers’
Compensation insurance with coverage on a statutory basis according to Maine Law and apply to all personnel on
the job site. Workers’ Compensation insurance required minimum limits:
.1 Coverage A (Workers’ Compensation)
.2 Coverage B (Employers Liability)
.1 Bodily injury by accident
.2 Bodily injury by disease
.3 Bodily injury by disease
Statutory Limits
$500,000 each accident
$500,000 each employee
$500,000 policy limit
§ 11.1.5.3 Vehicle Liability Insurance – Contractor shall provide Vehicle Liability insurance with coverage for
all owned, hired/rented and non-owned vehicles. Vehicle Liability insurance required minimum limit:
.1 Combined Single Limit
or
.2 Split Limits
$1,000,000 each accident
$1,000,000 bodily injury
$1,000,000 property damage
§ 11.3.1 Replace all of the existing § 11.3.1 and its subparagraphs with the following:
§ 11.3.1 For this project, Property Insurance coverage, up to the total amount of the Project, will be provided by
the Owner by adding the Project to the Owner’s existing master property insurance. Coverage shall be included
for the Contractor and all Subcontractors, as their interests may appear, while involved in the Project and until the
work is completed or the Contractor is otherwise advised in writing. This insurance is limited to the “all risk”
type coverage provided under the Owner’s master property insurance for direct physical loss or damage to the
building or building materials related to the project, subject to standard policy limitations and exclusions. The
Contractor is responsible for a $10,000 per claim deductible. Any other insurance desired by the Contractor
beyond that covered by the Owner’s insurance, or to cover the $10,000 deductible, is the responsibility of the
Contractor. This contract stands as verification of the Owner’s property insurance coverage on the project and no
further verification will be provided.
§ 11.4.1 Replace existing § 11.4.1 with the following:
§ 11.4.1 The Contractor shall furnish a Performance Bond and a Payment Bond covering the faithful
performance of the contract and payment of obligations arising thereof. Bonds may be obtained through the
Contractor’s usual source and the cost thereof shall be included in the Contract Sum. The amount of each bond
shall be equal to 100% of the Contract Sum. Should the Contract Sum change during the contract and corrections
periods, the amount of the Bonds will be changed to reflect the Contract Sum.
University of Maine System Supplementary Conditions to AIA A201-2007 ver 1.5 02/01/13
§ 11.4.1.1 The Contractor shall deliver the required bonds to the Owner at the same time as the signed Contract
Agreement is delivered to the Owner. Prior to the commencement of the Work, the Contractor shall submit
satisfactory evidence that such bonds will be furnished.
§ 11.4.1.2 The Contractor shall require the attorney-in-fact who executes the required bonds on behalf of the
surety to affix thereto a certified and current copy of the power of attorney.
§ 11.4.1.3 The Contract Bonds shall continue in effect for one year after final acceptance of each contract to
protect the Owner’s interest in connection with the one year guarantee of workmanship and materials and to
assure settlement of claims, for the payment of all bills for labor, materials and equipment by the Contractor.
§ 13.6 Delete in its entirety.
§ 14.1.1.4 Delete in its entirety.
§ 14.1.3 Delete the words “and damages.”
§ 14.4.3 Replace existing § 14.4.3 with the following:
§ 14.4.3 In case of such termination for the Owner’s convenience, the Contractor shall be entitled to receive
payment for the work executed and costs incurred by reason of such termination, but not overhead and profit on
Work not executed.
§ 15.4.1 Replace existing § 15.4.1 with the following:
§ 15.4.1 The parties have selected arbitration as the method for binding dispute resolution in this Agreement, any
claim, dispute or other matter in question arising out of or related to this Agreement subject to, but not resolved
by, mediation shall be subject to arbitration, which unless the parties mutually agree otherwise, shall be
administered by the American Arbitration Association in accordance with its Construction Industry Arbitration
Rules in effect on the date of this Agreement, except that the parties shall select only one Arbitrator, and there
shall be no discovery. A demand for arbitration shall be made in writing, delivered to the other party to this
Agreement, and filed with the person or entity administering the arbitration. The party filing a notice of demand
for arbitration must assert in the demand all Claims then known to that party on which arbitration is permitted to
be defended.
University of Maine System Supplementary Conditions to AIA A201-2007 ver 1.5 02/01/13
END OF SECTION 00 73 00.01
University of Maine System Supplementary Conditions to AIA A201-2007 ver 1.5 02/01/13
SECTION 00 73 00.11
SCHEDULE OF LIQUIDATED DAMAGES
Liquidated damages (a fixed amount set forth in the Contract) agreed to by the Owner and the Contractor are
intended to compensate the Owner for unexcused delay in the performance of the Contract. The parties agree
that the purpose of the liquidated damages schedule below is to establish, in advance, a reasonable estimate of
the damages that would be incurred by the Owner if there is an unexcused delay, or a breach of Contract, which
causes the work to be extended beyond the contractual substantial completion date. This agreement of
liquidated damages by the parties is made to establish the reasonableness of them to the actual damages an
Owner may have incurred due to unexcused delays by the Contractor, even though the actual damages may be
an uncertain amount and unprovable.
The specific per diem rates of Liquidated Damages are set forth below. By executing the Contract, the
Contractor acknowledges that such an amount is not a penalty and that the daily amount set forth in the Contract
is a reasonable per diem forecast of damages incurred by the Owner due to the Contractor’s failure to complete
the Work within the Contract Time.
Original Contract Amount
From
To
More Than
and Including
0
$100,000
$100,000
$300,000
$300,000
$500,000
$500,000
$1,000,000
$1,000,000
$2,000,000
$2,000,000
$4,000,000
$4,000,000
and more
Per Diem Amount
of Liquidated Damages
$500
$675
$750
$825
$1,000
$1,250
$1,500
END OF SECTION 00 73 00.11
SECTION 00 73 46
WAGE DETERMINATION SCHEDULE
SEE ATTACHED - 2 SHEETS
END OF SECTION 00 73 46
SECTION 01 10 00 – SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work under separate contracts.
4. Access to site.
5. Work restrictions.
6. Specification and drawing conventions.
7. Miscellaneous provisions.
1.2 PROJECT INFORMATION
A. Project Identification: University of Maine at Farmington CHP LP Gas Tank System
1. Project Location: Farmington, Maine
B. Owner: University of Maine at Farmington
1. Owner's Representative: Dirigo Architectural Engineering, LLC
C. Engineer: None
D. Contractor: TBD
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Furnish and install new LP Gas tank and appurtenances for backup fuel to new Central
Heating Plant
B. Type of Contract.
1. Project will be constructed under a single prime contract.
1.4 WORK UNDER SEPARATE CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried
out smoothly, without interfering with or delaying work under this Contract or other contracts.
1. Coordinate the Work of this Contract with work performed under separate contracts.
B. Concurrent Work: Owner will award separate contract(s) for the following construction
operations at Project site. Those operations will be conducted simultaneously with work under
this Contract.
1. Central Energy Plant Construction
1.5 ACCESS TO SITE
A. General: Contractor shall have limited use of Project site for construction operations as
indicated on Drawings by the Contract limits and as indicated by requirements of this section.
UMF CHP LP Gas Tank System
01 10 00 Summary
Page 1
October 13, 2015
B. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb
portions of Project site beyond areas in which the Work is indicated. Coordinate access with
Central Heating Plant Contractor – Trane. Contact: Mark Power, PE. 207.239.3424
1.6 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of
authorities having jurisdiction.
B. On-Site Work Hours: Limit work in and around buildings to normal business working hours of
C. 8:00 a.m. to 6:00 p.m., Monday through Friday, unless otherwise indicated. Campus activities
may require adjustments to work hours.
D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and
vibration, odors, or other disruption to adjacent occupancy with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
E. Nonsmoking campus: Smoking is not permitted anywhere on campus.
F. Controlled Substances: Use of tobacco products and other controlled substances on Project site
is not permitted.
1.7 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and
the intended meaning of certain terms, words, and phrases when used in particular situations.
B. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications.
The words "shall," "shall be," or "shall comply with," depending on the context, are
implied where a colon (:) is used within a sentence or phrase.
2. Specifications are a document used to coordinate information with the drawings and
other contract documents. Where there are conflicts in dimensions, depths, quantities,
materials, services, equipment, etc., within the contract documents, the more
expensive, and more stringent shall apply to this contract. It is expected that the
contractor will request clarification from the Engineer upon discovery of these conflicts.
3. Where conflicts arise between regulatory code requirements and specifications or other
contract documents, the more stringent will apply. Should the applicable code be more
stringent, the contractor is to adhere to the required code / regulation at no additional
cost to the Owner. Should an applicable governing regulation / code be updated prior
to contract award, it is expected that the contractor will adhere to the updated
regulation at no additional cost to the owner.
A. Division 01 General Requirements: Requirements of Sections in Division 01 apply to
the Work of all Sections in the Specifications.
B. Drawing Coordination: Requirements for materials and products identified on
Drawings are described in detail in the Specifications. One or more of the following
are used on Drawings to identify materials and products:
UMF CHP LP Gas Tank System
01 10 00 Summary
Page 2
October 13, 2015
4. Terminology: Materials and products are identified by the typical generic terms used in
the individual Specifications Sections.
5. Symbols: symbols are referenced in respective or general drawing keys or reference
sheets and are recognized as part of this contract document.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 10 00
UMF CHP LP Gas Tank System
01 10 00 Summary
Page 3
October 13, 2015
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.01
PROJECT CONDITIONS
A. Tobacco Free Campus Policy: On January 1, 2011 the University adopted a tobacco free campus
policy. As of January 1, 2012 compliance with the tobacco free campus policy became
mandatory. This paragraph serves as notification to Contractor of the policy and provides the
parameters of compliance enforcement. Contractor shall be responsible for notifying its workers
and subcontractors regarding the policy and for enforcement of the policy with same.
Noncompliance will be managed as follows:
1.
2.
First offense – notify Contractor to remind employee and/or subcontractor of policy.
Second offense – contractor/subcontractor employee removed from campus for the remainder
of the Work.
Additional information regarding the tobacco free campus policy is located at:
http://umaine.edu/tobaccofree/
PART 2 to 3 – Not Used
END OF SECTION 01 14 00
SECTION 01 23 00 - Alternates
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes descriptions of alternates to be priced by the contractor separately from the
base bid and provided on the bid response form.
1.2 Bid Alternates
A. Alternate 1. Provide a DEDUCT price to remove the cost of the Leak Detection System from the
project scope.
B. Alternate 2. Provide a DEDUCT price to substitute the steel/concrete bollards with 6x6
pressure-treated timbers, at spacing as required by code.
C. Alternate 3. Provide a DEDUCT price to substitute the steel/concrete bollards with concrete
block/barriers, at spacing as required by code.
END OF SECTION 01 23 00
UMF CHP LP Gas Tank System
01 23 00 AlternatesAlternates
Page 1
October 13, 2015
SECTION 01 29 00
PAYMENT PROCEDURES
PART 1 GENERAL
1.01
RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.02
SUMMARY
A. This Section specifies administrative and procedural requirements necessary to prepare and
process Applications for Payment.
1.03
DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum
to various portions of the Work and used as the basis for reviewing Contractor’s Applications for
Payment.
1.04
SCHEDULE OF VALUES
A. Construction Schedule.
1.
2.
Correlate line items in the Schedule of Values with other required administrative forms and
schedules, including the following:
a. Application for Payment forms with Continuation Sheets.
b. Submittals Schedule.
c. Contractor’s Construction Schedule.
Submit the Schedule of Values to Architect prior to the pre-construction meeting.
B. Format and Content: Use the specification table of contents as a guide to establish line items for
the Schedule of Values. Provide at least one line item for each Specification Section.
1.
2.
3.
4.
5.
Identification: Include the following Project identification on the Schedule of Values:
a. Project name and location.
b. Name of Architect.
c. Contractor’s name and address.
d. Date of submittal.
Submit draft of Section 00 62 76 AIA G702 Application for Payment form and 00 62 73 AIA
G703 Continuation Sheet (Schedule of Values) form.
Arrange the Schedule of Values in tabular form with separate columns to indicate the
following for each item listed:
a. Related Specification Section or Division.
b. Description of the Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
e. Name of supplier.
f. Change Orders (numbers).
g. Dollar value.
Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation
of Applications for Payment and progress reports. Coordinate with the Specification table of
contents. Provide several line items for principal subcontract amounts, where appropriate.
a. For each line item, provide a sublist breakdown as follows:
1) Material.
2) Labor.
Documentation: Submit proper documentation for the amounts being requisitioned from
subcontractors and material suppliers with each Application for Payment. Three (3) copies of
6.
7.
8.
9.
1.05
an Application for Payment or a Payment Requisition are required for all subcontracted work.
Three (3) copies of the invoice is required for each major supplier.
Stored Materials: If Contractor is requesting payment for stored materials as part of the
Application for Payment, Contractor must complete Column F in the G703 Continuation
Sheet (Schedule of Values) to record the stored materials amounts against line items that
pertain to those stored materials. Stored materials are materials or equipment purchased or
fabricated and stored, but not yet installed or incorporated into the Work.
a. Complete and provide three (3) copies of 00 62 79 Stored Materials form with all
required documentation. Differentiate between items stored on-site and items stored offsite. If specified, include evidence of insurance or bonded warehousing.
b. Only major long lead delivery items may be considered for off-site storage (example:
long lead custom mechanical unit). Standard order and production materials and
products shall be delivered to the site before including in Application for Payment of
such items.
Provide separate line items in the Schedule of Values for initial cost of materials, for each
subsequent stage of completion, and for total installed value of that part of the Work.
Each item in the Schedule of Values and Applications for Payment shall be complete. Include
total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-inplace shall be shown as separate line items in the Schedule of Values.
Schedule Updating: Update and resubmit the Schedule of Values before the next
Applications for Payment when approved Change Orders or Construction Change Directives
result in a change in the Contract Sum.
APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as
certified by Architect and paid for by Owner.
1.
Initial Application for Payment, Application for Payment at time of Substantial Completion,
and final Application for Payment involve additional requirements.
B. Payment Application Times: G702 Application for Payment shall be submitted to Architect and
Owner not less than seven (7) days before monthly progress meeting. The period covered by each
Application for Payment is one (1) month, ending on the last day of the month.
C. Payment Application Forms: The Contractor is required under the Contract Documents to use
official original AIA documents. Samples of the required documents are provided in Division 00
of the Specifications.
D. Application Preparation: Complete every entry on form. Notarize and execute by a person
authorized to sign legal documents on behalf of Contractor. Architect will return incomplete
applications without action.
1.
2.
Entries shall match data on the Schedule of Values and Contractor’s Construction Schedule.
Use updated schedules if revisions were made.
Include amounts of approved Change Orders and Construction Change Directives issued
before last day of construction period covered by application.
E. Transmittal:
1.
2.
