MPC Art Addendum 1 R..
Transcription
MPC Art Addendum 1 R..
ADDENDUM #1 to DRAWINGS & PROJECT MANUAL SPECIFICATIONS For MPC – Art Department Modernization, Building #1 & #30 Modifications 980 Fremont Street, Monterey, California May 7, 2013 The Contract Documents for the above listed project are hereby amended, and the following modifications shall be made a part of said documents and shall be subject to all applicable requirements as if originally shown or specified. Bidders shall acknowledge receipt of this Addendum on the Bid Form. PRE-BID REQUESTS for INFORMATION: PB001 SUBJECT: Detail 8/A9.4 calls out 2” diameter holes with screen. The (E) trough is to remain with only the gutter replaced. Are these (E) holes? If not, how do we install the screens? RESPONSE: All roof fascias and frieze boards are to be replaced (see revised demolition plans, attached); therefore ventilation holes will be new. PB002 SUBJECT: The specifications in 004513 Statement of Qualifications Form on section 5 question 5.9 states that if the bidders workers compensation insurance EMR is more than 1.25 the bidder is not qualified to bid this project. Our construction firm’s loss experience during the past 4 years would result in an EMR of .99. California law requires that our firm’s loss experience be calculated with the loss experience of every firm owned by our principal, which includes other businesses unrelated to the construction industry. This means of calculation results in an EMR higher than 1.25 due to greater loss experiences in our principal’s other non-construction businesses. Please confirm that our firm is permitted to bid this project because our loss experience when calculated in the same manner as any other stand alone construction firm would be much less than the Owner’s threshold of 1.25. RESPONSE: Please see revised sections 002113 and 004513 attached. Section 002113 article 12.6.5 the last item has been stricken from the paragraph. Section 004513 article 5.9 and 5.10 have been removed in their entirety. PB003 SUBJECT: Sheet E4.1, Note 26: “Provide and install Siemens EMS panel below lighting relay panel. . . .” Question: If we are to provide Siemens panel, please provide model number, etc. for this piece of equipment. RESPONSE: The Siemens Panel will be provided by Siemens Contractor. Please note location shall be below lighting control Panel. PB004 SUBJECT: Door 112B – Group 23: 3’6” x 6’-8”. Group 23 is written as a pair of doors. Please clarify spec for hardware group. Please specify change. RESPONSE: Hardware group 23 has been updated in revised Section 087100, attached. PB005 SUBJECT: Where is the actual IDF location? Where is the 12 strand multi-mode fiber going? RESPONSE: The existing IDF locations are shown on Sheet E3.1. The fiber and copper cables are going to be spliced and extended to new IDF for Building #1. The fiber and copper cables for relocated IDF to Building #30 will be preserved and reconnected to IDF which is to be relocated about 10 feet from existing location. PB006 SUBJECT: Section 007313 Special Conditions, Item #14 – Please clarify if aircraft liability insurance is required. Please clarify if pollution liability insurance is required with the limits indicated. Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1 1 PB007 PB008 PB009 PB0010 PB0011 PB0012 PB0013 PB0014 PB0015 PB0016 PB0017 PB0018 PB0019 RESPONSE: Aircraft liability insurance is required if aircraft is used for lifting items on the construction site; otherwise it is not required. Pollution liability insurance is required with the limits indicated. SUBJECT: Please confirm that all hazardous abatement work will be performed by a separate contract and is not in this project’s scope. RESPONSE: All hazardous abatement will be done under separate contract through the owner. SUBJECT: There are no window heights noted or shown at Building 30 windows W3, W4, W5, W6 and W7. We will need low and high point of frame to verify a 2” x 4 ½” system will meet the structural requirements. If they are over 13’ tall they might need to be curtain wall. RESPONSE: Windows are just under 13’ overall at the peak. SUBJECT: Are the structural mullions the wood post shown on 6/A9.2? RESPONSE: Yes. SUBJECT: Please verify whether the type of storefront finish is paint or anodizing. The documents note factory finish with a Permadized finish, which is anodizing, and also notes Fluoropolymer, which is paint. See part 2.10 paragraph B of Section 084113. RESPONSE: Permadize is a coating. It is not anodizing. SUBJECT: Please clarify if any of the storefront systems are to be deferred approval. RESPONSE: DSA did not require deferred approval at back check. No window exceeds 10’ in both directions. SUBJECT: The bid form indicates there are two alternates whereas Section 012300 indicates there are none. Please confirm what if any alternates are required. RESPONSE: There are no alternates. Please see revised page 5 of attached Section 004213. SUBJECT: If there will be any permits that are the responsibility of the contractor, please identify what permits, the agency, and the point of contact so that cost can be obtained. RESPONSE: There are no permits the contractor will be responsible for. SUBJECT: Section 015100 requires the contractor to pay for water usage. Please provide the water rate that the contractor will be charged. RESPONSE: The district will not be charging for the water usage. SUBJECT: Will the NIC art lockers between the two buildings be open to students during construction? RESPONSE: No, only the one furthest east will be used during the project; this locker structure is to be left outside the fenced area. SUBJECT: Please confirm if this project has phases of construction. RESPONSE: There will not be phases to the construction portion of this project; construction start and completion dates are for both buildings. There is a scheduled time frame for the site work north of Building 1, as noted in revised Section 011000, Summary of Work, attached. SUBJECT: Will abatement be done for both buildings at the same time? RESPONSE: Both buildings will start abatement and complete 99% before construction starts, due to coordination of scopes. It is expected the abatement contractor will be required to return for some small items during the construction period. SUBJECT: In janitor’s closet (Building 30) door 115 is called out but there is another door or a partition style in the room. Please advise. RESPONSE: The partition and door shall be sheet metal and shall be sealed with gasket tape. SUBJECT: Please confirm there is no scope for the footings at the modified (E) wood fence. Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1 2 PB0020 PB0021 PB0022 PB0023 PB0024 PB0025 PB0026 PB0027 PB0028 RESPONSE: Confirmed. SUBJECT: Demo sheet A2.1 calls out (N) gutter and downspouts. Please advise if this is to be copper. RESPONSE: Gutter and downspouts to match standing seam metal roof panels. SUBJECT: Please advise if the tackable panels require backing/blocking. RESPONSE: No. SUBJECT: Please advise if the (N) galvanized handrails are to be painted. RESPONSE: No. SUBJECT: Sheet A2.2 shows hatch marks along the building with no definition. Please advise. RESPONSE: See note which designates clips @ 12” OC at “cross hatched areas.” SUBJECT: Civil drawings state “BLDG 21” at title (above C2G). Please advise scope at BLDG 21. RESPONSE: No scope for Building 21. SUBJECT: Sheet S2.3. Please identify object in the corner of Rm 113. RESPONSE: Loose furniture – disregard. SUBJECT: Contractor assumes that any shear wall noted (E) is existing with no scope. Please confirm. RESPONSE: Confirmed. SUBJECT: Sheet S8.3, detail 11 shows a bracket but no specification is called out. Please advise. RESPONSE: Detail 11/S8.3 calls for the steel bracket to be plate 3/16” with 5 each wood screws. SUBJECT: Is Ethernet provided in each of the two buildings? RESPONSE: Cabling is to be provided and installed by systems contractor. CAT 6 cable. See Structured Cabling spec section. ADDITIONAL ITEMS: DRAWINGS: ITEM 1 Sheets A2.1, A5.1, A9.4: Use mesh grate shown in Detail 13A/A9.4 for all trenches. Change solid trench cover in Glaze Mixing 110 to mesh grate. ITEM 2 Sheets A6.1, A6.4, E4.1: Add motorized roller shades at high windows in Drawing Lab 101 and Painting 113 as shown on attached drawings ASK1.1 and ASK 1.3. Divide lower manually operated roller shades into segments as shown on attached drawings ASK1.2 and ASK1.3. ITEM 3 Sheet A2.3: Add base cabinet and mail sort unit in Division Office 100. See attached drawing ASK1.4. ITEM 4 Sheets A2.3, A7.1: Change width of door 103B to 4’-0”. Locate hinge side of door at (E) hinge side jamb. ITEM 5 Sheets A2.4, E5.1: Add ceiling track lighting in Building 1 Conference Room 107 as shown on ASK1.5 and ESK1.6. ITEM 6 Sheet A6.3: See ASK1.6 for elevation of island cabinet in Storage 108. ITEM 7 Sheet A6.2: See ASK1.7 for elevation of cabinetry in Glaze Mixing 110. ITEM 8 Sheets A2.1, A2.3: Add 3’ wide teacher cabinets in Printmaking Lab 103, Painting Lab 113, Drawing Lab 101, and Kiln Room 112 in locations shown on attached drawing ASK1.8 and detailed on ASK1.9. ITEM 9 Sheet A6.3: Change storage cabinet on south wall of Storage 108 to teacher cabinet detailed on ASK 1.9. Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1 3 ITEM 10 ITEM 11 ITEM 12 ITEM 13 ITEM 14 ITEM 15 ITEM 16 ITEM 17 ITEM 18 ITEM 19 ITEM 20 ITEM 21 ITEM 22 ITEM 23 ITEM 24 ITEM 25 ITEM 26 Sheets A6.1, A6.2, A9.3: Modify sections of wall shelving units in Ceramics Lab 113 and Throwing Wheel Lab 104 that have hinged VDS on them as shown on attached drawings ASK1.10 and ASK1.11. Sheets A2.3, A5.1, A6.3, P2.1: Add cabinetry and accessible sink at west wall of Conference Room in Building 1 as shown on ASK1.13 and PSK1.13. Sheet A2.1: Make revisions to Building 30 Demolition Plan as noted on attached revised Sheet A2.1. Sheet A2.3: Make revisions to Building 1 Demolition Plan as noted on attached revised Sheet A2.3. Sheet A5.1: Change portion of south wall in Dry Bulk Storage 109 to 2x6 stud framing as shown on ASK 1.12. Sheets A2.2, A2.4: Add note to Roof Plans: “Allow for 8 downspouts each building.” Sheets A6.1, A9.3: Add cabinetry below display cases as shown on ASK1.14 and ASK 1.15. Sheet M4.1: Revise note on Partial Floor Plan 2: Do not prime and paint galvanized steel hoods. Sheets M0.2, M2.2, M6.1: Change fan EF-30-6 and add roof hood IH-30-5 per attached AD1/M1 and AD1/M2; change exhaust hood in Glaze Mixing Room as shown on attached AD1/M3. Sheet E1.2: Revise Panelboard Schedules as shown on ESK 1.1, ESK 1.2. and ESK 1.3. Sheet E6.3: Revise Podium Panel Elevation as shown on ESK 1.4. Sheet E5.1: Revise light fixture switching to dimming switches for dimmable light fixtures as shown on ESK1.5. Sheet E5.1: Add emergency lighting in restrooms as shown on ESK1.7. Sheet E5.1: Revise light fixture switching to dimming switches for dimmable light fixtures as shown on ESK1.8. Sheet E3.1: Revise callout of existing pull box at Building #1 as shown on ESK1.9. Sheet E3.1: Revise sheet notes #4 and #5 with regards to splicing and extending existing fiber to new IDF location for Building #30 as shown on ESK1.10. Sheet E4.1: Make changes to Power Plans as shown on attached revised Sheet E4.1. SPECIFICATIONS ITEM 1 ITEM 2 ITEM 3 ITEM 4 ITEM 5 ITEM 6 ITEM 7 “2.3 Table of Contents; replace with attached revised Table of Contents with added sections. Section 002113, Instructions for Bidders. Portion of paragraph 12.6.5 is deleted; see revised section, attached. Section 004510, Subcontractors List. Section has been revised to clarify that address is “city and state”; see revised section, attached. Section 004513, Statement of Qualifications. Paragraphs 5.9 and 5.10 are deleted; see revised section, attached. Section 011000, Summary of Work. Subparagraphs B, C, and D are added to paragraph 1.04, Work Sequence or Phasing; see revised section, attached. Section 019100, Commissioning Requirements. New section is added in its entirety; see new section, attached. Section 061053, revise paragraphs 2.3 and 2.4; revise to read as follows: EXTERIOR BOARD ON BOARD SIDING, MATCHING TRIM AND FENCE BOARDS A. General: Kiln dried western red cedar, select, tight knot, appearance grade, full length without splices. Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1 4 B. Siding material shall match the existing siding actual thickness, believed to be 7/8 inch actual, contractor to confirm. Lengths shall be full length without splices. C. Trim boards shall be sized as detailed. D. Fence Boards shall be 1 x 6 nominal, lengths as detailed.” 2.4 FASCIA BOARDS E. General: Preservative treated, pre-primed, finger jointed Radiata Pine as manufactured by Bodyguard Products, Limited or approved equal. F. Fascia Boards shall be 2 by 10 nominal, 20 foot lengths.” ITEM 8 ITEM 9 Section 074113, paragraph 3.1A; delete “…gutters, downspouts,…” from this sentence. Section 084113; delete paragraph 2.7. ITEM 10 Section 099113, paragraph 1.7.A.1; revise to read as follows: “1. Initial exterior paint prep work including removal of loose and unstable hazardous materials, feathering of remaining stable material to adjacent unfinished surfaces and priming of existing unpainted surfaces has been executed by the Owner under a separate contract.” ITEM 11 Section 099113, paragraph 1.7.A.2; revise to read as follows: “2 ITEM 12 If materials requiring removal or further prep work are encountered, do not disturb; immediately notify Owner. Owner will remove or prep hazardous materials under a separate contract.” Section 099113, paragraph 2.2.C; add paragraph C as follows: “C. Exterior colors may involve up to two different base exterior wall colors and two different accent colors for doors, frames, etc., as selected by the architect.” ITEM 13 Section 099123, paragraph 2.2.E; add paragraph E as follows: “E. Interior colors may involve up to 5 different base wall colors, 5 accent wall colors, and two different accent colors for doors, frames, etc., as selected by the architect.” ITEM 14 ITEM 15 Section 099123; delete paragraph 3.3.F. Section 102800, paragraph 2.2.L; add paragraph L as follows: “L. Paper Towel Dispenser (H): 1. 2. Basis-of-Design Product: ASI 8522. Mounting: Surface. Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1 5 3. 4. 5. ITEM 16 ITEM 17 ITEM 18 ITEM 19 Minimum Capacity: One 8 inch wide, by 8 inch diameter standard towel roll up to 800 feet. Material and Finish: Stainless steel, No. 4 finish (satin), 18 gauge door and 22 gauge cabinet. Operation: Manual, accessible lever. Section 122413, Roller Window Shades. New section is added in its entirety; see new section, attached. Section 230900, Temperature Controls. New section is added in its entirety; see new section, attached. Section 230950, Commissioning Requirements. New section is added in its entirety; see new section, attached. Section 260519, Low Voltage Cable. Delete Paragraph 2.02B. The use of ROMEX/Nonmetallic cable in NOT allowed. Revised Section 260519 is attached. Art Department Modernization Building #1 & #30 Modifications - Addendum No. 1 6 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com EN S ED A RCH IT E CT S IA L I C T A T E O F FO CA LI R N HGHB Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 Architecture, Planning, Urban Design 9699 Blue Larkspur Lane, Suite 201 Monterey, California 93940 Tel 831 375-9594 Fax 831 646-9042 Monterey Peninsula College ART DEPARTMENT MODERNIZATION: BUILDINGS 1 AND 30 AURUM CONSULTING E NGINEERS M ONTEREY B AY, INC. Project No. 11188.00 60 Garden Court Suite 210 Monterey, CA 93940 T.831.646.3330 F.831.646.3336 www.acemb.com 27-C1 01-112810 Drawing Title: Scale: Sheet: E4.1 11 Of Revision: Date: 18 Sheets Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 TABLE OF CONTENTS SECTION 000110 Division Section Title Division 00 Procurement and Contracting Requirements 000110 000121 001113 002113 004213 004510 004513 004519 004526 004527 004547 004547.1 004547.2 004547.3 004547.4 004547.5 004547.6 004547.7 005213 006000 006110 006113.13 006113.16 007213 007313 Table of Contents DSA Form 103; Statement of Structural Tests and Special Inspections Notice Calling for Bids Instruction to Bidders Bid Proposal Subcontractors List Statement of Qualifications Non-Collusion Affidavit Certificate of Workers Compensation Drug-Free Workplace Certification Disabled Veteran Business Enterprises Participation Goal Policy DVBE Worksheets; Attachment A; Bidders DVBE Statement DVBE Worksheets; Attachment B; Subcontractible Items of Work DVBE Worksheets; Attachment C; DVBE Participation Summary DVBE Worksheets; Attachment D; DVBE Certification DVBE Worksheets; Attachment E; DVBEs Contacted DVBE Worksheets; Attachment F; DVBE Sub-Bids Not Accepted By Bidder DVBE Worksheets; Attachment G; Verification of DVBE Solicitations Agreement Project Forms Bid Bond Performance Bond Labor and Material Payment Bond General Conditions Special Conditions Division 01 General Requirements 011000 012000 012100 012300 012500 012613 Summary of Work Price and Payment Procedures Allowances Alternates Substitution Procedures Requests for Interpretation Section 000110 Pg #1 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 013100 013119 013216 013300 013323 013500 014100 014100.01 014213 014216 014219 014339 014523 015000 015100 015639 015713 016000 017123 017310 017329 017700 017800 019100 Project Management and Coordination Project Meetings Construction Progress Schedule Submittal Procedures Shop Drawings, Product Data, and Samples Special Procedures Regulatory Requirements Added Requirements for DSA Reviewed Projects Abbreviations, Symbols Definitions Reference Standards Mockups Testing and Inspection Temporary Facilities and Controls Temporary Utilities Temporary Tree and Plant Protection Temporary Erosion and Sediment Control Product Requirements Field Engineering Selective Demolition Cutting and Patching Closeout Procedures Closeout Submittals Commissioning Requirements DIVISION 02 EXISTING CONDITIONS Not Used DIVISION 03 CONCRETE 031100 Concrete Forming 032000 Concrete Reinforcing 033000 Cast-In-Place Concrete DIVISION 04 MASONRY Not Used DIVISION 05 METALS 051200 Structural Steel 053100 Steel Decking Section 000110 Pg #2 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 DIVISION 06 WOOD, PLASTICS, AND COMPOSITES 061000 061053 064116 066600 Rough Carpentry Miscellaneous Carpentry Plastic Laminate-Faced Architectural Cabinets Fiberglass Reinforced Products DIVISION 07 THERMAL AND MOISTURE PROTECTION 072100 074113 076200 078413 079200 Thermal Insulation Standing Seam Metal Roof Panels Sheet Metal Flashing and trim Penetration Firestopping Joint Sealants DIVISION 08 OPENINGS 081113 081416 083113 084113 087100 088000 089119 Hollow Metal Doors and Frames Flush Wood Doors Access Doors and Frames Aluminum Entrances and Storefronts Door Hardware Glazing Wall Louvers DIVISION 09 FINISHES 092900 093000 095113 096513 096519 096813 097202 097720 099113 099123 Gypsum Board Tiling Acoustical Panel Ceilings Resilient Base and Accessories Resilient Tile Flooring Tile Carpeting Wall Coverings Decorative Fiberglass Reinforced Wall Panels Exterior Painting Interior Painting DIVISION 10 SPECIALTIES 101100 101102 101423 102113 102800 Visual Display Surfaces Tackable Wall Panels Panel Signage Toilet Compartments Toilet and Bath Accessories Section 000110 Pg #3 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 104416 Fire Extinguishers 105113 Metal Lockers 105120 Phenolic Lockers DIVISION 11 Not Used DIVISION 12 FURNISHINGS 122413 Roller Window Shades DIVISION 13 THROUGH 21 Not Used DIVISION 22 PLUMBING 220000 Plumbing General 220500 Plumbing DIVISION 23 HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC) 230000 230500 230900 230950 Mechanical General Requirements HVAC Temperature Controls HVAC Commissioning DIVISION 24 THROUGH 25 Not Used DIVISION 26 ELECTRICAL 260500 260519 260526 260533 260542 260543 260544 262416 262726 262816 265100 265110 Electrical General Requirements Low Voltage Cable Grounding J-Boxes Conduits Underground Ducts Pull Boxes Panel Devices Breakers Lighting OCC-Sensor Section 000110 Pg #4 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 DIVISION 27 COMMUNICATIONS 270500 Voice and Data Cat6 DIVISION 28 ELECTRONIC SAFETY AND SECURITY 283100 Fire Alarm System DIVISION 29 THROUGH 30 Not Used DIVISION 31 EARTHWORK 311000 312000 312500 316329 Site Clearing & Demolition Earth Moving Erosion Control Cast-in-Place Concrete Drilled Piers DIVISION 32 EXTERIOR IMPROVEMENTS 321313 Site Concrete 323100 Screen Fencing DIVISION 33 UTILITIES 334100 Storm Drainage Section 000110 Pg #5 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 Section 000110 Pg #6 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 INSTRUCTIONS FOR BIDDERS 1. Preparation and Submittal of Bid Proposal. 1.1. Bid Proposal Preparation. All information required by the bid forms must be completely and accurately provided. Numbers shall be stated in both words and figures where so indicated in the bid forms; conflicts between a number stated in words and in figures are governed by the words. Partially completed Bid Proposals or Bid Proposals submitted on other than the bid forms included herein are non-responsive and will be rejected. Bid Proposals not conforming to these Instructions for Bidders and the Notice to Contractors Calling for Bids (“Call for Bids”) may be deemed non-responsive and rejected. 1.2. Bid Proposal Submittal. Bid Proposals shall be submitted at the place designated in the Call for Bids in sealed envelopes bearing on the outside the Bidder’s name and address along with an identification of the Work for which the Bid Proposal is submitted. Bidders are solely responsible for timely submission of Bid Proposals to the District at the place designated in the Call for Bids. 1.3. Date and Time of Bid Proposal Submittal. A Bid Proposal is submitted only if the outer envelope containing the Bid Proposal is marked with the Project title and is received by a District Purchasing Department representative for logging-in at (or before) the latest date and time for submittal of Bid Proposals. The official U.S. time-clock website: http://www.time.gov/timezone.cgi?Pacific/d/-8/java is controlling and determinative as to the time of the Bidder’s submittal of the Bid Proposal. The foregoing notwithstanding, whether or not Bid Proposals are opened exactly at the time fixed in the Call for Bids, no Bid Proposals shall be received or considered by the District after it has commenced the public opening and reading of Bid Proposals; Bid Proposals submitted after such time are non-responsive and will be returned to the Bidder unopened. 2. Bid Security. Each Bid Proposal shall be accompanied by Bid Security in the form of: (i) cash, (ii) a certified or cashier’s check made payable to the District or (iii) a Bid Bond, in the form and content attached hereto, in favor of the District executed by the Bidder as a principal and a Surety as surety (the “Bid Security”) in an amount equal to Ten Percent (10%) of the Bid Proposal amount, inclusive of the price(s) proposed for additive Alternate Bid Items, if any. A Bid Proposal submitted without the required Bid Security is non-responsive and will be rejected. If the Bid Security is in the form of a Bid Bond, the Bidder’s Bid Proposal shall be deemed responsive only if the Bid Bond is in the form and content included herein and the Surety is an Admitted Surety Insurer under Code of Civil Procedure §995.120. 3. Documents Accompanying Bid Proposal; Signatures. Documents which must be submitted with each Bid Proposal are identified in the Call for Bids. Any document submitted with a Bid Proposal which is not complete, accurate and executed, as required by each document, will result in the Bid Proposal being deemed non-responsive. 4. Bidder Modifications; Withdrawal or Modification of Submitted Bid Proposal. 4.1. Bidder Modifications to Bid Forms Prohibited. Modifications by a Bidder to the bid forms which are not specifically called for or permitted may result in the Bidder’s Bid Proposal being deemed non-responsive and rejected. 4.2. Withdrawal or Modification of Submitted Bid Proposal. A Bidder may not withdraw or modify a Bid Proposal submitted to the District except in strict conformity to the following. Bid Proposals may be withdrawn or modified only if: (i) the Bidder submitting the Bid Proposal submits a request for withdrawal or modification in writing to the District; and (ii) the written withdrawal or modification request is actually received by the District prior to the latest date/time for submittal of Bid Proposals. Requests for withdrawal of a Bid Proposal after the Page 1 Section 00 21 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 public opening of Bid Proposals pursuant to Public Contract Code §5100 et seq. will be considered only if in strict conformity with requirements of Public Contract Code §5100 et seq. 5. Erasures; Inconsistent or Illegible Bid Proposals. Bid Proposals must not contain any erasures, interlineations or other corrections unless the same are suitably authenticated by affixing in the margin immediately opposite such erasure, interlineations or correction the surname(s) of the person(s) signing the Bid Proposal. Any Bid Proposal not conforming to the foregoing may be deemed by the District to be non-responsive. If any Bid Proposal or portions thereof, is determined by the District to be illegible, ambiguous or inconsistent, whether by virtue of any erasures, interlineations, corrections or otherwise, the District may reject such a Bid Proposal as being non-responsive. 