MPC Art Addendum 1 R..

Transcription

MPC Art Addendum 1 R..
ADDENDUM #1 to DRAWINGS & PROJECT MANUAL SPECIFICATIONS
For
MPC – Art Department Modernization, Building #1 & #30 Modifications
980 Fremont Street, Monterey, California
May 7, 2013
The Contract Documents for the above listed project are hereby amended, and the following modifications
shall be made a part of said documents and shall be subject to all applicable requirements as if originally
shown or specified. Bidders shall acknowledge receipt of this Addendum on the Bid Form.
PRE-BID REQUESTS for INFORMATION:
PB001
SUBJECT:
Detail 8/A9.4 calls out 2” diameter holes with screen. The (E) trough is to
remain with only the gutter replaced. Are these (E) holes? If not, how do we
install the screens?
RESPONSE: All roof fascias and frieze boards are to be replaced (see revised demolition
plans, attached); therefore ventilation holes will be new.
PB002
SUBJECT:
The specifications in 004513 Statement of Qualifications Form on section 5
question 5.9 states that if the bidders workers compensation insurance EMR is
more than 1.25 the bidder is not qualified to bid this project.
Our construction firm’s loss experience during the past 4 years would result in
an EMR of .99. California law requires that our firm’s loss experience be
calculated with the loss experience of every firm owned by our principal,
which includes other businesses unrelated to the construction industry. This
means of calculation results in an EMR higher than 1.25 due to greater loss
experiences in our principal’s other non-construction businesses. Please
confirm that our firm is permitted to bid this project because our loss
experience when calculated in the same manner as any other stand alone
construction firm would be much less than the Owner’s threshold of 1.25.
RESPONSE: Please see revised sections 002113 and 004513 attached. Section 002113
article 12.6.5 the last item has been stricken from the paragraph. Section
004513 article 5.9 and 5.10 have been removed in their entirety.
PB003
SUBJECT:
Sheet E4.1, Note 26: “Provide and install Siemens EMS panel below lighting
relay panel. . . .” Question: If we are to provide Siemens panel, please provide
model number, etc. for this piece of equipment.
RESPONSE: The Siemens Panel will be provided by Siemens Contractor. Please note
location shall be below lighting control Panel.
PB004
SUBJECT:
Door 112B – Group 23: 3’6” x 6’-8”.
Group 23 is written as a pair of doors. Please clarify spec for hardware group.
Please specify change.
RESPONSE: Hardware group 23 has been updated in revised Section 087100, attached.
PB005
SUBJECT:
Where is the actual IDF location? Where is the 12 strand multi-mode fiber
going?
RESPONSE: The existing IDF locations are shown on Sheet E3.1.
The fiber and copper cables are going to be spliced and extended to new IDF
for Building #1. The fiber and copper cables for relocated IDF to Building #30
will be preserved and reconnected to IDF which is to be relocated about 10 feet
from existing location.
PB006
SUBJECT:
Section 007313 Special Conditions, Item #14 – Please clarify if aircraft
liability insurance is required. Please clarify if pollution liability insurance is
required with the limits indicated.
Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1
1
PB007
PB008
PB009
PB0010
PB0011
PB0012
PB0013
PB0014
PB0015
PB0016
PB0017
PB0018
PB0019
RESPONSE: Aircraft liability insurance is required if aircraft is used for lifting items on the
construction site; otherwise it is not required. Pollution liability insurance is
required with the limits indicated.
SUBJECT:
Please confirm that all hazardous abatement work will be performed by a
separate contract and is not in this project’s scope.
RESPONSE: All hazardous abatement will be done under separate contract through the
owner.
SUBJECT:
There are no window heights noted or shown at Building 30 windows W3,
W4, W5, W6 and W7. We will need low and high point of frame to verify a 2”
x 4 ½” system will meet the structural requirements. If they are over 13’ tall
they might need to be curtain wall.
RESPONSE: Windows are just under 13’ overall at the peak.
SUBJECT:
Are the structural mullions the wood post shown on 6/A9.2?
RESPONSE: Yes.
SUBJECT:
Please verify whether the type of storefront finish is paint or anodizing. The
documents note factory finish with a Permadized finish, which is anodizing,
and also notes Fluoropolymer, which is paint. See part 2.10 paragraph B of
Section 084113.
RESPONSE: Permadize is a coating. It is not anodizing.
SUBJECT:
Please clarify if any of the storefront systems are to be deferred approval.
RESPONSE: DSA did not require deferred approval at back check. No window exceeds 10’
in both directions.
SUBJECT:
The bid form indicates there are two alternates whereas Section 012300
indicates there are none. Please confirm what if any alternates are required.
RESPONSE: There are no alternates. Please see revised page 5 of attached Section 004213.
SUBJECT:
If there will be any permits that are the responsibility of the contractor, please
identify what permits, the agency, and the point of contact so that cost can be
obtained.
RESPONSE: There are no permits the contractor will be responsible for.
SUBJECT:
Section 015100 requires the contractor to pay for water usage. Please provide
the water rate that the contractor will be charged.
RESPONSE: The district will not be charging for the water usage.
SUBJECT:
Will the NIC art lockers between the two buildings be open to students during
construction?
RESPONSE: No, only the one furthest east will be used during the project; this locker
structure is to be left outside the fenced area.
SUBJECT:
Please confirm if this project has phases of construction.
RESPONSE: There will not be phases to the construction portion of this project;
construction start and completion dates are for both buildings. There is a
scheduled time frame for the site work north of Building 1, as noted in revised
Section 011000, Summary of Work, attached.
SUBJECT:
Will abatement be done for both buildings at the same time?
RESPONSE: Both buildings will start abatement and complete 99% before construction
starts, due to coordination of scopes. It is expected the abatement contractor
will be required to return for some small items during the construction period.
SUBJECT:
In janitor’s closet (Building 30) door 115 is called out but there is another door
or a partition style in the room. Please advise.
RESPONSE: The partition and door shall be sheet metal and shall be sealed with gasket
tape.
SUBJECT:
Please confirm there is no scope for the footings at the modified (E) wood
fence.
Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1
2
PB0020
PB0021
PB0022
PB0023
PB0024
PB0025
PB0026
PB0027
PB0028
RESPONSE: Confirmed.
SUBJECT:
Demo sheet A2.1 calls out (N) gutter and downspouts. Please advise if this is
to be copper.
RESPONSE: Gutter and downspouts to match standing seam metal roof panels.
SUBJECT:
Please advise if the tackable panels require backing/blocking.
RESPONSE: No.
SUBJECT:
Please advise if the (N) galvanized handrails are to be painted.
RESPONSE: No.
SUBJECT:
Sheet A2.2 shows hatch marks along the building with no definition. Please
advise.
RESPONSE: See note which designates clips @ 12” OC at “cross hatched areas.”
SUBJECT:
Civil drawings state “BLDG 21” at title (above C2G). Please advise scope at
BLDG 21.
RESPONSE: No scope for Building 21.
SUBJECT:
Sheet S2.3. Please identify object in the corner of Rm 113.
RESPONSE: Loose furniture – disregard.
SUBJECT:
Contractor assumes that any shear wall noted (E) is existing with no scope.
Please confirm.
RESPONSE: Confirmed.
SUBJECT:
Sheet S8.3, detail 11 shows a bracket but no specification is called out. Please
advise.
RESPONSE: Detail 11/S8.3 calls for the steel bracket to be plate 3/16” with 5 each wood
screws.
SUBJECT:
Is Ethernet provided in each of the two buildings?
RESPONSE: Cabling is to be provided and installed by systems contractor. CAT 6 cable.
See Structured Cabling spec section.
ADDITIONAL ITEMS:
DRAWINGS:
ITEM 1
Sheets A2.1, A5.1, A9.4: Use mesh grate shown in Detail 13A/A9.4 for all trenches. Change
solid trench cover in Glaze Mixing 110 to mesh grate.
ITEM 2
Sheets A6.1, A6.4, E4.1: Add motorized roller shades at high windows in Drawing Lab 101
and Painting 113 as shown on attached drawings ASK1.1 and ASK 1.3. Divide lower
manually operated roller shades into segments as shown on attached drawings ASK1.2 and
ASK1.3.
ITEM 3
Sheet A2.3: Add base cabinet and mail sort unit in Division Office 100. See attached drawing
ASK1.4.
ITEM 4
Sheets A2.3, A7.1: Change width of door 103B to 4’-0”. Locate hinge side of door at (E)
hinge side jamb.
ITEM 5
Sheets A2.4, E5.1: Add ceiling track lighting in Building 1 Conference Room 107 as shown
on ASK1.5 and ESK1.6.
ITEM 6
Sheet A6.3: See ASK1.6 for elevation of island cabinet in Storage 108.
ITEM 7
Sheet A6.2: See ASK1.7 for elevation of cabinetry in Glaze Mixing 110.
ITEM 8
Sheets A2.1, A2.3: Add 3’ wide teacher cabinets in Printmaking Lab 103, Painting Lab 113,
Drawing Lab 101, and Kiln Room 112 in locations shown on attached drawing ASK1.8 and
detailed on ASK1.9.
ITEM 9
Sheet A6.3: Change storage cabinet on south wall of Storage 108 to teacher cabinet detailed
on ASK 1.9.
Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1
3
ITEM 10
ITEM 11
ITEM 12
ITEM 13
ITEM 14
ITEM 15
ITEM 16
ITEM 17
ITEM 18
ITEM 19
ITEM 20
ITEM 21
ITEM 22
ITEM 23
ITEM 24
ITEM 25
ITEM 26
Sheets A6.1, A6.2, A9.3: Modify sections of wall shelving units in Ceramics Lab 113 and
Throwing Wheel Lab 104 that have hinged VDS on them as shown on attached drawings
ASK1.10 and ASK1.11.
Sheets A2.3, A5.1, A6.3, P2.1: Add cabinetry and accessible sink at west wall of Conference
Room in Building 1 as shown on ASK1.13 and PSK1.13.
Sheet A2.1: Make revisions to Building 30 Demolition Plan as noted on attached revised Sheet
A2.1.
Sheet A2.3: Make revisions to Building 1 Demolition Plan as noted on attached revised Sheet
A2.3.
Sheet A5.1: Change portion of south wall in Dry Bulk Storage 109 to 2x6 stud framing as
shown on ASK 1.12.
Sheets A2.2, A2.4: Add note to Roof Plans: “Allow for 8 downspouts each building.”
Sheets A6.1, A9.3: Add cabinetry below display cases as shown on ASK1.14 and ASK 1.15.
Sheet M4.1: Revise note on Partial Floor Plan 2: Do not prime and paint galvanized steel
hoods.
Sheets M0.2, M2.2, M6.1: Change fan EF-30-6 and add roof hood IH-30-5 per attached
AD1/M1 and AD1/M2; change exhaust hood in Glaze Mixing Room as shown on attached
AD1/M3.
Sheet E1.2: Revise Panelboard Schedules as shown on ESK 1.1, ESK 1.2. and ESK 1.3.
Sheet E6.3: Revise Podium Panel Elevation as shown on ESK 1.4.
Sheet E5.1: Revise light fixture switching to dimming switches for dimmable light fixtures as
shown on ESK1.5.
Sheet E5.1: Add emergency lighting in restrooms as shown on ESK1.7.
Sheet E5.1: Revise light fixture switching to dimming switches for dimmable light fixtures as
shown on ESK1.8.
Sheet E3.1: Revise callout of existing pull box at Building #1 as shown on ESK1.9.
Sheet E3.1: Revise sheet notes #4 and #5 with regards to splicing and extending existing fiber
to new IDF location for Building #30 as shown on ESK1.10.
Sheet E4.1: Make changes to Power Plans as shown on attached revised Sheet E4.1.
SPECIFICATIONS
ITEM 1
ITEM 2
ITEM 3
ITEM 4
ITEM 5
ITEM 6
ITEM 7
“2.3
Table of Contents; replace with attached revised Table of Contents with added sections.
Section 002113, Instructions for Bidders. Portion of paragraph 12.6.5 is deleted; see revised
section, attached.
Section 004510, Subcontractors List. Section has been revised to clarify that address is “city
and state”; see revised section, attached.
Section 004513, Statement of Qualifications. Paragraphs 5.9 and 5.10 are deleted; see revised
section, attached.
Section 011000, Summary of Work. Subparagraphs B, C, and D are added to paragraph 1.04,
Work Sequence or Phasing; see revised section, attached.
Section 019100, Commissioning Requirements. New section is added in its entirety; see new
section, attached.
Section 061053, revise paragraphs 2.3 and 2.4; revise to read as follows:
EXTERIOR BOARD ON BOARD SIDING, MATCHING TRIM AND FENCE BOARDS
A.
General: Kiln dried western red cedar, select, tight knot, appearance grade, full length without
splices.
Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1
4
B.
Siding material shall match the existing siding actual thickness, believed to be 7/8 inch actual,
contractor to confirm. Lengths shall be full length without splices.
C.
Trim boards shall be sized as detailed.
D.
Fence Boards shall be 1 x 6 nominal, lengths as detailed.”
2.4
FASCIA BOARDS
E.
General: Preservative treated, pre-primed, finger jointed Radiata Pine as manufactured by
Bodyguard Products, Limited or approved equal.
F.
Fascia Boards shall be 2 by 10 nominal, 20 foot lengths.”
ITEM 8
ITEM 9
Section 074113, paragraph 3.1A; delete “…gutters, downspouts,…” from this sentence.
Section 084113; delete paragraph 2.7.
ITEM 10
Section 099113, paragraph 1.7.A.1; revise to read as follows:
“1. Initial exterior paint prep work including removal of loose and unstable
hazardous materials, feathering of remaining stable material to adjacent
unfinished surfaces and priming of existing unpainted surfaces has been
executed by the Owner under a separate contract.”
ITEM 11
Section 099113, paragraph 1.7.A.2; revise to read as follows:
“2
ITEM 12
If materials requiring removal or further prep work are encountered, do not
disturb; immediately notify Owner. Owner will remove or prep hazardous
materials under a separate contract.”
Section 099113, paragraph 2.2.C; add paragraph C as follows:
“C. Exterior colors may involve up to two different base exterior wall colors and
two different accent colors for doors, frames, etc., as selected by the architect.”
ITEM 13
Section 099123, paragraph 2.2.E; add paragraph E as follows:
“E. Interior colors may involve up to 5 different base wall colors, 5 accent wall
colors, and two different accent colors for doors, frames, etc., as selected by
the architect.”
ITEM 14
ITEM 15
Section 099123; delete paragraph 3.3.F.
Section 102800, paragraph 2.2.L; add paragraph L as follows:
“L. Paper Towel Dispenser (H):
1.
2.
Basis-of-Design Product: ASI 8522.
Mounting: Surface.
Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1
5
3.
4.
5.
ITEM 16
ITEM 17
ITEM 18
ITEM 19
Minimum Capacity: One 8 inch wide, by 8 inch diameter standard
towel roll up to 800 feet.
Material and Finish: Stainless steel, No. 4 finish (satin), 18 gauge
door and 22 gauge cabinet.
Operation: Manual, accessible lever.
Section 122413, Roller Window Shades. New section is added in its entirety; see new section,
attached.
Section 230900, Temperature Controls. New section is added in its entirety; see new section,
attached.
Section 230950, Commissioning Requirements. New section is added in its entirety; see new
section, attached.
Section 260519, Low Voltage Cable. Delete Paragraph 2.02B. The use of ROMEX/Nonmetallic cable in NOT allowed. Revised Section 260519 is attached.
Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1
6
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No. 11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
EN
S ED
A RCH
IT
E
CT
S
IA
L
I
C
T
A
T
E
O F
FO
CA LI
R
N
HGHB
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
Architecture, Planning, Urban Design
9699 Blue Larkspur Lane, Suite 201
Monterey, California 93940
Tel 831 375-9594 Fax 831 646-9042
Monterey
Peninsula
College
ART DEPARTMENT
MODERNIZATION:
BUILDINGS 1 AND 30
AURUM CONSULTING
E NGINEERS
M ONTEREY B AY, INC.
Project No.
11188.00
60 Garden Court Suite 210 Monterey, CA 93940
T.831.646.3330 F.831.646.3336 www.acemb.com
27-C1
01-112810
Drawing Title:
Scale:
Sheet:
E4.1
11 Of
Revision:
Date:
18
Sheets
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
TABLE OF CONTENTS
SECTION 000110
Division
Section Title
Division 00
Procurement and Contracting Requirements
000110
000121
001113
002113
004213
004510
004513
004519
004526
004527
004547
004547.1
004547.2
004547.3
004547.4
004547.5
004547.6
004547.7
005213
006000
006110
006113.13
006113.16
007213
007313
Table of Contents
DSA Form 103; Statement of Structural Tests and Special Inspections
Notice Calling for Bids
Instruction to Bidders
Bid Proposal
Subcontractors List
Statement of Qualifications
Non-Collusion Affidavit
Certificate of Workers Compensation
Drug-Free Workplace Certification
Disabled Veteran Business Enterprises Participation Goal Policy
DVBE Worksheets; Attachment A; Bidders DVBE Statement
DVBE Worksheets; Attachment B; Subcontractible Items of Work
DVBE Worksheets; Attachment C; DVBE Participation Summary
DVBE Worksheets; Attachment D; DVBE Certification
DVBE Worksheets; Attachment E; DVBEs Contacted
DVBE Worksheets; Attachment F; DVBE Sub-Bids Not Accepted By
Bidder
DVBE Worksheets; Attachment G; Verification of DVBE Solicitations
Agreement
Project Forms
Bid Bond
Performance Bond
Labor and Material Payment Bond
General Conditions
Special Conditions
Division 01
General Requirements
011000
012000
012100
012300
012500
012613
Summary of Work
Price and Payment Procedures
Allowances
Alternates
Substitution Procedures
Requests for Interpretation
Section 000110
Pg #1
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
013100
013119
013216
013300
013323
013500
014100
014100.01
014213
014216
014219
014339
014523
015000
015100
015639
015713
016000
017123
017310
017329
017700
017800
019100
Project Management and Coordination
Project Meetings
Construction Progress Schedule
Submittal Procedures
Shop Drawings, Product Data, and Samples
Special Procedures
Regulatory Requirements
Added Requirements for DSA Reviewed Projects
Abbreviations, Symbols
Definitions
Reference Standards
Mockups
Testing and Inspection
Temporary Facilities and Controls
Temporary Utilities
Temporary Tree and Plant Protection
Temporary Erosion and Sediment Control
Product Requirements
Field Engineering
Selective Demolition
Cutting and Patching
Closeout Procedures
Closeout Submittals
Commissioning Requirements
DIVISION 02 EXISTING CONDITIONS
Not Used
DIVISION 03 CONCRETE
031100 Concrete Forming
032000 Concrete Reinforcing
033000 Cast-In-Place Concrete
DIVISION 04 MASONRY
Not Used
DIVISION 05 METALS
051200 Structural Steel
053100 Steel Decking
Section 000110
Pg #2
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
DIVISION 06 WOOD, PLASTICS, AND COMPOSITES
061000
061053
064116
066600
Rough Carpentry
Miscellaneous Carpentry
Plastic Laminate-Faced Architectural Cabinets
Fiberglass Reinforced Products
DIVISION 07 THERMAL AND MOISTURE PROTECTION
072100
074113
076200
078413
079200
Thermal Insulation
Standing Seam Metal Roof Panels
Sheet Metal Flashing and trim
Penetration Firestopping
Joint Sealants
DIVISION 08 OPENINGS
081113
081416
083113
084113
087100
088000
089119
Hollow Metal Doors and Frames
Flush Wood Doors
Access Doors and Frames
Aluminum Entrances and Storefronts
Door Hardware
Glazing
Wall Louvers
DIVISION 09 FINISHES
092900
093000
095113
096513
096519
096813
097202
097720
099113
099123
Gypsum Board
Tiling
Acoustical Panel Ceilings
Resilient Base and Accessories
Resilient Tile Flooring
Tile Carpeting
Wall Coverings
Decorative Fiberglass Reinforced Wall Panels
Exterior Painting
Interior Painting
DIVISION 10 SPECIALTIES
101100
101102
101423
102113
102800
Visual Display Surfaces
Tackable Wall Panels
Panel Signage
Toilet Compartments
Toilet and Bath Accessories
Section 000110
Pg #3
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
104416 Fire Extinguishers
105113 Metal Lockers
105120 Phenolic Lockers
DIVISION 11
Not Used
DIVISION 12 FURNISHINGS
122413 Roller Window Shades
DIVISION 13 THROUGH 21
Not Used
DIVISION 22 PLUMBING
220000 Plumbing General
220500 Plumbing
DIVISION 23 HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
230000
230500
230900
230950
Mechanical General Requirements
HVAC
Temperature Controls
HVAC Commissioning
DIVISION 24 THROUGH 25
Not Used
DIVISION 26 ELECTRICAL
260500
260519
260526
260533
260542
260543
260544
262416
262726
262816
265100
265110
Electrical General Requirements
Low Voltage Cable
Grounding
J-Boxes
Conduits
Underground Ducts
Pull Boxes
Panel
Devices
Breakers
Lighting
OCC-Sensor
Section 000110
Pg #4
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
DIVISION 27 COMMUNICATIONS
270500 Voice and Data Cat6
DIVISION 28 ELECTRONIC SAFETY AND SECURITY
283100 Fire Alarm System
DIVISION 29 THROUGH 30
Not Used
DIVISION 31 EARTHWORK
311000
312000
312500
316329
Site Clearing & Demolition
Earth Moving
Erosion Control
Cast-in-Place Concrete Drilled Piers
DIVISION 32 EXTERIOR IMPROVEMENTS
321313 Site Concrete
323100 Screen Fencing
DIVISION 33 UTILITIES
334100 Storm Drainage
Section 000110
Pg #5
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
Section 000110
Pg #6
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
INSTRUCTIONS FOR BIDDERS
1. Preparation and Submittal of Bid Proposal.
1.1. Bid Proposal Preparation. All information required by the bid forms must be completely and
accurately provided. Numbers shall be stated in both words and figures where so indicated in
the bid forms; conflicts between a number stated in words and in figures are governed by the
words. Partially completed Bid Proposals or Bid Proposals submitted on other than the bid
forms included herein are non-responsive and will be rejected. Bid Proposals not conforming
to these Instructions for Bidders and the Notice to Contractors Calling for Bids (“Call for Bids”)
may be deemed non-responsive and rejected.
1.2. Bid Proposal Submittal. Bid Proposals shall be submitted at the place designated in the Call
for Bids in sealed envelopes bearing on the outside the Bidder’s name and address along
with an identification of the Work for which the Bid Proposal is submitted. Bidders are solely
responsible for timely submission of Bid Proposals to the District at the place designated in
the Call for Bids.
1.3. Date and Time of Bid Proposal Submittal. A Bid Proposal is submitted only if the outer
envelope containing the Bid Proposal is marked with the Project title and is received by a
District Purchasing Department representative for logging-in at (or before) the latest date and
time for submittal of Bid Proposals.