Submit three (3) signed and notarized originals of:
a. AIA G702 Application & Certificate for Payment.
b. AIA G703 Continuation Sheet.
c. AIA G706 Contractor’s Affidavit of Payment of Debts & Claims.
d. AIA G706A Contractor’s Affidavit of Release of Liens.
e. 00 65 19.17 Waiver of Lien.
Transmit each Application for Payment with a transmittal form listing attachments and
recording appropriate information about submission.
F.
Waivers of Mechanic's Lien: With each Application for Payment, submit three (3) copies of
waivers of mechanic’s lien from subcontractors, sub-subcontractors, major suppliers, and every
entity who is lawfully entitled to file a mechanic’s lien arising out of the Contract and related to
the Work covered by the payment.
1.
2.
3.
4.
5.
Submit partial waivers on each item for amount requested in previous application, after
deduction for retainage, on each item.
When an application shows completion of an item, submit final waivers.
Owner reserves the right to designate which entities involved in the Work must submit
waivers.
Submit final Application for Payment with or preceded by final waivers from every entity
involved with performance of the Work covered by the application who is lawfully entitled to
a lien.
Waiver Forms: Submit 00 65 19.17 Waiver of Lien forms, executed in a manner acceptable
to Owner.
G. Certified Payrolls: Wages paid to all workers performing work on the Project shall be in
accordance with the Section 00 73 64 Wage Determination Schedule for the Project. Contractor
shall submit one (1) copy of each weekly certified payroll for Contractor and all subcontractors,
sub-subcontractors, sub-sub-subcontractors, etc. performing work on the Project during the time
covered by the Application for Payment The certified payroll shall be completed in accordance
with Supplementary Conditions Section 3.4.4 and contain the following information:
1.
2.
3.
4.
5.
6.
7.
Contractor name.
Contractor address.
Period number.
Week ending date.
Employee(s)’s name.
Employee(s)’s job title.
Employee hourly wage:
a. Straight time rate.
b. Overtime rate.
8. Hours worked per day (broken down by straight time and overtime hours).
9. Hours worked per week (broken down by straight time and overtime hours).
10. Total earned for the week:
a. Straight time.
b. Overtime.
11. Benefits that form a part of the wage rate.
12. The signature and name of the authorized payroll person.
H. Initial Application for Payment: Administrative actions and submittals that must precede
submittal of first Application for Payment include the following:
1.
2.
3.
4.
5.
6.
7.
8.
List of subcontractors.
Schedule of Values.
Contractor’s Construction Schedule.
Submittals Schedule.
List of Contractor’s staff assignments.
List of Contractor’s principal consultants.
Copies of building permits and other required permits.
Copies of authorizations and licenses from authorities having jurisdiction for performance of
the Work.
9. Initial progress report.
10. Report of preconstruction conference.
11. Insurance verification through submission of insurance certificates, for all Subcontractors.
I.
Progress Applications for Payment: Administrative actions and submittals that must precede or
coincide with submittal of progress Applications for Payment include the following:
1.
2.
3.
4.
5.
J.
Contractor’s Construction Schedule update.
Submittals for Work being requisitioned that are complete and approved.
Submission of list of completed tests, checklists, commissioning, reports, and similar
requirements for the work that are submitted and in compliance with the Contract Documents.
Distribution of minutes of previous month’s progress meeting.
Current record drawings.
Application for Payment at Substantial Completion: After issuing the Certificate of Substantial
Completion, submit an Application for Payment showing 100 percent completion, less retainage,
for portion of the Work claimed as substantially complete. Application must:
1.
2.
Include documentation supporting claim that the Work is substantially complete and a
statement showing an accounting of changes to the Contract Sum.
Reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy
of designated portions of the Work.
K. Final Payment Application: Submit final Application for Payment with releases and supporting
documentation not previously submitted and accepted, including, but not limited to, the following:
1.
2.
Evidence of completion of Project closeout requirements.
Insurance certificates for products and completed operations where required and proof that
fees and similar obligations were paid.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. AIA G707 Consent of Surety to Final Payment, three (3) originals.
5. Evidence that claims have been settled.
6. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date
of Substantial Completion or when Owner took possession of and assumed responsibility for
corresponding elements of the Work.
7. Final, liquidated damages settlement statement, if a liquidated damages claim has been
processed.
8. As-built drawings.
9. Operation and maintenance manuals.
10. Final lien waivers.
11. All training and equipment testing is complete.
PART 2 to 3 – Not Used
END OF SECTION 01 29 00
SECTION 01 31 00 - PROJECT MANAGEMENT AND ADMINISTRATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project
including, but not limited to, the following:
1. Requests for Information (RFIs).
2. Project meetings.
B. Related Requirements:
1. Section 017300 "Execution" for procedures for coordinating general installation and
2. Field-engineering services, including establishment of benchmarks and control points.
1.2 DEFINITIONS
A. RFI: Request from Owner, Engineer, or Contractor seeking information required by or
clarifications of the Contract Documents.
1.3 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each
portion of the Work, including those who are to furnish products or equipment fabricated to a
special design. Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying
products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
1.4 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate
construction operations, included in different sections, that depend on each other for proper
installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where
installation of one part of the Work depends on installation of other components,
before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and
accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Prepare memoranda for distribution to each party involved, outlining special procedures
required for coordination. Include such items as required notices, reports, and list of
attendees at meetings.
5. Prepare similar memoranda for Owner and separate contractors if coordination of their
Work is required.
B. Administrative Procedures: Coordinate scheduling and timing of required administrative
procedures with other construction activities and activities of other contractors to avoid
conflicts and to ensure orderly progress of the Work. Such administrative activities include, but
are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of
the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Engineer will return RFIs submitted to Engineer by other entities controlled by
Contractor with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's
work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or
interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of Engineer.
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time
or the Contract Sum, Contractor shall state impact in the RFI.
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data,
Shop Drawings, coordination drawings, and other information necessary to fully
describe items needing interpretation.
C. Engineer's Action: Engineer will review each RFI, determine action required, and respond.
D. Allow seven working days for Engineer's response for each RFI.
E. The following RFIs will be returned without action:
1. Requests for approval of submittals.
2. Requests for approval of substitutions.
3. Requests for coordination information already indicated in the Contract Documents.
4. Requests for adjustments in the Contract Time or the Contract Sum.
5. Requests for interpretation of Architect's actions on submittals.
6. Incomplete RFIs or inaccurately prepared RFIs.
F. Engineer's action may include a request for additional information, in which case
1. Engineer's time for response will date from time of receipt of additional information.
G. Engineer's action on RFIs that may result in a change to the Contract Time or the Contract Sum
may be eligible for Contractor to submit Change Proposal according to
1. Section 012600 "Contract Modification Procedures."
2. If Contractor believes the RFI response warrants change in the Contract Time or the
Contract Sum, notify Engineer in writing within 10 days of receipt of the RFI response.
H. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
1. Submit log bi-weekly. Include the following:
2. Project name.
3. Name and address of Contractor.
4. Name and address of Engineer.
5. RFI number including RFIs that were dropped and not submitted.
6. RFI description.
7. Date the RFI was submitted.
8. Date Engineer's response was received.
I. On receipt of Engineer's action, update the RFI log and immediately distribute the RFI response
to affected parties. Review response and notify Engineer within seven days if Contractor
disagrees with response.
1. Identification of related Minor Change in the Work, Construction Change Directive, and
Proposal Request, as appropriate.
2. Identification of related Field Order, Work Change Directive, and Proposal Request, as
appropriate.
1.6 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site unless otherwise
indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is
required, of date and time of each meeting. Notify Owner and Engineer of scheduled
meeting dates and times.
3. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
4. Minutes: Entity responsible for conducting meeting will record significant discussions
and agreements achieved. Distribute the meeting minutes to everyone concerned,
including Owner and Engineer within three days of the meeting. Any revisions to the
minutes requested for correction will be done so and redistributed prior to the following
meeting or within 3 days of request whichever should come first.
B. Preconstruction Conference: Schedule and conduct a preconstruction conference before
starting construction, at a time convenient to Owner and Engineer, but no later than 15 calendar
days after execution of the Agreement.
1. Attendees: Authorized representatives of Owner, Engineer, and their consultants;
Contractor and its superintendent; major subcontractors; suppliers; and other
concerned parties shall attend the conference. Participants at the conference shall be
familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Critical work sequencing and long-lead items.
c. Designation of key personnel and their duties.
d. Procedures for processing field decisions and Change Orders.
e. Procedures for RFIs.
f. Procedures for testing and inspecting.
g. Procedures for processing Applications for Payment.
h. Distribution of the Contract Documents.
i. Submittal procedures.
j. Preparation of record documents.
k. Use of the premises.
l. Work restrictions.
m. Working hours.
n. Owner's occupancy requirements.
o. Responsibility for temporary facilities and controls.
p. Procedures for moisture and mold control.
q. Procedures for disruptions and shutdowns.
r. Construction waste management and recycling.
s. Parking availability.
t. Office, work, and storage areas.
u. Equipment deliveries and priorities.
v. Safety and First aid.
w. Security.
x. Progress cleaning.
3. Minutes: Entity responsible for conducting meeting will record and distribute meeting
Minutes.
C. Pre-installation Conferences: Conduct a pre-installation conference at Project site before each
construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or
affected by the installation and its coordination or integration with other materials and
installations that have preceded or will follow, shall attend the meeting. Advise
Engineer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the
particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Review of mockups.
i. Possible conflicts.
j. Compatibility problems.
k. Time schedules.
l. Weather limitations.
m. Manufacturer's written instructions.
n. Warranty requirements.
o. Compatibility of materials.
p. Acceptability of substrates.
q. Temporary facilities and controls.
r. Space and access limitations.
s. Regulations of authorities having jurisdiction.
t. Testing and inspecting requirements.
u. Installation procedures.
v. Coordination with other work.
w. Required performance results.
x. Protection of adjacent work.
y. Protection of construction and personnel.
4. Record significant conference discussions, agreements, and disagreements, including
required corrective measures and actions.
5. Reporting: Distribute minutes of the meeting to each party present and to other parties
requiring information within 3 business days.
6. Do not proceed with installation if the conference cannot be successfully concluded.
7. Initiate whatever actions are necessary to resolve impediments to performance of the
8. Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: Conduct progress meetings at weekly intervals.
1. Attendees: In addition to representatives of Owner, each contractor, subcontractor,
supplier, and other entity concerned with current progress or involved in planning,
coordination, or performance of future activities shall be represented at these meetings.
2. All participants at the meeting shall be familiar with Project and authorized to conclude
matters relating to the Work.
3. Agenda: Review and correct or approve minutes of previous progress meeting. Review
other items of significance that could affect progress. Include topics for discussion as
appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
i. Determine whether each activity is on time, ahead of schedule, or behind
schedule, in relation to Contractor's construction schedule. Determine how
construction behind schedule will be expedited; secure commitments from
parties involved to do so. Discuss whether schedule revisions are required
to ensure that current and subsequent activities will be completed within
the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the
following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Progress cleaning.
10) Quality and work standards.
11) Status of correction of deficient items.
12) Field observations.
13) Status of RFIs.
14) Status of proposal requests.
15) Pending changes.
16) Status of Change Orders.
17) Pending claims and disputes.
18) Documentation of information for payment requests.
4. Minutes: Entity responsible for conducting the meeting will record and distribute the
meeting minutes to each party present and to parties requiring information.
5. Schedule Updating: Revise Contractor's construction schedule after each progress
meeting where revisions to the schedule have been made or recognized. Issue revised
schedule concurrently with the report of each meeting.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
SECTION 01 31 13 – PROJECT COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section specifies administrative and supervisory requirements necessary for Project
coordination including, but not necessarily limited to:
1. Interface between Contractor and Owner’s consultants.
2. Project coordination.
3. Structural, mechanical, plumbing, electrical, and fire protection coordination including
coordination drawings.
4. Administration and supervision.
5. Cleaning and protection.
6. Owner’s separate contracts.
7. Coordination with Owner.
1.2 COORDINATION
A. Coordinate construction activities included under various Sections of the Specifications to assure
efficient and orderly installation of each part of the Work. Coordinate construction operations
under different Sections of the Specifications that are dependent upon each other for proper
installation, connection, and operation.
1. Where installation of one part of the Work is dependent on installation of other
components, either before or after its own installation, schedule construction activities in
the sequence required to obtain the best results.
2. Where availability of space is limited, coordinate installation of different components to
assure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items schedules for later installation.
B. Prepare memoranda for distribution to each party involved outlining special procedures required
for coordination. Include such items as required notices, reports, and attendance at meetings.
1. Prepare similar memoranda for the Owner’s consultants and separate contractors where
coordination of their Work is required.
C. Coordinate scheduling and timing of required administrative procedures with other construction
activities to avoid conflicts and ensure orderly progress of the work. Such administrative activities
include but are not limited to:
1. Preparation of schedules.
2. Installation and removal of temporary facilities.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project Close-out activities.
6. Owner’s separate installation contracts.
1.3 SUBMTITALS
A. Provide coordination drawings for the integration of the Work, including Work first shown in
detail on Shop Drawings or product data. Show sequencing and relationship of separate units of
work which must interface in a restricted manner to fit in the space provided or function as
indicated. Coordination drawings are considered Shop Drawings and must be definitive in nature.
1. Prepare and submit coordinated composite layouts of the mechanical, plumbing,
electrical, and fire protection systems and equipment for all areas; drawn at a scale of not
less than ¼ inch per foot showing on both plan and/or elevation including but not limited
to all equipment, ducts, pipe sleeves, piping including plumbing and sprinkler systems,
lighting, special supports, and other items contained within the space. Show mechanical,
plumbing, electrical, and fire protection services as well as architectural and structural
features drawn to scale. Provide composite drawings for all areas such as corridors,
specify specialty spaces, mechanical rooms, shafts, tunnels, and all congested areas.
Copies of all composite drawings shall be distributed to all trades to assure a complete,
coordinated installation of work within the space available.
2. Show interrelationship of components shown on separate Shop Drawings.
3. Indicate required installation sequences.
4. Comply with requirements contained in Division l, Requirements for Shop Drawings,
Product Data, and Samples.
5. Refer to Division 22, Basic Plumbing Requirements, Division 23, Basic Mechanical
Requirements and Division 26, Basic Electrical Requirements for specific coordination
Drawing requirements for plumbing, mechanical and electrical installations.
6. Coordinated composite layouts of the ceiling including mechanical, plumbing, electrical,
and fire protection.
7. Submit coordination drawings to the Architect for review, comment, and approval. More
than one (l) submission of the coordination drawings isanticipated due to review
comments. Subsequent changes and resubmission of drawings shall be at the
Contractor’s expense.
B. Within l5 days of Notice to Proceed, submit a list of the Contractor’s principalstaff assignments,
including the Superintendent and other personnel in attendance at the site: identify individuals,
their duties and responsibilities; list their addresses and telephone numbers; complete list of
subcontractors, manufacturers, and suppliers.