6. Examination of Site and Contract Documents. Each Bidder shall, at its sole cost and expense, inspect the Site and to become fully acquainted with the Contract Documents and conditions affecting the Work. Failure of a Bidder to receive or examine any of the Contract Documents or to inspect the Site shall not relieve such Bidder from any obligation with respect to the Bid Proposal, or the Work required under the Contract Documents. The District assumes no responsibility or liability to any Bidder for, nor shall the District be bound by, any understandings, representations or agreements of the District’s agents, employees or officers concerning the Contract Documents or the Work made prior to execution of the Contract which are not in the form of Bid Addenda duly issued by the District. The submission of a Bid Proposal shall be deemed prima facie evidence of the Bidder’s full compliance with the requirements of this section. 7. Withdrawal of Bid Proposal. Any Bidder may withdraw its Bid Proposal only written request actually received by the District prior to the scheduled closing time for the receipt of Bid Proposals and the District’s public opening and reading of Bid Proposals; written requests to withdraw a submitted Bid Proposal received by the District after the scheduled closing time for receipt of Bid Proposals shall not be considered by the District, nor effective to withdraw such Bid Proposal. 8. Agreement and Bonds. The Agreement which the successful Bidder, as Contractor, will be required to execute along with the forms Payment Bond, Performance Bond and other documents and instruments which are required to be furnished are included in the Contract Documents and shall be carefully examined by the Bidder. The required number of executed copies of the Agreement and the form and content of the Performance Bond and the Payment Bond and other documents or instruments required at the time of execution of the Agreement are specified in the Contract Documents. 9. Interpretation of Drawings, Specifications or Contract Documents. Inquiries or clarification requests submitted by a Bidder in strict accordance with the Call for Bids will be responded to in writing by or on behalf of the District. If a response to an inquiry or clarification: (i) includes: interpretation, correction or clarification of the Contract Documents; or (ii) affects requirements of the bidding process or submittal of Bid Proposals, the District will issue addenda to the Contract Documents. A copy of any such addendum will be delivered by fax, email or mail to each Bidder who has obtained a set of the Contract Documents. No person is authorized to render an oral interpretation or correction of any portion of the Contract Documents to any Bidder, and no Bidder is authorized to rely on any such oral interpretation or correction. Failure to timely request interpretation or clarification of any portion of the Contract Documents pursuant to the foregoing is a waiver of any discrepancy, defect or conflict therein. 10. District’s Right to Modify Contract Documents. Before the public opening and reading of Bid Proposals, the District may modify the Work, the Contract Documents, or any portion(s) thereof by the issuance of written addenda disseminated to all Bidders who have obtained a copy of the Specifications, Drawings and Contract Documents pursuant to the Call for Bids. If the District Page 2 Section 00 21 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 issues any addenda during the bidding, the failure of any Bidder to acknowledge such addenda in its Bid Proposal will render the Bid Proposal non-responsive and rejected. 11. Bidders Interested in More Than One Bid Proposal; Non-Collusion Affidavit. No person, firm, corporation or other entity shall submit or be interested in more than one Bid Proposal for the same Work; provided, however, that a person, firm or corporation that has submitted a subproposal to a Bidder or who has quoted prices for materials to a Bidder is not disqualified from submitting a sub-proposal, quoting prices to other Bidders or submitting a Bid Proposal for the proposed Work to the District. The form of Non-Collusion Affidavit included in the Contract Documents must be completed and duly executed on behalf of the Bidder; failure of a Bidder to submit a completed and executed Non-Collusion Affidavit with its Bid Proposal will render the Bid Proposal non-responsive. 12. Award of Contract. 12.1. Waiver of Irregularities or Informalities. The District reserves the right to reject any and all Bid Proposals or to waive any irregularities or informalities in any Bid Proposal or in the bidding. 12.2. Award to Lowest Responsive Responsible Bidder. The award of the Contract, if made by the District through action of its Board of Trustees, will be to the responsible Bidder submitting the lowest priced responsive Bid Proposal on the basis of the Base Bid Proposal and Alternate Bid Items, if any, selected in accordance with these Instructions. 12.3. Selection of Alternate Bid Items. If Alternate Bid Items are included in the bidding for the Work, the selection of Alternate Bid Items for inclusion in the scope of the Work of the Contract and for determination of the lowest priced Bid Proposal will be by a “blind-bidder” process. After opening timely submitted Bid Proposals and before the public reading of Bid Proposals, District clerical staff (“Clerical Staff”) who not responsible for selecting Alternate Bid Items for inclusion in the Contract to be awarded will assign each Bidder an alphabetical letter for identification purposes. The Clerical Staff will mask all portions of the Bid Proposal and other documents submitted with Bid Proposals so that the identity of each Bidder is not revealed. The Clerical Staff will maintain a list (“the Bidders List”) which identifies by name and the alphabetical letter assigned by the Clerical Staff to each Bidder. After completing the Bidders List, the Clerical Staff will publicly read the Bid Proposals amounts of each Bidder for the Base Bid as well as each Alternate Bid Item. In this public reading of Bid Proposals, Bidders will not be identified by name; Bidders will be identified only by alphabetical letter assigned to each Bidder by the Clerical Staff. After the public reading of Bid Proposals, the Clerical Staff will provide the Architect and the District’s staff responsible for selection of Alternate Bid Items for inclusion in the Contract to be awarded (“District Project Staff”) copies of Bid Proposals with the identities of Bidders masked. At such time as the Architect and the District Project Staff have determined which Alternate Bid Items, if any are to be included in the scope of Work of the Contract and the Bidder submitting the lowest made a determination of which Bidder (by the alphabetical letter assigned by Clerical Staff) submitted the lowest priced Bid Proposal on the basis of the Base Bid Proposal and the combination of Alternate Bid Items, if any, for inclusion in the scope of Work of the Contract the Clerical Staff will provide the District Project Staff with the Bidders List so that the identity of the Bidder submitting the lowest priced Bid Proposal can be identified. Until such time as the District Project Staff have completed review of Bid Proposals and determination of which Alternate Bid Items are to be included in the Work and the scope of the Contract to be awarded, there will be no communication between the Clerical Staff and the Architect or the District Project Staff regarding the identities of Bidders or disclosure of any portion of the Bidders List to the District Project Staff. 12.4. Alternate Bid Items Not Included in Award of Contract. Bidders are referred to the provisions of the Contract Documents permitting the District, during performance of the Work, Page 3 Section 00 21 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 to add or delete from the scope of the Work any or all of the Alternate Bid Items with the cost or credit of the same being the amount(s) set forth by in the Alternate Bid Items Bid on the Proposal. 12.5. Responsive Bid Proposal. A responsive Bid Proposal shall mean a Bid Proposal which conforms to and complies with requirements of the Bid and Contract Documents. 12.6. Responsible Bidder. 12.6.1. Bidder Capacity. Factors affecting the Bidder’s capacity to perform and complete the Work will be assessed, including: (i) Bidder’s access to labor, materials and other resources necessary to complete the Work; (ii) Bidder’s ability to complete the Work within the time established for completion of the Work, or portions thereof; and (iii) Bidder’s ability to complete warranty obligations. 12.6.2. Bidder Character, Integrity. Factors reflecting the character and integrity of the Bidder, including: (i) other public agency finding/determination, within the past five (5) years, that the Bidder is not responsible; (ii) currently debarred from bidding public works projects or debarment from bidding within past five (5) years; and (iii) false claims liability within the past five (5) years under local, state or federal laws. 12.6.3. Bidder Financial Capability. Factors considered include: (i) sufficiency of the Bidder’s financial resources; (ii) whether the Bidder is current in payment of debts and performance of other financial obligations; and (iii) bankruptcy or insolvency proceedings have been instituted within the past five (5) years. 12.6.4. Bidder Prior Performance. The Bidder’s prior performance on prior public works contracts, including without limitation: (i) cost overruns; (ii) compliance with general conditions and other contractual requirements, including schedule development, schedule updates and coordination of labor, material/equipment procurements and subcontractors; (iii) completion within allocated time; (iv) submittal of unsubstantiated, unsupported or excessive cost proposals, claims or contract adjustment requests; (iv) completion of a project by a surety; (vi) owner’s exercise of default remedies; and (vii) finding or determination by any public agency that the Bidder is not a responsible bidder. 12.6.5. Safety. Factors include: (i) findings of serious or willful safety violations of safety laws, regulations or requirements by any local, state or federal agency within the past five (5) years; (ii) adequacy and implementation of safety plans, programs for on-site and off-site construction and construction related activities. 13. Subcontractors. 13.1. Designation of Subcontractors; Subcontractors List. Each Bidder shall submit a list of its proposed Subcontractors for the proposed Work as required by the Subletting and Subcontracting Fair Practices Act (California Public Contract Code §§ 4100 et seq.) on the form furnished. The failure of any Bid Proposal to include all information required by the Subcontractors List will result in rejection of the Bid Proposal for non-responsiveness. 13.2. Work of Subcontractors. All Bidders are referred to the Contract Documents and the notation therein that all Contract Documents are intended to be complimentary and that the organization or arrangements of the Specifications and Drawings shall not limit the extent of the Work of the Contract Documents. Accordingly, all Bidders are encouraged to disseminate all of the Specifications, Drawings and other Contract Documents to all persons or entities submitting sub-bids to the Bidder. The omission of any portion or item of Work from the Bid Proposal or from the sub-bidders’ sub-bids which is/are necessary to produce the intended results and/or which are reasonably inerrable from the Contract Documents is not a basis for adjustment of the Contract Price or the Contract Time. Page 4 Section 00 21 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 13.3. Subcontractor Bonds. Pursuant to California Public Contract Code §4108, if a Bidder requires a bond or bonds of its Subcontractor(s), whether the expense of procuring such bond or bonds are to be borne by the Bidder or the Subcontractor(s), such requirements shall be specified in the Bidder’s written or published request for sub-bids. Failure of the Bidder to comply with these requirements shall preclude the Bidder from imposing bonding requirements upon its Subcontractor(s) or rejection of a Subcontractor’s bid under California Public Contract Code §4108(b). 14. Workers’ Compensation Insurance. Pursuant to California Labor Code § 3700, the successful Bidder shall secure Workers’ Compensation Insurance for its employees engaged in the Work of the Contract. The successful Bidder shall execute and deliver to the District the form of Workers Compensation Certification included in the Contract Documents concurrently with such Bidder’s delivery of the executed Agreement to the District. 15. Bid Security Return. The Bid Security of the Bidders submitting the three lowest priced Bid Proposals, the number being solely at the discretion of the District, will be held by the District for ten (10) days after the period for which Bid Proposals must be held open (which is set forth in the Call for Bids) or until posting by the successful Bidder(s) of the bonds, certificates of insurance required and return of executed copies of the Agreement, whichever first occurs, at which time the Bid Security of such other Bidders will be returned to them. 16. Forfeiture of Bid Security. If the Bidder awarded the Contract fails or refuses to execute the Agreement within Five (5) calendar days from the date of receiving notification that it is the Bidder to whom the Contract has been awarded, the District may declare the Bidder’s Bid Security forfeited as damages caused by the failure of the Bidder to enter into the Contract and may thereupon award the Contract for the Work to the responsible Bidder submitting the next lowest Bid Proposal or may call for new bids, in its sole and exclusive discretion. 17. Contractors’ License. No Bid Proposal will be considered from a Bidder who, at the time Bid Proposals are opened, is not licensed to perform the Work of the Contract Documents, in accordance with the Contractors’ License Law, California Business & Professions Code §§7000 et seq. This requirement is not a mere formality and will not be waived by the District or its Board of Trustees. The required California Contractors’ License classification(s) for the Work is set forth in the Call for Bids. 18. Non-Discriminatory Employment Practices. It is the policy of the District that there be no discrimination against any prospective or active employee engaged in the Work because of race, color, ancestry, national origin, religious creed, sex, age, marital status or other legally protected classification. All Bidders agree to comply with the District’s non-discrimination policy and all applicable Federal and California anti-discrimination laws including but not limited to the California Fair Employment & Housing Act beginning with California Government Code §§ 12940 et seq. and California Labor Code § 1735. In addition, all Bidders agree to require like compliance by any Subcontractor employed by them on the Work of the Contract. 19. Bidder’s Qualifications. Each Bidder shall submit with its Bid Proposal the form of Statement of Bidder’s Qualifications, which is included within the Contract Documents. All information required by Statement of Bidder’s Qualifications shall be completely and fully provided. Any Bid Proposal not accompanied by the Statement of Bidder’s Qualifications completed with all information required and bearing the signature of the Bidder’s duly authorized representative under penalty of perjury will render the Bid Proposal non-responsive and rejected. If the District determines that any information provided by a Bidder in the Statement of Bidder’s Qualifications is false or misleading, or is incomplete so as to be false or misleading, the District may reject the Bid Page 5 Section 00 21 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 Proposal submitted by such Bidder as being non-responsive. If any response to the “Essential Requirements” section of the Statement of Qualifications is a “not qualified” response, the Bidder’s Bid Proposal will be rejected for failure of the Bidder to meet minimum qualifications for the Work. 20. Substitution of Specified Materials/Equipment. Pursuant to Public Contract Code §3400(a), the District will consider requests of Bidders for the District to consent to substitutions of specified materials/equipment (“Substitution Request”) only during the bidding process. The District will not consider or consent to a Substitution Request thereafter. 20.1. Latest Date/Time for Submittal of Substitution Request. The latest date/time for a Bidder to submit a Substitution Request is the latest date/time for Bidders to submit a Pre-Bid Inquiry, as set forth in the Call for Bids. The District will not consider or respond to a Substitution Request thereafter. 20.2. Submittal Requirements. Notwithstanding a Bidder’s timely submission of a Substitution Request, the District will not consider or respond to a Substitution Request unless all of the following are complied with by the Bidder: (i) the Substitution Request is submitted on a completed form of Submittal Substitution Form (Document 00 60 02), along with at least the following: (i) technical data establishing the equivalency of the proposed substitution with the specified materials/equipment, including without limitation drawings, performance specifications, samples, test reports, and other similar items; (ii) statement by the Contractor that the proposed substitution is in full compliance with the requirements of the Contract Documents and the Laws and that incorporation of the proposed substitution in lieu of the specified materials/equipment will not delay completion of the Work or extend the Contract Time; (iii) list of Subcontractors affected by the Substitution Request; and (iv) if the proposed substitution requires re-design or removal of any Work to accommodate the proposed substitution, drawings and engineering calculations prepared by a California licensed architect or registered engineer for the portions of the Work requiring re-design or removal. Notwithstanding submittal of the foregoing, if requested by the District or Architect, the Bidder submitting a Substitution Request shall submit such additional substantiating data as requested by the District or the Architect. 20.3. Specified Materials/Equipment. Where multiple manufacturers of specified materials/equipment are identified or there are multiple materials/equipment specified in the Contract Documents, the first named manufacturer or the first named material/equipment is the basis of the design of the Work; use of any other manufacturer or material/equipment is deemed a substitution which can be furnished and installed by the successful Bidder only if the District consents thereto in accordance with these provisions. 20.4. District Review and Notice of Consent. Timely submitted Substitution Requests will be reviewed by the District and Architect to determine the equivalency of the proposed substitution with the specified materials/equipment. The District’s decision to grant, deny or condition consent to substitute specified materials/equipment is final and not subject to further review or appeal. If the District consents to or conditionally consents to substitution of specified materials/equipment, the District will issue an Addendum identifying the specified materials/equipment and the alternative materials/equipment consent to or conditionally consented to by the District. 20.5. Bidder Responsibilities. If the District consents to or conditionally consents to substituted materials/equipment for those originally specified (Accepted Substitution) and a Bidder elects to incorporate any Accepted Substitution into its Bid Proposal, the Bidder shall be responsible for identifying in the Subcontractors List the Subcontractor(s) necessary to complete installation of the Accepted Substitution. 21. Job-Walk. The District will conduct a Job-Walk at the time(s) and place(s) designated in the Call for Bids. The District may, in its sole and exclusive discretion, elect to conduct one or more JobWalk(s) in addition to that set forth in the Call for Bids, in which event the District shall notify all Page 6 Section 00 21 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 Bidders who have theretofore obtained the Contract Documents pursuant to the Call for Bids of any such additional Job-Walk. If the District elects to conduct any Job-Walk in addition to that set forth in the Call for Bids, the District shall, in its notice of any such additional Job-Walk(s), indicate whether Bidders’ attendance at such additional Job-Walk(s) is/are mandatory. If attendance at the Job Walk is indicated in the Call for Bids as being mandatory, the failure of any Bidder to have its authorized representative present at the entirety of the Job-Walk will render the Bid Proposal of such Bidder to be non-responsive. Where the Job-Walk is mandatory, a Bidder may have more than one authorized representative and/or representatives of its Subcontractors present at the Job-Walk; provided, however that attendance by representatives of the Bidder’s Subcontractors without attendance by a representative of the Bidder shall not be sufficient to meet the Bidder’s obligations hereunder and will render the Bid Proposal of such Bidder to be non-responsive. The District will reject the Bid Proposal of a Bidder who obtains the Bid and Contract Documents after the date of the Mandatory Job-Walks set forth in the Call for Bids unless a Job-Walk is requested by such Bidder and a Job-Walk is conducted by the District in accordance with the following provisions. The District may, in its sole and exclusive discretion, conduct such requested JobWalk taking into consideration factors such as the time remaining prior to the scheduled opening of Bid Proposals. Any such requested Job Walk will be conducted only upon the requesting Bidder’s agreement to reimburse the District for the actual and/or reasonable costs for the District’s staff and its agents and representatives in arranging for and conducting such additional Job-Walk. 22. Public Records. Bid Proposals and other documents responding to the Call for Bids become the exclusive property of the District upon submittal to the District. At such time as the District issues the Notice of Intent to award the Contract pursuant to these Instructions for Bidders, all Bid Proposals and other documents submitted in response to the Call for Bids become a matter of public record and shall be thereupon be considered public records, except for information contained in such Bid Proposals deemed to be Trade Secrets (as defined in California Civil Code § 3426.1) and information provided in response to the Statement of Qualifications. A Bidder that indiscriminately marks all or most of its Bid Proposal as exempt from disclosure as a public record, whether by the notations of “Trade Secret,” “Confidential,” “Proprietary,” or other similar notations, may result in, or render, the Bid Proposal non-responsive and rejected. The District is not liable or responsible for the disclosure of such records, including those exempt from disclosure if disclosure is deemed required by law, by an order of Court, or which occurs through inadvertence, mistake or negligence on the part of the District or its officers, employees or agents. At such time as Bid Proposals are deemed a matter of public record, pursuant to the above, any Bidder or other party shall be afforded access for inspection and/or copying of such Bid Proposals, by request made to the District in conformity with the California Access to Public Records Act, California Government Code §§6250, et. seq. If the District is required to defend or otherwise respond to any action or proceeding wherein request is made for the disclosure of the contents of any portion of a Bid Proposal deemed exempt from disclosure hereunder, the Bidder submitting the materials sought by such action or proceeding agrees to defend, indemnify and hold harmless the District in any action or proceeding from and against any liability, including without limitation attorneys’ fees arising therefrom. The party submitting materials sought by any other party shall be solely responsible for the cost and defense in any action or proceeding seeking to compel disclosure of such materials; the District’s sole involvement in any such action shall be that of a stakeholder, retaining the requested materials until otherwise ordered by a court of competent jurisdiction. 23. Drug Free Workplace Certificate. In accordance with California Government Code §§ 8350 et seq., the Drug Free Workplace Act of 1990, the successful Bidder will be required to execute a Drug Free Workplace Certificate concurrently with execution of the Agreement. The successful Bidder will be required to implement and take the affirmative measures outlined in the Drug Free Workplace Certificate and in California Government Code §§8350 et seq. Failure of the Page 7 Section 00 21 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 successful Bidder to comply with the measures outlined in the Drug Free Workplace Certificate and in California Government Code §§ 8350 et seq. may result in penalties, including without limitation, the termination of the Agreement, the suspension of any payment of the Contract Price otherwise due under the Contract Documents and/or debarment of the successful Bidder. 24. Notice of Intent to Award Contract. Following the public opening and reading of Bid Proposals, the District will issue a Notice of Intent to Award the Contract, identifying the Bidder to whom the District intends to award the Contract and the date/time/place of the District’s Board of Trustees meeting at which award of the Contract will be considered. 25. Bid Protest. 