The official U.S. time-clock website:
http://www.time.gov/timezone.cgi?Pacific/d/-8/java is controlling and determinative as to the
time of the Bidder’s submittal of the Bid Proposal. The foregoing notwithstanding, whether or
not Bid Proposals are opened exactly at the time fixed in the Call for Bids, no Bid Proposals
shall be received or considered by the District after it has commenced the public opening and
reading of Bid Proposals; Bid Proposals submitted after such time are non-responsive and will
be returned to the Bidder unopened.
2. Bid Security. Each Bid Proposal shall be accompanied by Bid Security in the form of: (i) cash, (ii)
a certified or cashier’s check made payable to the District or (iii) a Bid Bond, in the form and
content attached hereto, in favor of the District executed by the Bidder as a principal and a Surety
as surety (the “Bid Security”) in an amount equal to Ten Percent (10%) of the Bid Proposal
amount, inclusive of the price(s) proposed for additive Alternate Bid Items, if any. A Bid Proposal
submitted without the required Bid Security is non-responsive and will be rejected. If the Bid
Security is in the form of a Bid Bond, the Bidder’s Bid Proposal shall be deemed responsive only if
the Bid Bond is in the form and content included herein and the Surety is an Admitted Surety
Insurer under Code of Civil Procedure §995.120.
3. Documents Accompanying Bid Proposal; Signatures. Documents which must be submitted with
each Bid Proposal are identified in the Call for Bids. Any document submitted with a Bid Proposal
which is not complete, accurate and executed, as required by each document, will result in the Bid
Proposal being deemed non-responsive.
4. Bidder Modifications; Withdrawal or Modification of Submitted Bid Proposal.
4.1. Bidder Modifications to Bid Forms Prohibited. Modifications by a Bidder to the bid forms
which are not specifically called for or permitted may result in the Bidder’s Bid Proposal being
deemed non-responsive and rejected.
4.2. Withdrawal or Modification of Submitted Bid Proposal. A Bidder may not withdraw or modify a
Bid Proposal submitted to the District except in strict conformity to the following. Bid
Proposals may be withdrawn or modified only if: (i) the Bidder submitting the Bid Proposal
submits a request for withdrawal or modification in writing to the District; and (ii) the written
withdrawal or modification request is actually received by the District prior to the latest
date/time for submittal of Bid Proposals. Requests for withdrawal of a Bid Proposal after the
Page 1
Section 00 21 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
public opening of Bid Proposals pursuant to Public Contract Code §5100 et seq. will be
considered only if in strict conformity with requirements of Public Contract Code §5100 et seq.
5. Erasures; Inconsistent or Illegible Bid Proposals. Bid Proposals must not contain any erasures,
interlineations or other corrections unless the same are suitably authenticated by affixing in the
margin immediately opposite such erasure, interlineations or correction the surname(s) of the
person(s) signing the Bid Proposal. Any Bid Proposal not conforming to the foregoing may be
deemed by the District to be non-responsive. If any Bid Proposal or portions thereof, is
determined by the District to be illegible, ambiguous or inconsistent, whether by virtue of any
erasures, interlineations, corrections or otherwise, the District may reject such a Bid Proposal as
being non-responsive.
6. Examination of Site and Contract Documents. Each Bidder shall, at its sole cost and expense,
inspect the Site and to become fully acquainted with the Contract Documents and conditions
affecting the Work. Failure of a Bidder to receive or examine any of the Contract Documents or to
inspect the Site shall not relieve such Bidder from any obligation with respect to the Bid Proposal,
or the Work required under the Contract Documents. The District assumes no responsibility or
liability to any Bidder for, nor shall the District be bound by, any understandings, representations
or agreements of the District’s agents, employees or officers concerning the Contract Documents
or the Work made prior to execution of the Contract which are not in the form of Bid Addenda duly
issued by the District. The submission of a Bid Proposal shall be deemed prima facie evidence of
the Bidder’s full compliance with the requirements of this section.
7. Withdrawal of Bid Proposal. Any Bidder may withdraw its Bid Proposal only written request
actually received by the District prior to the scheduled closing time for the receipt of Bid Proposals
and the District’s public opening and reading of Bid Proposals; written requests to withdraw a
submitted Bid Proposal received by the District after the scheduled closing time for receipt of Bid
Proposals shall not be considered by the District, nor effective to withdraw such Bid Proposal.
8. Agreement and Bonds. The Agreement which the successful Bidder, as Contractor, will be
required to execute along with the forms Payment Bond, Performance Bond and other documents
and instruments which are required to be furnished are included in the Contract Documents and
shall be carefully examined by the Bidder. The required number of executed copies of the
Agreement and the form and content of the Performance Bond and the Payment Bond and other
documents or instruments required at the time of execution of the Agreement are specified in the
Contract Documents.
9. Interpretation of Drawings, Specifications or Contract Documents. Inquiries or clarification
requests submitted by a Bidder in strict accordance with the Call for Bids will be responded to in
writing by or on behalf of the District. If a response to an inquiry or clarification: (i) includes:
interpretation, correction or clarification of the Contract Documents; or (ii) affects requirements of
the bidding process or submittal of Bid Proposals, the District will issue addenda to the Contract
Documents. A copy of any such addendum will be delivered by fax, email or mail to each Bidder
who has obtained a set of the Contract Documents. No person is authorized to render an oral
interpretation or correction of any portion of the Contract Documents to any Bidder, and no Bidder
is authorized to rely on any such oral interpretation or correction. Failure to timely request
interpretation or clarification of any portion of the Contract Documents pursuant to the foregoing is
a waiver of any discrepancy, defect or conflict therein.
10. District’s Right to Modify Contract Documents. Before the public opening and reading of Bid
Proposals, the District may modify the Work, the Contract Documents, or any portion(s) thereof by
the issuance of written addenda disseminated to all Bidders who have obtained a copy of the
Specifications, Drawings and Contract Documents pursuant to the Call for Bids. If the District
Page 2
Section 00 21 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
issues any addenda during the bidding, the failure of any Bidder to acknowledge such addenda in
its Bid Proposal will render the Bid Proposal non-responsive and rejected.
11. Bidders Interested in More Than One Bid Proposal; Non-Collusion Affidavit. No person, firm,
corporation or other entity shall submit or be interested in more than one Bid Proposal for the
same Work; provided, however, that a person, firm or corporation that has submitted a subproposal to a Bidder or who has quoted prices for materials to a Bidder is not disqualified from
submitting a sub-proposal, quoting prices to other Bidders or submitting a Bid Proposal for the
proposed Work to the District. The form of Non-Collusion Affidavit included in the Contract
Documents must be completed and duly executed on behalf of the Bidder; failure of a Bidder to
submit a completed and executed Non-Collusion Affidavit with its Bid Proposal will render the Bid
Proposal non-responsive.
12. Award of Contract.
12.1.
Waiver of Irregularities or Informalities. The District reserves the right to reject any and
all Bid Proposals or to waive any irregularities or informalities in any Bid Proposal or in the
bidding.
12.2.
Award to Lowest Responsive Responsible Bidder. The award of the Contract, if made
by the District through action of its Board of Trustees, will be to the responsible Bidder
submitting the lowest priced responsive Bid Proposal on the basis of the Base Bid Proposal
and Alternate Bid Items, if any, selected in accordance with these Instructions.
12.3.
Selection of Alternate Bid Items. If Alternate Bid Items are included in the bidding for
the Work, the selection of Alternate Bid Items for inclusion in the scope of the Work of the
Contract and for determination of the lowest priced Bid Proposal will be by a “blind-bidder”
process. After opening timely submitted Bid Proposals and before the public reading of Bid
Proposals, District clerical staff (“Clerical Staff”) who not responsible for selecting Alternate
Bid Items for inclusion in the Contract to be awarded will assign each Bidder an alphabetical
letter for identification purposes. The Clerical Staff will mask all portions of the Bid Proposal
and other documents submitted with Bid Proposals so that the identity of each Bidder is not
revealed. The Clerical Staff will maintain a list (“the Bidders List”) which identifies by name
and the alphabetical letter assigned by the Clerical Staff to each Bidder. After completing the
Bidders List, the Clerical Staff will publicly read the Bid Proposals amounts of each Bidder for
the Base Bid as well as each Alternate Bid Item. In this public reading of Bid Proposals,
Bidders will not be identified by name; Bidders will be identified only by alphabetical letter
assigned to each Bidder by the Clerical Staff. After the public reading of Bid Proposals, the
Clerical Staff will provide the Architect and the District’s staff responsible for selection of
Alternate Bid Items for inclusion in the Contract to be awarded (“District Project Staff”) copies
of Bid Proposals with the identities of Bidders masked. At such time as the Architect and the
District Project Staff have determined which Alternate Bid Items, if any are to be included in
the scope of Work of the Contract and the Bidder submitting the lowest made a determination
of which Bidder (by the alphabetical letter assigned by Clerical Staff) submitted the lowest
priced Bid Proposal on the basis of the Base Bid Proposal and the combination of Alternate
Bid Items, if any, for inclusion in the scope of Work of the Contract the Clerical Staff will
provide the District Project Staff with the Bidders List so that the identity of the Bidder
submitting the lowest priced Bid Proposal can be identified. Until such time as the District
Project Staff have completed review of Bid Proposals and determination of which Alternate
Bid Items are to be included in the Work and the scope of the Contract to be awarded, there
will be no communication between the Clerical Staff and the Architect or the District Project
Staff regarding the identities of Bidders or disclosure of any portion of the Bidders List to the
District Project Staff.
12.4.
Alternate Bid Items Not Included in Award of Contract. Bidders are referred to the
provisions of the Contract Documents permitting the District, during performance of the Work,
Page 3
Section 00 21 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
to add or delete from the scope of the Work any or all of the Alternate Bid Items with the cost
or credit of the same being the amount(s) set forth by in the Alternate Bid Items Bid on the
Proposal.
12.5.
Responsive Bid Proposal. A responsive Bid Proposal shall mean a Bid Proposal which
conforms to and complies with requirements of the Bid and Contract Documents.
12.6.
Responsible Bidder.
12.6.1. Bidder Capacity. Factors affecting the Bidder’s capacity to perform and complete the
Work will be assessed, including: (i) Bidder’s access to labor, materials and other
resources necessary to complete the Work; (ii) Bidder’s ability to complete the Work
within the time established for completion of the Work, or portions thereof; and (iii)
Bidder’s ability to complete warranty obligations.
12.6.2. Bidder Character, Integrity. Factors reflecting the character and integrity of the Bidder,
including: (i) other public agency finding/determination, within the past five (5) years, that
the Bidder is not responsible; (ii) currently debarred from bidding public works projects or
debarment from bidding within past five (5) years; and (iii) false claims liability within the
past five (5) years under local, state or federal laws.
12.6.3. Bidder Financial Capability. Factors considered include: (i) sufficiency of the Bidder’s
financial resources; (ii) whether the Bidder is current in payment of debts and
performance of other financial obligations; and (iii) bankruptcy or insolvency proceedings
have been instituted within the past five (5) years.
12.6.4. Bidder Prior Performance. The Bidder’s prior performance on prior public works
contracts, including without limitation: (i) cost overruns; (ii) compliance with general
conditions and other contractual requirements, including schedule development,
schedule updates and coordination of labor, material/equipment procurements and
subcontractors; (iii) completion within allocated time; (iv) submittal of unsubstantiated,
unsupported or excessive cost proposals, claims or contract adjustment requests; (iv)
completion of a project by a surety; (vi) owner’s exercise of default remedies; and (vii)
finding or determination by any public agency that the Bidder is not a responsible bidder.
12.6.5. Safety. Factors include: (i) findings of serious or willful safety violations of safety laws,
regulations or requirements by any local, state or federal agency within the past five (5)
years; (ii) adequacy and implementation of safety plans, programs for on-site and off-site
construction and construction related activities.
13. Subcontractors.
13.1.
Designation of Subcontractors; Subcontractors List. Each Bidder shall submit a list of
its proposed Subcontractors for the proposed Work as required by the Subletting and
Subcontracting Fair Practices Act (California Public Contract Code §§ 4100 et seq.) on the
form furnished. The failure of any Bid Proposal to include all information required by the
Subcontractors List will result in rejection of the Bid Proposal for non-responsiveness.
13.2.
Work of Subcontractors. All Bidders are referred to the Contract Documents and the
notation therein that all Contract Documents are intended to be complimentary and that the
organization or arrangements of the Specifications and Drawings shall not limit the extent of
the Work of the Contract Documents. Accordingly, all Bidders are encouraged to disseminate
all of the Specifications, Drawings and other Contract Documents to all persons or entities
submitting sub-bids to the Bidder. The omission of any portion or item of Work from the Bid
Proposal or from the sub-bidders’ sub-bids which is/are necessary to produce the intended
results and/or which are reasonably inerrable from the Contract Documents is not a basis for
adjustment of the Contract Price or the Contract Time.
Page 4
Section 00 21 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
13.3.
Subcontractor Bonds. Pursuant to California Public Contract Code §4108, if a Bidder
requires a bond or bonds of its Subcontractor(s), whether the expense of procuring such bond
or bonds are to be borne by the Bidder or the Subcontractor(s), such requirements shall be
specified in the Bidder’s written or published request for sub-bids. Failure of the Bidder to
comply with these requirements shall preclude the Bidder from imposing bonding
requirements upon its Subcontractor(s) or rejection of a Subcontractor’s bid under California
Public Contract Code §4108(b).
14. Workers’ Compensation Insurance. Pursuant to California Labor Code § 3700, the successful
Bidder shall secure Workers’ Compensation Insurance for its employees engaged in the Work of
the Contract. The successful Bidder shall execute and deliver to the District the form of Workers
Compensation Certification included in the Contract Documents concurrently with such Bidder’s
delivery of the executed Agreement to the District.
15. Bid Security Return. The Bid Security of the Bidders submitting the three lowest priced Bid
Proposals, the number being solely at the discretion of the District, will be held by the District for
ten (10) days after the period for which Bid Proposals must be held open (which is set forth in the
Call for Bids) or until posting by the successful Bidder(s) of the bonds, certificates of insurance
required and return of executed copies of the Agreement, whichever first occurs, at which time the
Bid Security of such other Bidders will be returned to them.
16. Forfeiture of Bid Security. If the Bidder awarded the Contract fails or refuses to execute the
Agreement within Five (5) calendar days from the date of receiving notification that it is the Bidder
to whom the Contract has been awarded, the District may declare the Bidder’s Bid Security
forfeited as damages caused by the failure of the Bidder to enter into the Contract and may
thereupon award the Contract for the Work to the responsible Bidder submitting the next lowest
Bid Proposal or may call for new bids, in its sole and exclusive discretion.
17. Contractors’ License. No Bid Proposal will be considered from a Bidder who, at the time Bid
Proposals are opened, is not licensed to perform the Work of the Contract Documents, in
accordance with the Contractors’ License Law, California Business & Professions Code §§7000 et
seq. This requirement is not a mere formality and will not be waived by the District or its Board of
Trustees. The required California Contractors’ License classification(s) for the Work is set forth in
the Call for Bids.
18. Non-Discriminatory Employment Practices. It is the policy of the District that there be no
discrimination against any prospective or active employee engaged in the Work because of race,
color, ancestry, national origin, religious creed, sex, age, marital status or other legally protected
classification. All Bidders agree to comply with the District’s non-discrimination policy and all
applicable Federal and California anti-discrimination laws including but not limited to the California
Fair Employment & Housing Act beginning with California Government Code §§ 12940 et seq. and
California Labor Code § 1735. In addition, all Bidders agree to require like compliance by any
Subcontractor employed by them on the Work of the Contract.
19. Bidder’s Qualifications. Each Bidder shall submit with its Bid Proposal the form of Statement of
Bidder’s Qualifications, which is included within the Contract Documents. All information required
by Statement of Bidder’s Qualifications shall be completely and fully provided. Any Bid Proposal
not accompanied by the Statement of Bidder’s Qualifications completed with all information
required and bearing the signature of the Bidder’s duly authorized representative under penalty of
perjury will render the Bid Proposal non-responsive and rejected. If the District determines that
any information provided by a Bidder in the Statement of Bidder’s Qualifications is false or
misleading, or is incomplete so as to be false or misleading, the District may reject the Bid
Page 5
Section 00 21 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
Proposal submitted by such Bidder as being non-responsive. If any response to the “Essential
Requirements” section of the Statement of Qualifications is a “not qualified” response, the Bidder’s
Bid Proposal will be rejected for failure of the Bidder to meet minimum qualifications for the Work.
20. Substitution of Specified Materials/Equipment. Pursuant to Public Contract Code §3400(a), the
District will consider requests of Bidders for the District to consent to substitutions of specified
materials/equipment (“Substitution Request”) only during the bidding process. The District will not
consider or consent to a Substitution Request thereafter.
20.1.
Latest Date/Time for Submittal of Substitution Request. The latest date/time for a
Bidder to submit a Substitution Request is the latest date/time for Bidders to submit a Pre-Bid
Inquiry, as set forth in the Call for Bids. The District will not consider or respond to a
Substitution Request thereafter.
20.2.
Submittal Requirements.
Notwithstanding a Bidder’s timely submission of a
Substitution Request, the District will not consider or respond to a Substitution Request
unless all of the following are complied with by the Bidder: (i) the Substitution Request is
submitted on a completed form of Submittal Substitution Form (Document 00 60 02), along
with at least the following: (i) technical data establishing the equivalency of the proposed
substitution with the specified materials/equipment, including without limitation drawings,
performance specifications, samples, test reports, and other similar items; (ii) statement by
the Contractor that the proposed substitution is in full compliance with the requirements of the
Contract Documents and the Laws and that incorporation of the proposed substitution in lieu
of the specified materials/equipment will not delay completion of the Work or extend the
Contract Time; (iii) list of Subcontractors affected by the Substitution Request; and (iv) if the
proposed substitution requires re-design or removal of any Work to accommodate the
proposed substitution, drawings and engineering calculations prepared by a California
licensed architect or registered engineer for the portions of the Work requiring re-design or
removal. Notwithstanding submittal of the foregoing, if requested by the District or Architect,
the Bidder submitting a Substitution Request shall submit such additional substantiating data
as requested by the District or the Architect.
20.3.
Specified Materials/Equipment.
Where multiple manufacturers of specified
materials/equipment are identified or there are multiple materials/equipment specified in the
Contract Documents, the first named manufacturer or the first named material/equipment is
the basis of the design of the Work; use of any other manufacturer or material/equipment is
deemed a substitution which can be furnished and installed by the successful Bidder only if
the District consents thereto in accordance with these provisions.
20.4.
District Review and Notice of Consent. Timely submitted Substitution Requests will be
reviewed by the District and Architect to determine the equivalency of the proposed
substitution with the specified materials/equipment. The District’s decision to grant, deny or
condition consent to substitute specified materials/equipment is final and not subject to further
review or appeal. If the District consents to or conditionally consents to substitution of
specified materials/equipment, the District will issue an Addendum identifying the specified
materials/equipment and the alternative materials/equipment consent to or conditionally
consented to by the District.
20.5.
Bidder Responsibilities. If the District consents to or conditionally consents to
substituted materials/equipment for those originally specified (Accepted Substitution) and a
Bidder elects to incorporate any Accepted Substitution into its Bid Proposal, the Bidder shall
be responsible for identifying in the Subcontractors List the Subcontractor(s) necessary to
complete installation of the Accepted Substitution.
21. Job-Walk. The District will conduct a Job-Walk at the time(s) and place(s) designated in the Call
for Bids. The District may, in its sole and exclusive discretion, elect to conduct one or more JobWalk(s) in addition to that set forth in the Call for Bids, in which event the District shall notify all
Page 6
Section 00 21 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
Bidders who have theretofore obtained the Contract Documents pursuant to the Call for Bids of
any such additional Job-Walk. If the District elects to conduct any Job-Walk in addition to that set
forth in the Call for Bids, the District shall, in its notice of any such additional Job-Walk(s), indicate
whether Bidders’ attendance at such additional Job-Walk(s) is/are mandatory. If attendance at the
Job Walk is indicated in the Call for Bids as being mandatory, the failure of any Bidder to have its
authorized representative present at the entirety of the Job-Walk will render the Bid Proposal of
such Bidder to be non-responsive. Where the Job-Walk is mandatory, a Bidder may have more
than one authorized representative and/or representatives of its Subcontractors present at the
Job-Walk; provided, however that attendance by representatives of the Bidder’s Subcontractors
without attendance by a representative of the Bidder shall not be sufficient to meet the Bidder’s
obligations hereunder and will render the Bid Proposal of such Bidder to be non-responsive. The
District will reject the Bid Proposal of a Bidder who obtains the Bid and Contract Documents after
the date of the Mandatory Job-Walks set forth in the Call for Bids unless a Job-Walk is requested
by such Bidder and a Job-Walk is conducted by the District in accordance with the following
provisions. The District may, in its sole and exclusive discretion, conduct such requested JobWalk taking into consideration factors such as the time remaining prior to the scheduled opening
of Bid Proposals. Any such requested Job Walk will be conducted only upon the requesting
Bidder’s agreement to reimburse the District for the actual and/or reasonable costs for the
District’s staff and its agents and representatives in arranging for and conducting such additional
Job-Walk.
22. Public Records. Bid Proposals and other documents responding to the Call for Bids become the
exclusive property of the District upon submittal to the District. At such time as the District issues
the Notice of Intent to award the Contract pursuant to these Instructions for Bidders, all Bid
Proposals and other documents submitted in response to the Call for Bids become a matter of
public record and shall be thereupon be considered public records, except for information
contained in such Bid Proposals deemed to be Trade Secrets (as defined in California Civil Code
§ 3426.1) and information provided in response to the Statement of Qualifications. A Bidder that
indiscriminately marks all or most of its Bid Proposal as exempt from disclosure as a public record,
whether by the notations of “Trade Secret,” “Confidential,” “Proprietary,” or other similar notations,
may result in, or render, the Bid Proposal non-responsive and rejected. The District is not liable or
responsible for the disclosure of such records, including those exempt from disclosure if disclosure
is deemed required by law, by an order of Court, or which occurs through inadvertence, mistake or
negligence on the part of the District or its officers, employees or agents. At such time as Bid
Proposals are deemed a matter of public record, pursuant to the above, any Bidder or other party
shall be afforded access for inspection and/or copying of such Bid Proposals, by request made to
the District in conformity with the California Access to Public Records Act, California Government
Code §§6250, et. seq. If the District is required to defend or otherwise respond to any action or
proceeding wherein request is made for the disclosure of the contents of any portion of a Bid
Proposal deemed exempt from disclosure hereunder, the Bidder submitting the materials sought
by such action or proceeding agrees to defend, indemnify and hold harmless the District in any
action or proceeding from and against any liability, including without limitation attorneys’ fees
arising therefrom. The party submitting materials sought by any other party shall be solely
responsible for the cost and defense in any action or proceeding seeking to compel disclosure of
such materials; the District’s sole involvement in any such action shall be that of a stakeholder,
retaining the requested materials until otherwise ordered by a court of competent jurisdiction.