1. Post copies of the list in the Project meeting room, the temporary field office, and each
temporary telephone.
PART 2 PRODUCTS
(Not Applicable)
PART 3 EXECUTION
3.1 GENERAL INSTALLATION PROVISIONS
A. Require the installer of each major component to inspect both the substrate and conditions under
which Work is to be performed. Do not proceed until unsatisfactory conditions have been
corrected in an acceptable manner.
B. Comply with manufacturer’s installation instructions and recommendations to the extent that
those instructions and recommendations are more explicit or stringent than requirements
contained in Contract Documents. The preceding shall not result in additional costs to the Owner.
C. Inspect materials and equipment immediately upon delivery and again prior to installation. Reject
any damaged or defective items.
D. Provide attachment and constructions devices and methods necessary for securing Work. Secure
Work true to line and level. Allow for expansion and building movement.
E. Provide uniform joint widths in exposed Work. Arrange joints in exposed Work to best visual
effect. Refer all arrangements to the Architect for final decision before starting work.
F. Recheck measurements and dimensions before starting each installation.
G. Install each component during weather conditions and Project status that will ensure the best
possible results. Isolate each part of the completed construction from incompatible material as
necessary to prevent deterioration.
H. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of
uncovering completed construction for that purpose.
I. Where mounting heights are not indicated, install individual components at standard mounting
heights recognized within the industry for the particular application indicated. Refer questionable
mounting height decision to the Architect for final decision.
J. Coordinate and insure all Data, Communications, and Security installations conform with all the
requirements of the Contract Documents and/or the Owner’s separate contract for the same
installations.
3.2 CLEANING AND PROTECTIONS
A. During handling and installation, clean and protect construction in progress and adjoining
materials in place. Apply protective covering where required to ensure protection from damage
or deterioration at Substantial Completion.
B. Clean and maintain completed construction as frequently as necessary through the remainder of
the construction period. Adjust and lubricate operable components to ensure operability without
damaging effects.
C. Supervise construction activities to ensure that no part of the construction, completed or in
progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during
the construction period.
END OF SECTION 01 17 04
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.01
SECTION INCLUDES
A. Submittal procedures.
B. Proposed products list.
C. Shop drawings and product data.
D. Manufacturers’ instructions.
E. Manufacturers’ certificates.
1.02
SUBMITTAL PROCEDURES
A. Identify Project, Contractor, Subcontractor or Supplier, pertinent Drawing sheet and detail
number(s), and Specification Section number, as appropriate.
B. Apply Contractor’s stamp, signed or initialed certifying that review, verification of Products
required, field dimensions, adjacent construction work, and coordination of information, is in
accordance with the requirements of the Work and Contract Documents.
C. Schedule submittals to expedite the Project, and deliver to Architect/Engineer at business address.
Coordinate submission of related items.
D. Identify variations from Contract Documents and Product or system limitations which may be
detrimental to successful performance of the completed Work.
E. Revise and resubmit submittals when changes occur; identify all changes made since previous
submittal.
F.
1.03
Distribute copies of reviewed submittals to concerned parties. Instruct parties to promptly report
any inability to comply with provisions.
PROPOSED PRODUCTS LIST
A. Submit complete list of major products proposed for use, with name of manufacturer and trade
name of each product.
1.04
SHOP DRAWINGS AND PRODUCT DATA
A. Submit five (5) copies which will be reviewed by Architect/Engineer.
1.05
MANUFACTURERS’ INSTRUCTIONS
A. Submit manufacturers’ printed instructions for delivery, storage, assembly, installation, and
finishing.
B. Identify conflicts between manufacturers’ instructions and Contract Documents.
1.06
MANUFACTURERS’ CERTIFICATES
A. When specified in individual Specification Sections, submit manufacturers’ certificates to
Architect/Engineer for review, in quantities specified for Product Data.
B. Indicate material or product conforms to or exceeds specified requirements. Submit supporting
reference data, affidavits and certifications as appropriate.
C. Certificates may be recent or previous test results on material or Product, but must be acceptable
to Architect/Engineer.
1.07
SCHEDULE
A. Within ten (10) days after signing the Contract, the Contractor shall submit a schedule in either bar
chart or CPM format, sufficiently detailed so that actual progress may be easily compared with
scheduled progress.
PART 2 to 3 – Not Used
END OF SECTION 01 33 00
SECTION 01 40 00 - QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for quality assurance and quality
control.
B. Testing and inspecting services are required to verify compliance with requirements specified or
indicated. These services do not relieve Contractor of responsibility for compliance with the
Contract Document requirements.
C. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance
and -control procedures that facilitate compliance with the Contract Document requirements.
D. Requirements for Contractor to provide quality-assurance and -control services required by
Engineer, Owner, or authorities having jurisdiction are not limited by provisions of this Section.
E. Specific test and inspection requirements are not specified in this Section.
1.2 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during
execution of the Work to guard against defects and deficiencies and substantiate that proposed
construction will comply with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after
execution of the Work to evaluate that actual products incorporated into the Work and
completed construction comply with requirements. Services do not include contract
enforcement activities performed by Engineer.
C. Mockups: Full-size physical assemblies that are constructed on-site. Mockups are constructed
to verify selections made under Sample submittals; to demonstrate aesthetic effects and, where
indicated, qualities of materials and execution; to review coordination, testing, or operation; to
show interface between dissimilar materials; and to demonstrate compliance with specified
installation tolerances. Mockups are not Samples. Unless otherwise indicated, approved
mockups establish the standard by which the Work will be judged.
D. Preconstruction Testing: Tests and inspections performed specifically for Project before
products and materials are incorporated into the Work, to verify performance or compliance
with specified criteria.
E. Product Testing: Tests and inspections that are performed by a testing agency qualified to
conduct product testing and acceptable to authorities having jurisdiction, to establish product
performance and compliance with specified requirements.
F. Source Quality-Control Testing: Tests and inspections that are performed at the source, e.g.,
plant, mill, factory, or shop.
G. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation
of the Work and for completed Work.
H. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing
laboratory shall mean the same as testing agency.
I.
J.
Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an
employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation,
including installation, erection, application, and similar operations.
1. Use of trade-specific terminology in referring to a trade or entity does not require that
certain construction activities be performed by accredited or unionized individuals, or
that requirements specified apply exclusively to specific trade(s).
Experienced: When used with an entity or individual, "experienced" means having successfully
completed a minimum of five previous projects similar in nature, size, and extent to this Project;
being familiar with special requirements indicated; and having complied with requirements of
authorities having jurisdiction.
1.3 CONFLICTING REQUIREMENTS
A. Referenced Standards: If compliance with two or more standards is specified and the standards
establish different or conflicting requirements for minimum quantities or quality levels, comply
with the most stringent requirement. Refer conflicting requirements that are different, but
apparently equal, to Engineer for a decision before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be
the minimum provided or performed. The actual installation may comply exactly with the
minimum quantity or quality specified, or it may exceed the minimum within reasonable limits.
C. To comply with these requirements, indicated numeric values are minimum or maximum, as
appropriate, for the context of requirements. Refer uncertainties to Engineer for a decision
before proceeding.
1.4 INFORMATIONAL SUBMITTALS
A. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to
demonstrate their capabilities and experience. Include proof of qualifications in the form of a
recent report on the inspection of the testing agency by a recognized authority.
1.5 REPORTS AND DOCUMENTS
A. Test and Inspection Reports: Prepare and submit certified written reports specified in other
Sections. Include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
9. Test and inspection results and an interpretation of test results.
10. Record of temperature and weather conditions at time of sample taking and testing and
inspecting.
11. Comments or professional opinion on whether tested or inspected Work complies with
the Contract Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on re-testing and re-inspecting.
B. Manufacturer's Field Reports: Prepare written information documenting tests and inspections
specified in other Sections. Include the following:
1. Name, address, and telephone number of representative making report.
2. Statement on condition of substrates and their acceptability for installation of product.
3. Summary of installation procedures being followed, whether they comply with
requirements and, if not, what corrective action was taken.
4. Results of operational and other tests and a statement of whether observed
performance complies with requirements.
5. Other required items indicated in individual Specification Sections.
C. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses,
certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee
payments, judgments, correspondence, records, and similar documents, established for
compliance with standards and regulations bearing on performance of the Work.
1.6 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this article establish the minimum qualification levels
required; individual Specification Sections specify additional requirements.
B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar
to those indicated for this Project and with a record of successful in-service performance, as well
as sufficient production capacity to produce required units.
C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated
for this Project and with a record of successful in-service performance, as well as sufficient
production capacity to produce required units.
D. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling
work similar in material, design, and extent to that indicated for this Project, whose work has
resulted in construction with a record of successful in-service performance.
E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice
in jurisdiction where Project is located and who is experienced in providing engineering services
of the kind indicated. Engineering services are defined as those performed for installations of
the system, assembly, or product that are similar in material, design, and extent to those
indicated for this Project.
F. Specialists: Certain Specification Sections require that specific construction activities shall be
performed by entities who are recognized experts in those operations. Specialists shall satisfy
qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirements of authorities having jurisdiction shall supersede requirements for
specialists.
G. Testing Agency Qualifications: An independent agency with the experience and capability to
conduct testing and inspecting indicated, as documented according to ASTM E 329; and with
additional qualifications specified in individual Sections; and, where required by authorities
having jurisdiction, that is acceptable to authorities.
H. Manufacturer's Representative Qualifications: An authorized representative of manufacturer
who is trained and approved by manufacturer to observe and inspect installation of
manufacturer's products that are similar in material, design, and extent to those indicated for
this Project.
1.7 QUALITY CONTROL
A. Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility,
Owner will engage a qualified testing agency to perform these services.
1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing
agencies engaged and a description of types of testing and inspecting they are engaged
to perform.
2. Costs for re-testing and re-inspecting construction that replaces or is necessitated by
work that failed to comply with the Contract Documents will be charged to Contractor.
3. Owner will provide geotechnical quality control services at UMPI’s expense. All other
quality control requirements are the responsibility of the Contractor.
B. Contractor Responsibilities: Tests and inspections not explicitly assigned to Owner are
Contractor's responsibility. Perform additional quality-control activities required to verify that
the Work complies with requirements, whether specified or not.
1. Where services are indicated as Contractor's responsibility, engage a qualified testing
agency to perform these quality-control services.
a. Contractor shall not employ same entity engaged by Owner, unless agreed to
in writing by Owner.
2. Notify testing agencies at least 24 hours in advance of time when Work that requires
testing or inspecting will be performed.
3. Where quality-control services are indicated as Contractor's responsibility, submit a
Certified written report, in duplicate, of each quality-control service.
4. Testing and inspecting requested by Contractor and not required by the Contract.
5. Documents are Contractor's responsibility.
6. Submit additional copies of each written report directly to authorities having
jurisdiction, when they so direct.
C. Manufacturer's Field Services: Where indicated, engage a manufacturer's representative to
observe and inspect the Work. Manufacturer's representative's services include examination of
substrates and conditions, verification of materials, inspection of completed portions of the
Work, and submittal of written reports.
D. Retesting/Re-inspecting: Regardless of whether original tests or inspections were Contractor's
responsibility, provide quality-control services, including retesting and re-inspecting, for
construction that replaced Work that failed to comply with the Contract Documents.
E. Testing Agency Responsibilities: Cooperate with Architect and Contractor in performance of
duties. Provide qualified personnel to perform required tests and inspections.
1. Notify Architect and Contractor promptly of irregularities or deficiencies observed in the
2. Work during performance of its services.
3. Determine the location from which test samples will be taken and in which in-situ tests
are conducted.
4. Conduct and interpret tests and inspections and state in each report whether tested and
inspected work complies with or deviates from requirements.
5. Submit a certified written report, in duplicate, of each test, inspection, and similar
quality-control service through Contractor.
6. Do not release, revoke, alter, or increase the Contract Document requirements or
approve or accept any portion of the Work.
7. Do not perform any duties of Contractor.
F. Associated Services: Cooperate with agencies performing required tests, inspections, and
similar quality-control services, and provide reasonable auxiliary services as requested. Notify
agency sufficiently in advance of operations to permit assignment of personnel. Provide the
following:
1. Access to the Work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
3. Adequate quantities of representative samples of materials that require testing and
inspecting. Assist agency in obtaining samples.
4. Facilities for storage and field curing of test samples.
5. Delivery of samples to testing agencies.
6. Preliminary design mix proposed for use for material mixes that require control by
testing agency.
7. Security and protection for samples and for testing and inspecting equipment at Project
site.
G. Coordination: Coordinate sequence of activities to accommodate required quality-assurance
and -control services with a minimum of delay and to avoid necessity of removing and replacing
construction to accommodate testing and inspecting.
H. Schedule times for tests, inspections, obtaining samples, and similar activities.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 TEST AND INSPECTION LOG
A. Test and Inspection Log: Prepare a record of tests and inspections. Include the following:
1. Date test or inspection was conducted.
2. Description of the Work tested or inspected.
3. Date test or inspection results were transmitted to Engineer.
4. Identification of testing agency or special inspector conducting test or inspection.
B. Maintain log at Project site. Post changes and revisions as they occur. Provide access to test
and inspection log for Engineer's reference during normal working hours.
3.2 REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair
damaged construction and restore substrates and finishes.
B. Provide materials and comply with installation requirements specified in other Specification
Sections or matching existing substrates and finishes. Restore patched areas and extend
restoration into adjoining areas with durable seams that are as invisible as possible. Comply
with the Contract Document requirements for cutting and patching in Section 017300
"Execution."
C. Protect construction exposed by or for quality-control service activities.
D. Repair and protection are Contractor's responsibility, regardless of the assignment of
responsibility for quality-control services.
END OF SECTION 01 40 00
SECTION 01 70 00 – Project Execution
PART 1 - GENERAL
1.1 SUMMARY
A. Work of this Section consists of execution and closeout requirements, and includes but is not
limited to the following:
1. Examination and Preparation
2. Execution
3. Cleaning
4. Starting and Adjusting
5. Protecting Installed Construction
B. Related Sections include the following:
1. All
1.2 EXECUTION
A. Execution Summary
1. Construction layout.
2. Field engineering and surveying.
3. General installation of products.
4. Coordination of Owner-installed products.
5. Progress cleaning.
6. Starting and adjusting.
7. Protection of installed construction.
8. Correction of the Work.
B. Execution Submittals
1. Submit Certified Surveys
2. Submit Final Property Survey
3. Submit Certificates certifying that location and elevation of improvements comply with
requirements.
4. Submit Land Surveyor Qualifications
PART 2 PRODUCTS
2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or
fabricator of the surface to be cleaned, and that meet requirements.
B. Do not use cleaning agents that are potentially hazardous to health or property or that might
damage finished surfaces.