25.1. Submittal of Bid Protest. Any Bidder submitting a Bid Proposal to the District may file a protest of the District’s intent to award the Contract provided that all of the following are complied with: (i) the bid protest is in writing; (ii) the bid protest is filed and received by the District’s Vice-President, Administrative Services not more than five (5) calendar days after the date of issuance of the District’s Notice of Intent to Award the Contract; and (iii) the written bid protest sets forth, in detail, all grounds for the bid protest, including without limitation all facts, supporting documentation, legal authorities and argument in support of the grounds for the bid protest; any matters not set forth in the written bid protest shall be deemed waived. All factual contentions must be supported by competent, admissible and creditable evidence. Any bid protest not conforming to the foregoing shall be rejected by the District as invalid. 25.2. District Review and Disposition of Bid Protest. Provided that a bid protest is filed in strict conformity with the foregoing, the District’s Vice-President, Administrative Services or such individual(s) as may be designated by him/her (“Designee”) will review and evaluate the basis of the bid protest. The District’s Vice-President, Administrative Services or Designee shall provide the Bidder submitting the bid protest with a written statement concurring with or denying the bid protest (Bid Protest Response). The Bid Protest Response is deemed the final action of the District and not subject to appeal or reconsideration by any other employee or officer of the District or the Board of Trustees of the District. The issuance of the Bid Protest Response by the District’s Vice-President, Administrative Services or the Designee is an express condition precedent to the institution of any legal or equitable proceedings relative to the bidding process, the District’s intent to award the Contract, the District’s disposition of any bid protest or the District’s decision to reject all Bid Proposals. If any such legal or equitable proceedings are instituted and the District is named as a party thereto, the prevailing party(ies) shall recover from the other party(ies), as costs, all attorneys’ fees and costs incurred in connection with any such proceeding, including any appeal arising therefrom. Each Bidder shall acknowledge in the Bid Proposal that the foregoing is a binding attorneys’ fee agreement pursuant to Civil Code §1717 and shall be enforceable against the Bidder and the District. [End of Section] Page 8 Section 00 21 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 THIS PAGE INTENTIONALLY BLANK Page 9 Section 00 21 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 SUBCONTRACTORS LIST Project (“the Work”) Art Department Modernization: Buildings 1 and 30 Bidder Name _________________________________________ Bidder’s Representative Signature _________________________________________ (Signature) _________________________________________ (Typed or Printed Name) Licensed Name of Subcontractor Address of Office, Mill or Shop (City & State) Trade or Portion of Work DUPLICATE THIS PAGE AS NECESSARY FOR LISTING ADDITIONAL SUBCONTRACTORS [END OF SECTION] Page 1 Section 00 45 10 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 THIS PAGE INTENTIONALLY BLANK Page 2 Section 00 45 10 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 STATEMENT OF QUALIFICATIONS 1. Bidder Information. 1.1. Contact Information _____________________________________________ Street Address _____________________________________________ City, State, Zip Code Mailing Address Physical Location (if different from mailing address) Telephone/Fax _____________________________________________ Street Address _____________________________________________ City, State, Zip Code (______) __________________ Telephone (______) __________________ Fax 1.2. Bidder Contacts. Name ______________________________________ Telephone: (______)______________________ Contact Information Fax (______)______________________ Email _____________________________ 1.3. California Contractors’ License. License Number(s) ______________________________________ License Classification(s) ______________________________________ Responsible Managing Employee; Responsible Managing Officer Expiration Date(s) ______________________________________ ______________________________________ 1.4. Bidder Form of Entity. Corporation General Partnership Limited Partnership Limited Liability Company Limited Liability Partnership Joint Venture Sole Proprietorship [CONTINUED NEXT PAGE] Page 1 Section 00 45 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 2. Revenue. Complete the following for the Bidder’s construction operations; if any portion of the revenue disclosed is generated by non-construction operations or activities, the Bidder must identify the portion of revenue attributed to construction operations and generally describe business activities of the Bidder that generates non-construction operations related revenue. Calendar Year/ Fiscal Year Annual Gross Revenue Average Dollar Value of all Contracts Dollar Value of Largest Contract 2010 (2009/2010) 2011 (2010/2011) 2012 (2011/2012) 3. References. DSA Project Inspectors Firm Name Address Telephone No. Contact Name Owners (K-12 school districts or community colleges preferred) Owner Name Address Telephone No. Contact Name Architects (K-12 or Community College Projects) Architect Firm Name & Address Telephone No. Architect Firm Contact Name Contact Name [CONTINUED NEXT PAGE] Page 2 Section 00 45 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 4. Insurance. Commercial General Liability Insurance Commercial General Liability Insurance Broker Insurer: _______________________________________ Policy No. _______________________________________ Broker _______________________________________ (Contact Name) ________________________________________ _____________________________________________________ (Street Address) _____________________________________________________ (City, State & Zip Code) (______) __________________ (______) ___________________ Telephone Fax _____________________________________________________ (Email address) Bid, Performance and Labor & Materials Payment Bond Surety Surety: _____________________________________ Surety Broker ____________________________________ _____________________________________________________ (Surety Broker Contact Name) _____________________________________________________ (Street Address) _____________________________________________________ (City, State & Zip Code) (______) __________________ (______) ___________________ Telephone Fax _____________________________________________________ (Email address) Workers Compensation Insurance Workers Compensation Insurance Broker Insurer: _______________________________________ Policy No. _______________________________________ Broker _______________________________________ (Contact Name) ________________________________________ _____________________________________________________ (Street Address) _____________________________________________________ (City, State & Zip Code) (______) __________________ (______) ___________________ Telephone Fax _____________________________________________________ (Email address) [CONTINUED NEXT PAGE] Page 3 Section 00 45 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 5. Essential Requirements. A Bidder will not be deemed qualified if the answer to any of the following questions results in a “not qualified” response and the Bid Proposal submitted by such a Bidder will be rejected for failure of the Bidder to meet minimum qualifications for the Work. 5.1. Bidder possesses a valid and currently in good standing California Contractors’ license for the Classification(s) of Contractors’ License required by the Call for Bids. __ Yes __ No (Not Qualified) 5.2. Bidder has a current commercial general liability insurance policy with coverage limits of at least $1,000,000 per occurrence and $2,000,000 in the aggregate. __ Yes __ No (Not Qualified) 5.3. Bidder has a current workers’ compensation insurance policy as required by the Labor Code or is legally self-insured pursuant to Labor Code §3700. __ Yes __ No (Not Qualified) __ Bidder is exempt from this requirement, because it has no employees 5.4. The Bidder is ineligible or debarred from submitting Bid Proposals for public works projects or public works contracts pursuant Labor Code §1777.1 or Labor Code §1777.7. __ Yes (Not Qualified) __ No 5.5. A public agency, within the past five (5) years conducted proceedings that resulted in a finding that the Bidder, or any predecessor to the Bidder, is not a “responsible” bidder for a public works project or a public works contract. __ Yes (Not Qualified) __ No 5.6. During the last five (5) years, the Bidder or any predecessor to the Bidder, or any of the equity owners of the Bidder have been convicted of a federal or state crime involving fraud, theft, or any other act of dishonesty. __ Yes (Not Qualified) __ No 5.7. During the past five (5) years a Surety has completed any project or the Bidder’s obligations under a construction contract. __ Yes (Not Qualified) __ No 5.8. During the past five (5) years the Bidder has been declared in default under any construction contract to which the Bidder was a party. __ Yes (Not Qualified) __ No 5.9. The Bidder’s Worker’s Compensation Insurance current EMR is more than 1.25. __ Yes (Not Qualified) __ No Page 4 Section 00 45 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 5.10. The Bidder’s Worker’s Compensation Insurance average EMR over the past five (5) years is more than 1.25. __ Yes (Not Qualified) __ No 6. Questionnaire. If the response to any of the following questions is a “yes” complete and accurate details must be attached; failure to attach such details will render the Bid Proposal of the Bidder to be non-responsive and rejected. Responses to the following will be used to evaluate Bidder responsibility. 6.1. Have legal, arbitration or administrative proceedings been brought construction project owner against the Bidder or any of the principals, officers or equity owners of the Bidder within the past ten (10) years which arise out of or are related to any construction project? If “yes” details must include: (i) name of party initiating proceedings against the Bidder; (ii) contact name, address, phone and email address of party initiating proceedings; (iii) circumstances resulting in the initiation of proceedings; (iv) amount or other relief demanded; and (v) outcome of proceedings. __ Yes __ No 6.2. Has the Bidder brought any legal, arbitration or administrative proceedings against the owner of a construction project within the past ten (10) years which arise out of or are related to the construction project? If “yes” details must include: (i) name of owner; (ii) contact name, address, phone and email address of contact person for owner; (iii) circumstances resulting in the initiation of proceedings; (iv) amount or other relief demand; and (v) outcome of proceedings. __ Yes __ No 6.3. Provide the following for three (3) projects the Bidder has completed within the past five (5) years similar in size, scope, function and construction value as the Work: Project Name Project Owner; Contact Information Function/Use of Project Original Contract Time Actual Project Completion Time Original Contract Price Final Adjusted Contract Price 6.4. During the past five (5) years, has your organization ever been denied bond coverage by a surety company? ____ Yes ____ No If “yes” on a separate attachment provide details of the denial of bond coverage and the name of the company or companies which denied coverage. 6.5. At any time during the past five (5) years, has any surety company made any payments on behalf the Bidder to satisfy any claims made against a bid, performance or payment bond issued to the Bidder, in connection with a construction project, either public or private? Page 5 Section 00 45 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 ____ Yes ____ No If “yes,” on a separate attachment set forth: (i) the amount of each such claim; (ii) the name and telephone number of the claimant; (iii) the date of the claim; (iv) the grounds for the claim; (v) the present status of the claim; (vi) the date of resolution of such claim if resolved; (vii) the method by which such was resolved if resolved; (viii) the nature of the resolution; and (ix) the amount, if any, at which the claim was resolved. 6.6. In the last five years has any insurance carrier, for any policy of insurance, refused to renew the insurance policy for your firm? ____ Yes ____ No 6.7. Within the past five (5) years, has the Bidder been required to pay either back wages or penalties for the Bidder’s failure to comply with California prevailing wage laws? This question refers only to the Bidder’s violation of prevailing wage laws, not to violations of the prevailing wage laws by a subcontractor to the Bidder. ____ Yes ____ No If ”yes,” on a separate attachment: (i) describe each instance of prevailing wage rate violation; (ii) identify the project on which a prevailing wage rate violation occurred; (iii) the public agency owner of the project; (iv) the number of employees affected by each prevailing wage rate violation; and (v) amount of back wages and penalties the Bidder was required to pay. 6.8. Within the past five (5) years, has there been more than one occasion in which the Bidder was penalized or required to pay back wages for failure to comply with the Federal DavisBacon prevailing wage requirements? ____ Yes ____ No If ”yes,” on a separate attachment: (i) describe each instance of prevailing wage rate violation; (ii) identify the project on which a prevailing wage rate violation occurred; ((iii) the number of employees affected by each prevailing wage rate violation; and (iv) amount of back wages and penalties the Bidder was required to pay. 6.9. Within the past five (5) years, has the Bidder been found to have violated any provision of California apprenticeship laws or regulations, or the laws pertaining to use of apprentices on public works projects? ____ Yes ____ No If “yes,” provide the date(s) of such findings, and attach copies of the Department’s final decision(s). 7. Accuracy and Authority. The undersigned is duly authorized to execute this Statement of Qualifications under penalty of perjury on behalf of the above-identified Bidder. The undersigned warrants and represents that he/she has personal knowledge of each of the responses to this Statement of Qualifications and/or that he/she has conducted all necessary and appropriate inquiries to determine the truth, completeness and accuracy of responses to this Statement of Qualifications. The undersigned declares and certifies that the responses to this Statement of Qualifications are complete and accurate; there are no omissions of material fact or information Page 6 Section 00 45 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 that render any response to be false or misleading and there are no misstatements of fact in any of the responses. The above-identified Bidder acknowledges and agrees that if the District determines that any response herein is false or misleading or contains misstatements of fact so as to be false or misleading, the Bidder’s Bid Proposal may be rejected by the District for nonresponsiveness. Executed this___ day of __________________ 20__ at_____________________________. (City and State) I declare under penalty of perjury under California law that the foregoing is true and correct. By: ____________________________________________ (Signature of Bidder’s Authorized Officer or Representative) ____________________________________________ (Typed or Printed Name) Title: ___________________________________________ Page 7 Section 00 45 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 THIS PAGE INTENTIONALLY BLANK Page 8 Section 00 45 13 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 SECTION 011000 SUMMARY OF WORK 1.01 WORK REQUIRED BY CONTRACT DOCUMENTS A. Description: 1. The Monterey Peninsula College, Art Department Modernization: Buildings 1 and 30 project consists of the renovation and remodeling of the existing Art Studio and Art Ceramics Buildings. 2. The Contractor shall be responsible for scheduling and coordinating the work with the MPC Staff, Representatives, and contractors on other MPC projects working concurrent with this project. Reference paragraph 1.04 of this section. 3. The work to be done includes all labor, tools and equipment necessary to furnish and install all materials and equipment shown on the drawings and described herein and to perform tests described herein, to provide complete and operating systems to the extent specified and shown on the drawings. The Contractor shall furnish all equipment, material and supplies, except where specifically noted as existing or supplied by the District. B. Location of Work: The project occupies a portion of Monterey Peninsula College’s property at 980 Fremont Street, Monterey, CA 93940 C. Limits of Work: As shown on Drawings. 1.02 SUBSTANTIAL COMPLETION Substantial Completion shall only be applicable to the entire Work. 1.03 FUTURE WORK Reference sub section 1.04 1.04 1.05 WORK SEQUENCE OR PHASING A. The Work shall be one continuous project, both buildings and site work must be completed within the contract time. B. The Site work North of Building 1 will be started on June 9th 2014. C. Site Fencing is to be deliver and placed August 19th, 2013, it is to include Green screen netting for the duration of the project, and as necessary will be driven post or concrete foot instead of “H” foot for the safety. A fencing plan will be submitted and approved before fencing is placed. The Fencing may be required to be relocated throughout the project and costs associated must be included in the bid D. Hazardous Material Abatement contractor will be contracted directly through the district. Abatement work will be mostly complete before construction starts some work will have to be done after Contractor starts work due to access. Protection of the building from weather is the general contractors responsibility. SITE ACCESS Section 011000 Pg. 1 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 1.06 1.07 A. All construction vehicles and material/equipment deliveries shall access the work area using main roads. Contractors and their workers must at all times display a parking permit provided by the owner. Contractor parking will be coordinated with District’s representative and may not be directly at the work site. B. Sequence all construction, including connections to existing utilities to preserve the following: existing site access, circulation, and use adjacent to the Site (access must be paved, lighted, and uninterrupted). CONTRACTOR'S USE OF PROJECT SITE A. Contractor's use of the Project site for work, staging, and storage is strictly to be coordinated with the construction manager and owner. B. Coordinate use of premises under direction of the District's Representative or Construction Manager. Cooperate with the District to minimize conflict and to facilitate the District's on-going operations and activities on and about the site. C. Cooperate with other contractors to facilitate work to be done within Limits of Work under the Contract. Access on major roads and access right-of-way is to be shared with other contractors. All weather access is to be adequately maintained for all major roads and right-of-ways within the Project Limits of Work. D. Contractor shall provide and maintain all fencing, barricades, guard rails, bridges, warning signs, lights, paved paths, and the like as are necessary to protect Contractor’s own personnel, MPC staff and student, and outside public from the work site. E. Contractor shall be responsible for protection and safekeeping of products furnished under the Contract that are stored within Limits of Work. F. Move products stored under the Contractor's control that interfere with operations of the District. G. Stockpiling of materials, storage of equipment, trailers and other appurtenances related to construction operations will be limited to specific locations to be approved by the District’s Representative or the District’s Construction Manager in their sole reasonable discretion. H. Note that construction operations within drip lines of existing trees are restricted. Refer to Section 015639 for requirements. I. All areas within Limits of Work that do not require specific work shall be returned to the District at completion of the Project in same condition as received by the Contractor; the Contractor shall repair, replace or correct any condition within the area of the Limits of Work that are damaged, destroyed or altered during performance of the Work to the condition(s) existing immediately prior to the Contractor’s commencement of Work. J. Disagreements between Contractor and other contractors about concurrent use of work areas or access to the site that are not resolved by the participants shall be referred to the District's Representative. Contractor shall agree to abide by the District Representative's determination as to concurrent use or priority of access and to perform its work in compliance with the District Representative's resolution at no additional cost to the District. K. The Limits of Work shall not be used for stockpiling or storage of materials, equipment, trailers, and other appurtenances not related to the construction operations of this Project without written approval from the District's Representative. Reference paragraph G above. L. All material and equipment deliveries shall be made only to the Project site. The District’s receiving personnel will not accept any material and equipment for this project that is received at the District’s warehouse or other facilities. CONDUCT OF THE CONTRACTOR'S PERSONNEL A. The Contractor shall at all times maintain discipline among personnel employed at or having business at the Project site, including during meal and break periods. The Contractor shall act promptly to correct Section 011000 Pg. 2 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 conduct which the District's Representative and/or The Construction Manager deems intimidating, offensive, or hostile to the District's personnel, students, and visitors; such as: whistling or staring at, calling to, or commenting on persons passing the site (whether intended as complimentary or offensive); making obscene gestures; making or displaying offensive drawings, graffiti, or photographs; making propositions or invitations for dates or sex; or making racially, sexually, or ethnically related remarks or jokes. The Contractor shall inform all new personnel of this policy. 1.08 B. In the event that any Contractor’s employee initiates such unwarranted or unwanted interaction, or utilizes profanity or offensive Language, the Contractor shall, either upon the request of the District, Construction Manager, or on its own initiative, replace the employee with another of equivalent skill, at no additional cost to the District. C. The Contractor shall be responsible to insure that its employees observe the District’s rules on Tobacco policies. The project site has been designated as a Tobacco-free zone. No Tobacco products of any kind are allowed on the Project site. D. The Contractor shall be responsible to insure that its employees do not bring to, posses at, or consume alcoholic beverages on or near the Project site. E. The Contractor shall be responsible to insure that its employees are properly attired at all times. Proper attire includes, but is not limited to, shirts, full-length pants, appropriate work shoes and boots, safety head gear, and safety eye protection. No suggestive, offensive or sexually explicit clothing shall be worn or displayed. OCCUPANCY The District's Occupancy: The District will occupy existing adjacent buildings during the entire period of construction. Contractor shall cooperate fully with the District during construction operations to minimize conflicts and to facilitate the District's usage. Contractor shall perform all work so as not to interfere with the District's operations. 1.09 DISTRICT-FURNISHED ITEMS Not Applicable. 1.10 APPLICABILITY OF ALL SECTIONS OF SPECIFICATIONS All sections of the Specifications and Drawings are interdependent and applicable to the Project as a whole. 1.11 DIVISION OF THE SPECIFICATIONS The Specifications are divided for convenience into sections as set forth in the Table of Contents. The actual limitation of work in the various trades and/or sections of the Specifications are the responsibility of Contractor. 1.12 START OF WORK The Contractor shall commence Work as of the date set forth in the Notice to Proceed issued by or on behalf of the District to the Contractor. The Contract Time shall be computed from the date for commencement of Work set forth in the Notice to Proceed issued by or on behalf of the District; the Contract Time will not be extended or otherwise adjusted if the Contractor does not commence Work as of the date established in the Notice to Proceed for commencement of the Work. 1.13 SURROUNDING SITE CONDITION SURVEY Prior to commencing the Work, Contractor, the District, and the District's Representative shall tour the Project site together to examine and record damage to existing adjacent buildings, curbs, roads, paved parking areas, and other structures and improvements. This record shall serve as a basis for determination of subsequent damage due to Contractor's operations and shall be signed by all parties making the tour. Any cracks, sags, or damage to existing adjacent buildings, curbs, roads, paved parking areas, and other structures and improvements not noted in the Section 011000 Pg. 3 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 original survey, but subsequently discovered, shall be reported to the District's Representative. 