23. Drug Free Workplace Certificate. In accordance with California Government Code §§ 8350 et
seq., the Drug Free Workplace Act of 1990, the successful Bidder will be required to execute a
Drug Free Workplace Certificate concurrently with execution of the Agreement. The successful
Bidder will be required to implement and take the affirmative measures outlined in the Drug Free
Workplace Certificate and in California Government Code §§8350 et seq. Failure of the
Page 7
Section 00 21 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
successful Bidder to comply with the measures outlined in the Drug Free Workplace Certificate
and in California Government Code §§ 8350 et seq. may result in penalties, including without
limitation, the termination of the Agreement, the suspension of any payment of the Contract Price
otherwise due under the Contract Documents and/or debarment of the successful Bidder.
24. Notice of Intent to Award Contract. Following the public opening and reading of Bid Proposals, the
District will issue a Notice of Intent to Award the Contract, identifying the Bidder to whom the
District intends to award the Contract and the date/time/place of the District’s Board of Trustees
meeting at which award of the Contract will be considered.
25. Bid Protest.
25.1.
Submittal of Bid Protest. Any Bidder submitting a Bid Proposal to the District may file a
protest of the District’s intent to award the Contract provided that all of the following are
complied with: (i) the bid protest is in writing; (ii) the bid protest is filed and received by the
District’s Vice-President, Administrative Services not more than five (5) calendar days after
the date of issuance of the District’s Notice of Intent to Award the Contract; and (iii) the written
bid protest sets forth, in detail, all grounds for the bid protest, including without limitation all
facts, supporting documentation, legal authorities and argument in support of the grounds for
the bid protest; any matters not set forth in the written bid protest shall be deemed waived. All
factual contentions must be supported by competent, admissible and creditable evidence.
Any bid protest not conforming to the foregoing shall be rejected by the District as invalid.
25.2.
District Review and Disposition of Bid Protest. Provided that a bid protest is filed in
strict conformity with the foregoing, the District’s Vice-President, Administrative Services or
such individual(s) as may be designated by him/her (“Designee”) will review and evaluate the
basis of the bid protest. The District’s Vice-President, Administrative Services or Designee
shall provide the Bidder submitting the bid protest with a written statement concurring with or
denying the bid protest (Bid Protest Response). The Bid Protest Response is deemed the
final action of the District and not subject to appeal or reconsideration by any other employee
or officer of the District or the Board of Trustees of the District. The issuance of the Bid
Protest Response by the District’s Vice-President, Administrative Services or the Designee is
an express condition precedent to the institution of any legal or equitable proceedings relative
to the bidding process, the District’s intent to award the Contract, the District’s disposition of
any bid protest or the District’s decision to reject all Bid Proposals. If any such legal or
equitable proceedings are instituted and the District is named as a party thereto, the
prevailing party(ies) shall recover from the other party(ies), as costs, all attorneys’ fees and
costs incurred in connection with any such proceeding, including any appeal arising
therefrom. Each Bidder shall acknowledge in the Bid Proposal that the foregoing is a binding
attorneys’ fee agreement pursuant to Civil Code §1717 and shall be enforceable against the
Bidder and the District.
[End of Section]
Page 8
Section 00 21 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
THIS PAGE INTENTIONALLY BLANK
Page 9
Section 00 21 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
SUBCONTRACTORS LIST
Project (“the Work”)
Art Department Modernization: Buildings 1 and 30
Bidder Name
_________________________________________
Bidder’s Representative
Signature
_________________________________________
(Signature)
_________________________________________
(Typed or Printed Name)
Licensed Name of
Subcontractor
Address of Office, Mill or Shop
(City & State)
Trade or Portion of
Work
DUPLICATE THIS PAGE AS NECESSARY FOR LISTING ADDITIONAL SUBCONTRACTORS
[END OF SECTION]
Page 1
Section 00 45 10
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
THIS PAGE INTENTIONALLY BLANK
Page 2
Section 00 45 10
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
STATEMENT OF QUALIFICATIONS
1. Bidder Information.
1.1. Contact Information
_____________________________________________
Street Address
_____________________________________________
City, State, Zip Code
Mailing Address
Physical Location
(if different from mailing address)
Telephone/Fax
_____________________________________________
Street Address
_____________________________________________
City, State, Zip Code
(______) __________________
Telephone
(______) __________________
Fax
1.2. Bidder Contacts.
Name
______________________________________
Telephone: (______)______________________
Contact Information
Fax
(______)______________________
Email
_____________________________
1.3. California Contractors’ License.
License Number(s)
______________________________________
License Classification(s)
______________________________________
Responsible Managing
Employee; Responsible
Managing Officer
Expiration Date(s)
______________________________________
______________________________________
1.4. Bidder Form of Entity.
Corporation
General Partnership
Limited Partnership
Limited Liability Company
Limited Liability Partnership
Joint Venture
Sole Proprietorship
[CONTINUED NEXT PAGE]
Page 1
Section 00 45 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
2. Revenue. Complete the following for the Bidder’s construction operations; if any portion of the
revenue disclosed is generated by non-construction operations or activities, the Bidder must
identify the portion of revenue attributed to construction operations and generally describe
business activities of the Bidder that generates non-construction operations related revenue.
Calendar Year/ Fiscal
Year
Annual Gross
Revenue
Average Dollar
Value of all
Contracts
Dollar Value of
Largest Contract
2010 (2009/2010)
2011 (2010/2011)
2012 (2011/2012)
3. References.
DSA Project Inspectors
Firm Name
Address
Telephone No.
Contact Name
Owners (K-12 school districts or community colleges preferred)
Owner Name
Address
Telephone No.
Contact Name
Architects (K-12 or Community College Projects)
Architect Firm Name &
Address
Telephone No.
Architect Firm Contact Name
Contact Name
[CONTINUED NEXT PAGE]
Page 2
Section 00 45 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
4. Insurance.
Commercial General Liability
Insurance
Commercial General Liability
Insurance Broker
Insurer:
_______________________________________
Policy No.
_______________________________________
Broker
_______________________________________
(Contact Name) ________________________________________
_____________________________________________________
(Street Address)
_____________________________________________________
(City, State & Zip Code)
(______) __________________ (______) ___________________
Telephone
Fax
_____________________________________________________
(Email address)
Bid, Performance and Labor &
Materials Payment Bond Surety
Surety:
_____________________________________
Surety Broker
____________________________________
_____________________________________________________
(Surety Broker Contact Name)
_____________________________________________________
(Street Address)
_____________________________________________________
(City, State & Zip Code)
(______) __________________ (______) ___________________
Telephone
Fax
_____________________________________________________
(Email address)
Workers Compensation Insurance
Workers Compensation Insurance
Broker
Insurer:
_______________________________________
Policy No.
_______________________________________
Broker
_______________________________________
(Contact Name) ________________________________________
_____________________________________________________
(Street Address)
_____________________________________________________
(City, State & Zip Code)
(______) __________________ (______) ___________________
Telephone
Fax
_____________________________________________________
(Email address)
[CONTINUED NEXT PAGE]
Page 3
Section 00 45 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
5. Essential Requirements. A Bidder will not be deemed qualified if the answer to any of the
following questions results in a “not qualified” response and the Bid Proposal submitted by such a
Bidder will be rejected for failure of the Bidder to meet minimum qualifications for the Work.
5.1. Bidder possesses a valid and currently in good standing California Contractors’ license for the
Classification(s) of Contractors’ License required by the Call for Bids.
__ Yes
__ No (Not Qualified)
5.2. Bidder has a current commercial general liability insurance policy with coverage limits of at
least $1,000,000 per occurrence and $2,000,000 in the aggregate.
__ Yes
__ No (Not Qualified)
5.3. Bidder has a current workers’ compensation insurance policy as required by the Labor Code
or is legally self-insured pursuant to Labor Code §3700.
__ Yes
__ No (Not Qualified)
__ Bidder is exempt from this requirement, because it has no employees
5.4. The Bidder is ineligible or debarred from submitting Bid Proposals for public works projects or
public works contracts pursuant Labor Code §1777.1 or Labor Code §1777.7.
__ Yes (Not Qualified)
__ No
5.5. A public agency, within the past five (5) years conducted proceedings that resulted in a
finding that the Bidder, or any predecessor to the Bidder, is not a “responsible” bidder for a
public works project or a public works contract.
__ Yes (Not Qualified)
__ No
5.6. During the last five (5) years, the Bidder or any predecessor to the Bidder, or any of the equity
owners of the Bidder have been convicted of a federal or state crime involving fraud, theft, or
any other act of dishonesty.
__ Yes (Not Qualified)
__ No
5.7. During the past five (5) years a Surety has completed any project or the Bidder’s obligations
under a construction contract.
__ Yes (Not Qualified)
__ No
5.8. During the past five (5) years the Bidder has been declared in default under any construction
contract to which the Bidder was a party.
__ Yes (Not Qualified)
__ No
5.9. The Bidder’s Worker’s Compensation Insurance current EMR is more than 1.25.
__ Yes (Not Qualified)
__ No
Page 4
Section 00 45 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
5.10.
The Bidder’s Worker’s Compensation Insurance average EMR over the past five (5)
years is more than 1.25.
__ Yes (Not Qualified)
__ No
6. Questionnaire. If the response to any of the following questions is a “yes” complete and accurate
details must be attached; failure to attach such details will render the Bid Proposal of the Bidder to
be non-responsive and rejected. Responses to the following will be used to evaluate Bidder
responsibility.
6.1. Have legal, arbitration or administrative proceedings been brought construction project owner
against the Bidder or any of the principals, officers or equity owners of the Bidder within the
past ten (10) years which arise out of or are related to any construction project? If “yes”
details must include: (i) name of party initiating proceedings against the Bidder; (ii) contact
name, address, phone and email address of party initiating proceedings; (iii) circumstances
resulting in the initiation of proceedings; (iv) amount or other relief demanded; and (v)
outcome of proceedings.
__ Yes
__ No
6.2. Has the Bidder brought any legal, arbitration or administrative proceedings against the owner
of a construction project within the past ten (10) years which arise out of or are related to the
construction project? If “yes” details must include: (i) name of owner; (ii) contact name,
address, phone and email address of contact person for owner; (iii) circumstances resulting in
the initiation of proceedings; (iv) amount or other relief demand; and (v) outcome of
proceedings.
__ Yes
__ No
6.3. Provide the following for three (3) projects the Bidder has completed within the past five (5)
years similar in size, scope, function and construction value as the Work:
Project Name
Project Owner; Contact Information
Function/Use of Project
Original Contract Time
Actual Project Completion Time
Original Contract Price
Final Adjusted Contract Price
6.4. During the past five (5) years, has your organization ever been denied bond coverage by a
surety company?
____ Yes ____ No
If “yes” on a separate attachment provide details of the denial of bond coverage and the name
of the company or companies which denied coverage.
6.5. At any time during the past five (5) years, has any surety company made any payments on
behalf the Bidder to satisfy any claims made against a bid, performance or payment bond
issued to the Bidder, in connection with a construction project, either public or private?
Page 5
Section 00 45 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
____ Yes ____ No
If “yes,” on a separate attachment set forth: (i) the amount of each such claim; (ii) the name
and telephone number of the claimant; (iii) the date of the claim; (iv) the grounds for the claim;
(v) the present status of the claim; (vi) the date of resolution of such claim if resolved; (vii) the
method by which such was resolved if resolved; (viii) the nature of the resolution; and (ix) the
amount, if any, at which the claim was resolved.
6.6. In the last five years has any insurance carrier, for any policy of insurance, refused to renew
the insurance policy for your firm?
____ Yes ____ No
6.7. Within the past five (5) years, has the Bidder been required to pay either back wages or
penalties for the Bidder’s failure to comply with California prevailing wage laws? This
question refers only to the Bidder’s violation of prevailing wage laws, not to violations of the
prevailing wage laws by a subcontractor to the Bidder.
____ Yes ____ No
If ”yes,” on a separate attachment: (i) describe each instance of prevailing wage rate violation;
(ii) identify the project on which a prevailing wage rate violation occurred; (iii) the public agency
owner of the project; (iv) the number of employees affected by each prevailing wage rate
violation; and (v) amount of back wages and penalties the Bidder was required to pay.
6.8. Within the past five (5) years, has there been more than one occasion in which the Bidder
was penalized or required to pay back wages for failure to comply with the Federal DavisBacon prevailing wage requirements?
____ Yes ____ No
If ”yes,” on a separate attachment: (i) describe each instance of prevailing wage rate violation;
(ii) identify the project on which a prevailing wage rate violation occurred; ((iii) the number of
employees affected by each prevailing wage rate violation; and (iv) amount of back wages and
penalties the Bidder was required to pay.
6.9. Within the past five (5) years, has the Bidder been found to have violated any provision of
California apprenticeship laws or regulations, or the laws pertaining to use of apprentices on
public works projects?
____ Yes ____ No
If “yes,” provide the date(s) of such findings, and attach copies of the Department’s
final decision(s).
7. Accuracy and Authority. The undersigned is duly authorized to execute this Statement of
Qualifications under penalty of perjury on behalf of the above-identified Bidder. The undersigned
warrants and represents that he/she has personal knowledge of each of the responses to this
Statement of Qualifications and/or that he/she has conducted all necessary and appropriate
inquiries to determine the truth, completeness and accuracy of responses to this Statement of
Qualifications. The undersigned declares and certifies that the responses to this Statement of
Qualifications are complete and accurate; there are no omissions of material fact or information
Page 6
Section 00 45 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
that render any response to be false or misleading and there are no misstatements of fact in any
of the responses. The above-identified Bidder acknowledges and agrees that if the District
determines that any response herein is false or misleading or contains misstatements of fact so as
to be false or misleading, the Bidder’s Bid Proposal may be rejected by the District for nonresponsiveness.
Executed this___ day of __________________ 20__ at_____________________________.
(City and State)
I declare under penalty of perjury under California law that the foregoing is true and correct.
By:
____________________________________________
(Signature of Bidder’s Authorized Officer or Representative)
____________________________________________
(Typed or Printed Name)
Title:
___________________________________________
Page 7
Section 00 45 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
THIS PAGE INTENTIONALLY BLANK
Page 8
Section 00 45 13
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
SECTION 011000
SUMMARY OF WORK
1.01
WORK REQUIRED BY CONTRACT DOCUMENTS
A.
Description:
1.
The Monterey Peninsula College, Art Department Modernization: Buildings 1 and 30 project
consists of the renovation and remodeling of the existing Art Studio and Art Ceramics Buildings.
2.
The Contractor shall be responsible for scheduling and coordinating the work with the MPC Staff,
Representatives, and contractors on other MPC projects working concurrent with this project.
Reference paragraph 1.04 of this section.
3.
The work to be done includes all labor, tools and equipment necessary to furnish and install all
materials and equipment shown on the drawings and described herein and to perform tests
described herein, to provide complete and operating systems to the extent specified and shown
on the drawings. The Contractor shall furnish all equipment, material and supplies, except where
specifically noted as existing or supplied by the District.
B.
Location of Work: The project occupies a portion of Monterey Peninsula College’s property at 980
Fremont Street, Monterey, CA 93940
C.
Limits of Work:
As shown on Drawings.
1.02
SUBSTANTIAL COMPLETION
Substantial Completion shall only be applicable to the entire Work.
1.03
FUTURE WORK
Reference sub section 1.04
1.04
1.05
WORK SEQUENCE OR PHASING
A.
The Work shall be one continuous project, both buildings and site work must be completed within the
contract time.
B.
The Site work North of Building 1 will be started on June 9th 2014.
C.
Site Fencing is to be deliver and placed August 19th, 2013, it is to include Green screen netting for the
duration of the project, and as necessary will be driven post or concrete foot instead of “H” foot for the
safety. A fencing plan will be submitted and approved before fencing is placed. The Fencing may be
required to be relocated throughout the project and costs associated must be included in the bid
D.
Hazardous Material Abatement contractor will be contracted directly through the district. Abatement work
will be mostly complete before construction starts some work will have to be done after Contractor starts
work due to access. Protection of the building from weather is the general contractors responsibility.
SITE ACCESS
Section 011000
Pg. 1
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
1.06
1.07
A.
All construction vehicles and material/equipment deliveries shall access the work area using main roads.
Contractors and their workers must at all times display a parking permit provided by the owner. Contractor
parking will be coordinated with District’s representative and may not be directly at the work site.
B.
Sequence all construction, including connections to existing utilities to preserve the following: existing site
access, circulation, and use adjacent to the Site (access must be paved, lighted, and uninterrupted).
CONTRACTOR'S USE OF PROJECT SITE
A.
Contractor's use of the Project site for work, staging, and storage is strictly to be coordinated with the
construction manager and owner.
B.
Coordinate use of premises under direction of the District's Representative or Construction Manager.
Cooperate with the District to minimize conflict and to facilitate the District's on-going operations and
activities on and about the site.
C.
Cooperate with other contractors to facilitate work to be done within Limits of Work under the Contract.
Access on major roads and access right-of-way is to be shared with other contractors. All weather
access is to be adequately maintained for all major roads and right-of-ways within the Project Limits of
Work.
D.
Contractor shall provide and maintain all fencing, barricades, guard rails, bridges, warning signs, lights,
paved paths, and the like as are necessary to protect Contractor’s own personnel, MPC staff and student,
and outside public from the work site.
E.
Contractor shall be responsible for protection and safekeeping of products furnished under the Contract
that are stored within Limits of Work.
F.
Move products stored under the Contractor's control that interfere with operations of the District.
G.
Stockpiling of materials, storage of equipment, trailers and other appurtenances related to construction
operations will be limited to specific locations to be approved by the District’s Representative or the
District’s Construction Manager in their sole reasonable discretion.
H.
Note that construction operations within drip lines of existing trees are restricted. Refer to Section
015639 for requirements.
I.
All areas within Limits of Work that do not require specific work shall be returned to the District at
completion of the Project in same condition as received by the Contractor; the Contractor shall repair,
replace or correct any condition within the area of the Limits of Work that are damaged, destroyed or
altered during performance of the Work to the condition(s) existing immediately prior to the Contractor’s
commencement of Work.
J.
Disagreements between Contractor and other contractors about concurrent use of work areas or access
to the site that are not resolved by the participants shall be referred to the District's Representative.
Contractor shall agree to abide by the District Representative's determination as to concurrent use or
priority of access and to perform its work in compliance with the District Representative's resolution at no
additional cost to the District.
K.
The Limits of Work shall not be used for stockpiling or storage of materials, equipment, trailers, and other
appurtenances not related to the construction operations of this Project without written approval from the
District's Representative. Reference paragraph G above.
L.
All material and equipment deliveries shall be made only to the Project site. The District’s receiving
personnel will not accept any material and equipment for this project that is received at the District’s
warehouse or other facilities.
CONDUCT OF THE CONTRACTOR'S PERSONNEL
A.
The Contractor shall at all times maintain discipline among personnel employed at or having business at
the Project site, including during meal and break periods. The Contractor shall act promptly to correct
Section 011000
Pg. 2
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
conduct which the District's Representative and/or The Construction Manager deems intimidating,
offensive, or hostile to the District's personnel, students, and visitors; such as: whistling or staring at,
calling to, or commenting on persons passing the site (whether intended as complimentary or offensive);
making obscene gestures; making or displaying offensive drawings, graffiti, or photographs; making
propositions or invitations for dates or sex; or making racially, sexually, or ethnically related remarks or
jokes. The Contractor shall inform all new personnel of this policy.
1.08
B.
In the event that any Contractor’s employee initiates such unwarranted or unwanted interaction, or utilizes
profanity or offensive Language, the Contractor shall, either upon the request of the District, Construction
Manager, or on its own initiative, replace the employee with another of equivalent skill, at no additional
cost to the District.
C.
The Contractor shall be responsible to insure that its employees observe the District’s rules on Tobacco
policies. The project site has been designated as a Tobacco-free zone. No Tobacco products of any kind
are allowed on the Project site.
D.
The Contractor shall be responsible to insure that its employees do not bring to, posses at, or consume
alcoholic beverages on or near the Project site.
E.
The Contractor shall be responsible to insure that its employees are properly attired at all times. Proper
attire includes, but is not limited to, shirts, full-length pants, appropriate work shoes and boots, safety
head gear, and safety eye protection. No suggestive, offensive or sexually explicit clothing shall be worn
or displayed.
OCCUPANCY
The District's Occupancy: The District will occupy existing adjacent buildings during the entire period of
construction. Contractor shall cooperate fully with the District during construction operations to minimize conflicts
and to facilitate the District's usage. Contractor shall perform all work so as not to interfere with the District's
operations.
1.09
DISTRICT-FURNISHED ITEMS
Not Applicable.
1.10
APPLICABILITY OF ALL SECTIONS OF SPECIFICATIONS
All sections of the Specifications and Drawings are interdependent and applicable to the Project as a whole.
1.11
DIVISION OF THE SPECIFICATIONS
The Specifications are divided for convenience into sections as set forth in the Table of Contents. The actual
limitation of work in the various trades and/or sections of the Specifications are the responsibility of Contractor.
1.12
START OF WORK
The Contractor shall commence Work as of the date set forth in the Notice to Proceed issued by or on behalf of
the District to the Contractor. The Contract Time shall be computed from the date for commencement of Work set
forth in the Notice to Proceed issued by or on behalf of the District; the Contract Time will not be extended or
otherwise adjusted if the Contractor does not commence Work as of the date established in the Notice to Proceed
for commencement of the Work.
1.13
SURROUNDING SITE CONDITION SURVEY
Prior to commencing the Work, Contractor, the District, and the District's Representative shall tour the Project site
together to examine and record damage to existing adjacent buildings, curbs, roads, paved parking areas, and other
structures and improvements. This record shall serve as a basis for determination of subsequent damage due to
Contractor's operations and shall be signed by all parties making the tour. Any cracks, sags, or damage to existing
adjacent buildings, curbs, roads, paved parking areas, and other structures and improvements not noted in the
Section 011000
Pg. 3
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
original survey, but subsequently discovered, shall be reported to the District's Representative.
1.14
EXAMINATION OF THE SITE AND VERIFICATION OF CONDITIONS
Contractor shall examine the site and become acquainted with the conditions under which the Work is to be
carried out. Upon submitting Contractor's bid, Contractor shall be held to have made such examination, and no
allowance for extras will be allowed for any error or oversight resulting from Contractor's unfamiliarity with the site
or existing conditions. Contractor shall obtain accurate field dimensions of all related areas, spaces, openings,
levels, and items of adjacent work and, before commencing work, report to the District, in writing, via the District's
Representative, all discrepancies between the Contract Documents and the actual field conditions.
Commencement of work by Contractor shall constitute acceptance of all existing conditions affecting the work.
1.15
INTENT OF THE CONTRACT DOCUMENTS
The intent is to provide the District with a Project that is complete in all respects as described in these Contract
Documents. All Work, labor, materials, equipment, services or items necessary or reasonably required are to be
provided to produce a complete and operational Project are deemed included within the Contract Price and shall
be completed within the Contract Time.