PART 3 EXECUTION
3.1 EXAMINATION AND PREPARATION
A. Examination
1. Existing Structures: Research, investigate, explore location of existing above and belowground structures.
2. Existing Utilities: Research, investigate, explore location of existing above and belowground utilities.
a. Coordinate with “Dig Safe” and or private utility locating company, where
required.
3. Examine substrates, areas, and conditions for compliance with requirements for
installation tolerances and other conditions affecting performance.
C. Preparation
1. Furnish information to local utility that is necessary to adjust, move, or relocate existing
utility structures, utility poles, lines, services, or other utility appurtenances located in or
affected by construction. Coordinate with AHJ.
2. Take field measurements as required to fit the Work properly
3. Verify space requirements and dimensions.
4. Review Contract Documents with field conditions. Request necessary clarifications from
Architect.
D. Construction Layout
1. Verify existing benchmark, control point, and property corner locations.
a. Coordinate with Owner.
2. Engage a land surveyor or professional engineer to lay out the Work using accepted
surveying practices.
3. Site Improvements: Locate and lay out site improvements, including pavements, grading
and fill, utility slopes, and invert elevations
4. Building Lines and Levels: Locate and lay out control lines and levels for structures,
building foundations, column grids, and floor levels, including those required for
mechanical and electrical Work.
5. Record Log: Maintain a log of layout control Work.
E. Field Engineering
1. Reference Points: Locate and protect existing permanent benchmarks, control points,
and similar reference points.
2. Site Benchmarks: Establish and maintain a minimum of two permanent site benchmarks
on Project site, referenced to data established by survey control points.
3. Certified Survey: On completion of foundation walls, major site improvements, and
other work requiring field-engineering services, prepare a certified survey showing
dimensions, locations, angles, and elevations of construction and sitework.
F. Installation
1. Locate the Work and components of the Work accurately, in correct alignment and
elevation, plumb and level.
2. Comply with manufacturer's written instructions and recommendations for installing
products in applications indicated.
3. Obtain, distribute and use necessary templates.
4. Check, coordinate and ensure installed items correspond to approved Shop Drawings.
5. Anchors and Fasteners: Provide anchors and fasteners required to anchor each
component securely in place, accurately located and with items being fastened aligned
with other portions of the Work.
a. Allow for building movement, including thermal expansion and contraction.
b. Verify finish of exposed anchors and fasteners with Architect.
6. Joints: Make joints of uniform width.
a. Where joint locations in exposed Work are not indicated, arrange joints for
the best visual effect.
b. Fit exposed connections together to form hairline joints.
7. Hazardous Materials: Use products, cleaners, and installation materials that are not
hazardous.
G. Owner-Installed Products
1. Site Access: Provide access to Project site for Owner's construction forces.
2. Coordination: Coordinate construction and operations of the Work with work
performed by Owner's construction forces.
a. Construction Schedule: Coordinate mutually acceptable work schedules.
b. Pre-installation Conferences: Both work forces are to attend and participate in
pre-installation conferences covering portions of the Work that are to receive
Owner's work.
H. Maintenance of Pedestrian Traffic. Contractor shall at all times be aware and make provisions
to divert and protect pedestrian traffic from construction activities. This includes detours,
signage, barriers, notices, and advanced planning as required by UMPI Facilities Management.
3.2 PROJECT CLEANING
A. Construction Cleaning:
1. Clean Project site and Work areas broom clean daily.
a. Coordinate progress cleaning for joint-use areas where more than one
installer has worked.
b. Enforce requirements strictly.
c. Dispose of materials lawfully.
2. Clean and protect construction in progress and adjoining materials already in place
during handling and installation.
a. Apply protective covering where required to ensure protection from damage
or deterioration at
A. Substantial Completion
3. Clean and provide maintenance on completed construction as frequently as necessary
through the remainder of the construction period.
a. Adjust and lubricate operable components to ensure operability without
damaging effects.
4. Limiting Exposures: Supervise construction operations to assure that no part of the
construction, completed or in progress, is subject to harmful, dangerous, damaging, or
otherwise deleterious exposure during the construction period.
3.3 STARTING AND ADJUSTING
A. Start equipment and operating components to confirm proper operation. Remove
malfunctioning units, replace with new units, and retest.
B. Adjust operating components for proper operation without binding. Adjust equipment for
proper operation.
C. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties.
Replace damaged and malfunctioning controls and equipment.
D. Manufacturer's Field Service: If a factory-authorized service representative is required to inspect
field assembled components and equipment installation, comply with qualification
requirements in SECTION 014000, QUALITY REQUIREMENTS.
3.4 PROTECTING INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage
or deterioration at time of Substantial Completion.
B. Comply with manufacturer's written instructions for temperature and relative humidity.
C. Correction of The Work
1. Repair or remove and replace defective construction.
2. Restore damaged substrates and finishes to previous condition.
3. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be
repaired without visible evidence of repair.
4. Restore permanent facilities used during construction to their specified condition.
5. Repair components that do not operate properly.
6. Remove and replace operating components that cannot be repaired.
7. Remove and replace chipped, scratched, and broken glass or reflective surfaces.
END OF SECTION 01 73 00
SECTION 01 74 19 – CONSTRUCTION WASTE MANAGEMENT
PART 1 GENERAL
1.1
1.2
SUMMARY
A.
Section includes:
1.
Special requirements for waste management during renovation operations.
a.
Protect the environment, both on-site and off-site, during renovation
operations.
b.
Prevent environmental pollution and damage.
c.
Maximize source reduction, reuse and recycling of solid waste.
B.
Related Sections:
1.
01 30 00 (01300) - Administrative Requirements: Environmental Manager and
Contractor training requirements.
2.
01 40 00 (01400) – Quality Requirements: Meetings and project coordination.
3.
01 78 53 (01780) – Sustainable Design Close-Out Documentation.
4.
02 41 13 (02220) – Selective Site Demolition
DEFINITIONS
A.
Definitions pertaining to sustainable development: As defined in ASTM E2114.
B.
1.3
QUALITY ASSURANCE
A.
B.
1.4
Maximize use of source reduction and recycling procedures.
Diversion Goals: A minimum 75 percent by weight of total project solid waste to be
diverted from landfill.
PRECONSTRUCTION MEETING
A.
1.5
Deconstruction: Disassembly of buildings for the purpose of recovering materials.
After award of Contract and prior to the commencement of the Work, schedule and
conduct meeting with Owner and Architect to discuss the proposed Waste Management
Plan and to develop mutual understanding relative to details of environmental protection.
1.
Coordinate deconstruction with work of Section 02 41 19.13
SUBMITTALS
A.
Solid Waste Management Plan: Not less than 10 days before the Pre-construction
meeting, prepare and submit a Solid Waste Management Plan including, but not limited
to, the following:
1.
List of the recycling facilities, reuse facilities, municipal solid waste landfills and
other disposal area(s) to be used. Include:
a.
Name, location, and phone number.
b.
Copy of permit or license for each facility.
2.
Identify materials that cannot be recycled or reused. Provide explanation or
justification.
3.
Revise and resubmit Plan as required by Owner.
a.
Approval of Contractor’s Plan will not relieve the Contractor of
responsibility for compliance with applicable environmental regulations.
B.
Progress Documentation: Document solid waste disposal and diversion. Include the
quantity by weight of waste generated; waste diverted through sale, reuse, or recycling;
and waste disposed by landfill or incineration. Identify landfills, recycling centers, waste
processors, and other organizations that process or receive the solid waste.
1.
Document on form in Appendix A of this Section, or similar form as approved by
Owner.
2.
With each Application for Payment, submit updated Documentation for solid
waste disposal and diversion.
3.
With each Application for Payment, submit manifests, weight tickets, receipts,
and invoices specifically identifying the Project and waste material.
C.
Record Submittals: With Record Submittals as specified in Section 01 77 00, submit the
following:
1.
Summary of solid waste disposal and diversion.
PART 2 - PRODUCTS
PART 3 EXECUTION
3.1
SOLID WASTE MANAGEMENT
A.
Develop and implement a waste management program in accordance with ASTM E1609
and as specified herein.
B.
Collection: Implement a recycling/reuse program that includes separate collection of
waste materials of the following types as appropriate to the project waste and to the
available recycling and reuse programs in the project area:
1.
Land clearing debris.
2.
Asphalt.
3.
Concrete and Masonry.
4.
Metal.
a.
Ferrous.
b.
Non-ferrous.
5.
Wood, nails and staples allowed.
6.
Debris.
7.
Glass, colored glass allowed.
8.
Paper.
a.
Bond.
b.
Newsprint.
c.
Cardboard and paper packaging materials.
9.
Plastic.
a.
Type 1: Polyethylene Terephthalate (PET, PETE).
b.
Type 2: High Density Polyethylene (HDPE).
c.
Type 3: Vinyl (Polyvinyl Chloride or PVC).
d.
Type 4: Low Density Polyethylene (LDPE).
e.
Type 5: Polypropylene (PP).
f.
Type 6: Polystyrene (PS).
g.
Type 7: Other. Use of this code indicates that the package in question is
made with a resin other than the six listed above, or is made of more
than one resin listed above, and used in a multi-layer combination.
10.
Gypsum.
11.
Non-hazardous paint and paint cans.
12.
Flooring.
C.
D.
a.
Carpet.
b.
Resilient Flooring.
13.
Insulation.
14.
Ceiling Tiles
15.
Others as appropriate.
Recycling/Reuse: Maximize recycling and reuse of materials.
1.
Recycling/Reuse on project site: As indicated on Drawings and other to the
greatest extent possible.
Handling:
1.
Clean materials that are contaminated prior to placing in collection containers.
Deliver materials in accordance with recycling or reuse facility requirements (e.g.,
free of dirt, adhesives, solvents, petroleum contamination, and other substances
deleterious to recycling process).
2.
Arrange for collection by or delivery to the appropriate recycling or reuse facility.
3.
Hazardous Waste and Hazardous Materials: Notify Owner immediately. Owner
will coordinate removal and remediation.
END OF SECTION
Appendix A
SUMMARY OF SOLID WASTE DISPOSAL AND DIVERSION
Project Name:
Project Number:
Contractor Name:
License
Number:
Contractor Address:
Solid Waste
Material
Appliances
Asphalt
Cardboard
Carpet
Concrete
Gypsum Drywall
Land
Clearing/Soil
Masonry
Metals: Ferrous
Metals:
Nonferrous
Mixed/Comingled
Waste
Plastic
Roofing:
Asphaltbased
Roofing: EPDM
Salvaged/Surplu
s Materials for
Reuse
Wood:
Landclearing
Debris
Wood: Scrap
Lumber
Ceiling Tiles
Vinyl
Composition Tile
(VCT)
Other:
Date Material
Disposed/
Diverted
Amount
Disposed/
Diverted (ton
or cubic yard)
Municipal
Solid Waste
Facility
(name,
address, &
phone number)
Recycling/
Reuse Facility
(name,
address, &
phone number)
Comments (if
disposed, state
why not
diverted)
Signature:
Date:
SECTION 01 77 00 - CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout, including,
but not limited to, the following:
1. Substantial Completion procedures.
2. Final completion procedures.
3. Warranties.
4. Final cleaning.
5. Repair of the Work.
B. Related Requirements:
1. Section 01 78 23 "Operation and Maintenance Data" for operation and maintenance
manual requirements.
2. Section 017839 "Project Record Documents" for submitting record Drawings, record
Specifications, and record Product Data.
1.2 ACTION SUBMITTALS
A. Product Data: For cleaning agents.
B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.
C. Certified List of Incomplete Items: Final submittal at Final Completion.
1.3 CLOSEOUT SUBMITTALS
A. Certificates of Release: From authorities having jurisdiction.
B. Certificate of Insurance: For continuing coverage.
1.4 MAINTENANCE MATERIAL SUBMITTALS
A. Schedule of Maintenance Material Items: For maintenance material submittal items specified in
other Sections.
1.5 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and
corrected (Contractor's punch list), indicating the value of each item on the list and reasons why
the Work is incomplete.
B. Submittals Prior to Substantial Completion: Complete the following a minimum of 10 days prior
to requesting inspection for determining date of Substantial Completion. List items below that
are incomplete at time of request.
3. Certificates of Release: Obtain and submit releases from authorities having jurisdiction
permitting Owner unrestricted use of the Work and access to services and utilities.
Include occupancy permits, operating certificates, and similar releases.
4. Submit closeout submittals specified in other Division 01 Sections, including project
record documents, operation and maintenance manuals, final completion construction
photographic documentation, damage or settlement surveys, property surveys, and
similar final record information.
5. Submit closeout submittals specified in individual Sections, including specific warranties,
workmanship bonds, maintenance service agreements, final certifications, and similar
documents.
6. Submit maintenance material submittals specified in individual Sections, including tools,
spare parts, extra materials, and similar items, and deliver to location designated by
Owner. Label with manufacturer's name and model number where applicable.
a. Schedule of Maintenance Material Items: Prepare and submit schedule of
maintenance material submittal items, including name and quantity of each
item and name and number of related Specification Section. Obtain Owner’s
signature for receipt of submittals.
7. Submit test/adjust/balance records.
8. Submit changeover information related to Owner's occupancy, use, operation, and
maintenance.
C. Procedures Prior to Substantial Completion: Complete the following a minimum of 10 days prior
to requesting inspection for determining date of Substantial Completion. List items below that
are incomplete at time of request.
1. Advise Owner of pending insurance changeover requirements.
2. Complete startup and testing of systems and equipment.
3. Perform preventive maintenance on equipment used prior to Substantial Completion.
4. Instruct Owner's personnel in operation, adjustment, and maintenance of products,
equipment, and systems. Submit demonstration and training video recordings specified
in Section 017900 "Demonstration and Training."
5. Advise Owner of changeover in heat and other utilities.
6. Participate with Owner in conducting inspection and walkthrough with local emergency
responders.
7. Terminate and remove temporary facilities from Project site, along with mockups,
construction tools, and similar elements.
8. Complete final cleaning requirements, including touchup painting.
9. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual
defects.
D. Inspection: Submit a written request for inspection to determine Substantial Completion a
minimum of 10 days prior to date the work will be completed and ready for final inspection and
tests. On receipt of request, Engineer will either proceed with inspection or notify Contractor of
unfulfilled requirements. Engineer will prepare the Certificate of Substantial Completion after
inspection or will notify Contractor of items, either on Contractor's list or additional items
identified by Architect, that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as
incomplete is completed or corrected.
2. Results of completed inspection will form the basis of requirements for final completion.
1.6 FINAL COMPLETION PROCEDURES
A. Preliminary Procedures: Before requesting final inspection for determining final completion,
complete the following:
1. Submit a final Application for Payment
2. Certified List of Incomplete Items: Submit certified copy of Engineer's Substantial
3. Completion inspection list of items to be completed or corrected (punch list), endorsed
and dated by Engineer. Certified copy of the list shall state that each item has been
completed or otherwise resolved for acceptance.