1.14 EXAMINATION OF THE SITE AND VERIFICATION OF CONDITIONS Contractor shall examine the site and become acquainted with the conditions under which the Work is to be carried out. Upon submitting Contractor's bid, Contractor shall be held to have made such examination, and no allowance for extras will be allowed for any error or oversight resulting from Contractor's unfamiliarity with the site or existing conditions. Contractor shall obtain accurate field dimensions of all related areas, spaces, openings, levels, and items of adjacent work and, before commencing work, report to the District, in writing, via the District's Representative, all discrepancies between the Contract Documents and the actual field conditions. Commencement of work by Contractor shall constitute acceptance of all existing conditions affecting the work. 1.15 INTENT OF THE CONTRACT DOCUMENTS The intent is to provide the District with a Project that is complete in all respects as described in these Contract Documents. All Work, labor, materials, equipment, services or items necessary or reasonably required are to be provided to produce a complete and operational Project are deemed included within the Contract Price and shall be completed within the Contract Time. 1.16 ORDER OF PRECEDENCE A. 1.17 The order of precedence of the documents set forth below will be used by the District's Representative to; (1) define the intent and meaning of the Contract Documents; (2) resolve apparent inconsistencies in Submittals and Contract Documents; (3) determine the adequacy and completeness of Contractor's submittals; (4) determine the acceptability of construction; and (5) determine entitlement to extra compensation: 1. Modifications 2. The Agreement 3. Addenda 4. Special Conditions 5. Division 1, General Requirements 6. General Conditions 7. Technical Specifications 8. Drawings 9. Standard Specifications 10. Standard Drawings 11. Submittals (as favorably reviewed) INTERPRETATION OF CONTRACT DOCUMENTS Should Contractor find discrepancies in, or omissions from the Drawings or Specifications, or should the Contractor be in doubt as to their meaning, the Contractor shall at once notify the District's Representative in writing and should it be found that the point in question is not clearly and fully set forth, a written clarification will be issued. Neither the District's Representative nor the District will be responsible for any oral instructions. 1.18 ORAL MODIFICATIONS It shall be distinctly understood that no oral statement of any person shall be allowed in any manner to modify any of the Contract provisions. Changes shall be made only on written authorization of the District's Representative, except in an emergency endangering life or property. 1.19 TRANSMITTAL Any correspondence from one party to the other under the Contract shall be in writing, and shall be dated and Section 011000 Pg. 4 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 signed by the party initiating such correspondence or by duly authorized representative of such party. Correspondence and other communications relating to the Work shall be through the Construction Manager. 1.20 CORRESPONDENCE A correspondence memo will be prepared by the Construction Manager at the commencement of work showing routing, number of copies, and addresses of all correspondents. 1.21 1.22 1.23 1.24 COPIES OF DOCUMENTS A. Contractor will be furnished with Ten (10) complete sets of all Contract Documents for Contractor's requirements as stated in the General Conditions. B. Contractor may obtain additional sets of the Contract Documents, at an agreed to additional cost, by making prior arrangements through the District’s Representative. SPECIFICATIONS AND DRAWINGS A. Contractor shall keep on the Project site a copy of the Contract documents, including but not limited to; Specifications, Drawings, Responses to Requests for Information (RFI), Change Orders, and the same shall be available at all reasonable times for inspection and use by the District's Representative and by any other person authorized by the District's Representative. Any Drawings listed in the detail Specifications shall be regarded as a part thereof and of the Contract. Anything mentioned in these Specifications and not shown on the Drawings, or shown on the Drawings and not mentioned in these Specifications, shall be of like effect as though shown or mentioned in both. B. It shall be the duty of Contractor to see that the provisions of these Specifications are complied with in detail irrespective of the inspection given the work during its progress by the District's Representative or others. Any failure on the part of Contractor to strictly comply with the requirements of the contract documents, including without limitation the Specifications, will be sufficient cause for the rejection of the work at any time before its acceptance and/or constitute an event of Contractor default. C. The District's Representative will furnish from time to time, such detail drawings, plans, profiles, and information, as the District's Representative may consider necessary for Contractor's guidance to insure the proper and adequate execution of the Contract. Contractor shall comply with such detail drawings, plans, profiles and information without adjustment of the Contract Price or the Contract Time. D. Only favorably reviewed shop drawings and submittals shall be used in construction. Refer to Section 013300. MANUFACTURER'S INSTRUCTIONS A. Where the contract documents state that products, processes, equipment or the like shall be installed or applied in accordance with manufacturer's instructions, directions or specifications, they shall be construed to mean that said application or installation shall be in strict accordance with printed instructions furnished by the manufacturer of the material concerned for use under conditions similar to those at the Project site. B. The manufacturer's directions do not take precedence over the Contract Drawings and Specifications. Where such directions are in conflict with the Contract Documents, Contractor shall request in writing a clarification from the District's Representative before proceeding with the work. NOTICE AND SERVICE THEREOF A. Any notice to Contractor from the District's Representative relative to any part of this Contract will be in writing and considered delivered and the service thereof completed, when said notice is posted, by certified or registered mail, to the said Contractor at Contractor's last given address, or delivered in person to the said Contractor or Contractor's authorized representative on the work. Section 011000 Pg. 5 Monterey Peninsula College Art Department Modernization: Buildings 1 and 30 1.25 1.26 MANAGEMENT A. Contractor shall designate in writing before starting Work, an authorized representative (Project Manager) who shall have complete authority to represent and act for Contractor. This representative shall be acceptable to the District and shall be approved by the District's Representative. B. Contractor shall designate in writing before starting Work, an authorized representative (Superintendent, as per General Conditions). This representative shall be acceptable to the District and shall be approved by the District's Representative. Said authorized representative shall be present at the site of the Work at all times while Work is actually in progress on the Contract, and during periods when Work is suspended, arrangements acceptable to the District shall be made for any emergency work that may be required. C. If such approval, as noted above for the Project Manager and Superintendent, shall be withdrawn by the District's Representative, Contractor shall, as soon as is practicable after having received written notice of such withdrawal, remove the representative(s) from the Project and shall not thereafter employ that person as Contractor's representative(s) on the Project. Contractor shall replace said representative(s) with another representative acceptable to the District and approved by the District's Representative as specified above. PAYMENT FOR PATENTS AND PATENT INFRINGEMENT All fees or claims for any patented invention, article or arrangement that may be used upon or any manner connected with the performance of the Work or any part thereof shall be included in the price bid for doing the work, and Contractor and Contractor's sureties shall protect and hold the District's Representative, and the District, together with all their officers, agents and employees, harmless against liability of any nature or kind for any and all costs, legal expenses, and demands made for such fees or claims and against any and all suits and claims brought or made by the holder of any invention or patent, or growing out of any use or alleged infringement of any invention or patent, or on account of any patented or unpatented invention, process, article, or appliance manufactured for or used in the performance of the Contract, including its use by the District, unless otherwise specifically stipulated in the Contract. Before final payment is made on the Contract, Contractor shall furnish acceptable proof to the District of a proper release from such fees or claims. 1.27 RELEASE The acceptance by Contractor of the final payment made under the terms of the Contract shall operate as, and shall be as a release to the District, the District's Representative and their duly authorized agents, from all claim of and/or liability to Contractor for anything done or furnished for, or in relation to, the Work or for any act or neglect of the District or any person related to or affecting the Work. 1.28 CLEANING Contractor shall clean up the Project and construction area such that the Project site is kept continuously clean. The Contractor is required to maintain at least one (1) dumpster adequately sized for general use as well as trash receptacles as necessary on the Project site. The Contractor shall dispose of all debris in accordance with Section 013500 and Section 015000. 1.29 UNAUTHORIZED INTERACTION WITH DISTRICT STAFF Any unauthorized interaction with the District’s staff, faculty, and students shall be documented in writing and submitted to the District’s Representative within 24 hours of the interaction. Any items, conflicts, or issues raised during this interaction must be referred to the District’s Representative immediately. END OF SECTION 011000 Section 011000 Pg. 6 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 SECTION 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 COMMISSIONING A. Commissioning is a systematic process of ensuring that all building systems perform interactively according to the design intent and the owner’s operational needs. This is achieved by beginning in the design phase and documenting design intent and continuing through construction, acceptance and the warranty period with actual verification of performance. The commissioning process shall encompass and coordinate the traditionally separate functions of system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training. B. Commissioning during the construction phase is intended to achieve the following specific objectives according to the Contract, documented accordingly: 1. Verify that applicable equipment and systems are installed according to the manufacturer’s recommendations and to industry accepted minimum standards and that they receive adequate operational checkout by installing contractors. 2. Verify and document proper performance of equipment and systems. 3. Verify that O&M documentation left on site is complete. 4. Verify that the Owner’s operating personnel are adequately trained. C. The commissioning process does not take away from or reduce the responsibility of the system designers or installing contractors to provide a finished and fully functioning product. 1.2 SYSTEMS TO BE COMMISSIONED A. All HVAC equipment will be commissioned. Related Specification Sections are 23 XX XX (which means all Mechanical Specifications Sections). B. Systems to be commissioned are (See all M sheets in contract documents) a. Furnaces b. Exhaust Fans c. Supply Fan d. Electric Heaters e. Kiln Exhaust Fans f. Ambient Air Cleaners g. TAB Verification h. Sequence of operations and mechanical control systems for all HVAC equipment i. Graphical interface including floor plans 1.3 ABBREVIATIONS A. The following are common abbreviations used in the Specifications and in the Commissioning Plan. A/E- Architect and design engineers GENERAL COMMISSIONING REQUIREMENTS FT- Functional performance test 01 91 00 - 1 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 1.4 CA- Commissioning authority GC- General contractor (prime) CC Controls Contractor MC- Mechanical contractor CM- Construction Manager owner’s representative) Cx- Commissioning PM- Project manager (of the Owner) Cx Plan- Commissioning Plan document Subs- Subcontractors to General EC- Electrical contractor TAB- Test and balance contractor (the PC- Prefunctional checklist DEFINITIONS A. Basis of Design: The basis of design is the documentation of the primary thought processes and assumptions behind design decisions that were made to meet the design intent. The basis of design describes the systems, components, conditions and methods chosen to meet the intent. Some reiterating of the design intent may be included. Basis of Design is reflected in bid documents. B. Commissioning Plan: An overall plan, developed after bidding that provides the structure, schedule and coordination planning for the commissioning process per specifications and project drawings. C. Design Intent: A dynamic document that provides the explanation of the ideas, concepts and criteria that are considered to be very important to the owner. It is initially the outcome of the programming and conceptual design phases. Design Intent is reflected in bid documents. D. Functional Performance Test (FT): Test of the dynamic function and operation of equipment and systems using manual (direct observation) or monitoring methods. Functional testing is the dynamic testing of systems (rather than just components) under full operation (e.g., the chiller pump is tested interactively with the chiller functions to see if the pump ramps up and down to maintain the differential pressure set point). Systems are tested under various modes, such as during low cooling or heating loads, high loads, component failures, unoccupied, varying outside air temperatures, fire alarm, power failure, etc. The systems are run through all the control system’s sequences of operation and components are verified to be responding as the sequences state. Traditional air or water test and balancing (TAB) is not functional testing, in the commissioning sense of the word. TAB’s primary work is setting up the system flows and pressures as specified, while functional testing is verifying that which has already been set up. The commissioning authority develops the functional test procedures in a sequential written form, coordinates, oversees and documents the actual testing, which is usually performed by the installing contractor or vendor. FTs are performed after prefunctional checklists and startups are complete. E. General Contractor (GC): The prime contractor for this project. Generally refers to all the GC’s subcontractors as well. Also referred to as the Contractor, in some contexts. F. Prefunctional Checklist (PC): A list of items to inspect and elementary component tests to conduct to verify proper installation of equipment, provided by the CA to the Sub. Prefunctional checklists are primarily static inspections and procedures to prepare the equipment or system for initial operation (e.g., belt tension, oil levels OK, labels affixed, gages in place, sensors calibrated, etc.). However, some prefunctional checklist items entail simple testing of the function of a component, a piece of equipment or system (such as measuring the voltage imbalance on a three phase pump motor of a chiller system). The word prefunctional refers to before functional testing. Prefunctional GENERAL COMMISSIONING REQUIREMENTS 01 91 00 - 2 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 checklists augment and are combined with the manufacturer’s start-up checklist. Even without a commissioning process, contractors typically perform some, if not many, of the prefunctional checklist items a commissioning authority will recommend. However, few contractors document in writing the execution of these checklist items. Therefore, for most equipment, the contractors execute the checklists on their own. The commissioning authority only requires that the procedures be documented in writing, and does not witness much of the prefunctional check listing, except for larger or more critical pieces of equipment. G. 1.5 Sampling: Functionally testing only a fraction of the total number of identical or near identical pieces of equipment. COMMISSIONING TEAM A. 1.6 The members of the commissioning team consist of the Commissioning Authority (CA), the Project Manager (PM), the designated representative of the owner’s Construction Management firm (CM), IOR (inspector of Record), the General Contractor (GC or Contractor), the architect and design engineers (particularly the mechanical engineer), the Mechanical Contractor (MC), the Electrical Contractor (EC), the TAB representative, the Controls Contractor (CC), any other installing subcontractors or suppliers of equipment. If known, the Owner’s building or plant operator/engineer is also a member of the commissioning team. COMMISSIONING AUTHORITY’S RESPONSIBILITIES A. The CA is hired by the Owner. The CA directs and coordinates the commissioning activities and is part of the CM team. All members work together to fulfill their contracted responsibilities and meet the objectives of the Contract Documents. B. The CA will provide the initial schedule of primary commissioning events at the commissioning scoping meeting during construction phase. C. The primary role of the CA is to develop and coordinate the execution of a testing plan, observe and document performance—that systems are functioning in accordance with the documented design intent and in accordance with the Contract Documents. The Contractors will provide all tools or the use of tools to start, check-out and functionally test equipment and systems. D. Construction and Acceptance Phase 1. 2. 3. 4. 5. 6. 7. Coordinates and directs the commissioning activities in a logical, sequential and efficient manner using consistent protocols and forms, centralized documentation, clear and regular communications and consultations with all necessary parties, frequently updated timelines and schedules and technical expertise. Plan and conduct a commissioning scoping meeting and other commissioning meetings. Write and distribute prefunctional checklists. Develop an enhanced start-up and initial systems checkout plan with Subs. Approve prefunctional checklists completion by reviewing prefunctional checklist reports and by selected site observation and spot checking. Review TAB execution plan. Oversee sufficient functional testing of the control system and approve it to be used for TAB, before TAB is executed. GENERAL COMMISSIONING REQUIREMENTS 01 91 00 - 3 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 8. 9. 10. 11. 12. 1.7 Coordinate witness and approve manual functional performance tests performed by installing contractors. Coordinate retesting as necessary until satisfactory performance is achieved. Review equipment warranties to ensure that the Owner’s responsibilities are clearly defined. Oversee and approve the training of the Owner’s operating personnel. Review and approve the preparation of the O&M manuals. Provide a final commissioning report (as described in this section). MECHANICAL AND ELECTRICAL DESIGNERS/ENGINEERS’ RESPONSIBILITIES A. Construction and Acceptance Phase 1. 2. 3. 4. 1.8 Perform normal submittal review, construction observation, as-built drawing preparation, etc., as contracted. One site observation should be completed just prior to system startup. The designers shall assist (along with the contractors) in clarifying the operation and control of commissioned equipment in areas where the specifications, control drawings or equipment documentation is not sufficient for writing detailed testing procedures. Participate in the resolution of system deficiencies identified during commissioning, according to the contract documents. Prepare and submit the final as-built design intent and operating parameters documentation for inclusion in the O&M manuals. Review and approve the O&M manuals. CONSTRUCTION MANAGER—OWNER’S REPRESENTATIVE (CM) A. Construction and Acceptance Phase 1. 2. 3. 4. 5. 6. 1.9 Facilitate the coordination of the commissioning work by the CA, and, with the GC and CA, ensure that commissioning activities are being scheduled into the master schedule. Review and approve the final Commissioning Plan—Construction Phase. Attend a commissioning scoping meeting and other commissioning team meetings. Review and approve the functional performance test procedures submitted by the CA, prior to testing. Observe and witness prefunctional checklists, startup and functional testing of selected equipment. Assist the GC in coordinating the training of owner personnel. GENERAL CONTRACTOR (GC) AND SUBS A. Construction and Acceptance Phase 1. 2. 3. 4. Facilitate the coordination of the commissioning work by the CA, and with the GC and CA ensure that commissioning activities are being scheduled into the master schedule. Include the cost of commissioning in the total contract price. Assign one person (commissioning coordinator) to coordinate and facilitate the commissioning activities with CA and subs. This person shall have experience in HVAC commissioning and procedures. Submit commissioning coordinator qualifications to CA. Furnish a copy of all construction documents, addenda, change orders and approved submittals and shop drawings related to commissioned equipment to the CA. GENERAL COMMISSIONING REQUIREMENTS 01 91 00 - 4 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 5. 6. 7. 8. 9. 10. B. Warranty Period 1. C. In each purchase order or subcontract written, include requirements for submittal data, O&M data, commissioning tasks and training. Ensure that all Subs execute their commissioning responsibilities according to the Contract Documents and schedule. A representative shall attend a commissioning scoping meeting and other necessary meetings scheduled by the CA to facilitate the Cx process. Coordinate the training of owner personnel. Prepare O&M manuals, according to the Contract Documents, including clarifying and updating the original sequences of operation to as-built conditions. Coordinate factory start-up events in construction schedule Ensure that Subs correct deficiencies and make necessary adjustments to O&M manuals and as-built drawings for applicable issues identified in any seasonal testing. CONTRACTOR RESPONSIBILITIES 1. Construction Phase 1) Include Cx requirements in price and plan for work 2) Attend coordination meetings called by CA 3) Remedy any deficiencies identified throughout construction 4) Prepare and submit required draft forms and systems information. TAB shall submit sample balancing forms. 5) Thoroughly complete and inspect installation of systems and equipment as detailed throughout Contract Documents, as required by reference or industry standards. 6) Start-up, test, adjust, and balance systems and equipment prior to verification and performance testing by the Commissioning Authority. Start-up procedures shall be in accordance with Contract Documents, reference or industry standards. 7) Record start-up and testing procedures on start-up forms or checklists and certify that the systems and equipment have been started and or tested in accordance with the requirements specified above. Each form shall be signed and dated by the individual responsible for the start-up or test. Tag equipment started with individuals name and date. 8) Complete approved start up checklists and submit along with other installation certification information such as balancing reports, warrantees, testing results, etc. 9) Schedule and coordinate Cx efforts required by appropriate subs and vendors. Participate in respective portions of start ups and training 10) Demonstrate the systems as specified 11) Certify that systems have been installed and are operating per Contract Documents. 12) Maintain an updated set of record documentation 13) Copy Commissioning Authority on indicated documentation such as factory start-up tests and documentation. 14) Conduct equipment specific operation, maintenance, diagnosis, and repair training as required by the respective section of the specifications. 2. Acceptance Phase 1) Assist Commissioning Authority in verification and performance testing. Assistance will generally include the following: GENERAL COMMISSIONING REQUIREMENTS 01 91 00 - 5 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 a) b) 3. 1.10 Manipulate systems and equipment to facilitate testing Provide instrumentation necessary for verification and performance testing c) Manipulate control systems to facilitate verification and performance testing d) Provide a TAB technician to work at the direction of Commissioning Authority for up to 8 hours per building beyond assistance specified. e) Provide a Control Contractor to work at the direction of Commissioning Authority for up to 8 hours beyond assistance specified above. 2) Correct any work not in accordance with Contract Documents. 3) Participate in the systems and operational training relative to use of O&M information and the Preventive Maintenance program 4) Compensate Commissioning Authority for site time necessitated by incompleteness of systems or equipment at time of functional performance testing. Warranty Phase 1) Provide warranty service 2) Correct any deficiencies identified 3) Update record documentation to reflect any changes made throughout the Warranty Phase COMMISSIONING DOCUMENTATION A. Commissioning Plan: It will be provided in first commissioning scope meeting. The commissioning plan provides guidance in the execution of the commissioning process. Just after the initial commissioning scoping meeting the CA will update the plan which is then considered the “final” plan, though it will continue to evolve and expand as the project progresses. The Specifications will take precedence over the Commissioning Plan. B. Commissioning Report: A final summary report by the CA will be provided to the Owner/ CM. The report will focus on evaluating commissioning process issues. All acquired documentation, logs, reports, deficiency lists, findings, unresolved issues, etc., will be provided with the summary report. 