1.16
ORDER OF PRECEDENCE
A.
1.17
The order of precedence of the documents set forth below will be used by the District's Representative to;
(1) define the intent and meaning of the Contract Documents; (2) resolve apparent inconsistencies in
Submittals and Contract Documents; (3) determine the adequacy and completeness of Contractor's
submittals; (4) determine the acceptability of construction; and (5) determine entitlement to extra
compensation:
1.
Modifications
2.
The Agreement
3.
Addenda
4.
Special Conditions
5.
Division 1, General Requirements
6.
General Conditions
7.
Technical Specifications
8.
Drawings
9.
Standard Specifications
10.
Standard Drawings
11.
Submittals (as favorably reviewed)
INTERPRETATION OF CONTRACT DOCUMENTS
Should Contractor find discrepancies in, or omissions from the Drawings or Specifications, or should the
Contractor be in doubt as to their meaning, the Contractor shall at once notify the District's Representative in
writing and should it be found that the point in question is not clearly and fully set forth, a written clarification will
be issued. Neither the District's Representative nor the District will be responsible for any oral instructions.
1.18
ORAL MODIFICATIONS
It shall be distinctly understood that no oral statement of any person shall be allowed in any manner to modify any
of the Contract provisions. Changes shall be made only on written authorization of the District's Representative,
except in an emergency endangering life or property.
1.19
TRANSMITTAL
Any correspondence from one party to the other under the Contract shall be in writing, and shall be dated and
Section 011000
Pg. 4
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
signed by the party initiating such correspondence or by duly authorized representative of such party.
Correspondence and other communications relating to the Work shall be through the Construction Manager.
1.20
CORRESPONDENCE
A correspondence memo will be prepared by the Construction Manager at the commencement of work showing
routing, number of copies, and addresses of all correspondents.
1.21
1.22
1.23
1.24
COPIES OF DOCUMENTS
A.
Contractor will be furnished with Ten (10) complete sets of all Contract Documents for Contractor's
requirements as stated in the General Conditions.
B.
Contractor may obtain additional sets of the Contract Documents, at an agreed to additional cost, by
making prior arrangements through the District’s Representative.
SPECIFICATIONS AND DRAWINGS
A.
Contractor shall keep on the Project site a copy of the Contract documents, including but not limited to;
Specifications, Drawings, Responses to Requests for Information (RFI), Change Orders, and the same
shall be available at all reasonable times for inspection and use by the District's Representative and by
any other person authorized by the District's Representative. Any Drawings listed in the detail
Specifications shall be regarded as a part thereof and of the Contract. Anything mentioned in these
Specifications and not shown on the Drawings, or shown on the Drawings and not mentioned in these
Specifications, shall be of like effect as though shown or mentioned in both.
B.
It shall be the duty of Contractor to see that the provisions of these Specifications are complied with in
detail irrespective of the inspection given the work during its progress by the District's Representative or
others. Any failure on the part of Contractor to strictly comply with the requirements of the contract
documents, including without limitation the Specifications, will be sufficient cause for the rejection of the
work at any time before its acceptance and/or constitute an event of Contractor default.
C.
The District's Representative will furnish from time to time, such detail drawings, plans, profiles, and
information, as the District's Representative may consider necessary for Contractor's guidance to insure
the proper and adequate execution of the Contract. Contractor shall comply with such detail drawings,
plans, profiles and information without adjustment of the Contract Price or the Contract Time.
D.
Only favorably reviewed shop drawings and submittals shall be used in construction. Refer to Section
013300.
MANUFACTURER'S INSTRUCTIONS
A.
Where the contract documents state that products, processes, equipment or the like shall be installed or
applied in accordance with manufacturer's instructions, directions or specifications, they shall be
construed to mean that said application or installation shall be in strict accordance with printed
instructions furnished by the manufacturer of the material concerned for use under conditions similar to
those at the Project site.
B.
The manufacturer's directions do not take precedence over the Contract Drawings and Specifications.
Where such directions are in conflict with the Contract Documents, Contractor shall request in writing a
clarification from the District's Representative before proceeding with the work.
NOTICE AND SERVICE THEREOF
A.
Any notice to Contractor from the District's Representative relative to any part of this Contract
will be in writing and considered delivered and the service thereof completed, when said notice is posted,
by certified or registered mail, to the said Contractor at Contractor's last given address, or delivered in
person to the said Contractor or Contractor's authorized representative on the work.
Section 011000
Pg. 5
Monterey Peninsula College
Art Department Modernization: Buildings 1 and 30
1.25
1.26
MANAGEMENT
A.
Contractor shall designate in writing before starting Work, an authorized representative (Project Manager)
who shall have complete authority to represent and act for Contractor. This representative shall be
acceptable to the District and shall be approved by the District's Representative.
B.
Contractor shall designate in writing before starting Work, an authorized representative (Superintendent,
as per General Conditions). This representative shall be acceptable to the District and shall be approved
by the District's Representative. Said authorized representative shall be present at the site of the Work at
all times while Work is actually in progress on the Contract, and during periods when Work is suspended,
arrangements acceptable to the District shall be made for any emergency work that may be required.
C.
If such approval, as noted above for the Project Manager and Superintendent, shall be withdrawn by the
District's Representative, Contractor shall, as soon as is practicable after having received written notice of
such withdrawal, remove the representative(s) from the Project and shall not thereafter employ that
person as Contractor's representative(s) on the Project. Contractor shall replace said representative(s)
with another representative acceptable to the District and approved by the District's Representative as
specified above.
PAYMENT FOR PATENTS AND PATENT INFRINGEMENT
All fees or claims for any patented invention, article or arrangement that may be used upon or any manner
connected with the performance of the Work or any part thereof shall be included in the price bid for doing the
work, and Contractor and Contractor's sureties shall protect and hold the District's Representative, and the
District, together with all their officers, agents and employees, harmless against liability of any nature or kind for
any and all costs, legal expenses, and demands made for such fees or claims and against any and all suits and
claims brought or made by the holder of any invention or patent, or growing out of any use or alleged infringement
of any invention or patent, or on account of any patented or unpatented invention, process, article, or appliance
manufactured for or used in the performance of the Contract, including its use by the District, unless otherwise
specifically stipulated in the Contract. Before final payment is made on the Contract, Contractor shall furnish
acceptable proof to the District of a proper release from such fees or claims.
1.27
RELEASE
The acceptance by Contractor of the final payment made under the terms of the Contract shall operate as, and
shall be as a release to the District, the District's Representative and their duly authorized agents, from all claim of
and/or liability to Contractor for anything done or furnished for, or in relation to, the Work or for any act or neglect
of the District or any person related to or affecting the Work.
1.28
CLEANING
Contractor shall clean up the Project and construction area such that the Project site is kept continuously clean.
The Contractor is required to maintain at least one (1) dumpster adequately sized for general use as well as trash
receptacles as necessary on the Project site. The Contractor shall dispose of all debris in accordance with
Section 013500 and Section 015000.
1.29
UNAUTHORIZED INTERACTION WITH DISTRICT STAFF
Any unauthorized interaction with the District’s staff, faculty, and students shall be documented in
writing and submitted to the District’s Representative within 24 hours of the interaction. Any items, conflicts, or
issues raised during this interaction must be referred to the District’s Representative immediately.
END OF SECTION 011000
Section 011000
Pg. 6
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
SECTION 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS
PART 1 - GENERAL
1.1
COMMISSIONING
A.
Commissioning is a systematic process of ensuring that all building systems perform interactively
according to the design intent and the owner’s operational needs. This is achieved by beginning in
the design phase and documenting design intent and continuing through construction, acceptance
and the warranty period with actual verification of performance. The commissioning process shall
encompass and coordinate the traditionally separate functions of system documentation, equipment
startup, control system calibration, testing and balancing, performance testing and training.
B.
Commissioning during the construction phase is intended to achieve the following specific
objectives according to the Contract, documented accordingly:
1.
Verify that applicable equipment and systems are installed according to the manufacturer’s
recommendations and to industry accepted minimum standards and that they receive adequate
operational checkout by installing contractors.
2.
Verify and document proper performance of equipment and systems.
3.
Verify that O&M documentation left on site is complete.
4.
Verify that the Owner’s operating personnel are adequately trained.
C.
The commissioning process does not take away from or reduce the responsibility of the system
designers or installing contractors to provide a finished and fully functioning product.
1.2
SYSTEMS TO BE COMMISSIONED
A.
All HVAC equipment will be commissioned. Related Specification Sections are 23 XX XX (which
means all Mechanical Specifications Sections).
B.
Systems to be commissioned are (See all M sheets in contract documents)
a.
Furnaces
b.
Exhaust Fans
c.
Supply Fan
d.
Electric Heaters
e.
Kiln Exhaust Fans
f.
Ambient Air Cleaners
g.
TAB Verification
h.
Sequence of operations and mechanical control systems for all HVAC equipment
i.
Graphical interface including floor plans
1.3
ABBREVIATIONS
A.
The following are common abbreviations used in the Specifications and in the Commissioning Plan.
A/E-
Architect and design engineers
GENERAL COMMISSIONING REQUIREMENTS
FT-
Functional performance test
01 91 00 - 1
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
1.4
CA-
Commissioning authority
GC-
General contractor (prime)
CC
Controls Contractor
MC-
Mechanical contractor
CM-
Construction
Manager
owner’s representative)
Cx-
Commissioning
PM-
Project manager (of the Owner)
Cx Plan-
Commissioning Plan document
Subs-
Subcontractors to General
EC-
Electrical contractor
TAB-
Test and balance contractor
(the PC-
Prefunctional checklist
DEFINITIONS
A.
Basis of Design: The basis of design is the documentation of the primary thought processes and
assumptions behind design decisions that were made to meet the design intent. The basis of design
describes the systems, components, conditions and methods chosen to meet the intent. Some
reiterating of the design intent may be included. Basis of Design is reflected in bid documents.
B.
Commissioning Plan: An overall plan, developed after bidding that provides the structure, schedule
and coordination planning for the commissioning process per specifications and project drawings.
C.
Design Intent: A dynamic document that provides the explanation of the ideas, concepts and criteria
that are considered to be very important to the owner. It is initially the outcome of the programming
and conceptual design phases. Design Intent is reflected in bid documents.
D.
Functional Performance Test (FT): Test of the dynamic function and operation of equipment and
systems using manual (direct observation) or monitoring methods. Functional testing is the dynamic
testing of systems (rather than just components) under full operation (e.g., the chiller pump is tested
interactively with the chiller functions to see if the pump ramps up and down to maintain the
differential pressure set point). Systems are tested under various modes, such as during low cooling
or heating loads, high loads, component failures, unoccupied, varying outside air temperatures, fire
alarm, power failure, etc. The systems are run through all the control system’s sequences of
operation and components are verified to be responding as the sequences state. Traditional air or
water test and balancing (TAB) is not functional testing, in the commissioning sense of the word.
TAB’s primary work is setting up the system flows and pressures as specified, while functional
testing is verifying that which has already been set up. The commissioning authority develops the
functional test procedures in a sequential written form, coordinates, oversees and documents the
actual testing, which is usually performed by the installing contractor or vendor. FTs are performed
after prefunctional checklists and startups are complete.
E.
General Contractor (GC): The prime contractor for this project. Generally refers to all the GC’s
subcontractors as well. Also referred to as the Contractor, in some contexts.
F.
Prefunctional Checklist (PC): A list of items to inspect and elementary component tests to conduct
to verify proper installation of equipment, provided by the CA to the Sub. Prefunctional checklists
are primarily static inspections and procedures to prepare the equipment or system for initial
operation (e.g., belt tension, oil levels OK, labels affixed, gages in place, sensors calibrated, etc.).
However, some prefunctional checklist items entail simple testing of the function of a component, a
piece of equipment or system (such as measuring the voltage imbalance on a three phase pump
motor of a chiller system). The word prefunctional refers to before functional testing. Prefunctional
GENERAL COMMISSIONING REQUIREMENTS
01 91 00 - 2
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
checklists augment and are combined with the manufacturer’s start-up checklist. Even without a
commissioning process, contractors typically perform some, if not many, of the prefunctional
checklist items a commissioning authority will recommend. However, few contractors document in
writing the execution of these checklist items. Therefore, for most equipment, the contractors
execute the checklists on their own. The commissioning authority only requires that the procedures
be documented in writing, and does not witness much of the prefunctional check listing, except for
larger or more critical pieces of equipment.
G.
1.5
Sampling: Functionally testing only a fraction of the total number of identical or near identical
pieces of equipment.
COMMISSIONING TEAM
A.
1.6
The members of the commissioning team consist of the Commissioning Authority (CA), the Project
Manager (PM), the designated representative of the owner’s Construction Management firm (CM),
IOR (inspector of Record), the General Contractor (GC or Contractor), the architect and design
engineers (particularly the mechanical engineer), the Mechanical Contractor (MC), the Electrical
Contractor (EC), the TAB representative, the Controls Contractor (CC), any other installing
subcontractors or suppliers of equipment.
If known, the Owner’s building or plant
operator/engineer is also a member of the commissioning team.
COMMISSIONING AUTHORITY’S RESPONSIBILITIES
A.
The CA is hired by the Owner. The CA directs and coordinates the commissioning activities and is
part of the CM team. All members work together to fulfill their contracted responsibilities and meet
the objectives of the Contract Documents.
B.
The CA will provide the initial schedule of primary commissioning events at the commissioning
scoping meeting during construction phase.
C.
The primary role of the CA is to develop and coordinate the execution of a testing plan, observe and
document performance—that systems are functioning in accordance with the documented design
intent and in accordance with the Contract Documents. The Contractors will provide all tools or the
use of tools to start, check-out and functionally test equipment and systems.
D.
Construction and Acceptance Phase
1.
2.
3.
4.
5.
6.
7.
Coordinates and directs the commissioning activities in a logical, sequential and efficient
manner using consistent protocols and forms, centralized documentation, clear and regular
communications and consultations with all necessary parties, frequently updated timelines
and schedules and technical expertise.
Plan and conduct a commissioning scoping meeting and other commissioning meetings.
Write and distribute prefunctional checklists.
Develop an enhanced start-up and initial systems checkout plan with Subs.
Approve prefunctional checklists completion by reviewing prefunctional checklist reports
and by selected site observation and spot checking.
Review TAB execution plan.
Oversee sufficient functional testing of the control system and approve it to be used for TAB,
before TAB is executed.
GENERAL COMMISSIONING REQUIREMENTS
01 91 00 - 3
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
8.
9.
10.
11.
12.
1.7
Coordinate witness and approve manual functional performance tests performed by installing
contractors. Coordinate retesting as necessary until satisfactory performance is achieved.
Review equipment warranties to ensure that the Owner’s responsibilities are clearly defined.
Oversee and approve the training of the Owner’s operating personnel.
Review and approve the preparation of the O&M manuals.
Provide a final commissioning report (as described in this section).
MECHANICAL AND ELECTRICAL DESIGNERS/ENGINEERS’ RESPONSIBILITIES
A.
Construction and Acceptance Phase
1.
2.
3.
4.
1.8
Perform normal submittal review, construction observation, as-built drawing preparation,
etc., as contracted. One site observation should be completed just prior to system startup.
The designers shall assist (along with the contractors) in clarifying the operation and control
of commissioned equipment in areas where the specifications, control drawings or equipment
documentation is not sufficient for writing detailed testing procedures.
Participate in the resolution of system deficiencies identified during commissioning,
according to the contract documents.
Prepare and submit the final as-built design intent and operating parameters documentation
for inclusion in the O&M manuals. Review and approve the O&M manuals.
CONSTRUCTION MANAGER—OWNER’S REPRESENTATIVE (CM)
A.
Construction and Acceptance Phase
1.
2.
3.
4.
5.
6.
1.9
Facilitate the coordination of the commissioning work by the CA, and, with the GC and CA,
ensure that commissioning activities are being scheduled into the master schedule.
Review and approve the final Commissioning Plan—Construction Phase.
Attend a commissioning scoping meeting and other commissioning team meetings.
Review and approve the functional performance test procedures submitted by the CA, prior to
testing.
Observe and witness prefunctional checklists, startup and functional testing of selected
equipment.
Assist the GC in coordinating the training of owner personnel.
GENERAL CONTRACTOR (GC) AND SUBS
A.
Construction and Acceptance Phase
1.
2.
3.
4.
Facilitate the coordination of the commissioning work by the CA, and with the GC and CA
ensure that commissioning activities are being scheduled into the master schedule.
Include the cost of commissioning in the total contract price.
Assign one person (commissioning coordinator) to coordinate and facilitate the
commissioning activities with CA and subs. This person shall have experience in HVAC
commissioning and procedures. Submit commissioning coordinator qualifications to CA.
Furnish a copy of all construction documents, addenda, change orders and approved
submittals and shop drawings related to commissioned equipment to the CA.
GENERAL COMMISSIONING REQUIREMENTS
01 91 00 - 4
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
5.
6.
7.
8.
9.
10.
B.
Warranty Period
1.
C.
In each purchase order or subcontract written, include requirements for submittal data, O&M
data, commissioning tasks and training.
Ensure that all Subs execute their commissioning responsibilities according to the Contract
Documents and schedule.
A representative shall attend a commissioning scoping meeting and other necessary meetings
scheduled by the CA to facilitate the Cx process.
Coordinate the training of owner personnel.
Prepare O&M manuals, according to the Contract Documents, including clarifying and
updating the original sequences of operation to as-built conditions.
Coordinate factory start-up events in construction schedule
Ensure that Subs correct deficiencies and make necessary adjustments to O&M manuals and
as-built drawings for applicable issues identified in any seasonal testing.
CONTRACTOR RESPONSIBILITIES
1.
Construction Phase
1)
Include Cx requirements in price and plan for work
2)
Attend coordination meetings called by CA
3)
Remedy any deficiencies identified throughout construction
4)
Prepare and submit required draft forms and systems information. TAB shall
submit sample balancing forms.
5)
Thoroughly complete and inspect installation of systems and equipment as
detailed throughout Contract Documents, as required by reference or industry
standards.
6)
Start-up, test, adjust, and balance systems and equipment prior to verification
and performance testing by the Commissioning Authority. Start-up procedures
shall be in accordance with Contract Documents, reference or industry
standards.
7)
Record start-up and testing procedures on start-up forms or checklists and
certify that the systems and equipment have been started and or tested in
accordance with the requirements specified above. Each form shall be signed
and dated by the individual responsible for the start-up or test. Tag equipment
started with individuals name and date.
8)
Complete approved start up checklists and submit along with other installation
certification information such as balancing reports, warrantees, testing results,
etc.
9)
Schedule and coordinate Cx efforts required by appropriate subs and vendors.
Participate in respective portions of start ups and training
10) Demonstrate the systems as specified
11) Certify that systems have been installed and are operating per Contract
Documents.
12) Maintain an updated set of record documentation
13) Copy Commissioning Authority on indicated documentation such as factory
start-up tests and documentation.
14) Conduct equipment specific operation, maintenance, diagnosis, and repair
training as required by the respective section of the specifications.
2.
Acceptance Phase
1)
Assist Commissioning Authority in verification and performance testing.
Assistance will generally include the following:
GENERAL COMMISSIONING REQUIREMENTS
01 91 00 - 5
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
a)
b)
3.
1.10
Manipulate systems and equipment to facilitate testing
Provide instrumentation necessary for verification and performance
testing
c)
Manipulate control systems to facilitate verification and performance
testing
d)
Provide a TAB technician to work at the direction of Commissioning
Authority for up to 8 hours per building beyond assistance specified.
e)
Provide a Control Contractor to work at the direction of Commissioning
Authority for up to 8 hours beyond assistance specified above.
2)
Correct any work not in accordance with Contract Documents.
3)
Participate in the systems and operational training relative to use of O&M
information and the Preventive Maintenance program
4)
Compensate Commissioning Authority for site time necessitated by
incompleteness of systems or equipment at time of functional performance
testing.
Warranty Phase
1)
Provide warranty service
2)
Correct any deficiencies identified
3)
Update record documentation to reflect any changes made throughout the
Warranty Phase
COMMISSIONING DOCUMENTATION
A.
Commissioning Plan: It will be provided in first commissioning scope meeting. The commissioning
plan provides guidance in the execution of the commissioning process. Just after the initial
commissioning scoping meeting the CA will update the plan which is then considered the “final”
plan, though it will continue to evolve and expand as the project progresses. The Specifications will
take precedence over the Commissioning Plan.
B.
Commissioning Report: A final summary report by the CA will be provided to the Owner/ CM. The
report will focus on evaluating commissioning process issues. All acquired documentation, logs,
reports, deficiency lists, findings, unresolved issues, etc., will be provided with the summary report.
1.11
COORDINATION
A.
Management: The CA is hired by the Owner. The CA directs and coordinates the commissioning
activities and is part of the CM team. All members work together to fulfill their contracted
responsibilities and meet the objectives of the Contract Documents
B.
Scheduling: The CA will work with the CM and GC according to established protocols to schedule
the commissioning activities. The CA will provide sufficient notice to the CM and GC for
scheduling commissioning activities. The GC will integrate all commissioning activities into the
master schedule. All parties will address scheduling problems and make necessary notifications in a
timely manner in order to expedite the commissioning process. The CA will provide the initial
schedule of primary commissioning events at the commissioning scoping meeting. The
Commissioning Plan provides a format for this schedule. As construction progresses, more detailed
schedules are developed by the CA and GC.
C.
Meetings
GENERAL COMMISSIONING REQUIREMENTS
01 91 00 - 6
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
1.
Scoping Meeting: Within 120 days of commencement of construction (after all the HVAC
submittals are approved), the CA will schedule, plan and conduct a commissioning scoping
meeting with the entire commissioning team in attendance. Meeting minutes will be
distributed to all parties by the CA. Information gathered from this meeting will allow the CA
to revise the Draft 2 Commissioning Plan to its “final” version, which will also be distributed
to all parties.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1
COMMISSIONING PROCESS
A.
The following narrative provides a brief overview of the typical commissioning tasks during
construction and the general order in which they occur:
1.
2.
3.
4.
5.
6.
7.
8.
Commissioning during construction begins with a scoping meeting conducted by the CA
where the commissioning process is reviewed with the commissioning team members.
Equipment documentation is submitted to the CA during normal submittals, including
detailed start-up procedures and O&M manuals in one three ring binder.
The CA works with the Subs in developing startup plans and startup documentation formats,
including providing the Subs with prefunctional checklists to be completed, during the startup
process.
In general, the checkout and performance verification proceeds from simple to complex; from
component level to equipment to systems and intersystem levels with prefunctional checklists
being completed before functional tests.
The Subs, under their own direction, execute and document the prefunctional checklists and
perform startup and initial checkout. The CA documents that the checklists and startup were
completed according to the approved plans. This may include the CA witnessing start-up of
selected equipment.