4. Certificate of Insurance: Submit evidence of final, continuing insurance coverage
complying with insurance requirements.
5. Instruct Owner's personnel in operation, adjustment, and maintenance of products,
equipment, and systems.
B. Inspection: Submit a written request for final inspection to determine acceptance. On receipt
of request, Engineer will either proceed with inspection or notify Contractor of unfulfilled
requirements. Engineer will prepare a final Certificate for Payment after inspection or will notify
Contractor of construction that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as
incomplete is completed or corrected.
1.7 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Organization of List: Include name and identification of each space and area affected by
construction operations for incomplete items and items needing correction including, if
necessary, areas disturbed by Contractor that are outside the limits of construction.
1. Organize list of spaces in sequential order, starting with exterior areas first.
2. Organize items applying to each space by major element, including categories for
ceiling, individual walls, floors, equipment, and building systems.
3. Submit list of incomplete items in the following format:
4. PDF electronic file. Engineer will return annotated copy.
1.8 SUBMITTAL OF PROJECT WARRANTIES
A. Time of Submittal: Submit written warranties on request of Engineer for designated portions of
the Work where commencement of warranties other than date of Substantial Completion is
indicated, or when delay in submittal of warranties might limit Owner's rights under warranty.
B. Organize warranty documents into an orderly sequence based on the table of contents of the
Project Manual.
1. Bind warranties and bonds in heavy-duty, three-ring, vinyl-covered, loose-leaf binders,
thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch
(215-by-280-mm) paper.
2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty.
Mark tab to identify the product or installation. Provide a typed description of the
product or installation, including the name of the product and the name, address, and
telephone number of Installer.
3. Identify each binder on the front and spine with the typed or printed title
4. "WARRANTIES," Project name, and name of Contractor.
5. Warranty Electronic File: Scan warranties and bonds and assemble complete warranty
and bond submittal package into a single indexed electronic PDF file with links enabling
navigation to each item. Provide bookmarked table of contents at beginning of
document.
C. Provide additional copies of each warranty to include in operation and maintenance manuals.
PART 2 – PRODUCTS
2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or
fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially
hazardous to health or property or that might damage finished surfaces.
PART 3 - EXECUTION
3.1 FINAL CLEANING
A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply
with local laws and ordinances and Federal and local environmental and antipollution
regulations.
B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each
surface or unit to condition expected in an average commercial building cleaning and
maintenance program. Comply with manufacturer's written instructions.
1. Complete the following cleaning operations before requesting inspection for
certification of Substantial Completion for entire Project or for a designated portion of
Project:
a. Clean Project site, yard, and grounds, in areas disturbed by construction
activities, including landscape development areas, of rubbish, waste material,
litter, and other foreign substances.
b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and
other foreign deposits.
c. Rake grounds that are neither planted nor paved to a smooth, even-textured
surface.
d. Remove tools, construction equipment, machinery, and surplus material from
Project site.
e. Remove snow and ice to provide safe access to building.
f. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free
condition, free of stains, films, and similar foreign substances. Avoid disturbing
natural weathering of exterior surfaces. Restore reflective surfaces to their
original condition.
g. Remove debris and surface dust from limited access spaces, including roofs,
plenums, shafts, trenches, equipment vaults, manholes, attics, and similar
spaces.
h. Sweep concrete floors broom clean in unoccupied spaces.
i. Remove labels that are not permanent.
j. Wipe surfaces of mechanical and electrical equipment and similar equipment.
k. Remove excess lubrication, paint and mortar droppings, and other foreign
substances.
l. Clean plumbing fixtures to a sanitary condition, free of stains, including stains
resulting from water exposure.
m. Leave Project clean and ready for occupancy.
3.2 REPAIR OF THE WORK
A. Complete repair and restoration operations before requesting inspection for determination of
Substantial Completion.
B. Repair or remove and replace defective construction. Repairing includes replacing defective
parts, refinishing damaged surfaces, touching up with matching materials, and properly
adjusting operating equipment. Where damaged or worn items cannot be repaired or restored,
provide replacements. Remove and replace operating components that cannot be repaired.
C. Restore damaged construction and permanent facilities used during construction to specified
condition.
D. Touch up and otherwise repair and restore marred or exposed finishes and surfaces.
E. Replace finishes and surfaces that that already show evidence of repair or restoration.
F. Do not paint over "UL" and other required labels and identification, including mechanical and
electrical nameplates. Remove paint applied to required labels and identification.
G. Replace parts subject to operating conditions during construction that may impede operation or
reduce longevity.
END OF SECTION 01 77 00
SECTION 01 78 23 OPERATIONS AND MAINTENANCE DATA
PART 1 - GENERAL
1.01
Related Documents
A. Drawings and general provisions of the Contract and Division 01 specification sections, apply to this section.
1.02
Summary
A. Section includes administrative and procedural requirements for preparing operation and maintenance
manuals, including the following:
1. Operation and maintenance documentation directory.
2. Emergency manuals.
3. Operation manuals for systems, subsystems, and equipment.
4. Product maintenance manuals.
5. Systems and equipment maintenance manuals.
6. Posted electronic maintenance manuals. B. Related Requirements:
1. Section 01 33 00 "Submittal Procedures" for submitting copies of submittals for operation and
maintenance manuals.
1.03
Definitions
A.
System: An organized collection of parts, equipment, or subsystems united by regular interaction.
B.
Subsystem: A portion of a system with characteristics similar to a system.
1.04
A.
B.
Closeout Submittals
Manual Content: Operations and maintenance manual content is specified in individual specification
sections to be reviewed at the time of section submittals. Submit reviewed manual content formatted and
organized as required by this section.
1.
Architect will comment on whether content of operations and maintenance submittals are
acceptable.
2.
Where applicable, clarify and update reviewed manual content to correspond to revisions and field
conditions.
Format: Submit operations and maintenance manuals in the following format:
1.
PDF electronic file. Assemble each manual into a composite electronically indexed file.
a. Name each indexed document file in composite electronic index with applicable item name.
Include a complete electronically linked operation and maintenance directory.
b. Enable inserted reviewer comments on draft submittals.
2.
One paper copies of each Manual. Include a complete operation and maintenance directory.
C.
Initial Manual Submittal: Submit draft copy of each manual at least 30 days before commencing
demonstration and training. Architect and Commissioning Authority will comment on whether general
scope and content of manual are acceptable.
D.
Final Manual Submittal: Submit each manual in final form prior to requesting inspection for Substantial
Completion and at least 15 days before commencing demonstration and training. Architect and
Commissioning Authority will return copy with comments.
1.
Correct or revise each manual to comply with Architect's and Commissioning Authority's
comments. Submit copies of each corrected manual within 15 days of receipt of Architect's and
Commissioning Authority's comments and prior to commencing demonstration and training.
PART 2 - PRODUCTS
2.01
A.
Operation and Maintenance Documentation Directory
Directory: Prepare a single, comprehensive directory of emergency, operation, and maintenance data and
materials, listing items and their location to facilitate ready access to desired information. Include a section
in the directory for each of the following:
1.
List of documents.
2.
List of systems.
3.
List of equipment.
4.
Table of contents.
B.
List of Systems and Subsystems: List systems alphabetically. Include references to operation and
maintenance manuals that contain information about each system.
C.
List of Equipment: List equipment for each system, organized alphabetically by system. For pieces of
equipment not part of system, list alphabetically in separate list.
D.
Tables of Contents: Include a table of contents for each emergency, operation, and maintenance manual.
E.
Identification: In the documentation directory and in each operation and maintenance manual, identify
each system, subsystem, and piece of equipment with same designation used in the Contract Documents.
If no designation exists, assign a designation according to ASHRAE Guideline 4, "Preparation of Operating
and Maintenance Documentation for Building Systems."
2.02
A.
B.
Requirements for Emergency, Operation, and Maintenance Manuals
Organization: Unless otherwise indicated, organize each manual into a separate section for each system
and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall
contain the following materials, in the order listed:
1.
Title page.
2.
Table of contents.
3.
Manual contents.
Title Page: Include the following information:
1.
Subject matter included in manual.
2.
Name and address of Project.
3.
Name and address of Owner.
C.
4.
Date of submittal.
5.
Name and contact information for Contractor.
6.
Name and contact information for Architect.
7.
Name and contact information for Commissioning Authority.
8.
Names and contact information for major consultants to the Architect that designed the systems
contained in the manuals.
9.
Cross-reference to related systems in other operation and maintenance manuals.
Table of Contents: List each product included in manual, identified by product name, indexed to the content
of the volume, and cross-referenced to specification section number in Project Manual.
1.
If operation or maintenance documentation requires more than one volume to accommodate
data, include comprehensive table of contents for all volumes in each volume of the set.
D.
Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system,
subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components
of one system into a single binder.
E.
Manuals, Electronic Files: Submit manuals in the form of a multiple file composite electronic PDF file for
each manual type required.
F.
1.
Electronic Files: Use electronic files prepared by manufacturer where available. Where scanning of
paper documents is required, configure scanned file for minimum readable file size.
2.
File Names and Bookmarks: Enable bookmarking of individual documents based on file names.
Name document files to correspond to system, subsystem, and equipment names used in manual
directory and table of contents. Group documents for each system and subsystem into individual
composite bookmarked files, then create composite manual, so that resulting bookmarks reflect
the system, subsystem, and equipment names in a readily navigated file tree. Configure electronic
manual to display bookmark panel on opening file.
Manuals, Paper Copy: Submit manuals in the form of hard copy, bound and labeled volumes.
1.
Binders: Heavy-duty, three-ring, vinyl-covered, post-type binders, in thickness necessary to
accommodate contents, sized to hold 8-1/2-by-11” paper; with clear plastic sleeve on spine to hold
label describing contents and with pockets inside covers to hold folded oversize sheets.
a. If two or more binders are necessary to accommodate data of a system, organize data in each
binder into groupings by subsystem and related components. Cross-reference other binders if
necessary to provide essential information for proper operation or maintenance of equipment
or system.
b. Identify each binder on front and spine, with printed title "OPERATION AND MAINTENANCE
MANUAL," Project title or name, and subject matter of contents, and indicate specification
section number on bottom of spine. Indicate volume number for multiple-volume sets.
2.
Dividers: Heavy-paper dividers with plastic-covered tabs for each section of the manual. Mark each
tab to indicate contents. Include typed list of products and major components of equipment
included in the section on each divider, cross-referenced to specification section number and title
of Project Manual.
3.
Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic software
storage media for computerized electronic equipment.
4.
Supplementary Text: Prepared on 8-1/2-by-11” white bond paper.
5.
Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.
a. If oversize drawings are necessary, fold drawings to same size as text pages and use as
foldouts.
b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes
and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten
pages indicating drawing titles, descriptions of contents, and drawing locations.
2.03
A.
B.
Emergency Manuals
Content: Organize manual into a separate section for each of the following:
1.
Type of emergency.
2.
Emergency instructions.
3.
Emergency procedures.
Type of Emergency: Where applicable for each type of emergency indicated below, include instructions and
procedures for each system, subsystem, piece of equipment, and component:
1.
Fire.
2.
Flood.
3.
Gas leak.
4.
Water leak.
5.
Power failure.
6.
Water outage.
7.
System, subsystem, or equipment failure.
8.
Chemical release or spill.
C.
Emergency Instructions: Describe and explain warnings, trouble indications, error messages, and similar
codes and signals. Include responsibilities of Owner's operating personnel for notification of Installer,
supplier, and manufacturer to maintain warranties.
D.
Emergency Procedures: Include the following, as applicable:
1.
Instructions on stopping.
2.
Shutdown instructions for each type of emergency.
3.
Operating instructions for conditions outside normal operating limits.
4.
Required sequences for electric or electronic systems.
5.
Special operating instructions and procedures.
2.04
A.
Operation Manuals
Content: In addition to requirements in this section, include operation data required in individual
specification sections and the following information:
1.
System, subsystem, and equipment descriptions. Use designations for systems and equipment
indicated on Contract Documents.
B.
2.
Performance and design criteria if Contractor has delegated design responsibility.
3.
Operating standards.
4.
Operating procedures.
5.
Operating logs.
6.
Wiring diagrams.
7.
Control diagrams.
8.
Piped system diagrams.
9.
Precautions against improper use.
10.
License requirements including inspection and renewal dates.
Descriptions: Include the following:
1.
Product name and model number. Use designations for products indicated on Contract
Documents.
2.
Manufacturer's name.
3.
Equipment identification with serial number of each component.
4.
Equipment function.
5.
Operating characteristics.
6.
Limiting conditions.
7.
Performance curves.
8.
Engineering data and tests.
9.
Complete nomenclature and number of replacement parts. C. Operating Procedures: Include the
following, as applicable:
10.
Startup procedures.
11.
Equipment or system break-in procedures.
12.
Routine and normal operating instructions.
13.
Regulation and control procedures.
14.
Instructions on stopping.
15.
Normal shutdown instructions.
16.
Seasonal and weekend operating instructions.
17.
Required sequences for electric or electronic systems.
18.
Special operating instructions and procedures.
D.
Systems and Equipment Controls: Describe the sequence of operation, and diagram controls as installed.
E.
Piped Systems: Diagram piping as installed, and identify color-coding where required for identification.
2.05
Product Maintenance Manuals
A.
Content: Organize manual into a separate section for each product, material, and finish. Include source
information, product information, maintenance procedures, repair materials and sources, and warranties
and guarantees, as described below.
B.
Source Information: List each product included in manual, identified by product name and arranged to
match manual's table of contents. For each product, list name, address, and telephone number of Installer
or supplier and maintenance service agent, and cross-reference specification section number and title in
Project Manual and drawing or schedule designation or identifier where applicable.
C.
Product Information: Include the following, as applicable:
D.
1.
Product name and model number.
2.
Manufacturer's name, Subcontractor, Suppliers.
3.
Color, pattern, and texture.
4.
Material and chemical composition.
5.
Reordering information for specially manufactured products.
Maintenance Procedures: Include manufacturer's written recommendations and the following:
1.
Inspection procedures.
2.
Types of cleaning agents to be used and methods of cleaning.
3.
List of cleaning agents and methods of cleaning detrimental to product.
4.
Schedule for routine cleaning and maintenance.
5.
Repair instructions.
E.
Repair Materials and Sources: Include lists of materials and local sources of materials and related services.
F.
Warranties and Guarantees: Include copies of warranties and guarantees and lists of circumstances and
conditions that would affect validity of warranties or guarantees.
1.
2.06
Include procedures to follow and required notifications for warranty claims.
Systems and Equipment Maintenance Manuals
A.
Content: For each system, subsystem, and piece of equipment not part of a system, include source
information, manufacturers' maintenance documentation, maintenance procedures, maintenance and
service schedules, spare parts list and source information, maintenance service contracts, and warranty and
bond information, as described below.