1.11 COORDINATION A. Management: The CA is hired by the Owner. The CA directs and coordinates the commissioning activities and is part of the CM team. All members work together to fulfill their contracted responsibilities and meet the objectives of the Contract Documents B. Scheduling: The CA will work with the CM and GC according to established protocols to schedule the commissioning activities. The CA will provide sufficient notice to the CM and GC for scheduling commissioning activities. The GC will integrate all commissioning activities into the master schedule. All parties will address scheduling problems and make necessary notifications in a timely manner in order to expedite the commissioning process. The CA will provide the initial schedule of primary commissioning events at the commissioning scoping meeting. The Commissioning Plan provides a format for this schedule. As construction progresses, more detailed schedules are developed by the CA and GC. C. Meetings GENERAL COMMISSIONING REQUIREMENTS 01 91 00 - 6 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 1. Scoping Meeting: Within 120 days of commencement of construction (after all the HVAC submittals are approved), the CA will schedule, plan and conduct a commissioning scoping meeting with the entire commissioning team in attendance. Meeting minutes will be distributed to all parties by the CA. Information gathered from this meeting will allow the CA to revise the Draft 2 Commissioning Plan to its “final” version, which will also be distributed to all parties. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 COMMISSIONING PROCESS A. The following narrative provides a brief overview of the typical commissioning tasks during construction and the general order in which they occur: 1. 2. 3. 4. 5. 6. 7. 8. Commissioning during construction begins with a scoping meeting conducted by the CA where the commissioning process is reviewed with the commissioning team members. Equipment documentation is submitted to the CA during normal submittals, including detailed start-up procedures and O&M manuals in one three ring binder. The CA works with the Subs in developing startup plans and startup documentation formats, including providing the Subs with prefunctional checklists to be completed, during the startup process. In general, the checkout and performance verification proceeds from simple to complex; from component level to equipment to systems and intersystem levels with prefunctional checklists being completed before functional tests. The Subs, under their own direction, execute and document the prefunctional checklists and perform startup and initial checkout. The CA documents that the checklists and startup were completed according to the approved plans. This may include the CA witnessing start-up of selected equipment. The CA develops specific equipment and system functional performance test procedures. The Subs review the procedures. The procedures are executed by the Subs, under the direction of, and documented by the CA. Items of non-compliance in material, installation or setup are corrected at the Sub’s expense (including the CA’s time) and the system retested. The General Contractor is responsible for collecting cost and expenses for retesting. Retesting will be charged to contractor minimum 4 hours of standard hourly rates of CA. a. Cost of Retesting 1) The cost for the Sub to retest a prefunctional or functional test, if they are responsible for the deficiency, shall be theirs. If they are not responsible, any cost recovery for retesting costs shall be GC. 2) For a deficiency identified, not related to any prefunctional checklist or start-up fault, the following shall apply: The CA and CM will direct the retesting of the equipment once at no “charge” to the GC for their time. However, the CA’s and CM’s time for a second retest will be charged to the GC, who may choose to recover costs from the responsible Sub. GENERAL COMMISSIONING REQUIREMENTS 01 91 00 - 7 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 3) 9. 10. 11. 12. B. The time for the CA and CM to direct any retesting required because a specific prefunctional checklist or start-up test item, reported to have been successfully completed, but determined during functional testing to be faulty, will be back charged to the GC, who may choose to recover costs from the party responsible for executing the faulty prefunctional test. The CA reviews the O&M documentation for completeness. Commissioning is completed before Substantial Completion. The CA reviews, pre-approves and coordinates the training provided by the Subs and verifies that is was completed. Deferred testing is conducted, as specified or required. Reporting 1. The CA will provide regular reports to the Owner and Architect. Standard forms are provided and referenced in the Commissioning Plan. 2. The CA will regularly communicate with all members of the commissioning team, keeping them apprised of commissioning progress and scheduling changes through memos, progress reports, etc. 3. Testing or review approvals and non-conformance and deficiency reports are made regularly with the review and testing as described in later sections. 4. A final summary report by the CA will be provided to the CM or PM (owner rep), focusing on evaluating commissioning process issues and identifying areas where the process could be improved. All acquired documentation will be compiled in appendices and provided with the summary report. Prefunctional checklists, functional tests and monitoring reports will not be part of the final report, but will be stored in the Commissioning Record in the O&M manuals in CA’s office. END OF SECTION 019100 GENERAL COMMISSIONING REQUIREMENTS 01 91 00 - 8 SECTION 08 71 00 DOOR HARDWARE PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions of Division 1 Specification Sections, apply to this Section. 1.02 SUMMARY A. This Section includes items known commercially as finish or door hardware that are required for swing, sliding, and folding doors, except special types of unique hardware specified in the same sections as the doors and door frames on which they are installed. B. This Section includes the following, but is not necessarily limited to: 1. 2. 3. 4. Door Hardware, including electric hardware. Storefront and Entrance door hardware. Thresholds, gasketing and weather-stripping. Door silencers or mutes. C. Related Sections: The following sections are noted as containing requirements that relate to this Section, but may not be limited to this listing. 1. 2. 3. 4. 1.03 Division 8: Section - Steel Doors and Frames. Division 8: Section - Wood Doors. Division 8: Section - Aluminum Storefront Division 28: Section - Fire/Life-Safety Systems & Security Access Systems. REFERENCES (Use date of standard in effect as of Bid date.) A. ADAAG - Americans with Disabilities Act (ACT) Accessibility Guidelines for Buildings and Facilities. B. BHMA - Builders' Hardware Manufacturers Association. C. DHI - Door and Hardware Institute. D. NFPA - National Fire Protection Association. 1. NFPA 80 - Fire Doors and Windows 2. NFPA 101 - Life Safety Code 3. NFPA 105 - Smoke and Draft Control Door Assemblies E. CBC 2010 - California Building Code. F. UL - Underwriters Laboratories. 1. UL 10C - Fire Tests of Door Assemblies 2. UL 305 - Panic Hardware G. WHI - Warnock Hersey Incorporated Monterey Peninsula College Door Hardware Art Department Modernizations Buildings 1 & 30 Section 08 71 00-1 H. SDI - Steel Door Institute 1.04 SUBMITTALS & SUBSTITUTIONS A. General: Submit in accordance with Conditions of the Contract and Division 1 Specification sections. B. Submit product data (catalog cuts) including manufacturers' technical product information for each item of door hardware, installation instructions, maintenance of operating parts and finish, and other information necessary to show compliance with requirements. C. Submit six (6) copies of schedule organized vertically into “Hardware Sets” with index of doors and headings, indicating complete designations of every item required for each door or opening. Include following information: 1. 2. 3. 4. 5. 6. 7. 8. Type, style, function, size and finish of each hardware item. Name, part number and manufacturer of each item. Fastenings and other pertinent information. Location of hardware set coordinated with floor plans and door schedule. Explanation of all abbreviations, symbols and codes contained in schedule. Mounting locations for hardware. Door and frame sizes and materials. List of manufacturers used and their nearest representative with address and phone number. 9. Keying information. D. Make substitution requests in accordance with Division 1. Substitution requests must be made prior to bid date. Include product data and indicate benefit to the project. Furnish samples of any proposed substitution. E. Keying Schedule: Submit separate detailed schedule indicating clearly how the Owner's final instructions on keying of locks has been fulfilled. F. Templates for doors, frames, and other work specified to be factory prepared for the installation of door hardware. Check shop drawings of other work to confirm that adequate provisions are made for locating and installing door hardware to comply with indicated requirements. G. Furnish as-built/as-installed schedule with close-out documents, including keying schedule and transcript, wiring/riser diagrams, manufacturers’ installation and adjustment and maintenance information. H. Fire Door Assembly Testing: Submit a written record of each fire door assembly to the Owner to be made available to the Authority Having Jurisdiction (AHJ) for future building inspections. I. 1.05 LEED Certification Points: Submit information and certifications necessary to achieve maximum points for LEED certification; coordinate and cooperate with Owner and Architect in providing information necessary for required LEED rating. QUALITY ASSURANCE A. Obtain each type of hardware (latch and lock sets, hinges, closers, exit devices, etc.) from a single manufacturer. Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-2 B. Supplier Qualifications: A recognized architectural door hardware supplier, with warehousing facilities in the project's vicinity, that has a record of successful in-service performance for supplying door hardware similar in quantity, type, and quality to that indicated for this project and that employs an experienced architectural hardware consultant (AHC) who is available to Owner, Architect, and Contractor, at reasonable times during the course of the Work, for consultation. 1. Responsible for detailing, scheduling and ordering of finish hardware. 2. Meet with Owner to finalize keying requirements and to obtain final instructions in writing. To maintain the integrity of patented key systems provide a letter of authorization from the specified manufacturer indicating that supplier has authorization to purchase the key system directly from the manufacturer. 3. Stock parts for products supplied and be capable of repairing and replacing hardware items found defective within warranty periods. C. Hardware Installer: Company specializing in the installation of commercial door hardware with five years documented experience. D. Fire-Rated Openings: Provide door hardware for fire-rated openings that complies with NFPA Standard No. 80 and requirements of authorities having jurisdiction. Provide only items of door hardware that are listed and tested by UL or Warnock Hersey for given type/size opening and degree of label. Provide proper latching hardware, door closers, approved-bearing hinges and seals whether listed in the Hardware Schedule or not. 1. Where emergency exit devices are required on fire-rated doors, (with supplementary marking on doors' UL labels indicating "Fire Door to be Equipped with Fire Exit Hardware") provide UL label on exit devices indicating "Fire Exit Hardware". E. Exit Doors: Operable from inside with single motion without the use of a key or special knowledge or effort. 1.06 DELIVERY, STORAGE AND HANDLING A. Coordinate delivery of packaged hardware items to the appropriate locations (shop or field) for installation. B. Hardware items shall be individually packaged in manufacturers’ original containers, complete with proper fasteners. Clearly mark packages on outside to indicate contents and locations in hardware schedule and in work. C. Provide locked storage area for hardware, protect from moisture, sunlight, paint, chemicals, etc. D. Inventory door hardware jointly with representatives of hardware supplier and hardware installer until each is satisfied that count is correct. 1.07 WARRANTY A. Provide warranties of respective manufacturers’ regular terms of sale from day of final acceptance as follows: 1. Closers: Ten (10) years, except electronic closers shall be two (2) years. 2. Exit devices: Three (3) years. 3. All other hardware: Two (2) years. Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-3 1.08 MAINTENANCE A. Maintenance Tools and Instructions: Furnish a complete set of specialized tools and maintenance instructions as needed for Owner's continued adjustment, maintenance, and removal and replacement of door hardware. 1.09 PRE-INSTALLATION CONFERENCE A. Convene a pre-installation conference at least one week prior to beginning work of this section. B. Attendance: Architect, Construction Manager, Contractor, Hardware Supplier, Installer, Key College District Personnel, and Project Inspector. C. Agenda: Review hardware schedule, products, installation procedures and coordination required with related work. Review College District keying requirements. PART 2 - PRODUCTS 2.01 2.02 MANUFACTURERS Item Manufacturer Acceptable Substitutes A. Hinges Ives Hager, Stanley B. Locks, Latches & Cylinders Schlage None C. Exit Devices Von Duprin None D. Closers LCN None E. Push, Pulls & Protection Plates Ives Trimco, BBW, Quality F. Flush Bolts Ives Trimco, BBW, Quality G. Dust Proof Strikes Ives Trimco, BBW, Quality H. Coordinators Ives Trimco, BBW, Quality I. Stops Ives Trimco, BBW, Quality J. Overhead Stops Glynn-Johnson None K. Thresholds National Guard Pemko, Zero L. Seals & Bottoms National Guard Pemko, Zero MATERIALS A. Hinges: Exterior out-swinging door butts shall be non-ferrous material and shall have stainless steel hinge pins. All doors to have non-rising pins. Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-4 1. Hinges shall be sized in accordance with the following: a. Height: 1) Doors up to 41" wide: 4-1/2" inches. 2) Doors 42" to 48" wide: 5 inches. b. Width: Sufficient to clear frame and trim when door swings 180 degrees. c. Number of Hinges: Furnish 3 hinges per leaf to 7'-5" in height. Add one for each additional 2 feet in height. 2. Furnish non-removable pins (NRP) at all exterior out-swing doors and interior key lock doors with reverse bevels. B. Continuous Hinges: As manufactured by Ives, an Ingersoll-Rand Company. UL rated as required. C. Extra Heavy duty Commercial Mortise Locks: Schlage “L” Series as scheduled with “03” Style Lever and “A” Style Rose. All cylinders to be interchangeable core. 1. Locksets to comply with ANSI A156.13, Series 1000, Operational Grade 1 and Security Grade 1 with all standard trims. Locksets shall also comply with UL10C and UBC 7-2 Positive Pressure requirements 2. Lock case shall be manufactured with heavy 12 gauge steel with fully wrapped design. Lock cases with exposed edges are not acceptable. Lock case shall be multi-functional allowing transformation to a different function without opening lock case. 3. Latchbolt shall have ¾” throw and be non-handed, field reversible without opening the lock case. Solid latchbolts and / or plastic anti-friction devices are not acceptable. 4. The deadbolt, when used, shall be 1” throw stainless steel with a ¾” internal engagement when fully extended. 5. All trim shall be through-bolted with the spring cages supporting the trim attached to the lock cases to prevent torquing. 6. Levers to have independent rotation in both directions. Exterior lever assembly to be one-piece design attached by threaded bushing. Interior lever assembly shall be attached by screwless shank 7. Thru-bolt lever assemblies through the door for positive interlock. Locks using a through the door spindle for attachment are not acceptable. Spindles shall be independent, designed to “break-away” at a maximum of 75psi torque. 8. Hand of lock chassis to be changeable by simply moving one screw from one side to the case to the other and pulling and reversing the latchbolt. 9. Cylinders to be secured by a cast stainless steel, dual retainer. Locks utilizing screws and / or stamped retainers are not acceptable. D. Exit devices: Von Duprin as scheduled. 1. Provide certificate by independent testing laboratory that device has completed over 1,000,000 cycles and can still meet ANSI/BHMA A156.3 - 2001 standards. 2. All internal parts shall be of cold-rolled steel with zinc dichromate coating. 3. Mechanism case shall have an average thickness of .140". 4. Compression spring engineering. 5. Non-handed basic device design with center case interchangeable with all functions. 6. All devices shall have quiet return fluid dampeners. 7. All latchbolts shall be deadlocking with ¾” throw and have a self-lubricating coating to reduce friction and wear. 8. Device shall bear UL label for fire and or panic as may be required. 9. All surface strikes shall be roller type and utilize a plate underneath to prevent movement. 10. All Exit Devices to be sex-bolted to the doors. Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-5 11. Panic Hardware shall comply with CBC Section 1008.1.9 and shall be mounted between 30" and 44" above the finished floor surface. The unlatching force shall not exceed 15 lbs. applied in the direction of travel. E. Closers: LCN as scheduled. Place closers inside building, stairs, room, etc. 1. Door closer cylinders shall be of high strength cast iron construction with double heat treated pinion shaft to provide low wear operating capabilities of internal parts throughout the life of the installation. All door closers shall be tested to ANSI/BHMA A156.4 test requirements by a BHMA certified testing laboratory. A written certification showing successful completion of a minimum of 10,000,000 cycles must be provided. 2. All door closers shall be fully hydraulic and have full rack and pinion action with a shaft diameter of a minimum of 11/16 inch and piston diameter of 1 inch to ensure longevity and durability under all closer applications. 3. All parallel arm closers shall incorporate one piece solid forged steel arms with bronze bushings. 1-9/16” steel stud shoulder bolts, shall be incorporated in regular arms, holdopen arms, arms with hold open and stop built in. All other closers to have forged steel main arms for strength, durability, and aesthetics for versatility of trim accommodation, high strength and long life. 4. All parallel arm closers so detailed shall provide advanced backcheck for doors subject to severe abuse or extreme wind conditions. This advanced backcheck shall be located to begin cushioning the opening swing of the door at approximately 45 degrees. The intensity of the backcheck shall be fully adjustable by tamper resistant non-critical screw valve. 5. Closers shall be installed to permit doors to swing 180 degrees. 6. All closers shall utilize a stable fluid withstanding temperature range of 120 degrees F. to -30 degrees F. without requiring seasonal adjustment of closer speed to properly close the door. 7. Provide the manufactures drop plates, brackets and spacers as required at narrow head rails and special frame conditions. NO wood plates or spacers will be allowed. 8. Maximum effort to operate doors shall not exceed 5 lbs., such pull or push effort being applied at right angles to hinged doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased but shall not to exceed 15 lbs. when specifically approved by fire marshal. All closers shall be adjusted to operate with the minimum amount of opening force and still close and latch the door. These forces do not apply to the force required to retract latch bolts or disengage other devices that hold the door in a closed position. Door shall take at least 5 seconds to move from an open position of 70 degrees to a point of 3 inches from the latch jamb. Reference CBC Sections 1133B.2.1, 1133B.2.5, 1133B2.5.1 & 1003.3.1.8. 9. Provide sex-bolted or through bolt mounting for all door closers. F. Flush Bolts & Dust Proof Strikes: Automatic Flush Bolts shall be of the low operating force design. Utilize the top bolt only model for interior doors where applicable and as permitted by testing procedures. 1. Manual flush bolts only permitted on storage or mechanical openings as scheduled. 2. Provide dust proof strikes at openings using bottom bolts. G. Door Stops: 1. Unless otherwise noted in Hardware Sets, provide wall type with appropriate fasteners. Where wall type cannot be used, provide floor type. If neither can be used, provide overhead type. 2. Do not install floor stops more than four (4) inches from the face of the wall or partition (Title 24, 1133B.8.6). Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-6 3. Overhead stops shall be made of stainless steel and non-plastic mechanisms and finished metal end caps. Field-changeable hold-open, friction and stop-only functions. H. Protection Plates: Fabricate either kick, armor, or mop plates with four beveled edges. Provide kick plates 10" high and 2" LDW. Sizes of armor and mop plates shall be listed in the Hardware Schedule. Furnish with machine or wood screws of bronze or stainless to match other hardware. I. Thresholds: As Scheduled and per details. 1. Thresholds shall not exceed 1/2" in height, with a beveled surface of 1:2 maximum slope. 2. Set thresholds in a full bed of butyl-rubber or polyisobutylene mastic sealant complying with requirements in Division 7 “Thermal and Moisture Protection”. 3. Use ¼” fasteners, red-head flat-head sleeve anchors (SS/FHSL). 4. Thresholds shall comply with CBC Section 1133B.2.4.1. J. Seals: Provide silicone gasket at all rated and exterior doors. 1. Fire-rated Doors, Resilient Seals: UL10C / UBC Standard 7-2 compliant. Coordinate with selected door manufacturers' and selected frame manufacturers' requirements. 2. Fire-rated Doors, Intumescent Seals: Furnished by selected door manufacturer. Furnish fire-labeled opening assembly complete and in full compliance with UL10C / UBC Standard 7-2. Where required, intumescent seals vary in requirement by door type and door manufacture -- careful coordination required. 3. Smoke & Draft Control Doors, Provide UL10C / UBC Standard 7-2 compliant for use on “S” labeled Positive Pressure door assemblies. K. Door Shoes & Door Top Caps: Provide door shoes at all exterior wood doors and top caps at all exterior out-swing doors. L. Silencers: Furnish silencers for interior hollow metal frames, 3 for single doors, 2 for pairs of doors. Omit where sound or light seals occurs, or for fire-resistive-rated door assemblies. 2.03 KEYING A. Furnish a Grand Master, Master, keyed alike or keyed different system as directed by the Owner or Architect. Locks are to be keyed to the College District’s Schlage “Classic Primus Level 3G Keyway”. B. Provide construction keying & cylinders for doors requiring locking during construction; remove construction cylinders immediately prior to Owner occupancy. Furnish permanent keys (and cores if applicable) directly to Owner. C. Key Blanks: Schlage original “Classic Primus "6" pin bow key blank; tag to identify. D. Supply keys and blanks as follows: 1. Supply 2 cut change keys for each different change key code. 2. Supply 1 uncut key blank for each change key code. 3. Supply 6 cut master keys for each different master key set. 4. Supply 3 uncut key blanks for each master key set. 2.04 FINISHES A. Generally to be satin chrome US26D (626 on bronze and 652 on steel) unless otherwise noted. Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-7 B. Furnish push plates, pull plates and kick or armor plates in satin stainless steel US32D (630) unless other wise noted. C. Door closers shall be powder-coated to match other hardware, unless otherwise noted. D. Aluminum items to be finished anodized aluminum except thresholds which can be furnished as standard mill finish. 2.05 FASTENERS A. Screws for strikes, face plates and similar items shall be flat head, countersunk type, provide machine screws for metal and standard wood screws for wood. B. Screws for butt hinges shall be flathead, countersunk, full-thread type. C. Fastening of closer bases or closer shoes to doors shall be by means of sex bolts and spray painted to match closer finish. D. Provide expansion anchors for attaching hardware items to concrete or masonry. E. All exposed fasteners shall have a phillips head. F. Finish of exposed screws to match surface finish of hardware or other adjacent work. G. All Exit Devices and Lock Protectors shall be fastened to the door by the means of sex bolts or through bolts. PART 3 - EXECUTION 3.01 INSPECTION A. Verify that doors and frames are square and plumb and ready to receive work and dimensions are as instructed by the manufacturer. B. Beginning of installation means acceptance of existing conditions. 