The CA develops specific equipment and system functional performance test procedures.
The Subs review the procedures.
The procedures are executed by the Subs, under the direction of, and documented by the CA.
Items of non-compliance in material, installation or setup are corrected at the Sub’s expense
(including the CA’s time) and the system retested. The General Contractor is responsible for
collecting cost and expenses for retesting. Retesting will be charged to contractor minimum 4
hours of standard hourly rates of CA.
a.
Cost of Retesting
1)
The cost for the Sub to retest a prefunctional or functional test, if they are
responsible for the deficiency, shall be theirs. If they are not responsible, any
cost recovery for retesting costs shall be GC.
2)
For a deficiency identified, not related to any prefunctional checklist or start-up
fault, the following shall apply: The CA and CM will direct the retesting of the
equipment once at no “charge” to the GC for their time. However, the CA’s and
CM’s time for a second retest will be charged to the GC, who may choose to
recover costs from the responsible Sub.
GENERAL COMMISSIONING REQUIREMENTS
01 91 00 - 7
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
3)
9.
10.
11.
12.
B.
The time for the CA and CM to direct any retesting required because a specific
prefunctional checklist or start-up test item, reported to have been successfully
completed, but determined during functional testing to be faulty, will be back
charged to the GC, who may choose to recover costs from the party responsible
for executing the faulty prefunctional test.
The CA reviews the O&M documentation for completeness.
Commissioning is completed before Substantial Completion.
The CA reviews, pre-approves and coordinates the training provided by the Subs and verifies
that is was completed.
Deferred testing is conducted, as specified or required.
Reporting
1.
The CA will provide regular reports to the Owner and Architect. Standard forms are provided
and referenced in the Commissioning Plan.
2.
The CA will regularly communicate with all members of the commissioning team, keeping
them apprised of commissioning progress and scheduling changes through memos, progress
reports, etc.
3.
Testing or review approvals and non-conformance and deficiency reports are made regularly
with the review and testing as described in later sections.
4.
A final summary report by the CA will be provided to the CM or PM (owner rep), focusing
on evaluating commissioning process issues and identifying areas where the process could be
improved. All acquired documentation will be compiled in appendices and provided with the
summary report. Prefunctional checklists, functional tests and monitoring reports will not be
part of the final report, but will be stored in the Commissioning Record in the O&M manuals
in CA’s office.
END OF SECTION 019100
GENERAL COMMISSIONING REQUIREMENTS
01 91 00 - 8
SECTION 08 71 00
DOOR HARDWARE
PART 1 - GENERAL
1.01
RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary
Conditions of Division 1 Specification Sections, apply to this Section.
1.02
SUMMARY
A. This Section includes items known commercially as finish or door hardware that are required
for swing, sliding, and folding doors, except special types of unique hardware specified in the
same sections as the doors and door frames on which they are installed.
B. This Section includes the following, but is not necessarily limited to:
1.
2.
3.
4.
Door Hardware, including electric hardware.
Storefront and Entrance door hardware.
Thresholds, gasketing and weather-stripping.
Door silencers or mutes.
C. Related Sections: The following sections are noted as containing requirements that relate to
this Section, but may not be limited to this listing.
1.
2.
3.
4.
1.03
Division 8: Section - Steel Doors and Frames.
Division 8: Section - Wood Doors.
Division 8: Section - Aluminum Storefront
Division 28: Section - Fire/Life-Safety Systems & Security Access Systems.
REFERENCES (Use date of standard in effect as of Bid date.)
A. ADAAG - Americans with Disabilities Act (ACT) Accessibility Guidelines for Buildings and
Facilities.
B. BHMA - Builders' Hardware Manufacturers Association.
C. DHI - Door and Hardware Institute.
D. NFPA - National Fire Protection Association.
1. NFPA 80 - Fire Doors and Windows
2. NFPA 101 - Life Safety Code
3. NFPA 105 - Smoke and Draft Control Door Assemblies
E. CBC 2010 - California Building Code.
F. UL - Underwriters Laboratories.
1. UL 10C - Fire Tests of Door Assemblies
2. UL 305 - Panic Hardware
G. WHI - Warnock Hersey Incorporated
Monterey Peninsula College
Door Hardware
Art Department Modernizations
Buildings 1 & 30
Section 08 71 00-1
H. SDI - Steel Door Institute
1.04
SUBMITTALS & SUBSTITUTIONS
A. General: Submit in accordance with Conditions of the Contract and Division 1 Specification
sections.
B. Submit product data (catalog cuts) including manufacturers' technical product information for
each item of door hardware, installation instructions, maintenance of operating parts and
finish, and other information necessary to show compliance with requirements.
C. Submit six (6) copies of schedule organized vertically into “Hardware Sets” with index of
doors and headings, indicating complete designations of every item required for each door or
opening. Include following information:
1.
2.
3.
4.
5.
6.
7.
8.
Type, style, function, size and finish of each hardware item.
Name, part number and manufacturer of each item.
Fastenings and other pertinent information.
Location of hardware set coordinated with floor plans and door schedule.
Explanation of all abbreviations, symbols and codes contained in schedule.
Mounting locations for hardware.
Door and frame sizes and materials.
List of manufacturers used and their nearest representative with address and phone
number.
9. Keying information.
D. Make substitution requests in accordance with Division 1. Substitution requests must be
made prior to bid date. Include product data and indicate benefit to the project. Furnish
samples of any proposed substitution.
E. Keying Schedule: Submit separate detailed schedule indicating clearly how the Owner's final
instructions on keying of locks has been fulfilled.
F. Templates for doors, frames, and other work specified to be factory prepared for the
installation of door hardware. Check shop drawings of other work to confirm that adequate
provisions are made for locating and installing door hardware to comply with indicated
requirements.
G. Furnish as-built/as-installed schedule with close-out documents, including keying schedule
and transcript, wiring/riser diagrams, manufacturers’ installation and adjustment and
maintenance information.
H. Fire Door Assembly Testing: Submit a written record of each fire door assembly to the
Owner to be made available to the Authority Having Jurisdiction (AHJ) for future building
inspections.
I.
1.05
LEED Certification Points: Submit information and certifications necessary to achieve
maximum points for LEED certification; coordinate and cooperate with Owner and Architect in
providing information necessary for required LEED rating.
QUALITY ASSURANCE
A. Obtain each type of hardware (latch and lock sets, hinges, closers, exit devices, etc.) from a
single manufacturer.
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-2
B. Supplier Qualifications: A recognized architectural door hardware supplier, with warehousing
facilities in the project's vicinity, that has a record of successful in-service performance for
supplying door hardware similar in quantity, type, and quality to that indicated for this project
and that employs an experienced architectural hardware consultant (AHC) who is available to
Owner, Architect, and Contractor, at reasonable times during the course of the Work, for
consultation.
1. Responsible for detailing, scheduling and ordering of finish hardware.
2. Meet with Owner to finalize keying requirements and to obtain final instructions in writing.
To maintain the integrity of patented key systems provide a letter of authorization from
the specified manufacturer indicating that supplier has authorization to purchase the key
system directly from the manufacturer.
3. Stock parts for products supplied and be capable of repairing and replacing hardware
items found defective within warranty periods.
C. Hardware Installer: Company specializing in the installation of commercial door hardware
with five years documented experience.
D. Fire-Rated Openings: Provide door hardware for fire-rated openings that complies with
NFPA Standard No. 80 and requirements of authorities having jurisdiction. Provide only
items of door hardware that are listed and tested by UL or Warnock Hersey for given
type/size opening and degree of label. Provide proper latching hardware, door closers,
approved-bearing hinges and seals whether listed in the Hardware Schedule or not.
1. Where emergency exit devices are required on fire-rated doors, (with supplementary
marking on doors' UL labels indicating "Fire Door to be Equipped with Fire Exit
Hardware") provide UL label on exit devices indicating "Fire Exit Hardware".
E. Exit Doors: Operable from inside with single motion without the use of a key or special
knowledge or effort.
1.06
DELIVERY, STORAGE AND HANDLING
A. Coordinate delivery of packaged hardware items to the appropriate locations (shop or field)
for installation.
B. Hardware items shall be individually packaged in manufacturers’ original containers,
complete with proper fasteners. Clearly mark packages on outside to indicate contents and
locations in hardware schedule and in work.
C. Provide locked storage area for hardware, protect from moisture, sunlight, paint, chemicals,
etc.
D. Inventory door hardware jointly with representatives of hardware supplier and hardware
installer until each is satisfied that count is correct.
1.07
WARRANTY
A. Provide warranties of respective manufacturers’ regular terms of sale from day of final
acceptance as follows:
1. Closers: Ten (10) years, except electronic closers shall be two (2) years.
2. Exit devices: Three (3) years.
3. All other hardware: Two (2) years.
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-3
1.08
MAINTENANCE
A. Maintenance Tools and Instructions: Furnish a complete set of specialized tools and
maintenance instructions as needed for Owner's continued adjustment, maintenance, and
removal and replacement of door hardware.
1.09
PRE-INSTALLATION CONFERENCE
A. Convene a pre-installation conference at least one week prior to beginning work of this
section.
B. Attendance: Architect, Construction Manager, Contractor, Hardware Supplier, Installer, Key
College District Personnel, and Project Inspector.
C. Agenda: Review hardware schedule, products, installation procedures and coordination
required with related work. Review College District keying requirements.
PART 2 - PRODUCTS
2.01
2.02
MANUFACTURERS
Item
Manufacturer
Acceptable Substitutes
A.
Hinges
Ives
Hager, Stanley
B.
Locks, Latches
& Cylinders
Schlage
None
C.
Exit Devices
Von Duprin
None
D.
Closers
LCN
None
E.
Push, Pulls
& Protection Plates
Ives
Trimco, BBW, Quality
F.
Flush Bolts
Ives
Trimco, BBW, Quality
G.
Dust Proof Strikes
Ives
Trimco, BBW, Quality
H.
Coordinators
Ives
Trimco, BBW, Quality
I.
Stops
Ives
Trimco, BBW, Quality
J.
Overhead Stops
Glynn-Johnson
None
K.
Thresholds
National Guard
Pemko, Zero
L.
Seals & Bottoms
National Guard
Pemko, Zero
MATERIALS
A. Hinges: Exterior out-swinging door butts shall be non-ferrous material and shall have
stainless steel hinge pins. All doors to have non-rising pins.
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-4
1. Hinges shall be sized in accordance with the following:
a. Height:
1) Doors up to 41" wide: 4-1/2" inches.
2) Doors 42" to 48" wide: 5 inches.
b. Width: Sufficient to clear frame and trim when door swings 180 degrees.
c. Number of Hinges: Furnish 3 hinges per leaf to 7'-5" in height. Add one for each
additional 2 feet in height.
2. Furnish non-removable pins (NRP) at all exterior out-swing doors and interior key lock
doors with reverse bevels.
B. Continuous Hinges: As manufactured by Ives, an Ingersoll-Rand Company. UL rated as
required.
C. Extra Heavy duty Commercial Mortise Locks: Schlage “L” Series as scheduled with “03”
Style Lever and “A” Style Rose. All cylinders to be interchangeable core.
1. Locksets to comply with ANSI A156.13, Series 1000, Operational Grade 1 and Security
Grade 1 with all standard trims. Locksets shall also comply with UL10C and UBC 7-2
Positive Pressure requirements
2. Lock case shall be manufactured with heavy 12 gauge steel with fully wrapped design.
Lock cases with exposed edges are not acceptable. Lock case shall be multi-functional
allowing transformation to a different function without opening lock case.
3. Latchbolt shall have ¾” throw and be non-handed, field reversible without opening the
lock case. Solid latchbolts and / or plastic anti-friction devices are not acceptable.
4. The deadbolt, when used, shall be 1” throw stainless steel with a ¾” internal engagement
when fully extended.
5. All trim shall be through-bolted with the spring cages supporting the trim attached to the
lock cases to prevent torquing.
6. Levers to have independent rotation in both directions. Exterior lever assembly to be
one-piece design attached by threaded bushing. Interior lever assembly shall be
attached by screwless shank
7. Thru-bolt lever assemblies through the door for positive interlock. Locks using a through
the door spindle for attachment are not acceptable. Spindles shall be independent,
designed to “break-away” at a maximum of 75psi torque.
8. Hand of lock chassis to be changeable by simply moving one screw from one side to the
case to the other and pulling and reversing the latchbolt.
9. Cylinders to be secured by a cast stainless steel, dual retainer. Locks utilizing screws
and / or stamped retainers are not acceptable.
D. Exit devices: Von Duprin as scheduled.
1. Provide certificate by independent testing laboratory that device has completed over
1,000,000 cycles and can still meet ANSI/BHMA A156.3 - 2001 standards.
2. All internal parts shall be of cold-rolled steel with zinc dichromate coating.
3. Mechanism case shall have an average thickness of .140".
4. Compression spring engineering.
5. Non-handed basic device design with center case interchangeable with all functions.
6. All devices shall have quiet return fluid dampeners.
7. All latchbolts shall be deadlocking with ¾” throw and have a self-lubricating coating to
reduce friction and wear.
8. Device shall bear UL label for fire and or panic as may be required.
9. All surface strikes shall be roller type and utilize a plate underneath to prevent
movement.
10. All Exit Devices to be sex-bolted to the doors.
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-5
11. Panic Hardware shall comply with CBC Section 1008.1.9 and shall be mounted between
30" and 44" above the finished floor surface. The unlatching force shall not exceed 15
lbs. applied in the direction of travel.
E. Closers: LCN as scheduled. Place closers inside building, stairs, room, etc.
1. Door closer cylinders shall be of high strength cast iron construction with double heat
treated pinion shaft to provide low wear operating capabilities of internal parts throughout
the life of the installation. All door closers shall be tested to ANSI/BHMA A156.4 test
requirements by a BHMA certified testing laboratory. A written certification showing
successful completion of a minimum of 10,000,000 cycles must be provided.
2. All door closers shall be fully hydraulic and have full rack and pinion action with a shaft
diameter of a minimum of 11/16 inch and piston diameter of 1 inch to ensure longevity
and durability under all closer applications.
3. All parallel arm closers shall incorporate one piece solid forged steel arms with bronze
bushings. 1-9/16” steel stud shoulder bolts, shall be incorporated in regular arms, holdopen arms, arms with hold open and stop built in. All other closers to have forged steel
main arms for strength, durability, and aesthetics for versatility of trim accommodation,
high strength and long life.
4. All parallel arm closers so detailed shall provide advanced backcheck for doors subject to
severe abuse or extreme wind conditions. This advanced backcheck shall be located to
begin cushioning the opening swing of the door at approximately 45 degrees. The
intensity of the backcheck shall be fully adjustable by tamper resistant non-critical screw
valve.
5. Closers shall be installed to permit doors to swing 180 degrees.
6. All closers shall utilize a stable fluid withstanding temperature range of 120 degrees F. to
-30 degrees F. without requiring seasonal adjustment of closer speed to properly close
the door.
7. Provide the manufactures drop plates, brackets and spacers as required at narrow head
rails and special frame conditions. NO wood plates or spacers will be allowed.
8. Maximum effort to operate doors shall not exceed 5 lbs., such pull or push effort being
applied at right angles to hinged doors. Compensating devices or automatic door
operators may be utilized to meet the above standards. When fire doors are required,
the maximum effort to operate the door may be increased but shall not to exceed 15 lbs.
when specifically approved by fire marshal. All closers shall be adjusted to operate with
the minimum amount of opening force and still close and latch the door. These forces do
not apply to the force required to retract latch bolts or disengage other devices that hold
the door in a closed position. Door shall take at least 5 seconds to move from an open
position of 70 degrees to a point of 3 inches from the latch jamb. Reference CBC
Sections 1133B.2.1, 1133B.2.5, 1133B2.5.1 & 1003.3.1.8.
9. Provide sex-bolted or through bolt mounting for all door closers.
F. Flush Bolts & Dust Proof Strikes: Automatic Flush Bolts shall be of the low operating force
design. Utilize the top bolt only model for interior doors where applicable and as permitted by
testing procedures.
1. Manual flush bolts only permitted on storage or mechanical openings as scheduled.
2. Provide dust proof strikes at openings using bottom bolts.
G. Door Stops:
1. Unless otherwise noted in Hardware Sets, provide wall type with appropriate fasteners.
Where wall type cannot be used, provide floor type. If neither can be used, provide
overhead type.
2. Do not install floor stops more than four (4) inches from the face of the wall or partition
(Title 24, 1133B.8.6).
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-6
3. Overhead stops shall be made of stainless steel and non-plastic mechanisms and
finished metal end caps. Field-changeable hold-open, friction and stop-only functions.
H. Protection Plates: Fabricate either kick, armor, or mop plates with four beveled edges.
Provide kick plates 10" high and 2" LDW. Sizes of armor and mop plates shall be listed in
the Hardware Schedule. Furnish with machine or wood screws of bronze or stainless to
match other hardware.
I.
Thresholds: As Scheduled and per details.
1. Thresholds shall not exceed 1/2" in height, with a beveled surface of 1:2 maximum slope.
2. Set thresholds in a full bed of butyl-rubber or polyisobutylene mastic sealant complying
with requirements in Division 7 “Thermal and Moisture Protection”.
3. Use ¼” fasteners, red-head flat-head sleeve anchors (SS/FHSL).
4. Thresholds shall comply with CBC Section 1133B.2.4.1.
J.
Seals: Provide silicone gasket at all rated and exterior doors.
1. Fire-rated Doors, Resilient Seals: UL10C / UBC Standard 7-2 compliant. Coordinate with
selected door manufacturers' and selected frame manufacturers' requirements.
2. Fire-rated Doors, Intumescent Seals: Furnished by selected door manufacturer. Furnish
fire-labeled opening assembly complete and in full compliance with UL10C / UBC
Standard 7-2. Where required, intumescent seals vary in requirement by door type and
door manufacture -- careful coordination required.
3. Smoke & Draft Control Doors, Provide UL10C / UBC Standard 7-2 compliant for use on
“S” labeled Positive Pressure door assemblies.
K. Door Shoes & Door Top Caps: Provide door shoes at all exterior wood doors and top caps at
all exterior out-swing doors.
L. Silencers: Furnish silencers for interior hollow metal frames, 3 for single doors, 2 for pairs of
doors. Omit where sound or light seals occurs, or for fire-resistive-rated door assemblies.
2.03
KEYING
A. Furnish a Grand Master, Master, keyed alike or keyed different system as directed by the
Owner or Architect. Locks are to be keyed to the College District’s Schlage “Classic Primus
Level 3G Keyway”.
B. Provide construction keying & cylinders for doors requiring locking during construction;
remove construction cylinders immediately prior to Owner occupancy. Furnish permanent
keys (and cores if applicable) directly to Owner.
C. Key Blanks: Schlage original “Classic Primus "6" pin bow key blank; tag to identify.
D. Supply keys and blanks as follows:
1. Supply 2 cut change keys for each different change key code.
2. Supply 1 uncut key blank for each change key code.
3. Supply 6 cut master keys for each different master key set.
4. Supply 3 uncut key blanks for each master key set.
2.04
FINISHES
A. Generally to be satin chrome US26D (626 on bronze and 652 on steel) unless otherwise
noted.
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-7
B. Furnish push plates, pull plates and kick or armor plates in satin stainless steel US32D (630)
unless other wise noted.
C. Door closers shall be powder-coated to match other hardware, unless otherwise noted.
D. Aluminum items to be finished anodized aluminum except thresholds which can be furnished
as standard mill finish.
2.05
FASTENERS
A. Screws for strikes, face plates and similar items shall be flat head, countersunk type, provide
machine screws for metal and standard wood screws for wood.
B. Screws for butt hinges shall be flathead, countersunk, full-thread type.
C. Fastening of closer bases or closer shoes to doors shall be by means of sex bolts and spray
painted to match closer finish.
D. Provide expansion anchors for attaching hardware items to concrete or masonry.
E. All exposed fasteners shall have a phillips head.
F. Finish of exposed screws to match surface finish of hardware or other adjacent work.
G. All Exit Devices and Lock Protectors shall be fastened to the door by the means of sex bolts
or through bolts.
PART 3 - EXECUTION
3.01
INSPECTION
A. Verify that doors and frames are square and plumb and ready to receive work and
dimensions are as instructed by the manufacturer.
B. Beginning of installation means acceptance of existing conditions.
3.02
INSTALLATION
A. Install hardware in accordance with manufacturer's instructions and requirements of DHI.
B. Use the templates provided by hardware item manufacturer.
C. Mounting heights for hardware shall be as recommended by the Door and Hardware Institute.
Operating hardware will to be located between 30" and 44" AFF.
D. Set units level, plumb and true to line and location. Adjust and reinforce the attachment
substrate as necessary for proper installation and operation.
E. Drill and countersink units that are not factory-prepared for anchorage fasteners. Space
fasteners and anchors in accordance with industry standards.
F. Set thresholds for exterior doors in full bed of butyl-rubber sealant.
G. If hand of door is changed during construction, make necessary changes in hardware at no
additional cost.
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-8
H. Hardware Installer shall coordinate with security contractor to route cable to connect
electrified locks, panic hardware and fire exit hardware to power transfers or electric hinges
at the time these items are installed so as to avoid disassembly and reinstallation of
hardware.
I.
3.03
Hardware Installer shall also be present with the security contractor when the power is turned
on for the testing of the electronic hardware applications. Installer shall make adjustments to
solenoids, latches, vertical rods and closers to insure proper and secure operation.
ADJUST AND CLEAN
A. Adjust and check each operating item of hardware and each door, to ensure proper operation
or function of every unit. Replace units which cannot be adjusted to operate freely and
smoothly as intended for the application made.
B. Clean adjacent surface soiled by hardware installation.
C. Final Adjustment: Wherever hardware installation is made more than one month prior to
acceptance or occupancy, return to that work area and make final check and adjustment of
all hardware items in such space or area. Clean operating items as necessary to restore
proper function and finish of hardware and doors. Adjust door control devices to compensate
for final operation of heating and ventilating equipment.
D. Instruct Owner's Personnel in proper adjustment and maintenance of hardware finishes,
during the final adjustment of hardware.
E. Continued Maintenance Service: Approximately six months after the completion of the
project, the Contractor accompanied by the Architectural Hardware Consultant, shall return to
the project and re-adjust every item of hardware to restore proper functions of doors and
hardware. Consult with and instruct Owner's personnel in recommended additions to the
maintenance procedures. Replace hardware items which have deteriorated or failed due to
faulty design, materials or installation of hardware units. Prepare a written report of current
and predictable problems (of substantial nature) in the performance of the hardware.
3.04
HARDWARE LOCATIONS
A. Conform to CCR, Title 24, Part 2, and ADAAG for positioning requirements for the disabled.
3.05
FIELD QUALITY CONTROL
A. Architectural Hardware Consultant (AHC) to inspect installation and certify that hardware and
it's installation have been furnished and installed in accordance with manufacturer's
instructions and as specified herein.
3.06
SCHEDULE
A. The items listed in the following schedule shall conform to the requirements of the foregoing
specifications.