B.
Source Information: List each system, subsystem, and piece of equipment included in manual, identified by
product name and arranged to match manual's table of contents. For each product, list name, address, and
telephone number of Installer or supplier and maintenance service agent, and cross-reference specification
section number and title in Project Manual and drawing or schedule designation or identifier where
applicable.
C.
Manufacturers' Maintenance Documentation: Manufacturers' maintenance documentation including the
following information for each component part or piece of equipment:
1.
Standard maintenance instructions and bulletins.
D.
E.
2.
Drawings, diagrams, and instructions required for maintenance, including disassembly and
component removal, replacement, and assembly.
3.
Identification and nomenclature of parts and components.
4.
List of items recommended to be stocked as spare parts.
Maintenance Procedures: Include the following information and items that detail essential maintenance
procedures:
1.
Test and inspection instructions.
2.
Troubleshooting guide.
3.
Precautions against improper maintenance.
4.
Disassembly; component removal, repair, and replacement; and reassembly instructions.
5.
Aligning, adjusting, and checking instructions.
6.
Demonstration and training video recording, if available.
Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants
for equipment, and separate schedules for preventive and routine maintenance and service with standard
time allotment.
1.
Scheduled Maintenance and Service: Tabulate actions for daily, weekly, monthly, quarterly,
semiannual, and annual frequencies.
2.
Maintenance and Service Record: Include manufacturers' forms for recording maintenance.
F.
Spare Parts List and Source Information: Include lists of replacement and repair parts, with parts identified
and cross-referenced to manufacturers' maintenance documentation and local sources of maintenance
materials and related services.
G.
Maintenance Service Contracts: Include copies of maintenance agreements with name and telephone
number of service agent.
H.
Warranties and Guarantees: Include copies of warranties and guarantees and lists of circumstances and
conditions that would affect validity of warranties or guarantees.
1.
2.07
Include procedures to follow and required notifications for warranty claims.
Posted Electronic Manuals
A. Post files directly to Princeton Collaborative System (PCS) specifically established for Project.
PART 3 - EXECUTION
3.01
Manual Preparation
A.
Operation and Maintenance Documentation Directory: Prepare a separate manual that provides an
organized reference to emergency, operation, and maintenance manuals.
B.
Emergency Manual: Assemble a complete set of emergency information indicating procedures for use by
emergency personnel and by Owner's operating personnel for types of emergencies indicated.
C.
Product Maintenance Manual: Assemble a complete set of maintenance data indicating care and
maintenance of each product, material, and finish incorporated into the Work.
D.
E.
Operation and Maintenance Manuals: Assemble a complete set of operation and maintenance data
indicating operation and maintenance of each system, subsystem, and piece of equipment not part of a
system.
1.
Engage a factory-authorized service representative to assemble and prepare information for each
system, subsystem, and piece of equipment not part of a system.
2.
Prepare a separate manual for each system and subsystem, in the form of an instructional manual
for use by Owner's operating personnel.
Manufacturers' Data: Where manuals contain manufacturers' standard printed data, include only sheets
pertinent to product or component installed. Mark each sheet to identify each product or component
incorporated into the Work. If data include more than one item in a tabular format, identify each item using
appropriate references from the Contract Documents. Identify data applicable to the Work and delete
references to information not applicable.
1.
F.
G.
Prepare supplementary text if manufacturers' standard printed data are not available and where
the information is necessary for proper operation and maintenance of equipment or systems.
Drawings: Prepare drawings supplementing manufacturers' printed data to illustrate the relationship of
component parts of equipment and systems and to illustrate control sequence and flow diagrams.
Coordinate these drawings with information contained in as-built drawings to ensure correct illustration of
completed installation.
1.
Do not use original project record documents as part of operation and maintenance manuals.
2.
Comply with requirements of newly prepared as-built drawings in section 01 78 39 "Project Record
Documents."
Comply with section 01 77 00 "Closeout Procedures" for schedule for submitting operation and
maintenance documentation.
END OF SECTION
SECTION 01 78 36 - WARRANTIES AND GUARANTEES
PART 1 GENERAL
1.01
REQUIREMENTS INCLUDED
A. Preparation and submittal of warranties and guarantees.
B. Schedule of submittals.
1.02
RELATED REQUIREMENTS
A. Instruction to Bidders:
B. Builder’s Performance and Bonds.
C. Section 01 77 00- Contract Closeout Procedures.
D. Individual Technical Specifications Sections: Warranties and Guarantees required for specific products or
work.
1.03
FORM OF SUBMITTALS
A. Bind in commercial quality 8 ½ x 11 inch three-ring side binders, with hardback, cleanable, plastic covers.
B. Label cover of each binder with typed or printed title `WARRANTIES AND GUARANTEES', with Contract
No. and Project Title; name, address and telephone number of Contractor.
C. Table of Contents: Neatly typed, in the sequence of the Table of Contents of the Project Manual, with
each item identified with the number and title of the specification section in which specified and the name
of the product or work item.
D. Separate each warranty or guaranty with index tab sheets keyed to the Table of Contents listing. Provide
full information, using separate typed sheet as necessary. List subcontractor, supplier and manufacturer,
with name, address and telephone number of responsible principal.
E. Include a copy of the applicable warranty/guaranty in O & M manuals.
1.04
WARRANTY PERIOD AND PREPARATION OF SUBMITTALS
A. Obtain warranties and guarantees, executed in duplicate by responsible subcontractors, suppliers, and
manufacturers, within ten (10) days after completion of the applicable item of work. Date of beginning of
time of warranty will be the date of Substantial Completion, or date of Beneficial Occupancy if equipment
is put to use by the Owner at date of Beneficial Occupancy. No warranty shall start prior to equipment
being put into operation. It is not necessary that all warranties shall start at the same time.
B. Equipment warranty period: Manufacturer's standard warranty, minimum one year from above date of
beginning of warranty, except as stated elsewhere.
C. Full service period: Installing contractor shall provide for full service and maintenance for a period of one
year for the equipment/systems, except as stated elsewhere. If, within this period, any equipment proves
defective, it shall be repaired or replaced at no additional cost to the Owner.
(1)
The service and maintenance shall include monthly inspections and adjustments, based on an
Owner approved monthly service schedule.
(2)
Each service and maintenance trip to the project shall be coordinated and reported to UMF’s
Facilities Management office and have a separate written report so an accurate log can be kept on the
operation and problems of the installation.
(3)
Monthly service schedule, showing tasks and service timetable, shall be submitted to UMF’s
Facilities Management office for review and approval prior to substantial completion.
(4)
Coordination with UMF’s Facilities Management office and distribution of monthly
maintenance/service reports to UMF shall be the responsibility of the Contractor.
D. Co-execute submittals when required.
E. Retain warranties and guarantees until time specified for submittal.
1.05
TIME OF SUBMITTALS
A. Make submittals per Section 01 77 00 and General Conditions.
B. For items of work when acceptance is delayed beyond date of Substantial Completion, as stated in
Section 01701, submit within ten (10) days after acceptance, listing the date of acceptance as the
beginning of the warranty or guaranty period.
PART 2
PRODUCTS
Not Used
PART 3
EXECUTION
Not Used
END OF SECTION
SECTION 23 11 27 - LIQUEFIED-PETROLEUM GAS PIPING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Pipes, tubes, and fittings.
2. Piping specialties.
3. Piping and tubing joining materials.
4. Valves.
5. Pressure regulators.
B. All components, where available, shall be designed for both natural gas and LP gas use.
1.3 DEFINITIONS
A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and
duct shafts, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces,
crawlspaces, and tunnels.
B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and
mechanical equipment rooms.
C. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient temperatures
and weather conditions. Examples include rooftop locations.
D. LPG: Liquefied-petroleum gas.
1.4 PERFORMANCE REQUIREMENTS
A. Minimum Operating-Pressure Ratings:
1. For Piping Containing Only Vapor:
a. Piping and Valves: 125 psig unless otherwise indicated.
2. For Piping Containing Liquid:
a. Piping between Shutoff Valves: 350 psig unless otherwise indicated.
b. Piping Other Than Above: 250 psig unless otherwise indicated.
c. Valves and Fittings: 250 psig unless otherwise indicated.
B. LPG System Pressure within Buildings: One pressure range. More than 0.5 psig but not more than 2 psig.
1.5 SUBMITTALS
A. Product Data: For each type of the following:
1. Piping specialties.
2. Valves. Include pressure rating, capacity, settings, and electrical connection data of selected
models.
3. Pressure regulators. Indicate pressure ratings and capacities.
4. Vaporizers.
5. Air mixers.
C. Operation and Maintenance Data: For LPG equipment and accessories to include in emergency,
operation, and maintenance manuals.
UMF CHP LP Gas Tank System
23 11 27 – Page 1
October 10, 2015
1.6 QUALITY ASSURANCE
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified
testing agency, and marked for intended location and application.
B. All valves, components and accessories: Listed and labeled as defined in NFPA 58 and NFPA 54.
1.7 DELIVERY, STORAGE, AND HANDLING
A. Handling Flammable Liquids: Remove and dispose of liquids from existing LPG piping according to
requirements of authorities having jurisdiction.
B. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and
handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture.
C. Store pipes and tubes with protective PE coating to avoid damaging coating and protect from direct
sunlight.
D. Protect stored PE pipes and valves from direct sunlight.
PART 2 - PRODUCTS
2.1 PIPES, TUBES, AND FITTINGS
A. Steel Pipe: ASTM A 53/A 53M, black steel, Schedules 40 and 80, Type E or S, Grade
1. Malleable-Iron Threaded Fittings: ASME B16.3, Class 150, standard pattern.
2. Wrought-Steel Welding Fittings: ASTM A 234/A 234M for butt welding and socket welding.
3. Unions: ASME B16.39, Class 150, malleable iron with brass-to-iron seat, ground joint, and
threaded ends.
4. Forged-Steel Flanges and Flanged Fittings: ASME B16.5, minimum Class 150, including bolts, nuts,
and gaskets of the following material group, end connections, and facings: a. Material Group: 1.1.
b. End Connections: Threaded or butt welding to match pipe.
c. Lapped Face: Not permitted underground.
d. Gasket Materials: ASME B16.20, metallic, flat, asbestos free, aluminum o-rings, and spiralwound metal gaskets.
e. Bolts and Nuts: ASME B18.2.1, carbon steel aboveground, and stainless steel underground.
B. Polyethylene Piping. SDR 11
1. Fittings: Standard plastic to steel per 2.1.A
2. Piping continuous where not accessible.
2.2 Not Used
2.3 JOINING MATERIALS
A. Joint Compound and Tape: Suitable for LPG and Natural Gas service.
B. Brazing Filler Metals: Alloy with melting point greater than 1000 deg F complying with
AWS A5.8/A5.8M.
2.4 MANUAL GAS SHUTOFF VALVES
A. Metallic Valves, NPS 2 and Smaller for Liquid Service: Comply with ASME B16.33 and UL 842.
1. CWP Rating: 250 psig.
2. Threaded Ends: Comply with ASME B1.20.1.
3. Socket ends for brazed joints.
4. Tamperproof Feature: Locking feature for valves indicated in "Underground Manual Gas Shutoff
UMF CHP LP Gas Tank System
23 11 27 – Page 2
October 10, 2015
Valve Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.
5. Listing by CSA or agency acceptable to authorities having jurisdiction for valves 1 inch and smaller.
6. Valves 1-1/4 inch and larger shall be suitable for LPG and Natural Gas service, with "WOG"
indicated on valve body.
B. Two-Piece, Full-Port, Bronze Ball Valves with Bronze Trim: MSS SP-110.
1. Body: Bronze, complying with ASTM B 584.
2. Ball: Chrome-plated bronze.
3. Stem: Bronze; blowout proof.
4. Seats: Reinforced TFE; blowout proof.
5. Packing: Threaded-body packnut design with adjustable-stem packing.
6. Ends: Threaded, flared, or socket as indicated in "Underground Manual Gas Shutoff Valve
Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.
7. CWP Rating: 600 psig.
8. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to authorities
having jurisdiction.
9. Service: Suitable for LPG and Natural Gas service with "WOG" indicated on valve body.
2.5 PRESSURE REGULATORS
A. General Requirements:
1. Single stage and suitable for LPG and future natural gas conversion.
2. Steel jacket and corrosion-resistant components.
3. Elevation compensator.
4. End Connections: Threaded for regulators NPS 2 and smaller; flanged for regulators NPS 2-1/2 and
larger.
B. Service Pressure Regulators: Comply with ANSI Z21.80.
1. Body and Diaphragm Case: Cast iron or die-cast aluminum.
2. Springs: Zinc-plated steel; interchangeable.
3. Diaphragm Plate: Zinc-plated steel.
4. Seat Disc: Nitrile rubber resistant to gas impurities, abrasion, and deformation at the valve port.
5. Orifice: Aluminum; interchangeable.
6. Seal Plug: Ultraviolet-stabilized, mineral-filled nylon.
7. Single-port, self-contained regulator with orifice no larger than required at maximum pressure
inlet and no pressure sensing piping external to the regulator.
8. Pressure regulator shall maintain discharge pressure setting downstream and not exceed 150
percent of design discharge pressure at shutoff.
9. Overpressure Protection Device: Factory mounted on pressure regulator.
10. Atmospheric Vent: Factory- or field-installed, stainless-steel screen in opening if not connected to
vent piping.
11. Maximum Inlet Pressure: 100 psig.
C. Line Pressure Regulators: Comply with ANSI Z21.80.
1. Body and Diaphragm Case: Cast iron or die-cast aluminum.
2. Springs: Zinc-plated steel; interchangeable.
3. Diaphragm Plate: Zinc-plated steel.
4. Seat Disc: Nitrile rubber resistant to gas impurities, abrasion, and deformation at the valve port.
5. Orifice: Aluminum; interchangeable.
6. Seal Plug: Ultraviolet-stabilized, mineral-filled nylon.
7. Single-port, self-contained regulator with orifice no larger than required at maximum pressure
inlet and no pressure sensing piping external to the regulator.
8. Pressure regulator shall maintain discharge pressure setting downstream and not exceed 150
percent of design discharge pressure at shutoff.
UMF CHP LP Gas Tank System
23 11 27 – Page 3
October 10, 2015
9. Overpressure Protection Device: Factory mounted on pressure regulator.
10. Atmospheric Vent: Factory- or field-installed, stainless-steel screen in opening if not connected to
vent piping.
D. Appliance Pressure Regulators: Comply with ANSI Z21.18.
1. Body and Diaphragm Case: Die-cast aluminum.
2. Springs: Zinc-plated steel; interchangeable.
3. Diaphragm Plate: Zinc-plated steel.
4. Seat Disc: Nitrile rubber.
5. Seal Plug: Ultraviolet-stabilized, mineral-filled nylon.
6. Factory-Applied Finish: Minimum three-layer polyester and polyurethane paint finish.
7. Regulator may include vent limiting device, instead of vent connection, if approved by authorities
having jurisdiction and within heating capacity limits of vent limiter.