3.02 INSTALLATION A. Install hardware in accordance with manufacturer's instructions and requirements of DHI. B. Use the templates provided by hardware item manufacturer. C. Mounting heights for hardware shall be as recommended by the Door and Hardware Institute. Operating hardware will to be located between 30" and 44" AFF. D. Set units level, plumb and true to line and location. Adjust and reinforce the attachment substrate as necessary for proper installation and operation. E. Drill and countersink units that are not factory-prepared for anchorage fasteners. Space fasteners and anchors in accordance with industry standards. F. Set thresholds for exterior doors in full bed of butyl-rubber sealant. G. If hand of door is changed during construction, make necessary changes in hardware at no additional cost. Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-8 H. Hardware Installer shall coordinate with security contractor to route cable to connect electrified locks, panic hardware and fire exit hardware to power transfers or electric hinges at the time these items are installed so as to avoid disassembly and reinstallation of hardware. I. 3.03 Hardware Installer shall also be present with the security contractor when the power is turned on for the testing of the electronic hardware applications. Installer shall make adjustments to solenoids, latches, vertical rods and closers to insure proper and secure operation. ADJUST AND CLEAN A. Adjust and check each operating item of hardware and each door, to ensure proper operation or function of every unit. Replace units which cannot be adjusted to operate freely and smoothly as intended for the application made. B. Clean adjacent surface soiled by hardware installation. C. Final Adjustment: Wherever hardware installation is made more than one month prior to acceptance or occupancy, return to that work area and make final check and adjustment of all hardware items in such space or area. Clean operating items as necessary to restore proper function and finish of hardware and doors. Adjust door control devices to compensate for final operation of heating and ventilating equipment. D. Instruct Owner's Personnel in proper adjustment and maintenance of hardware finishes, during the final adjustment of hardware. E. Continued Maintenance Service: Approximately six months after the completion of the project, the Contractor accompanied by the Architectural Hardware Consultant, shall return to the project and re-adjust every item of hardware to restore proper functions of doors and hardware. Consult with and instruct Owner's personnel in recommended additions to the maintenance procedures. Replace hardware items which have deteriorated or failed due to faulty design, materials or installation of hardware units. Prepare a written report of current and predictable problems (of substantial nature) in the performance of the hardware. 3.04 HARDWARE LOCATIONS A. Conform to CCR, Title 24, Part 2, and ADAAG for positioning requirements for the disabled. 3.05 FIELD QUALITY CONTROL A. Architectural Hardware Consultant (AHC) to inspect installation and certify that hardware and it's installation have been furnished and installed in accordance with manufacturer's instructions and as specified herein. 3.06 SCHEDULE A. The items listed in the following schedule shall conform to the requirements of the foregoing specifications. B. The Door Schedule on the Drawings indicates which hardware set is used with each door. Manufacturers Abbreviations (Mfr.) GLY = Glynn-Johnson IVE = Ives Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Overhead Door Stops Hinges, Pivots, Bolts, Coordinators, Dust Proof Door Hardware Section 08 71 00-9 LCN NGP SCH VON = = = = LCN National Guard Products Schlage Lock Company Von Duprin Strikes, Kick Plates, Door Stops & Silencers Door Closers Thresholds, Gasketing & Weather-stripping Locks, Latches & Cylinders Exit Devices SPECWORKS # 126248 HARDWARE GROUP: 01 2 Ea Continuous Hinge 224HD 1 Ea Mullion KR4954 X 154 STABILIZER 1 Ea Panic Hardware CD99EO 1 Ea Panic Hardware CD99NL-OP 1 Ea Rim Cylinder 20-057-ICX 4 Ea Primus Core Only 20-740 1 Ea Mortise Cylinder 26-091-ICX (MULLION) 2 Ea Mortise Cylinder 26-091-ICX XQ11-948 (DOGGING) 2 Ea Offset Door Pull 8190-2-O 2 Ea Surface Closer 4111 AVB EDA 2 Ea Floor Stop & Holder FS43 2 Ea Door Sweep 200NA 1 Ea Threshold Per Detail WEATHER-STRIPPING FURNISHED WITH DOOR & FRAME ASSEMBLY 628 689 626 626 626 626 626 626 630 689 626 628 AL IVE VON VON VON SCH SCH SCH SCH IVE LCN IVE NGP NGP 628 626 626 626 626 630 689 626 628 AL IVE VON SCH SCH SCH IVE LCN IVE NGP NGP 630 626 626 626 626 630 689 630 626 CHA 628 IVE VON SCH SCH SCH IVE LCN IVE IVE NGP NGP HARDWARE GROUP: 02 1 Ea Continuous Hinge 224HD 1 Ea Panic Hardware CD99NL-OP 1 Ea Rim Cylinder 20-057-ICX 2 Ea Primus Core Only 20-740 1 Ea Mortise Cylinder 26-091-ICX XQ11-948 (DOGGING) 1 Ea Offset Door Pull 8190-2-O 1 Ea Surface Closer 4111 AVB EDA 1 Ea Floor Stop & Holder FS43 1 Ea Door Sweep 200NA 1 Ea Threshold Per Detail WEATHER-STRIPPING FURNISHED WITH DOOR & FRAME ASSEMBLY HARDWARE GROUP: 03 3 1 1 2 1 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Ea Ea Ea Set Ea Hinge Panic Hardware Rim Cylinder Primus Core Only Mortise Cylinder Door Pull Surface Closer Kick Plate Floor Stop & Holder Seals Door Sweep Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 5BB1HW 4.5 X 4.5 NRP CD99NL-OP 20-057-ICX 20-740 26-091-ICX XQ11-948 (DOGGING) VR910NL 4111 AVB EDA 8400 10" X 2" LDW FS43 5050C 200NA Door Hardware Section 08 71 00-10 1 Ea Threshold Per Detail AL NGP 5BB1HW 4.5 X 4.5 NRP CD99NL-OP 20-057-ICX 20-740 26-091-ICX XQ11-948 (DOGGING) VR910NL 4111 AVB EDA 100H 8400 10" X 2" LDW 5050C 200NA Per Detail 630 626 626 626 626 630 689 630 630 CHA 628 AL IVE VON SCH SCH SCH IVE LCN GLY IVE NGP NGP NGP 5BB1 4.5 X 4.5 NRP LV9080T 03A 20-740 4111 EDA 8400 10" X 2" LDW FS43 5050C 200NA Per Detail 630 626 626 689 630 626 CHA 628 AL IVE SCH SCH LCN IVE IVE NGP NGP NGP 5BB1HW 4.5 X 4.5 NRP KR4954 X 154 STABILIZER CD99NL-OP LD99EO 20-057-ICX 20-740 26-091-ICX (MULLION) 26-091-ICX XQ11-948 (DOGGING) VR910NL 4111 AVB EDA 100H 8400 10" X 2" LDW FS43 5050C 200NA Per Detail 630 689 626 626 626 626 626 626 630 689 630 630 626 CHA 628 AL IVE VON VON VON SCH SCH SCH SCH IVE LCN GLY IVE IVE NGP NGP NGP HARDWARE GROUP: 04 3 1 1 2 1 1 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Ea Ea Ea Set Ea Ea Hinge Panic Hardware Rim Cylinder Primus Core Only Mortise Cylinder Door Pull Surface Closer Overhead Holder Kick Plate Seals Door Sweep Threshold HARDWARE GROUP: 05 3 1 1 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Set Ea Ea Hinge Storeroom Lock Primus Core Only Surface Closer Kick Plate Floor Stop & Holder Seals Door Sweep Threshold HARDWARE GROUP: 06 6 1 1 1 1 3 1 1 1 2 1 2 1 1 2 1 Ea Ea Ea Ea Ea Ea Ea Ea Ea Ea Ea Ea Ea Set Ea Ea Hinge Mullion Panic Hardware Panic Hardware Rim Cylinder Primus Core Only Mortise Cylinder Mortise Cylinder Door Pull Surface Closer Overhead Holder Kick Plate Floor Stop & Holder Seals Door Sweep Threshold Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-11 HARDWARE GROUP: 07 6 1 1 1 1 3 1 1 1 2 2 2 1 2 1 Ea Ea Ea Ea Ea Ea Ea Ea Ea Ea Ea Ea Set Ea Ea Hinge Mullion Panic Hardware Panic Hardware Rim Cylinder Primus Core Only Mortise Cylinder Mortise Cylinder Door Pull Surface Closer Kick Plate Floor Stop & Holder Seals Door Sweep Threshold 5BB1HW 4.5 X 4.5 NRP KR4954 X 154 STABILIZER CD99NL-OP LD99EO 20-057-ICX 20-740 26-091-ICX (MULLION) 26-091-ICX XQ11-948 (DOGGING) VR910NL 4111 AVB EDA 8400 10" X 2" LDW FS43 5050C 200NA Per Detail 630 689 626 626 626 626 626 626 630 689 630 626 CHA 628 AL IVE VON VON VON SCH SCH SCH SCH IVE LCN IVE IVE NGP NGP NGP 5BB1 4.5 X 4.5 NRP L9056T 03A L583-363 20-740 4011 FS436/8 5050C 35VA Per Detail 630 626 626 689 626 CHA CL AL IVE SCH SCH LCN IVE NGP NGP NGP 5BB1HW 4.5 X 4.5 NRP L9070T 03A 20-740 4111 EDA 8400 10" X 2" LDW FS18L 5050C 200NA Per Detail 630 626 626 689 630 BLK CHA 628 AL IVE SCH SCH LCN IVE IVE NGP NGP NGP HARDWARE GROUP: 08 3 1 1 1 1 1 1 1 Ea Ea Ea Ea Ea Set Ea Ea Hinge Office Lock Primus Core Only Surface Closer Dome Stop Seals Door Bottom Threshold HARDWARE GROUP: 09 3 1 1 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Set Ea Ea Hinge Classroom Lock Primus Core Only Surface Closer Kick Plate Security Floor Stop Seals Door Sweep Threshold Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-12 HARDWARE GROUP: 10 6 1 1 1 1 1 2 2 1 Ea Set Ea Ea Ea Ea Ea Ea Ea Hinge Const Latching Bolt Dust Proof Strike Storeroom Lock Primus Core Only Astragal Overhead Holder Door Sweep Threshold 5BB1 4.5 X 4.5 NRP FB51P DP1 LV9080T 03A 20-740 139SP (OR BY HM DOOR MFR) 700H 200NA Per Detail 630 630 626 626 626 600 626 628 AL IVE IVE IVE SCH SCH NGP GLY NGP NGP 5BB1HW 4.5 X 4.5 NRP LV9080T 03A 20-740 700H 5050C 200NA Per Detail 630 626 626 626 CHA 628 AL IVE SCH SCH GLY NGP NGP NGP 5BB1HW 4.5 X 4.5 NRP L9070T 03A 20-740 4111 EDA 8400 10" X 2" LDW FS43 5050C 200NA Per Detail 630 626 626 689 630 626 CHA 628 AL IVE SCH SCH LCN IVE IVE NGP NGP NGP 5BB1 4.5 X 4.5 L9056T 03A L583-363 20-740 FS436/8 5050C 652 626 626 626 CHA IVE SCH SCH IVE NGP HARDWARE GROUP: 11 3 1 1 1 1 1 1 Ea Ea Ea Ea Set Ea Ea Hinge Storeroom Lock Primus Core Only Overhead Holder Seals Door Sweep Threshold HARDWARE GROUP: 12 3 1 1 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Set Ea Ea Hinge Classroom Lock Primus Core Only Surface Closer Kick Plate Floor Stop & Holder Seals Door Sweep Threshold HARDWARE GROUP: 13 3 1 1 1 1 Ea Ea Ea Ea Set Hinge Office Lock Primus Core Only Dome Stop Seals Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-13 HARDWARE GROUP: 14 3 1 1 1 1 1 1 1 Ea Ea Ea Ea Set Set Ea Ea Hinge Privacy Lock Primus Core Only Wall Stop Light Seals Seals Door Bottom Threshold 5BB1HW 4.5 X 4.5 L9496T 03A L583-363 20-740 WS407CVX 110SA 5050C 225N Per Detail 652 626 626 630 CL CHA AL AL IVE SCH SCH IVE NGP NGP NGP NGP 5BB1HW 4.5 X 4.5 L9080T 03A 20-740 8400 10" X 2" LDW FS41 5050C 652 626 626 630 626 CHA IVE SCH SCH IVE IVE NGP 5BB1HW 4.5 X 4.5 NRP 99L-F 996L-03 20-057-ICX 20-740 4111 AVB EDA 8400 10" X 2" LDW FS436/8 5050C 652 626 626 626 689 630 626 CHA IVE VON SCH SCH LCN IVE IVE NGP 5BB1 4.5 X 4.5 L9080T 03A 20-740 4011 8400 10" X 2" LDW WS407CVX 5050C 652 626 626 689 630 630 CHA IVE SCH SCH LCN IVE IVE NGP HARDWARE GROUP: 15 3 1 1 1 1 1 Ea Ea Ea Ea Ea Set Hinge Storeroom Lock Primus Core Only Kick Plate Floor Stop & Holder Seals HARDWARE GROUP: 16 3 1 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Ea Set Hinge Fire Exit Hardware Rim Cylinder Primus Core Only Surface Closer Kick Plate Dome Stop Seals HARDWARE GROUP: 17 3 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Set Hinge Storeroom Lock Primus Core Only Surface Closer Kick Plate Wall Stop Seals HARDWARE GROUP: 18 3 Ea Hinge 1 Ea Classroom Lock 1 Ea Primus Core Only 1 Ea Surface Closer 1 Ea Kick Plate 1 Ea Dome Stop 1 Set Seals Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 5BB1HW 4.5 X 4.5 NRP L9070T 03A 20-740 4111 EDA 8400 10" X 2" LDW FS436/8 5050C Door Hardware 652 IVE 626 SCH 626 SCH 689 LCN 630 IVE 626 IVE CHA NGP Section 08 71 00-14 HARDWARE GROUP: 19 6 1 1 1 1 1 1 2 2 1 Ea Set Ea Ea Ea Ea Ea Ea Ea Set Hinge Const Latching Bolt Storeroom Lock Primus Core Only Coordinator Astragal Surface Closer Kick Plate Dome Stop Seals 5BB1HW 4.5 X 4.5 FB62 L9080T 03A 20-740 COR X FL 158SA 4011 8400 10" X 2" LDW FS436/8 5050C 652 630 626 626 628 CL 689 630 626 CHA IVE IVE SCH SCH IVE NGP LCN IVE IVE NGP 5BB1HW 4.5 X 4.5 FB61T L9070T 03A 20-740 COR X FL 158NA 4011 8400 10" X 2" LDW FS41 652 630 626 626 628 628 689 630 626 IVE IVE SCH SCH IVE NGP LCN IVE IVE 5BB1HW 4.5 X 4.5 NRP L9070T 03A 20-740 4111 EDA 8400 10" X 2" LDW FS41 5050C 652 626 626 689 630 626 CHA IVE SCH SCH LCN IVE IVE NGP 5BB1HW 4.5 X 4.5 NRP L9070T 03A 20-740 4111 EDA 8400 10" X 2" LDW FS436/8 9450C 652 626 626 689 630 626 CHA IVE SCH SCH LCN IVE IVE NGP HARDWARE GROUP: 20 6 1 1 1 1 1 1 2 2 Ea Ea Ea Ea Ea Ea Ea Ea Ea Hinge Const Latching Bolt Classroom Lock Primus Core Only Coordinator Astragal Surface Closer Kick Plate Floor Stop & Holder HARDWARE GROUP: 21 3 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Set Hinge Classroom Lock Primus Core Only Surface Closer Kick Plate Floor Stop & Holder Seals HARDWARE GROUP: 22 3 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Set Hinge Classroom Lock Primus Core Only Surface Closer Kick Plate Dome Stop Seals Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-15 HARDWARE GROUP: 23 3 1 1 1 1 1 1 Ea Ea Ea Ea Ea Ea Set Hinge Classroom Lock Primus Core Only Surface Closer Kick Plate Dome Stop Seals 5BB1HW 4.5 X 4.5 NRP L9070T 03A 20-740 4011 8400 10" X 2" LDW FS436/8 9450C 652 626 626 689 630 626 CHA IVE SCH SCH LCN IVE IVE NGP END OF SECTION Monterey Peninsula College Art Department Modernizations Buildings 1 & 30 Door Hardware Section 08 71 00-16 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 SECTION 23 09 00 – TEMPERATURE CONTROLS PART 1: GENERAL 1.0 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 1.1 SECTION INCLUDES Products Furnished But Not Installed Under This Section Products Installed But Not Furnished Under This Section Products Not Furnished or Installed But Integrated with the Work of this Section Related Sections Description Approved Control System Contractor Quality Assurance Codes and Standards System Performance Submittals Warranty Ownership of Proprietary Material PRODUCTS FURNISHED BUT NOT INSTALLED UNDER THIS SECTION A. Division 23 - Ductwork Accessories: 1. Automatic Dampers 2. Airflow Stations 1.2 PRODUCTS INSTALLED BUT NOT FURNISHED UNDER THIS SECTION A. Division 23 – Air Handling Equipment: 1. Thermostats 2. Sensors 3. Controllers 1.3 PRODUCTS NOT FURNISHED OR INSTALLED BUT INTEGRATED WITH THE WORK OF THIS SECTION A. Division 23 –Air Handling Equipment 1. Discharge Air Temperature Control 1.4 RELATED SECTIONS A. The General Conditions of the Contract, Supplementary Conditions, and General Requirements are a part of these Specifications and shall be used in conjunction with this Section as a part of the Contract Documents. Consult them for further instructions pertaining to this work. The Contractor is bound by the provisions of Division 0 and Division 1. B. The following sections constitute related work: 1. Division 1 - Commissioning 2. Division 23 00 00 – Mechanical General 3. Division 23 05 00 – Heating, Ventilating, and Air Conditioning 4. Division 26 – Electrical TEMPERATURE CONTROLS 23 09 00 - 1 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 1.5 DESCRIPTION A. General: The control system shall be as indicated on the drawings and described in the specifications, and consist of a peer-to-peer network of digital building control panels and operator workstation(s). The user interface shall be able to get through any personal computer available on the network. The PC shall provide users an interface with the system through dynamic color graphics of building areas and systems. B. Direct Digital Control (DDC) technology shall be used to provide the functions necessary for control of systems defined for control on this project. C. The control system shall accommodate simultaneous multiple user operation. Access to the control system data should be limited by operator ID and password. An operator shall be able to log onto any PC on the designated network and have access to all designated data. D. The control system shall be designed such that each mechanical system will operate under standalone control. As such, in the event of a network communication failure, or the loss of other controllers, the control system shall continue to independently operate the unaffected equipment. E. Communication between the control panels and all workstations shall be over a high-speed network. All nodes on this network shall be peers. A modem or internet connectivity may be provided for remote access to the system. 1.6 APPROVED CONTROL SYSTEM CONTRACTORS AND MANUFACTURERS A. Approved Control System Contractors and Manufacturers: a) Siemens 1. 1.7 The above list of manufacturers applies to user interface, controller software, custom application programming language, Building Controllers, Custom Application Controllers, and Application Specific Controllers. All other products specified herein (i.e., sensors, valves, dampers, and actuators) need not be manufactured by the above manufacturers. QUALITY ASSURANCE A. System Installer Qualifications 1. The Installer shall have an established working relationship with the Control System Manufacturer of not less than three years. 2. The Installer shall have successfully completed Control System Manufacturer's classes on the control system. The Installer shall present for review the certification of completed training, including the hours of instruction and course outlines upon request. 3. The installer shall have an office within 50 miles of the project site and provide 24-hour response in the event of a customer call. 1.8 CODES AND STANDARDS TEMPERATURE CONTROLS 23 09 00 - 2 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 A. Work, materials, and equipment shall comply with the rules and regulations of all codes and ordinances of local, state and federal authorities. As a minimum, the installation shall comply with the current editions in effect 30 days prior to receipt of bids of the following codes: 1. National Electric Code (NEC) 2. California Building Code (CBC) 3. California Mechanical Code (CMC) 4. Underwriters Laboratories: Products shall be UL-916-PAZX listed. 5. ISO/IEC 14908-1 (LonTalk) 1.9 SYSTEM PERFORMANCE A. Performance Standards. The system shall conform to the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Page Display. The system shall display a web page will be displayed within [5] seconds of the request. There is no maximum amount of dynamic points that can be displayed. Page Refresh. The system shall update all within [10] seconds. Graphic Refresh. The system shall update all dynamic points with current data within [30] seconds. Object Command. The maximum time between the command of a binary object by the operator and the reaction by the device shall be 10 seconds. Analog objects shall start to adjust within 10 seconds.Object Scan. All changes of state and change of analog values shall be transmitted over the high-speed network such that any data used or displayed at a controller or workstation will be current, within the prior [60] seconds. Alarm Response Time. The maximum time from when an object goes into alarm to when it is annunciated at the workstation shall not exceed [30] seconds. Program Execution Frequency. Custom programs shall be capable of running as often as once every second. The Contractor shall be responsible for selecting execution times consistent with the mechanical process under control. Performance. Programmable Controllers shall be able to execute DDC PID control loops at a selectable frequency from at least once every [5] seconds. The controller shall scan and update the process value and output generated by this calculation at this same frequency. Multiple Alarm Annunciations. All users on the network shall receive alarms within [10] seconds of each other. Reporting Accuracy. Table 1 lists minimum acceptable reporting accuracies for all values reported by the specified system. Table 1 Reporting Accuracy Measured Variable Space Temperature Ducted Air Outside Air Water Temperature Delta-T Relative Humidity Water Flow Air Flow (terminal) TEMPERATURE CONTROLS Reported Accuracy ±0.5°C [±1°F] ±1.0°C [±2°F] ±1.0°C [±2°F] ±0.5°C [±1°F] ±0.15°C [±0.25°F] ±5% RH ±5% of full scale ±10% of reading *Note 1 23 09 00 - 3 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 Air Flow (measuring stations) Air Pressure (ducts) Air Pressure (space) Water Pressure Electrical Power Carbon Monoxide (CO) Carbon Dioxide (CO2) ±5% of reading ±25 Pa [±0.1 "W.G.] ±3 Pa [±0.01 "W.G.] ±2% of full scale *Note 2 ± 5% of reading *Note 3 ± 5% of reading ± 50 PPM Note 1: (10%-100% of scale) (cannot read accurately below 10%) Note 2: for both absolute and differential pressure Note 3: * not including utility supplied meters 1.10 SUBMITTALS A. Contractor shall provide shop drawings and manufacturers’ standard specification data sheets on all hardware and software to be provided. No work may begin on any segment of this project until the Engineer and Owner have reviewed submittals for conformity with the plan and specifications. Six (6) copies are required. All shop drawings shall be provided to the Owner electronically as .dwg or .dxf file formats. B. Quantities of items submitted shall be reviewed by the Engineer and Owner. Such review shall not relieve the contractor from furnishing quantities required for completion. C. Provide the Engineer and Owner, any additional information or data which is deemed necessary to determine compliance with these specifications or which is deemed valuable in documenting the system to be installed. D. Submit the following within 20 days of contract award: 1. A complete bill of materials of equipment to be used indicating quantity, manufacturer and model number. A schedule of all control dampers. This shall include the damper size, pressure drop, manufacturer and model number. Provide manufacturers cut sheets for major system components. When manufacturer's cut sheets apply to a product series rather than a specific product, the data specifically applicable to the project shall be highlighted or clearly indicated by other means. Each submitted piece of literature and drawings shall clearly reference the specification and/or drawing that the submittal is being submitted to cover. Include: 2. 3. a) b) c) d) e) f) g) Building Controllers Custom Application Controllers Application Specific Controllers Operator Interface Computer(s) Portable Operator Workstation Auxiliary Control Devices Proposed control system riser diagram showing system configuration, device locations, addresses, and cabling h) Detailed termination drawings showing all required field and factory terminations. Terminal numbers shall be clearly labeled i) Points list showing all system objects, and the proposed English language object names TEMPERATURE CONTROLS 23 09 00 - 4 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 j) Sequence of operations for each system under control. This sequence shall be specific for the use of the Control System being provided for this project k) Color prints of proposed graphics with a list of points for display E. Project Record Documents. Upon completion of installation submit three (3) copies of record (asbuilt) documents. The documents shall be submitted for approval prior to final completion and include: 1. 2. 3. a) b) c) d) e) f) g) Project Record Drawings. These shall be as-built versions of the submittal shop drawings. One set of electronic media including CAD .DWG or .DXF drawing files shall also be provided. Testing and Commissioning Reports and Checklists. Operating and Maintenance (O & M) Manual. These shall be as-built versions of the submittal product data. In addition to that required for the submittals, the O & M manual shall include: Names, address and 24-hour telephone numbers of Contractors installing equipment, and the control systems and service representative of each. Provide on-line help for documenting operator instructions A listing and documentation of all custom software created using the programming language including the point database. One set of magnetic media containing files of the software and database shall also be provided. One set of electronic media containing files of all color-graphic screens created for the project. Complete original issue documentation, installation, and maintenance information for all third party hardware provided including computer equipment and sensors. Licenses and warranty documents for all equipment and systems. Recommended preventive maintenance procedures for all system components including a schedule of tasks, time between tasks, and task descriptions. F. Training Materials: The Contractor shall provide a course outline and training material for all training classes at least six weeks prior to the first class. The Owner reserves the right to modify any or all of the training course outline and training materials. Review and approval by Owner and Engineer shall be completed at least 3 weeks prior to first class. 1.11 WARRANTY A. Warrant all work as follows: 1. 2. 3. Labor & materials for control system specified shall be warranted free from defects for a period of twelve (12) months after final completion acceptance by the Owner. Control System failures during the warranty period shall be adjusted, repaired, or replaced at no charge or reduction in service to the Owner. The Contractor shall respond to the Owner's request for warranty service within 24 hours during customary business hours. At the end of the final start-up/testing, if equipment and systems are operating satisfactorily to the Owner and Engineer, the Owner shall sign certificates certifying that the control system's operation has been tested and accepted in accordance with the terms of this specification. The date of Owner's acceptance shall be the start of warranty. Operator workstation software, project specific software, graphics, database, and firmware updates shall be provided to the Owner at no charge during the warranty period. Written authorization by Owner must, however, be granted prior to the installation of such changes. TEMPERATURE CONTROLS 23 09 00 - 5 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 4. The system provider shall provide a web-accessible system and support on-line resource that provides the Owner access to a question/answer forum, graphics library, user tips, upgrades, and manufacturer training schedules. 1.12 OWNERSHIP OF PROPRIETARY MATERIAL A. All project-developed hardware and software shall become the property of the Owner. These items include but are not limited to: 1. Project graphic images 2. Record drawings 3. Project database 4. Project-specific application programming code 5. All documentation PART 2: PRODUCTS 2.0 1. 