B. The Door Schedule on the Drawings indicates which hardware set is used with each door.
Manufacturers Abbreviations (Mfr.)
GLY
=
Glynn-Johnson
IVE
=
Ives
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Overhead Door Stops
Hinges, Pivots, Bolts, Coordinators, Dust Proof
Door Hardware
Section 08 71 00-9
LCN
NGP
SCH
VON
=
=
=
=
LCN
National Guard Products
Schlage Lock Company
Von Duprin
Strikes, Kick Plates, Door Stops & Silencers
Door Closers
Thresholds, Gasketing & Weather-stripping
Locks, Latches & Cylinders
Exit Devices
SPECWORKS # 126248
HARDWARE GROUP: 01
2
Ea Continuous Hinge
224HD
1
Ea Mullion
KR4954 X 154 STABILIZER
1
Ea Panic Hardware
CD99EO
1
Ea Panic Hardware
CD99NL-OP
1
Ea Rim Cylinder
20-057-ICX
4
Ea Primus Core Only
20-740
1
Ea Mortise Cylinder
26-091-ICX (MULLION)
2
Ea Mortise Cylinder
26-091-ICX XQ11-948 (DOGGING)
2
Ea Offset Door Pull
8190-2-O
2
Ea Surface Closer
4111 AVB EDA
2
Ea Floor Stop & Holder
FS43
2
Ea Door Sweep
200NA
1
Ea Threshold
Per Detail
WEATHER-STRIPPING FURNISHED WITH DOOR & FRAME ASSEMBLY
628
689
626
626
626
626
626
626
630
689
626
628
AL
IVE
VON
VON
VON
SCH
SCH
SCH
SCH
IVE
LCN
IVE
NGP
NGP
628
626
626
626
626
630
689
626
628
AL
IVE
VON
SCH
SCH
SCH
IVE
LCN
IVE
NGP
NGP
630
626
626
626
626
630
689
630
626
CHA
628
IVE
VON
SCH
SCH
SCH
IVE
LCN
IVE
IVE
NGP
NGP
HARDWARE GROUP: 02
1
Ea Continuous Hinge
224HD
1
Ea Panic Hardware
CD99NL-OP
1
Ea Rim Cylinder
20-057-ICX
2
Ea Primus Core Only
20-740
1
Ea Mortise Cylinder
26-091-ICX XQ11-948 (DOGGING)
1
Ea Offset Door Pull
8190-2-O
1
Ea Surface Closer
4111 AVB EDA
1
Ea Floor Stop & Holder
FS43
1
Ea Door Sweep
200NA
1
Ea Threshold
Per Detail
WEATHER-STRIPPING FURNISHED WITH DOOR & FRAME ASSEMBLY
HARDWARE GROUP: 03
3
1
1
2
1
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Set
Ea
Hinge
Panic Hardware
Rim Cylinder
Primus Core Only
Mortise Cylinder
Door Pull
Surface Closer
Kick Plate
Floor Stop & Holder
Seals
Door Sweep
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
5BB1HW 4.5 X 4.5 NRP
CD99NL-OP
20-057-ICX
20-740
26-091-ICX XQ11-948 (DOGGING)
VR910NL
4111 AVB EDA
8400 10" X 2" LDW
FS43
5050C
200NA
Door Hardware
Section 08 71 00-10
1
Ea
Threshold
Per Detail
AL
NGP
5BB1HW 4.5 X 4.5 NRP
CD99NL-OP
20-057-ICX
20-740
26-091-ICX XQ11-948 (DOGGING)
VR910NL
4111 AVB EDA
100H
8400 10" X 2" LDW
5050C
200NA
Per Detail
630
626
626
626
626
630
689
630
630
CHA
628
AL
IVE
VON
SCH
SCH
SCH
IVE
LCN
GLY
IVE
NGP
NGP
NGP
5BB1 4.5 X 4.5 NRP
LV9080T 03A
20-740
4111 EDA
8400 10" X 2" LDW
FS43
5050C
200NA
Per Detail
630
626
626
689
630
626
CHA
628
AL
IVE
SCH
SCH
LCN
IVE
IVE
NGP
NGP
NGP
5BB1HW 4.5 X 4.5 NRP
KR4954 X 154 STABILIZER
CD99NL-OP
LD99EO
20-057-ICX
20-740
26-091-ICX (MULLION)
26-091-ICX XQ11-948 (DOGGING)
VR910NL
4111 AVB EDA
100H
8400 10" X 2" LDW
FS43
5050C
200NA
Per Detail
630
689
626
626
626
626
626
626
630
689
630
630
626
CHA
628
AL
IVE
VON
VON
VON
SCH
SCH
SCH
SCH
IVE
LCN
GLY
IVE
IVE
NGP
NGP
NGP
HARDWARE GROUP: 04
3
1
1
2
1
1
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Set
Ea
Ea
Hinge
Panic Hardware
Rim Cylinder
Primus Core Only
Mortise Cylinder
Door Pull
Surface Closer
Overhead Holder
Kick Plate
Seals
Door Sweep
Threshold
HARDWARE GROUP: 05
3
1
1
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Set
Ea
Ea
Hinge
Storeroom Lock
Primus Core Only
Surface Closer
Kick Plate
Floor Stop & Holder
Seals
Door Sweep
Threshold
HARDWARE GROUP: 06
6
1
1
1
1
3
1
1
1
2
1
2
1
1
2
1
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Set
Ea
Ea
Hinge
Mullion
Panic Hardware
Panic Hardware
Rim Cylinder
Primus Core Only
Mortise Cylinder
Mortise Cylinder
Door Pull
Surface Closer
Overhead Holder
Kick Plate
Floor Stop & Holder
Seals
Door Sweep
Threshold
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-11
HARDWARE GROUP: 07
6
1
1
1
1
3
1
1
1
2
2
2
1
2
1
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Set
Ea
Ea
Hinge
Mullion
Panic Hardware
Panic Hardware
Rim Cylinder
Primus Core Only
Mortise Cylinder
Mortise Cylinder
Door Pull
Surface Closer
Kick Plate
Floor Stop & Holder
Seals
Door Sweep
Threshold
5BB1HW 4.5 X 4.5 NRP
KR4954 X 154 STABILIZER
CD99NL-OP
LD99EO
20-057-ICX
20-740
26-091-ICX (MULLION)
26-091-ICX XQ11-948 (DOGGING)
VR910NL
4111 AVB EDA
8400 10" X 2" LDW
FS43
5050C
200NA
Per Detail
630
689
626
626
626
626
626
626
630
689
630
626
CHA
628
AL
IVE
VON
VON
VON
SCH
SCH
SCH
SCH
IVE
LCN
IVE
IVE
NGP
NGP
NGP
5BB1 4.5 X 4.5 NRP
L9056T 03A L583-363
20-740
4011
FS436/8
5050C
35VA
Per Detail
630
626
626
689
626
CHA
CL
AL
IVE
SCH
SCH
LCN
IVE
NGP
NGP
NGP
5BB1HW 4.5 X 4.5 NRP
L9070T 03A
20-740
4111 EDA
8400 10" X 2" LDW
FS18L
5050C
200NA
Per Detail
630
626
626
689
630
BLK
CHA
628
AL
IVE
SCH
SCH
LCN
IVE
IVE
NGP
NGP
NGP
HARDWARE GROUP: 08
3
1
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Set
Ea
Ea
Hinge
Office Lock
Primus Core Only
Surface Closer
Dome Stop
Seals
Door Bottom
Threshold
HARDWARE GROUP: 09
3
1
1
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Set
Ea
Ea
Hinge
Classroom Lock
Primus Core Only
Surface Closer
Kick Plate
Security Floor Stop
Seals
Door Sweep
Threshold
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-12
HARDWARE GROUP: 10
6
1
1
1
1
1
2
2
1
Ea
Set
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Hinge
Const Latching Bolt
Dust Proof Strike
Storeroom Lock
Primus Core Only
Astragal
Overhead Holder
Door Sweep
Threshold
5BB1 4.5 X 4.5 NRP
FB51P
DP1
LV9080T 03A
20-740
139SP (OR BY HM DOOR MFR)
700H
200NA
Per Detail
630
630
626
626
626
600
626
628
AL
IVE
IVE
IVE
SCH
SCH
NGP
GLY
NGP
NGP
5BB1HW 4.5 X 4.5 NRP
LV9080T 03A
20-740
700H
5050C
200NA
Per Detail
630
626
626
626
CHA
628
AL
IVE
SCH
SCH
GLY
NGP
NGP
NGP
5BB1HW 4.5 X 4.5 NRP
L9070T 03A
20-740
4111 EDA
8400 10" X 2" LDW
FS43
5050C
200NA
Per Detail
630
626
626
689
630
626
CHA
628
AL
IVE
SCH
SCH
LCN
IVE
IVE
NGP
NGP
NGP
5BB1 4.5 X 4.5
L9056T 03A L583-363
20-740
FS436/8
5050C
652
626
626
626
CHA
IVE
SCH
SCH
IVE
NGP
HARDWARE GROUP: 11
3
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Set
Ea
Ea
Hinge
Storeroom Lock
Primus Core Only
Overhead Holder
Seals
Door Sweep
Threshold
HARDWARE GROUP: 12
3
1
1
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Set
Ea
Ea
Hinge
Classroom Lock
Primus Core Only
Surface Closer
Kick Plate
Floor Stop & Holder
Seals
Door Sweep
Threshold
HARDWARE GROUP: 13
3
1
1
1
1
Ea
Ea
Ea
Ea
Set
Hinge
Office Lock
Primus Core Only
Dome Stop
Seals
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-13
HARDWARE GROUP: 14
3
1
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Set
Set
Ea
Ea
Hinge
Privacy Lock
Primus Core Only
Wall Stop
Light Seals
Seals
Door Bottom
Threshold
5BB1HW 4.5 X 4.5
L9496T 03A L583-363
20-740
WS407CVX
110SA
5050C
225N
Per Detail
652
626
626
630
CL
CHA
AL
AL
IVE
SCH
SCH
IVE
NGP
NGP
NGP
NGP
5BB1HW 4.5 X 4.5
L9080T 03A
20-740
8400 10" X 2" LDW
FS41
5050C
652
626
626
630
626
CHA
IVE
SCH
SCH
IVE
IVE
NGP
5BB1HW 4.5 X 4.5 NRP
99L-F 996L-03
20-057-ICX
20-740
4111 AVB EDA
8400 10" X 2" LDW
FS436/8
5050C
652
626
626
626
689
630
626
CHA
IVE
VON
SCH
SCH
LCN
IVE
IVE
NGP
5BB1 4.5 X 4.5
L9080T 03A
20-740
4011
8400 10" X 2" LDW
WS407CVX
5050C
652
626
626
689
630
630
CHA
IVE
SCH
SCH
LCN
IVE
IVE
NGP
HARDWARE GROUP: 15
3
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Set
Hinge
Storeroom Lock
Primus Core Only
Kick Plate
Floor Stop & Holder
Seals
HARDWARE GROUP: 16
3
1
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Set
Hinge
Fire Exit Hardware
Rim Cylinder
Primus Core Only
Surface Closer
Kick Plate
Dome Stop
Seals
HARDWARE GROUP: 17
3
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Set
Hinge
Storeroom Lock
Primus Core Only
Surface Closer
Kick Plate
Wall Stop
Seals
HARDWARE GROUP: 18
3
Ea Hinge
1
Ea Classroom Lock
1
Ea Primus Core Only
1
Ea Surface Closer
1
Ea Kick Plate
1
Ea Dome Stop
1
Set Seals
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
5BB1HW 4.5 X 4.5 NRP
L9070T 03A
20-740
4111 EDA
8400 10" X 2" LDW
FS436/8
5050C
Door Hardware
652 IVE
626 SCH
626 SCH
689 LCN
630 IVE
626 IVE
CHA NGP
Section 08 71 00-14
HARDWARE GROUP: 19
6
1
1
1
1
1
1
2
2
1
Ea
Set
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Set
Hinge
Const Latching Bolt
Storeroom Lock
Primus Core Only
Coordinator
Astragal
Surface Closer
Kick Plate
Dome Stop
Seals
5BB1HW 4.5 X 4.5
FB62
L9080T 03A
20-740
COR X FL
158SA
4011
8400 10" X 2" LDW
FS436/8
5050C
652
630
626
626
628
CL
689
630
626
CHA
IVE
IVE
SCH
SCH
IVE
NGP
LCN
IVE
IVE
NGP
5BB1HW 4.5 X 4.5
FB61T
L9070T 03A
20-740
COR X FL
158NA
4011
8400 10" X 2" LDW
FS41
652
630
626
626
628
628
689
630
626
IVE
IVE
SCH
SCH
IVE
NGP
LCN
IVE
IVE
5BB1HW 4.5 X 4.5 NRP
L9070T 03A
20-740
4111 EDA
8400 10" X 2" LDW
FS41
5050C
652
626
626
689
630
626
CHA
IVE
SCH
SCH
LCN
IVE
IVE
NGP
5BB1HW 4.5 X 4.5 NRP
L9070T 03A
20-740
4111 EDA
8400 10" X 2" LDW
FS436/8
9450C
652
626
626
689
630
626
CHA
IVE
SCH
SCH
LCN
IVE
IVE
NGP
HARDWARE GROUP: 20
6
1
1
1
1
1
1
2
2
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Hinge
Const Latching Bolt
Classroom Lock
Primus Core Only
Coordinator
Astragal
Surface Closer
Kick Plate
Floor Stop & Holder
HARDWARE GROUP: 21
3
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Set
Hinge
Classroom Lock
Primus Core Only
Surface Closer
Kick Plate
Floor Stop & Holder
Seals
HARDWARE GROUP: 22
3
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Set
Hinge
Classroom Lock
Primus Core Only
Surface Closer
Kick Plate
Dome Stop
Seals
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-15
HARDWARE GROUP: 23
3
1
1
1
1
1
1
Ea
Ea
Ea
Ea
Ea
Ea
Set
Hinge
Classroom Lock
Primus Core Only
Surface Closer
Kick Plate
Dome Stop
Seals
5BB1HW 4.5 X 4.5 NRP
L9070T 03A
20-740
4011
8400 10" X 2" LDW
FS436/8
9450C
652
626
626
689
630
626
CHA
IVE
SCH
SCH
LCN
IVE
IVE
NGP
END OF SECTION
Monterey Peninsula College
Art Department Modernizations
Buildings 1 & 30
Door Hardware
Section 08 71 00-16
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
SECTION 23 09 00 – TEMPERATURE CONTROLS
PART 1: GENERAL
1.0
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
1.1
SECTION INCLUDES
Products Furnished But Not Installed Under This Section
Products Installed But Not Furnished Under This Section
Products Not Furnished or Installed But Integrated with the Work of this Section
Related Sections
Description
Approved Control System Contractor
Quality Assurance
Codes and Standards
System Performance
Submittals
Warranty
Ownership of Proprietary Material
PRODUCTS FURNISHED BUT NOT INSTALLED UNDER THIS SECTION
A. Division 23 - Ductwork Accessories:
1.
Automatic Dampers
2.
Airflow Stations
1.2
PRODUCTS INSTALLED BUT NOT FURNISHED UNDER THIS SECTION
A. Division 23 – Air Handling Equipment:
1.
Thermostats
2.
Sensors
3.
Controllers
1.3
PRODUCTS NOT FURNISHED OR INSTALLED BUT INTEGRATED WITH THE WORK
OF THIS SECTION
A. Division 23 –Air Handling Equipment
1.
Discharge Air Temperature Control
1.4
RELATED SECTIONS
A.
The General Conditions of the Contract, Supplementary Conditions, and General Requirements
are a part of these Specifications and shall be used in conjunction with this Section as a part of the
Contract Documents. Consult them for further instructions pertaining to this work. The
Contractor is bound by the provisions of Division 0 and Division 1.
B.
The following sections constitute related work:
1.
Division 1 - Commissioning
2.
Division 23 00 00 – Mechanical General
3.
Division 23 05 00 – Heating, Ventilating, and Air Conditioning
4.
Division 26 – Electrical
TEMPERATURE CONTROLS
23 09 00 - 1
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
1.5
DESCRIPTION
A.
General: The control system shall be as indicated on the drawings and described in the
specifications, and consist of a peer-to-peer network of digital building control panels and
operator workstation(s). The user interface shall be able to get through any personal computer
available on the network. The PC shall provide users an interface with the system through
dynamic color graphics of building areas and systems.
B.
Direct Digital Control (DDC) technology shall be used to provide the functions necessary for
control of systems defined for control on this project.
C.
The control system shall accommodate simultaneous multiple user operation. Access to the
control system data should be limited by operator ID and password. An operator shall be able to
log onto any PC on the designated network and have access to all designated data.
D.
The control system shall be designed such that each mechanical system will operate under standalone control. As such, in the event of a network communication failure, or the loss of other
controllers, the control system shall continue to independently operate the unaffected equipment.
E.
Communication between the control panels and all workstations shall be over a high-speed
network. All nodes on this network shall be peers. A modem or internet connectivity may be
provided for remote access to the system.
1.6
APPROVED CONTROL SYSTEM CONTRACTORS AND MANUFACTURERS
A.
Approved Control System Contractors and Manufacturers:
a) Siemens
1.
1.7
The above list of manufacturers applies to user interface, controller software, custom
application programming language, Building Controllers, Custom Application
Controllers, and Application Specific Controllers. All other products specified herein
(i.e., sensors, valves, dampers, and actuators) need not be manufactured by the above
manufacturers.
QUALITY ASSURANCE
A. System Installer Qualifications
1.
The Installer shall have an established working relationship with the Control System
Manufacturer of not less than three years.
2.
The Installer shall have successfully completed Control System Manufacturer's classes on
the control system. The Installer shall present for review the certification of completed
training, including the hours of instruction and course outlines upon request.
3.
The installer shall have an office within 50 miles of the project site and provide 24-hour
response in the event of a customer call.
1.8
CODES AND STANDARDS
TEMPERATURE CONTROLS
23 09 00 - 2
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
A.
Work, materials, and equipment shall comply with the rules and regulations of all codes and
ordinances of local, state and federal authorities. As a minimum, the installation shall comply
with the current editions in effect 30 days prior to receipt of bids of the following codes:
1.
National Electric Code (NEC)
2.
California Building Code (CBC)
3.
California Mechanical Code (CMC)
4.
Underwriters Laboratories: Products shall be UL-916-PAZX listed.
5.
ISO/IEC 14908-1 (LonTalk)
1.9
SYSTEM PERFORMANCE
A.
Performance Standards. The system shall conform to the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Page Display. The system shall display a web page will be displayed within [5] seconds
of the request. There is no maximum amount of dynamic points that can be displayed.
Page Refresh. The system shall update all within [10] seconds.
Graphic Refresh. The system shall update all dynamic points with current data within
[30] seconds.
Object Command. The maximum time between the command of a binary object by the
operator and the reaction by the device shall be 10 seconds. Analog objects shall start to
adjust within 10 seconds.Object Scan. All changes of state and change of analog values shall be transmitted over
the high-speed network such that any data used or displayed at a controller or workstation
will be current, within the prior [60] seconds.
Alarm Response Time. The maximum time from when an object goes into alarm to when
it is annunciated at the workstation shall not exceed [30] seconds.
Program Execution Frequency. Custom programs shall be capable of running as often as
once every second. The Contractor shall be responsible for selecting execution times
consistent with the mechanical process under control.
Performance. Programmable Controllers shall be able to execute DDC PID control loops
at a selectable frequency from at least once every [5] seconds. The controller shall scan
and update the process value and output generated by this calculation at this same
frequency.
Multiple Alarm Annunciations. All users on the network shall receive alarms within [10]
seconds of each other.
Reporting Accuracy. Table 1 lists minimum acceptable reporting accuracies for all
values reported by the specified system.
Table 1
Reporting Accuracy
Measured Variable
Space Temperature
Ducted Air
Outside Air
Water Temperature
Delta-T
Relative Humidity
Water Flow
Air Flow (terminal)
TEMPERATURE CONTROLS
Reported Accuracy
±0.5°C [±1°F]
±1.0°C [±2°F]
±1.0°C [±2°F]
±0.5°C [±1°F]
±0.15°C [±0.25°F]
±5% RH
±5% of full scale
±10% of reading *Note 1
23 09 00 - 3
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
Air Flow (measuring stations)
Air Pressure (ducts)
Air Pressure (space)
Water Pressure
Electrical Power
Carbon Monoxide (CO)
Carbon Dioxide (CO2)
±5% of reading
±25 Pa [±0.1 "W.G.]
±3 Pa [±0.01 "W.G.]
±2% of full scale *Note 2
± 5% of reading *Note 3
± 5% of reading
± 50 PPM
Note 1: (10%-100% of scale) (cannot read accurately below 10%)
Note 2: for both absolute and differential pressure
Note 3: * not including utility supplied meters
1.10
SUBMITTALS
A.
Contractor shall provide shop drawings and manufacturers’ standard specification data sheets on
all hardware and software to be provided. No work may begin on any segment of this project
until the Engineer and Owner have reviewed submittals for conformity with the plan and
specifications. Six (6) copies are required. All shop drawings shall be provided to the Owner
electronically as .dwg or .dxf file formats.
B.
Quantities of items submitted shall be reviewed by the Engineer and Owner. Such review shall
not relieve the contractor from furnishing quantities required for completion.
C.
Provide the Engineer and Owner, any additional information or data which is deemed necessary
to determine compliance with these specifications or which is deemed valuable in documenting
the system to be installed.
D.
Submit the following within 20 days of contract award:
1.
A complete bill of materials of equipment to be used indicating quantity, manufacturer
and model number.
A schedule of all control dampers. This shall include the damper size, pressure drop,
manufacturer and model number.
Provide manufacturers cut sheets for major system components. When manufacturer's cut
sheets apply to a product series rather than a specific product, the data specifically
applicable to the project shall be highlighted or clearly indicated by other means. Each
submitted piece of literature and drawings shall clearly reference the specification and/or
drawing that the submittal is being submitted to cover. Include:
2.
3.
a)
b)
c)
d)
e)
f)
g)
Building Controllers
Custom Application Controllers
Application Specific Controllers
Operator Interface Computer(s)
Portable Operator Workstation
Auxiliary Control Devices
Proposed control system riser diagram showing system configuration, device locations,
addresses, and cabling
h) Detailed termination drawings showing all required field and factory terminations.
Terminal numbers shall be clearly labeled
i) Points list showing all system objects, and the proposed English language object names
TEMPERATURE CONTROLS
23 09 00 - 4
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
j)
Sequence of operations for each system under control. This sequence shall be specific
for the use of the Control System being provided for this project
k) Color prints of proposed graphics with a list of points for display
E.
Project Record Documents. Upon completion of installation submit three (3) copies of record (asbuilt) documents. The documents shall be submitted for approval prior to final completion and
include:
1.
2.
3.
a)
b)
c)
d)
e)
f)
g)
Project Record Drawings. These shall be as-built versions of the submittal shop drawings.