2.6 GAS SERVICE METERS
A. Not Required
2.7 DIELECTRIC FITTINGS
A. General Requirements: Assembly of copper alloy and ferrous materials with separating nonconductive
insulating material. Include end connections compatible with pipes to be joined.
B. Dielectric Unions:
1. Description:
a. Standard: ASSE 1079.
b. Pressure Rating: 125 psig minimum at 180 deg F.
c. End Connections: Solder-joint copper alloy and threaded ferrous.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine roughing-in for LPG piping system to verify actual locations of piping connections before
equipment installation.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 EARTHWORK
A. Comply with requirements in Division 31 Section "Earth Moving" for excavating, trenching, and
backfilling.
3.3 PREPARATION
A. Close equipment shutoff valves before turning off LPG to premises or piping section.
B. Inspect LPG piping according to NFPA 58 and NFPA 54 the International Fuel Gas Code to determine that
LPG utilization devices are turned off in piping section affected.
C. Comply with NFPA 58 and NFPA 54 the International Fuel Gas Code requirements for prevention of
accidental ignition.
3.4 OUTDOOR PIPING INSTALLATION
A. Comply with NFPA 58 and NFPA 54 the International Fuel Gas Code requirements for installation and
purging of LPG piping.
B. Install fittings for changes in direction and branch connections.
UMF CHP LP Gas Tank System
23 11 27 – Page 4
October 10, 2015
C. Joints for connection to inlets and outlets on regulators and valves may be flanged or threaded to match
the equipment.
3.5 INDOOR PIPING INSTALLATION
A. Comply with NFPA 54 the International Fuel Gas Code for installation and purging of LPG piping.
B. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems.
Indicated locations and arrangements were used to size pipe and calculate friction loss, expansion, and
other design considerations.
C. Arrange for pipe spaces, chases, slots, sleeves, and openings in building structure during progress of
construction, to allow for mechanical installations.
D. Install piping in concealed locations unless otherwise indicated and except in equipment rooms and
service areas.
E. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or
parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise.
F. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.
G. Locate valves for easy access.
H. Install LPG piping at uniform grade of 2 percent down toward drip and sediment traps.
I. Install piping free of sags and bends.
J. Install fittings for changes in direction and branch connections.
K. Verify final equipment locations for roughing-in.
L. Comply with requirements in Sections specifying gas-fired appliances and equipment for roughing-in
requirements.
M. Drips and Sediment Traps: Install drips at points where condensate may collect, including service-meter
outlets. Locate where readily accessible to permit cleaning and emptying. Do not install where condensate
is subject to freezing.
1. Construct drips and sediment traps using tee fitting with bottom outlet plugged or capped. Use
nipple a minimum length of 3 pipe diameters, but not less than 3 inches long and same size as
connected pipe. Install with space below bottom of drip to remove plug or cap.
N. Extend relief vent connections for service regulators, line regulators, and overpressure protection
devices to outdoors and terminate with weatherproof vent cap.
O. Conceal pipe installations in walls, pipe spaces, utility spaces, above ceilings, below grade or floors, and
in floor channels unless indicated to be exposed to view.
P. Concealed Location Installations:
1. Above Accessible Ceilings: LPG piping, fittings, valves, and regulators may be installed in accessible
spaces without containment conduit.
2. In Walls or Partitions: Protect tubing installed inside partitions or hollow walls from physical
damage using steel striker barriers at rigid supports.
a. Exception: Tubing passing through partitions or walls does not require striker barriers.
UMF CHP LP Gas Tank System
23 11 27 – Page 5
October 10, 2015
3. Prohibited Locations:
a. Do not install LPG piping in or through circulating air ducts, clothes or trash chutes,
chimneys or gas vents (flues), ventilating ducts, or dumbwaiter or elevator shafts.
b. Do not install LPG piping in solid walls or partitions.
Q. Use eccentric reducer fittings to make reductions in pipe sizes. Install fittings with level side down.
R. Connect branch piping from top or side of horizontal piping.
S. Install unions in pipes NPS 2 and smaller, adjacent to each valve, at final connection to each piece of
equipment. Unions are not required at flanged connections.
T. Do not use LPG piping as grounding electrode.
U. Install sleeves for piping penetrations of walls, ceilings, and floors. Comply with requirements for sleeves
specified in Division 23 Section "Sleeves and Sleeve Seals for HVAC Piping."
V. Install sleeve seals for piping penetrations of concrete walls and slabs. Comply with requirements for
sleeve seals specified in Division 23 Section "Sleeves and Sleeve Seals for HVAC Piping."
W. Install escutcheons for piping penetrations of walls, ceilings, and floors. Comply with requirements for
escutcheons specified in Division 23 Section "Escutcheons for HVAC Piping."
3.6 VALVE INSTALLATION
A. Install manual gas shutoff valve for each gas appliance ahead of copper connector.
B. Install regulators and overpressure protection devices with maintenance access space adequate for
servicing and testing.
3.7 PIPING JOINT CONSTRUCTION
A. Ream ends of pipes and tubes and remove burrs.
B. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.
C. Threaded Joints:
1. Thread pipe with tapered pipe threads complying with ASME B1.20.1.
2. Cut threads full and clean using sharp dies.
3. Ream threaded pipe ends to remove burrs and restore full ID of pipe.
4. Apply appropriate tape or thread compound to external pipe threads unless dryseal threading is
specified.
5. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do
not use pipe sections that have cracked or open welds.
D. Flared Joints: Cut tubing with roll cutting tool. Flare tube end with tool to result in flare dimensions
complying with SAE J513. Tighten finger tight, then use wrench. Do not over tighten.
3.8 HANGER AND SUPPORT INSTALLATION
A. Comply with requirements for pipe hangers and supports specified in Division 23 Section "Hangers and
Supports for HVAC Piping and Equipment."
B. Install hangers for horizontal steel piping with the following maximum spacing and minimum rod sizes:
1. NPS 1 and Smaller: Maximum span, 96 inches; minimum rod size, 3/8 inch.
2. NPS 1-1/4: Maximum span, 108 inches; minimum rod size, 3/8 inch.
UMF CHP LP Gas Tank System
23 11 27 – Page 6
October 10, 2015
3. NPS 1-1/2 and NPS 2: Maximum span, 108 inches; minimum rod size, 3/8 inch.
3.9 CONNECTIONS
A. Install LPG piping electrically continuous, and bonded to gas appliance equipment grounding conductor
of the circuit powering the appliance according to NFPA 70.
B. Install piping adjacent to appliances to allow service and maintenance of appliances.
C. Connect piping to appliances using manual gas shutoff valves and unions. Install valve within 72 inches of
each gas-fired appliances and equipment. Install union between valve and appliances or equipment.
D. Sediment Traps: Install tee fitting with capped nipple in bottom to form drip, as close as practical to inlet
of each appliance.
3.10 LABELING AND IDENTIFYING
A. Label all exposed piping: “LP Gas”
B. Install burial tap on top of all underground piping.
3.11 PAINTING
A. Paint exposed, exterior metal piping, valves, service regulators, and piping specialties, except
components with factory-applied paint or protective coating.
1. Alkyd System: MPI EXT 5.1D.
a. Prime Coat: Alkyd anticorrosive metal primer.
b. Intermediate Coat: Exterior alkyd enamel matching topcoat.
c. Topcoat: Exterior alkyd enamel (semigloss).
d. Color: Yellow.
C. Damage and Touchup: Repair marred and damaged factory-applied finishes with materials and by
procedures to match original factory finish.
3.12 FIELD QUALITY CONTROL
A. Tests and Inspections:
1. Test, inspect, and purge LPG according to NFPA 58 and NFPA 54 the International Fuel Gas Code
and requirements of authorities having jurisdiction.
B. LPG piping will be considered defective if it does not pass tests and inspections.
3.13 OUTDOOR PIPING SCHEDULE
A. Aboveground LPG piping shall be the following:
1. NPS 2 and Smaller: Schedule 40 steel pipe, malleable-iron threaded fittings and threaded joints.
Coat pipe and fittings with protective coating for steel piping.
2. NPS 2-1/2 and Larger: Schedule 40, steel pipe with wrought-steel fittings and welded joints, or
mechanical couplings. Coat pipe and fittings with protective coating for steel piping.
3.14 INDOOR PIPING SCHEDULE FOR SYSTEM PRESSURES MORE THAN 0.5 PSIG AND LESS THAN 5 PSIG
A. Aboveground, branch piping NPS 1 and smaller shall be one of the following:
1. Annealed-temper copper tube, Type L with wrought-copper fittings and flared joints.
2. Schedule 40, steel pipe with malleable-iron fittings and threaded joints.
B. Aboveground, distribution piping shall be the following:
1. Schedule 40, steel pipe with malleable-iron fittings and threaded joints.
3.15 ABOVEGROUND MANUAL GAS SHUTOFF VALVE SCHEDULE
UMF CHP LP Gas Tank System
23 11 27 – Page 7
October 10, 2015
A. Aboveground Liquid Piping:
1. Two-piece, full-port, bronze ball valves with bronze trim.
END OF SECTION 23 11 27
UMF CHP LP Gas Tank System
23 11 27 – Page 8
October 10, 2015
SECTION 23 13 00 – Above Ground Liquefied Petroleum Fuel Storage Tanks
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
Division 01 Specification Sections, apply to this Section.
B. American Petroleum Institute:
1. API 12P - Fiberglass Reinforced Plastic Tanks.
2. API 650 - Welded Steel Tanks for Oil Storage.
3. API 1615 - Installation of Underground Petroleum Storage Systems.
4. API 1632 - Cathodic Protection of Underground Petroleum Storage Tanks and Piping Systems.
5. API 2000 - Venting Atmospheric and Low-Pressure Storage Tanks: Nonrefrigerated and
Refrigerated.
C. NACE International:
1. NACE RP-02-85 - Corrosion Control of Underground Storage Tank Systems by Cathodic Protection.
D. National Electrical Manufacturers Association:
1. NEMA 250 - Enclosures for Electrical Equipment (1000 Volts Maximum).
E. National Fire Protection Association:
1. NFPA 30 - Flammable and Combustible Liquids Code.
2. NFPA 31 - Standard for the Installation of Oil-Burning Equipment.
F. Petroleum Equipment Institute:
1. PEI 100 - Recommended Practices for Installation of Underground Liquid Storage Systems.
G. Steel Tank Institute:
1. STI ACT-100 - Specification for External Corrosion Protection of FRP Composite Steel
Underground Storage Tanks.
F. Underwriters Laboratories Inc.:
1. UL 58 - Steel Underground Tanks for Flammable and Combustible Liquids.
2. UL 142 - Steel Aboveground Tanks for Flammable and Combustible Liquids.
3. UL 567 - Pipe Connectors for Flammable Liquids and Combustible Liquids and LP-Gas.
4. UL 913 - Intrinsically Safe Apparatus and Associated Apparatus for Use in Class I, II, and III,
Division 1, Hazardous Locations.
5. UL 1316 - Glass Fiber Reinforced Plastic Underground Storage Tanks for Petroleum Products,
Alcohols, and Alcohol-Gasoline Mixtures.
6. UL 2085 - Standard for Safety for Insulated Aboveground Tanks Flammable and Combustible
Liquids.
1.2 SUMMARY
A. Section Includes:
1. Aboveground fuel storage tanks.
2. Aboveground steel secondary containment dike tank.
3. Leak detection and location system.
B. Related Sections:
1. Section 03 30 00 - Cast-In-Place Concrete: Product requirements for concrete pad by this section.
UMF CHP LP Tank System
23 13 00 – Page 1
October 10, 2015
2.
3.
4.
Section 05 50 00 - Metal Fabrications: Product and execution requirements for bollards for
placement by this section.
Section 26 05 26 - Grounding and Bonding for Electrical Systems: Product and execution
requirements for grounding for placement by this section.
Section 31 21 00 - Excavation: Product and execution requirements for excavation and backfill
required by this section.
1.3 PERFORMANCE REQUIREMENTS
A. Provide aboveground pad-mounted tank of single wall of welded steel construction.
1. Provide tank with tank gage.
2. Each Tank Capacity:
a. Volume: 18,000 gallons
b. Diameter: 132” +/c. Overall Length: 41’ +/1.4 SUBMITTALS
A.
Shop Drawings:
1. Tanks: Indicate for fuel oil tanks dimensions; number, size, and location of openings; number,
size, and location of manholes; number and location of hold down straps, and accessories.
Indicate dimensions, reinforcing steel size, and reinforcing steel location of concrete pad.
B.
Product Data:
1. Tanks: Submit manufacturer’s catalog information including capacity.
2. Leak Detection and Location System: Submit manufacturer’s catalog information for controller,
alarm unit, cable type, and any other required appurtenances.
C.
Test Reports: Submit written test results for tank pressure test.
D.
Manufacturer's Installation Instructions: Submit tanks, and leak detection and location system data.
E.
Manufacturer's Certificate:
1. Certify tank meets or exceeds Industry requirements from applicable entities listed in Section 1.1
2. Submit certificate of evaluation of leak detection and location system by independent third
party.
F.
Manufacturer's Field Reports: Not Required.
1.5 CLOSEOUT SUBMITTALS
A.
Project Record Documents: Record actual locations of manholes, tanks, and leak detection and
location system.
B.
Identify and describe unexpected variations to subsoil conditions or discovery of uncharted utilities.
C.
Operation and Maintenance Data: Submit spare parts lists.
1.6 QUALITY ASSURANCE
A.
Perform Work in accordance with NFPA 30 and NFPA 31.
UMF CHP LP Tank System
23 13 00 – Page 2
October 10, 2015
B.
Perform Work in accordance with State of Maine Propane and Natural Gas Installation as required by
the Department of Professional and Financial Regulation.
C.
Evaluate leak detection and location system by independent third party according to Third Party
Procedures developed according to US EPS's "Standard Test Procedure for Evaluating Leak Detection
Methods: Liquid-Phase Out-of-Tank Product Detectors." Evaluation results to verify system
manufacturer's claim regarding sensitivity, range and other performance data.
D.
Maintain one copy of each document on site.
1.7 QUALIFICATIONS
A.
Manufacturer: Company specializing in manufacturing products specified in this section with minimum
three years experience.
B.
Above Ground Fuel Storage Tanks: Company specializing in manufacturing products specified in this
section with minimum three years experience.
C.
Leak Detection Systems: Company specializing in manufacturing products specified in this section with
minimum three years experience.
D.
Installer: Company specializing in performing Work of this section with minimum FIVE years
experience and approved by manufacturer.
1.8 Not used
1.9 DELIVERY, STORAGE, AND HANDLING
A.
Per manufacturer’s requirements.