2. 3. 4. 5. 6. 7. 8. SECTION INCLUDES Materials Communication Operator Interface Application and Control Software Building Controllers Application Specific Controllers Input/Output Interface Auxiliary Control Devices 2.1 MATERIALS A. All products used in this installation shall be new, currently under manufacture, and shall be applied in similar installations for a minimum of 2 years. The installation shall not be used as a test site for any new products unless explicitly approved by the Owner’s representative in writing. Spare parts shall be available for at least 5 years after completion of this contract. 2.2 COMMUNICATION A. This project shall comprise of a network utilizing high-speed for communications between Building Controllers. LonTalk sub-networks shall be used for communications between Building Controllers, Custom Application Controllers and Application Specific Controllers. B. The Owner will provide all communication media, connectors, repeaters, network switches, and routers necessary for the internetwork. An active Ethernet jack will be provided adjacent to each Building Control Panel and PC Workstation for connection to this network. C. All Building Controllers shall have an Ethernet communications port for connections with the operator interfaces. D. Communications services over the internetwork shall result in operator interface and value passing that is transparent to the internetwork architecture as follows: TEMPERATURE CONTROLS 23 09 00 - 6 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 1. Connection of an operator interface device to any one building controller on the internetwork will allow the operator to interface with all other building controllers as if that interface were directly connected to the other controllers. Data, status information, reports, system software, custom programs, etc., for all building controllers shall be available for viewing and editing from any one building controller on the internetwork. 2. All database values (i.e., points, software variable, custom program variables) of any one building controller shall be readable by any other building controller on the internetwork. This value passing shall be automatically performed by a controller when a reference to a point name not located in that controller is entered into the controller's database. An operator/installer shall not be required to set up any communications services to perform internetwork value passing. F. The time clocks in all building controllers shall be automatically synchronized daily. 2.3 OPERATOR INTERFACE A. Operator workstation is existing. 2.4 APPLICATION AND CONTROL SOFTWARE A. Scheduling. Provide the capability to schedule each object or group of objects in the system. Each of these schedules shall include the capability for start, stop, optimal start, optimal stop, and night economizer actions. Each schedule may consist of up to [10] events. When a group of objects are scheduled together, provide the capability to define advances and delays for each member. Each schedule shall consist of the following: 1. 2. 3. 4. B. Weekly Schedule. Provide separate schedules for each day of the week. Exception Schedules. Provide the ability for the operator to designate any day of the year as an exception schedule. This exception schedule shall override the standard schedule for that day. Exception schedules may be defined up to a year in advance. Once an exception schedule is executed it will be discarded and replaced by the standard schedule for that day of the week. Holiday Schedules. Provide the capability for the operator to define up to 99 special or holiday schedules. These schedules may be placed on the scheduling calendar and will be repeated each year. The operator shall be able to define the length of each holiday period. Optimal Start. The scheduling application outlined above shall support an optimal start algorithm. This shall calculate the thermal characteristics of a zone and start the equipment prior to occupancy to achieve the desired space temperature at the specified occupancy time. The algorithm shall calculate separate sets of heating and cooling rates for zones that have been unoccupied for less then and greater than 24 hours. Provide the ability to modify the start algorithm based on outdoor air temperature. Provide an early start limit in minutes to prevent the system from starting before an operator determined time limit. Remote Communications. The system shall have the ability to transmit alarms to multiple associated alarm receivers. Receivers shall include PC Workstations, email addresses, and cell phones. The alarm message shall include the name of the alarm location, the device that generated the alarm, and the alarm message itself. The operator shall be able to remotely access TEMPERATURE CONTROLS 23 09 00 - 7 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 and operate the system utilizing the system Ethernet communications, or dial up communications via modem, in the same format and method used on site as described under the Operator Interface section of this specification. C. PID Control. A PID (proportional-integral-derivative) algorithm with direct or reverse action and anti-wind-up shall be supplied. The algorithm shall calculate a time-varying analog value used to position an output or stage a series of outputs. The controlled variable, and set-point, shall be user-selectable. The set-point shall optionally be chosen to be a reset schedule. D. Point control. User shall have the option to set the update interval, minimum on/off time, event notification, custom programming on change of events E. Timed Override. A standard application shall be utilized to enable/disable temperature control when a user selects on/cancel at the zone sensor, workstation, or the operator display. The amount of time that the override takes precedence will be selectable from the workstation. F. Anti-Short Cycling. All binary output points shall be protected from short cycling. 2.5 BUILDING CONTROLLERS A. General. Provide Building Controllers to provide the performance specified in section 1 of this division. Each of these panels shall meet the following requirements. 1. The Building Automation System shall be composed of one or more independent, standalone, microprocessor based Building Controllers to manage the global strategies described in System software section. 2. The Building Controller shall have sufficient memory to support its operating system, database, and programming requirements. 3. The controller shall provide a USB communications port for connection to a PC. 4. The operating system of the Controller shall manage the input and output communications signals to allow distributed controllers to share real and virtual point information and allow central monitoring and alarms. 5. Controllers that perform scheduling shall have a real time clock. 6. Data shall be shared between networked Building Controllers. 7. The Building Controller shall utilize industry recognized open standard protocols for communication to unit controllers. 8. The Building Controller shall continually check the status of its processor and memory circuits. If an abnormal operation is detected, the controller shall: i. Assume a predetermined failure mode. ii. Generate an alarm notification. iii. Create a retrievable file of the state of all applicable memory locations at the time of the failure. iv. Automatically reset the Building Controller to return to a normal operating mode. Communications. Each Building Controller shall reside on the Enterprise wide network, which is same high-speed network as the workstations. The Enterprise wide network will be provided by the owner and supports the Internet Protocol (IP). Local connections of the Building Controller shall be on ISO 8802-3 (Ethernet). Each Building Controller shall also perform routing to a network of Custom Application and Application Specific Controllers) [Optional – Each Building Controller shall perform communications to a network of Custom Application and Application Specific Controllers using LonTalk FTT-10 and LonMark profiles. B. TEMPERATURE CONTROLS 23 09 00 - 8 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 C. Environment. Controller hardware shall be suitable for the anticipated ambient conditions. Controller used in conditioned ambient shall be mounted in an enclosure, and shall be rated for operation at -40 C to 50 C [-40 F to 122 F]. D. Serviceability. Provide diagnostic LEDs for power, communications, and processor. The Building Controller shall have a display on the main board that indicates the current operating mode of the controller. All wiring connections shall be made to field removable, modular terminal connectors. The building controller shall utilize standard DIN mounting methods for installation and replacement. E. Memory. The Building Controller shall maintain all BIOS and programming information indefinitely without power to the building controller. F. Immunity to power and noise. Controller shall be able to operate at 90% to 110% of nominal voltage rating and shall perform an orderly shut-down below 80% nominal voltage 2.6 APPLICATION SPECIFIC CONTROLLERS A. General. Application specific controllers (ASC) are microprocessor-based DDC controllers, which through hardware or firmware design are dedicated to control a specific piece of equipment. They are not fully user programmable, but are customized for operation within the confines of the equipment they are designed to serve. 1. 2. B. Each ASC shall be capable of stand-alone operation and shall continue to provide control functions without being connected to the network. Each ASC will contain sufficient I/O capacity to control the target system. Environment. The hardware shall be suitable for the anticipated ambient conditions. 1. 2. Controller used in conditioned ambient spaces shall be mounted in IP 20 type rated enclosures. Controllers located where not to be disturbed by building activity (such as above ceiling grid), may be provided with plenum-rated enclosures and non-enclosed wiring connections for plenum cabling. All controllers shall be rated for operation at 0 C to 50 C [32 F to 120 F]. Controllers used outdoors and/or in wet ambient shall be mounted within IP 56 type waterproof enclosures, and shall be rated for operation at -40 C to 65 C [-40 F to 150 F]. C. Serviceability. Provide diagnostic LEDs for power and communications. All wiring connections shall be clearly labeled and made to be field removable. D. Memory. The Application Specific Controller shall maintain all BIOS and programming information in the event of a power loss for at least 90 days. E. Immunity to Power and noise. Controller shall be able to operate at 90% to 110% of nominal voltage rating and shall perform an orderly shutdown below 80%. F. Transformer. Power supply for the ASC must be rated at minimum of 125% of ASC power consumption, and shall be fused or current limiting type. G. Application Specific Controllers shall communicate using LonTalk. In case of LonTalk, Controllers shall use FTT-10 transceivers. All communications shall follow LonMark profiles. TEMPERATURE CONTROLS 23 09 00 - 9 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 ASCs which do not have a profile that applies must comply with LonMark standards, utilize SNVTs for all listed points, and be provided with a XIF file for self-documentation. 2.7 INPUT/OUTPUT INTERFACE A. Hard-wired inputs and outputs may tie into the system through Building, Custom, or Application Specific Controllers. B. All input points and output points shall be protected such that shorting of the point to itself, another point, or ground will cause no damage to the controller. All input and output points shall be protected from voltage up to 24V of any duration, such that contact with this voltage will cause no damage to the controller. C. Binary inputs shall allow the monitoring of on/off signals from remote devices. The binary inputs shall provide a wetting current of at least 12 mA to be compatible with commonly available control devices. D. Pulse accumulation input points. This type of point shall conform to all the requirements of Binary Input points, and also accept up to 3 pulses per second for pulse accumulation, and shall be protected against effects of contact bounce and noise. E. Analog inputs shall allow the monitoring of low voltage (0-10 Vdc), current (4-20 ma), or resistance signals (thermistor, RTD). Analog inputs shall be compatible with, and field configurable to commonly available sensing devices. F. Binary outputs shall provide for on/off operation. Terminal unit and zone control applications may use 2 outputs for drive-open, drive-close (tri-state) modulating control. Binary outputs on custom application controllers shall have 3-mode (on/off/auto) program override control from the panel with output status lights. G. Analog outputs shall provide a modulating signal for the control of end devices. Outputs shall provide either a 0-10 Vdc or a 4-20 ma signal as required to provide proper control of the output device. Analog outputs on custom application controllers shall have a 2-mode (auto/manual) program override control, with manual output adjustment over 0-100% of range. 2.8 AUXILIARY CONTROL DEVICES A. For motorized and control damper requirements, see 23 05 00. B. Electric damper actuators. 1. 2. 3. 4. The actuator shall have electronic overload or digital rotation sensing circuitry to prevent damage to the actuator throughout the rotation of the actuator. Where shown, for power-failure/safety applications, an internal mechanical, spring return mechanism shall be built into the actuator housing. All rotary spring return actuators shall be capable of both clockwise and counter clockwise spring return operation. Linear actuators shall spring return to the retracted position. Proportional actuators shall accept a 0-10 VDC or 0-20 ma control signal and provide a 2-10 VDC or 4-20 ma operating range. TEMPERATURE CONTROLS 23 09 00 - 10 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 5. 6. 7. 8. E. Binary Temperature Devices 1. 2. 3. F. 3. 4. 5. 6. Temperature sensors shall be Resistance Temperature Device (RTD) or Thermistor. Duct sensors shall be rigid or averaging as shown. Averaging sensors shall be a minimum of 1.5m [5 feet] in length. Immersion sensors shall be provided with a separable stainless steel well. Pressure rating of well is to be consistent with the system pressure in which it is to be installed. Space sensors shall be equipped with set-point adjustment, override switch, display, and/or communication port as shown on the drawings. Provide matched temperature sensors for differential temperature measurement. Differential accuracy shall be within 0.1 C [0.2 F]. [Optional] The space temperature, set point, and override confirmation will be annunciated by a digital display for each zone sensor. The set point will be selectable utilizing buttons. Relays 1. 2. H. Low-Voltage Space Thermostats shall be 24 V, bimetal-operated, mercury-switch type, with either adjustable or fixed anticipation heater, concealed set point adjustment, 13°C30°C (55°F-85°F) set point range, 1°C (2°F) maximum differential, and vented cover. Line-Voltage Space Thermostats shall be bimetal-actuated, open-contact type or bellowsactuated, enclosed, snap-switch type or equivalent solid-state type, with heat anticipator, UL listing for electrical rating, concealed set point adjustment, 13°C-30°C (55°F-85°F) set point range, 1°C (2°F) maximum differential, and vented cover. Low-Limit airstream thermostats shall be UL listed, vapor pressure type. Element shall be at least 6 m (20 ft) long. Element shall sense temperature in each 30 cm (1 ft) section and shall respond to lowest sensed temperature. Low-limit thermostat shall be manual reset only. Temperature Sensors 1. 2. G. All non-spring return actuators shall have an external manual gear release to allow manual positioning of the damper when the actuator is not powered. Spring return actuators with more than 60 in-lb. torque capacity shall have a manual crank for this purpose. Actuators shall be provided with a conduit fitting and a minimum 1m electrical cable and shall be pre-wired to eliminate the necessity of opening the actuator housing to make electrical connections. Actuators shall be Underwriters Laboratories Standard 873 listed. Actuators shall be designed for a minimum of 60,000 full stroke cycles at the actuator's rated torque. Control relays shall be UL listed plug-in type with dust cover. Contact rating, configuration, and coil voltage suitable for application. Time delay relays shall be UL listed solid-state plug-in type with adjustable time delay. Delay shall be adjustable plus or minus 200% (minimum) from set-point shown on plans. Contact rating, configuration, and coil voltage suitable for application. Provide IP 20 Type enclosure when not installed in local control panel. Transformers and Power Supplies TEMPERATURE CONTROLS 23 09 00 - 11 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 1. 2. 3. 4. I. Current Switches 1. J. Control transformers shall be UL listed, Class 2 current-limiting type, or shall be furnished with over-current protection in both primary and secondary circuits for Class 2 service. Unit output shall match the required output current and voltage requirements. Current output shall allow for a 50% safety factor. Output ripple shall be 70.0 mV maximum Peak-to-Peak. Regulation shall be 5% line and load combined, with 50 microsecond response time for 50% load changes. Unit shall have built-in over-voltage protection. Unit shall operate between 0 C and 50 C. Unit shall be UL recognized. Current-operated switches shall be self-powered, solid state with adjustable trip current. The switches shall be selected to match the current of the application and output requirements of the DDC system. LOCAL CONTROL PANELS 1. 2. 3. All indoor control cabinets shall be fully enclosed IP 20 Type construction with hinged door, and removable sub-panels or electrical sub-assemblies. Interconnections between internal and face-mounted devices shall be pre-wired with color-coded stranded conductors neatly installed in plastic troughs and/or tie-wrapped. Terminals for field connections shall be UL listed for 600-volt service, individually identified per control/interlock drawings, with adequate clearance for field wiring. Control terminations for field connection shall be individually identified per control drawings. Provide on/off power switch with over-current protection for control power sources to each local panel. PART 3: EXECUTION 3.0 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. SECTION INCLUDES: Examination Protection General Workmanship Field Quality Control Wiring Fiber Optic Cable Installation of Sensors Actuators Warning Labels Identification of Hardware and Wiring Controllers Programming Cleaning Training Acceptance Control Dampers Sequence of Operation TEMPERATURE CONTROLS 23 09 00 - 12 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 3.1 EXAMINATION A. The project plans shall be thoroughly examined for control device and equipment locations, and any discrepancies, conflicts, or omissions shall be reported to the Architect/Engineer for resolution before rough-in work is started. B. The contractor shall inspect the site to verify that equipment is installable as shown, and any discrepancies, conflicts, or omissions shall be reported to the Architect/Engineer for resolution before rough-in work is started. 3.2 PROTECTION A. The Contractor shall protect all work and material from damage by his/her work or workers, and shall be liable for all damage thus caused. B. The Contractor shall be responsible for his/her work and equipment until finally inspected, tested, and accepted. The Contractor shall protect his/her work against theft or damage, and shall carefully store material and equipment received on site that is not immediately installed. The Contractor shall close all open ends of work with temporary covers or plugs during storage and construction to prevent entry of foreign objects. 3.3 GENERAL WORKMANSHIP A. Install equipment, piping, wiring/conduit parallel to building lines (i.e. horizontal, vertical, and parallel to walls) wherever possible. B. Provide sufficient slack and flexible connections to allow for vibration of piping and equipment. C. Install all equipment in readily accessible location as defined by chapter 1 article 100 part A of the NEC. Control panels shall be attached to structural walls unless mounted in equipment enclosure specifically designed for that purpose. Panels shall be mounted to allow for unobstructed access for service. D. Verify integrity of all wiring to ensure continuity and freedom from shorts and grounds. E. All equipment, installation, and wiring shall comply with acceptable industry specifications and standards for performance, reliability, and compatibility and be executed in strict adherence to local codes and standard practices. 3.4 FIELD QUALITY CONTROL A. All work, materials and equipment shall comply with the rules and regulations of applicable local, state, and federal codes and ordinances as identified in Part 1 of this Section. B. Contractor shall continually monitor the field installation for code compliance and quality of workmanship. All visible piping and or wiring runs shall be installed parallel to building lines and properly supported. C. Contractor shall arrange for field inspections by local and/or state authorities having jurisdiction over the work. TEMPERATURE CONTROLS 23 09 00 - 13 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 3.5 WIRING A. All control and interlock wiring shall comply with the national and local electrical codes and Division 26 of these specifications. Where the requirements of this section differ with those in Division 26, the requirements of this section shall take precedence. B. Where Class 2 wires are in concealed and accessible locations including ceiling return air plenums, approved cables not in raceway may be used provided that: C. Circuits meet NEC Class 2 (current-limited) requirements. (Low-voltage power circuits shall be sub-fused when required to meet Class 2 current-limit.) All cables shall be UL listed for application, i.e., cables used in ceiling plenums shall be UL listed specifically for that purpose. D. E. Do not install Class 2 wiring in conduit containing Class 1 wiring. Boxes and panels containing high voltage may not be used for low voltage wiring except for the purpose of interfacing the two (e.g. relays and transformers). F. Where class 2 wiring is run exposed, wiring shall be run parallel along a surface or perpendicular to it, and bundled, using approved wire ties at no greater than 3 m [10 ft] intervals. Such bundled cable shall be fastened to the structure, using specified fasteners, at 1.5 m [5 ft] intervals or more often to achieve a neat and workmanlike result. G. All wire-to-device connections shall be made at a terminal blocks or terminal strip. All wire-to wire connections shall be at a terminal block, or with a crimped connector. All wiring within enclosures shall be neatly bundled and anchored to permit access and prevent restriction to devices and terminals. H. Maximum allowable voltage for control wiring shall be 120V. If only higher voltages are available, the Control System Contractor shall provide step down transformers. I. All wiring shall be installed as continuous lengths, where possible. Any required splices shall be made only within an approved junction box or other approved protective device. J. Install plenum wiring in sleeves where it passes through walls and floors. Maintain fire rating at all penetrations in accordance with other sections of this specification and local codes. K. Size of conduit and size and type of wire shall be the design responsibility of the Control System Contractor, in keeping with the manufacturer's recommendation and NEC. L. Control and status relays are to be located in designated enclosures only. These relays may also be located within packaged equipment control panel enclosures. These relays shall not be located within Class 1 starter enclosures. M. Follow manufacturer's installation recommendations for all communication and network cabling. Network or communication cabling shall be run separately from other wiring. N. Adhere to Division 26 requirements for installation of raceway. TEMPERATURE CONTROLS 23 09 00 - 14 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 O. This Contractor shall terminate all control and/or interlock wiring and shall maintain updated (as-built) wiring diagrams with terminations identified at the job site. P. Flexible metal conduits and liquid-tight, flexible metal conduits shall not exceed 3' in length and shall be supported at each end. Flexible metal conduit less than 1/2" electrical trade size shall not be used. In areas exposed to moisture, including chiller and boiler rooms, liquid-tight, flexible metal conduits shall be used. 3.6 FIBER OPTIC CABLE SYSTEM A. All cabling shall be installed in a neat and workmanlike manner. Minimum cable and unjacketed fibber bend radii as specified by cable manufacturer shall be maintained. B. Maximum pulling tensions as specified by the cable manufacturer shall not be exceeded during installation. Post installation residual cable tension shall be within cable manufacture's specifications. C. Fiber optic cabinets, hardware, and cable entering the cabinet shall be installed in accordance with manufacturers' instructions. Minimum cable and unjacketed fiber bend radii as specified by cable manufacturer shall be maintained. 