One set of electronic media including CAD .DWG or .DXF drawing files shall also be
provided.
Testing and Commissioning Reports and Checklists.
Operating and Maintenance (O & M) Manual. These shall be as-built versions of the
submittal product data. In addition to that required for the submittals, the O & M manual
shall include:
Names, address and 24-hour telephone numbers of Contractors installing equipment, and
the control systems and service representative of each.
Provide on-line help for documenting operator instructions
A listing and documentation of all custom software created using the programming
language including the point database. One set of magnetic media containing files of the
software and database shall also be provided.
One set of electronic media containing files of all color-graphic screens created for the
project.
Complete original issue documentation, installation, and maintenance information for all
third party hardware provided including computer equipment and sensors.
Licenses and warranty documents for all equipment and systems.
Recommended preventive maintenance procedures for all system components including a
schedule of tasks, time between tasks, and task descriptions.
F.
Training Materials: The Contractor shall provide a course outline and training material for all
training classes at least six weeks prior to the first class. The Owner reserves the right to modify
any or all of the training course outline and training materials. Review and approval by Owner
and Engineer shall be completed at least 3 weeks prior to first class.
1.11
WARRANTY
A.
Warrant all work as follows:
1.
2.
3.
Labor & materials for control system specified shall be warranted free from defects for a
period of twelve (12) months after final completion acceptance by the Owner. Control
System failures during the warranty period shall be adjusted, repaired, or replaced at no
charge or reduction in service to the Owner. The Contractor shall respond to the Owner's
request for warranty service within 24 hours during customary business hours.
At the end of the final start-up/testing, if equipment and systems are operating
satisfactorily to the Owner and Engineer, the Owner shall sign certificates certifying that
the control system's operation has been tested and accepted in accordance with the terms
of this specification. The date of Owner's acceptance shall be the start of warranty.
Operator workstation software, project specific software, graphics, database, and
firmware updates shall be provided to the Owner at no charge during the warranty period.
Written authorization by Owner must, however, be granted prior to the installation of
such changes.
TEMPERATURE CONTROLS
23 09 00 - 5
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
4.
The system provider shall provide a web-accessible system and support on-line resource
that provides the Owner access to a question/answer forum, graphics library, user tips,
upgrades, and manufacturer training schedules.
1.12
OWNERSHIP OF PROPRIETARY MATERIAL
A.
All project-developed hardware and software shall become the property of the Owner. These
items include but are not limited to:
1.
Project graphic images
2.
Record drawings
3.
Project database
4.
Project-specific application programming code
5.
All documentation
PART 2: PRODUCTS
2.0
1.
2.
3.
4.
5.
6.
7.
8.
SECTION INCLUDES
Materials
Communication
Operator Interface
Application and Control Software
Building Controllers
Application Specific Controllers
Input/Output Interface
Auxiliary Control Devices
2.1
MATERIALS
A.
All products used in this installation shall be new, currently under manufacture, and shall be
applied in similar installations for a minimum of 2 years. The installation shall not be used as a
test site for any new products unless explicitly approved by the Owner’s representative in writing.
Spare parts shall be available for at least 5 years after completion of this contract.
2.2
COMMUNICATION
A.
This project shall comprise of a network utilizing high-speed for communications between
Building Controllers. LonTalk sub-networks shall be used for communications between Building
Controllers, Custom Application Controllers and Application Specific Controllers.
B.
The Owner will provide all communication media, connectors, repeaters, network switches, and
routers necessary for the internetwork. An active Ethernet jack will be provided adjacent to each
Building Control Panel and PC Workstation for connection to this network.
C.
All Building Controllers shall have an Ethernet communications port for connections with the
operator interfaces.
D.
Communications services over the internetwork shall result in operator interface and value
passing that is transparent to the internetwork architecture as follows:
TEMPERATURE CONTROLS
23 09 00 - 6
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
1.
Connection of an operator interface device to any one building controller on the
internetwork will allow the operator to interface with all other building controllers as if
that interface were directly connected to the other controllers. Data, status information,
reports, system software, custom programs, etc., for all building controllers shall be
available for viewing and editing from any one building controller on the internetwork.
2.
All database values (i.e., points, software variable, custom program variables) of any one
building controller shall be readable by any other building controller on the internetwork.
This value passing shall be automatically performed by a controller when a reference to a
point name not located in that controller is entered into the controller's database. An
operator/installer shall not be required to set up any communications services to perform
internetwork value passing.
F.
The time clocks in all building controllers shall be automatically synchronized daily.
2.3
OPERATOR INTERFACE
A.
Operator workstation is existing.
2.4
APPLICATION AND CONTROL SOFTWARE
A.
Scheduling. Provide the capability to schedule each object or group of objects in the system.
Each of these schedules shall include the capability for start, stop, optimal start, optimal stop, and
night economizer actions. Each schedule may consist of up to [10] events. When a group of
objects are scheduled together, provide the capability to define advances and delays for each
member. Each schedule shall consist of the following:
1.
2.
3.
4.
B.
Weekly Schedule. Provide separate schedules for each day of the week.
Exception Schedules. Provide the ability for the operator to designate any day of the year
as an exception schedule. This exception schedule shall override the standard schedule
for that day. Exception schedules may be defined up to a year in advance. Once an
exception schedule is executed it will be discarded and replaced by the standard schedule
for that day of the week.
Holiday Schedules. Provide the capability for the operator to define up to 99 special or
holiday schedules. These schedules may be placed on the scheduling calendar and will
be repeated each year. The operator shall be able to define the length of each holiday
period.
Optimal Start. The scheduling application outlined above shall support an optimal start
algorithm. This shall calculate the thermal characteristics of a zone and start the
equipment prior to occupancy to achieve the desired space temperature at the specified
occupancy time. The algorithm shall calculate separate sets of heating and cooling rates
for zones that have been unoccupied for less then and greater than 24 hours. Provide the
ability to modify the start algorithm based on outdoor air temperature. Provide an early
start limit in minutes to prevent the system from starting before an operator determined
time limit.
Remote Communications. The system shall have the ability to transmit alarms to multiple
associated alarm receivers. Receivers shall include PC Workstations, email addresses, and cell
phones. The alarm message shall include the name of the alarm location, the device that
generated the alarm, and the alarm message itself. The operator shall be able to remotely access
TEMPERATURE CONTROLS
23 09 00 - 7
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
and operate the system utilizing the system Ethernet communications, or dial up communications
via modem, in the same format and method used on site as described under the Operator Interface
section of this specification.
C.
PID Control. A PID (proportional-integral-derivative) algorithm with direct or reverse action and
anti-wind-up shall be supplied. The algorithm shall calculate a time-varying analog value used to
position an output or stage a series of outputs. The controlled variable, and set-point, shall be
user-selectable. The set-point shall optionally be chosen to be a reset schedule.
D.
Point control. User shall have the option to set the update interval, minimum on/off time, event
notification, custom programming on change of events
E.
Timed Override. A standard application shall be utilized to enable/disable temperature control
when a user selects on/cancel at the zone sensor, workstation, or the operator display. The
amount of time that the override takes precedence will be selectable from the workstation.
F.
Anti-Short Cycling. All binary output points shall be protected from short cycling.
2.5
BUILDING CONTROLLERS
A.
General. Provide Building Controllers to provide the performance specified in section 1 of this
division. Each of these panels shall meet the following requirements.
1.
The Building Automation System shall be composed of one or more independent,
standalone, microprocessor based Building Controllers to manage the global strategies
described in System software section.
2.
The Building Controller shall have sufficient memory to support its operating system,
database, and programming requirements.
3.
The controller shall provide a USB communications port for connection to a PC.
4.
The operating system of the Controller shall manage the input and output
communications signals to allow distributed controllers to share real and virtual point
information and allow central monitoring and alarms.
5.
Controllers that perform scheduling shall have a real time clock.
6.
Data shall be shared between networked Building Controllers.
7.
The Building Controller shall utilize industry recognized open standard protocols for
communication to unit controllers.
8.
The Building Controller shall continually check the status of its processor and memory
circuits. If an abnormal operation is detected, the controller shall:
i. Assume a predetermined failure mode.
ii. Generate an alarm notification.
iii. Create a retrievable file of the state of all applicable memory locations at the time
of the failure.
iv. Automatically reset the Building Controller to return to a normal operating mode.
Communications. Each Building Controller shall reside on the Enterprise wide network, which is
same high-speed network as the workstations. The Enterprise wide network will be provided by
the owner and supports the Internet Protocol (IP). Local connections of the Building Controller
shall be on ISO 8802-3 (Ethernet). Each Building Controller shall also perform routing to a
network of Custom Application and Application Specific Controllers) [Optional – Each Building
Controller shall perform communications to a network of Custom Application and Application
Specific Controllers using LonTalk FTT-10 and LonMark profiles.
B.
TEMPERATURE CONTROLS
23 09 00 - 8
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
C.
Environment. Controller hardware shall be suitable for the anticipated ambient conditions.
Controller used in conditioned ambient shall be mounted in an enclosure, and shall be rated for
operation at -40 C to 50 C [-40 F to 122 F].
D.
Serviceability. Provide diagnostic LEDs for power, communications, and processor. The
Building Controller shall have a display on the main board that indicates the current operating
mode of the controller. All wiring connections shall be made to field removable, modular
terminal connectors. The building controller shall utilize standard DIN mounting methods for
installation and replacement.
E.
Memory. The Building Controller shall maintain all BIOS and programming information
indefinitely without power to the building controller.
F.
Immunity to power and noise. Controller shall be able to operate at 90% to 110% of nominal
voltage rating and shall perform an orderly shut-down below 80% nominal voltage
2.6
APPLICATION SPECIFIC CONTROLLERS
A.
General. Application specific controllers (ASC) are microprocessor-based DDC controllers,
which through hardware or firmware design are dedicated to control a specific piece of
equipment. They are not fully user programmable, but are customized for operation within the
confines of the equipment they are designed to serve.
1.
2.
B.
Each ASC shall be capable of stand-alone operation and shall continue to provide control
functions without being connected to the network.
Each ASC will contain sufficient I/O capacity to control the target system.
Environment. The hardware shall be suitable for the anticipated ambient conditions.
1.
2.
Controller used in conditioned ambient spaces shall be mounted in IP 20 type rated
enclosures. Controllers located where not to be disturbed by building activity (such as
above ceiling grid), may be provided with plenum-rated enclosures and non-enclosed
wiring connections for plenum cabling. All controllers shall be rated for operation at 0 C
to 50 C [32 F to 120 F].
Controllers used outdoors and/or in wet ambient shall be mounted within IP 56 type
waterproof enclosures, and shall be rated for operation at -40 C to 65 C [-40 F to 150 F].
C.
Serviceability. Provide diagnostic LEDs for power and communications. All wiring connections
shall be clearly labeled and made to be field removable.
D.
Memory. The Application Specific Controller shall maintain all BIOS and programming
information in the event of a power loss for at least 90 days.
E.
Immunity to Power and noise. Controller shall be able to operate at 90% to 110% of nominal
voltage rating and shall perform an orderly shutdown below 80%.
F.
Transformer. Power supply for the ASC must be rated at minimum of 125% of ASC power
consumption, and shall be fused or current limiting type.
G.
Application Specific Controllers shall communicate using LonTalk. In case of LonTalk,
Controllers shall use FTT-10 transceivers. All communications shall follow LonMark profiles.
TEMPERATURE CONTROLS
23 09 00 - 9
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
ASCs which do not have a profile that applies must comply with LonMark standards, utilize
SNVTs for all listed points, and be provided with a XIF file for self-documentation.
2.7
INPUT/OUTPUT INTERFACE
A.
Hard-wired inputs and outputs may tie into the system through Building, Custom, or Application
Specific Controllers.
B.
All input points and output points shall be protected such that shorting of the point to itself,
another point, or ground will cause no damage to the controller. All input and output points shall
be protected from voltage up to 24V of any duration, such that contact with this voltage will
cause no damage to the controller.
C.
Binary inputs shall allow the monitoring of on/off signals from remote devices. The binary
inputs shall provide a wetting current of at least 12 mA to be compatible with commonly
available control devices.
D.
Pulse accumulation input points. This type of point shall conform to all the requirements of
Binary Input points, and also accept up to 3 pulses per second for pulse accumulation, and shall
be protected against effects of contact bounce and noise.
E.
Analog inputs shall allow the monitoring of low voltage (0-10 Vdc), current (4-20 ma), or
resistance signals (thermistor, RTD). Analog inputs shall be compatible with, and field
configurable to commonly available sensing devices.
F.
Binary outputs shall provide for on/off operation. Terminal unit and zone control applications
may use 2 outputs for drive-open, drive-close (tri-state) modulating control. Binary outputs on
custom application controllers shall have 3-mode (on/off/auto) program override control from the
panel with output status lights.
G.
Analog outputs shall provide a modulating signal for the control of end devices. Outputs shall
provide either a 0-10 Vdc or a 4-20 ma signal as required to provide proper control of the output
device. Analog outputs on custom application controllers shall have a 2-mode (auto/manual)
program override control, with manual output adjustment over 0-100% of range.
2.8
AUXILIARY CONTROL DEVICES
A.
For motorized and control damper requirements, see 23 05 00.
B.
Electric damper actuators.
1.
2.
3.
4.
The actuator shall have electronic overload or digital rotation sensing circuitry to prevent
damage to the actuator throughout the rotation of the actuator.
Where shown, for power-failure/safety applications, an internal mechanical, spring return
mechanism shall be built into the actuator housing.
All rotary spring return actuators shall be capable of both clockwise and counter
clockwise spring return operation. Linear actuators shall spring return to the retracted
position.
Proportional actuators shall accept a 0-10 VDC or 0-20 ma control signal and provide a
2-10 VDC or 4-20 ma operating range.
TEMPERATURE CONTROLS
23 09 00 - 10
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
5.
6.
7.
8.
E.
Binary Temperature Devices
1.
2.
3.
F.
3.
4.
5.
6.
Temperature sensors shall be Resistance Temperature Device (RTD) or Thermistor.
Duct sensors shall be rigid or averaging as shown. Averaging sensors shall be a minimum
of 1.5m [5 feet] in length.
Immersion sensors shall be provided with a separable stainless steel well. Pressure rating
of well is to be consistent with the system pressure in which it is to be installed.
Space sensors shall be equipped with set-point adjustment, override switch, display,
and/or communication port as shown on the drawings.
Provide matched temperature sensors for differential temperature measurement.
Differential accuracy shall be within 0.1 C [0.2 F].
[Optional] The space temperature, set point, and override confirmation will be
annunciated by a digital display for each zone sensor. The set point will be selectable
utilizing buttons.
Relays
1.
2.
H.
Low-Voltage Space Thermostats shall be 24 V, bimetal-operated, mercury-switch type,
with either adjustable or fixed anticipation heater, concealed set point adjustment, 13°C30°C (55°F-85°F) set point range, 1°C (2°F) maximum differential, and vented cover.
Line-Voltage Space Thermostats shall be bimetal-actuated, open-contact type or bellowsactuated, enclosed, snap-switch type or equivalent solid-state type, with heat anticipator,
UL listing for electrical rating, concealed set point adjustment, 13°C-30°C (55°F-85°F)
set point range, 1°C (2°F) maximum differential, and vented cover.
Low-Limit airstream thermostats shall be UL listed, vapor pressure type. Element shall
be at least 6 m (20 ft) long. Element shall sense temperature in each 30 cm (1 ft) section
and shall respond to lowest sensed temperature. Low-limit thermostat shall be manual
reset only.
Temperature Sensors
1.
2.
G.
All non-spring return actuators shall have an external manual gear release to allow
manual positioning of the damper when the actuator is not powered. Spring return
actuators with more than 60 in-lb. torque capacity shall have a manual crank for this
purpose.
Actuators shall be provided with a conduit fitting and a minimum 1m electrical cable and
shall be pre-wired to eliminate the necessity of opening the actuator housing to make
electrical connections.
Actuators shall be Underwriters Laboratories Standard 873 listed.
Actuators shall be designed for a minimum of 60,000 full stroke cycles at the actuator's
rated torque.
Control relays shall be UL listed plug-in type with dust cover. Contact rating,
configuration, and coil voltage suitable for application.
Time delay relays shall be UL listed solid-state plug-in type with adjustable time delay.
Delay shall be adjustable plus or minus 200% (minimum) from set-point shown on plans.
Contact rating, configuration, and coil voltage suitable for application. Provide IP 20
Type enclosure when not installed in local control panel.
Transformers and Power Supplies
TEMPERATURE CONTROLS
23 09 00 - 11
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
1.
2.
3.
4.
I.
Current Switches
1.
J.
Control transformers shall be UL listed, Class 2 current-limiting type, or shall be
furnished with over-current protection in both primary and secondary circuits for Class 2
service.
Unit output shall match the required output current and voltage requirements. Current
output shall allow for a 50% safety factor. Output ripple shall be 70.0 mV maximum
Peak-to-Peak. Regulation shall be 5% line and load combined, with 50 microsecond
response time for 50% load changes. Unit shall have built-in over-voltage protection.
Unit shall operate between 0 C and 50 C.
Unit shall be UL recognized.
Current-operated switches shall be self-powered, solid state with adjustable trip current.
The switches shall be selected to match the current of the application and output
requirements of the DDC system.
LOCAL CONTROL PANELS
1.
2.
3.
All indoor control cabinets shall be fully enclosed IP 20 Type construction with hinged
door, and removable sub-panels or electrical sub-assemblies.
Interconnections between internal and face-mounted devices shall be pre-wired with
color-coded stranded conductors neatly installed in plastic troughs and/or tie-wrapped.
Terminals for field connections shall be UL listed for 600-volt service, individually
identified per control/interlock drawings, with adequate clearance for field wiring.
Control terminations for field connection shall be individually identified per control
drawings.
Provide on/off power switch with over-current protection for control power sources to
each local panel.
PART 3: EXECUTION
3.0
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
SECTION INCLUDES:
Examination
Protection
General Workmanship
Field Quality Control
Wiring
Fiber Optic Cable
Installation of Sensors
Actuators
Warning Labels
Identification of Hardware and Wiring
Controllers
Programming
Cleaning
Training
Acceptance
Control Dampers
Sequence of Operation
TEMPERATURE CONTROLS
23 09 00 - 12
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
3.1
EXAMINATION
A.
The project plans shall be thoroughly examined for control device and equipment locations, and
any discrepancies, conflicts, or omissions shall be reported to the Architect/Engineer for
resolution before rough-in work is started.
B.
The contractor shall inspect the site to verify that equipment is installable as shown, and any discrepancies, conflicts, or omissions shall be reported to the Architect/Engineer for resolution
before rough-in work is started.
3.2
PROTECTION
A.
The Contractor shall protect all work and material from damage by his/her work or workers, and
shall be liable for all damage thus caused.
B.
The Contractor shall be responsible for his/her work and equipment until finally inspected, tested,
and accepted. The Contractor shall protect his/her work against theft or damage, and shall
carefully store material and equipment received on site that is not immediately installed. The
Contractor shall close all open ends of work with temporary covers or plugs during storage and
construction to prevent entry of foreign objects.
3.3
GENERAL WORKMANSHIP
A.
Install equipment, piping, wiring/conduit parallel to building lines (i.e. horizontal, vertical, and
parallel to walls) wherever possible.
B.
Provide sufficient slack and flexible connections to allow for vibration of piping and equipment.
C.
Install all equipment in readily accessible location as defined by chapter 1 article 100 part A of
the NEC. Control panels shall be attached to structural walls unless mounted in equipment
enclosure specifically designed for that purpose. Panels shall be mounted to allow for
unobstructed access for service.
D.
Verify integrity of all wiring to ensure continuity and freedom from shorts and grounds.
E.
All equipment, installation, and wiring shall comply with acceptable industry specifications and
standards for performance, reliability, and compatibility and be executed in strict adherence to
local codes and standard practices.
3.4
FIELD QUALITY CONTROL
A.
All work, materials and equipment shall comply with the rules and regulations of applicable local,
state, and federal codes and ordinances as identified in Part 1 of this Section.
B.
Contractor shall continually monitor the field installation for code compliance and quality of
workmanship. All visible piping and or wiring runs shall be installed parallel to building lines
and properly supported.
C.
Contractor shall arrange for field inspections by local and/or state authorities having jurisdiction
over the work.
TEMPERATURE CONTROLS
23 09 00 - 13
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
3.5
WIRING
A.
All control and interlock wiring shall comply with the national and local electrical codes and
Division 26 of these specifications. Where the requirements of this section differ with those in
Division 26, the requirements of this section shall take precedence.
B.
Where Class 2 wires are in concealed and accessible locations including ceiling return air
plenums, approved cables not in raceway may be used provided that:
C.
Circuits meet NEC Class 2 (current-limited) requirements. (Low-voltage power circuits shall be
sub-fused when required to meet Class 2 current-limit.)
All cables shall be UL listed for application, i.e., cables used in ceiling plenums shall be UL listed
specifically for that purpose.
D.
E.
Do not install Class 2 wiring in conduit containing Class 1 wiring. Boxes and panels containing
high voltage may not be used for low voltage wiring except for the purpose of interfacing the two
(e.g. relays and transformers).
F.
Where class 2 wiring is run exposed, wiring shall be run parallel along a surface or perpendicular
to it, and bundled, using approved wire ties at no greater than 3 m [10 ft] intervals. Such bundled
cable shall be fastened to the structure, using specified fasteners, at 1.5 m [5 ft] intervals or more
often to achieve a neat and workmanlike result.
G.
All wire-to-device connections shall be made at a terminal blocks or terminal strip. All wire-to
wire connections shall be at a terminal block, or with a crimped connector. All wiring within
enclosures shall be neatly bundled and anchored to permit access and prevent restriction to
devices and terminals.
H.
Maximum allowable voltage for control wiring shall be 120V. If only higher voltages are
available, the Control System Contractor shall provide step down transformers.
I.
All wiring shall be installed as continuous lengths, where possible. Any required splices shall be
made only within an approved junction box or other approved protective device.
J.
Install plenum wiring in sleeves where it passes through walls and floors. Maintain fire rating at
all penetrations in accordance with other sections of this specification and local codes.
K.
Size of conduit and size and type of wire shall be the design responsibility of the Control System
Contractor, in keeping with the manufacturer's recommendation and NEC.
L.
Control and status relays are to be located in designated enclosures only. These relays may also
be located within packaged equipment control panel enclosures. These relays shall not be located
within Class 1 starter enclosures.
M.
Follow manufacturer's installation recommendations for all communication and network cabling.
Network or communication cabling shall be run separately from other wiring.
N.
Adhere to Division 26 requirements for installation of raceway.
TEMPERATURE CONTROLS
23 09 00 - 14
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
O.
This Contractor shall terminate all control and/or interlock wiring and shall maintain updated
(as-built) wiring diagrams with terminations identified at the job site.
P.