1.10 ENVIRONMENTAL REQUIREMENTS
A.
Do not install tank foundations when bedding is wet or frozen.
1.11 FIELD MEASUREMENTS
A.
Verify field measurements prior to fabrication.
1.12 COORDINATION
A.
Coordinate installation of tank with plumbing and electrical trades.
1.13 WARRANTY
A.
Furnish five year manufacturer warranty for tanks.
B.
Furnish five year manufacturer warranty for leak detection and location system.
UMF CHP LP Tank System
23 13 00 – Page 3
October 10, 2015
PART 2 - PRODUCTS
2.1 ABOVE GROUND FUEL STORAGE TANKS
A.
Manufacturers:
1. Highland Tank
2. Clawson Tank
3. Lannon Tank Corporation
4. Approved Equal
B.
Furnish materials in accordance with the State of Maine rules and regulations applicable to aboveground LP gas tanks.
C.
Tank Configuration: Cylindrical.
D.
Primary Tank: Single wall steel tank constructed in accordance with UL 142 not less than 3/16 inch (5
mm) thick.
E.
Finish: Factory painted with industrial epoxy and urethane coating with dry film thickness of 4 mils (0.1
mm). Color: white.
F.
Normal Vent: Furnish each compartment of primary tank with 2 inch (50 mm) updraft venting device
exhausting upward at elevation of at least 12 feet (3.7 m) aboveground. Size vent in accordance with
NFPA 30.
G.
Emergency Vent: Furnish each compartment of primary tank with emergency vent sized in accordance
with NFPA 30. Do not use access openings for emergency venting purposes.
H.
Monitor Port: Minimum 2 inch (50 mm) steel pipe with locking cap to be used for detecting leaks
between primary and outer tanks.
I.
Accessories:
1. Level Gage: Mechanical float activated level gage capable of indicating approximate fluid level in
tank reading in feet and inches.
2. Tank Decals: Furnish warning and tank identification signs located prominently on tank following
local code requirements.
J.
Capacity:
1. Volume: 18,000 gallons.
2. Diameter: 132” +/3. Overall Length: 41’ +/4. Tank Fittings:
a. Fill: Coordinate with Purchaser LP Gas Supplier
b. Vent: Minimum size required by code, galvanized, including "T" and elbow assembly with
1/4 inch (6 mm) square mesh screen over inlet.
c. Suction: minimum size required by code, anti-siphon connection to tank bottom with foot
valve.
d. Return: Minimum size required by code
e. Gage fitting Minimum size required by code
5. Manway: 22 inch (550 mm) diameter, with cover and gasket, and extension sleeve; located at
top of tank.
UMF CHP LP Tank System
23 13 00 – Page 4
October 10, 2015
2.2 LEAK DETECTION AND LOCATION SYSTEM
A.
Manufacturers:
1. Highland Tank
2. Clawson Tank
3. Lannon Tank Corporation
4. Approved Equal
B.
Furnish materials in accordance with the State of Maine rules and regulations applicable to aboveground LP gas tanks.
C.
Product Description: Microprocessor based monitoring unit, sensor cable, probes, system layout map,
and auxiliary equipment to provide continuous monitoring of sensing strings for leaks, shorts, breaks,
and probe activation. When any of these conditions occur at any point along cable, alarm sounds, type
of condition is identified and location displayed. System monitors interstitial space of double
contained tanks. Construct system to meet requirements of UL 913.
D.
Performance:
1. Detect and identify location of first leak within 0.2 percent of sensor string length or 5 feet (1500
mm), whichever is greater. Identify type of alarm.
2. Sensing String Length: Monitor up to 500 feet of cable for each sensor string from single
monitoring unit.
3. Multiple Leaks: Detect and locate multiple leaks or additional liquid on sensor cable.
4. Breaks and Shorts: Identify location of breaks and shorts on cable. When faults occur, sound
alarm, and display on front of monitoring unit type of fault and location of fault.
5. Liquids Detected: Only hydrocarbons are to be detected.
6. Remote Annunciation: Furnish relays for remote indication of alarm conditions. Relays indicate
no alarm conditions exist, alarm condition exists but has not yet been acknowledged, and alarm
condition exists and has been acknowledged. Communications available via RS-232 and ASCII
communication protocols to allow central point monitoring and control via remote computer.
7. Archives: Record significant events in nonvolatile memory with capacity of 900 events. When
memory becomes full, recorded events are deleted from memory on first-in-first-out basis. Each
recorded event includes time and date event occurred. Archives retrievable through RS-232 and
ASCII communication protocols.
8. System Status: Continuously give positive indication of monitoring sensing string and status of
sensing string. System clock indicates time and date on LCD of monitoring panel. System clock is
programmable. Include time and date indication for events recorded in memory.
9. Security: Assignable password security for varying levels of system access. Minimum of 20
passwords available within system. System to not allow unauthorized modifications to sensing
string to be made without causing alarm condition.
10. Sensor Types: Capable of monitoring sensor cables, probe sensors, and switch sensors such as
float switches, and pressure switches, from same monitoring panel. English language displays
indicate status of sensors.
11. Sensitivity: System to not detect incidental liquid contact. Sensitivity field adjustable to increase
or decrease amount of wetted cable needed to cause alarm.
E.
Components:
1. Monitoring Unit:
a. Indicates when liquid comes in contact with sensor cable by sounding alarm, actuating
output relays, displaying message leak has been detected and giving location of leak on
sensing string.
b. Unit furnished with green LED on panel front indicates unit is powered. Furnish two line by
forty character backlit LCD visible from front of unit to provide system data. Red LED on
UMF CHP LP Tank System
23 13 00 – Page 5
October 10, 2015
2.
panel front indicates alarm condition has occurred. Unit power requirements: 120/240 VAC,
100 VA, 50/60 Hz, single phase. Equip with RS-232 communication port and minimum of
one common and one SPDT output relay for each cable, rated for 250 VAC, 10 amp.
c. Enclose in modified NEMA 250 Type 4X enclosure. UL listed to provide connections for
intrinsically safe sensor circuits for use in hazardous locations. Ability to locate leak does
not depend on battery backed up functions. In event of power failure, store system
conditions and parameters in nonvolatile memory allowing unit to automatically resume
monitoring, without resetting, upon restoration of power. Furnish on-off switch in panel.
Sensor Cable: Coaxial construction consisting of insulated copper center conductor, spacer
material, and outer braid. Center conductors not less than 20 AWG for mechanical strength.
Cables field repairable.
PART 3 - EXECUTION
3.1 EXAMINATION
A.
Verify excavations are to required grade, dry, and not over-excavated.
B.
Verify concrete pad is ready for tanks installation.
3.2 INSTALLATION - ABOVEGROUND TANKS
A.
Install aboveground tanks in accordance with API 1615, PEI 100, NFPA 30, and NFPA 31.
B.
Check factory installed equipment and accessories for loosening during transit.
C.
Clean and flush tanks prior to delivery to site. Seal until pipe connections are made.
D.
Install aboveground tanks on concrete foundation. Secure with manufacturer-supplied anchoring
devices.
E.
Backfill tank foundation in accordance with manufacturer’s instructions.
F.
Install aboveground tank supports in accordance with applicable codes and manufacturer’s
instructions.
G.
Install grounding for aboveground tanks in accordance with applicable codes and manufacturer’s
instructions.
H.
Install piping connections to tanks. Provide venting in accordance with API 2000.
I.
Tank Accessories:
1. Install tank accessories shipped loose with tank.
2. Install the following tank accessories: anti-siphon devices, overfill shutoff and alarms, vents,
gages, emergency vents and other required appurtenances.
J.
Adjust liquid level gages before initial start-up and after filling of tank.
K.
Install aboveground tanks in accordance with applicable code.
UMF CHP LP Tank System
23 13 00 – Page 6
October 10, 2015
3.3 INSTALLATION - LEAK DETECTION AND LOCATION SYSTEM
A.
Install cable on flat surfaces with hold down clips every 8 feet (2400 mm) and cable tags every 50 feet
(15 m).
B.
Graphic Locator Map: Provide location map with system reflecting actual installation showing system
configuration and sensing string layout. Furnish length along cable as references to locate leaks. Base
footage on calibration points.
C.
Calibration Points: Record calibration points along sensing string in accordance with manufacturer's
procedures. Provide sensor cables with cable tags every 50 feet (15 m).
D.
Direct Buried of Hydrocarbon Sensing Cable:
1. Replace cable damaged during installation.
2. Seal cable ends to prevent moisture ingress.
3. Install cable so connectors are accessible in junction boxes at grade or in manholes, valve pits or
other locations.
4. Install cable from underground to grade using PVC pipe.
5. Install on prepared bedding.
6. Backfill cable with 6 inches of sand placed on top of cable and compacted prior to pipe
installation.
7. Where cable is to be covered by concrete or other structures, install sensor cable in slotted PVC
pipe. Install with access points space 4 feet apart to allow replacing and servicing.
8. Install Work in accordance with State of Maine rules and regulations.
3.4 FIELD QUALITY CONTROL
A.
Field inspecting, testing, adjusting, and balancing as recommended by manufacturer.
B.
Pressure test aboveground tanks in accordance with the following:
1. Pressure test tank as required by code.
2. Repair leaks.
3. Retest until no leaks are detected.
C.
Field Testing Leak Detection System:
1. Perform tests to demonstrate ability of system to detect and locate breaks, shorts and probes on
sensor string.
2. Perform leak testing in accordance with the following procedure to verify operation and ability to
work with condensation pools or other static moisture:
a. Wet sensor cable near start of sensor string and acknowledge detection or location alarm
and recheck system.
b. Wet sensor cable near end of sensor string with first location still wetted and acknowledge
detection or location alarm and recheck system.
c. Wet sensor cable in three additional locations between first and second leak locations with
each detection or location alarm being acknowledged and prior leak locations still wetted.
3. Prepare and submit report verifying each leak location and detection accuracy. Furnish history
print out of test results from panel. [Submit TDR traces for each test run to allow verification of
wet locations.]
END OF SECTION 23 13 00
UMF CHP LP Tank System
23 13 00 – Page 7
October 10, 2015
SECTION 23 18 10 – LP GAS ELECTRIC GAS VAPORIZER
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
Division 01 Specification Sections, apply to this Section.
B.
The vaporizer shall comply with Class I, Division 1, Group D requirements as specified by NFPA
Pamphlets #58 and #70 and Zone 1 Hazardous Locations in Europe.
C.
Marking and installation information:
1. NFPA Pamphlet 70 requirements for Class I Division 1 Group D
2. NFPA Pamphlet 58 requirements for Electric Vaporizers
3. May be installed per indirect fired vaporizers limitations
4. FM, FMc, NEMKO, PED and CE approved
5. EEx d IIB T3
6. NEMKO 04 ATEX 1026X
1.2 SUMMARY
A. Section Includes:
1. Pipes, tubes, and fittings.
2. Piping specialties.
3. Piping and tubing joining materials.
4. Valves.
5. Pressure regulators.
B.
Related Sections:
1. Section 23 11 27 “LP Gas Piping”
PART 2 – PRODUCTS
2.1 VAPORIZER COMPONENTS
A.
B.
Pressure Vessel
1.
Encloses a cast aluminum core which shall be the heat transfer medium. The unit shall be
electrically heated by independent "cast-in" resistance heater elements. The operating
temperature controller will utilize a low voltage control system and an analog sensing device.
The vaporizer will require a maximum of .25 KW of electrical power to vaporize 1 Gallon of
propane.
2.
Each electric vaporizer shall consist of a vertical tubular pressure vessel through which propane
flows. The pressure vessel shall be fabricated in accordance with the ASME code for pressure
vessels for an internal working pressure of 250 PSIG. The pressure vessel shall be equipped with
a relief valve to prevent unsafe internal pressure. The relief valve shall be sized in accordance
with NFPA Pamphlet #58. The pressure vessel shall be covered with an insulating jacket to
minimize radiant heat loss.
Explosion proof control box
UMF CHP LP Gas Tank System
23 18 10 – Page 1
October 10, 2015
1.
The vaporizer is capable of accepting an optional energy (Economy) conservation system that
automatically closes the outlet of the vaporizer when natural storage tank vaporization rates are
sufficient to maintain the demand. The optional energy (Economy) conservation system also
automatically opens the outlet of the vaporizer and begins vaporizing liquid propane when the
natural storage tank vaporization rate becomes insufficient to meet the demand.
PART 3 – EXECUTION
3.1 VAPORIZER INSTALLATION
A. The contractor shall furnish and install TORREXX Electric Vaporizer(s) as manufactured by Algas-SDI
International, LLC (ASDI), or approved equal
B.
Vaporizer to be listed in the Factory Mutual Systems (FM) approval guide.
C.
The vaporizer shall be equipped with two independent direct monitoring high temperature safety
shutdown devices, and a float activated high liquid level safety manual reset valve to prevent passage
of liquid propane downstream. In the event of:
1.
High temperature shutdown - power to the heating elements shall shut down and the inlet
solenoid valve shall close. The former shall prevent the core from overheating whereas the latter
shall prevent the liquid propane from coming inside the pressure vessel. Remaining heat energy
supplied by the vaporizer shall cause the remainder of the liquid propane in the pressure vessel to
get vaporized and consumed by downstream equipment. After the occurrence and correction of a
safety shutdown manual reset button on the control board shall be reset and the vaporization
process shall resume.
1.
Liquid carryover shutdown - liquid inside the pressure vessel will rise causing the manual reset
valve to close. The manual reset valve shall provide a pressure tight seal at the outlet of the
vaporizer preventing the escape of liquid. Heat energy supplied by the vaporizer shall cause the
remaining liquid in the pressure vessel to be pushed back to the storage tank. After the occurrence
and correction of a safety shutdown situation manual reset valve can be reset and the vaporization
process shall resume.
2.
Power interruption - power to the heating elements shall shut down and the inlet solenoid valve
shall close preventing liquid from entering the pressure vessel. Residual heat energy supplied by
the vaporizer shall cause the remaining liquid propane in the pressure vessel to vaporize and
consumed downstream equipment. Once the power is restored, vaporizer shall heat up and inlet
solenoid valve shall open to allow further liquid to be vaporized thus restoring propane supply to
downstream equipment.
D.
Provide vaporizer with an explosion proof control box. Mount in location to be determined by
Owner.
E.
Provide bollards in front of Vaporizer as required.
END OF SECTION 23 18 10
UMF CHP LP Gas Tank System
23 18 10 – Page 2
October 10, 2015
LP GAS TANK
SYSTEM RFP
- FOR
COORDINATIO
N PURPOSES
ONLY
SCOPE DELINEATION POINT
LP GAS TANK
SYSTEM RFP FOR
COORDINATION
PURPOSES
ONLY
COUPLING BY LP
TANK SUPPLIER
LP TANK
SUPPLIER
CHP
CONTRACTOR