3.7 INSTALLATION OF SENSORS A. Install sensors in accordance with the manufacturer's recommendations. B. Mount sensors rigidly and adequate for the environment within which the sensor operates. C. Room temperature sensors shall be installed on concealed junction boxes properly supported by the wall framing. D. All wires attached to sensors shall be air sealed in their conduits or in the wall to stop air transmitted from other areas affecting sensor readings. E. Install duct static pressure tap with tube end facing directly down-stream of air flow. F. Wiring for space sensors shall be concealed in building walls. EMT conduit is acceptable within mechanical and service rooms. G. Install outdoor air temperature sensors on north wall complete with sun shield at designated location. 3.8 ACTUATORS A. Mount and link control damper actuators per manufacturer's instructions. 1. 2. To compress seals when spring return actuators are used on normally closed dampers, power actuator to approximately 5° open position, manually close the damper, and then tighten the linkage. Check operation of damper/actuator combination to confirm that actuator modulates damper smoothly throughout stroke to both open and closed positions. TEMPERATURE CONTROLS 23 09 00 - 15 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 3.9 WARNING LABELS A. Affix labels on each starter and equipment automatically controlled through the DDC System. Warning label shall indicate the following: CAUTION This equipment is operating under automatic control and may start or stop at any time without warning. Disconnect switch to “Off” position before servicing. B. Affix labels to motor starters and control panels that are connected to multiple power sources utilizing separate disconnects. Labels shall indicate the following: CAUTION This equipment is fed from more than one power source with separate disconnects. Disconnect all power sources before servicing. 3.10 IDENTIFICATION OF HARDWARE AND WIRING A. All wiring and cabling, including that within factory-fabricated panels, shall be labeled at each end within 2" of termination with a cable identifier and other descriptive information. B. Permanently label or code each point of field terminal strips to show the instrument or item served. C. Identify control panels with minimum 1-cm (1/2”) letters on nameplates. D. Identify all other control components with permanent labels. Identifiers shall match record documents. All plug-in components shall be labeled such that removal of the component does not remove the label. 3.11 CONTROLLERS A. Provide a separate Controller for each major piece of HVAC equipment. A custom application controller may control more than one system provided that all points associated with that system are assigned to the same controller. Points used for control loop reset such as outside air or space temperature are exempt from this requirement. B. Building Controllers and Custom Application Controllers shall be selected to provide a minimum of 15% spare I/O point capacity for each point type found at each location. If input points are not universal, 15% of each type is required. If outputs are not universal, 15% of each type is required. A minimum of one spare is required for each type of point used. TEMPERATURE CONTROLS 23 09 00 - 16 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 1. Future use of spare capacity shall require providing the field device, field wiring, points database definition, and custom software. No additional Controller boards or point modules shall be required to implement use of these spare points. 3.12 PROGRAMMING A. Provide sufficient internal memory for the specified control sequences and trend logging. There shall be a minimum of 25% of available memory free for future use. B. Point Naming: System point names shall be modular in design, allowing easy operator interface without the use of a written point index. C. Software Programming 1. D. Provide programming for the system as written in the specifications and adhere to the sequence strategies provided. All other system programming necessary for the operation of the system but not specified in this document shall also be provided by the Control System Contractor. Imbed into any custom-written control programs sufficient comment statements or inherent flow diagrams to clearly describe each section of the program. The comment statements shall reflect the language used in the sequence of operations. Operators' Interface 1. 2. 3. Standard Graphics. Provide graphics for each major piece of equipment and floor plan in the building. This includes each Chiller, Air Handler, VAV Terminal, Fan Coil, Boiler, and Cooling Tower. These standard graphics shall show all points dynamically as specified in the points list. The controls contractor shall provide all the labor necessary to install, initialize, start-up, and trouble-shoot all operator interface software and their functions as described in this section. This includes any operating system software, the operator interface database, and any third party software installation and integration required for successful operation of the operator interface. As part of this execution phase, the controls contractor will perform a complete test of the operator interface. Test duration shall be a minimum of 16 hours on-site. Tests shall be made in the presence of the Owner or Owner's representative. E. Demonstration: A complete demonstration and readout of the capabilities of the monitoring and control system shall be performed. The contractor shall dedicate a minimum of 16 hours on-site with the Owner and his representatives for a complete functional demonstration of all the system requirements. This demonstration constitutes a joint acceptance inspection, and permits acceptance of the delivered system for on-line operation. 3.13 CLEANING A. This contractor shall clean up all debris resulting from his or her activities daily. The contractor shall remove all cartons, containers, crates, etc. under his control as soon as their contents have been removed. Waste shall be collected and placed in a location designated by the Construction Manager or General Contractor. B. At the completion of work in any area, the Contractor shall clean all of his/her work, equipment, etc., making it free from dust, dirt and debris, etc. TEMPERATURE CONTROLS 23 09 00 - 17 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 C. At the completion of work, all equipment furnished under this Section shall be checked for paint damage, and any factory finished paint that has been damaged shall be repaired to match the adjacent areas. Any metal cabinet or enclosure that has been deformed shall be replaced with new material and repainted to match the adjacent areas. 3.14 TRAINING A. Provide a minimum of 4 classroom training sessions, 4 hours each, throughout the contract period for personnel designated by the Owner. Computer-based audio-visual training may be substituted for up to 8 hours of hands on training. B. Train the designated staff of Owner's representative and Owner to enable them to proficiently operate the system; create, modify and delete programming; add, remove and modify physical points for the system, and perform routine diagnostic and troubleshooting procedures. C. Additional training shall be available in courses designed to meet objectives as divided into three logical groupings; participants may attend one or more of these, depending on the level of knowledge required: 1. 2. 3. Day-to-day Operators Advanced Operators System Managers/Administrators D. Provide course outline and materials as per Part 1 of this Section. The instructor(s) shall provide one copy of training material per student. E. The instructor(s) shall be factory-trained instructors experienced in presenting this material. F. Classroom training shall be done using a network of working controllers representative of the installed hardware or at the customer’s site. G. This training shall be made available in addition to the interactive audio-visual tutorial, provided with the system. 3.15 ACCEPTANCE A. The control systems will not be accepted as meeting the requirements of Completion until all tests described in this specification have been performed to the satisfaction of both the Engineer and Owner. Any tests that cannot be performed due to circumstances beyond the control of the Contractor may be exempt from the Completion requirements if stated as such in writing by the Owner's representative. Such tests shall then be performed as part of the warranty. 3.17 CONTROL DAMPER INSTALLATION A. Damper submittals shall be coordinated for type, quantity, and size to ensure compatibility with sheet metal design. TEMPERATURE CONTROLS 23 09 00 - 18 MONTEREY PENINSULA COLLEGE – Art Department/Buildings 1 & 30 B. Duct openings shall be free of any obstruction or irregularities that might interfere with blade or linkage rotation or actuator mounting. Duct openings shall measure 1/4" larger than damper dimensions and shall be square, straight, and level. C. Individual damper sections, as well as entire multiple section assemblies, must be completely square and free from racking, twisting, or bending. Measure diagonally from upper corners to opposite lower corners of each damper section. Both dimensions must be equal ±1/8". D. Follow manufacturer's instructions for field installation of control dampers. Unless specifically designed for vertical blade application, dampers must be mounted with blade axis horizontal. E. Install extended shaft or jackshaft per manufacturer's instructions. (Typically, a sticker on the damper face shows recommended extended shaft location. Attach shaft on labeled side of damper to that blade.) F. Damper blades, axles, and linkage must operate without binding. Before system operation, cycle damper after installation to assure proper operation. On multiple section assemblies, all sections must open and close simultaneously. G. Provide a visible and accessible indication of damper position on the drive shaft end. H. Support duct-work in area of damper when required to prevent sagging due to damper weight. I. After installation of low-leakage dampers with seals, caulk between frame and duct or opening to prevent leakage around perimeter of damper. 3.19 SEQUENCE OF OPERATIONS A. For Sequences of Operations, see Drawings. *** END OF SECTION 15900 *** TEMPERATURE CONTROLS 23 09 00 - 19 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 SECTION 23 09 50 COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. 1.2 Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. SUMMARY A. Section includes commissioning process requirements for HVAC&R systems including Controls, assemblies, and equipment. B. Related Sections: 1. 1.3 Division 01 Section "01 91 00 General Commissioning Requirements" for general commissioning process requirements. DEFINITIONS A. 1.4 See Section 01 91 00 Commissioning Requirements for definitions CONTRACTOR'S RESPONSIBILITIES A. 1.5 See Section 01 91 00 Commissioning Requirements for contractor’s and sub contractors responsibilities CA'S RESPONSIBILITIES A. 1.6 See Section 01 91 00 Commissioning Requirements for CA responsibilities COMMISSIONING DOCUMENTATION A. Provide the following information to the CA for inclusion in the commissioning plan: 1. 2. Plan for delivery and review of submittals, systems manuals, and other documents and reports. Identification of installed systems, assemblies, equipment, and components including design changes that occurred during the construction phase. COMMISSIONING OF HVAC SYSTEM 23 09 50-1 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 3. 4. 5. 6. 7. 8. 1.7 Process and schedule for completing construction checklists and manufacturer's prestart and startup checklists for HVAC&R systems, assemblies, equipment, and components to be verified and tested. Certificate of completion certifying that installation, prestart checks, and startup procedures have been completed. Certificate of readiness certifying that HVAC&R systems, subsystems, equipment, and associated controls are ready for testing. Test and inspection reports and certificates. Corrective action documents. Verification of testing, adjusting, and balancing reports. SUBMITTALS A. Certificates of readiness. B. Certificates of completion of installation, prestart, and startup activities. Manufacturer start-up forms shall be submitted to CA within one week of completion of start-ups. C. Provide two copies of O&M manuals, sequence of operations and control diagrams and blank start-up forms related to commissioned equipment and systems within 30 days of engineers approval in a three ring binder. Controls drawings shall be minimum 11x17. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 TESTING PREPARATION A. Review 01 91 00 General Commissioning Requirements, in inter trade coordination meeting.(Mechanical dry and wet side, TAB, Controls and Electrical subcontractors minimum). Meeting minutes shall be submitted to CA. Inter trade meeting is mandatory per this section. B. Certify that HVAC&R systems, subsystems, and equipment have been installed, calibrated, and started and are operating according to the Contract Documents. C. Certify that HVAC&R instrumentation and control systems have been completed and calibrated, that they are operating according to the Contract Documents, and that pretest set points have been recorded. D. Certify that testing, adjusting, and balancing procedures have been completed and that testing, adjusting, and balancing reports have been submitted, discrepancies corrected, and corrective work approved. E. Set systems, subsystems, and equipment into operating mode to be tested (e.g., normal shutdown, normal auto position, normal manual position, unoccupied cycle, emergency power, and alarm conditions). COMMISSIONING OF HVAC SYSTEM 23 09 50-2 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 F. Inspect and verify the position of each device and interlock identified on checklists. G. Check safety cutouts, alarms, and interlocks with smoke control and life-safety systems during each mode of operation. H. Testing Instrumentation: Install measuring instruments and logging devices to record test data as directed by the CA. I. Certify that all related A/E punch list items are complete prior to commencing functional test procedures. 3.2 Testing and balance verification A. Prior to performance of testing and balancing Work, provide copies of reports, sample forms, checklists, and certificates to the CA. B. Notify the CA at least 10 days in advance of testing and balancing Work, and provide access for the CA to witness testing and balancing Work. C. Provide technicians, instrumentation, and tools to verify testing and balancing of HVAC&R systems at the direction of the CA. 1. 2. 3. 4. 3.3 The CA will notify testing and balancing Subcontractor 10 days in advance of the date of field verification. Notice will not include data points to be verified. The testing and balancing Subcontractor shall use the same instruments (by model and serial number) that were used when original data were collected. Failure of an item includes, other than sound, a deviation of more than 10 percent. Failure of more than 10 percent of selected items shall result in rejection of final testing, adjusting, and balancing report. For sound pressure readings, a deviation of 3 dB shall result in rejection of final testing. Variations in background noise must be considered. Remedy the deficiency and notify the CA so verification of failed portions can be performed. GENERAL TESTING REQUIREMENTS A. Provide installing technicians, instrumentation, and tools to perform commissioning test at the direction of the CA. B. Scope of HVAC&R testing shall include entire HVAC&R installation, from central equipment for heat generation and refrigeration through distribution systems to each conditioned space. Testing shall include measuring capacities and effectiveness of operational and control functions. C. Test all operating modes, interlocks, control responses, and responses to abnormal or emergency conditions, and verify proper response of building automation system controllers and sensors. COMMISSIONING OF HVAC SYSTEM 23 09 50-3 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 D. The CA along with the HVAC&R Subcontractor, testing and balancing Subcontractor, and HVAC&R Instrumentation and Control Subcontractor shall prepare detailed testing plans, procedures, and checklists for HVAC&R systems, subsystems, and equipment. E. Tests will be performed using design conditions whenever possible. F. Simulated conditions may need to be imposed using an artificial load when it is not practical to test under design conditions. Before simulating conditions, calibrate testing instruments. Provide equipment to simulate loads. Set simulated conditions as directed by the CA and document simulated conditions and methods of simulation. After tests, return settings to normal operating conditions. G. The CA may direct that set points be altered when simulating conditions is not practical. H. The CA may direct that sensor values be altered with a signal generator when design or simulating conditions and altering set points are not practical. I. If tests cannot be completed because of a deficiency outside the scope of the HVAC&R system, document the deficiency and report it to the Owner. After deficiencies are resolved, reschedule tests. J. If the testing plan indicates specific seasonal testing, complete appropriate initial performance tests and documentation and schedule seasonal tests. 3.4 HVAC&R SYSTEMS, SUBSYSTEMS, AND EQUIPMENT TESTING PROCEDURES A. HVAC&R Instrumentation and Control System Testing: Assist the CA with preparation of testing plans. Prefunctional checklists and functional test forms will be provided by CA during construction phase. B. Pipe system cleaning, flushing, hydrostatic tests and chemical treatment requirements: HVAC&R Subcontractor shall prepare a pipe system cleaning, flushing, and hydrostatic testing plan. Provide cleaning, flushing, testing, and treating plan and final reports to the CA. Plan shall include the following: 1. 2. 3. 4. C. Sequence of testing and testing procedures for each section of pipe to be tested, identified by pipe zone or sector identification marker. Markers shall be keyed to Drawings for each pipe sector, showing the physical location of each designated pipe test section. Drawings keyed to pipe zones or sectors shall be formatted to allow each section of piping to be physically located and identified when referred to in pipe system cleaning, flushing, hydrostatic testing, and chemical treatment plan. Description of equipment for flushing operations. Minimum flushing water velocity. Tracking checklist for managing and ensuring that all pipe sections have been cleaned, flushed, hydrostatically tested, and chemically treated. HVAC&R Distribution System Testing: Provide technicians, instrumentation, tools, and equipment to test performance of air and hydronic distribution systems; special exhaust; and other distribution systems, including HVAC&R terminal equipment and unitary equipment. COMMISSIONING OF HVAC SYSTEM 23 09 50-4 MONTEREY PENINSULA COLLEGE - Art Department/Buildings 1 & 30 D. Vibration and Sound Tests: Provide technicians, instrumentation, tools, and equipment to test performance of vibration isolation and seismic controls. E. See Section 01 91 00 Commissioning Requirements for contractor’s responsibilities and retesting procedures. END OF SECTION 23 09 50 COMMISSIONING OF HVAC SYSTEM 23 09 50-5 Monterey Peninsula College Art Department Modernization Buildings 1 and 30 SECTION 260519 LINE VOLTAGE WIRE AND CABLE PART 1 - GENERAL 1.01 Description of Work: A. The work of this Section consists of providing all wire and cable rated 600 volts or less, including splices and terminations, as shown on the Drawings and as described herein. 1.02 Related Work: A. See the following Specification Section for work related to the work in this Section: 1. 260542 Conduits, Raceways and Fittings. 2. 260533 Junction and Pull Boxes. 1.03 Quality Assurance A. Field tests shall be performed as specified in paragraph 3.04 of this Section. PART 2 - PRODUCTS 2.01 Conductors: A. Conductors shall be copper, type THHN/THWN/MTW oil and gasoline resistant, 600 volt rated insulation. B. Conductors shall be stranded copper. C. Minimum power and control wire size shall be No. 12 AWG unless otherwise noted. D. All conductors used on this Project shall be of the same type and conductor material. 2.02 Cables: A. All individual conductors shall be copper with type THHN/THWN, 600 volt rated insulation. LINE VOLTAGE WIRE AND CABLE 260519-1 Monterey Peninsula College Art Department Modernization Buildings 1 and 30 C. Insulation Marking - All insulated conductors shall be identified with printing colored to contrast with the insulation color. D. Color Coding - As specified in paragraph 3.03. E. Special Wiring - Where special wiring is proposed by an equipment manufacturer, submit the special wiring requirements to the Owner's Representative and, if approved, provide same. Special wire shall be the type required by the equipment manufacturer. F. Other Wiring - Wire or cable not specifically shown on the Drawings or specified, but required, shall be of the type and size required for the application and as approved by the Owner's Representative. G. Manufacturer - Acceptable manufacturers including Cablec, Southwire, or equal. 2.03 Terminations: A. Manufacturer - Terminals as manufactured by T&B, Burndy or equal. B. Wire Terminations – Stranded conductors shall be terminated in clamping type terminations which serve to contain all the strands of the conductor. Curling of a stranded conductor around a screw type terminal is not allowed. For screw type terminations, use a fork type stake-on termination on the stranded conductor. Use only a stake-on tool approved for the fork terminals selected. C. End Seals - Heat shrink plastic caps of proper size for the wire on which used. 2.04 Tape: A. Tape used for terminations and cable marking shall be compatible with the insulation and jacket of the cable and shall be of plastic material. PART 3 - EXECUTION 3.01 Cable Installation: A. Clean Raceways - Clean all raceways prior to installation of cables as specified in Section 260542 - Conduits Raceway and Fittings. B. All line voltage wiring shall be installed in conduit. LINE VOLTAGE WIRE AND CABLE 260519-2 Monterey Peninsula College Art Department Modernization Buildings 1 and 30 C. All feeder conductors shall be continuous from equipment to equipment. Splices in feeders are not permitted unless specifically noted or approved by the Electrical Engineer. D. All branch circuit wiring shall be run concealed in ceiling spaces, walls, below floors or in crawl spaces unless noted otherwise. E. Cable Pulling - Exercise care in pulling wires and cables into conduit or wireways so as to avoid kinking, putting undue stress on the cables or otherwise abrading them. No grease will be permitted in pulling cables. Only soapstone, talc, or UL listed pulling compound will be permitted. The raceway construction shall be complete and protected from the weather before cable is pulled into it. Swab conduits before installing cables and exercise care in pulling, to avoid damage to conductors. F. Bending Radius - Cable bending radius shall be per applicable code. Install feeder cables in one continuous length. G. Equipment Grounding Conductors - Provide an equipment grounding conductor, whether or not it is shown on the Drawings, in all conduits or all raceways. H. Panelboard Wiring - In panels, bundle incoming wire and cables which are No. 6 AWG and smaller, lace at intervals not greater than 6 inches, neatly spread into trees and connect to their respective terminals. Allow sufficient slack in cables for alterations in terminal connections. Perform lacing with plastic cable ties or linen lacing twine. Where plastic panel wiring duct is provided for cable runs, lacing is not necessary when the cable is properly installed in the duct. 3.02 Cable Terminations and Splices: A. Splices - UL Listed wirenuts. B. Terminations - Shall comply with the following: 1. Make up and form cable and orient terminals to minimize cable strain and stress on device being terminated on. 2. Burnish oxide from conductor prior to inserting in oxide breaking compound filled terminal. 3.03 Circuit and Conductor Identification: LINE VOLTAGE WIRE AND CABLE 260519-3 Monterey Peninsula College Art Department Modernization Buildings 1 and 30 A. Color Coding - Provide color coding for all circuit conductors. Insulation color shall be white for neutrals and green for grounding conductors. Conductor colors shall be as follows: VOLTAGE 208/120V 480/277V Phase A Phase B Phase C Neutral Ground Black Red Blue White Green Brown Orange Yellow Grey Green B. Color coding shall be in the conductor insulation for all conductors #10 AWG and smaller; for larger conductors, color shall be either in the insulation or in colored plastic tape applied at every location where the conductor is readily accessible. C. Circuit Identification - All underground distribution and service circuits shall be provided with plastic identification tags in each secondary box and at each termination. Tags shall identify the source transformer of the circuit and the building number(s) serviced by the circuit. 3.04 Field Tests: A. All systems shall test free from short circuits and grounds, shall be free from mechanical and electrical defects, and shall show an insulation resistance between phase conductors and ground of not less than the requirements of the CEC. All circuits shall be tested for proper neutral connections. B. Insulation Resistance Tests: Perform insulation resistance tests on circuits with #2 AWG and larger conductors to be energized with a line-to-neutral voltage of 120 volts or more. Make these tests before all equipment has been connected. Test the insulation with a 500Vdc insulation resistance tester with a scale reading 100 megohms. The insulation resistance shall be 2 megohms or more. Submit results for review. END OF SECTION LINE VOLTAGE WIRE AND CABLE 260519-4