Flexible metal conduits and liquid-tight, flexible metal conduits shall not exceed 3' in length and
shall be supported at each end. Flexible metal conduit less than 1/2" electrical trade size shall not
be used. In areas exposed to moisture, including chiller and boiler rooms, liquid-tight, flexible
metal conduits shall be used.
3.6
FIBER OPTIC CABLE SYSTEM
A.
All cabling shall be installed in a neat and workmanlike manner. Minimum cable and unjacketed
fibber bend radii as specified by cable manufacturer shall be maintained.
B.
Maximum pulling tensions as specified by the cable manufacturer shall not be exceeded during
installation. Post installation residual cable tension shall be within cable manufacture's
specifications.
C.
Fiber optic cabinets, hardware, and cable entering the cabinet shall be installed in accordance
with manufacturers' instructions. Minimum cable and unjacketed fiber bend radii as specified by
cable manufacturer shall be maintained.
3.7
INSTALLATION OF SENSORS
A.
Install sensors in accordance with the manufacturer's recommendations.
B.
Mount sensors rigidly and adequate for the environment within which the sensor operates.
C.
Room temperature sensors shall be installed on concealed junction boxes properly supported by
the wall framing.
D.
All wires attached to sensors shall be air sealed in their conduits or in the wall to stop air
transmitted from other areas affecting sensor readings.
E.
Install duct static pressure tap with tube end facing directly down-stream of air flow.
F.
Wiring for space sensors shall be concealed in building walls. EMT conduit is acceptable within
mechanical and service rooms.
G.
Install outdoor air temperature sensors on north wall complete with sun shield at designated
location.
3.8
ACTUATORS
A.
Mount and link control damper actuators per manufacturer's instructions.
1.
2.
To compress seals when spring return actuators are used on normally closed dampers,
power actuator to approximately 5° open position, manually close the damper, and then
tighten the linkage.
Check operation of damper/actuator combination to confirm that actuator modulates
damper smoothly throughout stroke to both open and closed positions.
TEMPERATURE CONTROLS
23 09 00 - 15
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
3.9
WARNING LABELS
A.
Affix labels on each starter and equipment automatically controlled through the DDC System.
Warning label shall indicate the following:
CAUTION
This equipment is operating under automatic control and may start or stop at any time without
warning. Disconnect switch to “Off” position before servicing.
B.
Affix labels to motor starters and control panels that are connected to multiple power sources
utilizing separate disconnects. Labels shall indicate the following:
CAUTION
This equipment is fed from more than one power source with separate disconnects.
Disconnect all power sources before servicing.
3.10
IDENTIFICATION OF HARDWARE AND WIRING
A.
All wiring and cabling, including that within factory-fabricated panels, shall be labeled at each
end within 2" of termination with a cable identifier and other descriptive information.
B.
Permanently label or code each point of field terminal strips to show the instrument or item
served.
C.
Identify control panels with minimum 1-cm (1/2”) letters on nameplates.
D.
Identify all other control components with permanent labels. Identifiers shall match record
documents. All plug-in components shall be labeled such that removal of the component does
not remove the label.
3.11
CONTROLLERS
A.
Provide a separate Controller for each major piece of HVAC equipment. A custom application
controller may control more than one system provided that all points associated with that system
are assigned to the same controller. Points used for control loop reset such as outside air or space
temperature are exempt from this requirement.
B.
Building Controllers and Custom Application Controllers shall be selected to provide a minimum
of 15% spare I/O point capacity for each point type found at each location. If input points are not
universal, 15% of each type is required. If outputs are not universal, 15% of each type is
required. A minimum of one spare is required for each type of point used.
TEMPERATURE CONTROLS
23 09 00 - 16
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
1.
Future use of spare capacity shall require providing the field device, field wiring, points
database definition, and custom software. No additional Controller boards or point
modules shall be required to implement use of these spare points.
3.12
PROGRAMMING
A.
Provide sufficient internal memory for the specified control sequences and trend logging. There
shall be a minimum of 25% of available memory free for future use.
B.
Point Naming: System point names shall be modular in design, allowing easy operator interface
without the use of a written point index.
C.
Software Programming
1.
D.
Provide programming for the system as written in the specifications and adhere to the
sequence strategies provided. All other system programming necessary for the operation
of the system but not specified in this document shall also be provided by the Control
System Contractor. Imbed into any custom-written control programs sufficient comment
statements or inherent flow diagrams to clearly describe each section of the program.
The comment statements shall reflect the language used in the sequence of operations.
Operators' Interface
1.
2.
3.
Standard Graphics. Provide graphics for each major piece of equipment and floor plan in
the building. This includes each Chiller, Air Handler, VAV Terminal, Fan Coil, Boiler,
and Cooling Tower. These standard graphics shall show all points dynamically as
specified in the points list.
The controls contractor shall provide all the labor necessary to install, initialize, start-up,
and trouble-shoot all operator interface software and their functions as described in this
section. This includes any operating system software, the operator interface database, and
any third party software installation and integration required for successful operation of
the operator interface.
As part of this execution phase, the controls contractor will perform a complete test of the
operator interface. Test duration shall be a minimum of 16 hours on-site. Tests shall be
made in the presence of the Owner or Owner's representative.
E.
Demonstration: A complete demonstration and readout of the capabilities of the monitoring and
control system shall be performed. The contractor shall dedicate a minimum of 16 hours on-site
with the Owner and his representatives for a complete functional demonstration of all the system
requirements. This demonstration constitutes a joint acceptance inspection, and permits
acceptance of the delivered system for on-line operation.
3.13
CLEANING
A.
This contractor shall clean up all debris resulting from his or her activities daily. The contractor
shall remove all cartons, containers, crates, etc. under his control as soon as their contents have
been removed. Waste shall be collected and placed in a location designated by the Construction
Manager or General Contractor.
B.
At the completion of work in any area, the Contractor shall clean all of his/her work, equipment,
etc., making it free from dust, dirt and debris, etc.
TEMPERATURE CONTROLS
23 09 00 - 17
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
C.
At the completion of work, all equipment furnished under this Section shall be checked for paint
damage, and any factory finished paint that has been damaged shall be repaired to match the
adjacent areas. Any metal cabinet or enclosure that has been deformed shall be replaced with
new material and repainted to match the adjacent areas.
3.14
TRAINING
A.
Provide a minimum of 4 classroom training sessions, 4 hours each, throughout the contract period
for personnel designated by the Owner. Computer-based audio-visual training may be substituted
for up to 8 hours of hands on training.
B.
Train the designated staff of Owner's representative and Owner to enable them to proficiently
operate the system; create, modify and delete programming; add, remove and modify physical
points for the system, and perform routine diagnostic and troubleshooting procedures.
C.
Additional training shall be available in courses designed to meet objectives as divided into three
logical groupings; participants may attend one or more of these, depending on the level of
knowledge required:
1.
2.
3.
Day-to-day Operators
Advanced Operators
System Managers/Administrators
D.
Provide course outline and materials as per Part 1 of this Section. The instructor(s) shall provide
one copy of training material per student.
E.
The instructor(s) shall be factory-trained instructors experienced in presenting this material.
F.
Classroom training shall be done using a network of working controllers representative of the
installed hardware or at the customer’s site.
G.
This training shall be made available in addition to the interactive audio-visual tutorial, provided
with the system.
3.15
ACCEPTANCE
A.
The control systems will not be accepted as meeting the requirements of Completion until all tests
described in this specification have been performed to the satisfaction of both the Engineer and
Owner. Any tests that cannot be performed due to circumstances beyond the control of the
Contractor may be exempt from the Completion requirements if stated as such in writing by the
Owner's representative. Such tests shall then be performed as part of the warranty.
3.17
CONTROL DAMPER INSTALLATION
A.
Damper submittals shall be coordinated for type, quantity, and size to ensure compatibility with
sheet metal design.
TEMPERATURE CONTROLS
23 09 00 - 18
MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30
B.
Duct openings shall be free of any obstruction or irregularities that might interfere with blade or
linkage rotation or actuator mounting. Duct openings shall measure 1/4" larger than damper
dimensions and shall be square, straight, and level.
C.
Individual damper sections, as well as entire multiple section assemblies, must be completely
square and free from racking, twisting, or bending. Measure diagonally from upper corners to
opposite lower corners of each damper section. Both dimensions must be equal ±1/8".
D.
Follow manufacturer's instructions for field installation of control dampers. Unless specifically
designed for vertical blade application, dampers must be mounted with blade axis horizontal.
E.
Install extended shaft or jackshaft per manufacturer's instructions. (Typically, a sticker on the
damper face shows recommended extended shaft location. Attach shaft on labeled side of
damper to that blade.)
F.
Damper blades, axles, and linkage must operate without binding. Before system operation, cycle
damper after installation to assure proper operation. On multiple section assemblies, all sections
must open and close simultaneously.
G.
Provide a visible and accessible indication of damper position on the drive shaft end.
H.
Support duct-work in area of damper when required to prevent sagging due to damper weight.
I.
After installation of low-leakage dampers with seals, caulk between frame and duct or opening to
prevent leakage around perimeter of damper.
3.19
SEQUENCE OF OPERATIONS
A.
For Sequences of Operations, see Drawings.
*** END OF SECTION 15900 ***
TEMPERATURE CONTROLS
23 09 00 - 19
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
SECTION 23 09 50
COMMISSIONING OF HVAC
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
SUMMARY
A.
Section includes commissioning process requirements for HVAC&R systems including
Controls, assemblies, and equipment.
B.
Related Sections:
1.
1.3
Division 01 Section "01 91 00 General Commissioning Requirements" for general
commissioning process requirements.
DEFINITIONS
A.
1.4
See Section 01 91 00 Commissioning Requirements for definitions
CONTRACTOR'S RESPONSIBILITIES
A.
1.5
See Section 01 91 00 Commissioning Requirements for contractor’s and sub contractors
responsibilities
CA'S RESPONSIBILITIES
A.
1.6
See Section 01 91 00 Commissioning Requirements for CA responsibilities
COMMISSIONING DOCUMENTATION
A.
Provide the following information to the CA for inclusion in the commissioning plan:
1.
2.
Plan for delivery and review of submittals, systems manuals, and other documents and
reports.
Identification of installed systems, assemblies, equipment, and components including
design changes that occurred during the construction phase.
COMMISSIONING OF HVAC SYSTEM
23 09 50-1
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
3.
4.
5.
6.
7.
8.
1.7
Process and schedule for completing construction checklists and manufacturer's prestart
and startup checklists for HVAC&R systems, assemblies, equipment, and components to
be verified and tested.
Certificate of completion certifying that installation, prestart checks, and startup
procedures have been completed.
Certificate of readiness certifying that HVAC&R systems, subsystems, equipment, and
associated controls are ready for testing.
Test and inspection reports and certificates.
Corrective action documents.
Verification of testing, adjusting, and balancing reports.
SUBMITTALS
A.
Certificates of readiness.
B.
Certificates of completion of installation, prestart, and startup activities. Manufacturer start-up
forms shall be submitted to CA within one week of completion of start-ups.
C.
Provide two copies of O&M manuals, sequence of operations and control diagrams and blank
start-up forms related to commissioned equipment and systems within 30 days of engineers
approval in a three ring binder. Controls drawings shall be minimum 11x17.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1
TESTING PREPARATION
A.
Review 01 91 00 General Commissioning Requirements, in inter trade coordination
meeting.(Mechanical dry and wet side, TAB, Controls and Electrical subcontractors minimum).
Meeting minutes shall be submitted to CA. Inter trade meeting is mandatory per this section.
B.
Certify that HVAC&R systems, subsystems, and equipment have been installed, calibrated, and
started and are operating according to the Contract Documents.
C.
Certify that HVAC&R instrumentation and control systems have been completed and
calibrated, that they are operating according to the Contract Documents, and that pretest set
points have been recorded.
D.
Certify that testing, adjusting, and balancing procedures have been completed and that testing,
adjusting, and balancing reports have been submitted, discrepancies corrected, and corrective
work approved.
E.
Set systems, subsystems, and equipment into operating mode to be tested (e.g., normal
shutdown, normal auto position, normal manual position, unoccupied cycle, emergency power,
and alarm conditions).
COMMISSIONING OF HVAC SYSTEM
23 09 50-2
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
F.
Inspect and verify the position of each device and interlock identified on checklists.
G.
Check safety cutouts, alarms, and interlocks with smoke control and life-safety systems during
each mode of operation.
H.
Testing Instrumentation: Install measuring instruments and logging devices to record test data
as directed by the CA.
I.
Certify that all related A/E punch list items are complete prior to commencing functional test
procedures.
3.2
Testing and balance verification
A.
Prior to performance of testing and balancing Work, provide copies of reports, sample forms,
checklists, and certificates to the CA.
B.
Notify the CA at least 10 days in advance of testing and balancing Work, and provide access for
the CA to witness testing and balancing Work.
C.
Provide technicians, instrumentation, and tools to verify testing and balancing of HVAC&R
systems at the direction of the CA.
1.
2.
3.
4.
3.3
The CA will notify testing and balancing Subcontractor 10 days in advance of the date of
field verification. Notice will not include data points to be verified.
The testing and balancing Subcontractor shall use the same instruments (by model and
serial number) that were used when original data were collected.
Failure of an item includes, other than sound, a deviation of more than 10 percent.
Failure of more than 10 percent of selected items shall result in rejection of final testing,
adjusting, and balancing report. For sound pressure readings, a deviation of 3 dB shall
result in rejection of final testing. Variations in background noise must be considered.
Remedy the deficiency and notify the CA so verification of failed portions can be
performed.
GENERAL TESTING REQUIREMENTS
A.
Provide installing technicians, instrumentation, and tools to perform commissioning test at the
direction of the CA.
B.
Scope of HVAC&R testing shall include entire HVAC&R installation, from central equipment
for heat generation and refrigeration through distribution systems to each conditioned space.
Testing shall include measuring capacities and effectiveness of operational and control
functions.
C.
Test all operating modes, interlocks, control responses, and responses to abnormal or
emergency conditions, and verify proper response of building automation system controllers
and sensors.
COMMISSIONING OF HVAC SYSTEM
23 09 50-3
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
D.
The CA along with the HVAC&R Subcontractor, testing and balancing Subcontractor, and
HVAC&R Instrumentation and Control Subcontractor shall prepare detailed testing plans,
procedures, and checklists for HVAC&R systems, subsystems, and equipment.
E.
Tests will be performed using design conditions whenever possible.
F.
Simulated conditions may need to be imposed using an artificial load when it is not practical to
test under design conditions. Before simulating conditions, calibrate testing instruments.
Provide equipment to simulate loads. Set simulated conditions as directed by the CA and
document simulated conditions and methods of simulation. After tests, return settings to normal
operating conditions.
G.
The CA may direct that set points be altered when simulating conditions is not practical.
H.
The CA may direct that sensor values be altered with a signal generator when design or
simulating conditions and altering set points are not practical.
I.
If tests cannot be completed because of a deficiency outside the scope of the HVAC&R system,
document the deficiency and report it to the Owner. After deficiencies are resolved, reschedule
tests.
J.
If the testing plan indicates specific seasonal testing, complete appropriate initial performance
tests and documentation and schedule seasonal tests.
3.4
HVAC&R SYSTEMS, SUBSYSTEMS, AND EQUIPMENT TESTING PROCEDURES
A.
HVAC&R Instrumentation and Control System Testing: Assist the CA with preparation of
testing plans. Prefunctional checklists and functional test forms will be provided by CA during
construction phase.
B.
Pipe system cleaning, flushing, hydrostatic tests and chemical treatment requirements:
HVAC&R Subcontractor shall prepare a pipe system cleaning, flushing, and hydrostatic testing
plan. Provide cleaning, flushing, testing, and treating plan and final reports to the CA. Plan
shall include the following:
1.
2.
3.
4.
C.
Sequence of testing and testing procedures for each section of pipe to be tested, identified
by pipe zone or sector identification marker. Markers shall be keyed to Drawings for
each pipe sector, showing the physical location of each designated pipe test section.
Drawings keyed to pipe zones or sectors shall be formatted to allow each section of
piping to be physically located and identified when referred to in pipe system cleaning,
flushing, hydrostatic testing, and chemical treatment plan.
Description of equipment for flushing operations.
Minimum flushing water velocity.
Tracking checklist for managing and ensuring that all pipe sections have been cleaned,
flushed, hydrostatically tested, and chemically treated.
HVAC&R Distribution System Testing: Provide technicians, instrumentation, tools, and
equipment to test performance of air and hydronic distribution systems; special exhaust; and
other distribution systems, including HVAC&R terminal equipment and unitary equipment.
COMMISSIONING OF HVAC SYSTEM
23 09 50-4
MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30
D.
Vibration and Sound Tests: Provide technicians, instrumentation, tools, and equipment to test
performance of vibration isolation and seismic controls.
E.
See Section 01 91 00 Commissioning Requirements for contractor’s responsibilities and
retesting procedures.
END OF SECTION 23 09 50
COMMISSIONING OF HVAC SYSTEM
23 09 50-5
Monterey Peninsula College
Art Department Modernization Buildings 1 and 30
SECTION 260519
LINE VOLTAGE WIRE AND CABLE
PART 1 - GENERAL
1.01 Description of Work:
A. The work of this Section consists of providing all wire and cable rated 600 volts or less,
including splices and terminations, as shown on the Drawings and as described herein.
1.02 Related Work:
A. See the following Specification Section for work related to the work in this Section:
1. 260542
Conduits, Raceways and Fittings.
2. 260533
Junction and Pull Boxes.
1.03 Quality Assurance
A. Field tests shall be performed as specified in paragraph 3.04 of this Section.
PART 2 - PRODUCTS
2.01 Conductors:
A. Conductors shall be copper, type THHN/THWN/MTW oil and gasoline resistant, 600
volt rated insulation.
B. Conductors shall be stranded copper.
C. Minimum power and control wire size shall be No. 12 AWG unless otherwise noted.
D. All conductors used on this Project shall be of the same type and conductor material.
2.02 Cables:
A. All individual conductors shall be copper with type THHN/THWN, 600 volt rated
insulation.
LINE VOLTAGE WIRE AND CABLE
260519-1
Monterey Peninsula College
Art Department Modernization Buildings 1 and 30
C. Insulation Marking - All insulated conductors shall be identified with printing colored
to contrast with the insulation color.
D. Color Coding - As specified in paragraph 3.03.
E. Special Wiring - Where special wiring is proposed by an equipment manufacturer,
submit the special wiring requirements to the Owner's Representative and, if approved,
provide same. Special wire shall be the type required by the equipment manufacturer.
F. Other Wiring - Wire or cable not specifically shown on the Drawings or specified, but
required, shall be of the type and size required for the application and as approved by
the Owner's Representative.
G. Manufacturer - Acceptable manufacturers including Cablec, Southwire, or equal.
2.03 Terminations:
A. Manufacturer - Terminals as manufactured by T&B, Burndy or equal.
B. Wire Terminations – Stranded conductors shall be terminated in clamping type
terminations which serve to contain all the strands of the conductor. Curling of a
stranded conductor around a screw type terminal is not allowed. For screw type
terminations, use a fork type stake-on termination on the stranded conductor. Use only
a stake-on tool approved for the fork terminals selected.
C. End Seals - Heat shrink plastic caps of proper size for the wire on which used.
2.04 Tape:
A. Tape used for terminations and cable marking shall be compatible with the insulation
and jacket of the cable and shall be of plastic material.
PART 3 - EXECUTION
3.01 Cable Installation:
A. Clean Raceways - Clean all raceways prior to installation of cables as specified in
Section 260542 - Conduits Raceway and Fittings.
B. All line voltage wiring shall be installed in conduit.
LINE VOLTAGE WIRE AND CABLE
260519-2
Monterey Peninsula College
Art Department Modernization Buildings 1 and 30
C. All feeder conductors shall be continuous from equipment to equipment. Splices in
feeders are not permitted unless specifically noted or approved by the Electrical
Engineer.
D. All branch circuit wiring shall be run concealed in ceiling spaces, walls, below floors or
in crawl spaces unless noted otherwise.
E. Cable Pulling - Exercise care in pulling wires and cables into conduit or wireways so as
to avoid kinking, putting undue stress on the cables or otherwise abrading them. No
grease will be permitted in pulling cables. Only soapstone, talc, or UL listed pulling
compound will be permitted. The raceway construction shall be complete and
protected from the weather before cable is pulled into it. Swab conduits before
installing cables and exercise care in pulling, to avoid damage to conductors.
F. Bending Radius - Cable bending radius shall be per applicable code. Install feeder
cables in one continuous length.
G. Equipment Grounding Conductors - Provide an equipment grounding conductor,
whether or not it is shown on the Drawings, in all conduits or all raceways.
H. Panelboard Wiring - In panels, bundle incoming wire and cables which are No. 6 AWG
and smaller, lace at intervals not greater than 6 inches, neatly spread into trees and
connect to their respective terminals. Allow sufficient slack in cables for alterations in
terminal connections. Perform lacing with plastic cable ties or linen lacing twine.
Where plastic panel wiring duct is provided for cable runs, lacing is not necessary
when the cable is properly installed in the duct.
3.02 Cable Terminations and Splices:
A. Splices - UL Listed wirenuts.
B. Terminations - Shall comply with the following:
1. Make up and form cable and orient terminals to minimize cable strain and stress on
device being terminated on.
2. Burnish oxide from conductor prior to inserting in oxide breaking compound filled
terminal.
3.03 Circuit and Conductor Identification:
LINE VOLTAGE WIRE AND CABLE
260519-3
Monterey Peninsula College
Art Department Modernization Buildings 1 and 30
A. Color Coding - Provide color coding for all circuit conductors. Insulation color shall
be white for neutrals and green for grounding conductors. Conductor colors shall be as
follows:
VOLTAGE
208/120V
480/277V
Phase A
Phase B
Phase C
Neutral
Ground
Black
Red
Blue
White
Green
Brown
Orange
Yellow
Grey
Green
B. Color coding shall be in the conductor insulation for all conductors #10 AWG and
smaller; for larger conductors, color shall be either in the insulation or in colored
plastic tape applied at every location where the conductor is readily accessible.
C. Circuit Identification - All underground distribution and service circuits shall be
provided with plastic identification tags in each secondary box and at each termination.
Tags shall identify the source transformer of the circuit and the building number(s)
serviced by the circuit.
3.04 Field Tests:
A. All systems shall test free from short circuits and grounds, shall be free from
mechanical and electrical defects, and shall show an insulation resistance between
phase conductors and ground of not less than the requirements of the CEC. All circuits
shall be tested for proper neutral connections.
B. Insulation Resistance Tests: Perform insulation resistance tests on circuits with #2
AWG and larger conductors to be energized with a line-to-neutral voltage of 120 volts
or more. Make these tests before all equipment has been connected. Test the insulation
with a 500Vdc insulation resistance tester with a scale reading 100 megohms. The
insulation resistance shall be 2 megohms or more. Submit results for review.
END OF SECTION
LINE VOLTAGE WIRE AND CABLE
260519-4